Professional Documents
Culture Documents
lower usage on the weekends higher usage during the summer and winter
greater temperature extremes
Economics
savings are gained by decommitting some of the generation units when they are not need to meet the current load demand the engineering problem is committing enough units to meet current and future load demands while minimizing starting and operating costs
Max Gen
Min Gen
P1
P2
P3
F1
F2
150 0 50 0 50
Infeasible Infeasible Infeasible 0 3760 5389 0 4911 0 3030 2440 2787 2244
F3
Unit 3
on on on on off off off off off off off off off off off
on on on on on on on on on on on on on on on
Total Loading
Unit Output
Regional Generation
Unit Capacity
Spinning Reserve
Region
(MW)
(MW)
(MW)
(MW)
Western region
Units 1, 2 & 3 550 MW maximum
1 Western 2 3 4 5
100 380 380 160 290 1310 160 (in) 160 (out)
Eastern region
Units 4 & 5 Eastern Total
2002, 2004 Florida State University
(MW)
Unit
eastern region
generation of largest unit: 1040 MW available spinning reserve
local: 450 MW; tie-line capacity: 550 MW; western region: 700 MW total: 1000 MW - load can not be completely supplied
10
11
two approaches available to treating a thermal unit during its down time
allow the boiler to cool down and then heat it back up to operating temperature in time for a scheduled turn-on provide enough fuel to supply sufficient energy to the boiler to just maintain the operating temperature
12
banking input sufficient energy into the boiler to just maintain the operating temperature banking cost function:
Cbank = H bank F fuel tshut down + C fixed
0 0 1 2 3 4 5 6 7 hr
13
Commitment by enumeration
a brute force method
total combinations to investigate: 2N 1 for the total period of M intervals, the maximum number of possible combinations is: (2N 1)M
example: for a 24-hour period made up of 1-hr intervals, a 5 unit network become 6.2 1035 combinations
2002, 2004 Florida State University
14
various enhancements can be made to the priority-list scheme by the grouping of units to ensure that various constraints are met
15
16
17
notes
this scheme does not completely parallel the shut-down sequence described in the first example
there unit 2 was shut down at 600 MW leaving unit 1 here unit 1 is shut down at 400 MW leaving unit 2 why the differences? where is the problem?
18