You are on page 1of 221

INDEX

CONTENTS

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25

Introductory Notes.
Excavation
Anti-termite treatment
Earthwork
Earthwork support
Concrete
Timber formwork
Steel reinforcement
Brickwork
Hollow block masonry
Random rubble masonry
Pressed tiling
Wall tiling & Terrazzo tiles
Roofing
Roof plumbing
Ceiling
Doors & windows
Ironmongery
Plastering
Painting & Decorating
Plumbing (PVC)
External drainage (EW pipes)
Plumbimg (C.I. pipes)
Manholes & Gulleys
Sanitary fittings
Gutters & Downpipes.

Page No.

MATERIAL AND LABOUR ANALYSIS FOR BUILDING WORKS.


Analysis for Basic Rates
The material and labour component required for the various items of work including the minimal
plant required for same is detailed in the analysis of the Basic Rates which have been included
in the following pages.
Basic Rate.
The basic rate is analysed under the following headings.
(a)

Materials.
The quantities of material required for the items are computed from known
data and experience. Their total value is calculated on the basis of current
costs of purchase at sources of supply. Unless otherwise stated wastage
is allowed in the norms.

(b)

Transport.
This component provides for the cost of transport of material from sources
of supply to basis the sites of work. This component is usually added to
the material cost.

(c)

Labour.
The labour wages are as approved by the Government from time to time
and on the basis of an 8 hour working day.

(d)

Plant.
This component provides for the minimum plant required for the items of work.
The cost of tools and implements is provided for in the overheads allowances.

(e)

Basic Cost.
The Basic Cost is the sum of the costs of items (a), (b), (c) and (d) above.

Overheads and Profit factor.


Overhead costs include such costs that cannot be considered as direct productive work
on the job. These may be generally grouped as follows.
(a)

Job Overheads. - that vary with and are caused directly by the individual jobs.

(b)

General Overheads - which include costs of maintaining an office, workshop


and yard in which to do business whether or not there is a job under way.
Such expences are continuous and may be shared by the job turnover.

The common items that make up the overhead costs are listed below. The cost of the
overhead items involved on a job is assessed as a percentage of the Basic cost of the
job. In the case of the Construction Agencies executing building construction works
the overhead componenet may be listed as below.

Job Overheads (Site Overheads)

% of Basic Cost.

Supervision of work. (Wages of work Supervisors)

1.00

Supervision of Labour ( Wages of Gangers)

4.00

Temporary Works.
(a)

Access Road & Maintenance

0.20

(b)

Site buildings for accomodation of part labour.

0.70

(c)

Central Stores Building

0.60

(d)

Fencing and protection

0.30

(e)

Provision of water, light etc.

0.30

(f)

Cleaning and tidying up

0.20

(g)

Collection of building materials including cement and steel.

0.40

Watchers for field stores and security of site.

0.80

Tools and implements for miscellaneous work

0.90

(a)

Setting out and measurements

0.50

(b)

Providing samples for testing

0.20

Transportation of supervisory staff

1.00

Job office, furniture, stationary, supplies, water, light etc.

0.90

Wages of job office staff

1.20

10

Transportation of job office staff.

0.40

11

12

(a)

Bonds for bid performance and Fidelity Guarantee.

0.30

(b)

Insurance of works and workmen's compensation

0.50

Interest in capital investment

1.60
16.00

General Overheads.
13

Head office rent, lights, telephone, stationary supplies, furniture etc. for same

0.60

14

Salaries of Head Office Manager, Engineers, Technical Assistants,


Draughtsmen, Clerks, Stenos, Typists, Minor Staff and Drivers.

1.20

15

Transportation and subsistance of Head office staff.

1.00

16

Insurance, Interest and Taxes on business.

0.40

17

Legal expenses and consultancy fee

0.20

18

Workshop & Yard rents, sheds, garages & supplies.

2.20

19

Salaries of workshop & Yard Storekeepers, Drivers, Foremen,


Mechanics and Workmen.

Profit
Ten percent (10%) of the Basic costs is allowed as profit of the Contractor.
Overheads and Profit Factor
Combining the factors for overheads and the profit factors we get 35% of the Basic
Rate as the Overhead and Profit factor which is also called the 'Mark-up' on the Basic
Rate. i.e. the Basic Rate is multiplied by the factor 1.35 to obtain the working rate.
This Basic Rate Anaylsis does not include for the use of heavy plant and equipment.
This analysis provides for a labour intensive method of work with a minimal use of
machinary. The machinery allowed In this analysis is the concrete mixer, the vibrator
and a hoist in the case of a multi-storeyed building for the lift of materials to the
various floors.
This analysis is applicable for a building having a maximum of four storeys.
i.e. ground and three upper floors.
If a building has more than four floors or when the Contrat period is compressed to a
few months then it will be necessary to allow of the use of heavy machinery such as
tower cranes, dumpers, loaders, batching plant for the mixing of concrete, bins for
storage of materials etc. and also for the employment of contract managers and
additional staff.
The cost of such items of work will not be accommodated within the 35% 'Mark-up'
and will have to be provided for in separate items such as preliminaries to the Contract.

0.40
6.00

Conversion - Imperial to Metric


-----------------------------------------------------------------------------------------------------------------------------To Convert
To Rate
Rate per
per
------------------------------------------------------------------------------------------------------------------------------

Multiply
by

Cube

M3

0.353

Square

M2

0.1075

Sq.ft

M2

10.7584

L.ft

3.28

Cwt
Kg.
------------------------------------------------------------------------------------------------------------------------------

0.02

Allowances to be made in the rates for lift in respect of work on upper floorsIn the analysis of the various items of work in the fllowing pages the rates refer to work
on the ground floor.
To these rates the percentages ( of the ground floor rates) indicate in the table below
should be added to obtain the rates applicable to the 1st, 2nd, 3rd floors. This B.S.R.
is limited to work on the ground and 3 upper floors only.
-----------------------------------------------------------------------------------------------------------------------------Ground to Ground to Ground to
1st floor
2nd floor 3rd floor
-----------------------------------------------------------------------------------------------------------------------------Concrete
Cube
3%
5%
9" Brickwork
Sqr
5%
7%
9" Brickwork
Cube
5%
7%
4 1/2" Brickwork
Sqr
5%
7%
Steel Reinforcements
Cwt
2.50%
5%
Plastering
Sqr
5%
10%
Painting
Sqr
3%
6%
Floor tiling
Sqr
2%
4%
Wall tiling
Sqr
2%
4%
Roof calicut tiles
Sqr
3%
6%
Roof Asbestos
Sqr
3%
5%
Ceiling work
Sqr
3%
5%
------------------------------------------------------------------------------------------------------------------------------

7%
9%
10%
10%
7.50%
15%
9%
6%
6%
9%
7%
7%

EARTH WORK AND LANDSCAPING


Note:
1

Soils met within excavation have been classified as follows.


1)
2)
3)
4)
5)
6)

Soft/Loose soil
Ordinary soil
Hard/Dense soil
Mud/Wet clay
Soft disintegrated rock
( i.e. rock not requiring blasting)
Hard rock - a) Where blasting is approved.
b) Where blasting is prohibited.

The analysis has been prepared for each of the above categories as shown in
items nos 3 - 9.

However, in the preparation of estimates for purposes of calling for Tenders, only two
B.O.Q. items would be included in the B.O.Q. as against the B.S.R. item Nos. 3, 4,
5, 6, 7, 8 & 9. The description of these two B.O.Q. itmes would be as follows:
(a) Ecavation in any material met with except rock requiring blasting.
(b) Excavation in rock requiring blasting.

This classification has been adopted (where tenders are called) to avoid any dispute
that may arise as to the exact nature of the soil that will be met with when the actual
excavation is carried out. The tenderer is expected to examine the site and to form his
own opinion of the nature of the soil that is met with and rate his tender accordingly.

The classification of the soils in Note 1 above and the analysis provided for the different
type of soil will help the estimator in arriving at the actual cost of excavation, for which
he will have to allow in his estimate.

Under Note 1 (6) b Hard Rock, an analysis is provided for removing Hard Rock met
within foundation excavations where blasting is prohibited or cannot be done, like in
built ut areas where blasting can cause damage to adjoining buildings.

In the excavation itmes Nos 3 to 9, the labour norm allowed in the items is for an
excavation up to a maximum depth of 5'-0" an additional unskilled labourer should
be added for every additional 5'-0" or part thereof for each cube of excavation beyond
the original 5'-0" depth.

EXCAVATION
--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------1

Removing top soil to a depth not exceeding 6" & depositing as directed within site.
Per Square
Consider an area of 10.00 sqrs. i.e 5.00 cubes of excavation
10

days

Cost

per

U/Sk labourer
10

600.00

squares

Cost per Square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------2

Excavation over site to reduce level, in any material except rock requiring blasting
including depositing and levelling as directed up to a distance not exceeding 30'-0"
Per cube
1 5/8

days

U/Sk labourer

600.00

Cost per cube


35%

Overheads & Profit


Rate per cube

--------------------------------------------------------------------------------------------------------------------------------------------------------------3

Excavation in trenches for walls / column pits in soft / loose soil up to 5'-0" deep and
depositing excavated material to a distance not exceeding 30'-0" (Earth work support
to be paid separately where necessary).
Per cube
1

day

U / Sk labourer

Cost per cube


35%

Overheads & Profit

700.00

Rate per cube


--------------------------------------------------------------------------------------------------------------------------------------------------------------Items
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------4

Excavation in trenches for walls / column pits in ordinary soil up to 5'-0" deep
and depositing excavated material to a distance not exceeding 30'-0".
Per cube
2 1/4

days

U / Sk labourer

600.00

Cost per cube


35%

Overheads & Profit


Rate per cube

---------------------------------------------------------------------------------------------------------------------------------------------------------------

Excavation in trenches for walls / column pits in Hard / dense soil up to a depth
of 5'-0" and depositing excavated material up to a distance not exceeding 30'-0"
Per cube
3 1/2

days

U/Sk labourer

600.00

Cost per cube


35%

Overheads & Profit


Rate per cube

--------------------------------------------------------------------------------------------------------------------------------------------------------------6

Excavation in trenches for walls / column pits in Mud / wet soil up to a depth
of 5'-0" and depositing excavated material to a distance not exceeding 30'-0".
(Earthwork support & dewatering paid for separately)
Per cube
3

days

U / Sk labourer

Cost per cube


35%

Overheads & Profit

790.00

Rate per cube


--------------------------------------------------------------------------------------------------------------------------------------------------------------Items
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------7

Excavation in trenches for walls / column pits in soft disintegrated rock ( not requiring blasting)
to a depth of 5'-0" and depositing excavated material to a distance not exceeding 30'-0".
Per cube
2 1/2

days

U / Sk labourer

600.00

Cost per cube


35%

Overheads & Profit


Rate per cube

--------------------------------------------------------------------------------------------------------------------------------------------------------------8

Excavation in trenches for wall / column pits in Hard rock requiring blasting up to a
depth of 5'-0' and depositing excavated material to a distance not exceeding 30'-0".
Per cube
Materials
0.75
10
1

lbs
L.ft
lb

blasting powder
fuse
jumper steel

Fuel & forge Add


20%

of material cost

Labour
1
2

Sk labourer
U / Sk labourer

day
days

50.00
25.00
80.00

800.00
600.00

Cost per cube


35%

Overheads & Profit


Rate per cube

--------------------------------------------------------------------------------------------------------------------------------------------------------------9

Benching rock in foundation in 3" - 6" steps.(Blasting prohibited)


Per 10 square feet
Drilling, chipping & wedging1 1/2
days
Sk labourer

800.00

Steel, fuel & forge Add


25%

of labour cost

Collecting & Disposing 1 1/2


days
U /Sk labourer
Per
35%

10

600.00

sq.ft

Overheads & Profit


Rate per sq. ft.

--------------------------------------------------------------------------------------------------------------------------------------------------------------Items
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

Amount

-----------------------------------------

6,000.00
6,000.00
600.00
210.00
810.00

-----------------------------------------

975.00
975.00
341.25
1,316.25

-----------------------------------------

700.00
700.00
245.00
945.00

87.08

Amount

-----------------------------------------

1,350.00
1,350.00
472.50
1,822.50

643.34

-----------------------------------------

2,100.00
2,100.00
735.00
2,835.00

-----------------------------------------

2,370.00
2,370.00
829.50
3,199.50

1,000.76

Amount

-----------------------------------------

quiring blasting)
ng 30'-0".

1,500.00
1,500.00
525.00
2,025.00

-----------------------------------------

37.50
250.00
80.00

73.50

800.00
1,200.00
2,441.00
854.35
3,295.35

-----------------------------------------

1,200.00

300.00

900.00
2,400.00
840.00
3,240.00

Amount

-----------------------------------------

ANTI - TERMITE TREATMENT


10

Anti - termite treatment on excavated foundation and compacted soil under floors.
Per square
Materials
16
lbs
D.D.T. powder
( 8% in 20 glas of water)
20
gallons water
Labour
1/2

day

U / Sk labourer

60.00
2.25

600.00

Cost per cube


35%

Overheads & Profit


Rate per cube

NOTE:

Alternative Mixes

a)
b)
c)

Copper Naphthenate (5% in 4 to 8 gals of fuel oil)


Sodium Arsenate (10% in 12 to 20 gals of water.)
Dieldrine (0.3% in 19 gals of Water).

--------------------------------------------------------------------------------------------------------------------------------------------------------------Items
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

960.00
45.00

300.00
1,305.00
456.75
1,761.75

Amount

-----------------------------------------

EARTHWORK - BACKFILLING & COMPACTING.


11

Backfilling to trenches with selected earth available at site


Per cube
1

day

U / Sk labourer

600.00

Cost per cube


35%

Overheads & Profit


Rate per cube

--------------------------------------------------------------------------------------------------------------------------------------------------------------12

Back filling to trenches with imported material.


Per cube
1

cube

earth delivered at site

Add

15%

for compaction

Filling & Compaction


1 1/4
days
U / Sk labourer

640.00

600.00

Cost per cube


35%

Overheads & Profit


Rate per cube

--------------------------------------------------------------------------------------------------------------------------------------------------------------13

Filling under floors including levelling, watering & compacting in 3" layers
with available and selected earth at site.
Per cube
2

days

U / Sk labourer

600.00

Cost per cube


35%

Overheads & Profit


Rate per cube

--------------------------------------------------------------------------------------------------------------------------------------------------------------Items
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

14

Filling under floors including levelling, watering & compacting in 3" layers
with imported selected earth.
Per cube
1
Add
2

cube
15%
days

earth delivered at site.


for compaction
U / Sk labourer

640.00
600.00

Cost per cube


35%

Overheads & Profit


Rate per cube

--------------------------------------------------------------------------------------------------------------------------------------------------------------15

Cutting turf sods, loading to hand carts and transporting upto 30 yards,
laying and watering for 30 days. (Royalty for turf, pegging and transport
beyond 30 yards paid separately).
Per cube
Cutting turf sods, loading and transporting to site and unloading2 1/2
days
U / Sk labourer

600.00

Laying turf sods at site


1/2
day
U / Sk labourer

600.00

Watering for 30 days1 1/2


days
U / Sk labourer
60
gallons water

600.00
2.25

Cost per cube


35%

Overheads & Profit


Rate per cube

NOTE:
Rate does not include for :
a)
Royalty for turf
b)
Transport of turf
c)
Pegs on sloping site
d)
Water.
--------------------------------------------------------------------------------------------------------------------------------------------------------------Items
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

600.00
600.00
210.00
810.00

-----------------------------------------

sand filling
640.00

6300

96.00

945

750.00

750.00

1,486.00

7,995.00

520.10

2,798.25

2,006.10

708.15

10,793.25

-----------------------------------------

1,200.00
1,200.00
420.00
1,620.00

Amount

-----------------------------------------

571.86

640.00
96.00
1,200.00
1,936.00
677.60
2,613.60

-----------------------------------------

1,500.00

300.00

900.00
135.00
2,835.00
992.25
3,827.25

Amount

-----------------------------------------

922.60

EARTHWORK SUPPORT
16

Earthwork support ( open planking ) in trenches up to a depth of 5'-0".


Consider trench 15'-0" long 3'-0" wide and 5'-0" deep open planking to both faces.
Total area

2/15'-0" x 5'-0" =

150 sq.ft

Per 150 sq.ft


Materials
17.5
Add

cu. ft
5%

class II timber (4 uses)


on above for wedges.

800.00

Labour
1
3

day
days

carpenter
U / Sk labourer

800.00
600.00

Total for 150 sq. ft


Cost per sqr
35%

Overheads & Profit


Rate per Square

--------------------------------------------------------------------------------------------------------------------------------------------------------------17

Earthwork support (close planking) in trenches up to 5'-0" depth.


Consyder trenches 15' 0" ie long 3' 0' wide and 5' 0" height of planking to both faces.
Total area of planking 2/15' 0" x 5' 0" ie 150 sq.ft
Per 150 sq.ft
Materials
30
Add

cu.ft
5%

class II timber (4 uses)


on above for wedges.

800.00

Labour
2
6

days
days

carpenter
U / Sk labourer

800.00
600.00

Total for 150 sq.ft


Cost per sqr
35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Items
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------18

Earthwork support (close planking) in deep excavation in trenches up to 15'-0" depth.


Consider trench of lenth of 15'-0" width 5'-6" at top & 3'-6" at bottom.
Then area supported is 2/15' x 15' i.e 450 sq.ft
Per 450 sq.ft
Materials
100
Add

cu.ft
5%

class II timber (4 uses)


on above for wedges.

800.00

Labour
8
20

days
days

carpenter
U / Sk labourer

800.00
600.00

Total for 450 sq.ft


Cost per sqr
35%

Overheads & Profit


Rate per square

3,500.00
175.00

800.00
1,800.00
6,275.00
4,183.33
1,464.17
5,647.50

-----------------------------------------

6,000.00
300.00

1,600.00
3,600.00
11,500.00
7,666.67
2,683.33
10,350.00

Amount

-----------------------------------------

20,000.00
1,000.00

6,400.00
12,000.00
39,400.00
8,755.56
3,064.44
11,820.00
1,272.34

Wages
Mason
Carpenter
Blacksmith
Tinker
Glazier
Painter
Plumber
Special Mason
Skilled Labourer
Semi skilled labour
Unskilled Labourer

per
per
per
per
per
per
per
per
per
per
per

day
day
day
day
day
day
day
day
day
day
day

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

800.00
800.00
800.00
800.00
800.00
800.00
800.00
950.00
800.00
700.00
600.00

Blasting powder
Fuse
Jumper Steel
D.D.T. powder
Earth

per
per
per
per
per

lb.
l.ft.
lb
lb
cube

Rs.
Rs.
Rs.
Rs.
Rs.

50.00
25.00
80.00
60.00
640.00

Cement (50 Kg.)


Sand
Bricks
Wirecut bricks
16"x8"x8" blocks
16"x8"x4" blocks
1 1/2" Metal
1" Metal
3/4" Metal
Rubble
Slaked lime
Jute Hessian

per
per
per
per
per
per
per
per
per
per
per
per

bag
cube
no.
no.
no.
no.
cube
cube
cube
Cube
lb
sq.ft.

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

790.00
4,500.00
6.50
12.00
65.00
38.00
6,000.00
7,000.00
7,500.00
3,500.00
35.00
10.00

Wire nails.
16 mm 18" long bolts
Soldering lead
Clout headed nails
1 1/2" Brass nails
Roofing Screws
5/8" M.S. dowels
M S/Tor steel
Binding wire

per
per
per
per
per
per
per
per
per

lb.
no.
lb
lb
kg.
no.
no.
cwt.
lb.

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

82.00
30.00
30.00
60.00
120.00
15.00
12.00
6,600.00
85.00

8"x8" pressed tiles

per

no.

Rs.

6.00

Material Prices

Fire wood
Coloured pigment
Cotton waste
6"x6" glazed tiles
White cement
12"x12" terrazzo tiles

per
per
per
per
per
per

lb
lb.
lb.
no.
lb
no.

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

2.00
128.00
20.00
15.00
30.00
35.00

G.I. Sheet 8'x4'


Fibre/plastic plugs
Plugs & 4" B. screws
Calicut tiles
Half round tiles
Calicut ridge tiles

per
per
per
per
per
per

no.
no.
no.
no.
no.
no.

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

950.00
2.50
10.00
10.00
5.00
25.00

Cor. Asbestos Sheet


Asbestos ridges
Flat asbestos sheets

per
per
per

sq.ft.
pair
sq.ft.

Rs.
Rs.
Rs.

26.00
250.00
14.00

Spur stones

per

no.

Rs.

30.00

Wire brush
2" Brush
3" Brush
6" Brush
6" Coir Brush
Floor Brush

per
per
per
per
per
per

no.
no.
no.
no.
no.
no.

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

100.00
120.00
140.00
250.00
60.00
80.00

Glass panes
Brass panel pins

per
per

sq.ft.
doz.

Rs.
Rs.

30.00
0.60

4" dia. E.W. pipes


4" dia. C.I. pipes
Yarn
Wood plug 6"x6"x2"
3" Iron screws
Lead
4" S.W. gulley
4" G.I. Grating
RCC cover slab 2'x2'

per
per
per
per
per
per
per
per
per

l.ft.
l.ft.
lb.
no.
no.
lb.
no.
no.
no.

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

55.00
115.00
9.50
10.00
1.50
35.00
550.00
25.00
500.00

Overhead & profit

35%

Plant Hire Rates


Concrete mixer
Vibrater

per
per

day
day

Rs.
Rs.

3,000.00
1,200.00

L.ft.
L.ft.
L.ft.
L.ft.
L.ft.
L.ft.
L.ft.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
grm
no.
no.

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

7.45
12.60
18.70
31.25
46.40
77.15
180.80
5.66
8.75
12.10
22.00
42.40
64.10
115.00
215.00
7.35
10.40
20.00
26.70
49.75
75.75
165.00
366.70
7.50
10.00
14.50
26.70
41.70
79.00
175.00
495.00
3.50
8.00
12.35
17.40
26.35
46.35
75.00
115.00
0.65
2.00
5.00

PVC pipes & fittings (1000 Type)


1/2" dia. Pipe
3/4" dia. Pipes
1" dia. Pipes
1 1/4" dia. Pipes
1 1/2" dia. Pipes
2" dia. Pipes
3" dia. Pipes
1/2" dia. Elbows
3/4" dia. Elbows
1" dia. Elbows
1 1/4" dia. Elbows
1 1/2" dia. Elbows
2" dia. Elbows
2 1/2" dia. Elbows
3" dia. Elbows
1/2" dia.Tees
3/4" dia. Tees
1" dia. Tees
1 1/4" dia. Tees
1 1/2" dia. Tees
2" dia. Tees
2 1/2" dia. Tees
3" dia. Tees
1/2" dia. Bends
3/4" dia. Bends
1" dia. Bends
1 1/4" dia. Bends
1 1/2" dia. Bends
2" dia. Bends
2 1/2" dia. Bends
3" dia. Bends
1/2" dia. Socket
3/4" dia. Socket
1" dia. Socket
1 1/4" dia. Socket
1 1/2" dia. Socket
2" dia. Socket
2 1/2" dia. Socket
3" dia. Socket
Solvent cement
Clips & nails
Clips & nails over 2"

per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per

Ironmongery
Butt hinges 5"x2 1/2"
Tee hinges 6"x12"
Rim lock
Mortice lock (Union)
Casement stay
Door closer
Tower bolt
Barrel bolt 4"
Casement fastener
Spring loaded catch
Draw ring
1/2" Brass screws
3/4" Brass screws
1 1/2" Brass screws
4" Brass screws.
1 1/4" Brass screws
1" Brass screws

per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per

pair
pair
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

180.00
350.00
250.00
2,215.00
48.00
850.00
73.00
48.00
34.00
30.00
15.00
1.00
1.50
3.60
8.50
3.00
2.50

per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per

litre
gallon
gallon
lb.
litre
litre
litre
litre
litre
no
bushel
lb.
lb.
lb.
litre
litre
yard
gallon
gallon
gallon

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

60.00
85.00
80.00
80.00
90.00
72.00
321.00
259.00
302.00
7.00
125.00
2.00
35.00
50.00
300.00
327.00
90.00
100.00
2.25
338.00

Paint etc.
mould oil
Bitumen
Tarnap
Wax polish
Anti-corrosive primer
Turpentine
Enamel
Emulsion
Wood primer
Sand paper
boiled lime
salt
yellow ochre
blue
Wall primer
Varnish
flannel cloth
Acid
Water
Wood preservative

Class 1 Timber
4"x3" frames
1 1/2" Planks
1" thick planks
Timber
4"x2" joists
2"x1" timber strips
3"x1 1/2" Planks
1/2" x 1/2" beading
Class 11 timber
1" thick planks
2" x 2" yokes.
2" x 1" battens.
4" x 2" props
Wedges

cu.ft
sq.ft
sq.ft
cu.ft.
l.ft.
l.ft.
sq.ft.
l.ft.
cu.ft.
sq.ft.
l.ft.
l.ft.
l.ft.
no.

3/4" thick Planks


2"x2" cove moulding
1 1/2" beading

per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per
per

1,200.00
200.00
150.00
1,500.00
60.00
8.00
85.00
0.75
800.00
50.00
15.00
3.00
40.00
5.00

sq.ft.
l.ft.
l.ft.

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

2'-9"x 6'-9" ply. door

per

no.

Rs.

1,200.00

per
per
per
per
per
per
per
per
per
per
per
per
per
per
per

no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.
no.

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

3,950.00
4,500.00
950.00
1,050.00
3,500.00
4,750.00
1,200.00
690.00
50.00
2.00
125.00
250.00
3.50
150.00
3.00

26.00
20.00
4.00

Sanitary Fittings
Wash basin
Low level suite
Squatting pan
C.I. Cistern complete
Sink
Bidet
Urinal Bowls
1/2" dia. tap
Plug & Chain
Wooden plugs 2" thk.
L iron brackets
1/2" dia stop cock
Clip
Spreader
Rawl plugs 2" PVC

Rain water goods.

6" dia. PVC gutter


Gutter Joiner
Gutter bracket
Gutter head
Mitre bend
End cap
3 1/2" dia. Down pipe
3 1/2" D.P. joiner
PVC Straps
60/80 Elbow
60/80 Shoe

per
per
per
per
per
per
per
per
per
per
per

length
no.
no.
no.
no.
no.
length
no.
no.
no.
no.

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Machines (Rates include Fuel and Wages of operators)

480.00
49.00
8.50
200.00
141.70
29.50
360.00
35.00
8.00
50.00
45.00

CONCRETE
Preamble
Assumptions;
1
Mixing concerte using a concerte mixer 14/10 cu.ft capacity and manual loading are
the basis on which the norms are worked.
2

A gang of one skilled and six unskilled labourers produce 3.00 cubes of concrete per
day using a 14/10 cu.ft capacity concrete mixer. This is as per accepted practice.

The production of concrete is at the mixer site; transporting mixed concrete and
placing same in position is paid for separately.

In concrete itmes 26 to 39 both inclusive , placing of concrete in columns, beams


and floor slabs onthe ground floor, the labour component allowed is for the placing
of concrete between the ground floor and the top of the 1st floor slab which is called
the ground floor area. Similarly the area between the top of the 1st floor slab and the
top of the 2nd floor slab is called the 1st floor area etc.

NOTE:
a)
b)
c)

Water available at site


If water is not available at site allowance must be made for transport of Water .
Sand - includes 15% for bulking.

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------19
Mixing concrete 1:3:6 (1 1/2")
Grade 10
Per cube
Materials
13
0.53
0.92
1/3
110
Labour
1/3
2

cwt
cubes
cubes
day
gallons

day
days

(50 Kg bags) cement


sand
1 1/2" metal
hire of mixer
water

skilled labourer
U / Sk labourer

790.00
4,500.00
6,000.00
3,000.00
2.25

800.00
600.00

Cost per cube


--------------------------------------------------------------------------------------------------------------------------------------------------------------20

Mixing concrete 1 : 2 1/2 : 5 (1")


Per cube

Materials
14
0.6
0.9
1/3
100
Labour
1/3
2

cwt
cubes
cubes
day
gallons

day
days

cement (50 Kg. Bags)


sand
1" metal
hire of mixer
Water

790.00
4,500.00
7,000.00
3,000.00
2.25

skilled labourer
U / Sk labourer

800.00
600.00

Cost per cube


--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------21

Mixing concrete 1 : 2 : 4 ( 3/4" )

Gradeb 15

Per cube
Materials
18
0.5
0.88
1/3
120
Labour
1/3
2

cwt
cubes
cubes
day
gallons

day
days

cement ( 50 Kg. Bags )


sand
3/4" metal
hire of mixer
Water

skilled labourer
U / Sk labourer

790.00
4,500.00
7,500.00
3,000.00
2.25

800.00
600.00

Cost per cube


--------------------------------------------------------------------------------------------------------------------------------------------------------------22

Mixing concrete 1: 1 1/2 : 3 ( 3/4")

Grade 25

Per cube
Materials
23
0.42
0.82
1/3
150
Labour
1/3
2

cwt
cubes
cubes
day
gallons

day
days

cement ( 50 bags )
sand
3/4" metal
hire of mixer
water

skilled labourer
U / Sk labourer

790.00
4,500.00
7,500.00
3,000.00
2.25

800.00
600.00

Cost per cube


--------------------------------------------------------------------------------------------------------------------------------------------------------------23

Mixing concrete 1 : 1 : 2 ( 3/4" )

Grade 30

Per cube
Materials
31
0.44
0.96
1/3
200
Labour
1/3
2

cwt
cubes
cubes
day
gallons

day
days

cement ( 50 Kg. Bags )


sand
3/4" metal
hire of mixer
Water

skilled labourer
U / Sk labourer

790.00
4,500.00
7,500.00
3,000.00
2.25

800.00
600.00

Cost per cube


--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------24

2" thick cement concrete 1:3:6(1 1/2") screed in foundation at depths not exceeding 5'-0".
Per square
Materials
1/6
Add
Labour
1/8
1/2

cube
10%

day
day

concrete
for wastage

Sk labourer
U / Sk labourer

20,889.17

800.00
600.00

Cost per sqr


35%

Overheads & Profit


Rate per square

NOTE:

For laying concrete more than 5'-0", add 1/6 day unskilled labourer for each
additional 5'-0" or part thereof per square.

--------------------------------------------------------------------------------------------------------------------------------------------------------------25

3" thick cement concrete 1:3:6(1 1/2") screed in foundation at depths not exceeding 5'-0".
Per square

Materials
1/4
Add

cube
10%

Labour
1/8
3/4

day
day

concrete
for wastage

Sk labourer
U / Sk labourer

20,889.17

800.00
600.00

Cost per sqr


35%

Overheads & Profit


Rate per square

NOTE:
For laying concrete at depths more than 5'-0", add 1/4 day unskilled labourer for each
additional 5'-0" or part there-of per square.
--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------26

6" thick cement concrete floor in ( mass concrete )1:3:6(1 1/2")


Per square
Materials
0.5
Add
200

cubes
5%
gallons

Labour
1/2
1 1/4

day
day

concrete
for wastage
Water

Sk labourer
U / Sk labourer

20,889.17
2.25

800.00
600.00

Cost per sqr


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------27

Cement concrete 1:2:4(3/4") in 4 1/2" x 6" columns in ground floor.


Consider 24 No. columns each 4 1/2" x 6" x 10'-0" i.e. 0.45 cubes.
Per 0.45 cube
Materials
0.45
Add

cubes
10%

concrete
for wastage

24,433.50

Plant
1

day

hire of vibrator

Labour
1
1
3
1

day
day
days
day

mason
carpenter
U / Sk labourer
Sk labourer ( Vibrator )

800.00
800.00
600.00
800.00

Curing
100
170
1

sq.ft
gallons
day

Jute Hessian
Water
U / Sk labourer

10.00
2.25
600.00

1,200.00

Total for 0.45 cubes


Cost per cube
35%

Overheads & Profit


Rate per cube

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------28

Cement concrete 1:2:4(3/4") in 6" x 6" columns in ground floor.


Consider 18 No. columns 6" x 6" each 10'-0" high i.e. 0.45 cubes.
Per 0.45 cubes
Materials
0.45
Add

cubes
10%

concrete
for wastage

25,806.67

Plant
1

day

hire of vibrator

Labour
1
1
1
3

day
day
day
days

mason
carpenter
Sk labourer ( vibrator )
U / Sk labourer

800.00
800.00
800.00
600.00

Curing
80
140
1 1/2

Sf.ft
gallons
days

Jute Hessian
Water
U / Sk labourer

10.00
2.25
600.00

Total for 0.45 cubes

1,200.00

Cost per cube


35%

Overheads & Profit


Rate per cube

--------------------------------------------------------------------------------------------------------------------------------------------------------------29

Cement concrete 1:2:4(3/4") in 9" x 9" columns in ground floor.


Consider 8 No. 9" x 9" columns each 10'-0" high I.e. 0.45 cubes.
Per 0.45 cubes
Materials
0.45
Add

cubes
10%

concrete
for wastage

25,806.67

Plant
1

day

hire of vibrator

Labour
1
1
1
3

day
day
day
days

mason
carpenter
Sk labourer ( Vibrator )
U / Sk labourer

800.00
800.00
800.00
600.00

Curing
60
100
1/2

sq.ft
gallons
day

Jute Hessian
water
U / Sk labourer

10.00
2.25
600.00

1,200.00

Total for 0.45 cubes


Cost per cube
35%

Overheads & Profit


Rate per cube

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------30

Cement concrete 1:2:4(3/4") in 12" x 12" columns in ground floor.


Consider 5 No. columns 12" x 12" each 10'-0" high.
Per 0.50 cubes
Materials

0.5
Add

cubes
5%

concrete
for wastage

25,246.45

Plant
1

day

hire of vibrator

Labour
1
1
1
3

day
day
day
days

mason
carpenter
Sk labourer ( Vibrator )
U / Sk labourer

800.00
800.00
800.00
600.00

Curing
40
100
1 1/2

sq.ft
gallons
days

Jute Hessian
water
U / Sk labourer curing

10.00
2.25
600.00

1,200.00

Total for 0.50 cube


Cost per cube
35%

Overheads & Profit


Rate per cube

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------31

Cement concrete 1:2:4(3/4") in 13 1/2" x 13 1/2" columns in ground floor.


Consider 4 No. columns 13 1/2" x 13 1/2" each 10'-0" high i.e. 0.51 cubes.
Per 0.51 cubes
Materials
0.51
Add

cubes
5%

concrete
for wastage

Plant
1

day

hire of vibrator

Labour
1
1
3
1

day
day
days
day

mason
carpenter
U / Sk labourer
Sk labourer ( vibrator.)

Curing
45
100

sq.ft
gallons

Jute Hessian
water

25,806.67

1,200.00

800.00
800.00
600.00
800.00

10.00
2.25

1 1/2

days

U / Sk labourer

600.00

Total for 0.51 cubes


Cost per cube
35%

Overheads & Profit

Rate per cube


--------------------------------------------------------------------------------------------------------------------------------------------------------------32

Cement concrete 1:2:4(3/4") in 6" x 6" beam up to 1st floor level.


Consider 180 L.ft of beam 6" x 6" i.e. 0.45 cubes.
Per 0.45 cubes
Materials
0.45
Add

cubes
5%

concrete
for wastage

25,806.67

Plant
1

day

hire of vibrator

Labour
1
1
4
1

day
day
days
day

mason
carpenter
U / Sk labourer
Sk labourer ( vibrator )

800.00
800.00
600.00
800.00

Curing
90
180
1 1/2

sq.ft
gallons
days

Jute Hessian
water
U / Sk labourer

10.00
2.25
600.00

1,200.00

Total for 0.45 cubes


Cost per cube
35%

Overheads & Profit


Rate per cube

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------33

Cement concrete 1:2:4(3/4") in 9" x 6" beam up to 1st floor level.


Consider 120 L.ft of beam 9" x 6" i.e. 0.45 cubes.
Per 0.45 cubes

Materials
0.45
Add

cubes
10%

concrete
for wastage

25,806.67

Plant
1

day

hire of vibrator

Labour
1
1
4
1

day
day
days
day

mason
carpenter
U / Sk labourer
Sk labourer ( vibrator )

800.00
800.00
600.00
800.00

Curing
75
150
1 1/2

sq.ft
gallons
days

Jute Hessian
water
U / Sk labourer

10.00
2.25
600.00

1,200.00

Total for 0.45 cubes


Cost per cube
35%

Overheads & Profit


Rate per cube

--------------------------------------------------------------------------------------------------------------------------------------------------------------34

Cement concrete 1:2:4(3/4") in 9" x 9" beam up to 1st floor level.


Consider 80'-0" length of beam 9" x 9" i.e. 0.45 cubes.
Per 0.45 cubes
Materials
0.45
Add

cubes
10%

concrete
for wastage

25,806.67

Plant
1

day

hire of vibrator

Labour
1
1
4
1

day
day
days
day

mason
carpenter
U / Sk labourer
Sk labourer ( vibrator )

800.00
800.00
600.00
800.00

Curing
60
120
1 1/2

sq.ft
gallons
days

Jute Hessian
water
U / Sk labourer

10.00
2.25
600.00

1,200.00

Total per 0.45 cubes


Cost per cube
35%

Overheads & Profit


Rate per cube

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------35

5" thick R.C.C 1:2:4(3/4") slab in 1st floor


Consider 5" thick slab 10'-0" x 12' -0" -Volume of concrete 0.50 cube
Per 0.50 cube
Materials
0.50
Add

cube
10%

concrete
for wastage

25,806.67

Plant
1

day

hire of vibrator

Labour
1
1
1
4

day
day
day
days

mason
carpenter
SK labourer ( vibrator )
U / Sk labourer

800.00
800.00
800.00
600.00

Curing
30
90
1 1/2

sq.ft
gallons
days

Jute Hessian
Water
U / Sk labourer

10.00
2.25
600.00

1,200.00

Total for 0.50 cube


Cost per cube
35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------36

6" thick R.C.C 1:2:4(3/4") slab in 1st floor


Consider 10'-0" x 10'-0" panel = 0.50 cube
Materials

0.50
Add

cube
10%

concrete
for wastage

25,806.67

Plant
1

day

hire of vibrator

Labour
1
1
1
4

day
day
day
days

mason
carpenter
SK labourer ( vibrator )
U / Sk labourer

800.00
800.00
800.00
600.00

Curing
25
90
1 1/2

sq.ft
gallons
days

Jute Hessian
Water
U / Sk labourer

10.00
2.25
600.00

1,200.00

Total for 0.50 cube


Cost per cube
35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------37

Cement concrete 1:2:4(3/4") in 4 1/2" x 6" lintels in ground floor


Consider 240 L.ft -i.e. 0.45 cube
Materials
0.45
Add

cube
10%

concrete
for wastage

25,246.45

Plant
1

day

hire of vibrator

Labour
1
1
1
4

day
day
day
days

mason
carpenter
Sk labourer ( vibrator )
U / Sk labourer

800.00
800.00
800.00
600.00

Curing
10
90
1 1/2

sq.ft
gallons
days

Jute Hessian
Water
U / Sk labourer

10.00
2.25
600.00

Total for 0.45 cube

1,200.00

Cost per cube


35%

Overheads & Profit


Rate per Cube

---------------------------------------------------------------------------------------------------------------------------------------------------------------

38

Cement concrete 1:2:4(3/4") in 9" x 9" lintels in ground floor


Consider 80 L.ft of lintel -i.e. 0.45 cube
Materials
0.45
Add

cu.ft
10%

concrete
for wastage

Plant
1

day

hire of vibrator

Labour
1
1
1
4

day
day
day
days

mason
carpenter
Sk labourer ( vibrator )
U / Sk labourer

800.00
800.00
800.00
600.00

Curing
60
90
1 1/2

sq.ft
gallons
days

Jute Hessian
Water
U / Sk labourer

10.00
2.25
600.00

25,806.67

1,200.00

Total for 0.45 cube


Cost per cube
35%

Overheads & Profit


Rate per Cube

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------39

Cement concrete 1:2:4(3/4") in 9" x 12" lintels in ground floor


Consider length 60'-0" of lintel = 0.45 cube
Materials
0.45
Add

cu.ft
10%

concrete
for wastage

25,806.67

Plant
1

day

hire of vibrator

Labour
1
1
1
4

day
day
day
days

mason
carpenter
Sk labourer ( vibrator )
U / Sk labourer

800.00
800.00
800.00
600.00

Curing
55
90
1 1/2

sq.ft
gallons
days

Jute Hessian
Water
U / Sk labourer

10.00
2.25
600.00

1,200.00

Total for 0.45 cube


Cost per cube
35%

Overheads & Profit


Rate per Cube

--------------------------------------------------------------------------------------------------------------------------------------------------------------40

Cement concrete 1:2:4(3/4") in 12" x 15" lintels in ground floor


Consider leanth of 36'-0"-i.e. 0.45 cube
Materials
0.45
Add

cu.ft
10%

concrete
for wastage

Plant
1

day

hire of vibrator

Labour
1
1
1
4

day
day
day
days

mason
carpenter
Sk labourer ( vibrator )
U / Sk labourer

800.00
800.00
800.00
600.00

Curing
40
90
1 1/2

sq.ft
gallons
days

Jute Hessian
Water
U / Sk labourer

10.00
2.25
600.00

Total for 0.45 cube


Cost per cube
35%

Overheads & Profit

25,806.67

1,200.00

Rate per Cube


--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

--------------------------------------Amount
---------------------------------------

10,270.00
2,385.00
5,520.00
1,000.00
247.50

266.67
1,200.00
20,889.17

---------------------------------------

11,060.00
2,700.00
6,300.00
1,000.00
225.00

266.67
1,200.00
22,751.67

--------------------------------------Amount
---------------------------------------

14,220.00
2,250.00
6,600.00
1,000.00
270.00

266.67
1,200.00
25,806.67

---------------------------------------

18,170.00
1,890.00
6,150.00
1,000.00
337.50

266.67
1,200.00

29,014.17

---------------------------------------

24,490.00
1,980.00
7,200.00
1,000.00
450.00

266.67
1,200.00
36,586.67

--------------------------------------Amount
---------------------------------------

3,481.53
348.15

100.00
300.00
4,229.68
1,480.39
5,710.07

---------------------------------------

5,222.29
522.23

100.00
450.00
6,294.52
2,203.08
913.49
8,497.60

--------------------------------------Amount
---------------------------------------

10,444.58
522.23
450.00

400.00
750.00
12,566.81
4,398.38
1,823.76
16,965.20

---------------------------------------

10,995.08
1,099.51

1,200.00

800.00
800.00
1,800.00
800.00

1,000.00
382.50
600.00
19,477.08
43,282.41
15,148.84
20,626.23
58,431.25

--------------------------------------Amount
---------------------------------------

11,613.00
1,161.30

1,200.00

800.00
800.00
800.00
1,800.00

800.00
315.00
900.00
20,189.30

44,865.11
15,702.79
60,567.90

---------------------------------------

11,613.00
1,161.30

1,200.00

800.00
800.00
800.00
1,800.00

600.00
225.00
300.00
19,299.30
42,887.33
15,010.57
57,897.90

--------------------------------------Amount
---------------------------------------

12,623.23
631.16

1,200.00

800.00
800.00
800.00
1,800.00

400.00
225.00
900.00
20,179.39
40,358.77
14,125.57
19,232.97
54,484.34

--------------------------------------Amount
---------------------------------------

13,161.40
658.07

1,200.00

800.00
800.00
1,800.00
800.00

450.00
225.00

900.00
20,794.47
40,773.47
14,270.71

55,044.19
---------------------------------------

11,613.00
580.65

1,200.00

800.00
800.00
2,400.00
800.00

900.00
405.00
900.00
20,398.65
45,330.33
15,865.62
61,195.95

--------------------------------------Amount
---------------------------------------

11,613.00
1,161.30

1,200.00

800.00
800.00
2,400.00
800.00

750.00
337.50
900.00
20,761.80
46,137.33
16,148.07
62,285.40

---------------------------------------

11,613.00
1,161.30

1,200.00

800.00
800.00
2,400.00
800.00

600.00
270.00
900.00

20,544.30
45,654.00
15,978.90
61,632.90

21,778.41

--------------------------------------Amount
---------------------------------------

12,903.33
1,290.33

1,200.00

800.00
800.00
800.00
2,400.00

300.00
202.50
900.00
21,596.17
43,192.33
15,117.32
58,309.65

---------------------------------------

12,903.33
1,290.33

1,200.00

800.00
800.00
800.00
2,400.00

250.00
202.50
900.00
21,546.17
43,092.33
15,082.32
6,253.77
58,174.65

--------------------------------------Amount
---------------------------------------

11,360.90
1,136.09

1,200.00

800.00
800.00
800.00
2,400.00

100.00
202.50
900.00
19,699.49

43,776.65
15,321.83
59,098.48

---------------------------------------

11,613.00
1,161.30

1,200.00

800.00
800.00
800.00
2,400.00

600.00
202.50
900.00
20,476.80
45,504.00
15,926.40
61,430.40

--------------------------------------Amount
---------------------------------------

11,613.00
1,161.30

20,861.76

1,200.00

800.00
800.00
800.00
2,400.00

550.00
202.50
900.00
20,426.80
45,392.89
15,887.51
61,280.40

---------------------------------------

11,613.00
1,161.30

1,200.00

800.00
800.00
800.00
2,400.00

400.00
202.50
900.00
20,276.80
45,059.56
15,770.84

60,830.40

--------------------------------------Amount
---------------------------------------

TIMBER FORMWORK
41

Sawn timber formwork to 9" x 9" cement concrete column in ground floor.
Per Sqr.
Consider column leanth of 5'-0" contact area - 15.0 sq.ft

( A ) MAKING MOULD
1 ) Materials
18.15
sq.ft
17.1
L.ft
16.12
L.ft
1 1/2
lbs
2 ) Fabricanting
1/2
day
1/2
day

1" thick class II timber planks


2" x 2" class II timber in yokes.
2" x 1" class II timber battens.
wire nails.

carpenter
U / Sk labourer

50.00
15.00
3.00
82.00

800.00
600.00

Total cost
Allowing

uses cost of mould per use.

( B ) Assembling ( Per use )


Materials
12
nos.
16 mm 18" long bolts ( 20 uses)
1/2
litre
mould oil
35
L.ft
4" x 2" props ( 10 uses )
1/4
1/4

day
day

carpenter
U / Sk labourer

(A)

30.00
60.00
40.00
800.00
600.00

Cost of Assembling Per use

(B)

( C ) Dismantling cleaning & repairing ( per use )


1/4
1/4

day
day

carpenter
U / Sk labourer

Cost of dismantling per use.

800.00
600.00
(C)

Total cost per use ( For 15.0 sq.ft ) i.e. ( A + B + C )


Cost per Square.
35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

42

Sawn timber formwork for concrete beams in ground floor.


Consider 9" x 12" beam of 20'-0" long. Concrete area 55 sq.ft.

( A ) Making the mould.


1 ) Materials
60
sq.ft
24
L.ft
45
L.ft
30
L.ft
2
lbs
2 ) Labour
1 1/2
2

days
days

1" timber planks.


2" x 1" battens.
2" x 2" ledgers.
4" x 2" bearers at bottom of mould.
wire nails.

carpenter
U / Sk labourer

50.00
3.00
15.00
40.00
82.00

800.00
600.00

Total cost of mould


Assuming
Add

4
10%

uses cost per use


for repairs
Cost per use

(A)

( B ) Assembling
110
80
50
6
22

L.ft
L.ft
L.ft
sq.ft
Nos

4" x 2" vertical props ( 10 uses )


2" x 2" bracing to mould & props.
2" x 2" bracing to a set of props.
1" timber base plate to props.
wedges

40.00
15.00
15.00
50.00
5.00

Cost of materials for aseembling .


Assuming an average of 6 uses.
Cost of materials per use.
Add
10%
of cost of materials for repairs.
Total cost of materials per use.
( C ) Labour & Sundries
Labour
1
day
2
day
1/2
gallons
1/2
lb

carpenter
U / Sk labourer
mould oil
nails

(B)

800.00
600.00
60.00
82.00

Cost per use.


( D ) Dismantling and Cleaning
Labour
1/2
day
carpenter
2
day
U / Sk labourer

(C)

800.00
600.00

Cost of labour for dismantling per use.

(D)

Total cost for making the mould assembling aligning


dismantling and cleaning for 55 sq.ft per use .
( A + B+ C + D )
Cost per Square
35%

Overheads & Profit


Rate per square.

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------43

Sawn timber formwork for underside of first floor slab.


Consider a slab of dismansions 20'-0" x 10'-0"
Concrete area = 2.0 sqrs.

( A ) Making panels
1 ) Materials
220
sq.ft
121
L.ft
4
lbs.
2 ) labour
3
3

days
days

1" thick tongue and grooved timber planks.


4" x 2" runners at 2'-0" centres.
wire nails.

carpenter
U / Sk labourer

50.00
40.00
82.00

800.00
600.00

Total cost of making panels.


Assuming
Add

4
uses cost per use.
20%
for repairs.
Total cost of panels per use.

( B ) Assembling
Materials
690
66
122
33

L.ft
L.ft
No.
sq.ft

4" x 2" vertical timber props. ( 10 uses. )


2" x 2" bracing for props.
wedges
1" base plates for props.

(A)

40.00
15.00
5.00
50.00

Cost of materials for assembling.


Assuming
6
uses cost of materials .
For assembling per use.
Add
20%
of above for repairs.
Total cost of materials for assuming per use.

(B)

( C ) Labour & Sundries for Assembling


1
day
carpenter
4
days
U / Sk labourer
1
gallons molud oil for assembling
2
lbs
wire nails.

800.00
600.00
60.00
82.00

Total cost per use for assembling.


( D ) Dismantling & Cleaning
Labour
1/2
day
carpenter
2
days
U / Sk labourer
Total cost for dismantling per use.

(C)

800.00
600.00
(D)

Total cost for assembling per use for 200 sq.ft


(A+B+C+D)
Cost of formwork per square
35%

Overheads & Profit


Rate per Square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

907.50
256.50
48.36
123.00

400.00
300.00
2,035.36
508.84

18.00
30.00
140.00
200.00
150.00
538.00

200.00
150.00
350.00
1,396.84
9,312.27
3,259.29
12,571.56

Amount

-----------------------------------------

3,000.00
72.00
675.00
1,200.00
164.00

1,200.00
1,200.00
7,511.00
1,877.75
187.78
2,065.53

440.00
1,200.00
750.00
300.00
110.00
2,800.00

466.67
46.67
513.33

800.00
1,200.00
30.00
41.00
2,071.00

400.00
1,200.00
1,600.00

6,249.86
11,363.38
3,977.18
15,340.56

Amount

-----------------------------------------

11,000.00
4,840.00
328.00

2,400.00
1,800.00
20,368.00
5,092.00
1,018.40
6,110.40

2,760.00
990.00
610.00
1,650.00
6,010.00

1,001.67
200.33
1,202.00

1,649.11

800.00
2,400.00
60.00
164.00
3,424.00

400.00
1,200.00
1,600.00
12,336.40

6,168.20
2,158.87
8,327.07

Amount

-----------------------------------------

STEEL REINFORCEMENTS
44

Mild steel / Tor steel reinforcement to lintels, slabs, beams or columns bent to shape
laid in position and tied with G . I . wire as directed.
Materials
1

cwt

Allow

15%

1 1/2
Add
Labour
1
1

lbs
1.50%

day
day

M. S./ Tor steel rods including


transport to site.
for wastage
16 BWG binding wire
of steel cost for spacers or chairs.

blacksimth
U / Sk labourer

6,600.00

85.00

800.00
600.00

Cost per cwt


35%

Overheads & Profit


Rate per cwt

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

6,600.00
990.00
127.50
99.00

800.00
600.00
9,216.50
3,225.78
12,442.28
248.85
Amount

-----------------------------------------

248.85

19,409.95

BRICKWORK
45

Brick work in cement & sand 1:5 in foundation up to D. P. C. level.


Per cube
Materials
1450
Add
4
0.25
150
Labour
3
4

bricks
5%
cwt
cubes
gallons

days
days

6.50
wastage
cement ( 50 Kg bags )
sand
water

mason
U / Sk labourer

790.00
4,500.00
2.25

800.00
600.00

Cost per cube


35%

Overheads & Profit


Rate per cube

--------------------------------------------------------------------------------------------------------------------------------------------------------------46

Brick work in cement & sand 1:8 in foundation up to D. P. C. level.


Per cube
Materials
1450
Add
2 1/3
3/8
150
Labour
3
4

Nos.
5%
cwt
cubes
gallons

days
days

bricks
wastage
cement ( 50 Kg bags )
sand
water

mason
U / Sk labourer

6.50
790.00
4,500.00
2.25

800.00
600.00

Cost per cube


35%

Overheads & Profit


Rate per cube

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------47

Brick work in cement and sand 1:5 in 4 1/2" thick walls in ground floor

Per square
Materials
550
Add
1.3
1/10
50

Nos.
5%
cwt
cubes
gallons

Labour
1 1/2
days
2
days
Scaffolding - Add

bricks
wastage
cement ( 50 Kg bags )
sand
water

mason
U / Sk labourer
5%
of labour cost

6.50
790.00
4,500.00
2.25

800.00
600.00

Total per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------48

9" thick brick wall in cement & sand 1:5 in ground floor
Per square
Materials
1090
Add
3
0.2
115

Nos.
5%
cwt
cubes
gallons

Labour
2 1/4
days
3 3/4
days
Scaffolding - Add

bricks
for wastage
cement ( 50 Kg bags )
sand
water

mason
U / Sk labourer
3%
of labour cost

6.50
790.00
4,500.00
2.25

800.00
600.00

Total per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------49

Brickwork 13 1/2" thick in cement & sand 1:5 in superstructure in ground floor
Per square

Materials
1630
Add
4.5
0.3
170

Nos.
5%
cwt
cubes
gallons

Labour
3 1/2
days
5 1/2
days
Scaffolding - Add

bricks
for wastage
cement ( 50 Kg bags )
sand
water

6.50
790.00
4,500.00
2.25

mason
U / Sk labourer
2%
of labour cost

800.00
600.00

Total per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------50

9" thick brick wall in cement & sand 1:5 in superstructure in ground floor
Per square ( i.e 0.75 cubes )
Materials
1090
Add
1.75
0.3
115

Nos.
5%
cwt
cubes
gallons

Labour
2 1/4
days
3
days
Scaffolding - Add

bricks
for wastage
cement ( 50 Kg bags )
sand
water

mason
U / Sk labourer
3%
of labour cost

6.50
790.00
4,500.00
2.25

800.00
600.00

Total per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------51

4 1/2" thick brick wall ( wire cut ) in cement & sand 1:5 in ground floor
( Facing to brickwork measured separately )
Per square

Materials
550
Add
1.2
0.08
30

Nos.
2%
cwt
cubes
gallons

Labour
1 1/2
days
2
days
Scaffolding - Add

wire cut bricks


for wastage
cement ( 50 Kg bags )
sand
water

12.00
790.00
4,500.00
2.25

mason
U / Sk labourer
5%
of labour cost

800.00
600.00

Total per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------52

9" thick brick in cement & sand 1:5 with wire cut bricks
( Facing to brickwork measured separately )
Per square
Materials
1080
Add
2.5
0.18
100

Nos.
4%
cwt
cubes
gallons

Labour
2 1/4
days
3 3/4
days
Scaffolding - Add

wire cut bricks


for wastage
cement ( 50 Kg bags )
sand
water

12.00
790.00
4,500.00
2.25

mason
U / Sk labourer
3%
of labour cost

800.00
600.00

Total per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------53

13 1/2" thick brick wall ( wire cut ) in cement & sand 1:5 in ground floor
( Facing to brickwork measured separately )

Per square
Materials
1630
Add
4.5
0.3
150

Nos.
2%
cwt
cubes
gallons

Labour
3 3/4
days
5 1/2
days
Scaffolding - Add

wire cut bricks


for wastage
cement ( 50 kg bags )
sand
water

mason
U / Sk labourer
2%
of labour cost

12.00
790.00
4,500.00
2.25

800.00
600.00

Total per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------54

Extra over for facing including raised pointing 1 / 8" thick in cement and sand
1:1 mixture in ground floor
( Facing to brick work measured separately )
Per square
Materials
0.5
1
1/10
10

cwt
cu.ft
gallons
gallons

Labour
5
3 1/2

days
days

cement ( 50 Kg bags )
sand
acid
water

mason
U / Sk labourer

790.00
4,500.00
100.00
2.25

800.00
600.00

Total per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------55

3" thick brick paved floor in lime sand mortar 2 : 5 in ground floor

Per square
Materials
350
1.2
0.11
45

Nos.
cwt
cubes
gallons

Labourer
1 1/4
2 1/2

days
days

bricks
slaked lime
sand
water

mason
U / Sk labourer

6.50
35.00
4,500.00
2.25

800.00
600.00

Total per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------56

Steps 1'-11/2" x 0'-6" in brick in cement and sand 1:5 with 1/2" thick cement
and sand 1:2 rendering including necessary excavation.
Per 10 L.ft
Materials
120
0.5
0.05
15
Labour
1/2
1/2

Nos.
cwt
cubes
gallons

day
day

bricks
cement ( 50 Kg bags )
sand
water

mason
U / Sk labourer

6.50
790.00
4,500.00
2.25

800.00
600.00

Total for 10 L.ft


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------57

Brick drains in cement and sand 1 : 5, 9" wide and 6" - 9" average depth
including cement rendering 1/2" thick 1:2 to exposed faces with 1'-6" ramp
including necessary excavation.
Per 10 L.ft

Materials
140
0.8
0.05
20

Nos
cwt
cubes
gallons

Labour
1 1/4
1 1/4

days
days

bricks
cement ( 50 kg bags )
sand
water

6.50
790.00
4,500.00
2.25

mason
U / Sk labourer

800.00
600.00

Total for 10 L.ft


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------58

Brick drains in cement and sand 1 : 5, 9" wide and 6" - 9" average depth
including cementrendering 1/2" thick 1:2 to exposed faces without ramp
including necessary excavation.
Per 10 L.ft
Materials
110
0.7
0.04
15

bricks
cwt
cubes
gallons

cement ( 50 Kg bags )
sand
water

Labour
1
1 1/4

days
days

mason
U / Sk labourer

6.50
790.00
4,500.00
2.25

800.00
600.00

Total for 10 L.ft


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

HOLLOW BLOCKWORK

59

8" thick Hollow blockwork in cement and sand mortar 1 : 5 in ground floor
( Cavities unfilled )
Per square
10'-0" x 10'-0" area ( size of each block 16" x 8" x 8" )
Materials
112
Allow
0.75
0.06

Nos
5%
cwt
cubes

Labour
1 1/2
2 1/2
Add

days
days
3%

Hollow cement block


for wastage
cement ( 50 Kg bags )
sand

mason
U / Sk labourer
for Scaffolding

65.00
790.00
4,500.00

800.00
600.00

Total per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------60

4" thick Hollow block masonry in cement and sand mortar 1 : 5


with cavities unfilled
Per square
10'-0" x 10'-0" area ( size of each block 16" x 8" x 4" )
Materials
112
Allow
0.4
0.03
Labour
1
2
Add

Nos.
5%
cwt
cubes

days
days
5%

Hollow cement block


for wastage
cement ( 50 Kg bags )
sand

mason
U / Sk labourer
for Scaffolding

38.00
790.00
4,500.00

800.00
600.00

Total per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

9,425.00
471.25
3,160.00
1,125.00
337.50

2,400.00
2,400.00
19,318.75
6,761.56
26,080.31

-----------------------------------------

9,425.00
471.25
1,843.33
1,687.50
337.50

2,400.00
2,400.00
18,564.58
6,497.60
25,062.19

Amount

-----------------------------------------

3,575.00
178.75
1,027.00
450.00
112.50

1,200.00
1,200.00
120.00
7,863.25
2,752.14
10,615.39

-----------------------------------------

7,085.00
354.25
2,370.00
900.00
258.75

1,800.00
2,250.00
121.50
15,139.50
5,298.83
20,438.33

Amount

-----------------------------------------

2,197.12

10,595.00
529.75
3,555.00
1,350.00
382.50

2,800.00
3,300.00
122.00
22,634.25
7,921.99
30,556.24

-----------------------------------------

7,085.00
354.25
1,382.50
1,350.00
258.75

1,800.00
1,800.00
108.00
14,138.50
4,948.48
19,086.98

Amount

-----------------------------------------

6,600.00
132.00
948.00
360.00
67.50

1,200.00
1,200.00
120.00
10,627.50
3,719.63
14,347.13

-----------------------------------------

12,960.00
518.40
1,975.00
810.00
225.00

1,800.00
2,250.00
121.50
20,659.90
7,230.97
27,890.87

Amount

-----------------------------------------

2,998.27

19,560.00
391.20
3,555.00
1,350.00
337.50

3,000.00
3,300.00
126.00
31,619.70
11,066.90
42,686.60

-----------------------------------------

395.00
4,500.00
10.00
22.50

4,000.00
2,100.00
11,027.50
3,859.63
14,887.13

Amount

-----------------------------------------

2,275.00
42.00
495.00
101.25

1,000.00
1,500.00
5,413.25
1,894.64
7,307.89

-----------------------------------------

780.00
395.00
225.00
33.75

400.00
300.00
2,133.75
213.38
74.68
288.06

Amount

-----------------------------------------

910.00
632.00
225.00
45.00

1,000.00
750.00
3,562.00
356.20
124.67
480.87

-----------------------------------------

715.00
553.00
180.00
33.75

800.00
750.00
3,031.75
303.18
106.11
409.29

Amount

-----------------------------------------

7,280.00
364.00
592.50
270.00

1,200.00
1,500.00
81.00
11,287.50
3,950.63
15,238.13

-----------------------------------------

4,256.00
212.80
316.00
135.00

800.00
1,200.00
100.00
7,019.80
2,456.93
9,476.73

Amount

-----------------------------------------

RUBBLE MASONRY
61

Random Rubble masonry in cement motar 1 : 5 in foundation


Per cube ( 14" thick )
Materials
1.3
7.25
0.3
100
Labour
4
6

cubes
cwt
cube
gallons

days
days

6" - 9" rubble


cement ( 50 Kg bags )
sand
water

mason
U / Sk labourer

3,500.00
790.00
4,500.00
2.25

800.00
600.00

Cost per cube


35%

Overheads & Profit


Rate per cube

--------------------------------------------------------------------------------------------------------------------------------------------------------------62

Random Rubble masonry in cement motar 1 : 5 in supersturcture


Per cube ( 14" thick )
Materials
1.3
7.25
0.3
100

cubes
cwt
cube
gallons

Labour
4 1/2
7
Add

days
days
3%

6" - 9" rubble


cement ( 50 Kg bags )
sand
water

mason
U / Sk labourer
for Scaffolding

3,500.00
790.00
4,500.00
2.25

800.00
600.00

Cost per cube


35%

Overheads & Profit


Rate per cube

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

4,550.00
5,727.50
1,350.00
225.00

3,200.00
3,600.00
18,652.50
6,528.38
25,180.88

-----------------------------------------

4,550.00
5,727.50
1,350.00
225.00

3,600.00
4,200.00
234.00
19,886.50
6,960.28
26,846.78

Amount

-----------------------------------------

8,888.85

TILE WORKS
63

Pressed floor tiles bedded in 1/2" cement mortar 1 : 2 and


pointing in neat cement in ground floor.
Per square
Materials
225
Add
1 1/4
0.07
1/4
1/4
2

Nos.
5%
cwt
cube
lb
lb
lbs

pressed tiles 8" x 8"


for wastage
cement ( 50 Kg bags )
sand
wax polish
coloured pigment
cotton waste

Labour
4
4
1/2

days
days
day

Special mason
U / Sk labourer
U / Sk labourer for polishing

6.00
790.00
4,500.00
80.00
128.00
20.00

950.00
600.00
600.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------WALL TILING & TERRAZZO TILES
64

Glazed tiles fixed to walls including bedding in cement mortar 1 : 2 and


raking inground floor. (Specials measured separately ).
Per square
Materials
400
Add
2 1/2
0.11
1

Nos
10%
cwt
cube
lb

galzed tiles 6" x 6"


for wastage on cutting
cement ( 50 Kg bags )
sand
white cement

Labour
4
4
1/4

days
days
day

Special mason
U / Sk laboruer
U / Sk laboruer for cleaning

Cost per square

15.00
790.00
4,500.00
30.00

950.00
600.00
600.00

35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------65

Terrazzo floor tiles on 1/2" thick cement and sand 1 : 2 in ground floor
Per square
Materials
100
Add
1 1/4
0.07
2
1/2
2
Labour
4
3
1/2

Nos
5%
cwt
cubes
lbs
lb
lb

days
days
day

12" x 12" terrazzo tiles


for wastage
cement ( 50 kg bags )
sand
Coloured pigment
wax polish
cotton waste

Special mson
U / Sk labourer
U / Sk labourer ( polishing )

35.00
790.00
4,500.00
128.00
80.00
20.00

950.00
600.00
600.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

1,350.00
67.50
987.50
315.00
20.00
32.00
40.00

3,800.00
2,400.00
300.00
9,312.00
3,259.20
12,571.20

Amount

-----------------------------------------

6,000.00
600.00
1,975.00
495.00
30.00

3,800.00
2,400.00
150.00
15,450.00

5,407.50
20,857.50

-----------------------------------------

3,500.00
175.00
987.50
315.00
256.00
40.00
40.00

3,800.00
1,800.00
300.00
11,213.50
3,924.73
15,138.23

Amount

-----------------------------------------

2,242.18

ROOF WORK
66

Timber framework for calicut pattern tile hip roof in single storey building
consisting of wall plate, beam, ridge plate, rafters etc. (Preservative
treatment to be measured separately.)
Per 6.00 square
Materials
34
Add
660
Add
8
2

cu.ft
10%
l.ft
5%
lbs
lbs

class 1 timber
for wastage
2" x 1" reepers
for wastage
wire nails 6" long
wire nails 2" long

Labour
7
8

days
days

carpenter
U / Sk labourer

1,500.00
8.00
82.00
82.00

800.00
600.00

Total per 6.00 squares


Total per square
35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------67

Roof covering with calicut pattern clay tiles in single storeyed building
(Timber frame work & ridge covering measured separately)
Per 6.00 squares
Materials
750

nos.

tiles

Labour
3
3

days
days

carpenter
U / Sk labourer

10.00

800.00
600.00

Cost per 6.00 squares.


Cost per square
35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate

--------------------------------------------------------------------------------------------------------------------------------------------------------------68

Timber framework for corrugated asbestos sheet roof in single storeyed building.
Per 3.60 sqrs.
Materials
13 1/4
Add

cu.ft
10%

timber purlins
for wastage

Labour
2 1/2
3

days
days

carpenter
U / Sk labourer

1,500.00

800.00
600.00

Total per 3.60 squares


Total per square
35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------69

Roof covering with corrugated asbestos sheets ( Timber frame work & ridge
covering measured separately )
Per 3.60 squares
Materials
420
72

sq.ft
Nos.

asbestos corrugated sheets.


roofing screws and washers.

Labour
1
2

days
days

carpenter
U / Sk labourer

26.00
15.00

800.00
600.00

Total per 3.60 squares.


Cosr per square
35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------70

One layer half round clay tiles over corrugated asbestos roof covering
Per square

Materials
650

Nos

half round clay tiles

Labour
2

days

U / Sk labourer

5.00

600.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------71

Asbestos close fittings ridging fixed complete with roofing screws or bols ( hook )
Per 13' - 4" length
Materials
4
16
Labour
1/4
1/4

pairs
nos.

day
day

ridges 3' - 8" long


roofing screws or bolts

250.00
15.00

carpenter
U / Sk labourer

800.00
600.00

Tota per 13' - 4" ridging


Cost per L.ft
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------72

Ridging covering with calicut pattren ridge tiles bedded in cement lime mortar 1 : 1 : 4
Per 12 L.ft ridging
Materials
9
1/3
0.02
15
1/2
Labour
1/4

nos.
cwt
cube
lbs
lb

day

ridge tiles
cement ( 50 Kg bags )
sand
slaked lime
colouring powder

mason

25.00
790.00
4,500.00
35.00
128.00

700.00

1/4

day

U / Sk labourer

400.00

Total per 12 L.ft ridging


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------73

3/4" x 9" high valance board fixed with brass screws to ends of rafters ( for tile roofing )
Per 100 L.ft
Materials
75
Add
70

sq.ft
5%
Nos.

1" thick planks


for wastage
1 1/2" brass screws

150.00

Labour
3
3
Add

days
days
5%

carpenter
U / Sk labourer
for scaffolding

700.00
400.00

3.60

Total per 100 L.ft


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------74

3/4" x 9" high valance board fixed with brass screws at 2'-0" centres to sides of rafters.
Per 100 L.ft
Materials
75
Add
50

sq.ft
5%
Nos.

1" thick planks


for wastage
1 1/2" brass screws

150.00

Labour
3
3
Add

days
days
5%

carpenter
U / Sk labourer
for scaffolding

700.00
400.00

3.60

Total per 100 L.ft


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

51,000.00
5,100.00
5,280.00
264.00
656.00
164.00

5,600.00
4,800.00
72,864.00
12,144.00
4,250.40
16,394.40

1,764.74

-----------------------------------------

7,500.00

2,400.00
1,800.00
11,700.00
1,950.00
682.50
2,632.50

Amount

-----------------------------------------

19,875.00
1,987.50

2,000.00
1,800.00
25,662.50
7,128.47
2,494.97
9,623.44

-----------------------------------------

10,920.00
1,080.00

800.00
1,200.00
14,000.00
3,888.89
1,361.11
5,250.00

Amount

-----------------------------------------

3,250.00

1,200.00
4,450.00
1,557.50
6,007.50

-----------------------------------------

1,000.00
240.00

200.00
150.00
1,590.00
119.28
41.75
161.03

Amount

-----------------------------------------

225.00
263.33
90.00
525.00
64.00

175.00
100.00

1,442.33
120.19
42.07
162.26

-----------------------------------------

11,250.00
562.50
252.00

2,100.00
1,200.00
165.00
15,529.50
155.30
54.35
209.65

Amount

-----------------------------------------

11,250.00
562.50
180.00

2,100.00
1,200.00
165.00
15,457.50

154.58
54.10
208.68

Amount

-----------------------------------------

ROOF PLUMBING
75

18 B.W.G.( 1.2 mm ) galvanised iron sheet valley gutter 3'-0" girth overall once bent with
end laps not less than 9" width including 3/4" tongued and grooved planks laid to slope
and profile on timber and profile on members.
Consider 15'-0" L.ft
Materials
2
1/4
0.1
0.05
1
50
2

no.
gal
cwt
cwt
cu.ft
sq.ft
lbs

G.I. sheet ( 8' x 4' )


wood preservative
cememnt ( 50 Kg bags )
slaked lime
sand
planks
1 1/2" wire nails

2,500.00
338.00
605.00
35.00
6,500.00
26.00
45.00

Fixing boarding and applying wood preservative


1
day
carpenter
1
day
U / Sk labourer

700.00
400.00

Making and fixing G.I. Sheets


1/2
day
tinker
1/2
day
U / Sk labourer

700.00
400.00

Building sides
1/4
day
1/2
day

700.00
400.00

Labour

mason
U / Sk labourer

Total per 15.00 L.ft


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------76

18 B.W.G. ( 1.2 mm ) galvanised iron flashing 1'-6" girth overall 3 times bent with
end laps notless than 6", lead soldered, turned and tucked up to not less than 6"
in to chase cut in wall and pointed in cement morter 1:2 lower end dressed over
roof covering not less than 1'-0" wide.
Consider 15' 0" L.ft
Materials
1

no.

G.I. sheet ( 8' x 4' )

2,500.00

0.05
1
1

cwt
cu.ft
lbs

cememnt ( 50 Kg bags )
sand
soldering lead

605.00
65.00
30.00

Labour
Cutting bending , soldering & fixing
1/2
day
tinker
1/8
day
mason ( caulking )
3/4
day
U / Sk labourer

700.00
700.00
400.00

Building sides
1/4
day
1/2
day

700.00
400.00

mason
U / Sk labourer

Total per 15.00 L.ft


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

5,000.00
84.50
60.50
1.75
65.00
1,300.00
90.00

700.00
400.00

350.00
200.00

175.00
200.00
8,626.75
575.12
201.29
776.41

Amount

-----------------------------------------

2,500.00
30.25

65.00
30.00

350.00
87.50
300.00

175.00
200.00
3,737.75
249.18
87.21
336.40

Amount

-----------------------------------------

CEILING WORK
77

Timber framework for 4'-0" x 4'-0" flat asbestos ceiling ( sheet measured separately ),
comprising of 4" x 2" joists and 2" x 2" bearers in class I timber.
Per 1.95 square
Materials
8
1
26
25
2
1/4
1/3

cu.ft
lb
Nos.
lbs
cu.ft
use
gal

timber class I
2" nails
fiber / plastic plugs
cement
sand
2" brush
tarnap

Labour
2 1/2
1/2
1 1/2
Add

days
day
days
5%

carpenter
mason
U / Sk labourer
for scaffolding

1,500.00
45.00
2.50
605.00
6,500.00
175.00
90.00

700.00
700.00
400.00

Total per 1.95 squares


Cost per square
35%

Overheads & Profit


Rate per sqrare

--------------------------------------------------------------------------------------------------------------------------------------------------------------78

Horizontal ceiling lining using 4' 0" x 4' 0" flat asbestos cement sheet fixed with
and including beading and cove mouldings on timber framework.(Timber framework
& painting measured separately)
Per 1.95 square
Materials
210
60
125
1/4
96

sq.ft
l.ft
l.ft
lb
nos

flat asbestos sheets


2" x 2" Halmilla cove mouldings
1/2" x 1 1/2" Halmilla beadings
1/4" clout headed nails
1 1/2" brass screws

Labour
1 1/2
2
Add

days
days
5%

carpenter
U / Sk labourer
for scaffolding

Total for 1.95 squares

16.00
20.00
4.00
75.00
4.50

700.00
400.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------79

3/4" thick tongued and grooved Lunumidella ceiling boards fixed horizontal
on 4" x 2" class I timber Joists at 2'-0" centres with 1 1/2" brass nails.
Consider room 15'-0" x 13'-0" i.e. 1.95 squares
Materials
115
215
3
4
4

l.ft
sq.ft
lbs
cu.ft
Kg

4" x 2" timber joists


6" x 3/4" Lunumidella ceiling planks.
cement
sand
1 1/2" brass nails

Labour
Making holes, fixing joints & making good 1
day
mason
1
day
carpenter
3
days
U / Sk labourer
Fixing ceiling boards
3
days
4
days
Add
3%

carpenter
U / Sk labourer
for scaffolding

65.00
46.00
605.00
6,500.00
120.00

700.00
700.00
400.00

700.00
400.00

Total per 1.95 squares


Cost per square
35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------80

3/4" x 6" wide tongued and grooved Lunumidella ceiling boards fixed to
underside of roof rafters, (existing) with 1 1/2" brass nails including levelling
with timber strips where necessary.
Consider room 15'-0" x 12'-0" = 1.80 squares.
Materials
220

sq.ft

ceiling planks

46.00

40
2
4
Labour
3
6
Add

l.ft
Kg
Kg

days
days
3%

2" x 1/4" timber strips


3/4" nails
1 1/2" brass nails

8.00
45.00
120.00

carpenter
U / Sk labourer
for scaffolding

700.00
400.00

Total per 1.80 sqrs.


Cost per square
35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

#######
45.00
65.00
137.50
130.00
43.75
30.00

1,750.00
350.00
600.00
135.00
#######
7,839.10
2,743.69
#######

-----------------------------------------

3,360.00
1,200.00
500.00
18.75
432.00

1,050.00
800.00
92.50
7,453.25

3,822.18
1,337.76
5,159.94

Amount

-----------------------------------------

7,475.00
9,890.00
16.50
260.00
480.00

700.00
700.00
1,200.00

2,100.00
1,600.00
111.00
#######
#######
4,403.27
#######

-----------------------------------------

#######
320.00

90.00
480.00

2,100.00
2,400.00
135.00
#######
8,691.67
3,042.08
#######

Amount

-----------------------------------------

DOORS & WINDOWS


81

Door single hung 3'-3" x 7'-0" high overall with frame having 1 1/4" thick sash and
3 3/4"x 2 3/4" timber frame (glazing, ironmongery & painting measured separately)
Per 22.75 square feet ( 3'-3" x 7'-0" )
Materials
a) Frame 1 1/2
2
6
2

cu.ft
No.
No.
No.

4" x 3" timber


spur stones
fiber/plastic plugs with 4" long brass screws
5/8" mild steel dowels 4" long

b) Sash 14
5

sq.ft
sq.ft

1 1/2" planks
1" planks

200.00
150.00

Labour
5
1 1/2

days
days

carpenter
U / Sk labourer

700.00
400.00

1,200.00
30.00
10.00
12.00

Total per 22.75 sq.ft


Cost per sq.ft.
35%

Overheads & Profit


Rate per square foot

--------------------------------------------------------------------------------------------------------------------------------------------------------------82

Door glazed and panelled double hung 4'-0" x 7'-0" high overall with frame
including 1 1/4" thick sash and 3 3/4" x 2 3/4" frame (Glazing, ironmongery
& painting measured separately)
Per 28.00 square feet ( 4'-0" x 7'-0" )
Materials
a) Frame 1 2/3
2
6
2

cu.ft
No.
No.
No.

4" x 3" timber


spur stones
fiber / plastic plugs with 4" long screws
5/8" dia mild steel dowels 4" long

b) Sashes 16
7

sq.ft
sq.ft

1 1/2" planks
1" planks

Labour

1,200.00
30.00
10.00
12.00

200.00
150.00

6
2

days
days

carpenter
U / Sk labourer

700.00
400.00

Total per 28.00 sq.ft


Cost per sq.ft.
35%

Overheads & Profit


Rate per square foot

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------83

Plywoood door single hung 3'-1 1/2" x 6'-11 1/2" overall with frame having 1 1/4" thick
sash and 3 1/4" x 2 1/4" frame . ( Iron-mongery and painting measrued separately ).
Per 21.75 square feet ( 3'-1 1/2" x 6'-11 1/2" )
Materials
a) Frame 1.8
2
6

cu.ft
No.
No.

4" x 3" timber


spur stones
fiber/plastic plugs with 4" long brass screws

1,200.00
30.00
10.00

b) Sash 1

No.

6'-9" x 2'-9" plywood sash

1,200.00

Labour
3/4
3/8
1/4
1/4

day
day
day
day

carpenter
U / Sk labourer
mason ( fixing frame )
U / Sk labourer ( - do - )

700.00
400.00
700.00
400.00

Total per 21.75 square feet


Cost per sq.ft.
35%

Overheads & Profit


Rate per square feet

--------------------------------------------------------------------------------------------------------------------------------------------------------------84

Door ledged, braced and battened single hung 2'-6" x 6'-6" overall, with frame
having 7/8" thick tongued & grooved planks and 3 3/4" x 2 3/4" frame.
(Ironmongery & painting measured separately)
Per 16.25 square feet ( 2' 6" x 6' 6" )

Materials
a) Frame 1.7
2
6
2

cu.ft
No.
No.
No.

4" x 3" timber


spur stones
fiber/plastic plugs with 4" long brass screws
5/8" mild steel dowels 4" long.

b) Sash 21
3

sq.ft
doz

1" thick planks


1 1/4" long brass screws.

150.00
3.00

Labour
2 1/4
1
1/4
1/4

day
day
day
day

carpenter
U / Sk labourer
mason ( fixing frame )
U / Sk labourer ( - do - )

700.00
400.00
700.00
400.00

1,200.00
30.00
10.00
12.00

Total per 16.25 square feet


Cost per sq.ft.
35%

Overheads & Profit


Rate per square feet

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------85

Window, glazed 7'-0" x 4'-0" high overall with frame comprising 3 No.
openable sashes and 3 3/4" x 2 3/4" frame and mullions.
( Glazing, ironmongery and painting measured separately )
Per window 7'-0" x 4'-0" ( sashes )
i.e. per 28 sq.ft.
Materials
a) Frame 3.2
4

cu.ft
No

4" x 3" timber


fiber/plastic plugs with 4" long brass screws

b) Sashes 9.25

sq.ft

3" x 1 1/2" timber

Labour
6
2 1/2
1/2
1/2

days
days
day
day

carpenter
U / Sk labourer
mason ( fixing frame )
U / Sk labourer ( - do - )

1,200.00
10.00

85.00

700.00
400.00
700.00
400.00

Total per 28.00 sq.ft


Cost per sq.ft.
35%

Overheads & Profit


Rate per square foot

--------------------------------------------------------------------------------------------------------------------------------------------------------------86

1/6" clear sheet glass panes exceeding 1 but not exceeding 4 square feet
cut and fixed with timber beadings to doors and windows.
Consider sash 3'-0"x4'-0" high with 3" x 1 1/4" stile and 4 Nos. glass panes.
Per 9.00 sq.ft
Materials
9
30
4

sq.ft
L.ft
doz

glass panes
1/2" x 1/2" beading
brass panel pins

Labour
1/2
1/2

day
day

glazier
U / Sk labourer

30.00
0.75
0.60

700.00
400.00

Total per 9.00 sq.ft


Cost per sq.ft.
35%

Overheads & Profit


Rate per sqaure foot

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

1,800.00
60.00
60.00
24.00

2,800.00
750.00

3,500.00
600.00
9,594.00
421.71
147.60
569.31

-----------------------------------------

2,000.00
60.00
60.00
24.00

3,200.00
1,050.00

4,200.00

800.00
#######
406.93
142.43
549.35

Amount

-----------------------------------------

2,160.00
60.00
60.00

1,200.00

525.00
150.00
175.00
100.00
4,430.00
203.68
71.29
274.97

-----------------------------------------

2,040.00
60.00
60.00
24.00

3,150.00
108.00

1,575.00
400.00
175.00
100.00
7,692.00
473.35
165.67
639.03

Amount

-----------------------------------------

3,840.00
40.00

786.25

4,200.00
1,000.00
350.00
200.00

#######
372.01
130.20
502.21

-----------------------------------------

270.00
22.50
2.40

350.00
200.00
844.90
93.88
32.86
126.74

Amount

-----------------------------------------

IRONMONGARY
87

Butt hinges 5" x 2 1/2"


Per Pair.
Materials
1 1/2
24
Labour
1/4
1/4

pairs
nos

day
day

butt hinges
3/4" brass screws

180.00
1.50

carpenter
U / Sk labourer

700.00
400.00

Per 1 1/2 pairs


Cost per pair
35%

Overheads & Profit


Rate per pair

--------------------------------------------------------------------------------------------------------------------------------------------------------------88

Tee hinges 6" x 12"


Per Pair.
Materials
1
24

pair
nos

Tee hinges
3/4" iron screws

350.00
1.50

Labour
1/4
1/4

day
day

carpenter
U / Sklabourer

800.00
600.00

Cost per pair


35%

Overheads & Profit


Rate per pair

--------------------------------------------------------------------------------------------------------------------------------------------------------------89

Rim lock
Per No.
Materials
1

No

rim lock with screws

250.00

Labour
1/4
1/4

day
day

carpenter
U / Sklabourer

800.00
600.00

Cost per no.


35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------90

Mortice lock
Per No.
Materials
1

No

mortice lock with screws

Labour
1/2
1/2

day
day

carpenter
U / Sklabourer

2,215.00

800.00
600.00

Cost per no.


35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------91

Casement stays.
Per No.
Materials
4
16

Nos
Nos

csaement stays
1/2" brass screws

Labour
1/4
1/4

day
day

carpenter
U / Sk labourer

Total for 4 nos.


Cost per no.
35%

Overheads & Profit


Rate per No.

48.00
1.00

800.00
600.00

--------------------------------------------------------------------------------------------------------------------------------------------------------------92

Door closer ( Hydraulic )


Per No.
Materials
1
8

No
Nos

door closer
3/4' brass screws

850.00
1.50

Labour
1/4
1/4

day
day

carpenter
U / Sk labourer

800.00
600.00

Cost per no.


35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------93

Tower / Skeleton brass bolts.


Per No.
Materials
1
10
Labour
1/2
1/2

No
Nos

hr
hr

Tower / Skeleton bolt


1/2" brass screws

carpenter
U / Sk labourer

73.00
1.00

800.00
600.00

Cost per no.


35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------94
Barrel bolt 4"
Per No.
Materials
1
8

No
Nos

barrel bolt
1/2' brass screws

48.00
1.00

Labour
1/2
1/2

hr
hr

carpenter
U / Sk labourer

800.00
600.00

Cost per no.


35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------95

Casement fasteners.
Per No.
Materials
6
24

Nos
Nos

casement fasteners
1/2" brass screws

Labour
1/2
1/2

day
day

carpenter
U / Sk labourer

34.00
1.00

800.00
600.00

Total per 6 Nos.


Cost per no.
35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------96

Spring loaded fanlight catches


Per No.
Materials
6
24

Nos
nos

brass fanlight catches


1/2" brass screws

Labour
1/2
1/2

day
day

carpenter
U / Sk labourer

Total per 6 Nos.


Cost per no.

30.00
1.00

800.00
600.00

35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------97
Draw rings
Per No.
Materials
6
12

Nos
nos

draw rings
1/2" brass screws

Labour
1/4
1/4

day
day

carpenter
U / Sk labourer

15.00
1.00

800.00
600.00

Total per 6 Nos.


Cost per no.
35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

270.00
36.00

175.00
100.00
581.00
387.33
135.57
522.90

-----------------------------------------

350.00
36.00

200.00
150.00
736.00
257.60
993.60

-----------------------------------------

250.00

200.00
150.00
600.00
210.00
810.00

Amount

-----------------------------------------

2,215.00

400.00
300.00
2,915.00
1,020.25
3,935.25

-----------------------------------------

192.00
16.00

200.00
150.00
558.00
139.50
48.83
188.33

-----------------------------------------

850.00
12.00

200.00
150.00
1,212.00
424.20
1,636.20

Amount

-----------------------------------------

73.00
10.00

400.00
300.00
783.00
274.05
1,057.05

-----------------------------------------

48.00
8.00

50.00
37.50
143.50
50.23
193.73

-----------------------------------------

204.00
24.00

400.00
300.00
928.00
154.67
54.13
208.80

Amount

-----------------------------------------

180.00
24.00

400.00
300.00
904.00
150.67
52.73

203.40

-----------------------------------------

90.00
12.00

200.00
150.00
452.00
75.33
26.37
101.70

Amount

-----------------------------------------

PLASTERWORKS.
98

3/4" thick DPC, in cement sand 1:2 finished with 2 coats hot tar and blinded with sand.
Per square
Materials
2.25
0.11
1 1/2
10
10

cwt
cube
gals
lbs
gallons

Labour
1 1/4
2 1/2

days
days

cement ( 50 Kg bags )
sand
bitumen
Firewood
water

mason
U / Sk labourer

605.00
5,600.00
85.00
2.00
2.25

700.00
400.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------99

3/4" thick plastering to wall in lime and sand 2 : 5 including floating with lime putty.
Per square
Materials
1.3
0.07
10

cwt
cube
gallons

Labour
1
1 3/4
Add

day
days
3%

slaked lime
sand
water

mason
U / Sk labourer
for scaffolding

35.00
6,500.00
2.25

700.00
400.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------100

5/8" thick plastering to wall in lime and sand 2 : 5 including floating with lime putty.

Per square
Materials
1.4
0.06
10

cwt
cube
gallons

Labour
1
1 1/2
Add

days
days
3%

cement ( 50 Kg bags )
sand
water

mason
U / Sk labourer
for scaffolding

605.00
6,500.00
2.25

700.00
400.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------101

3/8" thick plastering to soffit of slab in cement and sand 1 : 3 including


floating with lime putty.
Per square
Materials
0.8
0.16
0.03
5

cwt
cwt
cube
gallons

Labour
2 1/2
2 1/2
Add

days
days
3%

cement ( 50 Kg bags )
salked lime
sand
water

mason
U / Sk labourer
for scaffolding

605.00
35.00
6,500.00
2.25

700.00
400.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------102

3/8" thick plastering to sides and soffit of beams in cement and sand 1 : 3
including floating with lime putty.
Per Sqr.
Materials

0.8
0.16
0.03
5
Labour
2
2
Add

cwt
cwt
cube
gallons

days
days
3%

cement ( 50 Kg bags )
salked lime
sand
water

mason
U / Sk labourer
for scaffolding

605.00
35.00
6,500.00
2.25

700.00
400.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------103

5/8" thick plastering to wall in lime, cement and sand 1 : 1 : 5 finished semi
rough with wooden floating.
Per square
Materials
0.8
0.4
0.07
10

cwt
cwt
cube
gallons

Labour
1
1 1/4
Add

day
days
3%

cement ( 50 Kg bags )
salked lime
sand
water

mason
U / Sk labourer
for saffolding

605.00
35.00
6,500.00
2.25

700.00
400.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------104

5/8" thick plastering to wall in lime, cement and sand 1 : 1 : 5 finished


smooth with lime putty floating.
Per square
Materials
0.8

cwt

cement ( 50 Kg bags )

605.00

0.6
0.07
10
Labour
1
1 1/4
Add

cwt
cube
gallons

day
days
3%

salked lime
sand
water

35.00
6,500.00
2.25

mason
U / Sk labourer
for scaffolding

700.00
400.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------105

1/2" thick rendering in cement and sand 1 : 3 finished smooth.


Per square
Materials
1.07
0.05
10

cwt
cube
gallons

Labour
1
1 1/2
1/4

day
days
day

cement ( 50 Kg bags )
sand
water

605.00
6,500.00
2.25

mason
U / Sk labourer
U / Sk labourer ( curing )

700.00
400.00
400.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------106

1/2" thick rendering in cement and sand 1 : 2 in floors, finished smooth.


Per square
Materials
1.5
0.05
10
Labour
1

cwt
cube
gallons

day

cement ( 50 Kg bags )
sand
water

mason

605.00
6,500.00
2.25

700.00

1 1/2
1/4

days
day

U / Sk labourer
U / Sk labourer ( curing )

400.00
400.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------107

3/4" thick rendering in cement and sand 1 : 3 finished smooth.


Per square
Materials
1.75
0.08
10

cwt
cube
gallons

Labour
1 1/4
2
1/4

days
days
day

cement ( 50 Kg bags )
sand
water

605.00
6,500.00
2.25

mason
U / Sk labourer
U / Sk labourer ( curing )

700.00
400.00
400.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------108

3/4" thick rendering in cement and sand 1 : 2 in floors finished smooth.


Per square
Materials
2.25
0.08
10

cwt
cube
gallons

Labour
1 1/4
2
1/4

days
days
day

cement ( 50 Kg bags )
sand
water

mason
U / Sk labourer
U / Sk labourer ( curing )

Cost per square


35%

Overheads & Profit

605.00
6,500.00
2.25

700.00
400.00
400.00

Rate per square


--------------------------------------------------------------------------------------------------------------------------------------------------------------109

3/4" thick rendering in cement and sand 1 : 2 in coloured cement floors finished smooth.
Per square
Materials
2.25
0.05
5
10

cwt
cube
lbs
gallons

Labour
1 1/4
2
1/4

days
days
day

cement ( 50 Kg bags )
sand
powder pigment
water

mason
U / Sk labourer
U / Sk labourer ( curing )

605.00
6,500.00
2.25

700.00
400.00
400.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------110

1/2" x 6" skirting in cement and sand 1:3 projected or flush to walls finished
with floating including forming groove.
Per 10 L.ft
Materials
0.1
0.003
0.25

cwt
cube
lbs

cement ( 50 Kg bags )
sand
powdered pigment

Labour
3/8
5/16

days
days

mason
U / Sk labourer

Total per 10 L.ft


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

605.00
6,500.00
2.25

700.00
400.00

NOTE:
Where coloured skirting is not required , delete provision for powdered pigment.
--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

1,361.25
616.00
127.50
20.00
22.50

875.00
1,000.00
4,022.25
1,407.79
5,430.04

-----------------------------------------

45.50
455.00
22.50

700.00
700.00
42.00
1,965.00
687.75
2,652.75

Amount

-----------------------------------------

583.73

847.00
390.00
22.50

700.00
600.00
39.00
2,598.50
909.48
3,507.98

-----------------------------------------

484.00
5.60
195.00
11.25

1,750.00
1,000.00
82.50
3,528.35
1,234.92
4,763.27

Amount

-----------------------------------------

512.05

484.00
5.60
195.00
11.25

1,400.00
800.00
66.00
2,961.85
1,036.65
3,998.50

-----------------------------------------

484.00
14.00
455.00
22.50

700.00
500.00
36.00
2,211.50
774.03
2,985.53

Amount

-----------------------------------------

484.00
21.00

320.94

455.00
22.50

700.00
500.00
36.00
2,218.50
776.48
2,994.98

-----------------------------------------

647.35
325.00
22.50

700.00
600.00
100.00
2,394.85
838.20
3,233.05

Amount

-----------------------------------------

907.50
325.00
22.50

700.00
600.00

321.96

100.00
2,655.00
929.25
3,584.25

-----------------------------------------

1,058.75
520.00
22.50

875.00
800.00
100.00
3,376.25
1,181.69
4,557.94

Amount

-----------------------------------------

1,361.25
520.00
22.50

875.00
800.00
100.00
3,678.75
1,287.56

4,966.31

-----------------------------------------

1,361.25
325.00
11.25

875.00
800.00
100.00
3,472.50
1,215.38
4,687.88

Amount

-----------------------------------------

60.50
19.50
0.56

262.50
125.00
468.06
46.81
16.38
63.19

207.26

Amount

-----------------------------------------

PAINTING & DECORATING


111

Prepare and apply one coat of preservative (oil type) to structural timber
including touching up cut ends etc. after fixing.
Per square
Materials
2.75
1/10

ltr.
use

Wood preservative (oil type)


3" brush

338.00
140.00

Labour
3/4
1/2

day
day

painter
U / Sk labourer

800.00
600.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------112

Prepare surface of steel truss and apply two coats of anticorrosive primer.
Consider one square
Materials
2 1/4
0.15
1
1/8

ltr
ltr
No.
use

anti - corrosive primer


mineral turpentine or thinner
wire brush
2" brush

90.00
72.00
100.00
120.00

Labour
1 1/2
1 1/2

days
days

painter
U / Sk labourer

800.00
600.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------113

Apply one coat of anti-corrosive primer and two coats enamel paint on
already shop primed and erected steel roof truss.
Consider one square
Materials

0.2
1 1/3
0.2
1/5
Labour
2 1/2
1
Add
35%

ltr.
ltr.
ltr.
use

anti - corrosive primer


enamel paint
mineral turpentine or thinnner
2" brush

days
painter
day
U / Sk labourer
3%
for scaffolding
Cost per square
Overheads & Profit

90.00
321.00
72.00
120.00

800.00
600.00

Rate per square


--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------114

Perpare and apply two coats primer and finishing coat of enamel
paint to mild steel ( angle/flat ) gate
Consider 50 sq.ft
Materials
1 1/2
2/3
0.2
1/2
1/5

ltr.
ltr.
ltr.
use
use

anti - corrosive primer


enamel paint
mineral turpentine or thinnner
wire brush
2" brush

90.00
321.00
72.00
100.00
120.00

Labour
1/2
3/4

day
day

painter
U / Sk labourer

800.00
600.00

Total per 50 sq.ft


Cost per square
35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------115

Painting steel on new work with 2 coats of anti - corrosive paint


Per square
Materials
2/3
1/5

ltr
use

anti - corrosive paint


2" brush

90.00
100.00

Labour
1 1/2

days

painter

800.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------116

Painting new timber work with 2 coats wood preservative


Per square
Materials
1/2
1/5
Labour
1/2

gallon
use

day

Wood preservative
2" brush

338.00
120.00

painter

800.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------117

Preparing and painting wood work with primer and 2 coats enamel paint
Per square
Materials
3/4
2.5
1/10
2

ltr.
ltr.
use
nos

Wood primer
enamel paint ( 2 coats )
2" brush
sand papers

302.00
321.00
120.00
7.00

Labour
1 1/2
1/2

days
day

painter
U / Sk labourer

800.00
600.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------118

White or colour washing two coats in single storeyed building.


Per 10 squares
Materials
0.5
2
1/2
2
1/3
10

cwt
lbs
lb
ozs
use
gallons

Labour
2 1/2
2 1/2
Add

days
days
3%

boiled lime
salt
yellow ochre
blue
6" brush
water

125.00
2.00
35.00
50.00
250.00
2.25

painter
U / Sk labourer
for scaffolding

800.00
600.00

Total per 10.00 squares


Cost per square
35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------119

White or colour washing in two storeyed building.


Per 10 squares
( As per above )
Add
1/2
day
1/2
day
Add
3%

painter
U / Sk labourer
for scaffolding

800.00
600.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------120

Prepare and apply one coat of Alkali resistant primer and two
coats of emulsion paint to walls.

Per square
Materials
0.9
1.4
1
1/10
2

ltr
ltr
gallon
use
nos

primer
emulsion paint
water
6" brush
sand papers

300.00
259.00
2.25
250.00
7.00

Labour
1 1/4
Add

days
3%

painter
for scaffolding

800.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------121

Cement washing to walls of single storeyed building 2 coats.


Per 10 squares
Materials
5/8
1
5
Labour
2
2
Add

cwt
no.
gallons

days
days
3%

cement ( 50 Kg bags )
6" coir brush
water

790.00
60.00
2.25

painter
U / Sk labourer
for scaffolding

800.00
600.00

Total per 10.00 squares


Cost per square
35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------122

Painting walls with emulsion paint ( 2 coats )


Per square
1st coat2nd coat-

1/6
1/7
1/10

gallons
gallons
use

emulsion pint
emulsion pint
6" brush

259.00
259.00
250.00

1
Labour
3/4
Add

35%

gallons

water

day
painter
3%
for scaffolding
Cost per square

2.25
800.00

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------123

Prepare and apply one coat alkali resistant primer and two coats of emulsion
paint to soffit of slabs.
Consider 1.00 square
Materials
0.9
1.5
1/10

ltr
ltr
use

wall primer
emulsion paint
6" brush

300.00
259.00
250.00

Labour
1 3/4
Add

days
3%

painter
for scaffolding

800.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------124

Varnishing two coats with copal varnish after sand papering


Per square
Materials
1.8
1/3
2

ltr.
use
No.

varnish
3" brush
sand papers

327.00
140.00
7.00

Labour
1/2
1/2

day
day

painter
U / Sk labourer

800.00
600.00

Cost per square


35%

Overheads & Profit

Rate per square


--------------------------------------------------------------------------------------------------------------------------------------------------------------125

Wax polishing to timber in panels & floors.


Per square
Materials
3/4
6
1/10
1/2
Labour
3

lb
nos.
use
yards

hrs.

wax polish
sheets sand papers
floor brush
flannel cloth

U / Sk labourer

80.00
7.00
80.00
90.00

600.00

Cost per square


35%

Overheads & Profit


Rate per square

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

14.00

600.00
300.00
914.00
319.90
1,233.90

-----------------------------------------

202.50
10.80
100.00
15.00

1,200.00
900.00
2,428.30
849.91
3,278.21

-----------------------------------------

18.00

428.00
14.40
24.00

2,000.00
600.00
78.00
3,162.40
1,106.84
4,269.24

Amount

-----------------------------------------

135.00
214.00
14.40
50.00
24.00

400.00
450.00
1,287.40
2,574.80
901.18
3,475.98

-----------------------------------------

60.00
20.00

458.94

1,200.00
1,280.00
448.00
1,728.00

-----------------------------------------

169.00
24.00

400.00
593.00
207.55
800.55

Amount

-----------------------------------------

226.50
802.50
12.00
14.00

1,200.00
300.00
2,555.00
894.25
3,449.25

-----------------------------------------

187.50
4.00
17.50
6.25
83.33
22.50

2,000.00
1,500.00
105.00
3,926.08
392.61
137.41
530.02

-----------------------------------------

321.08
400.00
300.00
21.00
1,042.08
364.73
1,406.81

Amount

-----------------------------------------

270.00
362.60
2.25
25.00
14.00

1,000.00
30.00
1,703.85
596.35
2,300.20

-----------------------------------------

493.75
60.00
11.25

1,600.00
1,200.00
84.00
3,449.00
344.90
120.72
465.62

-----------------------------------------

43.17
37.00
25.00
2.25

247.27

600.00
18.00
725.42
253.90
979.31

Amount

-----------------------------------------

270.00
388.50
25.00

1,400.00
42.00
2,125.50
743.93
2,869.43

-----------------------------------------

588.60
46.67
14.00

400.00
300.00
1,349.27
472.24

105.28

1,821.51

-----------------------------------------

60.00
42.00
8.00
45.00

225.00
380.00
133.00
513.00

Amount

-----------------------------------------

PLUMBING - PVC PIPES


126

1/2" diameter PVC pipes fixed to walls ( specials paid separately )


Per 10 L.ft
Materials
13
3
2
Labour
1
1

L.ft
Nos
grms

pipes
clips and nails
solvent cement

7.45
2.00
0.65

hr
hr

plumber
U / Sk labourer

800.00
600.00

Total per 10.00 L.ft


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------127

3/4" diameter PVC pipes to walls ( specials paid separately )


Per 10 L.ft
Materials
13
3
3
Labour
1
1

L.ft
Nos
grms

pipes
clips and nails
solvent cement

12.60
2.00
0.65

hr
hr

plumber
U / Sk labourer

800.00
600.00

Total per 10.00 L.ft


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------128

1" diameter PVC pipes fixed to walls ( specials paid separately )

Per 100 L.ft


Materials
100
Add
8
32
35
Labour
1/2
1/2

L.ft
5%
Nos
grns.
Nos

pipes
for wastage
1" dia sockets
Solvent cement
clips and nails

18.70

day
day

plumber
U / Sk labourer

800.00
600.00

12.35
0.65
2.00

Total per 100 L.ft


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------129

1 1/4" diameter PVC pipes fixed to walls ( specials paid separately )


Per 100 L.ft
Materials
100
Add
8
48
35
Labour
3/4
3/4

L.ft
5%
Nos
grns.
Nos

day
day

pipes
for wastage
1 1 / 4" dia sockets
Solvent cement
clips and nails

plumber
U / Sk labourer

31.25
17.40
0.65
2.00

800.00
600.00

Total per 100 L.ft


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------130

1 1/2" diameter PVC pipes laid to walls ( specials paid separately )

Per 100 L.ft


Materials
100
Add
8
64
35

L.ft
5%
Nos
grns.
Nos

Labour
3/4
3/4

day
day

pipes
for wastage
1 1 / 2" dia sockets
Solvent cement
clips and nails

plumber
U / Sk labourer

46.40
26.35
0.65
2.00

800.00
600.00

Total per 100 L.ft


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------131

2" diameter PVC pipes laid to walls ( specials paid separately )


Per 100 L.ft
Materials
100
Add
8
112
35
Labour
3/4
3/4

L.ft
5%
Nos
grns.
Nos

pipes
for wastage
2" dia sockets
Solvent cement
clips and nails

77.15

day
day

plumber
U / Sk labourer

800.00
600.00

46.35
0.65
5.00

Total per 100 L.ft


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------132

3" diameter PVC pipes laid to walls ( specials paid separately )

Per 100 L.ft


Materials
100
Add
8
200
35
Labour
1
1

L.ft
5%
Nos
grns.
Nos

pipes
for wastage
3" dia sockets
Solvent cement
clips and nails

180.80

day
day

plumber
U / Sk labourer

800.00
600.00

115.00
0.65
5.00

Total per 100 L.ft


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------133

Excavation for laying 1/2" to 3" diameter PVC pipes in ground not less than
1'-6" deep, back filling & compacting.
Per 100 L.ft
Labour
2 1/4

days

U / Sk labourer

600.00

Total per 100 L.ft


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------134

Chasing brickwork for laying 1/2" to 1 1/2" dia PVC pipes and making good
average depth 2". ( Pipes and specials paid separately )
Per 100 L.ft
Materials
0.1
0.01

cwt
cubes

cement ( 50 Kg bags )
sand

790.00
4,500.00

Labour
3
3

days
days

mason
U / Sk labourer

800.00
600.00

Total per 100 L.ft


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------135

Chasing brickwork for laying 1 1/2" to 3" dia PVC pipes and making good
average depth 3". ( Pipes and specials paid separately )
Per 100 L.ft
Materials
0.2
0.03

cwt
cubes

Labour
3 1/2
3 1/2

days
days

cement ( 50 Kg bags )
sand

mason
U / Sk labourer

790.00
4,500.00

800.00
600.00

Total per 100 L.ft


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------136

1/2" dia PVC specials viz - elbows / bends / sockets.


Per 10 specials
Materials
10
20
Labour
2

No.
grms.

hrs.

1/2" elbows / bends / sockets


solvent cement

plumber

Total per 10 Nos.


Cost per no.

5.66
0.65

800.00

35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------137

3/4" dia PVC specials viz - elbows / bends / sockets.


Per 10 specials
Materials
10
30
Labour
2

No.
grms.

hrs.

3/4" elbows / bends / sockets


solvent cement

plumber

8.75
0.65

800.00

Total per 10 Nos.


Cost per No.
35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------138

1" dia PVC specials viz - elbows / bends / sockets.


Per 10 specials
Materials
10
40
Labour
2

No.
grms.

hrs.

1" elbows / bends / sockets


solvent cement

plumber

12.10
0.65

800.00

Total per 10 Nos.


Cost per No.
35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------139

1 1/4" dia PVC specials viz - elbows / bends / sockets.

Per 10 specials
Materials
10
60
Labour
2

No.
grms.

hrs.

1 1/4" elbows / bends / sockets


solvent cement

plumber

22.00
0.65

800.00

Total per 10 Nos.


Cost per No.
35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------140

1 1/2" dia PVC specials viz - elbows / bends / sockets.


Per 10 specials
Materials
10
80

No.
grms.

1 1/2" elbows / bends / sockets


solvent cement

Labour
1/2

days

plumber

42.40
0.65

800.00

Total per 10 Nos.


Cost per No.
35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------141

2" dia PVC specials viz - elbows / bends / sockets.


Per 10 specials
Materials
10
100
Labour
1/2

Nos.
grms.

day

2" elbows / bends / sockets


solvent cement

plumber

64.10
0.65

800.00

Total per 10 Nos.


Cost per No.
35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------142

2 1/2" dia PVC specials viz - elbows / bends / sockets.


Per 10 specials
Materials
10
200
Labour
1/2

Nos.
grms.

day

2 1/2" elbows / bends / sockets


solvent cement

115.00
0.65

plumber

800.00

Total per 10 Nos.


Cost per No.
35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------143

3" dia PVC specials viz - elbows / bends / sockets.


Per 10 specials
Materials
10
240
Labour
1/2

Nos.
grms.

day

3" elbows / bends / sockets


solvent cement

215.00
0.65

plumber

800.00

Total per 10 Nos.


Cost per No.
35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------144

1/2" dia PVC specials viz -Tees


Per 10 Tees
Materials
10
30

Nos.
grms.

Labour
1/2

day

1/2" dia Tees


solvent cement

plumber

7.35
0.65

800.00

Total per 10 Tees.


Cost per No.
35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------145

3/4" dia PVC specials viz -Tees


Per 10 Tees
Materials
10
45

Nos.
grms.

Labour
1/2

day

3/4" dia Tees


solvent cement

plumber

10.40
0.65

800.00

Total per 10 Tees.


Cost per No.
35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------146

1" dia PVC specials viz -Tees


Per 10 Tees
Materials

10
60

Nos.
grms.

Labour
1/2

day

1" dia Tees


solvent cement

plumber

20.00
0.65

800.00

Total per 10 Tees


Cost per No.
35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------147

1 1/4" dia PVC specials viz -Tees


Per 10 Tees
Materials
10
90

Nos.
grms.

Labour
1/2

day

1 3/4" dia Tees


solvent cement

plumber

26.70
0.65

800.00

Total per 10 Tees


Cost per No.
35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------148

1 1/2" dia PVC specials viz -Tees


Per 10 Tees
Materials
10
120
Labour
1

Nos.
grms.

day

1 1/2" dia Tees


solvent cement

plumber

Total per 10 tees.


Cost per No.

49.75
0.65

800.00

35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------149

2" dia PVC specials viz -Tees


Per 10 Tees
Materials
10
210

Nos.
grms.

Labour
1

day

2" dia Tees


solvent cement

plumber

75.75
0.65

800.00

Total per 10 Tees


Cost per No.
35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------150

2 1/2" dia PVC specials viz -Tees


Per 10 Tees
Materials
10
300
Labour
1

Nos.
grms.

day

2 1/2" dia Tees


solvent cement

165.00
0.65

plumber

800.00

Total per 10 Tees.


Cost per No.
35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------151

3" dia PVC specials viz -Tees

Per 10 Tees
Materials
10
360

Nos.
grms.

3" dia Tees


solvent cement

366.70
0.65

Labour
1 1/2

days

plumber

800.00

Total per 10 tees


Cost per No.
35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

96.85
6.00
1.30

100.00
75.00
279.15
27.92
9.77
37.69

-----------------------------------------

163.80
6.00
1.95

100.00
75.00
346.75
34.68
12.14
46.81

Amount

-----------------------------------------

1,870.00
93.50
98.80
20.80
70.00

400.00
300.00
2,853.10
28.53
9.99
38.52

-----------------------------------------

3,125.00
156.25
139.20
31.20
70.00

600.00
450.00
4,571.65
45.72
16.00
61.72

Amount

-----------------------------------------

4,640.00
232.00
210.80
41.60
70.00

600.00
450.00
6,244.40
62.44
21.86
84.30

-----------------------------------------

7,715.00
385.75
370.80
72.80
175.00

600.00
450.00
9,769.35
97.69
34.19
131.89

Amount

-----------------------------------------

#######
904.00
920.00
130.00
175.00

800.00
600.00
#######
216.09
75.63
291.72

-----------------------------------------

1,350.00
1,350.00
13.50
4.73
18.23

Amount

-----------------------------------------

79.00
45.00

2,400.00
1,800.00
4,324.00
43.24
15.13
58.37

-----------------------------------------

158.00
135.00

2,800.00
2,100.00
5,193.00
51.93
18.18
70.11

-----------------------------------------

56.60
13.00

200.00
269.60
26.96
9.44

36.40

Amount

-----------------------------------------

87.50
19.50

200.00
307.00
30.70
10.75
41.45

-----------------------------------------

121.00
26.00

200.00
347.00
34.70
12.15
46.85

-----------------------------------------

220.00
39.00

200.00
459.00
45.90
16.07
61.97

Amount

-----------------------------------------

424.00
52.00

400.00
876.00
87.60
30.66
118.26

-----------------------------------------

641.00
65.00

400.00

1,106.00
110.60
38.71
149.31

-----------------------------------------

1,150.00
130.00

400.00
1,680.00
168.00
58.80
226.80

Amount

-----------------------------------------

2,150.00
156.00

400.00
2,706.00
270.60
94.71
365.31

-----------------------------------------

73.50
19.50

400.00
493.00
49.30
17.26
66.56

-----------------------------------------

104.00
29.25

400.00
533.25
53.33
18.66
71.99

Amount

-----------------------------------------

200.00

39.00

400.00
639.00
63.90
22.37
86.27

-----------------------------------------

267.00
58.50

400.00
725.50
72.55
25.39
97.94

-----------------------------------------

497.50
78.00

800.00
1,375.50
137.55
48.14

185.69

Amount

-----------------------------------------

757.50
136.50

800.00
1,694.00
169.40
59.29
228.69

-----------------------------------------

1,650.00
195.00

800.00
2,645.00
264.50
92.58
357.08

-----------------------------------------

3,667.00
234.00

1,200.00
5,101.00
510.10
178.54
688.64

Amount

-----------------------------------------

EXTERNAL DRAINAGE (EW PIPES)


152

4" dia glazed earthenware pipes laid on 6" thick bedding in cement concrete
1:3:6(1 1/2") including excavation average 2'-0" depth, backfilling with
selected excavated materials and concrete haunching to joints.
Per 100 L.ft
Materials
50
0.75
2
0.5
4

Nos
cubes
lbs
cwt
cubes

4" dia EW pipes


cement concrete 1:3:6 (1 1/2" )
yarn
cement ( jointing )
excavation

55.00
20,889.17
9.50
790.00
1,350.00

Labour
Laying concrete bedding 1 1/2
days
U / Sk labourer

600.00

Laying and testing pipes 2


days
plumber
1 1/2
days
U / Sk labourer

800.00
600.00

Backfilling 2 1/2

600.00

days

U / Sk labourer

Total per 100L.ft


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------PLUMBING (C I PIPES)
153

4' dia C.I. Soil/vent pipe fixed vertically to walls jointed with cement caulking.
(Specials measured separately )
Per 6'-0" length
Materials
6
Add
5/16
1
2

L.ft
10%
lbs
No
Nos

4' dia C.I. Pipe


for wastage
yarn
timber plug 6" x 6" x 2"
3" iron screws

115.00
9.50
10.00
1.50

2
Labour
1/4
1/4
Add

lbs

days
days
5%

cement

790.00

plumber
U / Sk labourer
Scaffolding

800.00
600.00

Total for 6 L.ft


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------154

4' dia C.I. pipes fixed to walls jointed with lead caulking. (Specials measured separately)
Per 6'-0" length
Materials
6
Add
5/16
1
2
6
1/16

L.ft
10%
lbs
No
Nos
lbs
cwt

4" dia C.I. Pipe


for wastage
yarn
wood plug 6" x 6" x 2"
3" iron screws
lead
firewood

115.00

Labour
1/4
1/4
Add
Add

day
day
10%
5%

plumber
U / Sk labourer
for sundries in cement and sand
for Scaffolding

800.00
600.00

9.50
10.00
1.50
35.00
2.00

Total for 6 L.ft.


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

2,750.00
15,666.88
19.00
395.00
5,400.00

900.00

1,600.00
900.00

1,500.00
29,130.88
291.31
101.96
393.27

Amount

---------------------------------------

690.00
69.00
2.97
10.00
3.00
14.36

200.00
150.00
17.50
1,156.83
192.81
67.48
260.29

---------------------------------------

690.00
69.00
2.97
10.00
3.00
210.00
14.00

200.00
150.00
35.00
17.50
1,401.47
233.58
81.75
315.33

Amount

---------------------------------------

1,034.28

MANHOLES & GULLEYS


155

4" dia stoneware gulley with 6" x 6" x 6" gulley box including excavation, 4" thick
cement concrete 1:2:4(3/4") base, surrounded by 4 1/2" thick brickwork in cement
and sand 1:5 extended 6" above top of gulley box including making connection,
1/2" cement and sand 1:2 rendering internally and exposed faces finished smooth
with neat cement floating and providing G.I. grating on top of gulley.
Per No.
Materials
1
4
5.5
0.8
1
1

No
cu.ft
sq.ft
cu.ft
sq.ft
No

4" S.W. gulley


excavation
4 1/2" brickwork
cement concrete 1:2:4(3/4")
1/2" cement rendering 1:2
4" G.I. grating

Labour
1/2
1/2

day
day

mason
U / Sk labourer

550.00
1,350.00
7,863.25
25,806.67
2,655.00
25.00

800.00
600.00

Cost per No.


35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------156

Manhole 2'-0"x2'-0" internally with invert depth not exceeding 2'-0" including excavation,
backfilling 6" cement concrete 1:2:4 ( 3/4" ) base with 3/8" dia. mild steel rods at
4" centres bothways, forming channels and benching in similar concrete, 4 1/2" walls
in brick in cement 1:5, 1/2" thick cement and sand 1:2 rendering internally and exposed
surfaces including channels, benching and 2" thick RCC removable cover slab
2'-3"x2'-3" inlet and outlet connection al complete to working order
Per No.
Materials
35
7
33
28
1
Labour
1 1/2
2 1/2

cu.ft
cu.ft
sq.ft
sq.ft
No

excavation
cement concrete 1:2:4( 3/4' ) in
base & channels
4 1/2" brickwork in cement 1 : 5
1/2" cement rendering 1 : 2
RCC cover slab

days
days

mason
U / Sk labourer

Cost per No.

1,350.00
25,806.67
7,863.25
2,655.00
500.00

800.00
600.00

35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

550.00
54.00
432.48
206.45
26.55
25.00

400.00
300.00
1,994.48
698.07
2,692.55

-------------------------------------

472.50
1,806.47
2,594.87
743.40
500.00

1,200.00
1,500.00
8,817.24

3,086.03
#######

Amount

-------------------------------------

SANITARY FITTINGS.
157

22"x16" glazed fireclay wash basin with 1/2" dia Chromium plated pillar tap,
waste plug, Chromium plated waste chain and stay, including fixing wash basin
on brackets. ( water supply and waste water connection measured separately ).
Per No.
Materials
1
1
4
6
2

No
No
Nos
Nos
lbs

wash basin complete with brackets.


1/2" tap with waste plug and chain
wooden plugs
1 1/2" brass screws
cement

Labour
1/2
1

day
day

mason
U / Sk labourer

3,950.00
690.00
2.00
3.60
790.00

800.00
600.00

Cost per No.


35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------158

Sink 24"x15"x7" overall vitreous China with rubber plug and Chromium plated chain
waste carried on iron brackets painted and fixed to walls. ( Water supply and waste
water connection measured separately ).
Per No.
Materials
1
2
2
2
8

No
Nos
lbs
Nos
Nos

sink 24" x 15" x 7"


L iron bracktes
cement
tapered wooden blocks 2" thick
1 1/2" brass screws

Labour
1/2
1/2

day
day

mason
U / Sk labourer

3,500.00
125.00
790.00
2.00
3.60

800.00
600.00

Cost per No.


35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate

--------------------------------------------------------------------------------------------------------------------------------------------------------------159

Closet pedestal type with L / L flushing cistern, flush pipe double plastic seat cover,
1/2" dia stop cock , trap supplied & fixed complete to working order.
Per No.
Materials
1
1
2
1/4
2

No.
No.
lbs
cu.ft
Nos.

low level suite complete


1/2" dia stop cock
cement
sand
1 1/2" brass screws

Labour
1/4
1
1

day
day
day

mason
plumber
U / Sk albourer

4,500.00
250.00
790.00
4,500.00
3.60

800.00
800.00
600.00

Cost per No.


35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------160

Closet squatting type with trap including high level cistern fixed complete with flush pipe
and 1/2" dia stop cock, all complete to working order.
Per No.
Materials
1
1

No.
No.

1
5
1
1
1/4
1/2
1/4

No.
No.
doz.
No.
cwt
cu.ft
cu.ft

squatting pan with trap


2 gallons C.I. Cistern with 1 1/4" flush
pipe chain and overflow pipe
clip
wooden plugs
1 1/2" brass screws
1/2" stop cock
cement
1" metal
sand

Labour
1/2
1
1

day
day
day

mason
plumber
U / Sk labourer

Cost per No.


35%

Overheads & Profit

950.00
1,050.00
3.50
2.00
3.60
250.00
790.00
7,000.00
4,500.00

800.00
800.00
600.00

Rate per No.


--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------161

Vitreous China bidet suite fixed complete to working order


Per No.
Materials
1

No.

bidet

Labour
1
1

day
day

plumber
U / Sk labourer

4,750.00

800.00
600.00

Cost per No.


35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------162

4 No. Bowl type urinal with trap and 2 glas capacity automatic flushing cistern and
spreaders complete to working prders.
Per No.
Materials
4
1
8
1
1
4
4
1/8

Nos.
No.
Nos.
No.
No.
Nos.
lbs
cu.ft

Urinals Bowls
2 gallons cistern
rowl
plugs
spreader
wooden plugs ( for cistern )
1 1/2" brass screws
cement
sand

Labour
1/4
1
1

day
day
day

mason
plumber
U / Sk labourer

Total per 4 Nos.


Cost per No.
35%

Overheads & Profit

1,200.00
1,050.00
3.00
150.00
2.00
3.60
790.00
4,500.00

800.00
800.00
600.00

Rate per No.


--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
---------------------------------------------------------------------------------------------------------------------------------------------------------------

3,950.00
690.00
8.00
21.60
14.36

400.00
600.00
5,683.96
1,989.39
7,673.35

-----------------------------------------

3,500.00
250.00
14.36
4.00
28.80

400.00
300.00
4,497.16
1,574.01
6,071.17

Amount

-----------------------------------------

4,500.00
250.00
14.36
11.25
7.20

200.00
800.00
600.00
6,382.81
2,233.98
8,616.80

-----------------------------------------

950.00
1,050.00
3.50
10.00
43.20
250.00
1.80
35.00
11.25

400.00
800.00
600.00
4,154.75
1,454.16

5,608.91

Amount

-----------------------------------------

4,750.00

800.00
600.00
6,150.00
2,152.50
8,302.50

-----------------------------------------

4,800.00
1,050.00
24.00
150.00
2.00
14.40
28.73
5.63

200.00
800.00
600.00
7,674.75
1,918.69
671.54
2,590.23

Amount

-----------------------------------------

GUTTERS & DOWN PIPES


163

6" dia half round PVC eaves gutter fixed to timber valance board including gutter joiner
and brackets fixed at 18" centres. ( Other specials paid separately ).
Consider 24 L.ft
Materials
2
1
17
34
20

Nos.
No.
Nos.
Nos.
grms

6" dia eaves gutter lengths


joiner
gutter brackets
3/4" brass screws
solvent cement

480.00
49.00
8.50
1.50
0.65

Labour
1/2
1/2
Add

days
days
5%

plumber
U / Sk labourer
Scaffolding

800.00
600.00

Total per 24 L.ft


Cost per L.ft.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------164

6" dia PVC gutter head


Consider 1 No. gutter head
Materials
1
2
2
12
4
Labour
1/8
1/8
Add

No
Nos
Nos
grms
Nos

day
day
5%

PVC gutter head


gutter joiners
gutter brackets
solvent cement
3/4" brass screws

200.00
49.00
8.50
0.65
1.50

plumber
U / Sk labourer
Scaffolding

800.00
600.00

Cost per No.


35%

Overheads & Profit


Rate per No.

---------------------------------------------------------------------------------------------------------------------------------------------------------------

Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------165

6" dia PVC mitres


Consider 1 No. mitre
Materials
1
2
2
12
4
Labour
1/8
1/8
Add

No
Nos
Nos
grms
Nos

day
day
5%

PVC mitre
gutter joiners
brackets
solvent cement
3/4" brass screws

141.70
49.00
8.50
0.65
1.50

plumber
U / Sk labourer
Scaffolding

800.00
600.00

Cost per No.


35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------166

6" dia PVC end caps


Consider 1 No. end cap
Materials
1
12

No.
grms

end cap
solvent cement

29.50
0.65

Labour
1/16
1/16
Add

day
day
5%

plumber
U / Sk labourer
Scaffolding

800.00
600.00

Cost per No.


35%

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------Item
Description
Rate
--------------------------------------------------------------------------------------------------------------------------------------------------------------167

3 1/2" dia PVC rain water down pipes fixed to brick wall with wooden plugs buried
in wall. ( Specials measured separately )

Consider 24 L.ft pipe length


Materials
2
1
4
8
30

Nos.
No.
Nos.
Nos.
grms

3 1/2' dia pipe lengths


3 1/2" joiner
PVC straps
brass screws 1" long
solvent cement

360.00
35.00
8.00
2.50
0.65

Labour
1/3
1/3
Add

days
day
5%

plumber
U / Sk labourer
Scaffolding

800.00
600.00

Total per 24 L.ft


Cost per No.
35%

Overheads & Profit


Rate per L.ft

--------------------------------------------------------------------------------------------------------------------------------------------------------------168

3 1/2" dia PVC Elbow


Consider 1 No. Elbow
Materials
1
32
Labour
1/16
1/16
Add

35%

No
grms

60 deg. - 80 deg. Elbow


solvent cement

day
plumber
day
U / Sk labourer
5%
Scaffolding
Cost per No.

50.00
0.65

800.00
600.00

Overheads & Profit


Rate per No.

--------------------------------------------------------------------------------------------------------------------------------------------------------------169

3 1/2" dia PVC shoe


Consider 1 No. Shoe
Materials
1
15

No
grms

60 deg. - 80 deg. Shoe


solvent cement

45.00
0.65

Labour
1/16
1/16
Add

35%

day
plumber
day
U / Sk labourer
5%
Scaffolding
Cost per No.
Overheads & Profit
Rate per No.

800.00
600.00

960.00
49.00
144.50
51.00
13.00

400.00
300.00
35.00
799.00
33.29
11.65
44.94

-----------------------------------------

200.00
98.00
17.00
7.80
6.00

100.00
75.00
8.75
197.55
69.14
266.69

Amount

-----------------------------------------

141.70
98.00
17.00
7.80
6.00

100.00
75.00
8.75
197.55
69.14
266.69

-----------------------------------------

29.50
7.80

50.00
37.50
4.38
129.18
45.21
174.39

Amount

-----------------------------------------

720.00
35.00
32.00
20.00
19.50

266.67
200.00
23.33
529.50
22.06
7.72
29.78

-----------------------------------------

50.00
20.80

50.00
37.50
4.38
162.68
56.94
219.61

-----------------------------------------

45.00
9.75

50.00
37.50
4.38
146.63
51.32
197.94

0.9

0.8

0.7

0.6

0.5

0.4

0.3

0.2

0.1

0
Excavation in trenches for walls / column pits in soft / loose soil up to 5'-0" deep and

No

Description

Rate

Unit

EXCAVATION
1

Removing top soil to a depth not exceeding 6" & depositing as directed within site.

810.00

Excavation over site to reduce level, in any material except rock requiring blasting
includingdepositing and levelling as directed up to a distance not exceeding 30'- 0"

1,316.25

cube

945.00

cube

Excavation in trenches for walls / column pits in ordinary soil up to 5'-0" deep
and depositing excavated material to a distance not exceeding 30'-0".

1,822.50

cube

Excavation in trenches for walls / column pits in Hard / dense soil up to a depth
of 5'-0" and depositing excavated material up to a distance not exceeding 30'-0"

2,835.00

cube

Excavation in trenches for walls / column pits in Mud / wet soil up to a depth
of 5'-0" and depositing excavated material to a distance not exceeding 30'-0".

3,199.50

cube

Excavation in trenches for walls / column pits in soft disintegrated rock


(not requiring blasting ) to a depth of 5'-0" and depositing excavated
material to a distance not exceeding 30'-0".

2,025.00

cube

Excavation in trenches for wall / column pits in Hard rock requiring blasting up to a
depth of 5'-0' and depositing excavated material to a distance not exceeding 30'-0".

3,295.35

cube

Benching rock in foundation in 3" - 6" steps.(Blasting prohibited)

3,240.00

sq.ft

1,761.75

square

Excavation in trenches for walls / column pits in soft / loose soil up to 5'-0" deep and
depositing excavated material to a distance not exceeding 30'-0" (Earth work support
to be paid separately where necessary).

10 Anti - termite treatment on excavated foundation and compacted soil under floors.
11 Backfilling to trenches with selected earth available at site

square

810.00

cube

12 Back filling to trenches with imported material.

2,006.10

cube

13 Filling under floors including levelling, watering & compacting in 3" layers with
available and selected earth at site.

1,620.00

cube

14 Filling under floors including levelling, watering & compacting in 3" layers
with imported selected earth.

2,613.60

cube

15 Cutting turf sods, loading to hand carts and transporting upto 30 yards, laying
and watering for 30 days. (Royalty for turf, pegging and transport
beyond 30 yards paid separately )

3,827.25

cube

16 Earthwork support ( open planking ) in trenches up to a depth of 5'-0".

5,647.50

square

17 Earthwork support (close planking) in trenches up to 5'-0" depth.

10,350.00

square

18 Earthwork support (close planking) in deep excavation in trenches up to 15'-0" depth.

11,820.00

square

No

Description

Rate

Unit

19 Mixing concrete 1:3:6 (1 1/2")

20,889.17

cube

20 Mixing concrete 1 : 2 1/2 : 5 (1")

22,751.67

cube

21 Mixing concrete 1 : 2 : 4 ( 3/4" )

25,806.67

cube

22 Mixing concrete 1: 1 1/2 : 3 ( 3/4")

29,014.17

cube

23 Mixing concrete 1 : 1 : 2 ( 3/4" )

36,586.67

cube

24 2" thick cement concrete 1:3:6(1 1/2") screed in foundation at depths


not exceeding 5'-0".

5,710.07

square

25 3" thick cement concrete 1:3:6(1 1/2") screed in foundation at depths


not exceeding 5'-0".

8,497.60

square

26 6" thick cement concrete floor in ( mass concrete )1:3:6(1 1/2")

16,965.20

square

27 Cement concrete 1:2:4(3/4") in 4 1/2" x 6" columns in ground floor.

58,431.25

cube

28 Cement concrete 1:2:4(3/4") in 6" x 6" columns in ground floor.

60,567.90

cube

29 Cement concrete 1:2:4(3/4") in 9" x 9" columns in ground floor.

57,897.90

cube

30 Cement concrete 1:2:4(3/4") in 12" x 12" columns in ground floor.

54,484.34

cube

31 Cement concrete 1:2:4(3/4") in 13 1/2" x 13 1/2" columns in ground floor.

55,044.19

cube

32 Cement concrete 1:2:4(3/4") in 6" x 6" beam up to 1st floor level.

61,195.95

cube

33 Cement concrete 1:2:4(3/4") in 9" x 6" beam up to 1st floor level.

62,285.40

cube

34 Cement concrete 1:2:4(3/4") in 9" x 9" beam up to 1st floor level.

61,632.90

cube

35 5" thick R.C.C 1:2:4(3/4") slab in 1st floor

58,309.65

square

36 6" thick R.C.C 1:2:4(3/4") slab in 1st floor

58,174.65

square

37 Cement concrete 1:2:4(3/4") in 4 1/2" x 6" lintels in ground floor

59,098.48

cube

38 Cement concrete 1:2:4(3/4") in 9" x 9" lintels in ground floor

61,430.40

cube

39 Cement concrete 1:2:4(3/4") in 9" x 12" lintels in ground floor

61,280.40

cube

40 Cement concrete 1:2:4(3/4") in 12" x 15" lintels in ground floor

60,830.40

cube

41 Sawn timber formwork to 9" x 9" cement concrete column in ground floor.

12,571.56

square

42 Sawn timber formwork for concrete beams in ground floor.

15,340.56

square

8,327.07

square

12,442.28

cwt

CONCRETE

TIMBER FORMWORK

43 Sawn timber formwork for underside of first floor slab.


REINFORCEMENTS
44 Mild steel / Tor steel reinforcement to lintels, slabs, beams or columns bent
to shape laid in position and tied with G . I . wire as directed.

No

Description

Rate

Unit

45 Brick work in cement & sand 1:5 in foundation up to D. P. C. level.

26,080.31

cube

46 Brick work in cement & sand 1:8 in foundation up to D. P. C. level.

25,062.19

cube

47 Brick work in cement and sand 1:5 in 4 1/2" thick walls in ground floor

10,615.39

square

48 9" thick brick wall in cement & sand 1:5 in ground floor

20,438.33

square

49 Brickwork 13 1/2" thick in cement & sand 1:5 in superstructure in ground floor

30,556.24

square

50 9" thick brick wall in cement & sand 1:5 in superstructure in ground floor

19,086.98

square

51 4 1/2" thick brick wall ( wire cut ) in cement & sand 1:5 in ground floor

14,347.13

square

52 9" thick brick in cement & sand 1:5 with wire cut bricks
( Facing to brickwork measured separately )

27,890.87

square

53 13 1/2" thick brick wall ( wire cut ) in cement & sand 1:5 in ground floor
( Facing to brickwork measured separately )

42,686.60

square

54 Extra over for facing including raised pointing 1 / 8" thick in cement and sand 1:1
mixture in ground floor ( Facing to brickwork measured separately )

14,887.13

square

7,307.89

square

BRICKWORK

55 3" thick brick paved floor in lime sand mortar 2 : 5 in ground floor
56 Steps 1'-11/2" x 0'-6" in brick in cement and sand 1:5 with 1/2" thick cement
and sand 1:2 rendering including necessary excavation.

288.06

L.ft

57 Brick drains in cement and sand 1 : 5, 9" wide and 6" - 9" average depth including
cement rendering1/2" thick 1:2 to exposed faces with 1'-6" ramp including
necessary excavation

480.87

L.ft

58 Brick drains in cement and sand 1 : 5, 9" wide and 6" - 9" average depth including
cement rendering 1/2" thick 1:2 to exposed faces without ramp including
necessary excavation.

409.29

L.ft

BLOCK WORK
59 8" thick Hollow blockwork in cement and sand mortar 1 : 5 in ground floor
(cavities unfilled)

15,238.13

square

9,476.73

square

61 Random Rubble masonry in cement motar 1 : 5 in foundation

25,180.88

cube

62 Random Rubble masonry in cement motar 1 : 5 in supersturcture

26,846.78

cube

12,571.20

square

64 Glazed tiles fixed to walls including bedding in cement mortar 1 : 2 and


raking inground floor. (Specials measured separately ).

20,857.50

square

65 Terrazzo floor tiles on 1/2" thick cement and sand 1 : 2 in ground floor

15,138.23

square

60 4" thick Hollow block masonry in cement and sand mortar 1:5 with cavity unfilled.
RANDOM RUBBLE MASONRY

TILE WORKS
63 Pressed floor tiles bedded in 1/2" cement mortar 1 : 2 and pointing in neat cement in
ground floor.
WALL TILING & TERRAZZO TILES

No

Description

Rate

Unit

16,394.40

square

67 Roof covering with calicut pattern clay tiles in single storeyed building
(Timber frame work & ridge covering measured separately)

2,632.50

square

68 Timber framework for corrugated asbestos sheet roof in single storeyed building.

9,623.44

square

69 Roof covering with corrugated asbestos sheets ( Timber frame work & ridge covering
measured separately )

5,250.00

square

70 One layer half round clay tiles over corrugated asbestos roof covering

6,007.50

square

ROOF WORK
66 Timber framework for calicut pattern tile hip roof in single storey building consisting
of wall plate,beam,ridge plate,rafters etc.( Preservative treatment to be
measured separately )

71 Asbestos close fittings ridging fixed complete with roofing screws or bols ( hook )

161.03

L.ft

72 Ridging covering with calicut pattren ridge tiles bedded in cement lime mortar 1 : 1 : 4

162.26

L.ft

73 3/4" x 9" high valance board fixed with brass screws to ends of rafters (for tile roofing)

209.65

L.ft

74 3/4"x 9" high valance board fixed with brass screws at 2'-0" centres to sides of rafters.

208.68

L.ft

75 18 B.W.G.( 1.2 mm ) galvanised iron sheet valley gutter 3'-0" girth overall
once bent with end laps not less than 9" width including 3/4" tongued and grooved
planks laid to slope and profile on timber and profile on members.

776.41

L.ft

76 18 B.W.G. ( 1.2 mm ) galvanised iron flashing 1'-6" girth overall 3 times bent with
end laps notless than 6", lead soldered, turned and tucked up to not less than 6"
in to chase cut in wall and pointed in cement morter 1:2 lower end dressed over
roof covering not less than 1'-0" wide.

336.40

L.ft

ROOF PLUMBING

CEILING WORK
77 Timber framework for 4'-0" x 4'-0" flat asbestos ceiling ( sheet measured separately ),
comprising of 4" x 2" joists and 2" x 2" bearers in class I timber.

10,582.79

square

78 Horizontal ceiling lining using 4' 0" x 4' 0" flat asbestos cement sheet fixed withand
including beading and cove mouldings on timber framework.(Timber framework and
painting measured separately)

5,159.94

square

79 3/4" thick tongued and grooved Lunumidella ceiling boards fixed horizontal on 4" x 2"
class I timber Joists at 2'-0" centres with 1 1/2" brass nails.

16,984.04

square

80 3/4" x 6" wide tongued and grooved Lunumidella ceiling boards fixed to underside of
roof rafters, (existing) with 1 1/2" brass nails including levelling with timber sterips
where necessary.

11,733.75

square

DOORS & WINDOWS


81 Door single hung 3'-3" x 7'-0" high overall with frame having 1 1/4" thick sash and
3 3/4"x 2 3/4" timber frame (glazing, ironmongery & painting measured separately)

569.31

sq.ft

82 Door glazed and panelled double hung 4'-0" x 7'-0" high overall with frame including
1 1/4" thick sash and 3 3/4" x 2 3/4" frame (Glazing, ironmongery and painting
measured separately)

549.35

sq.ft

83 Plywoood door single hung 3'-1 1/2" x 6'-11 1/2" overall with frame having 1 1/4" thick
sash and 3 1/4" x 2 1/4" frame . ( Iron-mongery and painting measrued separately ).

274.97

sq.ft

No

Description

Rate

Unit

84 Door ledged, braced and battened single hung 2'-6" x 6'-6" overall, with frame having
7/8" thick tongued & grooved planks and 3 3/4" x 2 3/4" frame.
(Ironmongery & painting measured separately)

639.03

sq.ft

85 Window, glazed 7'-0" x 4'-0" high overall with frame comprising 3 No.
openable sashes and 3 3/4" x 2 3/4" frame and mullions.

502.21

sq.ft

86 1/6" clear sheet glass panes exceeding 1 but not exceeding 4 square feet
cut and fixed with timber beadings to doors and windows.

126.74

sq.ft

87 Butt hinges 5" x 2 1/2"

522.90

pair

88 Tee hinges 6" x 12"

993.60

pair

89 Rim lock

810.00

No

3,935.25

No

188.33

No

92 Door closer ( Hydraulic )

1,636.20

No

93 Tower / Skeleton brass bolts.

1,057.05

No

94 Barrel bolt 4"

193.73

No

95 Casement fasteners.

208.80

No

96 Spring loaded fanlight catches

203.40

No

97 Draw rings

101.70

No

IRONMONGARY

90 Mortice lock
91 Casement stays.

PLASTERWORKS.
98 3/4" thick DPC, in cement sand 1:2 finished with 2 coats hot tar and blinded with sand.

5,430.04

square

99 3/4" thick plastering to wall in lime and sand 2 : 5 including floating with lime putty.

2,652.75

square

100 5/8" thick plastering to wall in lime and sand 2 : 5 including floating with lime putty.

3,507.98

square

101 3/8" thick plastering to soffit of slab in cement and sand 1 : 3 including floating with
lime putty.

4,763.27

square

102 3/8" thick plastering to sides and soffit of beams in cement and sand 1 : 3 including
floating with lime putty.

3,998.50

square

103 5/8" thick plastering to wall in lime, cement and sand 1 : 1 : 5 finished semi rough
with wooden floating.

2,985.53

square

104 5/8" thick plastering to wall in lime, cement and sand 1 : 1 : 5 finished
smooth with lime putty floating.

2,994.98

square

105 1/2" thick rendering in cement and sand 1 : 3 finished smooth.

3,233.05

square

106 1/2" thick rendering in cement and sand 1 : 2 in floors, finished smooth.

3,584.25

square

107 3/4" thick rendering in cement and sand 1 : 3 finished smooth.

4,557.94

square

108 3/4" thick rendering in cement and sand 1 : 2 in floors finished smooth.

4,966.31

square

No

Description

109 3/4" thick rendering in cement sand 1 : 2 in coloured cement floors finished smooth.
110 1/2" x 6" skirting in cement and sand 1:3 projected or flush to walls finished with
floating including forming groove.

Rate
4,687.88

63.19

Unit
square

L.ft

PAINTING & DECORATING


111 Prepare and apply one coat of preservative (oil type) to structural timber including
touching up cut ends etc. after fixing.

1,233.90

square

112 Prepare surface of steel truss and apply two coats of anticorrosive primer.

3,278.21

square

113 Apply one coat of anti-corrosive primer and two coats enamel paint on
already shop primed and erected steel roof truss.

4,269.24

square

114 Perpare and apply two coats primer and finishing coat of enamel
paint to mild steel ( angle/flat ) gate

3,475.98

square

115 Painting steel on new work with 2 coats of anti - corrosive paint

1,728.00

square

800.55

square

3,449.25

square

530.02

square

119 White or colour washing in two storeyed building.

1,406.81

square

120 Prepare and apply one coat of Alkali resistant primer and two
coats of emulsion paint to walls.

2,300.20

square

121 Cement washing to walls of single storeyed building 2 coats.

465.62

square

122 Painting walls with emulsion paint ( 2 coats )

979.31

square

123 Prepare and apply one coat alkali resistant primer and two coats of emulsion
paint to soffit of slabs.

2,869.43

square

124 Varnishing two coats with copal varnish after sand papering

1,821.51

square

513.00

square

126 1/2" diameter PVC pipes fixed to walls ( specials paid separately )

37.69

L.ft

127 3/4" diameter PVC pipes to walls ( specials paid separately )

46.81

L.ft

128 1" diameter PVC pipes fixed to walls ( specials paid separately )

38.52

L.ft

129 1 1/4" diameter PVC pipes fixed to walls ( specials paid separately )

61.72

L.ft

130 1 1/2" diameter PVC pipes laid to walls ( specials paid separately )

84.30

L.ft

131 2" diameter PVC pipes laid to walls ( specials paid separately )

131.89

L.ft

132 3" diameter PVC pipes laid to walls ( specials paid separately )

291.72

L.ft

133 Excavation for laying 1/2" to 3" diameter PVC pipes in ground not less than
1'-6" deep back filling & compacting.

18.23

L.ft

134 Chasing brickwork for laying 1/2" to 1 1/2" dia PVC pipes and making good
average depth 2". ( Pipes and specials paid separately )

58.37

L.ft

116 Painting new timber work with 2 coats wood preservative


117 Preparing and painting wood work with primer and 2 coats enamel paint
118 White or colour washing two coats in single storeyed building.

125 Wax polishing to timber in panels & floors.


PLUMBING - PVC PIPES

No

Description

Rate

Unit

135 Chasing brickwork for laying 1 1/2" to 3" dia PVC pipes and making good
a verage depth 3". ( Pipes and specials paid separately )

70.11

L.ft

136 1/2" dia PVC specials viz - elbows / bends / sockets.

36.40

No

137 3/4" dia PVC specials viz - elbows / bends / sockets.

41.45

No

138 1" dia PVC specials viz - elbows / bends / sockets.

46.85

No

139 1 1/4" dia PVC specials viz - elbows / bends / sockets.

61.97

No

140 1 1/2" dia PVC specials viz - elbows / bends / sockets.

118.26

No

141 2" dia PVC specials viz - elbows / bends / sockets.

149.31

No

142 2 1/2" dia PVC specials viz - elbows / bends / sockets.

226.80

No

143 3" dia PVC specials viz - elbows / bends / sockets.

365.31

No

144 1/2" dia PVC specials viz -Tees

66.56

No

145 3/4" dia PVC specials viz -Tees

71.99

No

146 1" dia PVC specials viz -Tees

86.27

No

147 1 1/4" dia PVC specials viz -Tees

97.94

No

148 1 1/2" dia PVC specials viz -Tees

185.69

No

149 2" dia PVC specials viz -Tees

228.69

No

150 2 1/2" dia PVC specials viz -Tees

357.08

No

151 3" dia PVC specials viz -Tees

688.64

No

393.27

L.ft

260.29

L.ft

315.33

L.ft

2,692.55

No

11,903.27

No

EXTERNAL DRAINAGE (EW PIPES)


152 4" dia glazed earthenware pipes laid on 6" thick bedding in cement concrete
1:3:6 (1 1/2" ) including excavation average 2'-0" depth, backfilling with selected
excavated material and concrete haunching to joints.
PLUMBING (C I PIPES)
153 4" dia C.I. Soil/vent pipe fixed vertically to walls jointed with cement caulking.
(Specials measured separately )
154 4" dia C.I. pipes fixed to walls jointed with lead caulking.
(Specials measured separately)
MANHOLES & GULLEYS
155 4" dia stoneware gulley with 6" x 6" x 6" gulley box including excavation, 4" thick
cement concrete 1:2:4(3/4") base, surrounded by 4 1/2" thick brickwork in cement
and sand 1:5 extended 6" above top of gulley box including making connection,
1/2" cement and sand 1:2 rendering internally and exposed faces finished smooth
with neat cement floating and providing G.I. grating on top of gulley.
156 Manhole 2'-0"x2'-0" internally with invert depth not exceeding 2'-0" including
excavation, backfilling, 6" cement concrete 1:2:4 ( 3/4" ) base with 3/8" dia. mild
steel removable cover slab rods at 4" centres bothways, forming channels and
benching in similar concrete, 4 1/2" walls in brick in cement 1:5, 1/2" thick cement
and sand 1:2 rendering internally and exposed surfaces including channels,
benching and 2" thick RCC removable cover slab 2'-3"x2'-3" inlet and outlet
connection all complete to working order

No

Description

Rate

Unit

SANITARY FITTINGS.
157 22"x16" glazed fireclay wash basin with 1/2" dia Chromium plated pillar tap,
waste plug, Chromium plated waste chain and stay, including fixing wash basin
on brackets. ( water supply and waste water connection measured separately ).

7,673.35

No

158 Sink 24"x15"x7" overall vitreous China with rubber plug and Chromium plated chain
waste carried on iron brackets painted and fixed to walls. ( Water supply and waste
water connection measured separately ).

6,071.17

No

159 Closet pedestal type with L / L flushing cistern, flush pipe double plastic seat cover,
1/2" dia stop cock , trap supplied & fixed complete to working order.

8,616.80

No

160 Closet squatting type with trap including high level cistern fixed complete with flush
pipe and 1/2" dia stop cock, all complete to working order.

5,608.91

No

161 Vitreous China bidet suite fixed complete to working order

8,302.50

No

162 4 No. Bowl type urinal with trap and 2 glas capacity automatic flushing cistern and
spreaders complete to working prders.

2,590.23

No

44.94

L.ft

164 6" dia PVC gutter head

266.69

No

165 6" dia PVC mitres

266.69

No

166 6" dia PVC end caps

174.39

No

29.78

L.ft

168 3 1/2" dia PVC Elbow

219.61

No

169 3 1/2" dia PVC shoe

197.94

No

GUTTERS & DOWN PIPES


163 6" dia half round PVC eaves gutter fixed to timber valance board including gutter
joiner and brackets fixed at 18" centres. ( Other specials paid separately ).

167 3 1/2" dia PVC rain water down pipes fixed to brick wall with wooden plugs buried
in wall. ( Specials measured separately )

You might also like