Professional Documents
Culture Documents
Learning Objectives
After reading this lesson you will be able to understand
Importance of material planning
Applying MRP as scheduling and ordering system
Good Morning students, today we are going to introduce the concept of what
is known as Material Resources Planning. We will discuss about material
requirements planning (MRP) as an information system that enables managers to improve
the efficiency of operations, shorten delivery lead times to customers, and reduce
inventory levels.
Improved customer service and other advantages come at a cost, however. They
require a system for accurate inventory and product buildup information. They
also require a realistic master production schedule (MPS) to specify when
various quantities of end items will be completed.
DEMAND DEPENDENCY
The MPS is initially developed from firm customer orders or from forecasts
of demand before the MRP system begins to operate. The MPS is an input to the
MRP system. Designed to meet market demand, the MPS identifies the quantity
of each and product (end item) and when it needs to be produced during each
future period in the production-planning horizon.
The MRP system must retain an up-to-date file of the inventory status of each
item in the product structure. This file provides accurate information about the
availability of every item controlled by the MRP system which can then maintain
an accurate accounting of all inventory transaction, both actual and planned.
The MRP processing logic accepts the master schedule and determines
the components schedules for successively lower-level items of the product
structures. It calculates for each item in each product structure and for each time
period (typically one week) in the planning horizon how many of that item are
needed (gross requirements), how many units from inventory are already
available, the net quantity that must be planned on receiving in new shipments
(planned order receipts), and when orders for the new shipments must be placed
(planned order releases) so that all materials arrive just when needed.
The MRP computational procedure uses the input information to calculate the
current records for each component and item.
The MRP processing logic is applied first to the high-level items (end products) in
the product structure, then to the items on the next lower level.
PRODUCT EXPLOSION
LOW-LEVEL CODING
Often a single item is in the product structure of several end items, or it exists in
several levels of one product structure.
MRP is not state; it is responsive to new job orders from customers and current
shop conditions, as well as changes anticipated for the future.
1. Pegging: The process of tracing through the MRP records and all
levels in the product structure to identify how changes in the records of
one component will affect the records of other components.
2. Cycle counting: Counting on-hand inventories at regular intervals to
verify inventory quantities shown in the MRP
3. Regenerative method: A procedure, used at regular intervals, to
update the MRP by completely reprocessing the entire set of
information and recreating the entire MRP
4. Time fence: A designated length of time that must pass without
changing the MPS, to stabilize the MRP system; afterward, the MPS is
allowed to change.
LOT SIZING
The MRP system generates planned order releases, which trigger purchase
orders for outside suppliers or work orders for internal component production.
Each time the MRP system is updated managers must ask whether shop
capacity is sufficient to implement the current plan. Detailed capacity planning
(also called capacity requirements planning) is a technique that addresses this
question and it does so in more detail than the rough-cut method. New
information from MRP permits refinements that were not possible at the rough-
cut level.
A document that shows the routing of a component, including the work centers
and an operation time, through its production processes is called route sheet.
With that, we have come to the end of today’s discussions. I hope it has been an
enriching and satisfying experience. See you around in the next lecture. Take care. Bye.
With that, we have come to the end of today’s discussions. I hope it has been an
enriching and satisfying experience. See you around in the next lecture. Take care. Bye.