Professional Documents
Culture Documents
Course Outline
Initiating a Project Planning Project Work Developing Project Schedules, Cost Estimates, and Budgets Planning Project Quality, Staffing, and Communications Analyzing Risks and Planning Risk Response Planning Project Procurement Executing Project Work Monitoring and Controlling Project Work Monitoring and Controlling Project Schedules and Costs Monitoring and Controlling Project Quality, Staffing, and Communications Monitoring and Controlling Project Risk and Contracts Closing the Project
Page 1 of 108
Inputs
Outputs
Initiating Processes
Planning Processes
Executing Processes
Closing Processes
Page 2 of 108
Pretest
1.
2.
Page 3 of 108
3.
4.
5.
Page 4 of 108
6.
7.
8.
9.
Page 5 of 108
10.
11.
12.
Page 6 of 108
13.
14.
15.
Page 7 of 108
16.
17.
18.
Page 8 of 108
19.
20.
21.
Page 9 of 108
22.
23.
24.
Page 10 of 108
25.
26.
27.
Page 11 of 108
28.
29.
Page 12 of 108
30.
31.
Page 13 of 108
32.
33.
34.
Page 14 of 108
35.
36.
Page 15 of 108
37.
38.
Page 16 of 108
39.
40.
41.
Page 17 of 108
42.
Page 18 of 108
43.
44.
Page 19 of 108
45.
46.
Page 20 of 108
47.
48.
Page 21 of 108
49.
50.
Page 22 of 108
51.
52.
53.
Page 23 of 108
54.
55.
Page 24 of 108
56.
57.
Page 25 of 108
58.
59.
Page 26 of 108
60.
61.
Page 27 of 108
62.
63.
Page 28 of 108
64.
65.
Page 29 of 108
66.
67.
68.
Page 30 of 108
Identify Stakeholders
Test Questions
____ 1. The project ____ usually provides the direction and funding for the project. a. planner c. sponsor b. coordinator d. auditor 2. Project ____ work with the project sponsors, the project team, and the other people involved in a project to meet project goals. a. organizers c. handlers b. designers d. managers 3. A projects ____ addresses questions concerning what unique product, service or result should be delivered to a customer or sponsor. a. schedule c. time-frame b. scope d. cost PMP Preparation Class | Out of Bounds Technology Page 31 of 108
____
____
____
____
____
____
____
____
____
____
____
____
____
____
4. Key elements of the project management framework include the project stakeholders, project management ____, project management tools and techniques, project success, and contribution of a portfolio of projects to the success of the entire enterprise. a. domain c. vision b. scope d. knowledge areas 5. Project ____ management involves defining and managing all the work required to complete the project successfully. a. time c. risk b. communications d. scope 6. Project ____ management, the ninth knowledge area, is an overarching function that affects and is affected by all of the other knowledge areas. a. human resource c. integration b. procurement d. quality 7. Some popular ____-management tools and techniques include Gantt charts, project network diagrams, and critical-path analysis. a. quality c. cost b. time d. scope 8. Project ____ may be defined as a test of whether a project has met scope, time, and cost goals. a. depth c. success b. clarity d. vision 9. Two important concepts that help projects meet enterprise goals are the use of programs and project ____ management. a. waste c. means b. portfolio d. promotion 10. Which of the following it the logical flow of any project? a. Planning, Initiating, Executing, Montoring c. Initiating, Planning, Montoring and and Controlling, Closing Controlling, Executing, Closing b. Initiating, Planning, Executing, Montoring d. Planning, Initiating, Executing, Montoring and Controlling, Closing and Controlling, Closing 11. A program ____ provides leadership and direction for the project managers heading the projects within the program. a. director c. facilitator b. organizer d. manager 12. Individual projects often address ____ goals, whereas project portfolio management addresses strategic goals. a. program c. tactical b. long-term d. minor 13. By grouping projects into ____, organizations can better tie their projects to meeting strategic goals. a. portfolios c. suites b. applications d. collections 14. Project managers and their teams must develop knowledge and skills in all ____ project management knowledge areas. a. five c. eleven b. nine d. fifteen 15. ____ management is a soft skill required to achieve high performance on projects. a. Scope c. Conflict b. Time d. Cost PMP Preparation Class | Out of Bounds Technology Page 32 of 108
____ 16. An organization should consider only projects with a ____ NPV if financial value is a key criterion for project selection. a. positive c. zero b. negative d. well-defined ____ 17. Projects involve five project management process groups: initiating, planning, ____, monitoring and controlling, and closing. a. delivering c. maintaining b. designing d. executing ____ 18. ____ processes include devising and maintaining a workable scheme to ensure that the project meets its scope, time, and cost goals as well as organizational needs. a. Initiating c. Securing b. Planning d. Protecting ____ 19. A ____ is a product or service produced or provided as part of a project. a. process c. deliverable b. result d. requirement ____ 20. Based on the PMBOK Guide, Fifth Edition , there are ____ knowledge areas in project management. a. 7 c. 25 b. 9 d. 10 ____ 21. Most time and money is normally spent on ____ because that is where the projects products and/or services (for example, the buildings for a construction project, the training courses for a training project, and so on) are produced. a. monitoring c. controlling b. executing d. planning ____ 22. The PMBOK Guide is a ____ that describes best practices for what should be done to manage a project. a. rule book c. protocol b. standard d. secondary authority ____ 23. After a project is approved, senior managers should meet to determine the ____, time, and cost constraints for the project. a. range c. vision b. scope d. boundary ____ 24. It often makes sense to break large projects down into two or more smaller ____. a. projects c. portfolios b. programs d. enterprises
Page 33 of 108
Page 34 of 108
Collect Requirements
Define Scope
Create WBS
Page 35 of 108
Define Activities
Sequence Activities
Page 36 of 108
Relationship
Description
Finish-to-start (FS)
Finish-to-finish (FF)
Start-to-start (SS)
Start-to-finish (SF)
Finish to Start
0
A 10 days
B 4 days
B (4 days)
Page 37 of 108
Start to Start
A 10 days
SS
B 4 days
A (10 days)
B (4 days)
Page 38 of 108
Finish to Finish
A 10 days
FF
B 4 days
A (10 days)
Page 39 of 108
Start to Finish
A 10 days SF
B 4 days
A (10 days)
B (4 days)
Page 40 of 108
Page 41 of 108
Develop Schedule
ES
EF
LS
DU
LF
Page 42 of 108
Page 43 of 108
Conduct a forward pass to determine early start (ES) and early finish (EF) times for each activity. Perform a backward pass to determine late start (LS) and late finish (LF) times for each activity. Calculate float. Identify the critical path as the path with the longest total duration and zero float.
Page 44 of 108
Page 45 of 108
Estimate Costs
Page 46 of 108
Determine Budget
Test Questions
____ 1. The main purpose of project planning is to guide project ____. a. initiation c. review b. execution d. evaluation 2. Planning includes tasks related to each of the ____ project management knowledge areas. a. 4 c. 10 b. 5 d. 16 3. Project ____ management involves coordinating all the project management knowledge areas throughout a projects life span. a. union c. unification b. synthesis d. integration 4. Project management ____ facilitate communication among stakeholders and provide a baseline for progress measurement and project control. a. charters c. contracts b. plans d. compacts 5. The main planning tasks performed as part of project scope management include scope planning, scope definition, and ____. a. scope evaluation c. creating the WBS b. scope reduction d. scope expansion 6. The main output of scope planning is a ____ management plan, which is a document that includes descriptions of how the team will prepare the scope statement, create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope. a. scope c. program b. project d. portfolio 7. The project team develops a preliminary scope statement during project ____. a. review c. orientation b. initiation d. development PMP Preparation Class | Out of Bounds Technology Page 47 of 108
____
____
____
____
____
____
____
____
____
____
____
____
____
____
____
____
8. Scope statements should include, at a minimum, a description of the project, including its overall objectives and justification; detailed descriptions of all project ____; characteristics and requirements of products and services produced as part of the project; and project success criteria. a. stakeholders c. meetings b. volunteers d. deliverables 9. To define the ____ of the project accurately, it is very important to ensure consistency between the project charter, scope statement, WBS, Gantt chart, and related documents. a. scope c. vision b. charter d. parameters 10. The project manager should work with his or her team and ____ to determine the level of detail needed in the WBS dictionary. a. client c. auditor b. customer d. sponsor 11. Performance in meeting project scope goals is based on the scope ____. a. definition c. baseline b. revision d. statement 12. The project team begins to develop a ____ by first clearly defining all the activities it needs to perform. a. charter c. scope b. schedule d. work flow diagram 13. Activity ____ provide schedule-related information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity. a. features c. properties b. characteristics d. attributes 14. After defining project activities, the next step in project time management is activity ____. a. organization c. segmenting b. sequencing d. ordering 15. There are ____ basic reasons for creating dependencies among project activities. a. three c. five b. four d. six 16. ____ dependencies are inherent in the nature of the work being performed on a project. a. Embedded c. Mandatory b. Absolute d. Compulsory 17. ____ dependencies involve relationships between project and nonproject activities. a. Internal c. Ancillary b. External d. Miscellaneous
____ 18. A three-point estimate is an estimate that includes a(n) ____, most likely, and pessimistic estimate, such as three weeks, four weeks, and five weeks, respectively. a. optimistic c. remote b. unusual d. conditional ____ 19. Duration estimates are provided as a ____ number, such as four weeks; as a range, such as three to five weeks; or as a three-point estimate. a. continuous c. fractional b. random d. discrete ____ 20. What is the PERT weighted average based on an optimistic estimate of 6 days, a most likely estimate of 8 days, and a pessimistic time of 12 days? a. 6 c. 11 b. 8 d. 12 PMP Preparation Class | Out of Bounds Technology Page 48 of 108
Page 49 of 108
Identify Risks
Page 50 of 108
Page 51 of 108
Page 52 of 108
Page 53 of 108
Page 54 of 108
Hygiene factors: Larger salaries, more supervision, and a more attractive work environment. These factors cause dissatisfaction if not present, but do not motivate workers to do more.
Page 56 of 108
Power Modes
Power is the potential ability to influence behavior to get people to do things they would not otherwise do. Types of power include: Coercive power Legitimate power Expert power Reward power Referent power
Manage Communications
Page 57 of 108
Conduct Procurements
Page 58 of 108
Monitoring and Controlling Process Group Monitor and Control Project Work
Page 59 of 108
Validate Scope
Control Scope
Control Schedule
Page 60 of 108
Control Costs
Measurement
Equation
Schedule variance
SV = EV - PV
SPI = EV / PV
Cost variance
CV = EV AC
CPI = EV / AC
Page 61 of 108
EAC= AC+(BAC-EV) EAC=BAC/CPI TCPI = (BAC-EV)/(BAC-AC) VAC = BAC-EAC ETC = remaining money left
Page 62 of 108
Control Quality
Control Communications
Page 63 of 108
Control Risks
Control Procurements
Page 64 of 108
Close Procurements
Page 65 of 108
Test Questions
Page 66 of 108
Page 67 of 108
Page 68 of 108
Page 69 of 108
Page 70 of 108
Page 71 of 108
Page 72 of 108
Page 73 of 108
Page 74 of 108
Page 75 of 108
Page 76 of 108
Page 77 of 108
Page 78 of 108
Page 79 of 108
Page 80 of 108
Page 81 of 108
Page 82 of 108
Page 83 of 108
Page 84 of 108
Page 85 of 108
Page 86 of 108
Page 87 of 108
Page 88 of 108
Page 89 of 108
Page 90 of 108
Page 91 of 108
Page 92 of 108
Page 93 of 108
Page 94 of 108
Page 95 of 108
Page 96 of 108
Page 97 of 108
Page 98 of 108
Page 99 of 108