You are on page 1of 5

Activity ID

Activity Name

Original
Duration

Activity % Start
Complete

Finish

246
22-May-13
30-Apr-14
Energia Mayakan Pipeline Expansion Project - Detailed
E&D
- Revised

A
22-May-13 A 14-Mar-14

213

Milestones

BL1 Start

BL1 Finish

22-May-13 15-Oct-13
22-May-13 15-Oct-13

Limited Notice to Proceed (LNTP)

100% 22-May-13 A

A1010

Full Notice to Proceed (FNTP)

100% 17-Jun-13 A

A1020

Project Kick-off Meeting

100%

22-May-13 A

22-May-13

A1030

LNTP Deliverables Issued

100%

14-Jun-13 A

14-Jun-13

A1040

Detail Engineering & Design Schedule

100%

11-Jul-13 A

11-Jul-13

A1050

Receive 100% Survey Data for Pipeline Cooridor

0%

03-Dec-13*

19-Jul-13

A1060

Issue Drawings for Client Review - EM#2

100%

12-Nov-13 A

24-Sep-13

A1070

Issue for Construction Drawings - All Drawings

0%

14-Mar-14*

15-Oct-13

A1080

Issue SCADA Specification

100%

23-Jul-13 A

31-Jul-13

A1090

Issue Preliminary Plot Plans

100%

18-Jul-13 A

17-Jul-13

A1170

Issue Drawings for Client Review - Pipeline, MLV#1, MLV#2 0

0%

06-Mar-14

24-Sep-13

A1180

Issue Drawings for Client Review - EM#3

24-Oct-13 A

10-Sep-13

A1190

Issue Drawings for Client Review - Interconnect

Engineering, Design and Procurement

100%

100%

213

17-Jun-13

12-Nov-13 A
22-May-13 A 14-Mar-14

26

02

June
09 16

23

30

July
07 14

21

28

August
04 11 18

25

2013
September
01 08 15 22

17-Sep-13

22-May-13 15-Oct-13

-108

Design Basis Manual

17

100% 22-May-13 A 14-Jun-13 A 22-May-13 14-Jun-13

-1

Pipeline
A1110
Survey Specification

15
7

22-May-13 A 11-Jun-13 A 22-May-13 11-Jun-13


100% 22-May-13 A 31-May-13 A 22-May-13 31-May-13

0
-1

11

100% 22-May-13 A 06-Jun-13 A 22-May-13 06-Jun-13

-1

100% 03-Jun-13 A 11-Jun-13 A 03-Jun-13 11-Jun-13

18
17

22-May-13 A 14-Jun-13 A 22-May-13 14-Jun-13


100% 22-May-13 A 14-Jun-13 A 22-May-13 14-Jun-13

0
-1

Preliminary Pipe/Costing Requisition

Mechanical / Piping
A1140
Preliminary P&IDs

Full Notice to Proceed (FNTP)


General
Project Management (General)
A1220 Pipeline Cooridor Survey - By Arendal

23

30

06

April
13

20

27

May
04
30-Apr-14, Energia Mayakan Pi

Receive 100% Survey Data for Pipeline Cooridor


Issue Drawings for Client Review - EM#2
Issue for Construction Drawings - All Drawings
Issue SCADA Specification
Issue Preliminary Plot Plans
Issue Drawings for Client Review - Pipeline, MLV#1, MLV#2
Issue Drawings for Client Review - EM#3
Issue Drawings for Client Review - Interconnect
14-Mar-14, Engineering, Design and Procurement

14-Jun-13 A, Project Management / Project Engineering

Design Basis Manual


11-Jun-13 A, Pipel ine
Survey Specification
Preliminary Hydraulic Analysis
Preliminary Pipe/Costing Requisition
14-Jun-13 A, Mechanical / Piping
Preliminary P&IDs

-108

14-Mar-14, Full Notice to Proceed (FNTP)

201
201
11

07-Jun-13 A 14-Mar-14
07-Jun-13 A 14-Mar-14
90.91% 07-Jun-13 A 03-Dec-13

07-Jun-13 14-Oct-13
07-Jun-13 09-Aug-13
07-Jun-13 21-Jun-13

-109
-155
-117

14-Mar-14, General
14-Mar-14, Project Management (General)

100% 07-Jun-13 A 11-Jul-13 A

07-Jun-13 03-Jul-13

-6

A1380

Facilities Survey

15

100% 07-Jun-13 A 19-Jul-13 A

A1440

Site Visit

A1790
A1800
A1860

Internal HAZOP

07-Jun-13 27-Jun-13

-16

100% 24-Jun-13 A 28-Jun-13 A 24-Jun-13 28-Jun-13

Formal Client HAZOP

100% 05-Aug-13 A 06-Aug-13 A 30-Jul-13

Review IFC Package

21

0% 14-Feb-14

100% 16-Jul-13 A

146
135
16

31-Jul-13

14-Mar-14

29-Jul-13

09-Aug-13

16-Jul-13 A

16-Jul-13

16-Jul-13

07-Jun-13 A 30-Dec-13
24-Jun-13 A 30-Dec-13
0% 03-Dec-13* 27-Dec-13

Pipeline Cooridor Survey - By Arendal


Detail Engineering and Design Schedule
Facilities Survey
Site Visit
Formal Client HAZOP

-11
0

07-Jun-13 14-Oct-13
24-Jun-13 14-Oct-13
01-Aug-13 30-Aug-13

-55
-55
3

24-Jun-13 15-Jul-13

-1

Review IFC Package


Internal HAZOP
30-Dec-13, Engineering (General)
30-Dec-13, Mechanical/Piping (General)
Stress Analysis

A1990 Filters/Separator Skids Requisition

15

100% 24-Jun-13 A 16-Jul-13 A

A2010 Meter Skid Requisition

16

100% 15-Jul-13 A

01-Aug-13

A2030 Condensate Tank Requi sition

15

100% 16-Aug-13 A 27-Aug-13 A 05-Aug-13 23-Aug-13

Condensate Tank Requi sition

100% 02-Aug-13 A 21-Aug-13 A 22-Jul-13

09-Aug-13

Instrument Gas Posts Requisition

05-Aug-13 A 11-Jul-13

A3040 Ball Valves Requisition

15

100% 08-Jul-13 A

30-Jul-13 A

29-Jul-13

16-Aug-13

-1

A3060 Plug Valves Requisition

100% 26-Jul-13 A

31-Jul-13 A

15-Jul-13

02-Aug-13

12

A3080 Large Pipe and Fittings Requisition

15

100% 19-Aug-13 A 18-Oct-13 A 19-Aug-13 09-Sep-13

-30

A3400 Pressure Safety Valves Requisition

15

100% 20-Aug-13 A 23-Oct-13 A 26-Aug-13 16-Sep-13

-31

A3420 Restriction Orifices Requisition

15

100% 20-Aug-13 A 19-Nov-13 A 26-Aug-13 16-Sep-13

-50

A3440 Valves (6" and Smaller) Requisition

15

100% 15-Aug-13 A 07-Oct-13 A 08-Aug-13 28-Aug-13

-22

A3470 Filters/Separator Skid TBE

100% 20-Aug-13 A 27-Aug-13 A 08-Oct-13 14-Oct-13

A3480 Check Valves Requisition

15

100% 05-Aug-13 A 20-Aug-13 A 29-Jul-13

16-Aug-13

100% 20-Aug-13 A 13-Sep-13 A 03-Sep-13 09-Sep-13

-14

A3500 Globe Valves Requisition

March
09 16

07-Jun-13 15-Oct-13

19

A3490 Ball Valves TBE

02

07-Jun-13 A 14-Mar-14

Detail Engineering and Design Schedule

A3010 Instrument Gas Posts Requisition

23

201

A1230

Engineering (General)
Mechanical/Piping (General)
A1980 Stress Analysis

26

Detail Engineering & Design Schedule

Mobilization of Project Team Personnel and famil iari zati on of F EED documents

A1150

29

LNTP Deliverables Issued

0
0

Preliminary Hydraulic Analysis

01

February
02 09 16

Full Notice to Proceed (FNTP)

A1130

24

January
05 12 19

Project Kick-off Meeting

22-May-13 A 14-Jun-13 A 22-May-13 14-Jun-13

A1120

27

December
08 15 22

14-Mar-14, Milestones

18
22-May-13 A 14-Jun-13 A 22-May-13 14-Jun-13
Project Management / Project Engineering
A1100
Mobilization of Project Team Personnel and famil iari zati on of F3EED documents
100% 22-May-13 A 24-May-13 A 22-May-13 24-May-13

18

29

November
03 10 17

Limited Notice to Proceed (LNTP)

14-Jun-13 A, Limited Notice to Proceed (LNTP)

Limited Notice to Proceed (LNTP)

2014
October
06 13 20

-108

A1000

22-May-13

Variance BL1
Duration19
-141

15

100% 05-Aug-13 A 20-Aug-13 A 29-Jul-13

16-Aug-13

A3510 Meter Skid TBE

100% 26-Aug-13 A 30-Aug-13 A 03-Sep-13 09-Sep-13

A3520 Plug Valves TBE

100% 30-Aug-13 A 06-Sep-13 A

-6

A3530 Instrument Gas Post TBE

100% 01-Oct-13 A 28-Oct-13 A

-19

A3540 Condensate Tank TBE

A3550 Check Valves TBE

100% 26-Sep-13 A 02-Oct-13 A

A3560 Globe Valves TBE

A3570 Valves (2"-6") TBE

16.67% 26-Sep-13 A 09-Dec-13

Primary Baseline

Critical Remaining Work

Actual Work

Milestone

Remaining Work

Summary

Filters/Separator Skids Requisition


Meter Skid Requisition

Ball Valves Requisition


Plug Valves Requisition
Large Pipe and Fittings Requisition
Pressure Safety Valves Requisition
Restriction Orifices Requisition
Valves (6" and Smaller) Requisition
Filters/Separator Skid TBE
Check Valves Requisition
Ball Valves TBE
Globe Valves Requisition
Meter Skid TBE
Plug Valves TBE
Instrument Gas Post TBE
Condensate Tank TBE

-53
-5

Check Valves TBE

100% 26-Sep-13 A 02-Oct-13 A

-5

Globe Valves TBE

0% 28-Oct-13 A 16-Dec-13

-36

Valves (2"-6") TBE

Activity ID

Activity Name

Original
Duration

Activity % Start
Complete

Finish

27.27% 25-Nov-13 A 12-Dec-13

BL1 Start

BL1 Finish

19-Aug-13 30-Aug-13

Variance BL1
Duration19
-4

26

02

June
09 16

23

30

July
07 14

21

28

August
04 11 18

2013
September
01 08 15 22

25

A3580 Large Pipe and Fittings TBE

11

A3590 Gate Valve

19

100% 09-Aug-13 A 06-Sep-13 A 09-Sep-13 09-Sep-13

A4960 Wall Thickness Calculations

33

100% 01-Jul-13 A

26-Jul-13 A

01-Jul-13

15-Aug-13

13

Wall Thickness Calculations

A4970 Facility Piping Specification

29

100% 08-Jul-13 A

30-Jul-13 A

08-Jul-13

15-Aug-13

13

Facility Piping Specification

A4980 Tie-in List

12

100% 12-Sep-13 A 07-Oct-13 A 15-Jul-13

01-Oct-13

39

-20

A4990 Pressure Safety Valves TBE

0% 03-Dec-13

12-Dec-13

01-Aug-13 14-Aug-13

A5110 Restriction Orifices TBE

0% 25-Nov-13 A 30-Dec-13

03-Sep-13 09-Sep-13

-21

27-Sep-13
15-Aug-13

-17
-8

100% 26-Sep-13 A 23-Oct-13 A 23-Sep-13 27-Sep-13

-14

117
38

07-Jun-13 A 16-Dec-13
100% 07-Jun-13 A 23-Jul-13 A

07-Jun-13 07-Oct-13
07-Jun-13 31-Jul-13

-50
6

A1960 Telecommunications Specification

38

100% 07-Jun-13 A 30-Jul-13 A

08-Jul-13

28-Aug-13

A2200 Leak Detection Specification

38

100% 07-Jun-13 A 01-Aug-13 A 08-Jul-13

28-Aug-13

-1

A2410 Instrument Skid Specification

100% 08-Jul-13 A

10-Jul-13

-4

A2960 Analyzer Control Building TBE

12

A3140 RTU Requisition

20

100% 01-Aug-13 A 05-Sep-13 A 22-Aug-13 22-Aug-13

100% 16-Oct-13 A 22-Oct-13 A 26-Aug-13 09-Sep-13

Electrical (General)
A1520 Thermoelectric Generators Requisition
A2450 Thermoelectric Generators TBE
Instrumentation (General)
A1710 SCADA Specification

A3150 RTU TBE

50
15
6

26-Jul-13 A
100% 26-Jul-13 A

23-Oct-13 A 26-Jul-13
28-Aug-13 A 26-Jul-13

16-Jul-13 A

09-Jul-13

75% 24-Oct-13 A 05-Dec-13

11-Sep-13 A 15-Jul-13

06-Sep-13

-6

A4380 Instruments Requisitions

24

100% 08-Jul-13 A

26-Sep-13 A 08-Jul-13

08-Aug-13

-35

A4390 SCADA TBE

100% 03-Sep-13 A 10-Sep-13 A 12-Aug-13 07-Oct-13

35

A4400 Leak Detection TBE

100% 03-Sep-13 A 10-Sep-13 A 29-Jul-13

25

100% 03-Sep-13 A 10-Sep-13 A 07-Oct-13 07-Oct-13

09-Sep-13

RTU TBE
Analyzer Control Building Requisition
Instruments Requisitions
SCADA TBE
Leak Detection TBE

-5

Telecommunications T BE

100% 07-Jun-13 A 19-Aug-13 A

-51

Leak Detection Requisition

100% 07-Jun-13 A 19-Aug-13 A

-51

A1430 Monolithic Isolation Joint Requisition

24

A1460 Cathodic Protection Calculations

46

A1620 Monolithic Isolation Joint TBE

100% 17-Jun-13 A 18-Jul-13 A


0% 22-Jul-13 A

14-Mar-14

17-Jun-13 19-Jul-13
08-Jul-13

-108
-123
-123
-2
1

24-Sep-13

-114

100% 19-Aug-13 A 20-Aug-13 A 13-Aug-13 19-Aug-13

A1640 Hinged Closures TBE

12

A1650 Review IFC Package

A1660 Pig Sig Passage Indicator Requisition

100% 30-Sep-13 A 01-Oct-13 A 30-Jul-13

12-Aug-13

100% 16-Oct-13 A 26-Nov-13 A 19-Aug-13 19-Aug-13

-29

A1670 Pig Sig Passage Indicator TBE


A5300 Hinged Closures Requisition
Mechanical/Piping (PL, MLV1, MLV2)
A3600 Small Pipe and Fittings Requisition
A3620 Large Pipe and Fittings TBE
A5480 Review IFC Package
A5560 Small Pipe & Fitting TBE
A5590 Large Pipe and Fittings Requisition

100% 29-Aug-13 A 20-Sep-13 A 29-Jul-13


0% 07-Mar-14

14-Mar-14

-6
-6

13

100% 08-Jul-13 A

82
5

19-Aug-13 A 14-Mar-14
19-Aug-13 30-Aug-13
100% 18-Nov-13 A 26-Nov-13 A 19-Aug-13 30-Aug-13

11-Jul-13 A

09-Aug-13

16-Aug-13 16-Aug-13

25-Jun-13 12-Jul-13

0% 25-Nov-13 A 12-Dec-13

-14

0% 03-Dec-13

14-Mar-14

-74

0% 03-Dec-13

12-Dec-13

-8

100% 19-Aug-13 A 19-Nov-13 A


20-Aug-13 A 14-Mar-14
0% 20-Aug-13 A 20-Dec-13

01-Jul-13 30-Aug-13
26-Aug-13 30-Aug-13

A1610 Review IFC Package

34

0% 07-Oct-13 A 14-Mar-14

01-Jul-13

Electrical (PL, MLV1, MLV2)


A5490 Review IFC Package

36
34

07-Oct-13 A 14-Mar-14
0% 07-Oct-13 A 14-Mar-14

23-Aug-13

20-Sep-13
17-Jul-13

A5370 I/O List

13

100% 16-Jul-13 A

18-Jul-13 A

16-Jul-13

01-Aug-13

11

A5380 Review IFC Package

34

0% 07-Oct-13 A 14-Mar-14

09-Sep-13 20-Sep-13

-105

195
190
65

17-Jun-13 A 14-Mar-14
24-Jun-13 A 14-Mar-14
0% 24-Jun-13 A 06-Mar-14

17-Jun-13 15-Oct-13
24-Jun-13 15-Oct-13
24-Jun-13 24-Sep-13

-108
-108
-119

0% 08-Jul-13 A

08-Jul-13

24-Sep-13

-118

01-Aug-13 24-Sep-13

-64

06-Mar-14

01-Aug-13 24-Sep-13

-126

10-Jul-13 A

02-Jul-13

12-Jul-13

A1410 Typical Pipeline Drawings/Details

28

A1420 Site Location Maps

28

0% 22-Jul-13 A

100% 02-Jul-13 A

A1480 Geotech Testing Locati on Drawi ngs

06-Mar-14

35.71% 12-Aug-13 A 31-Dec-13

Mainline Pipe / Coating Requisition


Monolithic Isolation Joint Requisition
Cathodic Protection Calculations
Monolithic Isolation Joint TBE
Hinged Closures TBE
Review IFC Package
Pig Sig Passage Indicator Requisition
Pig Sig Passage Indicator TBE
Hinged Closures Requisition
14-Mar-14, Mechanical/Piping (PL, MLV1, MLV2)
Small Pipe and Fittings Requisition
Large Pipe and Fittings TBE
Review IFC Package
Small Pipe & Fitting TBE
Large Pipe and Fittings Requisition
14-Mar-14, Civil/Structural (PL, MLV1, MLV2)
MLV Foundation Calculations

-76

08-Jul-13
08-Jul-13

46

14-Mar-14, Pipeline, MLV#1, MLV#2


14-Mar-14, Engineering (PL, MLV1, MLV2)
14-Mar-14, Pipeline (PL, MLV1, MLV2)

Review IFC Package


14-Mar-14, Electrical (PL, MLV1, MLV2)
Review IFC Package

-115
-115

14-Mar-14
18-Jul-13 A

A1400 HDD Drawings

SCADA Network Architectural Diagram

-66

03-Jul-13 A
100% 03-Jul-13 A

Design (PL, MLV1, MLV2)


Pipeline (PL, MLV1, MLV2)
A1360 Construction Alignment Sheets

Telecommunications Requisition
23-Jul-13 A, Design (General)
23-Jul-13 A, Instrumentation (General)

-104
-84

108
8

Instrumentation (PL, MLV1, MLV2)


A5360 Instrument Index

Instruments TBE

-140
4

71

73
5

Civil/Structural (PL, MLV1, MLV2)


A1550 MLV Foundation Calculations

10

-128
-3

14-Mar-14, Instrumentation (PL, MLV1, MLV2)


Instrument Index
I/O List
Review IFC Package
14-Mar-14, Design (PL, MLV1, MLV2)
14-Mar-14, Pipeline (PL, MLV1, MLV2)
Construction Alignment Sheets
HDD Drawings
Typical Pipeline Drawings/Details
Site Location Maps
Geotech Testing Locati on Drawi ngs

A1490 Crossing Drawings

36

0% 01-Aug-13 A 06-Mar-14

15-Jul-13

24-Sep-13

-105

Crossing Drawings

A1510 Class Location Study

64

0% 25-Jun-13 A 06-Mar-14

25-Jun-13 24-Sep-13

-119

Class Location Study

A1600 Finalize IFC Drawings

0% 07-Mar-14

25-Sep-13 15-Oct-13

17-Jun-13 15-Oct-13
17-Jun-13 10-Jul-13

-108
-9

14-Mar-14

Finalize IFC Drawings


14-Mar-14, Mechanical/Piping (PL, MLV1, MLV2)

Mechanical/Piping (PL, MLV1, MLV2)


A1450 PFD/P&ID (IFCA)

195
17

A1570 Piping Sections and Details

41

100% 02-Jul-13 A

12-Nov-13 A 15-Jul-13

24-Sep-13

-45

Piping Sections and Details

A1580 MLV Assembly Drawing

51

100% 15-Jul-13 A

12-Nov-13 A 15-Jul-13

24-Sep-13

-35

MLV Assembly Drawing

A1760 Finalize IFC Drawings

71

25-Sep-13 15-Oct-13

-59

A1820 Piping Plot Plan

22

Civil/Structural (PL, MLV1, MLV2)

176

17-Jun-13 A 14-Mar-14
100% 17-Jun-13 A 23-Jul-13 A

0% 03-Dec-13

14-Mar-14

100% 17-Jun-13 A 18-Jul-13 A


24-Jun-13 A 14-Mar-14

08-Jul-13

06-Aug-13

-1

12-Jul-13

15-Oct-13

-122

May
04

Analyzer Control Building TBE

15-Oct-13
24-Sep-13
24-Sep-13
29-Jul-13

27

RTU Requisition

17-Jun-13
17-Jun-13
17-Jun-13
17-Jun-13

20

Leak Detection Specification

A5420 Telecommunications Requisition

14-Mar-14
14-Mar-14
14-Mar-14
31-Jul-13 A

April
13

Instrument Skid Specification

A5410 Leak Detection Requisition

17-Jun-13 A
17-Jun-13 A
17-Jun-13 A
100% 17-Jun-13 A

06

Telecommunications Specification

SCADA Requisition

195
195
195
30

30

16-Dec-13, Instrumentation (General)

-53

9
9
9

23

SCADA Specification

-51

31-Jul-13
31-Jul-13
31-Jul-13

March
09 16

Thermoelectric Generators TBE

100% 07-Jun-13 A 19-Aug-13 A

08-Jul-13
08-Jul-13
08-Jul-13

02

Thermoelectric Generators Requisition

23-Jul-13 A
23-Jul-13 A
23-Jul-13 A

23

Restriction Orifices TBE

A5400 SCADA Requisition

10-Jul-13 A
10-Jul-13 A
100% 10-Jul-13 A

26

23-Oct-13 A, Electrical (General)

50% 26-Sep-13 A 16-Dec-13

18
18
18

01

Pressure Safety Valves TBE

20

Pipeline, MLV#1, MLV#2


Engineering (PL, MLV1, MLV2)
Pipeline (PL, MLV1, MLV2)
A1390 Mainline Pipe / Coating Requisition

23-Sep-13 27-Sep-13

24

February
02 09 16

Tie-in List

100% 10-Jul-13 A

Design (General)
Instrumentation (General)
A3020 SCADA Network Architectural Diagram

27

December
January
08 15 22 29 05 12 19
Large Pipe and Fittings TBE

Gate Valve

-25

39

A4420 Instruments TBE

29

November
03 10 17

-31

A4010 Analyzer Control Building Requisition

A4410 Telecommunications T BE

2014
October
06 13 20

PFD/P&ID (IFCA)

Finalize IFC Drawings


Piping Plot Plan
14-Mar-14, Civil/Structural (PL, MLV1, MLV2)

Activity ID

Activity Name

Original
Duration

Activity % Start
Complete

Finish

BL1 Start

26

02

June
09 16

23

30

July
07 14

21

28

August
04 11 18

25

2013
September
01 08 15 22

2014
29

October
November
December
06 13 20 27 03 10 17 24 01 08 15 22
Soil Erosion & Sediments and Control Details

51

100% 15-Jul-13 A

A1530 Foundation Plans & Details

16

100% 24-Jun-13 A 07-Oct-13 A 26-Aug-13 17-Sep-13

-59

Foundation Plans & Details

A1560 Fencing/Grading Details

52

100% 08-Jul-13 A

24-Sep-13

-13

Fencing/Grading Details

A1750 Finalize IFC Drawings

71

25-Sep-13 15-Oct-13

-59

Electrical (PL, MLV1, MLV2)


A1590 Electrical Plans & Details
A1770 Finalize IFC Drawings
Instrumentation (PL, MLV1, MLV2)
A1780 Finalize IFC Drawings
A2480 Wiring Diagrams
CPG Nuevo Pemex Interconnect
Engineering (Interconnect)
Mechanical/Piping (Interconnect)
A2210 Flow Control Valves Skid Requisition
A2330 Flow Control Valves Skid TBE

185
60

03-Jul-13 A
100% 03-Jul-13 A

07-Oct-13 A 12-Jul-13
14-Mar-14

14-Mar-14
01-Jul-13
07-Oct-13 A 01-Jul-13

24-Sep-13

Variance BL1
Duration19
-9

A1470 Soil Erosion & Sediments and Control Details

0% 03-Dec-13

07-Oct-13 A 15-Jul-13

BL1 Finish

15-Oct-13
24-Sep-13

-106
-8

71

0% 03-Dec-13

14-Mar-14

25-Sep-13 15-Oct-13

-59

160
71

24-Jul-13 A
0% 03-Dec-13

14-Mar-14
14-Mar-14

08-Jul-13 27-Sep-13
09-Sep-13 27-Sep-13

-108
-59

24

100% 24-Jul-13 A

07-Oct-13 A 08-Jul-13

06-Sep-13

-9

195
185
185
15

17-Jun-13 A
01-Jul-13 A
01-Jul-13 A
100% 01-Jul-13 A

14-Mar-14
14-Mar-14
14-Mar-14
26-Jul-13 A

15-Oct-13
16-Sep-13
16-Sep-13
22-Jul-13

-108
-129
-129
-4

100% 28-Aug-13 A 30-Aug-13 A 10-Sep-13 16-Sep-13

A2380 Review IFC Package

71

Civil/Structural (Interconnect)
A5500 Review IFC Package

108
71

21-Oct-13 A 14-Mar-14
0% 03-Dec-13 14-Mar-14

-105
-74

A5510 Flow Control Valve Skid Foundation Calculation

0% 21-Oct-13 A 20-Dec-13

-45

A5520 Engineered Pipe Supports Requisition

0% 18-Nov-13 A 17-Dec-13

-22

0% 06-Jan-14

A5530 Engineered Pipe Supports TBE


A5540 Vault Foundation Calculation

10

0% 03-Dec-13

14-Mar-14

17-Jun-13
01-Jul-13
01-Jul-13
01-Jul-13
15-Jul-13

06-Sep-13

10-Jan-14

-5
-45

Engineered Pipe Supports TBE


Vault Foundation Calculation
14-Mar-14, Design (Interconnect)
14-Mar-14, Mechanical/Piping (Interconnect)

27

100% 19-Aug-13 A 12-Nov-13 A 08-Aug-13 17-Sep-13

A1870 Piping Isometric Drawings

71

0% 03-Dec-13

14-Mar-14

18-Sep-13 01-Oct-13

-64

A1920 Finalize IFC Drawings

71

0% 03-Dec-13

14-Mar-14

18-Sep-13 15-Oct-13

-54

A5090 Finalize Piping Plot Plan

15

Civil/Structural (Interconnect)
A5430 Site Fence & Grading Plan

122
1

19-Aug-13 A 14-Mar-14
100% 19-Aug-13 A 12-Nov-13 A

-150
-62

A5440 Pipe Support Details

100% 19-Aug-13 A 12-Nov-13 A

-62

Pipe Support Details

A5450 Hot Tap Vault Details

100% 19-Aug-13 A 11-Nov-13 A

-61

Hot Tap Vault Details

100% 19-Aug-13 A 12-Nov-13 A

-62

Typical Details

17-Jun-13 A
27-Jun-13 A
01-Jul-13 A
100% 10-Jul-13 A

A1890 Cathodic Protection Design

69

A1950 Valve List

56

Piping Isometric Drawings


Finalize IFC Drawings
Finalize Piping Plot Plan
14-Mar-14, Civil/Structural (Interconnect)
Site Fence & Grading Plan

Finalize IFC Drawings

-74
17-Jun-13
01-Jul-13
01-Jul-13
08-Jul-13

15-Oct-13
15-Oct-13
07-Oct-13
13-Aug-13

-108
-110
-114
-5

0% 01-Jul-13 A

14-Mar-14

01-Jul-13

07-Oct-13

-116

91.07% 15-Jul-13 A

09-Dec-13

15-Jul-13

01-Oct-13

-50

100% 31-Oct-13 A 26-Nov-13 A 09-Sep-13 09-Sep-13

-18

A3630 Large Pipe and Fittings Requisition

100% 19-Aug-13 A 18-Nov-13 A

-65

0% 25-Nov-13 A 12-Dec-13

-14

Piping Plans, Sections, Details

-5

A3610 Small Pipe & Fittings Requisition


A3640 Large Pipe and Fittings TBE

PFD / P&IDs (IFCA)


Piping Plot Plan (IFCA)

-33

14-Mar-14
14-Mar-14
14-Mar-14
23-Aug-13 A

14-Mar-14, Nuevo Pemex Meter Station - EM#2


14-Mar-14, Engineering (EM#2)
14-Mar-14, Mechanical/Piping (EM#2)
Line Sizing Calculations
Cathodic Protection Design
Valve List
Small Pipe & Fittings Requisition
Large Pipe and Fittings Requisition
Large Pipe and Fittings TBE

A5000 Restriction Orifice Sizing Calculation

13

100% 16-Aug-13 A 19-Nov-13 A 01-Aug-13 21-Aug-13

-52

A5010 Equipment List

41

87.8% 29-Jul-13 A

09-Dec-13

15-Jul-13

01-Oct-13

-40

Equipment List

A5020 Line List

41

87.8% 16-Aug-13 A 09-Dec-13

15-Jul-13

01-Oct-13

-26

Line List

A5160 Review IFC Package

71

24-Sep-13 30-Sep-13

-69

A5570 Small Pipe & Fittings TBE

0% 03-Dec-13

14-Mar-14

Restriction Orifice Sizing Calculation

Review IFC Package


Small Pipe & Fittings TBE

60% 18-Nov-13 A 06-Dec-13

154
5

20-Aug-13 A 14-Mar-14
0% 20-Aug-13 A 20-Dec-13

10-Jul-13 11-Oct-13
07-Oct-13 11-Oct-13

-81
-84

Analyzer Building Foundation Calculation

A5120 Filter/Scrubber Skid Foundation Calculation

0% 20-Aug-13 A 20-Dec-13

13-Aug-13 19-Aug-13

-84

Filter/Scrubber Skid Foundation Calculation

A5130 Meter Skid Foundation Calculation

0% 20-Aug-13 A 20-Dec-13

30-Aug-13 06-Sep-13

-84

Meter Skid Foundation Calculation

10

0% 20-Aug-13 A 20-Dec-13

18-Sep-13 01-Oct-13

-79

Misc. Equipment Foundation Calculations

A5150 Emergeny Generator Foundation Calculation

0% 20-Aug-13 A 20-Dec-13

30-Sep-13 04-Oct-13

-84

Emergeny Generator Foundation Calculation

A5240 Engineered Pipe Supports TBE

0% 20-Dec-13

23-Dec-13

10-Jul-13

A5270 Review IFC Package

71

0% 03-Dec-13

14-Mar-14

20-Aug-13 20-Aug-13

-74

A5310 Engineered Pipe Supports Requisition

41

80.49% 20-Aug-13 A 12-Dec-13

12-Aug-13 16-Aug-13

-78

175
15

27-Jun-13 A 14-Mar-14
15-Jul-13 15-Oct-13
100% 01-Aug-13 A 29-Aug-13 A 09-Aug-13 29-Aug-13

-120
-5

A2230 Distribution Panel / MCC Requisition

15

100% 13-Aug-13 A 11-Sep-13 A 16-Aug-13 06-Sep-13

-6

A2250 Transformer Requisition

15

100% 01-Aug-13 A 22-Aug-13 A 04-Sep-13 24-Sep-13

A2260 UPS Requisition

15

100% 20-Aug-13 A 11-Sep-13 A 16-Aug-13 06-Sep-13

-2

A2270 ATS Requisition

15

100% 08-Aug-13 A 29-Aug-13 A 16-Aug-13 06-Sep-13

A2280 200 A Breakers Requisition

15

100% 20-Aug-13 A 11-Sep-13 A 16-Aug-13 06-Sep-13

-2

A2300 SKM Calculations

11

100% 11-Jul-13 A

Civil/Structural (EM#2)
A5100 Analyzer Building Foundation Calculation

A5140 Misc. Equipment Foundation Calculations

Electrical (EM#2)
A2220 Emergency Generator Requisition

A2310 Load Study


A2320 Cable Sizing
A2340 Emergency Generator TBE
A2440 Review IFC Package

-15

11-Oct-13 A 25-Jul-13

100% 27-Jun-13 A 22-Jul-13 A

15-Jul-13

30-Jul-13

-56

23-Jul-13

-10

21

100% 20-Aug-13 A 17-Oct-13 A 26-Aug-13 24-Sep-13

-21

100% 26-Sep-13 A 26-Nov-13 A 15-Aug-13 21-Aug-13

-38

71

A2470 Distribution Panel / MCC TBE

A2680 UPS TBE

A2690 ATS TBE

0% 03-Dec-13

14-Mar-14, Civil/Structural (EM#2)

13

08-Aug-13

14-Mar-14

16-Aug-13 06-Sep-13

-59

0% 02-Oct-13 A 09-Dec-13

27-Sep-13 27-Sep-13

-49

0% 02-Oct-13 A 09-Dec-13

15-Jul-13

02-Aug-13

-34

100% 26-Sep-13 A 23-Oct-13 A 19-Aug-13 23-Aug-13

-14

May
04

Flow Control Valve Skid Foundation Calculation

A1850 Piping Plans, Sections, Details

195
185
185
27

27

Engineered Pipe Supports Requisition

-1

Nuevo Pemex Meter Station - EM#2


Engineering (EM#2)
Mechanical/Piping (EM#2)
A1880 Line Sizing Calculations

20

Review IFC Package


14-Mar-14, Civil/Structural (Interconnect)
Review IFC Package

17-Jun-13 17-Jul-13

14-Mar-14

April
13

Flow Control Valves Skid TBE

100% 17-Jun-13 A 18-Jul-13 A

0% 03-Dec-13

06

Flow Control Valves Skid Requisition

22

71

30

14-Mar-14, CPG Nuevo Pemex Interconnect


14-Mar-14, Engineering (Interconnect)
14-Mar-14, Mechanical/Piping (Interconnect)

A1840 Piping Plot Plan (IFCA)

A5470 Finalize IFC Drawings

23

Finalize IFC Drawings

-108
-108
4

A5460 Typical Details

March
09 16

Wiring Diagrams

17-Jun-13 15-Oct-13
17-Jun-13 15-Oct-13
17-Jun-13 29-Jul-13

07-Aug-13

02

Finalize IFC Drawings


14-Mar-14, Instrumentation (PL, MLV1, MLV2)

17-Jun-13 A 14-Mar-14
17-Jun-13 A 14-Mar-14
100% 17-Jun-13 A 23-Jul-13 A

15-Aug-13 A 18-Jul-13

23

Electrical Plans & Details

-35

0% 21-Oct-13 A 20-Dec-13

100% 18-Jul-13 A

26

February
02 09 16

Finalize IFC Drawings


14-Mar-14, Electrical (PL, MLV1, MLV2)

195
195
30

Design (Interconnect)
Mechanical/Piping (Interconnect)
A1830 PFD / P&IDs (IFCA)

29

January
05 12 19

Engineered Pipe Supports TBE


Review IFC Package
Engineered Pipe Supports Requisition
14-Mar-14, Electrical (EM#2)
Emergency Generator Requisition
Distribution Panel / MCC Requisition
Transformer Requisition
UPS Requisition
ATS Requisition
200 A Breakers Requisition
SKM Calculations
Load Study
Cable Sizing
Emergency Generator TBE
Review IFC Package
Distribution Panel / MCC TBE
UPS TBE
ATS TBE

Activity ID

Activity Name

Original
Duration

Activity % Start
Complete

Finish

BL1 Start

BL1 Finish

Variance BL1
Duration19
-44

A2710 200 A Breakers TBE

0% 02-Oct-13 A 09-Dec-13

09-Oct-13 15-Oct-13

A2720 Lighting Requisition

0% 26-Sep-13 A 12-Dec-13

03-Sep-13 09-Sep-13

A2950 Transformer TBE

100% 26-Sep-13 A 18-Oct-13 A

Instrumentation (EM#2)
A2350 Instrument Index

183
8

03-Jul-13 A
100% 03-Jul-13 A

14-Mar-14
18-Jul-13 A

03-Jul-13
03-Jul-13

20-Sep-13
15-Jul-13

A2360 I/O List

13

100% 16-Jul-13 A

18-Jul-13 A

16-Jul-13

01-Aug-13

11

A2460 Review IFC Package

71

14-Mar-14

09-Sep-13 20-Sep-13

-64

0% 03-Dec-13

26

02

June
09 16

23

30

July
07 14

21

28

August
04 11 18

-125
-3

01

PFD / P&IDs (IFCA)

-1

Piping Plot Plan (IFCA)

A1930 Piping Plans, Sections, Details

28

100% 19-Aug-13 A 12-Nov-13 A 15-Aug-13 24-Sep-13

A1940 Piping Isometric Drawings

10

0% 22-Oct-13 A 14-Mar-14

25-Sep-13 08-Oct-13

-94

A2570 Finalize IFC Drawings

71

0% 03-Dec-13

25-Sep-13 15-Oct-13

-59

A5070 Finalize Piping Plot Plan

20

-34

24-Jun-13 A 14-Mar-14
08-Jul-13
100% 24-Jun-13 A 12-Nov-13 A 08-Jul-13

15-Oct-13
16-Aug-13

-118
-72
-44

Steel Plans & Details

12-Nov-13 A 29-Jul-13

24-Sep-13

-36

Sedimentation and Erosion Control Details

A2070 Site Plan

51

100% 02-Jul-13 A

12-Nov-13 A 15-Jul-13

24-Sep-13

-45

Site Plan

A2080 Grading & Drainage Plan

35

100% 15-Jul-13 A

12-Nov-13 A 15-Jul-13

30-Aug-13

-52

Grading & Drainage Plan

A2090 Typical Details

49

100% 24-Jun-13 A 12-Nov-13 A 09-Jul-13

16-Sep-13

-53

Typical Details

A2100 Foundation Location Plan

36

100% 19-Aug-13 A 12-Nov-13 A 01-Aug-13 24-Sep-13

-24

Foundation Location Plan

A2110 Finalize IFC Drawings

71

-119
-18

12-Nov-13 A 21-Aug-13 24-Sep-13

-71

A2390 Area Classification Plan & Details

24

100% 03-Jul-13 A

A2400 One Line Diagrams

54

100% 25-Jun-13 A 29-Jul-13 A

A2420 Electrical Details

46

100% 03-Jul-13 A

A2430 Electrical Plans

31

A2490 Finalize IFC Drawings

71

Instrumentation (EM#2)
A2500 Wiring Diagrams

167
31

-59

15-Oct-13
24-Sep-13

Conduit & Cable Schedule


Area Classification Plan & Details

24-Sep-13

30

12-Nov-13 A 22-Jul-13

24-Sep-13

-49

Electrical Details

100% 19-Aug-13 A 12-Nov-13 A 22-Jul-13

24-Sep-13

-16

Electrical Plans

25-Sep-13 15-Oct-13

-59

25-Jul-13 A
100% 25-Jul-13 A

14-Mar-14

14-Mar-14
30-Jul-13
12-Nov-13 A 30-Jul-13

15-Oct-13
24-Sep-13

-111
-39

14-Mar-14

25-Sep-13 15-Oct-13

-59

14-Mar-14
14-Mar-14
14-Mar-14
23-Aug-13 A

17-Jun-13
01-Jul-13
01-Jul-13
01-Jul-13

15-Oct-13
11-Oct-13
07-Oct-13
07-Oct-13

-108
-112
-114
30

One Line Diagrams

Finalize IFC Drawings


14-Mar-14, Instrumentation (EM#2)
Wiring Diagrams

A2930 Finalize IFC Drawings

71

0% 03-Dec-13

Macuspana Meter Station - EM#3


Engineering (EM#3)
Mechanical/Piping (EM#3)
A2520 Line Sizing Calculations

195
138
120
69

17-Jun-13 A
27-Jun-13 A
01-Jul-13 A
100% 01-Jul-13 A

A2530 Cathodic Protection Design

69

88.41% 01-Jul-13 A

12-Dec-13

01-Jul-13

07-Oct-13

-50

A2540 Valve List

56

89.29% 15-Jul-13 A

10-Dec-13

15-Jul-13

01-Oct-13

-51

A3370 Pressure Regulating Skid Requisition

16

100% 22-Jul-13 A

30-Jul-13 A

15-Jul-13

05-Aug-13

10

A5030 Restriction Orifice Sizing Calculation

13

100% 16-Aug-13 A 19-Nov-13 A 01-Aug-13 21-Aug-13

-52

A5040 Line List

41

82.93% 16-Aug-13 A 11-Dec-13

15-Jul-13

01-Oct-13

-28

A5050 Equipment List

41

82.93% 29-Jul-13 A

15-Jul-13

01-Oct-13

-42
2

Pressure Regulating Skid TBE


Fuel Gas Supply Package Requisition

11-Dec-13

A5250 Pressure Regulating Skid TBE

100% 28-Aug-13 A 30-Aug-13 A 14-Aug-13 20-Aug-13

A5260 Fuel Gas Supply Package Requisition

100% 12-Aug-13 A 21-Aug-13 A 31-Jul-13

13-Aug-13

A5320 Fuel Gas Supply Package TBE

0% 01-Oct-13 A 11-Dec-13

01-Aug-13 14-Aug-13

-42

34

0% 07-Oct-13 A 14-Mar-14

21-Aug-13 21-Aug-13

-115

A5340 Large Pipe and Fittings TBE

0% 25-Nov-13 A 12-Dec-13

15-Jul-13

A5550 Small Pipe & Fittings Requisition

100% 20-Aug-13 A 21-Nov-13 A

A5580 Small Pipe & Fittings TBE

A5600 Large Pipe and Fittings Requisition

A5330 Review IFC Package

Civil/Structural (EM#3)
A2700 Engineered Pipe Supports Requisition
A2970 Engineered Pipe Supports TBE
A3000 Review IFC Package
A5170 Filters/Scrubber Skid Foundation Calculation
A5190 Pressure Regulating Skid Foundation Calculation

107
15
3

0% 06-Dec-13

06-Sep-13

0% 06-Jan-14

Line Sizing Calculations


Cathodic Protection Design
Valve List
Pressure Regulating Skid Requisition
Restriction Orifice Sizing Calculation
Line List
Equipment List

Fuel Gas Supply Package TBE


Review IFC Package

25

Large Pipe and Fittings TBE


Small Pipe & Fittings Requisition
Small Pipe & Fittings TBE

-6

100% 19-Aug-13 A 10-Dec-13 A


20-Aug-13 A 14-Mar-14
26.67% 20-Aug-13 A 17-Dec-13

Finalize IFC Drawings


14-Mar-14, Macuspana Meter Station - EM#3
14-Mar-14, Engineering (EM#3)
14-Mar-14, Mechanical/Piping (EM#3)

-68

13-Dec-13

Large Pipe and Fittings Requisition

-81
06-Aug-13 11-Oct-13
04-Sep-13 24-Sep-13

-100
-71

08-Jan-14

14-Mar-14, Civil/Structural (EM#3)


Engineered Pipe Supports Requisition
Engineered Pipe Supports TBE

-3

22

0% 07-Oct-13 A 14-Mar-14

19-Aug-13 10-Sep-13

-99

0% 20-Aug-13 A 20-Dec-13

06-Aug-13 12-Aug-13

-84

Review IFC Package


Filters/Scrubber Skid Foundation Calculation

0% 20-Aug-13 A 10-Dec-13

04-Sep-13 10-Sep-13

-76

Pressure Regulating Skid Foundation Calculation

A5200 Misc. Equipment Foundation Calculations

10

0% 20-Aug-13 A 20-Dec-13

18-Sep-13 01-Oct-13

-79

Misc. Equipment Foundation Calculations

A5210 Emergency Generator Foundation Calculation

24

41.67% 20-Aug-13 A 20-Dec-13

16-Sep-13 20-Sep-13

-84

Emergency Generator Foundation Calculation

A5220 Analyzer Building Foundation Calculation

0% 20-Aug-13 A 20-Dec-13

07-Oct-13 11-Oct-13

-84

Analyzer Building Foundation Calculation

A5230 Meter Skid Foundation Calculation

0% 20-Aug-13 A 20-Dec-13

17-Sep-13 23-Sep-13

-84

Meter Skid Foundation Calculation

Electrical (EM#3)
A2740 Emergency Generator Requisition

108
15

27-Jun-13 A 14-Mar-14
08-Jul-13
100% 26-Jul-13 A 22-Aug-13 A 26-Jul-13

30-Sep-13
15-Aug-13

-126
-4

A2750 Distribution Panel / MCC Requisition

15

100% 30-Jul-13 A

11-Sep-13 A 16-Aug-13 06-Sep-13

-17

A2770 Transformer Requisition

15

100% 01-Aug-13 A 22-Aug-13 A 20-Aug-13 10-Sep-13

A2780 UPS Requisition

15

100% 07-Aug-13 A 11-Sep-13 A 16-Aug-13 06-Sep-13

-10

A2790 ATS Requisition

15

100% 07-Aug-13 A 27-Aug-13 A 16-Aug-13 06-Sep-13

A2800 100 A Breakers Requisition

15

100% 07-Aug-13 A 11-Sep-13 A 16-Aug-13 06-Sep-13

-10

A2820 SKM Calculations

11

100% 11-Jul-13 A

25-Jul-13

-56

16-Jul-13

-10

A2830 Load Study

A2840 Cable Sizing

20

A2880 Review IFC Package

34

11-Oct-13 A 11-Jul-13

100% 27-Jun-13 A 22-Jul-13 A

08-Jul-13

100% 12-Aug-13 A 08-Oct-13 A 12-Aug-13 09-Sep-13


0% 07-Oct-13 A 14-Mar-14

15-Jul-13

06-Sep-13

-21
-76

May
04

Finalize IFC Drawings


14-Mar-14, Electrical (EM#2)

10-Jul-13

0% 03-Dec-13

27

14-Mar-14, Civil/Structural (EM#2)

100% 29-Jul-13 A

25-Jun-13 A 14-Mar-14
10-Jul-13
100% 05-Aug-13 A 12-Nov-13 A 10-Jul-13

20

Foundation Plans & Details

100% 19-Aug-13 A 12-Nov-13 A 29-Aug-13 24-Sep-13

178
46

April
13

Finalize IFC Drawings

36

Electrical (EM#2)
A2370 Conduit & Cable Schedule

06

Finalize Piping Plot Plan

18

25-Sep-13 15-Oct-13

30

Piping Isometric Drawings

A2060 Sedimentation and Erosion Control Details

14-Mar-14

23

Piping Plans, Sections, Details

A2050 Steel Plans & Details

0% 03-Dec-13

March
09 16

Review IFC Package


14-Mar-14, Design (EM#2)
14-Mar-14, Mechanical/Piping (EM#2)

17-Jun-13 17-Jul-13

02

I/O List

100% 17-Jun-13 A 18-Jul-13 A

14-Aug-13

23

14-Mar-14, Instrumentation (EM#2)

22

15-Aug-13 A 18-Jul-13

26

February
02 09 16

Instrument Index

A1910 Piping Plot Plan (IFCA)

180
30

24

December
January
08 15 22 29 05 12 19
200 A Breakers TBE
Lighting Requisition

-108
-108
-9

Civil/Structural (EM#2)
A2040 Foundation Plans & Details

27

November
03 10 17

Transformer TBE

17-Jun-13 15-Oct-13
17-Jun-13 15-Oct-13
17-Jun-13 10-Jul-13

100% 18-Jul-13 A

29

-16

17-Jun-13 A 14-Mar-14
17-Jun-13 A 14-Mar-14
100% 17-Jun-13 A 23-Jul-13 A

14-Mar-14

2014
October
06 13 20

-51

195
195
17

Design (EM#2)
Mechanical/Piping (EM#2)
A1900 PFD / P&IDs (IFCA)

25

2013
September
01 08 15 22

14-Mar-14, Electrical (EM#3)


Emergency Generator Requisition
Distribution Panel / MCC Requisition
Transformer Requisition
UPS Requisition
ATS Requisition
100 A Breakers Requisition
SKM Calculations
Load Study
Cable Sizing
Review IFC Package

Activity ID

Activity Name

Original
Duration

Activity % Start
Complete

Finish

BL1 Start

BL1 Finish

Variance BL1
Duration19
-43

A2980 Emergency Generator TBE

100% 26-Sep-13 A 26-Nov-13 A

A3030 Distribution Panel / MCC TBE

0% 02-Oct-13 A 09-Dec-13

26-Aug-13 30-Aug-13

-44

A3050 UPS TBE

0% 02-Oct-13 A 09-Dec-13

12-Aug-13 16-Aug-13

-44

A3070 ATS TBE

100% 26-Sep-13 A 31-Oct-13 A 19-Aug-13 23-Aug-13

-21

A3090 100 A Breakers TBE

0% 02-Oct-13 A 09-Dec-13

A3100 Transformer TBE

100% 26-Sep-13 A 18-Oct-13 A

A3110 Lighting Requisition

24-Sep-13 30-Sep-13

02

23

30

July
07 14

21

28

August
04 11 18

29-Jul-13

-24

03-Jul-13 A
100% 03-Jul-13 A

14-Mar-14
18-Jul-13 A

03-Jul-13
03-Jul-13

01-Aug-13
15-Jul-13

-161
-3

A2860 I/O List

13

100% 16-Jul-13 A

18-Jul-13 A

16-Jul-13

01-Aug-13

A2940 Review IFC Package

34

0% 07-Oct-13 A 14-Mar-14

29

11

21

100% 19-Aug-13 A 07-Oct-13 A 01-Aug-13 10-Sep-13

A2590 Piping Isometric Drawings

56

0% 27-Dec-13

14-Mar-14

11-Sep-13 24-Sep-13

-46

A5060 Finalize IFC Drawings

31

0% 07-Oct-13 A 14-Mar-14

11-Sep-13 15-Oct-13

-90

A5080 Finalize Piping Plot Plan

10

-7

-10

Finalize IFC Drawings


Finalize Piping Plot Plan
14-Mar-14, Civil/Structural (EM#3)

-112
-58

A2610 Steel Plans & Details

18

100% 19-Aug-13 A 24-Oct-13 A 15-Aug-13 10-Sep-13

-31

A2620 Sedimentation and Erosion Control Details

41

100% 15-Jul-13 A

10-Sep-13

-19

Sedimentation and Erosion Control Details

A2630 Site Plan

51

100% 28-Jun-13 A 07-Oct-13 A 28-Jun-13 10-Sep-13

-20

Site Plan

A2640 Grading & Drainage Plan

41

100% 10-Jul-13 A

07-Oct-13 A 15-Jul-13

10-Sep-13

-22

Grading & Drainage Plan

A2650 Typical Details

49

100% 24-Jun-13 A 24-Oct-13 A 02-Jul-13

10-Sep-13

-39

A2660 Foundation Location Plan

26

100% 19-Aug-13 A 07-Oct-13 A 18-Jul-13

10-Sep-13

11-Sep-13 15-Oct-13

-90

25-Jun-13 A 14-Mar-14
25-Jun-13 15-Oct-13
100% 19-Aug-13 A 07-Oct-13 A 10-Jul-13 10-Sep-13

-108
9

A2890 Area Classification Plan & Details

24

100% 03-Jul-13 A

A2900 One Line Diagrams

54

100% 25-Jun-13 A 29-Jul-13 A

A2910 Electrical Details

46

100% 03-Jul-13 A

07-Oct-13 A 08-Jul-13

10-Sep-13

-22

A2920 Electrical Plans

26

100% 19-Aug-13 A 07-Oct-13 A 22-Jul-13

10-Sep-13

A5280 Finalize IFC Drawings

31

11-Sep-13 15-Oct-13

-90

14-Mar-14
12-Aug-13 15-Oct-13
07-Oct-13 A 12-Aug-13 10-Sep-13

-125
-36

A5290 Finalize IFC Drawings

Construction / Commissioning
Commissioning
A5610

Pre-Commissioning / Commissioning Plan

80
21
31

18-Jul-13 A
100% 18-Jul-13 A

0% 07-Oct-13 A 14-Mar-14

11-Sep-13 15-Oct-13

May
04

Piping Isometric Drawings

24-Jun-13 A 14-Mar-14
28-Jun-13 15-Oct-13
100% 24-Jun-13 A 24-Oct-13 A 30-Jul-13 10-Sep-13

Instrumentation (EM#3)
A2990 Wiring Diagrams

27

Piping Plans, Sections, Details

109
30

0% 07-Oct-13 A 14-Mar-14

20

14-Mar-14, Design (EM#3)


14-Mar-14, Mechanical/Piping (EM#3)

A2580 Piping Plans, Sections, Details

25-Jun-13 10-Sep-13

April
13

Review IFC Package

PFD / P&IDs (IFCA)

07-Oct-13 A 07-Aug-13 10-Sep-13

06

I/O List

Piping Plot Plan (IFCA)

0% 07-Oct-13 A 14-Mar-14

30

-115

-1

22

23

14-Mar-14, Instrumentation (EM#3)

17-Jun-13 17-Jul-13

112
26

March
09 16

Instrument Index

100% 17-Jun-13 A 18-Jul-13 A

A2670 Finalize IFC Drawings

02

Lighting Requisition

22

Electrical (EM#3)
A2870 Conduit & Cable Schedule

23

100 A Breakers TBE

A2560 Piping Plot Plan (IFCA)

07-Oct-13 A 15-Jul-13

26

February
02 09 16

Transformer TBE

-108
-108
-9

Civil/Structural (EM#3)
A2600 Foundation Plans & Details

January
05 12 19

UPS TBE

17-Jun-13 15-Oct-13
17-Jun-13 15-Oct-13
17-Jun-13 10-Jul-13

31-Jul-13

December
24 01 08 15 22 29
Emergency Generator TBE

ATS TBE

17-Jun-13 A 14-Mar-14
17-Jun-13 A 14-Mar-14
100% 17-Jun-13 A 23-Jul-13 A

15-Aug-13 A 18-Jul-13

27

November
03 10 17

Distribution Panel / MCC TBE

195
195
17

100% 18-Jul-13 A

2014
October
06 13 20

-17

100% 26-Sep-13 A 12-Nov-13 A 16-Jul-13

Design (EM#3)
Mechanical/Piping (EM#3)
A2550 PFD / P&IDs (IFCA)

25

2013
September
01 08 15 22

-44

111
8

Instrumentation (EM#3)
A2850 Instrument Index

26

June
09 16

Foundation Plans & Details


Steel Plans & Details

Typical Details
Foundation Location Plan
Finalize IFC Drawings
14-Mar-14, Electrical (EM#3)
Conduit & Cable Schedule

-44
30

-90

Area Classification Plan & Details


One Line Diagrams
Electrical Details
Electrical Plans
Finalize IFC Drawings
14-Mar-14, Instrumentation (EM#3)
Wiring Diagrams
Finalize IFC Drawings

12

15-Apr-14

30-Apr-14

-12

30-Apr-14, Construction / Comm

12

15-Apr-14

30-Apr-14

-12

30-Apr-14, Commissioning

30-Apr-14

-12

Pre-Commissioning / Commiss

12

0% 15-Apr-14*