You are on page 1of 12

THE CITY OF ROSWELL

RECREATION, PARKS, HISTORIC & CULTURAL AFFAIRS DEPARTMENT

ROSWELL RIVER LANDING

Presented to: Mr. Jeff Pruitt Prepared by: Roy Weidman ARR

November 4, 2013

Introduction
At the request of Mr. Jeff Pruitt, Mark Tanner of M. Tanner Contracting and Roy Weidman of Atlanta Roofing Resources completed an examination of the roofs at Roswell River Landing on October 22, 2013. The examination was conducted in an effort to identify the sources of current leaks and collect information necessary to develop roof replacement and restoration recommendations. Information gathered during the roof examination is summarized in this report.

Roswell River Landing

November 4, 2013

Roof Construction
The roofs inspected at Roswell River Landing are separated into five different roof sections. The main roof is a steep sloped shingle roof. The shingle roof slopes steeply from a central metal covered chimney. The slope of the roof diminishes as it reaches the eaves. The last fifteen feet of the roof on all four sides has a slope of less than three inches per foot. The shingle roof terminates at all four sides with aluminum gutters and integral gutter covers. The chimney is sheathed in plywood and covered with shingles. The four smaller roofs on either side of the main roof are covered with two ply cold applied smooth surfaced modified bitumen roofs installed over plywood decks. These roofs are essentially flat and hold water around internally plumbed roof drains. Each of the two larger low slope roof sections has three covered curbs. The west roof section is over the Mens Room and Storage and the east roof section is over the Ladies Room and Storage.

Roof Conditions
The roof examination determined that leaks are entering the facility through several roof and roof related components. Defects that were found above or aligned with the leaks include the following: 1. Aged, delaminated, and failed shingles. The protective granules have worn off, leaving fiberglass stands exposed. 2. Exposed shingle staples. 3. Defective chimney cover. 4. Defective chimney cover fasteners. 5. Collapsed decking over the east low slope roof section. 6. Excessive build up of debris and ponding water on the low slope roof areas. Photographs taken of the roofs and related defects during the examination follow.

Roswell River Landing

November 4, 2013

The main roof, chimney structure, and low sloped side roofs on Roswell River Landing are shown above and below.

Roswell River Landing

November 4, 2013

Shingles used on the vertical chimney surface do not meet current manufacturers requirements. A vertical wall siding detail separated from the roof with metal counterflashing is a warranted detail.

These water defectors are not warranted details and will be eliminated.

Roswell River Landing

November 4, 2013

The steeply sloped shingle roof transitions to a moderately sloped roof around the last fifteen feet of the main roof. The last fifteen feet of the main roof, all around the perimeter, will require installation of Ice and Water Shield to protect the deck.

Roswell River Landing

November 4, 2013

All of the shingles have failed. The shingles appear to be the original shingles installed when the structure was built. The shingles are eroded, protective granules are missing, glass fibers are visible, and many shingle staples are protruding.

Roswell River Landing

November 4, 2013

Exposed staples are shown above and below. Staples are no longer an approved fastening method for manufacturer warranted shingle roofs.

Roswell River Landing

November 4, 2013

The chimney cover is badly rusted and is leaking. Exposed fasteners have backed out. The chimney cover, the stack cover, and the stack collar should all be replaced with pre-finished corrosion and rust resistant metal.

Roswell River Landing

November 4, 2013

The upper east roof section should have the covered curbs removed and the roof should be restored.

The upper west low slope roof area has collapsed around the covered curbs and drains. We found rotten decking and sagging joists below the sunken curb.

Roswell River Landing

10

November 4, 2013

Roof Replacement and Restoration Scope of Work Main Steep Slope Shingle Roof Area
1. Remove the existing shingles, underlayment, and any flashings. Dispose of all materials removed off site. 2. Remove and replace defective decking on a unit cost basis. 3. Remove the chimney covering shingles and dispose of off site. Install new chimney vertical plywood wall sheathing and trim. 4. Remove and replace the existing chimney cover with new 22 gauge Kynar coated steel. Install new gasket screw fasteners. Seal all folding lock seams with high performance twenty year construction sealant. Provide and install a new chimney stack cap and collar. 5. Install new wall flashing details at the base of the chimney. 6. Install new 30 pound underlayment over the steep sloped portion of the roof. Install ice and Water Shield over the chimney to roof flashing transition and over the low slope fifteen feet of the lower portion of the roof deck. 7. Install GAF Timberline Architectural shingles with a manufacturers 30 year warranty. Color to be selected by the City of Roswell from standard available colors. 8. Install all new termination and projection details per the roof system manufacturers requirements. Low Slope Roof Areas Upper West Roof Area 1. Remove the entire upper west low slope roof section of all materials removed off site. 2. Remove and replace defective decking on a unit cost basis. 3. Remove and replace defective joists on a unit costs basis. 4. Install new Red Rosin bleeder paper to the deck. Nail into place with one inch disc nails. Lap ends and sides 3 inches. 5. Install new G-2 fiberglass base sheet over the Red Rosin bleeder sheet. 6. Install tapered isocyanurate insulation to the base sheet with screws and discs applied at the rate of one per every three square feet. Minimum thickness shall be three inches; slope shall be 1/8 inch per foot. 7. Install a two ply cold applied mineral surfaced modified bitumen membrane assembly. 8. Install all new termination and projection details per the roof system manufacturers requirements. 9. Install New 24 gauge Kynar coated perimeter metal.

Roswell River Landing

11

November 4, 2013

Low Slope Roof Areas Lower West, Upper and Lower East Roof Areas 1. Remove the existing covered curbs from the east low slope roof area. Dispose of all materials removed off site. 2. Remove and replace defective decking on a unit cost basis. 3. Remove and replace defective decking on a unit cost basis. 4. Remove and replace defective joists on a unit costs basis. 5. Install new G-2 fiberglass base sheet over the Red Rosin bleeder sheet. 6. Install insulation to the base sheet with screws and discs applied at the rate of one per every three square feet. Match the thickness of the surrounding roof level. 7. Install a two ply cold applied mineral surfaced modified bitumen membrane assembly. 8. Repair all roof membrane and flashing defects with two plies of glass mesh embedded in and top dressed with asphalt mastic. 9. Allow the new roof materials to cure for 30 days, then apply one coat of SBS modified fibrated aluminum coating to the entire roof area at the rate of 2 gallons per 100 square feet in a figure 8 pattern.

Roswell River Landing

12

November 4, 2013

You might also like