Professional Documents
Culture Documents
PM CASE STUDIES
4- Cost rates:
Average labor cost rate = $ 10 per man-day
-----------------------------------------------------------------------------------------Part 3: PM Case Studies
-1 -
Required:
1)
2)
3)
4)
5)
6)
7)
8)
810
810 * 6 = 4860
Annual
Frequency
1
Duration
(day)
15
PM Downtime
(day)
15 * 1= 15
1
2
8
10
5
2
10 * 1 = 10
5 * 2 = 10
2 * 8 = 16
51
Annual
Frequency
1
1
2
8
Cost
$1000
10
8
5
2
Spare parts PM
Cost $1000
10 * 1= 10
8*1=8
5 * 2 = 10
2 * 8 = 16
Month #
6
7
3M
3M
M
M
S
M
M
M
3M
M
M
3M
Y
M
M
S
M
M
M
3M
M
M
M
Y
M
M
S
3M
M
M
3M
M
M
M
Y
M
M
M
3M
M
M
3M
S
M
M
Y
M
M
M
3M
M
M
M
S
M
M
Y
3M
M
M
3M
M
10
11
12
Resource analysis:
Manday
Day/
month
Workers
SP cost
DT
580 230 580 230 580 230 580 230 580 230 580 230
24
24
24
24
24
24
24
24
24
24
24
24
24
26
33
10
18
18
24
26
33
10
18
18
24
26
33
10
18
18
24
26
33
10
18
18
24
26
33
10
18
18
24
26
33
10
18
18
Y= 300 S= 200
Y= 10 S= 8
Y= 15 S= 10
3M= 75
3M= 5
3M= 5
M= 20
M= 2
M= 2
man-day
$1000
day
Month #
G01
G02
G03
G04
G05
G06
10 11 12
3M
3M
M M Y
M 3M M
M
S
M
3M M M
M M 3M
M
M
M
S
M
M 3M M M S
Y M M 3M M
3M M M
Y
M
M M 3M M M
M
S
M M 3M
M
M
M
Y
M
M 3M
S M
3M M
M M
M
Y
Resource analysis:
Manday
Workers
SP cost
DT
455 355 455 355 455 355 355 455 355 455 355 455
19
23
28
15
21
23
19
23
28
15
21
23
Y= 300 S= 200
Y= 10 S= 8
Y= 15 S= 10
19
23
28
15
21
23
3M= 75
3M= 5
3M= 5
15
21
23
19
23
28
M= 20
M= 2
M= 2
15
21
23
19
23
28
15
21
23
19
23
28
man-day
$1000
day
Month #
G01
G02
G03
G04
G05
G06
10 11 12
3M
3M
M
M
M
M
M
M
3M
S
M
3M
Y
M
M
M
M
M
M
3M
S
M
M
Y
M
M
M
3M
M
M
3M
S
M
M
Y
M
M
M
3M
M
M
3M
M
M
M
Y
M
S
M
3M
M
M
M
M
M
M
Y
3M
S
M
3M
M
Resource analysis:
Manday
Workers
SP cost
DT
400 410 400 410 400 410 400 410 400 410 400 410
17
20
25
17
24
26
17
20
25
17
24
26
Y= 300 S= 200
Y= 10 S= 8
Y= 15 S= 10
17
20
25
17
24
26
3M= 75
3M= 5
3M= 5
17
20
25
17
24
26
M= 20
M= 2
M= 2
17
20
25
17
24
26
17
20
25
17
24
26
man-day
$1000
day
G01
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
Y
SB
G02
G03
G04
G05
G06
M
M
SB
M
M
SB
M
M
SB
M
M
SB
M
M
SB
PM worker
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
10
10
10
10
10
10
10
10
10
10
-
Coding:
-----------------------------------------------------------------------------------------Part 3: PM Case Studies
- 10 -
Spare
parts
cost $1000
10
8
5
2
---
Y Level 1 Yearly
Shutdown 14 day
20
S Level 2
6 Monthly Shutdown 7 day
15
3M Level 3 3 Monthly Shutdown 4 day
10
M Level 4 Monthly
Shutdown 2 day
8
W Level 5 Weekly
Running 5 hours
2
D Level 6 Daily
Running 1 hours
2
Gas turbine operating conditions: 24 hour/day
Workers operating conditions: 300 day/year & 8 hour/day
Average effort of CM = 380 man-day per gas turbine
Average annual CM cost = $ 12000 per gas turbine
Average CM downtime = 15 days/year per gas turbine
Average downtime cost rate = $ 1000 per day
Labor cost rate = $ 10 per man-day
Overhead cost = 25 % direct cost (spare parts & labor)
Required:
1. The size of maintenance labor force.
2. Average system availability.
3. Annual PM plan.
4. Annual downtime cost losses.
5. Annual maintenance cost.
P4:
The yearly PM programs information for six similar fire tube
boilers (FB01 through FB06) in a textile company are as
follows:
Weekly
Monthly
(Shutdown)
(Shutdown)
Check for tight
closing of fuel
Inspect burner
valves
Check fuel and Analyze
air linkage
combustion
Check indicating
Check cams
lights and alarms
S. Annually
(Shutdown)
Clean low
Check water
water cutlevel
off(s)
Blowdown
Check oil
boiler
preheater
Blowdown
Inspect
water column
refractory
Check
Clean oil
Check operating Inspect for flue
combustion
pump strainer
and limit controls gas leaks
visually
and filter
Treat water
Clean air
Check safety
according to the
Inspect for hot cleaner and
and interlock
established
spots
air/oil
controls
program
separator
Record boiler
Check low water Review boiler Check pump
operating
cutoff(s)
blowdown
coupling
pressure/
operation
procedures
alignment
temperature
Check for leaks,
Record feed
Check
noise, vibration,
Reset
water pressure/
combustion air
unusual
combustion
temperature
supply
conditions
Inspect
Record flue gas Check operation Check all filter
mercury
temperature
of all motors
elements
switches
Record oil
Check general Check fuel
pressure and
burner operation systems
temperature
Annually
(Shutdown)
Clean fireside
surfaces
Clean breeching
Clean waterside
surfaces
Check oil storage
tanks
Check fluid levels
on hydraulic
valves
Check gauge
glass
Remove and
recondition safety
valves
Check oil pumps
Check boiler feed
pumps
Record gas
pressure
Check
condensate
receivers
Record
atomizing
pressure
Check general
boiler/burner
operation
Check flame
scanner
assembly
Check chemical
feed systems
Check packing
glands
Check
lubrication
requirements
Tighten all
electrical
terminals
PM Level
Y Level 1
S Level 2
M Level 4
W Level 5
Spare parts
cost $1000
4
2
1
0.5
Required:
1. The size of maintenance labor force.
2. Average system availability.
3. Annual PM plan.
4. Annual downtime cost losses.
5. Annual maintenance cost.
Number
of M/C
Turning
Grinding
M/c
Type
Turning
Grinding
6
3
Required:
1. The size of PM labor force.
2. Annual PM cost.
3. Annual PM plan.
4. Average down time per month.
5. Average system availability.
0.95
0.9
0.95
0.9
0.8
0.8
G
0.9
M/c
Type
Number
Maintenance level
of
10 days
6 Monthly
Yearly
M/cs
W D O
W
D
O
W
D
Lath
4
3 1 10
4
2
20
5
4
Drilling
2
2 1 10
4
2
20
Grinding 1
3
2
20
3
3
W: Number of workers D: Maint. duration (day) O: Oil (liter)
- Working conditions:
Operating: 52 week/year, 6 day/week, two shifts
Manpower: 45 week/year, 6 day/week, one shift
O
20
20
Lath
2
100
2000
20
Drilling Grinding
2
60
1000
12
2
80
1000
10
T
T
Standby
Standby
M/c
Type
Number
of
machines
Turning
3
Milling
2
Drilling
1
Grinding
1
M/c Type
Turning
Milling
Drilling
Grinding
- Working conditions:
Production & maintenance 52 week/year, 6 day/week, two
shifts.
Manpower 45 week/year, 6 day/week, one shift.
-----------------------------------------------------------------------------------------Part 3: PM Case Studies
- 18 -
Drilling
12
Grinding
8
Required:
1. The size of maintenance labor force.
2. Annual maintenance cost.
3. Annual maintenance plan with the best manpower
profile.
4. Average down time for each machine type.
5. Average availability for each machine type.
6. Average system availability
7. Average down time cost for each machine type.
MAINTENANCE FORECASTING
Y=a+bX
Sum Y = n . a + b Sum X ,
Year
2000
Year
2001
Year
2002
Exp.
2003
1450
1300
1200
1000
3
1200
3600
4
1000
4000
X
Y
XY
1
1450
1450
2
1300
2600
n=4
Sum X = 10
Sum Y = 4950
Forecasting
limits
2003
?
5
?
Sum X2 = 30
Sum XY = 11650
Sum Y = n . a + b Sum X ,
4950 = 4 a + 10 b
11650 = 10 a + 30 b
14850 = 12 a + 30 b
a = 1600
b = - 145
Y = 1600 145 X
X
A
F
(A-F)
(A-F)2
2
1300
1310
10
100
3
1200
1165
35
1225
4
1000
1020
20
400
5
875
CLs = 0 Z S = 0 48
-----------------------------------------------------------------------------------------Part 3: PM Case Studies
- 21 -
P9:
An casting company has the following yearly production and
overhead cost data:
Year
Production
quantity
(1000 ton)
Maintenance
cost (M L.E.)
96
5.2
97
5.5
98 99
6.0 6.4
00
6.5
01
7.0
02
7.5
03
7.9
1.3
1.5
1.8 2.0
2.1
2.2
2.5
3.0
Required:
1)
2)
3)
4)
5)
6)
P10:
Uncertain spare parts cost
Spare parts cost
Probability
$ 100,000
9
10
11
12
13
%
20
50
20
7
3
T01
D01
M01
T02
M02
T01
8
M01
20
5
5
8
4
7
3
5
6
5
12
Required:
1. If the maximum worker limit is 12 worker/day,
construct the corresponding monthly maintenance
plan.
2. Calculate the monthly spare parts cost.
3. Construct the monthly spare parts cost profile.
Required:
1. If the maximum worker limit is 12 worker/day,
construct the corresponding monthly
maintenance plan.
2. Calculate the monthly spare parts cost.
3. Construct the monthly spare parts cost profile.
P13: A Bus company has about 1500 bus. The capital maintenance
and engine overhaul is carrying out after about 250,000 to 300,000
km (about two years) and its duration is about 10 day. The overhaul
information for each bus engine are as follows:
Activity ID
Predecessors
Duration (day)
Worker/day
A
2
4
B
1
2
C
1
3
D
1
2
E
B&D
2
4
F
C
1
3
G
F
2
1
H
E&G
2
1
W01
W02
W03
1- Activity List
ID
Activity
1
2
3
Preparation
PRP
Mech. maintenance # 01 MM1
Elec. maintenance # 01 EM1
4
5
6
7
8
Mech. maintenance # 02
Elec. maintenance # 02
Mech. maintenance # 03
Elec. maintenance # 03
Setup
MM2
EM2
MM3
EM3
STP
Duration
Predece
(day)
ssors
2
7
PRP
9
M
M
1
6
PRP
8
MM2
5
PRP
7
MM3
1
EM1
EM2
EM3
Relations
(SS, FS,
FF, and SF)
SS 3
SS 2
SS 2
-
2- Resource List
Resource
Code
L01
L02
SPS
Resources description
Unit
Mechanical worker
Electrical worker
Spare parts & supplies
md
md
cost
Limits/day
Norm. Max.
3
6
4
8
-
Price
LE/unit
40
60
1000
3- Resource Allocation
ID
Activity
1
2
3
4
5
6
7
8
Preparation
PRP
Mech. maintenance # 01 MM1
Elec. maintenance # 01
EM1
Mech. maintenance # 02 MM2
Elec. maintenance # 02
EM2
Mech. maintenance # 03 MM3
Elec. maintenance # 03
EM3
Setup
STP
L01/
day
2
4
3
2
2
Resource
L02/
SPS
day
(Total)
1
1
3
5
4
2
4
3
2
3
3
2
1
Monday
Tuesday
Wednesday
Thursday
X
1/01/04
Friday
Required:
1. Draw the project network (logic diagram)?
2. Draw the corresponding Gantt chart?
3. Construct the corresponding smoothed worker
loading?
4. Construct the corresponding worker leveling?
5. Construct the target action plan?.
6. Construct the cost profile & S-curve?
7. Construct the target master plan?
1- Activity List
1
2
3
4
5
6
7
8
9
Activity
Preparation
Server maintenance
Hardware maintenance
Lab #01
Software maintenance
Lab #01
Hardware maintenance
Lab #02
Software maintenance
Lab #02
Hardware maintenance
Lab #03
Software maintenance
Lab #03
Setup
PRP
SRM
HM1
Duration
(day)
1
3
4
Predece Relations
ssors
PRP
SRM
-
SM1
HM1
SS 2
HM2
SRM
SM2
HM2
SS 1
HM3
SRM
SM3
HM3
SS 1
STP
SM1
SM2
SM3
ID
2- Resource List
Resource
Code
L01
L02
SPS
Resources description
Unit
Hardware Engineer
Software Engineer
Spare parts & supplies
md
md
cost
Limits/day
Norm. Max.
3
6
4
8
-
Price
LE/unit
120
100
1000
3- Resource Allocation
ID
Activity
1
2
3
Preparation
Server maintenance
Hardware maintenance
Lab #01
Software maintenance
Lab #01
Hardware maintenance
Lab #02
Software maintenance
Lab #02
Hardware maintenance
Lab #03
Software maintenance
Lab #03
Setup
4
5
6
7
8
9
Resource
L02/
SPS
day
(Total)
1
1
1
1
2
PRP
SRM
HM1
L01/
day
2
1
4
SM1
HM2
SM2
HM3
SM3
STP
Sunday
Monday
Tuesday
Wednesday
Thursday
Friday
X
X
X
X 1/01/04
Holidays: 20 to 21 Jan. 2004
Required:
1. Draw the project network (logic diagram)?
2. Draw the corresponding Gantt chart?
3. Construct the corresponding smoothed worker loading?
4. Construct the corresponding worker leveling?
5. Construct the target action plan?.
6. Construct the cost profile & S-curve?
7. Construct the target master plan?
-----------------------------------------------------------------------------------------Part 3: PM Case Studies
- 30 -
A
B(2)
D(2)
C(2)
E(2)
E(2)
F(2)
G(1)
Component
Lead time (week)
On-Hand
A
1
10
B
2
15
D(2)
C
1
20
D
1
10
E
2
10
F
3
5
Required:
1. Time-phased for the gear box structure
2. Gross requirements plan for 50 gear box
3. Net material requirements plan for 50 gear box.
G
2
0
Solution
Mean arrival
rate
= 3, {0,8}
Maintenance
service
facility
Mean service
rate
= 6, {0,7}
P19:
The CM information for a production department are as
follows:
1. Labor maintenance cost rate = $10/hr
2. Downtime cost rate = $50/hr per machine.
3. The mean number of failures is four/hr, and distributed
according to a Poisson distribution.
4. The mean number of repairs is six repairs per workerhour, and distributed exponentially
What is the best maintenance crew size?
Solution
Mean arrival rate
= 4, Poisson
Labor cost =
$10/hr
= 6 /worker,
Exp.
Crew Size?
Downtime cost =
$50/hr/machine
Crew
Size
1
2
3
4
5
6
12
18
24
30
Ns =
Labor
Downtime
Total
/ ( - )
cost
cost
cost
2.00
0.50
0.29
0.20
0.15
$/hr
10
20
30
40
50
$/hr
100.00
25.00
14.29
10.00
7.69
$/hr
110
45
44.29
50.00
57.69
P20:
The CM information for a production department are as
follows:
5. Labor maintenance cost rate = $20/hr
6. Downtime cost rate = $150/hr per machine.
7. The mean number of failures is five/hr, and distributed
according to a Poisson distribution.
8. The mean number of repairs is five repairs per workerhour, and distributed exponentially
What is the best maintenance crew size?
P21:
The CM information for a production department is as
follows:
Labor maintenance cost rate = $20/hr
Downtime cost rate = $150/hr per machine.
The mean number of failures is five/hr, and distributed
according to a Poisson distribution.
The mean number of repairs is five repairs per worker-hour,
and distributed exponentially
Required:
1. Determine the best maintenance crew size?
2. Calculate the utilization factor of the maintenance
crew?
3. Determine the mean time in the system?
4. Calculate the probability of finding two machines in the
system?
P22:
A factory has 200 machines and the maintenance
engineer supervises the repair crews who repair
malfunctioning machines. The maintenance policy is to
repair the broken down machine and bring back in
production within 2 hours on the average. If average
breakdown rate is 3.5 machines/hour and each repair
crew can repair 0.25 machine per hour on the average.
How many repair crews are required ?
The formula for average repair rate () is
1
ts = ---------or
-
Where = repair rate
= + 1/ ts
Month
March
Week 1
360
Week 2
320
Week 3
300
Week 4
380
April
340
350
320
380
May
420
412
452
380
June
390
370
350
410
Determine and plot the control chart for the weekly backlog.
(For n = 4, d2 = 2.059.)
Basic data
Item
January
February
2004
2004
Production rate (ton/hr)
8
8
Total time (hr/day)
24
Feb. / Jan.
100 %
24
100 %
67 %
20
111 %
100 %
17
113 %
136
113 %
105
125 %
98
129 %
7
(7%)
684
64 %
1326
98 %
92 %
Performance Evaluation
Indicator
January
2004
Availability
18/24= 75 %
February
2004
20/24= 83 %
Feb. / Jan.
111 %
Performance
efficiency
Quality rate
80/120= 67 %
105/136= 77 %
115 %
70/80= 88 %
98/105= 93 %
106 %
Utilization ratio
15/18= 83 %
17/20= 85 %
102 %
Uptime (hr/day)
70/8= 8.75
98/8= 12.25
140 %
Uptime ratio
8.75/15= 49%
12.25/17=72 %
147 %
OEE
44 %
60 %
136 %
TEEP
37 %
51 %
138 %
NEE
29 %
52 %
179 %
700
684
98 %
1326
92 %
Energy
productivity
(kwh/ton)
Material
productivity (1000
L.E/ton)
1429
P26:
The six-monthly maintenance costs ($1000) for a
productive system are as follows:
Target Costs:
Jan
Feb
Month #
Mar Apr May
100
50
100
50
100
50
100
50
100
50
100
50
100
50
200
150
300
200
150
300
200
150
300
200
150
300
200
150
300
200
150
300
200
150
300
Feb
Month #
Mar Apr May
Jun
Jly
23
32
38
65
49
96
56
94
68
94
65
90
54
72
231
503
407
213
370
397
181
293
320
185
164
290
199
201
330
196
193
320
157
142
362
Cost item
PM Cost:
Spar parts
Labor
CM Cost:
Spar parts
Labor
DT Cost
Jun
Jly
Actual Costs:
Cost item
PM Cost:
Spar parts
Labor
CM Cost:
Spar parts
Labor
DT Cost
Jan
Target:
Cost item
PM Cost
CM Cost
TM Cost
DT Cost
TM+DT
PM/TM
CM/PM
Jan
150
350
800
300
1100
0.14
2.33
Feb
150
350
800
300
1100
0.14
2.33
Mar
150
350
800
300
1100
0.14
2.33
Month #
Apr May
150 150
350 350
800 800
300 300
1100 1100
0.14 0.14
2.33 2.33
Jun
150
350
800
300
1100
0.14
2.33
Jly Total
150 1050
350 2450
800 5600
300 2100
1100 7700
0.14 0.955
2.33 16.33
Actual:
Cost item
PM Cost
CM Cost
TM Cost
DT Cost
TM+DT
PM/TM
CM/PM
Month #
Apr May
150 162
349 400
789 892
290 330
1079 1222
0.19 0.18
2.33 2.47
Jun
155
369
864
320
1184
0.18
2.38
Jly Total
126
896
299 3208
787 6550
362 2426
1149 8976
0.16 1.007
2.37 31.82
Change %:
Cost item
Jan
Month #
Feb Mar Apr May Jun
Jly
Total
PM Cost
CM Cost
TM Cost
DT Cost
TM+DT
PM/TM
CM/PM
P27:
The yearly PM programs information for six similar gas
turbines in a power station are as follows:
PM
18
264
--51
CM
7
72
--15
Total
25
336
75
514
66
PM
20
300
--45
CM
10
100
--5
Total
30
400
80
520
50
Target
Actual
25
336
30
400
Change
%
+ 20
+ 19
($1000)
Annual labor cost ($1000)
Overhead cost ($1000)
Total m. cost ($1000)
Average down time
Down time cost ($1000)
75
514
925
66
66
80
520
1000
50
50
+ 6.6
+ 1.2
+ 8.1
- 24.3
- 24.3
991
81.9
7/18 =
38.9
72/264 =
27.3
514/411=
1.25
1050
86.3
10/20 =
50
100/300 =
33.3
520/480=
1.08
+ 6.0
+ 5.3
+ 28.5
25/6=
4.17
30/6=
5.00
- 16.6
TMC + DTC
Availability %
CM/PM % (labor force)
CM/PM % (Spare parts)
Overhead %
Labor productivity %
(worker/gas turbine)
+ 22.0
- 13.6
P28:
The six-monthly maintenance costs ($1000) for a productive
system are as follows:
Target Costs:
Cost item
Month #
PM Cost:
Spar parts
Labor
CM Cost:
Spar parts
Labor
DT Cost
100
50
100
50
100
50
100
50
100
50
100
50
100
50
200
150
300
200
150
300
200
150
300
200
150
300
200
150
300
200
150
300
200
150
300
Actual Costs:
Cost item
PM Cost:
Spar parts
Labor
CM Cost:
Spar parts
Labor
DT Cost
Jan
Feb
Month #
Mar
Apr May
Jun
Jly
23
32
38
65
49
96
56
94
68
94
65
90
54
72
231
503
407
213
370
397
181
293
320
185
164
290
199
201
330
196
193
320
157
142
362
Target:
Cost item
Jan
PM Cost
CM Cost
DT Cost
TM Cost
150
350
300
800
Feb
150
350
300
800
Month #
Mar Apr May
150
350
300
800
150
350
300
800
150
350
300
800
Jun
Jly
150
350
300
800
150
350
300
800
Jun
Jly
155
369
320
864
126
299
362
787
Actual:
Cost item
Jan
PM Cost
55
CM Cost
734
DT Cost
407
TM Cost 1196
Feb
103
583
397
1083
Month #
Mar Apr May
145
474
320
939
150
349
290
789
162
400
330
892
Standard
Quantity
Rate
20,00
6000
ton
40,000
L.E.
15
hour
L.E.
150,000 L.E.
100,000 L.E.
300,000 L.E.
Actual
Quantity
Rate
15,00
6400
ton
45,000
L.E.
18
hour
L.E.
180,000 L.E.
80,000 L.E.
350,000 L.E.
P30:
The annual budget and the actual maintenance cost for XXX
production department are as follows:
Budget
Current Year to
Actual
Current
Year to
month
6000
5936
2000
1000
1000
month
5000
4111
700
500
1200
date
60000
53834
12000
10000
10000
date
65000
58834
10000
5000
12000
P31:
Maintenance Planning for Spare Parts Work Shop
1- Equipment List
Plant
Systems
Productive
systems
Supportive
systems
Location
Machining
shop
Equipment Type
Turning
Milling
Drilling
Grinding
Press
Induction furnaces
Molding machines
Arc Welding
Foundry
shop
Welding
shop
Material
Fork lift
handling
Air room
Compressor
Water room Pump 50 HP
Pump 100 HP
Power
Diesel generator
room
Number of
Machines
4
2
2
2
1
2
5
1
4
2
2
2
2
3- Equipment reliability
T
0.9
0.9
0.8
0.8
0.9
0.9
0.9
0.8
0.8
0.9
Weekly
Man Hr
Turning
2
5
Milling
2
5
Drilling
1
3
Grinding
2
3
Press
1
2
Monthly
Man Hr
3
16
3
12
-
6 Monthly
Yearly
Man Hr
Man Hr
5
24
5
16
2
10
3
12
3
12
3
16
2
6
3
12
Weekly
B
O
Turning
3
Milling
2
Drilling
1
Grinding
1
Press
1
B : Bearing
4-3- PM Cost:
Monthly
6 Monthly
B
O
B
O
5
4
4
6
4
8
4
6
O: Oil (liter)
Yearly
B
O
4
12
4
10
4
8
4
8
4
8
Oil $ 5 /liter