Site Test Report For Differential Protection

Customer SEC-SOA
Extension of Muhayil
Project
S/S 132/33 KV
Location MUHAYEL

Contract #

40631024/00

Job #
Equipment Tag

6T1

RELAY DETAILS
RELAY ANSI NO.

87T

RELAY FUNCTION

TRANS. DIFF

RELAY MAKE

SIEMENS

NOMINAL CURRENT

1A

TYPE / STYLE

7UT612

AUX SUPPLY VOLTAGE

60-125VDC

S. NO.

1-VISUAL AND MECHANICAL INSPECTION:


O.K

CHECK NAME PLATE DATA ACCORDING TO THE DRAWING

O.K

CHECK FOR TRANSPORTATION DAMAGE AND CORRECT POSITION

O.K

VERIFY TIGHTNEES OF EXTERNAL WIRING

2-ELECTRICAL CHECKS:
O.K

ALL CONNECTIONS CHECK ACCORDING TO WIRING DIAGRAM

O.K

AUX.SUPPLY CHECKED FOR RATING AND POLARITY

O.K

CASING EARTHING CHECK


All 7 programmable LEDs apply Test LEDs under Test mode (Hardware test).

OK

Remarks
Test Inst. Used

FREJA300

Name: Eng.

Tested By

Mohamed

Shokry
Date:
20/07/09
Signature:

Witnessed
By

Name: Eng .ALI Al AMRI


Date:
Page 1 of 11

Site Test Report For Differential Protection


Customer SEC-SOA
Extension of Muhayil
Project
S/S 132/33 KV
Location MUHAYEL

Contract #

40631024/00

Job #
Equipment Tag

6T1

3- TRANSFORMER DATA:

RATIO: 132/13.8KV
MVA: 67 MVA
H.V SIDE VOLTAGE: 132KV
L.V SIDE VOLTAGE: 13.8KV
GROUP NO: DYN1
FREQUNCEY: 60 HZ
H.V SIDE C.T RATIO: 500/1
H.V SIDE C.T RATIO: 3000/1
IMPEDENCE VOLTAGE: 14%
H.V CALCULATED FULL LOAD CURRENT: 293.0 A = 0.586 A (sec value)
LV CALCULATED FULL LOAD CURRENT: 2803.0 A = 0.934 (sec value)

*** Full load current= Trans MVA/Root of 3* KV

Remarks
Test Inst. Used

FREJA300

Name: Eng.

Tested By

Mohamed

Shokry
Date:
20/07/09
Signature:

Witnessed
By

Name: Eng .ALI Al AMRI


Date:
Page 2 of 11

Site Test Report For Differential Protection


Customer SEC-SOA
Extension of Muhayil
Project
S/S 132/33 KV
Location MUHAYEL

Contract #

40631024/00

Job #
Equipment Tag

6T1

4. INPUT OPTO-ISOLATORS CHECKS (With Relay Energized):


GO TO TEST MODE (HARDWARE TEST) FOR CHECKING STATUS OF INPUTS
OPTO
INPUT
NO.
OPTO 1

TEST METHOD
(Energize only one at a time by soft ware)

RESULT
Display 0
to 1

REMARKS

ENERGIZE BI 1 (High)

OK

Spare

OPTO 2

ENERGIZE BI 2 (High)

OK

Spare

OPTO 3

ENERGIZE BI 3 (High)

OK

Spare

5. OUTPUT RELAYS CHECKS (With Relay Energized):

OUTPUT
RELAY
No.

TEST METHOD
(Energize only one at a time by soft ware)

RL1
RL2
RL3
RL4

CONTACT OPERATED F6-F7


(N/O)
CONTACT OPERATED F8-F9
(N/O)
CONTACT OPERATED F10-F11
(N/O)
CONTACT OPERATED F12-F13
(N/O)

RESULT
Contact
Checked

REMARKS

OK

Relay trip

OK

Spare

OK

Spare

OK

Spare

Witnessed
By

Name: Eng .ALI Al AMRI


Date:

Remarks
Test Inst. Used

FREJA300

Name: Eng.

Tested By

Mohamed

Shokry
Date:
20/07/09
Signature:

Page 3 of 11

Site Test Report For Differential Protection


Customer SEC-SOA
Extension of Muhayil
Project
S/S 132/33 KV
Location MUHAYEL

Contract #

40631024/00

Job #
Equipment Tag

6T1

6- PICK UP TEST IDIFF> :


CALCULATED
I D>

CT INPUT
1
(HV Side)

CT INPUT
2
(LV Side)

KVG

TRIP

P.U

PH A
D.O

TRIP

PH B

P.U

D.O

TRIP

P.U

PH C
D.O

TRIP

P.U

D.O

0.102

0.25

1.0

0.147

0.125

0.103

0.147

0.126

0.104

0.146

0.123

0.102

0.147

0.1
25

0.5

1.0

0.293

0.249

0.205

0.293

0.250

0.207

0.292

0.248

0.205

0.293

0.25
0

0.207

1.0

1.0

0.586

0.498

0.410

0.586

0.502

0.413

0.586

0.497

0.410

0.586

0.49
8

0.411

0.25

1.73

0.41

0.35

0.287

0.403

0.342

0.285

0.403

0.344

0.286

0.401

0.34
5

0.285

0.5

1.73

0.810

0.688

0.567

0.810

0.689

0.567

0.806

0.684

0.567

0.807

1.0

1.73

1.620

1.377

1.134

1.621

1.374

1.138

1.619

1.381

0.139

1.613

0.68
5
1.37
7

0.570
1.134

Select any Phase in HVS and inject current until pickup led then go up until trip contact operate then go
down again tell the pickup led disappear for delta winding program the O/P contact for each phase you
test every time
TRIP = IDIFF>* Kvg*In Trans /In CT
TRIP h.v = IDIFF>*1.0* 293/(500/1)= 0.586*IDFF> A
TRIP l.v = IDIFF>*1.73* 2803/(3000/1)= 1.62*IDFF> A
P.U =85% TRIP VALUE
D.O =70% TRIP VALUE
7- TIMING TEST (adress1625):
SETTING TIME
(S)
0.0

MEASURED TIME @ 2 Is
A

H.V

L.V

H.V

L.V

H.V

L.V

37.8ms

37.9ms

39.9ms

37.2ms

38.3ms

34.3ms

Remarks
Test Inst. Used

FREJA300

Name: Eng.

Tested By

Mohamed

Shokry
Date:
20/07/09
Signature:

Witnessed
By

Name: Eng .ALI Al AMRI


Date:
Page 4 of 11

Site Test Report For Differential Protection


Customer SEC-SOA
Extension of Muhayil
Project
S/S 132/33 KV
Location MUHAYEL

Contract #

40631024/00

Job #
Equipment Tag

6T1

RELAY INHERENT TIME = 35 ms

8- PICK UP& TIMING FOR IDFF>> :


I DIFF>>
SETTING
CT INPUT 1
(HV WINDING)

CT INPUT 2
(LV WINDING)

Kvg

CAL. Trip
(A)

Trip value (A)


Ph A

Ph B

Ph C

TRIP TIME @ 2 Is (ms)


Ph A
Ph B
Ph C

1.5 In

1.0

0.879

0.87
9

0.876

0.878

27

27.4

28.4

1.5 In

1.73

2.43

2.41
8

2.418

2.425

27

27.4

27.6

Change the setting for I DIFF> to be 2 In then make pick up for I DIFF>> or make another contact for
I DIFF>> only

Pick up = I diff>> * Kvg * In trans/ In CT


Trip hv = IDIFF>*1.0* 293/(500/1)= 0.586 *IDFF>> A
Trip l.v = IDIFF>*1.73* 2803/(3000/1)= 1.62*IDFF>> A
P.U =85% TRIP VALUE
D.O =70% TRIP Value
RELAY INHERENT TIME = 25 ms

Remarks
Test Inst. Used

FREJA300

Name: Eng.

Tested By

Mohamed

Shokry
Date:
20/07/09
Signature:

Witnessed
By

Name: Eng .ALI Al AMRI


Date:
Page 5 of 11

Site Test Report For Differential Protection


Customer SEC-SOA
Extension of Muhayil
Project
S/S 132/33 KV
Location MUHAYEL

Contract #

40631024/00

Job #
Equipment Tag

6T1

9- Slop (Bias) Test:


I: slope 1
Slope1

0.25

0.5
1
1.5

I1 (source1) I2 (source2)
0.293
0.586
0.879

0.81
1.62
2.43

Operating angle
(Either one source)
27.9
27
27.7

Measured slope
0.24
0.24
0.23

Slope calculation:

Slope

= [A2 + B2] 1/2


2xM

A = [M - M x cos ]
B = M x sin

I1= Kvg *M* I nsec W1 = 0.586 M


where M constant , Kvg = (1.0) Ph-N
I2= Kvg *M* I nsec W2 = 1.62 M
where M constant , Kvg = (1.73) Ph-N
The calculated slope 1 should be with in +-10% of setting

Inject same phase (L1) to High side & low side by stable current in table with phase shift 180 and
increase the angle of HS till Trip then calculate the slop by this angle

Remarks
Test Inst. Used

FREJA300

Name: Eng.

Tested By

Mohamed

Shokry
Date:
20/07/09
Signature:

Witnessed
By

Name: Eng .ALI Al AMRI


Date:
Page 6 of 11

Site Test Report For Differential Protection


Customer SEC-SOA
Extension of Muhayil
Project
S/S 132/33 KV
Location MUHAYEL

Contract #

40631024/00

Job #
Equipment Tag

6T1

II: slope 2 :
Slope2

0.50

1
1.5
2

I1 (source1) I2 (source2)
0.586
0.879
1.172

1.62
2.43
3.24

Operating angle
(Either one source)
59
58
51.1

Measured slope
0.49
0.48
0.34

Slope calculation:

Slope

= [A2 + B2] 1/2


2xM

A = [M - M x cos ]
B = M x sin

I1= Kvg* M* In sec W1 = 0.586 M


where M constant , Kvg = (1.0) Ph-N
I2= Kvg* M* In sec W2 =1.62 M
where M constant , Kvg = (1.73) Ph-N
The calculated slope 2 should be with in +-10% of setting

*** To test slope 2 base point to shifted to origin.

Inject same phase(L1) to High side & low side by stable current in table with phase shift 180 and
increase the angle of HS till Trip then calculate the slop by this angle
Remarks
Test Inst. Used

FREJA300

Name: Eng.

Tested By

Mohamed

Shokry
Date:
20/07/09
Signature:

Witnessed
By

Name: Eng .ALI Al AMRI


Date:
Page 7 of 11

Site Test Report For Differential Protection


Customer SEC-SOA
Extension of Muhayil
Project
S/S 132/33 KV
Location MUHAYEL

Contract #

40631024/00

Job #
Equipment Tag

6T1

10- HARMONICS CHECK:


I 2nd HARMONICS :
SETTING
%
15

INJECTED
CURRENT
(A)
1

HV

LV

TRIP

BLOCK

TRIP

BLOCK

<16%

>16%

<16%

>16%

REMARKS
-

By Freja Remote mode (Edit curve)


Inject 1A Have fundamental + 10 % of 2nd Harmonic and increase the value of harmonic in curve till
Block
II 5TH HARMONICS :

SETTING
%
30

INJECTED
CURRENT
(A)
0.4

HV

LV

TRIP

BLOCK

TRIP

BLOCK

<30%

>30%

<30%

>30%

REMARKS
-

Remarks
Test Inst. Used

FREJA300

Name: Eng.

Tested By

Mohamed

Shokry
Date:
20/07/09
Signature:

Witnessed
By

Name: Eng .ALI Al AMRI


Date:
Page 8 of 11

Site Test Report For Differential Protection


Customer SEC-SOA
Extension of Muhayil
Project
S/S 132/33 KV
Location MUHAYEL

Contract #

40631024/00

Job #
Equipment Tag

6T1

By Freja Remote mode


Inject 0.4A Have fundamental + 10 % of 5nd Harmonic and increase the value of harmonic in curve till
Block (Injection current must not excised the( limit IDIFF max of n-th harm-Restrain) setting

11-Cross Blocking 2nd Harmonics adress1612:


Procedure:
1. Inject two different phase at same time at one side
2. Phase A>Id with fundamental harmonics
3. Phase B>Id with 2nd harmonics
4. 1 Cycle=60HZ=1/60 =0.01666 sec
Time set in
(Cycles)
0.0
125
250
500
1000

Time set in
(s)
2.075
4.15
8.3
16.6

Time measured
(s)
126.3

Remarks
Test Inst. Used

FREJA300

Name: Eng.

Tested By

Mohamed

Shokry
Date:
20/07/09
Signature:

Witnessed
By

Name: Eng .ALI Al AMRI


Date:
Page 9 of 11

Site Test Report For Differential Protection


Customer SEC-SOA
Extension of Muhayil
Project
S/S 132/33 KV
Location MUHAYEL

Contract #

40631024/00

Job #
Equipment Tag

6T1

Table 6: Correction Factor for 87-Itrip(Wx)

Notes:
1. For this table, 0 is considered even.
2. Use this row if the I0Process setting for the tested winding is I0 Elimination. The settings
are Address 1106 for Winding 1, Address 1126 for Winding 2, and Address 1146 for Winding 3.
3. Use this row if the I0Process setting for the tested winding is either without or I0 CORRECTION. The settings
are Address 1106 for Winding 1, Address 1126 for Winding 2, and Address 1146 for Winding 3.In tests 1-3 current
is injected in one phase at any time; therefore, use the rows for 1-phase faults. The
other fault types are given if the user wishes to expand the tests.

Remarks
Test Inst. Used

FREJA300

Name: Eng.

Tested By

Mohamed

Shokry
Date:
20/07/09
Signature:

Witnessed
By

Name: Eng .ALI Al AMRI


Date:
Page 10 of 11

Site Test Report For Differential Protection


Customer SEC-SOA
Extension of Muhayil
Project
S/S 132/33 KV
Location MUHAYEL

Contract #

40631024/00

Job #
Equipment Tag

6T1

Remarks
Test Inst. Used

FREJA300

Name: Eng.

Tested By

Mohamed

Shokry
Date:
20/07/09
Signature:

Witnessed
By

Name: Eng .ALI Al AMRI


Date:
Page 11 of 11