You are on page 1of 17

Underground Construction 2005

Examples of the use of Wriggle Surveys of Tunnels Robin B. Clay

EXAMPLES OF THE USE OF WRIGGLE SURVEYS OF TUNNELS


ROBIN B. CLAY M.SC., C.ENG., M.I.C.E. LONDON ENGINEERS LIMITED

SUMMARY
When a tunnel is driven, particularly using a TBM, alignment problems can arise, and, with high-speed tunnelling, can get worse very quickly, and so need swift resolution. Changes to the alignment, where possible, are always cheaper and quicker than breaking out newly-built lining. A wriggle survey of the out-of-tolerance lining is the first step, followed by processing and analysis, followed in turn by judicious re-design of the alignment. The wriggle survey data then needs to be processed again using the new alignment, in an iterative process. This Paper presents some incidents, one from the 1960s, one from the 1980s and some more recent, so that others may learn from the experience.

Keywords
Computer-aided design, Design methods and aids, Land surveying, Mathematical modelling, Rail track design, Rehabilitation reclamation and renovation, Roads and highways, Tunnels and tunnelling, Wriggle survey

Underground Construction 2005

Examples of the use of Wriggle Surveys of Tunnels Robin B. Clay

EXAMPLES OF THE USE OF WRIGGLE SURVEYS OF TUNNELS


ROBIN B. CLAY M.SC., C.ENG., M.I.C.E. LONDON ENGINEERS LIMITED Introduction
Railways generally are quite tolerant of mis-alignments, which is just as well, because tracks historically are laid on ballast that moves under the influence of the loading imposed by trains. One of the traditional items of maintenance has been checking and adjusting top and line, and for top, this is done by inserting (or occasionally abstracting) ballast under the tracks as necessary. For line, the tracks are nudged over as necessary. In the last fifty years, these tasks have been mechanised. But the first task is to establish where the rails are in relation to where they should be. This whole procedure is fairly straight forward out in the open, but when the line is in tunnel, the situation is completely changed. This is because the cost of driving a tunnel is a function of both the perimeter of the excavation (i.e. the quantity of lining), and also a function of the cross-sectional area (i.e. the volume to be dug out). Consequently, the cost is roughly proportional to the square of the diameter, and so tunnels are usually built with as small a (1) clearance as practicable . The consequence of this is that any error in alignment encroaches on the clearance, and if the tolerance is exceeded, then, strictly, the lining needs to be broken out to accommodate the alignment. This is as true for roads as it is for railways (water tunnels and sewerage tunnels are generally immune to these problems). Any experienced tunneller knows that, for all the modern aids we have to control tunnel driving, every Tunnel Boring Machine (TBM) has a mind of its own regarding alignment, and if the driving tolerances are exceeded, there is the real possibility that extra work will be required. However, it is often possible to avoid this extra work, which is both expensive and timeconsuming, by carrying out a wriggle survey, to establish the precise location of the tunnel, and follow that with detailed inspection and processing, that can lead to the development of a new design for the alignment that complies with the relevant standards and will also allow the as-built lining to be accepted. Below are given some examples, at twenty-year intervals, that indicate how some aspects have changed enormously, while the principles remain unchanged.

The Victoria Line


Introduction The Victoria Line was built in the early 1960s, before the days of computers or even handheld calculators, and survey calculations were carried out using seven figure log tables, writing down every step of the calculations. Distances were measured in feet and decimal feet, but sometimes in feet, inches and fractions of an inch; angles were measured in degrees, minutes and seconds. During the construction, the first TBM drive on one Contract was from Highbury to Kings Cross, through stiff London Clay. The tunnel was 12-2 (3721mm) ID and lined with flexible concrete lining - two-foot (610mm) long mass-concrete segments with knuckle joints. Tunnel-driving tolerance laid down in the Specification was the usual within an inch, but at Tender time, the Tenderers offered to build a 14 (4267mm) ID tunnel for the same price, to
(2)

Underground Construction 2005

Examples of the use of Wriggle Surveys of Tunnels Robin B. Clay

increase their construction tolerance. This proposal was rejected by the Client, as a close fit was required for ventilation purposes (see below). After the straight section through Highbury Station, the alignment started on a 56 chains (1126.5m) radius clockwise curve. The Setting-out process Survey stations were established at one hundred foot (30m) centres in the crown of the tunnel at the intersection point (IP) of two tangents to the curve. Each IP comprised a screw-eye fixed into the concrete lining, with a small hole drilled vertically through the bottom part of the eye. A piece of string was threaded through this hole, with a knot above to retain it, and a weight on the other end usually a lump of tunnel spoil to form a plumb-line. The theodolite was placed beneath this (the weight being replaced by a plumb-bob), and a back-sight taken to the previous station. Plumb-lines were then established at twenty-foot (7m) centres, fixed on the tangent to the curve, with three in use at a time, checked against each other. The location of the TBM in plan was established by lining up two plumb-lines onto a target plate fixed to the TBM, and measuring the offset. The direction in which the TBM was facing was checked by comparing the lead at axis level of the left hand side of the TBM against the right hand side, measured from square marks inscribed on the tunnel walls perpendicular to the alignment. For level, inverted-T adjustable boning rods were suspended from the tunnel roof in threes at ten-foot (3m) centres, and adjusted so that the top of the horizontal arm was in the design location. Three were always used, so that any mis-alignment would show up immediately. Readings were taken by sighting across the boning rods onto the target fixed to the TBM, and measuring the vertical distance from the target centre; this was then compared with the design offset. Overhang or look-up was measured with a plumb-bob. At the start of each shift, the Contractors Site Engineer calculated the required offsets for each of the next ten rings, and gave these to the Shift Boss. The incident The calculations of the offsets were all carefully checked, as were the setting-out points and the measurements of the offsets to the TBM, but the HIPs (Horizontal Intersection Points) were checked only every three hundred feet, as a follow-up survey and as luck would have it, the follow-up survey fell behind schedule. Thus the TBM had travelled over seven hundred feet along the curve before it was discovered that it was in the wrong place some 7-6 (2286mm) off line. It is easy to imagine the consternation that ensued. The TBM was stopped, and the length of tunnel very carefully surveyed to establish where it actually was. This survey and subsequent investigation showed that the deflection angles had been set out ten minutes less than they should have been. The error had arisen because the Contractors setting-out Engineer had started to use a new theodolite with which he was not familiar.
8 7 6 5 4 3 2 1 0 0 100 200 300 400 Chainage 500 600 700 800

Error in feet

Figure 1: Victoria Line - As-built errors from design alignment

Underground Construction 2005 The wriggle survey

Examples of the use of Wriggle Surveys of Tunnels Robin B. Clay

The tunnel cross-section was circular. The first step was to check and re-check the HIPs that had been established at 300-ft (90m) spacing. From these, the lining was surveyed at fivering (ten foot, 3m) intervals, by setting up the theodolite under one HIP and sighting the next. Using a levelling staff held horizontally, the offset of each tunnel wall at axis level was measured, at the leading edge of the ring. The level of the crown of the tunnel was also checked, but the invert level was only very rarely checked, for the invert was full of tunnel spoil and water. Also, there was more space at the bottom of the tunnel, and it did not impinge on clearances. Processing the wriggle survey From these horizontal offsets, the versines at each surveyed ring were calculated on a twenty-foot (7m) chord, and these versines were plotted on squared paper against chainage. The design line of these versines would have been along the zero intercept where the alignment was straight, then an inclined straight line where the alignment passed through the transition (radius, and hence versine, being proportional to distance), and then a straight horizontal line (constant versine) where the alignment ran along the circular curve (constant radius). The as-built versines formed a series of arcs (created by the offsets that were correct for a 56 chain curve) along a straight line lower than intended (created by deflection angles being too small, i.e. a larger radius curve). A best-fit line was drawn on the squared paper, and the radius of this was deduced. The process was then repeated using this radius as the new design radius, to check the clearances. The results Having established the alignment of the as-built tunnel, a second new curve was designed to join this first new curve to the original alignment; due to the large radii, no transition between them was necessary. Fortunately, the design radius was very large, and the new alignment lay within the limits of deviation, and the as-built tunnel was within tolerance, so no remedial work was necessary.

Underground Construction 2005

Examples of the use of Wriggle Surveys of Tunnels Robin B. Clay

320

300

280

260

Northings
240

220

200

180

Design alignment As-built alignment Design HIPs As-built HIPs New alignment

160 1 2 3 4 Eastings 5 6 7 8
Figure 2: Victoria Line - Design, As-built and New Alignments (feet)

Underground Construction 2005


215

Examples of the use of Wriggle Surveys of Tunnels Robin B. Clay

210

205

200

Northings
195

190

185

Design alignment As-built alignment Design HIPs As-built HIPs New alignment
2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 3

180 Eastings

Figure 3: Victoria Line - Design, As-built and New Alignments (feet) (enlargement of part of previous figure) An intermediate curve was then introduced to get the TBM back to the original alignment before the next obstacle, a chamber at Gibson Square that had already been built to accommodate the TBM for servicing before it completed the drive to Kings Cross.
0.000 -0.005 -0.010 -0.015 Error in -0.020 feet -0.025 -0.030 -0.035 -0.040 0 25 50 75 100 125 150 175 200 225 250 275 300 325 350 375 400 425 Chainage

Figure 4: Victoria Line - As-built errors from new alignment (compare with Figure 1) From the above graph, Figure 4, it can be seen that the maximum error was changed from some 11 feet (3.5m) at the eventual worst point to some 0.035 feet (11mm), less than half an inch, and so within tolerance. No lining needed to be modified; the only penalty was a lot of extra work for the site engineers and the design engineers.

Underground Construction 2005

Examples of the use of Wriggle Surveys of Tunnels Robin B. Clay

The Hong Kong Mass Transit Railway


Introduction The Hong Kong Mass Transit Railway was constructed in phases, starting in 1975. By this time, hand-held calculators were commonplace, although still quite large. Desktop computers were just starting to become available the first IBM PC was introduced in 1980, with provision for recording onto cassette tape. Design of theodolites, too, had progressed, and total stations were available, with electronic distance measurement (EDM). Wriggle The wriggle was processed by computer, which accepted wriggle data over the telephone from surveyors on site, in the form of horizontal and vertical angles and distance, from the instrument to each of about six points disposed around the periphery of the tunnel, and checked at five-metre centres. The measuring was done by holding up to each point a wand with a 35mm dia. reflector at the end; the instrument then measured to the centre of the reflector. The computer then compared this data with the alignment, and the calculations produced profiles showing the error at each surveyed point from the design position. Later, this program was further developed by the Author to show the errors longitudinally. Incident One incident in particular is worthy of mention. Here, the tunnel had been constructed to form a slight trough compared with the design, i.e. the TBM had gone low, but had then been pulled up again to the correct alignment, and this trough extended over a distance of about fifty metres. The railway is operated by overhead line equipment (OLE), with electricity carried along wires suspended from the tunnel soffit, and picked up by pantographs mounted on the trains. In this incident, the trough exceeded the construction tolerance, in that the tunnel soffit encroached further into the tunnel than it should have done. Under the terms of the contract, the Contractor could have been required to dig out the tunnel lining in the crown and re-build it to the correct alignment. This would have been an expensive exercise, but more significantly would have delayed the opening of the railway. Result From inspection of the longitudinal plot, it was possible to put to the Contractor the alternative, that if he was prepared to pay for the extra cost of installing a few extra OLE support brackets (at about $6,000 each), then the tunnel could be accepted as-built. Silly question, really!

Channel Tunnel Rail Link


Phase Two of the Channel Tunnel Rail Link is mostly in tunnel. However, the trains travel at considerably higher speeds than they do in the London Underground. In a normal Tube tunnel, the train is a close fit in the tunnel, as described above. This means that the train tends to push the air ahead of it, what is called the piston effect. This shows itself in the draughts experienced by passengers waiting on the platform as the train approaches. With the CTRL high speed trains, this is not a practicable option, so the tunnels are much bigger, to allow the trains to pass through the air, the air being squeezed into the gap between the train and the tunnel walls. This means that there is much greater clearance between tunnel and train, and this allows the tunnel alignment to wander away from its designed position to a much greater extent, i.e. the construction tolerances are greatly increased. In these particular circumstances, and if nothing goes wrong, a wriggle survey may not be necessary.

Underground Construction 2005

Examples of the use of Wriggle Surveys of Tunnels Robin B. Clay

Adana-Gaziantep Motorway tunnels


The 220-km motorway between Adana and Gazi-antep in Southern Turkey was constructed in the 1990s. The route passes through several tunnels that were driven by drill-and-blast through rock, and supported by a structural primary lining of sprayed concrete, followed by a secondary lining of in-situ concrete. Although the tunnel drives were not without incident(2),(3), there were no significant alignment problems. The survey equipment used to check the tunnel included the latest total stations, and with sightings taken onto reflecting studs fixed around the periphery of the tunnel to form profiles. The instrument was set up in a suitable location on a tripod at ground level, and a series of readings was taken on previous studs (to locate the instrument) and then on new ones. There were no survey stations as used in the previously conventional method. For checking over-/under-break, a specialist profiler was used, that used a laser beam to sweep a full circle around the periphery of the tunnel, recording the distance of the tunnel wall from the instrument. This machine was fully automatic; once one profile was complete, the machine moved itself on to the next location. All readings were logged and fed into a computer for detailed processing and the results could be seen on screen or printed out, in whatever format was required. A far cry from the methods used on the Victoria Line thirty years before.

Another motorway tunnel


Introduction During the construction of a recently-completed pair of two-lane motorway tunnels, some alignment problems arose despite the use of the most up-to-date equipment. The TBM had been erected inside an adit, resting on rails cast into concrete. The machine was built to cut rock that constituted most of the drive, but the shaft had been sunk in the only suitable surface location, through soft ground down to tunnel level. The first short stretch of tunnel was therefore through soft ground. The TBM was set slightly low, in anticipation of a tendency to float in the soft ground, the weight of the TBM being less than that of the removed spoil. Unfortunately, shortly after the TBM left the adit, an unexpected pocket of sand was encountered at crown level. With the tail firmly supported by the rails, with the TBM being nose-heavy, and with little resistance at the top of the cutter-head, the TBM started to tilt downwards. The alignment here, at the start of the drive, was on a 4% down gradient, a relaxation from the normal 3% maximum gradient, allowed only for the first 100 metres. As the drive progressed, the tilt became worse, and eventually reached about 7%. Finally, at the suggestion of the Author, cables were attached to the top of the TBM and anchored back to the shaft. This provided the necessary resistance, and thereafter the TBM was under control. However, the final maximum error was some 800mm low, compared with the tolerance of 75mm. Fortunately, there was sufficient clearance within the tunnel to adjust the alignment such that a 4% gradient could be wriggled through the as-built tunnel without any need to modify the primary lining. Special measures were needed, however, for the secondary lining, whose thickness was reduced in places from a nominal 225mm to only 150mm. The changes to the alignment affected not just the vertical alignment, but the horizontal alignment as well. In addition, due to a cross-over tunnel between the two bores, the horizontal and vertical alignments of the other tunnel also had to be re-designed to suit. Here follow three pairs of figures, in each pair the top figure is before, showing as-built compared with the design alignment; the second is after, to the re-designed alignment. The three sets are firstly a cross-section at the worst pinch-point in the invert, secondly a crosssection at the worst pinch-point in the crown, and thirdly longitudinal sections showing (a) Line & Level; (b) Shoulder clearances, and (c) Knee clearances..

Underground Construction 2005

Examples of the use of Wriggle Surveys of Tunnels Robin B. Clay


Back of R1, Ch. 2+279.023, to DESIGN / Shutters DESIGN alignments

7000

6000

5000

4000

3000 19 2000

20

2 3

1000 17 0 16 15 -1000 14 13 12 11 10 9 6 7 8 18 4 5

-2000

-3000

-4000

-5000

Secondary Lining Wriggle

-6000

Rotated Traffic Envelope: Minimum Thickness 225 mm Kickers

-7000 -7000

-6000

-5000

-4000

-3000

-2000

-1000

1000

2000

3000

4000

5000

6000

7000

Figure 5: Ring 1 to DESIGN alignment


Back of R1, Ch. 2+278.990, to Option 104 / Shutters 104jg alignments

7000 6000 5000 4000 3000 2000 1000 17 0 -1000 -2000 -3000 -4000
Secondary Lining

20 19

2 3

18

5 6 7

16 15 14 13 12 11 10 9

-5000
Wriggle

-6000 -7000 -7000

Rotated Traffic Envelope: Minimum Thickness 225 mm

-6000

-5000

-4000

-3000

-2000

-1000

1000

2000

3000

4000

5000

6000

7000

Figure 6: Ring 1 to Option 104 alignment

Underground Construction 2005

Examples of the use of Wriggle Surveys of Tunnels Robin B. Clay


Face of R38, Ch. 2+343.672, to DESIGN / Shutters DESIGN alignments

7000

6000

5000

4000 3000 19 2000

20

2 3

1000 17 0 16 15 -1000 14 13 12 11 10 9 6 7 8 18 4 5

-2000

-3000 -4000
Secondary Lining Wriggle Rotated Traffic Envelope:

-5000

-6000

Minimum Thickness 225 mm Kickers

-7000 -7000

-6000

-5000

-4000

-3000

-2000

-1000

1000

2000

3000

4000

5000

6000

7000

Figure 7: Ring 38 to DESIGN alignment


Face of R38, Ch. 2+343.606, to Option 104 / Shutters 104jg alignments
7000

6000

5000

4000 3000 19 2000

20

2 3

1000 17 0 16 15 -1000 14 13 12 11 10 9 6 7 8 18 4 5

-2000

-3000 -4000
Secondary Lining Wriggle

-5000

-6000

Rotated Traffic Envelope: Minimum Thickness 225 mm

-7000 -7000

-6000

-5000

-4000

-3000

-2000

-1000

1000

2000

3000

4000

5000

6000

7000

Figure 8: Ring 38 to Option 104 alignment

Underground Construction 2005

Examples of the use of Wriggle Surveys of Tunnels Robin B. Clay

Line and Level relative to the Alignment


-1300 -1200 -1100 -1000 -900 -800 -700 -600 -500 -400 -300

Tunnel Line

Shutter Line

Tunnel Level

Shutter Level

Crown Thickness

900 800 700 600 500 400 300 200 100 0 -100 -200 -300 -400 -500 -600 -700 -800

Up from Alignment

Crown Thickness is shown by a solid green line with round black blobs; this line SHOULD always be above the dotted green line at 225, and below the solid green line at 400, and MUST always be above the dotted black line at 200 (Right hand axis) Tunnel Level is shown by a Solid red line with square blobs; this line should be close to the red Zero line (Right hand axis) Shutter Level is shown by a dotted red line with round blobs; this line should be between the red Tunnel Level line and the red Zero line (Right hand axis) These criteria are only met over the first seven metres of the tunnel drive. Tunnel Line is shown by a solid blue line with diamond blobs; this line should be close to the blue Zero line (Left hand axis) Shutter Line is shown by a dotted blue line with round blobs; this line should be between the blue Tunnel Line line and the blue Zero line (Left hand axis)

Offsets to the Right

-200 -100 0 100 200 300 2278 2280 2282 2284 2286 2288 2290 2292 2294 2296 2298 2300 2302 2304 2306 2308 2310 2312 2314 2316 2318 2320 2322 2324 2326 2328 2330 2332 2334 2336 2338 2340 2342 400

Figure 9: Line & Level to DESIGN alignment

Underground Construction 2005

Examples of the use of Wriggle Surveys of Tunnels Robin B. Clay

Line and Level relative to the Alignment


-1100 -1000 -900 -800 -700 -600 -500 -400 -300 -200 -100 2279 0 100 200

Tunnel Line

Shutter Line

Tunnel Level

Shutter Level

Crown Thickness

Minimum Thickness

Maximum Thickness

700 600 500

Up from Alignment

400 300 200 100 0

-100 -200 -300 2289 2299 2309 2319 2329 2339 2349 2359 2369 2379 2389 2399 2409 2419 2429 2439 2449 2459 2469 2479 2489 2499 -400 -500 -600

The re-alignment has lifted the line, but kept it at 4%. There has also been some slight adjustment in the horizontal alignment, to keep the line central to the as-built tunnel at the worst points. The improvements achieved in the crown of the tunnel by adjusting both the alignment and the shutter means that the concrete thickness is very rarely more than 400mm (isolated spots), very rarely less than 200mm (isolated spots), and mostly more than 225mm.

Offsets to the Right

Figure 10: Line and Level to Option 104 alignment

Underground Construction 2005

Examples of the use of Wriggle Surveys of Tunnels Robin B. Clay

800 700 600 500

Clearances and Concrete Thicknesses at Shoulders

Left Shoulder Clearance

Left Shoulder Thickness

Right Shoulder Thickness

Right Shoulder Clearance

-1100 -1000 -900 -800 -700 -600 -500 -400 -300 -200 -100 0 100 200 300 400 500 600 700 800

Left Shoulder Clearance is shown by a dotted blue line with square blobs; this line MUST always be above the blue Zero line Left Shoulder Thickness is shown by a solid blue line with triangular blobs; this line SHOULD always be above the blue line at 225, and MUST always be above the blue line at 200. Right Shoulder Clearance is shown by a dotted red line with diamond blobs; this line MUST always be below the red Zero line Right Shoulder Thickness is shown by a solid red line with round blobs; this line SHOULD always be below the red line at 225, and MUST always be below the red line at 200. These criteria are only met over the first 20 metres of the tunnel drive.

Left Shoulder

400 300 200 100 0 2278 2280 2282 2284 2286 2288 2290 2292 2294 2296 2298 2300 2302 2304 2306 2308 2310 2312 2314 2316 2318 2320 2322 2324 2326 2328 2330 2332 2334 2336 2338 2340 2342 -100 -200 -300 -400 -500 -600 -700 -800 -900 -1000 -1100

Right Shoulder

Figure 11: Shoulder clearances to DESIGN alignment

Underground Construction 2005

Examples of the use of Wriggle Surveys of Tunnels Robin B. Clay

Clearances and Concrete Thicknesses at Shoulders


800 700 600 500
Left Shoulder

Left Shoulder Clearance

Left Shoulder Thickness

Right Shoulder Thickness

Right Shoulder Clearance

-1100 -1000 -900 -800 -700 -600 -500 -400 -300


2279 2289 2299 2309 2319 2329 2339 2349 2359 2369 2379 2389 2399 2409 2419 2429 2439 2449 2459 2469 2479 2489 2499

400 300 200 100 0 -100 -200 -300 -400 -500 -600 -700 -800 -900 -1000 -1100

-200
Right Shoulder

-100 0 100 200 300 400 500 600 700 800

Figure 12: Shoulder clearances to Option 104 alignment The re-alignment has lifted the line, but kept it at 4%. There has also been some slight adjustment in the horizontal alignment, to keep the line central to the as-built tunnel at the worst points. The improvements achieved in the shoulders of the tunnel by adjusting both the alignment and the shutter means that the concrete thickness is rarely more than 400mm, and never less than 200mm. At no point does the lining impinge on the Traffic Envelope (clearance always more than zero).

Underground Construction 2005

Examples of the use of Wriggle Surveys of Tunnels Robin B. Clay

Clearances and Concrete Thicknesses at Knees


800 700 600 500 400 300

Left Knee Clearance

Left Knee Thickness

Right Knee Clearance

Right Knee Thickness

-1100 -1000 -900 -800 -700 -600 -500 -400 -300 -200 -100 0 100 200 300 400 500 600 700 800

Left Knee Clearance is shown by a dotted blue line with square blobs; this line MUST always be above the blue Zero line Left Knee Thickness is shown by a solid blue line with triangular blobs; this line SHOULD always be above the blue line at 225, and MUST always be above the blue line at 200. Right Knee Clearance is shown by a dotted red line with diamond blobs; this line MUST always be below the red Zero line Right Knee Thickness is shown by a solid red line with round blobs; this line SHOULD always be below the red line at 225, and MUST always be below the red line at 200. These criteria are met, but the alignment is not acceptable on account of the encroachments in the top half of the tunnel.

Left Knee

200 100 0 2278 2280 2282 2284 2286 2288 2290 2292 2294 2296 2298 2300 2302 2304 2306 2308 2310 2312 2314 2316 2318 2320 2322 2324 2326 2328 2330 2332 2334 2336 2338 2340 2342 -100 -200 -300 -400 -500 -600 -700 -800 -900 -1000 -1100

Right Knee

Figure 13: Knee clearances to DESIGN alignment

Underground Construction 2005

Examples of the use of Wriggle Surveys of Tunnels Robin B. Clay

800 700 600 500 400 300 200


Left Knee

Clearances and Concrete Thicknesses at Knees

Left Knee Clearance

Left Knee Thickness

Right Knee Clearance

Right Knee Thickness

-1100 -1000 -900 -800 -700 -600 -500 -400 -300

100 0 -100 -200 -300 -400 -500 -600 -700 -800 -900 -1000 -1100
2279 2289 2299 2309 2319 2329 2339 2349 2359 2369 2379 2389 2399 2409 2419 2429 2439 2449 2459 2469 2479 2489 2499

-200 -100 0 100 200 300 400 500 600 700 800 Right Knee

Figure 14: Knee clearances to Option 104 alignment The re-alignment has lifted the line, but kept it at 4%. There has also been some slight adjustment in the horizontal alignment, to keep the line central to the as-built tunnel at the worst points. The improvements achieved in the knees of the tunnel by adjusting both the alignment and the shutter means that the concrete thickness is rarely more than 400mm, and never less than 200mm. Over the first 30m or so at the start of the tunnel, the lining would impinge on the Traffic Envelope (clearance less than zero). Over this length, special measures had to be employed, using a thinner lining of a different material to maintain the fire-protection to the primary lining.

Underground Construction 2005

Examples of the use of Wriggle Surveys of Tunnels Robin B. Clay

Incident No 2 In another incident, the TBM wandered 240mm off-line. Following a wriggle survey, a new horizontal alignment was produced that enabled tunnel-driving to continue, and the secondary lining to be completed without modification, maintaining both the minimum thickness of the secondary lining and the specified clearances. Incident No 3 In a third incident, the TBM wandered 80mm off-line and 100mm off-level. Unfortunately, matters were exacerbated by the operator bringing the TBM back on line as rapidly as he could. This produced a kink in the as-built alignment. However, following the wriggle survey a new alignment was produced that enabled the as-built tunnel to be accepted, but the secondary lining shutter alignment had to be adjusted significantly relative to the primary lining in order to maintain clearance and concrete thickness. Results The results obtained in all three incidents allowed the secondary lining to be placed without any need to break out any primary lining, thus saving a considerable amount of time and money. This was achieved by the use of wriggle survey and bespoke VBA routines written by the Author and running in MicroSofts Excel.

Conclusions
For both road and railway tunnels, where alignment and clearances are important, wriggle survey is an essential tool in the tunnellers armoury. Equally important is the facility to process the results not just in cross-section, but longitudinally as well, and is to appreciate that a re-design of the alignment should be regarded as the first option to solve any problem with clearances. It is important, too, to realise that things can always go wrong.

Acknowledgements
The Author acknowledges his debt to those organisations that have enabled him to gather the experiences outlined above. These include Sir William Halcrow & Partners, Mott, Hay & Anderson, Charles Haswell & Partners, Rail Link Engineering and the HK MTRC.

References
(1) Morgan and Bartlett The Victoria Line: planning and design ICE Proceedings Paper 7270S Suppl. 1969 pp.377-395 (2) Clay and Takacs Tunnel collapses - case study Tunnelling 97, The Institution of Mining and Metallurgy, ISBN 1 870706 34 X, 1997 (3) Takacs and Clay Lessons from a NATM (SCL) breakthrough in difficult geological conditions; 8th Congress of the International Association of Engineering Geology and Environment, Balkema, 1998

You might also like