INSTALLATION PROCEDURE FOR DRUMS

EXTERNAL

CLIENT (FW)
END USER (EMAPPL)

TOTAL

ExxonMobil Asia Pacific Pte. Ltd.


Foster Wheeler
Project Title : Singapore Hydrocarbon Expansion Project (S-HCF)
ISBL Mechanical Works, Piping Fabrication and
Installation
Contract No. : SC-12/13900/9
P.O. No.

M.R. No.

Equip. Item No. :

PURPOSE
INFORMATION
PRELIMINARY
TENDER

APPROVAL

Req. Item No. :

CONFIRMATION

Equip. Title

CONSTRUCTION

Client Document No. :

AS-BUILT

FWIC Doc Type :

DSN :

FWIC Rev:

Supplier Doc No. :


Status Code:
By :

Dept:

Supplier Rev:
Date:

Comment Status Code:


1-Rejected; 2-Comments as Noted; 3-Minor Comments Acceptable;
4-No Comments; 5-Information Only

Total No. of Sheets


4 (Incl. cover sheet)

A
REV.
TITLE:

Issued For Approval


DESCRIPTION

Gin Ling
PREPD

Zhao JC
CHKD

Page

Page 1 of 4

Chan YB
APPD

16.01.08
DATE

INSTALLATION PROCEDURE( DRUM )


PEC JOB NO.
00AP2000

0!

FW CONTRACT NO.
SC-12/13900/9

DOCUMENT NO.
ISBL-WP-MEC-27

REV. NO.
A

PLANT ENGINEERING CONSTRUCTION PTE LTD


21 SHIPYARD ROAD SINGAPORE 628144 TEL: 6268 9788 FAX: 6268 9488
Document No:

Date:
16 Jan. 2008
Rev. No:

Installation Procedure for Drums

ISBL-WP-MEC-27
Page 2 of 4

CONTENTS

1.0

SCOPE

2.0

REFERENCES

3.0

LIFTING & LIFTING GEARS

4.0

INSTALLATION METHOD

5.0

ALIGNMENT

6.0

GROUTING

7.0

SAFETY

PLANT ENGINEERING CONSTRUCTION PTE LTD


21 SHIPYARD ROAD SINGAPORE 628144 TEL: 6268 9788 FAX: 6268 9488
Document No:

Date:
16 Jan. 2008
Rev. No:

1.0

Installation Procedure for Drums

ISBL-WP-MEC-27
Page 3 of 4

SCOPE
This procedure specifies the requirement for the erection, alignment and grouting work of drums.
Erection, Alignments & Leveling BY PEC
R9601 Cold Separator Drum , D-9602
T-9601 Overhead Drum ,
D-9603
Fuel Gas Knock Out Drum ,
D-9611
C-9601 Suction K.O Drum,
D-9620
R-9702 Cold Separator Drum , D-9702
T-9801 Overhead Drum ,
D-9801
T-9802 Overhead Drum ,
D-9802
Erection by Heavy Lifting Contractor & Alignments / Leveling BY PEC
Kero Feed Surge Drum
D9600
R9601 Hot Separator Drum , D-9601
Hot Oil Surge Drum ,
D-9610
R-9702 Hot Separator Drum , D-9701
T-9701 Overhead Drum ,
D-9703
T-9701 Off Gas Drum ,
D-9704

2.0

REFERENCES
2.1 Manufacturers drawings
2.2 Specification for grouting and workmanship 13900-43C8

3.0

LIFTING & LIFTING GEARS


Refer to lifting plan by FW & PEC.

4.0

INSTALLATION METHOD
4.1 Mark out locations where drum is to be installed and conduct necessary site measurements to
note if there is any deviations from equipment drawing.
4.2 Check the anchor bolts dimension, quantity, elevation and the orientation of the concrete
foundation against the drum skirt/saddle baseplate.
4.3 Install the soleplate padding level.

PLANT ENGINEERING CONSTRUCTION PTE LTD


21 SHIPYARD ROAD SINGAPORE 628144 TEL: 6268 9788 FAX: 6268 9488
Document No:

Date:
16 Jan. 2008
Rev. No:

Installation Procedure for Drums

ISBL-WP-MEC-27

Page 4 of 4

4.4 After lifting the drums into position, lock nuts of anchor bolt. Later, tightened it to the specified
torque value.
4.5 Conduct the following inspection before and after grouting: : a. Plumbness for the vertical shall be made by viewing from two direction 90 deg.
b. Levelness, orientation and interference
5.0

ALIGNMENT
Plumbness of the drums shall be checked not to exceed a certain tolerance value. Other information
refers to ITP.

6.0

GROUTING
Unless otherwise specified, grouting shall be carried out in accordance with the following:
6.1 Foundation surface shall be cleaned thoroughly and be removed of any dirt or oily spots. Surface
of foundation shall be wetted thoroughly with fresh water prior to grouting.
6.2 Portland cement mortar may be used and mixing ratio with clean fine sand shall be
approximately 1: 2 in volume and ratio of water to cement shall be less than 40 % in volume.
6.3 Grouting on base plate shall be:
a. Space under the base plate shall be packed fully with non-shrink grout
b. All shims and wedges shall be fully cover with grout
c. After pouring, excess grout shall be trimmed and surface of mortar outside of the base plate
shall be finished smoothly.

7.0

SAFETY
Refer to the attached JRIS for the alignment work of Drums.