You are on page 1of 87

Mandal : Duggirala

Estimate

Name of the work

Construction of CC Drains and CC Roads in Godavarru village of Duggirala Mandal

Estimate Cost Rs.

77.00

Lakhs

Name of the Work: Construction of Side Drains and CC Roads in Godavarru Village of Duggirala Mandal

CROSS SECTION OF DRAIN & Road

for 6.00 Mtrs WIDTH ROAD

70 cm

Gravel Shoulders Concrete pavement 200 mm


Gravel Shoulders

20 cm

20 cm

Granular Sub base 75 mm Grading 2nd layer 75 mm Grading 1st layer 75 mm

20 cm VCC 1:3:6 VCC 1:3:6 45 cm 0.30

GL 60 cm
10 cm

6.900 Length of Road 1 Length of Road 2 Length of Road 3 Length of Road 4 Length of Road 5 Length of Road 6 Length of Road 7 Main Road from 6th to 90 90 90 90 85 81 85 35 646

10 CM

10 cm

PCC 1:5:10 - 10 cm Sand Filling -15 cm

90 cm

Specification report to accompany the Detailed estimate for the work Name of the Work: Construction of CC Roads in Godavarru Village of Duggirala Mandal Est.Rs. 41.00 Lakhs

The above work was proposed for sanction under under indiramma Infrastructure funds in Indiramma Layouts where SC/STs are more than 90%. Hence detailed estimate is prepared with the following provisions. Removal of Unserviceable soil including excavation, loading and disposal upto 1000 m lead but excluding compaction ground supporting embankment subgrade replacement by suitable soil, which shall be paid separately as per Clause 303.5.2 as per Technical Specification Clause 302.3.11 MORD / 301 MORTH is proposed to a depth of 75 mm Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80 -100 kN static roller in stages to proper grade and camber, applying and brooming, stone screening/binding materials to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 1 as per Technical Specification Clause 404 (WBM Grading 2nd Layer to a compacted thickness of 75mm ) for providing two grading layers of each 75 mm thick Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 402 MORTH Grading C (Granular Sub-Base with Coarse Graded Material (Table:- 400- 2)) of granular sub-base is proposed to thick ness of 75 mm
Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade) design mix, coarse and fine aggregates conforming to IS : 383, maximum in a concrete mixer of not less than 0.2 cum capacity and appropeiate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 mictron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with sholvels, rakes, compacted using needle, scareed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant, dowel bars, near approaches to bridge / culvert and construction joints, admixtures as approved, curing of concrete slabs for 14- days, curing compound (where specified) and water finishing to lines and grade as per drawing and Technical Specification Clause 1501 MORD of un-reinforced plain cement concrete pavement M30 (Grade design mix ) to thick ness of 200 mm is proposed

Construction of Gravel Base / shoulders including cost, seigniorage charges and conveyance of all materials to work site and spreading in uniform layers by approved means, on prepared surface and compacting with vibratory roller to achieve the desired density at OMC etc., complete for finished item of work as per MoRT&H Specification 401& 407 (4th revision) and as directed by the Engineer-in-charge. Gravel shoulders on both sides of the road and proposed required CD works Necessary provisions are also made for Joint filler board, VAT @ 5%, Q.C charges @ 2.50 % ,Labour cess @ 1.00 %, Ps Charges 7.50 % , Etc. The detailed estimate is prepared with current schedule of rates (ie 2013-14 ) and the work will be carried out as per APDSS

Assistant Engineer APSHCL, Duggirala

Deputy Executive Engineer APSHCL, Mangalagiri

Executive Engineer APSHCL, Guntur

GENERAL ABSTRACT Name of the Work: Construction of Side Drains and CC Roads in Godavarru Village of Duggirala Mandal Estimate Cost : Rs 7700000.00 S.No 1 2 Description of Item Construction of CC Road (Sub Estimate) Construction of Drain (Sub Estimate) Sub Total (1+2) 4 5 6 7 8 10 Provision for PS Charges 7.5% Provision for VAT at 5% Provision for 3rd Party Quality control @2.5% Provision for labour cess 1% Provision for Tender premium at 5.00% Unforceen Items Grand Total:- Rs Amount 3328378.00 2920009.00 6248387.00 468629.00 312419.00 156209.00 62484.00 312419.00 139453.00 7700000.00

Assistant Engineer APSHCL, Duggirala

Deputy Executive Engineer APSHCL, Mangalagiri

Executive Engineer APSHCL, Guntur

DETAILED CUM ABSTRACT ESTIMATE


Name of the Work: Construction of CC Roads in Godavarru Village of Duggirala Mandal
SNo. Estimate cost Rs. 41.00 lakhs Description of Item Nos. L B D Qty. Rate per Total value Removal of Unserviceable soil including excavation, loading and disposal upto 1000 m lead but excluding compaction ground supporting embankment 1 subgrade replacement by suitable soil, which shall be paid separately as per Clause 303.5.2 as per Technical Specification Clause 302.3.11 MORD / 301 MORTH 6 3.60 0.075 87.48 Cross Roads 54.00 5 3.60 0.075 54.00 Cross Roads 40.00 141.48 10600.00 74.92 Cu.m 1 cu.m Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80 -100 kN static roller in stages to proper grade and camber, applying and brooming, stone 2 screening/binding materials to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 1 as per Technical Specification Clause 404 (WBM Grading 2nd Layer to a compacted thickness of 75mm ) Grading 1st Layer Cross Roads Cross Roads 6 5 54.00 40.00 3.30 0.075 3.30 0.075 80.19 49.50 129.69 Cu.m Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80 -100 kN static roller in stages to proper grade and camber, applying and brooming, stone 3 screening/binding materials to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 1 as per Technical Specification Clause 404 (WBM Grading 2nd Layer to a compacted thickness of 75mm ) Grading 2 Layer Cross Roads Cross Roads 6 5 54.00 40.00 3.30 0.075 3.30 0.075 80.19 49.50 129.69 Cu.m Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by 4 mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 402 MORTH Grading C (Granular Sub-Base with Coarse Graded Material (Table:- 400- 2)) Sub Base Cross Roads Cross Roads 6 5 54.00 40.00 3.30 0.075 3.30 0.075 80.19 49.50 129.69 Cu.m 2642.00 1 Cum 342641.00 2642.00 1 Cum 342641.00

1929.79 1 cu.m

250274.00

5 /87

SNo.

Description of Item

Nos.

Qty. Rate per

Total value

Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade) design mix , coarse and fine aggregates conforming to IS : 383, maximum in a concrete mixer of not less than 0.2 cum capacity and appropeiate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 mictron thick polythene film, wedges, steel plates including levelling the formwork as per 5 drawing), spreading the concrete with sholvels, rakes, compacted using needle, scareed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant, dowel bars, near approaches to bridge / culvert and construction joints, admixtures as approved, curing of concrete slabs for 14- days, curing compound (where specified) and water finishing to lines and grade as per drawing and Technical Specification Clause 1501 MORD.

Cross Roads Cross Roads

6 5

54.00 40.00

3.30 3.30

0.20 0.20

213.84 132.00 345.84 Cu.m

6021.92 1 cu.m

2082621.00

Construction of Gravel Base / shoulders including cost, seigniorage charges and conveyance of all materials to work site and spreading in uniform layers by approved means, on prepared surface and compacting with vibratory roller to 6 achieve the desired density at OMC etc., complete for finished item of work as per MoRT&H Specification 401& 407 (4th revision) and as directed by the Engineer-in-charge. For shoulders both side Cross Roads Cross Roads 6 5 2 2 54.00 40.00 0.75 0.75 0.20 0.20 97.20 60.00 157.20 Cu.m 7 Supply and delivery of RCC NP3 pipes of 450 mm dia including collars and conveyance charges etc, complete for Cross Roads for Cross Roads 2 2 11 11 2.50 2.50 55.00 55.00 110.00 8 Laying and fixing of RCC NP3 pipes of 450 mm dia including all labour charges etc, complete for Cross Roads 11 2 2.50 for Cross Roads 11 2 2.50 Total Estamate Provision for PS Charges 7.5% Provision for VAT at 5% Provision for 3rd Party Quality control @2.5% Provision for labour cess 1% Provision for Tender premium at 5.00% Unforceen Items Total 1555.50 171105.00 742.60 1 cu.m 116737.00

55.00 55.00 110.00

106.90

11759.00 3328378.00 249628.00 166419.00 83209.00 33284.00 166419.00 72663.00 4100000.00

Assistant Engineer APSHCL, Duggirala

Deputy Executive Engineer APSHCL, Mangalagiri

Executive Engineer APSHCL, Guntur

6 /87

Specification report to accompany the detailed estimate for the work

Name of the Work: Construction of Side Drains in Godavarru Village of Duggirala Mandal Est.Rs. 36.00 Lakhs

The above work was proposed under indiramma Infrastructure funds. Hence detailed estimate is prepared with the following provisions. Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material as per Technical Specification 305 MORD / 304 MORTH Sand filling 150 mm th for shoe wall fondation is proposed with filling Sand in foundation trenches as per drawing and technical specification Clause 305.3.9 MORD & 304 MORTH Providing concrete for plain concrete in open foundations using 40 mm nominal size Graded hard stone aggregate, mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH. ( M10 Concrete , nominal mix 1:3:6) for Bed Concrete 0.10m depth is proposed.

Plain cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH ( M15 concrete design mix ) for Drain Wall is proposed to a length of 843.00 mts on both sides of the road is proposed.

Plain cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH Excluding Seignorage and VAT including OH&CP (at bottom portion of drain) M20 concrete at Concreting at bottom of drain to thick ness of 100 mm is proposed

Plastering with cement mortar (1:4), 12 mm thickness as per technical specification 1300 & 2200 MORTH for inside and top portion of drain is proposed Certified that the above village is with in 12 Km Radious of from Tadepalli Municipality limits. Hence 20 % extra over the rates on labour component of works provision is made in this estimate Necessary provisions are also made for Joint filler board, VAT @ 5%, Q.C charges @ 2.50 % ,Labour cess @ 1.00 %, Ps Charges 7.50 % , Etc. The detailed estimate is prepared with current schedule of rates (ie 2013-14 ) and the work will be carried out as per APDSS

Assistant Engineer APSHCL, Duggirala

Deputy Executive Engineer APSHCL, Mangalagiri

Executive Engineer APSHCL, Guntur

DETAILED CUM ABSTRACT ESTIMATE

Name of the Work: Construction of Side Drains in Godavarru Village of Duggirala Mandal
SNo. Description of Item Nos. L Estimate cost B D Rs. 36.00 lakhs Qty. Rate per Total value

Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material as per Technical Specification 305 MORD / 304 MORTH Side walls Main Road Cross Roads Cross Roads

1 x 7 x 7 x

2 185.00 2 40.00 2 54.00

0.90 0.90 0.90

0.600 199.80 0.600 302.40 0.600 408.24 910.44 Cu.m

Cum Cum Cum

116.19 1 cu.m

105784.00

Filling Sand in foundation trenches as per drawing and technical specification Clause 305.3.9 MORD & 304 MORTH Main Road Cross Roads Cross Roads 1 x 7 x 7 x 2 185.00 2 40.00 2 54.00 0.90 0.90 0.90 0.150 0.150 0.150 49.95 75.60 102.06 227.61 Cu.m

512.70 1 cu.m

116696.00

Providing concrete for plain concrete in open foundations using 40 mm nominal size Graded hard stone aggregate, mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH. for Bed Concrete ( M10 Concrete , nominal mix 1:3:6) Bottom Main Road Cross Roads Cross Roads 1 x 7 x 7 x 2 185.00 2 40.00 2 54.00 0.90 0.90 0.90 0.100 0.100 0.100 33.30 50.40 68.04 151.74 Cu.m Plain cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH ( M15 concrete design mix) Side walls Main Road Cross Roads Cross Roads 1 7 7 2 x 2 x 2 x 2 185.00 2 40.00 2 54.00 0.20 0.20 0.20 0.550 0.550 0.550 81.40 123.20 166.32

3799.40 1 cu.m

576521.00

8 /87

SNo.

Description of Item

Nos.

Qty. Rate per Total value 370.92 4479.60 1661573.00 Cu.m 1 cu.m

Plain cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH Excluding Seignorage and VAT including OH&CP (at bottom portion of drain) M20 concrete At bottom of Drain Main Road Cross Roads Cross Roads

1 7 7

2 185.00 2 2 40.00 54.00

0.30 0.30 0.30

0.100 0.100 0.100

11.10 16.80 22.68 50.58 Cu.m 4828.40 1 cu.m 244220.00

Plastering with cement mortar (1:4), 12 mm thickness as per technical specification 1300 & 2200 MORTH Total drain Main Road Cross Roads Cross Roads 1 7 7 2 185.00 2 40.00 2 54.00 1.600 592.00 1.600 896.00 1.600 1209.60 2697.60 Sq.m

79.78 1 Sq.m

215215.00 2920009.00 219001.00 146000.00 73000.00 29200.00 146000.00 66790.00 3600000.00

Total Estamate Provision for PS Charges 7.5% Provision for VAT at 5% Provision for 3rd Party Quality control @2.5% Provision for labour cess 1% Provision for Tender premium at 5.00% Unforceen Items

Total amount

Assistant Engineer APSHCL, Duggirala

Deputy Executive Engineer APSHCL, Mangalagiri

Executive Engineer APSHCL, Guntur

9 /87

Name of the Work:


S. No 1 Quantity 2 Unit 3 Description 4 Rate Rs. 5 per 6

Seignorage Charges SSR


MUNICIPAL ALLOWANCE Overheads & Contractor's Profit 1

"13-14
0% 14% Removal of Unserviceable Soil with Disposal upto 1000 m Removal of Unserviceable soil including excavation, loading and disposal upto 1000 m lead but excluding compaction ground supporting embankment subgrade replacement by suitable soil, which shall be paid separately as per Clause 303.5.2 as per Technical Specification Clause 302.3.11 MORD / 301 MORTH Unit = cum Taking output = 360 cum a) Labour Mate Mazdoor (Unskilled) b) Machinery Excavator 0.90 cum bucket capacity @ 100 cum per hour Tipper 5.5 cum capacity, 4 trips per hour c&d) Overheads & Contractors Profit Cost for 360 cum = a+b+c+d Rate per cum = (a+b+c+d)/360 Granular Sub-Base with Coarse Graded Material (Table:- 400- 2) Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 402 MORTH Grading C Unit = cum Taking output = 300 cum a) Labour Mate Mazdoor skilled Mazdoor b) Machinery Mortar Grader 110 HP @ 50 cum per hour Three wheel Roller 80-100 KN @10cu.m/hour Water tanker 6 KL capacity Tractor with Rotavator 25 cu.m/hour c) Material For coarse graded Granular sub-base Materials per table 400-2 For Grading-C Material (CBR Value minimum 20) 9.5 mm to 4.75 mm @ 35 per cent 4.75 mm to 2.36 mm @ 12.5 per cent 2.36 mm below @ 52.5 per cent (Dust) Cost of water

Sand 40.00
HBG Metal 50.00 Gravel/Earth 22.00

2.080 3.60 15.00 14%

RBR-EECD

day day hour hour

280.00 2754.50 877.30 23658.10

1 1 1

day hour hour

2.40 8.00 6.00 30.00 3.00 12.00

day day day hour hour hour hour

280.00 280.00 3216.00 1704.60 624.00 422.00

1 1 1 1 1 1

day day hour hour hour hour

134.00 48.00 201.60 18.00

cum cum cum KL

1327.51 987.51 1015.01 0.00 19180.00

1 2 1 1

cum cum cum KL

Total Seignorage Charges

10 /87

S. No 1

Quantity 2 14%

Unit 3

Description 4

Rate Rs. 5 491014.84

per 6

Add over heads& contr.profit Exclu. Sei. Charges


Cost for 300 cum = a+b+c+d+e Rate per cum = (a+b+c+d)/300

3a

Grading 1 Layer

Water Bound Macadam Sub-base/base With stone screening / binding materials WBM Grading 1 Layer 100mm thick (i) Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80 -100 kN static roller in stages to proper grade and camber, applying and brooming, stone screening/binding materials to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 1 as per Technical Specification Clause 404 MORTH & 405 MORD. For compacted thickness of 100 mm. By Manual Means (Common for rural & urban works) Unit = cum Taking output = 360 cum a) Labour Mate Mazdoor (Skilled) Mazdoor (Unskilled) b) Machinery Vibratory roller 8-10 tonnes @ 60 cum per hour Water tanker 6 kl capacity c) Material Aggregate Grading 1 90 mm to 45 mm @ 1.21 cum per 10 sqm for compacted thickness of 100 mm 75mm IRC HBG metal 63mm IRC HBG M/C metal 45 mm IRC HBG M/C metal Stone Screenings Type A 13.2 mm for Grading-1 @ 0.27 cum per 10sqm Binding Material Binding Material @ 0.08 cum per 10 sqm for grading 1 material (Rate of 2.36mm & Below) Water

12.08 250.00 6.00 24.00

RBR-SBBS-9

day day day hour hour

280.00 280.00 2541.40 624.00

1 1 1 1

day day hour hour

217.8 200.38 17.42 97.20 28.80 144.00

cum cum cum cum cum kl

906.51 981.51 1190.51 1577.51 1015.01 0.00 28080.00 672944.60

1 1 1 1 1 1

cum cum cum cum cum KL

Total Seignorage Charges


14%

Add over heads& contr.profit Exclu. Sei. Charges


Cost for 360 cum = a+b+c+d+e (3 Wheel Roller) Rate per cum = (a+b+c+d+e)/360 WBM Grading 2nd Layer 75mm thick By Mechanical Means Unit = cum Taking output = 360 cum a) Labour day Mazdoor (Skilled) day Mazdoor (Unskilled) b) Machinery hour Three wheel Roller 80-100 KN @10cu.m/hour

3b

Grading 2 Layer

12.08 250.00 36.00

280.00 280.00 1704.60

1 1 1

day day hour

11 /87

S. No 1

Quantity 2 24.00 217.8 200.38 17.42 86.40

Unit

Description

Rate Rs. 5 624.00 1021.51 1337.51 1832.51 1577.51

per 6 hour cum cum cum cum

3 4 hour Water tanker 6 kl capacity Materials cum 60-63mm IRC HBG metal cum 40-45mm IRC HBG M/C metal cum 19-22.40 mm IRC HBG M/C metal cum Type B 11.2 mm for Grading 2 @ 0.18 cum per 10sqm Binding Material Binding material @ 0.06 cum / 10sqm (Rate of 2.36mm & cum Below) kl Water

1 1 1 1 1

28.80 144.00

1015.01 0.00 27540.00 810130.61

1 1

cum KL

Seignorage Charges
14%

Add over heads& contr.profit Exclu. Sei. Charges


Cost for 360 cum = a+b+c+d+e (3 Wheel Roller) Rate per cum = (a+b+c+d+e)/360 Note : Type A Screening can be used in Grading 2

3c

Grading 3 Layer

WBM Grading 3 Layer (i) Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405 MORD/ 404 MORTH. For compacted thickness of 75 mm. By Manual Means Unit = cum Taking output = 360 cum a) Labour Mazdoor (Skilled) Mazdoor (Unskilled) b) Machinery Three wheel Roller 80-100 KN @10cu.m/hour Water tanker 6 kl capacity c) Material (Refer Tables 400.7, 8, 9 & 10 MORD/ 400.6, 7, 8 & 9 MORTH) Aggregate Grading 3 53 mm to 22.4 mm @ 0.91 cum per 10 sqm for compacted thickness of 75 mm 40-45mm IRC HBG M/C metal 19-22.40 mm IRC HBG M/C metal Stone Screening

12.08 250.00 36.00 24.00

RBR-SBBS-9

day day hour hour

280.00 280.00 1704.60 624.00

1 1 1 1

day day hour hour

cum 357.19 78.41 86.40 cum cum

1337.51 1832.51 1422.51

1 1 1

cum cum cum

cum Type B 11.2 mm for Grading 3 @ 0.18 cum per 10sqm Binding Material

28.80 144.00

cum kl

Binding Material @ 0.06 cum per 10 sqm for Grading 2 material (Rate of 2.36mm & Below) Water

1015.01 0.00 27540.00

1 1

cum KL

Seignorage Charges

12 /87

S. No 1

Quantity 2 14%

Unit 3

Description 4

Rate Rs. 5 895753.46

per 6

Add over heads& contr.profit Exclu. Sei. Charges


Cost for 360 cum = a+b+c+d+e (3 Wheel Roller) Rate per cum = (a+b+c+d)/360

Note : When BT is taken up, simultaneously, avoid Binding material 3d


II

WBM Grading 2

Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening/binding materials to fill-up the interstices of coarse aggregate, watering and compacting to the required density grading 2 as per Technical Specification Clause 405 MORD / 404 MORTH. For compacted thickness of 75 mm.
By Manual Means Unit = cum Taking output = 360 cum a) Labour
day

RBR-SBBS-9

Mate Mazdoor (Skilled) Mazdoor (Unskilled) b) Machinery

280.00 280.00 280.00

1 1 1

day day day

12.08 250.00

day day

36.00 24.00

hour hour

Three wheel 80-100 kN static roller @ 10 cum per hour for Rural Area works

1704.60 624.00

1 1

hour hour

Water tanker 6 kl capacity c) Material (Refer Tables 400.7, 8, 9 and 10 MORD/ 400.6, 7, 8 & 9 MORTH) Aggregate

435.60

cum

Grading 2 63 mm to 45 mm @ 0.91 cum per 10 sqm for compacted thickness of 75 mm Stone Screening
Type B 11.2 mm for Grading 2 @ 0.18 / 0.20 cum/10sqm

1058.51 1422.51 1577.51

1.00 1.00 1.00

cum cum cum

86.40

cum

(OR)
57.60 cum

Type B 13.2 mm for Grading 2 @ 0.12 cum per 10sqm Binding Material

28.80 144.00

cum kl

Binding Material @ 0.06 cum per 10 sqm for Grading 2 1015.01 material Water 0.00 Using 11.2 mm for Grading 2 :

1.00 1.00

cum KL

Seignorage Charges
14%

26100.00 707615.82

Add over heads& contr.profit Exclu. Sei. Charges


Cost for 360 cum = a+b+c+d+e

13 /87

S. No 1

Quantity 2

Unit 3

Description 4 Rate per cum = (a+b+c+d+e)/360


Using 13.2 mm for Grading 2

Rate Rs. 5

per 6

Seignorage Charges
14%

26100.00 704807.82

Add over heads& contr.profit Exclu. Sei. Charges


Cost for 360 cum = a+b+c+d+e Rate per cum = (a+b+c+d+e)/360 Providing and applying track coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous/granular surface cleaned with mechanical broom as per Tech. specification No 503 MORTH Unit = sqm Taking output = 3500 sqm a) Labour Mazdoor (Unskilled) b) Machinery Mechanical broom @ 1250 sqm per hour Air compressor 250 cfm Emulsion pressure distributor @ 1750 sqm per hour c) Material Bitumen emulsion @ 0.2 kg per sqm d&e) Overheads & Contractors Profit Rate per sq.m = (a+b+c+d)/3500 sq.m Rate per sq.m = (a+b+c+d)/3500 sq.m 20mm thick Open-Graded Premix Carpet using Bituminous (penetration grade/modified bitumen) Binder Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including mixing a suitable plant, laying and rolling with a three wheel 0-100 kN static roller capacity, finished to required level and grades to be followed by seal coat of either type A or Type B or Type C as per Technical Specification Clause 508 MORD. Case - II By Mechanical Means Bitumen (S-65) Unit = sqm Taking output = 4000 sqm (80 cum) a) Labour Mazdoor (Unskilled) Mazdoor (Skilled) b) Machinery HMP 30/40 t per hour Electric generator set 125 KVA Front end loader 1 cum bucket capacity Tipper 5.5 cum - 10 t capacity Paver finisher Three wheel 80-100 kN static roller c) Material Bitumen (S-65) @ 14.60 kg per 10 sqm

2.080 2.800 2.800 2.000 0.700 14%

day hour hour hour t

280.00 357.00 499.40 860.00 37179.93 30726.27

1 1 1 1 1

day hour hour hour Mt

10.000 3.520 6.000 6.000 6.000 3.640 6.000 16.000 5.840

day day hour hour hour hour hour hour t

280.00 280.00 19120.00 1320.00 1646.00 877.30 2249.00 1283.00 37179.93

1 1 1 1 1 1 1 1 1

day day hour hour hour hour hour hour Mt

14 /87

S. No 1

Quantity 2 108.000

Unit 3

Description

Rate Rs. 5 1422.51 5400.00 538878.84 1

per 6 cum

4 Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum cum per 10 sqm

Seignorage Charges
14%

Add over heads& contr.profit Exclu. Sei. Charges


Cost of 4000 sqm = a+b+c+d+e Rate per 1 sq.m = (a+b+c+d)/4000 sq.m Seal Coat Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type A, Type B and Type C as per Technical Specification Clause 510 MORD. (using Three wheel 80-100 kN static roller) By Manual Means Bitumen (S-65) Unit = sqm Taking output = 1100 sqm a) Labour Mate Bitumen Sprayer Mazdoor (Unskilled) Mazdoor (Semi-Skilled) b) Machinery Bitumen boiler oil fired, capacity 1000 litre fitted with spray set Three wheel 80-100 kN static roller c) Material Bitumen (S-65) @ 9.80 kg per 10 sqm Crushed stone chipping of 6.7 mm size 100 per cent passing 11.2 mm sieve and retained on 2.36 mm sieve applied @ 0.09 cum per 10 sqm

1.000 22.000 7.150 2.200 2.200 1.078 9.900

day day day day hour hour t cum

280.00 280.00 280.00 209.00 1283.00 37179.93 1232.51

1 1 1 1 1 1 1

day day day hour hour cum cum

Seignorage Charges
14%

495.00 63511.21

Add over heads& contr.profit Exclu. Sei. Charges


Cost of 1100 sqm = a+b+c+d+e Rate per 1 sq.m = (a+b+c+d)/1100 Cost and supply of Gravel for formation of roads Including cost and Seignorage charges and conveyance of all materials to work site and spreading in uniform layers by approved means, on prepared surface and compacating with vibrating roller to achieve the desired density. A. Gravel Roads The rate as applicable for sub-grade construction may be adopted. For Grading III Material (CBR Value minimum 20) Unit = cum Taking output = 300 cum D&e) Overheads & Contractors Profit Mazdoor (Skilled) Mazdoor (Unskilled) b) Machinery Three wheel 80-100 kN Static Roller Tractor with Rotavator Tractor with Grader Water tanker 6 kl capacity

2.40 8.00 36.00 12.00 12.00 3.00

day day hour hour hour hour

280.00 280.00 1704.60 422.00 422.00 624.00

1 1 1 1 1 1

day day hour hour hour hour

15 /87

S. No 1

Quantity 2 237.6 122.4 18.00

Unit 3

Description

Rate Rs. 5 508.46 1015.01 1 1 1

per 6 cum cum KL

4 c) Material cum Gravel(9.5MM-4.75mm)66% cum 2.36 mm below @ 34 per cent (Dust) kl Water

14%

Seignorage Charges Add over heads& contr.profit Exclu. Sei. Charges Cost for 300cum = a+b+c+d+e (3 Wheel Roller)
Rate per cum = (a+b+c+d)/300 Construction of Gravel shoulders including cost, seigniorage charges and conveyance of all materials to work site and spreading in uniform layers by approved means, on prepared surface and compacting with vibratory roller to achieve the desired density at OMC etc., complete for finished item of work as per MoRT&H Specification 401& 407 (4th revision) and as directed by the Engineer-in-charge.

11347.20 309977.72

( Payment will be made based on levels for finished item of work )

Unit = cum Taking output = 300 cum (A) 0.40 day 2.00 day 8.00 day
Labour Mate Mazdoor skilled Mazdoor unskilled
280.00 280.00 280.00 1 1 1 day day day

(B) Machinery 6.00 hr Vibratory roller 8T 3.00 hr Water tanker 6 KL (C) Material 384.00 cum Gravel
Seignorage Charges Add over heads& contr.profit Exclu. Sei. Charges Cost for 300cum = a+b+c+d
Rate per cum = (a+b+c+d)/300
Granular sub-base/base/surface course with local materials (Table 400.13) by mix in place method normal Construction of granular sub-base by providing local material spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at once and compacting with smooth wheel roller to achieve the desired density complete as per Clause 401.4 as per Technical Specification Clause 408 MORD.

2541.40 624.00

1.00 hr 1.00 hr

508.46 8448.00 206833.04

1.00 cum

14%

RBR-SBBS-12

day 2.48 10.00 6.00 30.00 12.00 day day hour hour hour

Using naturally occurring gravel Unit = cum Taking output = 300 cum a) Labour Mate Mazdoor (Skilled) Mazdoor (Unskilled) b) Machinery Motor grader 110 HP 50 cum per hour
Three wheel 80-100 kN static roller @10 cum per hour

280.00 280.00 280.00 3216.00 1704.60 422.00

1 1 1 1 1 1

day day day hour hour hour

Tractor with rotavator 25 cum per hour

16 /87

S. No 1

Quantity 2
5.00

Unit 3
hour

Description 4
Water tanker 6 kl capacity c) Material
Naturally occurring gravel (Local materials as per Table 400.13)

Rate Rs. 5 624.00 508.46 0.00 19200.00 258161.04

per 6 hour cum kl

1 1 1

384.00 30.00

cum kl

Water Basic Cost

14%

Seignorage Charges Add over heads& contr.profit Exclu. Sei. Charges Cost for 300cum = a+b+c+d
Rate per cum = (a+b+c+d)/300

10

Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade) design mix, coarse and fine aggregates conforming to IS : 383, maximum in a concrete mixer of not less than 0.2 cum capacity and appropeiate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 mictron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with sholvels, rakes, compacted using needle, scareed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant, dowel bars, near approaches to bridge / culvert and construction joints, admixtures as approved, curing of concrete slabs for 14- days, curing compound (where specified) and water finishing to lines and grade as per drawing and Technical Specification Clause 1501 MORD.
Unit = cum Taking output = 75 cum (172.50 t) (100 x 3.75 x 0.200) a) Labour Mate Mason (1st class) Mason (2nd class) Mazdoor (Unskilled) Mazdoor (Skilled) Surveyor Mazdoor (Semi-Skilled) Blacksmith for cutting of dowel bars including removal of burrs, fabrications & fixing of dowel bars. b) Machinery Concrete mixer 0.28 / 0.4 cum capacity (6 mixers) with weigh batcher and suitable capacity calibrated water tank Needle vibrator Screed vibrator Plate vibrator Concrete joint cutting machine for initial & final cuts Water tanker 6 kl capacity Air Compressor (1 hour initial + 1 hour final) c) Material Crushed stone coarse aggregates, grading will be as per Clause 1501.2.4.1 (Table 1500.1) of specifications @ 0.90 cum/cum of concrete (25 mm & 12.5 mm blending) 20 mm HBG Metal 12 mm HBG Metal Sand as per IS:383 and conforming to Clause 1500.2.4.2 @ 0.45 cum/cum of concrete Cement @ 310 kg/cum of concrete Polythene sheet 125 micron

RBR-CCPV-5

day 5.00 5.00 150.00 6.00 2.00 6.00 1.00 day day day day day day day

280.00 350.00 320.00 280.00 280.00 320.00 280.00

1.00 1.00 1.00 1.00 1.00 1.00 1.00

day day day day day day day

36.00 9.00 9.00 9.00 4.00 5.00 2.00

hour hour hour hour hour hour hour

417.40 1.00 Hour 152.20 0.00 152.20 0.00 624.00 499.40 1.00 1.00 1.00 1.00 1.00 1.00 Hour Hour Hour Hour Hour Hour

44.55 22.95 33.75 26.25 412.50

cum cum cum t sqm

1832.51 1.00 Cum 1577.51 1.00 Cum 467.77 1.00 Cum 5.70 1.00 Cum 15.00 1.00 Sq mt

17 /87

S. No 1

Quantity 2

Unit 3

Description 4
Mild steel dowel bar 25 mm dia of grade S 240. 500 mm long 20 Nos. at culvert/bridge slab and at construction joint including 5 per cent wastage. (4 x 20 x 0.500) + 5 per cent wastage = 42 m @ 2.80 kg per m = 117.6 kg. Bitumen primer @ 200 ml per joint for 23 joints Bituminous sealant 800 ml per joint for 23 joints Jute rope 12 mm dia including 5 per cent wastage Debonding strips 3.75 m (length) x 10 mm (width) x 5 mm (thick) cut-out of rubber filler board or similar material including 5 per cent wastage Polythene sheathing, covering 2/3rd dowel bars (20x23) and tight fit including 5 per cent wastage Plasticizer 0.5 per cent by weight of cement Curing compound (if used) @ 0.33 litre per sqm Water for curing Joint filler board 20 mm thick as per IS:1838 (4 x 3.75 x 0.200 = 3 sqm)
(d) Formwork @ 3% on cost of material, labour and machinery (a+b+c)

Rate Rs. 5

per 6

0.118 5.00 19.00 90.00 90.00

t kg litre m m

43000.00 1.00 ton 37179.93 1.00 ton 37179.93 1.00 ton

483.00 122.00 131.25 18.00 3.00 3.00%

sqmt litre litre kl sqm

15.00 1.00 Sq mt 70.00 1.00 Ltr 0.00 1.00 kl 925.00 1.00 Ltr 385203.05

Basic rate per 75 Cum Seignorage Charges Sand Agrregate 14% Add over heads& contr.profit Exclu. Sei. Charges Add sundries Rate per 75 Cum Rate per Cum Cost of RCC Pipes NP2 1350.00 3375.00 4725.00
392034.15

11

Supply and delivery of RCC NP2 pipes of 300mm dia including collars and conveyance charges etc, complete
Unit = 1Rm

5.00 RM 1 No

Cost and Conveyance charges of RCC Pipes Cost of collars Cost for 5Rm =a+b+c+d Rate per RM is ( a+b+c+d )/5

370.60 1.00 RM 87.00 1.00 No

14%

Add over heads& contr.profit Exclu. Sei. Charges Add sundries Rate Per RM
Laying of RCC pipes NP2

388.00

12

Laying and fixing of RCC NP2 pipes of 300mm dia including all labour charges etc, complete
Unit = 1Rm Taking out put = 7.50 RM (3 pipes of 2.50 Mts length each ) upto 500 mm dia a) Labour

2.51

day Mazdoor (Unskilled)


deduct 20% for 300mm RCC Pipes

280.00 1.00 day

b)Material Cost for 5Rm =a+b Rate per RM is ( a+b )/7.50

14%

Add over heads& contr.profit Exclu. Sei. Charges

74.97

18 /87

S. No 1

Quantity 2

Unit 3

Description 4

Rate Rs. 5

per 6

13

Add sundries Rate Per RM Cost of RCC Pipes NP2 Supply and delivery of RCC NP2 pipes of 450mm dia including collars and conveyance charges etc, complete
Unit = 1Rm

5.00 RM 1 No

Cost and Conveyance charges of RCC Pipes Cost of collars Cost for 5Rm =a+b+c+d Rate per RM is ( a+b+c+d )/5

666.00 1.00 RM 185.00 1.00 No

14%

Add over heads& contr.profit Exclu. Sei. Charges Add sundries Rate Per RM

703.00

14

Laying of RCC pipes NP2

Laying and fixing of RCC NP2 pipes of 450 mm dia including all labour charges etc, complete
Unit = 1Rm Taking out put = 7.50 RM (3 pipes of 2.50 Mts length each ) upto 500 mm dia a) Labour

2.51 day Mazdoor (Unskilled)


deduct 20% for 300mm RCC Pipes

280.00 1.00 day

b)Material Cost for 5Rm =a+b Rate per RM is ( a+b )/7.50

14%

Add over heads& contr.profit Exclu. Sei. Charges Add sundries Rate Per RM

93.71

15

Cost of RCC Pipes NP3 Supply and delivery of RCC NP3 pipes of 300mm dia including collars and
Unit = 1Rm

5.00 RM 1 No

Cost and Conveyance charges of RCC Pipes Cost of collars Cost for 5Rm =a+b+c+d Rate per RM is ( a+b+c+d )/5

845.40 1.00 RM 124.00 1.00 No

14%

Add over heads& contr.profit Exclu. Sei. Charges Add sundries Rate Per RM

870.20

16

Laying of RCC pipes NP3

Laying and fixing of RCC NP3 pipes of 300mm dia including all labour charges etc, complete
Unit = 1Rm Taking out put = 7.50 RM (3 pipes of 2.50 Mts length each ) upto 500 mm dia a) Labour

2.51 day Mazdoor (Unskilled)


deduct 20% for 300mm RCC Pipes

280.00 1.00 day

b)Material Cost for 5Rm =a+b

19 /87

S. No 1

Quantity 2

Unit 3

Description 4
Rate per RM is ( a+b )/7.50

Rate Rs. 5

per 6

14%

Add over heads& contr.profit Exclu. Sei. Charges

74.97

17

Add sundries Rate Per RM Cost of RCC Pipes NP3 Supply and delivery of RCC NP3 pipes of 450mm dia including collars and
Unit = 1Rm

5.00 RM 1 No

Cost and Conveyance charges of RCC Pipes Cost of collars Cost for 5Rm =a+b+c+d Rate per RM is ( a+b+c+d )/5

1317.80 1.00 RM 233.00 1.00 No

14%

Add over heads& contr.profit Exclu. Sei. Charges Add sundries Rate Per RM

1364.40

18

Laying of RCC pipes NP3

Laying and fixing of RCC NP3 pipes of 450 mm dia including all labour charges etc, complete
Unit = 1Rm Taking out put = 7.50 RM (3 pipes of 2.50 Mts length each ) upto 500 mm dia a) Labour

2.51

day Mazdoor (Unskilled)


deduct 20% for 300mm RCC Pipes

280.00 1.00 day

b)Material Cost for 5Rm =a+b Rate per RM is ( a+b )/7.50

14%

Add over heads& contr.profit Exclu. Sei. Charges Add sundries Rate Per RM

93.71

19

Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material as per Technical Specification 305 MORD / 304 MORTH RBR-FNDN-1 Note : Classifications of Earth Work Specification are as per 302.2.1(a) of MORD and (I) Ordinary soil (A) Manual Means (i) Upto 3 m depth Unit = cum Taking output = 10 cum a) Labour day Mate 280.00 1.00 day day Mazdoor (Unskilled) 280.00 1.00 day 1019.20 10.00 Cu.m b&c) Overheads & Contractors Profit Add sundries Cost for 10 cum = a+b+c Rate per cum = (a+b+c)/10 Filling in foundation trenches as per drawing and technical specification Clause 305.3.9 MORD & 304 MORTH

3.64 14%

20

20 /87

S. No 1

Quantity 2

Unit 3 RBR-FNDN-2 Sand filling


Unit = cum a) Labour
day

Description 4

Rate Rs. 5

per 6

Mate Mazdoor (Unskilled) b) Material Sand

0.31

day

280.00 1.00 day 280.00 1.00 day 367.77 1.00 Basic rate per 1 Cum
cum

1.00

cum

Seignorage Charges Sand 14% Add over heads& contr.profit Exclu. Sei. Charges Add sundries Rate per cum
Gravel filling
Unit = cum a) Labour
day 0.52 day

40.00 414.57 1.00 Cu.m

Mate Mazdoor (Unskilled) b) Material Gravel

280.00 1.00 day 280.00 1.00 day 508.46 1.00 Basic rate per 1 Cum
cum

1.00

cum

Seignorage Charges
Gravel

14%

Add over heads& contr.profit Exclu. Sei. Charges Add sundries Rate per cum

22.00 632.06 1.00 Cu.m

21 a

Providing concrete for plain/reinforced concrete in open foundations using 40 mm nominal size Graded hard stone aggregate, mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH.
a)

RBR-FNDN-4
P.C.C grade M 10 Nominal mix 1:3:6 Unit = cum (a) Material

With out form work

0.22 0.45 0.9 1.2

t cum cum kl

Cement Coarse sand 40 mm aggregate Water (b) Labour Mate Mason (1st Class) Mazdoor (Unskilled) (c) Machinery
Mechanical concrete mixer 0.4/0.28 cum capacity fitted with water measuring device and preferably also with load cell.

5.70 467.77 1337.51 0.00

1.00 Kg 1.00 Cum 1.00 Cum kl 1.00

day 0.1 1.39 day day

280.00 1.00 day 350.00 1.00 day 280.00 1.00 day 417.40 1.00 Hour 624.00 1.00 Hour

0.40 0.13

hour hour

Water tanker 6 kl capacity

21 /87

S. No 1

Quantity 2
0.00%

Unit 3

Description 4
(d) Formwork @ 4% on cost of material, labour and machinery (a+b+c)

Rate Rs. 5

per 6

3340.54 1.00 Cum

Basic rate per 1 Cum Seignorage Charges Sand


40 mm aggregate Total

14%

Add over heads& contr.profit Exclu. Sei. Charges Add sundries Rate per cum = a+b+c+d+e+f
b)

18.00 45.00 63.00 3277.54 1.00 Cu.m

21 b

P.C.C. grade M 20 (MORD) Nominal mix (1:2:4) (Mechanical Mixer) Unit = cum (a) Material

0.33 0.45 0.36 0.36 0.18

t cum cum cum cum

Cement Sand 40 mm aggregate 20 mm aggregate 10 mm aggregate (b) Labour Mate Mason (1st Class) Mazdoor (Unskilled) Bhisti (c) Machinery Concrete mixer 0.4/0.28 cum capacity d) Formwork @ 4% on cost of material, labour and machinery (a+b+c)

5.70 467.77 1337.51 1832.51 1422.51

1.00 1.00 1.00 1.00 1.00

Kg Cum Cum Cum Cum

day 0.1 1.39 day day day

280.00 1.00 day 350.00 1.00 day 280.00 1.00 day

0.4 4.00%

hour

417.40 1.00 Hour 4079.94 1.00 Cum

Basic rate per 1 Cum Seignorage Charges Sand


Coarse aggregate Total

14%

Add over heads& contr.profit Exclu. Sei. Charges Add sundries Rate per cum = a+b+c+d+e+f
e)

18.00 45.00 63.00 4180.14 1.00 Cu.m

21 c

P.C.C grade M 15 (MORD) Nominal mix (1:2.5:5) (Mechanical Mixer) Unit = cum (a) Material

0.275 0.48 0.48 0.24 0.08

t cum cum cum cum

Cement Coarse sand 40 mm aggregate 20 mm aggregate 10 mm aggregate (b) Labour Mate Mason (1st Class) Mazdoor (Unskilled) (c) Machinery Concrete mixer 0.4/0.28 cum capacity d) Formwork @ 10 % on cost of material, labour and machinery (a+b+c)

5.70 467.77 1337.51 1832.51 1422.51

1.00 1.00 1.00 1.00 1.00

Kg Cum Cum Cum Cum

day 0.10 1.39 day day

280.00 1.00 day 350.00 1.00 day 280.00 1.00 day 417.40 1.00 Hour 3578.82 1.00 Cum

0.40 10.00%

hour

22 /87

S. No 1

Quantity 2

Unit 3

Description 4

Rate Rs. 5

per 6

Basic rate per 1 Cum Seignorage Charges Sand


Coarse aggregate Total

14%

Add over heads& contr.profit Exclu. Sei. Charges Add sundries Rate per cum = a+b+c+d+e+f

19.20 40.00 59.20 3877.51 1.00 Cu.m

Note : Needle Vibrator is an item of minor T & P which is already included in overhead charges. Hence not added in rate analysis of cement concrete works.

21 d

d)

RBR-FNDN-5
Sub-analysis Cement mortar 1:5 (1 cement : 5 sand) Unit = cum (a) Material

0.288 1.05

t cum

Cement Sand (b) Labour Mate Mazdoor (Unskilled) Total material and labour = (a+b) Cement mortar 1:4 (1 cement : 4 sand) Unit = cum (a) Material

5.70 1.00 Kg 467.77 1.00 Cum 280.00 1.00 day 280.00 1.00 day

day 0.2 day

0.360 1.05

t cum

Cement Sand (b) Labour Mate Mazdoor (Unskilled) Total material and labour = (a+b)

5.70 1.00 Kg 467.77 1.00 Cum 280.00 1.00 day 280.00 1.00 day

day 0.2 day

22

Plastering with cement mortar (1:5), 12 mm thick on brickwork in substructure as per technical specification

RBR-SBST-3 Unit = 10 sqm Taking output = 10 sqm (a) Material


0.144 cum

Cement mortar 1:5 (Rate as in item 11.5 II ) (b) Labour Mate Mason 1st Class Mazdoor (Unskilled)

2188.76 1.00 Cum 280.00 1.00 day 350.00 1.00 day 280.00 1.00 day

day 0.500 0.540 day day

14%

Basic rate per 1 Cum Seignorage Charges Sand Add over heads& contr.profit Exclu. Sei. Charges Add sundries Rate per 10 sq mt Rate per 1 sq mt
Plastering with cement mortar (1:4), on brickwork in substructure as per technical specification Section 1300 & 2200 MORTH

6.05 635.34 1.00 Cu.m

23

23 /87

S. No 1

Quantity 2

Unit 3

Description 4
Unit = 10 sqm Taking output = 10 sqm (a) Material Cement mortar 1:4 (Rate as in item 11.5 II ) (b) Labour Mate Mason 1st Class Mazdoor (Unskilled)

Rate Rs. 5

per 6

0.144

cum

2599.16

1.00 Cum

day 0.500 0.540 day day

280.00 1.00 day 350.00 1.00 day 280.00 1.00 day

14%

Basic rate per 1 Cum Seignorage Charges Sand Add over heads& contr.profit Exclu. Sei. Charges Add sundries Rate per 10 sq mt Rate per 1 sq mt

6.05 694.43 1.00 Cu.m

Assistant Engineer APSHCL, Duggirala

Deputy Executive Engineer APSHCL, Mangalagiri

Executive Engineer APSHCL, Guntur

24 /87

Amount Rs. 7

norage Charges

582.40 9916.20 13159.50 3312.13 26970.23 74.92

672.00 2240.00 19296.00 51138.00 1872.00 5064.00

177886.34 47400.48 204626.02 0.00 510194.84

25 /87

Amount Rs. 7 68742.08 578936.91 1929.79

3382.40 70000.00 15248.40 14976.00

197437.88 196674.97 20738.68 153333.97 29232.29 0.00 701024.60

94212.24 795236.84 2209.00

3382.40 70000.00 61365.60

26 /87

Amount Rs. 7 14976.00 222484.88 268010.25 31922.32 136296.86

29232.29 0.00 837670.61

113418.29 951088.89 2642.00

3382.40 70000.00 61365.60 14976.00

477745.20 143687.11 122904.86

29232.29 0.00 923293.46

27 /87

Amount Rs. 7 125405.48 1048698.94 2913.10

0.00 3382.40 70000.00

61365.60 14976.00

461086.96 122904.86 90864.58

29232.29 0.00

733715.82

99066.21 832782.03

28 /87

Amount Rs. 7 2313.28

730907.82

98673.09 829580.91 2304.39

582.40 999.60 1398.32 1720.00 26025.95 4301.68 35027.95 10.10

2800.00 985.60 114720.00 7920.00 9876.00 3193.37 13494.00 20528.00 217130.79

29 /87

Amount Rs. 7 153631.08 544278.84

75443.04 619721.88 155.00

280.00 6160.00 2002.00 459.80 2822.60 40079.96 12201.85 64006.21

8891.57 72897.78 66.27

672.00 2240.00 61365.60 5064.00 5064.00 1872.00

30 /87

Amount Rs. 7 120810.10 124237.22 0.00 321324.92 43396.88 364721.80 1215.80

112.00 560.00 2240.00

15248.40 1872.00

195248.64 215281.04 28956.63 244237.67 814.20

0.00 694.40 2800.00 19296.00 51138.00 5064.00

31 /87

Amount Rs. 7 3120.00 195248.64 0.00 277361.04 36142.55 313503.59 1045.10

0.00 1750.00 1600.00 42000.00 1680.00 640.00 1680.00

15026.40 1369.80 0.00 1369.80 0.00 3120.00 998.80

81638.33 36203.86 15787.24 149625.00 6187.50

32 /87

Amount Rs. 7

5074.00 185.90 706.42

7245.00 8540.00 0.00 2775.00 11556.10

396759.15

54884.79 0.00 451644.00 6021.92

1853.00 87.00

1940.00 388.00 54.32 0.08 442.40

702.80

140.56 562.24 74.97 10.50

33 /87

Amount Rs. 7

0.03 85.50

3330.00 185.00

3515.00 703.00 98.42 0.08 801.50

702.80

702.80 93.71 13.12 0.07 106.90

4227.00 124.00

4351.00 870.20 121.83 0.07 992.10

702.80

140.56 562.24

34 /87

Amount Rs. 7

74.97 10.50 0.03 85.50

6589.00 233.00

6822.00 1364.40 191.02 0.08 1555.50

702.80

702.80 93.71 13.12 0.07 106.90

0.00 1019.20 142.69 0.01 1161.90 116.19

35 /87

Amount Rs. 7

0.00 86.80 367.77

454.57

58.04 0.09 512.70

0.00 145.60 508.46

654.06

88.49 0.05 742.60

1254.00 210.50 1203.76 0.00 0.00 35.00 389.20 166.96 81.12

36 /87

Amount Rs. 7 0.00

3340.54

458.86 0.00 3799.40

1881.00 210.50 481.51 659.71 256.06 0.00 35.00 389.20

166.96 163.20

4243.14

585.22 0.04 4828.40

1567.50 224.53 642.01 439.81 113.81 0.00 35.00 389.20 166.96 357.89

37 /87

Amount Rs. 7

3936.71

542.86 0.03 4479.60

Hence not added in rate analysis of cement

1641.60 491.16 0.00 56.00

2188.76

2052.00 491.16 0.00 56.00

2599.16

315.19 0.00 175.00 151.20

641.39

88.95 0.06 730.40 73.04

38 /87

Amount Rs. 7

374.28 0.00 175.00 151.20

700.48

97.23 0.09 797.80 79.78

Executive Engineer APSHCL, Guntur

39 /87

Labour & Materials Name of the Work: Construction of Side Drains and CC Roads in Godavarru Village of Duggirala Mandal SSR
MUNICIPAL ALLOWANCE
Overheads & Contractor's Profit

"13-14 0% 14% LABOUR CHARGES


SSR Sl.No. I-11 II-35 I-11 II-35 I-35 II-37 II-10 III-3 III-4 I-5 II-34 II-34 pno.231/1292 Initial Rate 350.00 320.00 350.00 320.00 400.00 320.00 320.00 280.00 280.00 400.00 320.00 320.00 70.00
0% Allow.

Sl.No. 1 2 3 4 5 6 7 8 9 10 11 12 13

Description 1st class mason 2nd class mason 1st class Brick Layer 2nd class Brick layer 1st class Painter 2nd class Painter Head mazdoor Man mazdoor Woman mazdoor skilled electrician semiskilled electrician helper Cost of binding wire

Final Rate 350.00 320.00 350.00 320.00 400.00 320.00 320.00 280.00 280.00 400.00 320.00 320.00 70.00

Unit per day per day per day per day per day per day per day per day per day per day per day per day per Kg

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

HIRE CHARGES FOR ACCESS SCAFFOLDING - up to 3.66 M using Casurina Bellies, Bamboos, Wooden Reapers, Runners, Wood Posts, Wall Plates etc., for BRICK MASONRY/STONE MASONRY - 1 sqm(Pno.91) A 1st - Floor B 2nd - Floor C 3rd - Floor D 4th - Floor per 1 sqm per 1 sqm per 1 sqm per 1 sqm Rs. Rs. Rs. Rs. 8.99 8.99 8.99 8.99 Rs. Rs. Rs. Rs. 54.34 77.01 99.69 122.36 Rs. Rs. Rs. Rs.

HIRE CHARGES FOR ACCESS SCAFFOLDING - up to 3.66 M using Casurina Bellies, Bamboos, Wooden Reapers, Runners, Wood Posts, Wall Plates etc., for PLASTERING TO WALLS - 1 sqm(Pno-91) A 1st - Floor B 2nd - Floor C 3rd - Floor D 4th - Floor per 1 sqm per 1 sqm per 1 sqm per 1 sqm Rs. Rs. Rs. Rs. 0.90 0.90 0.90 0.90 Rs. Rs. Rs. Rs. 5.43 7.70 9.97 12.24 Rs. Rs. Rs. Rs.

HIRE CHARGES FOR STAGE SCAFFOLDING - up to 3.66 M using Casurina Bellies, Bamboos, Wooden Reapers, Runners, Wood Posts, Wall Plates etc., for CEILING PLASTERING - 1 sqm(Pno.92) A 1st - Floor B 2nd - Floor C 3rd - Floor per 1 sqm per 1 sqm per 1 sqm Rs. Rs. Rs. 2.11 2.11 2.11 Rs. Rs. Rs. 11.08 15.57 20.05 Rs. Rs. Rs.

Page 40 of 87

D 4th - Floor

per 1 sqm

Rs.

2.11

Rs.

24.54

Rs.

MATERIAL RATES OF BUILDING ITEMS Sl. No. 1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 22 23 24 25 Description of Item 2 White Cement Surya Cem or Equivalent Quality Water proof Cement Superior Quality Snowcem or Equv. Quality Oil Bound Distemper POWDER Oil Bound Distemper Wood Primer Red Oxide Primer Paint Grade-I Cement Primer Grade - I Synthetic enamel paint 1st quality (All Shades) Plastic emulsion paint Impervious Water proofing compound Cost of binding wire Cement Jally 50mm thick Cement Jally 40mm thick Ceramic tiles 7.3mm thick White Glazed Tiles of any Size 1st. Quality Vitrified floor tiles 600 x 600 mm normal colour 1 st quality Mastic Pad 0.60 x 1.20 Mts, 25.4mm thick Mastic Pad 0.60 x 1.20 Mts, 12.7mm thick Polished kadapa slabs Polished kadapa slabs 25mm thick Rabbit wire mesh RCC Door Frame size 0.98 X1.98 mt (NK Materials) RCC Door Frame size 0.75 X1.98 mt (NK Materials) RCC Window Frame size 0.90 X1.20 mt (NK Materials)
SSR Sl. No.

Unit 4 Kg Kg Kg Kg Ltr Kg

Rate 5 27.00 20.60 47.00 44.24 40.00 81.00 135.00 121.00 134.00 230.00 244.00 24.00 70.00 375.00 274.00 447.00 335.00 1008.00 925.00 530.00 1544.00 3603.00 16.00 0.00 0.00 0.00

3 BMS-W.68 BMT.J.27 BMT.J.24 BMT.J.26 BMT.J.20 BMT.J.21

BMT.J.05 Ltr BMT.J.03 Ltr BMT.J.01 Kg BMT.J.30 Ltr BMT.J.22 Ltr BMT.H.01 Kg CSSR-A.03 Kg BMS.W.17 Sqmt. BMS.W.16 Sqmt. BMT.C.01 Sqmt. BMT.C.06 Sqmt. BMT.B.16 Sqmt. BMS.W.20 Sqmt. BMS.W.21 Sqmt. BMT.B.05 10Sqmt. BMT.B.07 10Sqmt. BMT-F.28 Sqmt. 1 No 1 No 1 No

Page 41 of 87

avarru Village of

amboos, Wooden Reapers, m(Pno.91) 63.33 86.00 108.68 131.35

amboos, Wooden Reapers, 6.33 8.60 10.87 13.14

mboos, Wooden Reapers, 13.19 17.68 22.16 Page 42 of 87

26.65

Page 43 of 87

LEAD STATEMENT Name of the Work: Construction of Side Drains and CC Roads in Godavarru Village of Duggirala Mandal SSR "13-14 Muncipal Allowancwe 0% Contractor Profit 14% FOR BUILDINGS-CCRoads-CCDrains SI. No. Conveyance Charges Description SSR Sl.No. Source of Material Unit Initial Cost DISTANCE TOTAL RATE 22.81 22.81 482.51 482.51 482.51 482.51 482.51 3.00 3.00 3.00 188.48 0.00 0.00 0.00 368.50 482.51 368.50 0.00 Tenali Tenali Tenali Tenali Tenali Tenali RM RM RM RM RM RM 348.00 611.00 993.00 791.00 1235.00 2019.00 25.00 25.00 25.00 25.00 25.00 25.00 22.60 55.00 94.20 54.40 82.80 156.00 Loading charges Unloading charges
Area allowence on loading & unloading charges @

Total

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 1 23 24

Sand for Mortor Sand for Filling 6mm HBG Metal 10 mm HBG metal 12 mm HBG metal 20 mm HBG metal 40 mm HBG metal FAL-G.block (290x200x140) FAL-G.block (290x150x140) FAL-G.block (290x100x140) 2nd class Country brick Cement Water Steel Gravel Stone crusher dust Quarry Rubbish Earth(Conveyance only) 300 dia. RCC NP2 class Plain ended pipes 450 dia. RCC NP2 class Plain ended pipes 600 dia. RCC NP2 class Plain ended pipes 300 dia. RCC NP3 class Plain ended pipes 450 dia. RCC NP3 class Plain ended pipes 600 dia. RCC NP3 class Plain ended pipes

M-005 M-004 M-050 M-051 M-052 M-053 M-055 BMT-A11 BMT-A12 BMT-A13 BMT-A01 0 0 0 M-008 M-021 M-148

Krishna River Krishna River Lam Lam Lam Lam Lam Local Local Local Kollipara Local Local Local Vejandla Lam Vejandla

Cu.m Cu.m Cu.m Cu.m Cu.m Cu.m Cu.m 1 No 1 No 1 No 1000 No 1kg KL MT 1 Cu.m 1 Cum Cu.m

425.00 325.00 750.00 940.00 1095.00 1350.00 855.00 16.00 12.00 10.00 3707.00 5.70 0.00 43000.00 120.00 390.00 267.00

3.00 3.00 50.00 50.00 50.00 50.00 50.00 0.00 0.00 0.00 12.00 0.00 0.00 0.00 37.00 50.00 37.00

13.31 13.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 36.60 0.00 0.00 0.00 13.31 13.31 13.31

6.65 6.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 36.60 0.00 0.00 0.00 6.65 6.65 6.65

0% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

467.77 367.77 1232.51 1422.51 1577.51 1832.51 1337.51 19.00 15.00 13.00 3968.68 5.70 0.00 43000.00 508.46 892.47 655.46 0.00 370.60 666.00 1087.20 845.40 1317.80 2175.00

1. Certified that the above leads are corrcet and best of my knowledge. Assistant Engineer Deputy Executive Engineer Executive Engineer

APSHCL, Duggirala

APSHCL, Mangalagiri

APSHCL, Guntur

LEAD STATEMENT Name of the Work: Construction of Side Drains and CC Roads in Godavarru Village of Duggirala Mandal SSR "13-14 Muncipal Allowancwe 0% Contractor Profit 14% FOR ROADS & Levelling Works SI. No. 1 2 3 4 5 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Sand for Mortor Sand for Filling 60 to 63 mm IRC and MoRTH HBG metal 50 to 55 mm IRC and MoRTH HBG metal 40 to 45 mm IRC and MoRTH HBG metal SS Revetment work 300mm Quarry spall (Field picked metal) Av. of rate 25mm & 40mm 150 mm soling stone HBG metal 40 to 45 mm IRC and MoRTH HBG M/C metal 25 to 27 mm IRC and MoRTH HBG M/C metal 19 to 22 mm IRC and MoRTH HBG M/C metal 12 to 14 mm IRC and MoRTH HBG M/C metal 9.5 to 11.20 mm IRC and MoRTH HBG M/C metal 5 to 7 mm IRC and MoRTH HBG M/C metal 2.36 to 5 mm IRC and MoRTH HBG M/C metal HBG Stone chips 2.36mm and below 75mm size IRC and Morth HBG metal 65mm size IRC and Morth HBG metal FAL-G.block (290x200x140) FAL-G.block (290x150x140)

Description

SSR Sl.No.

Source of Material

Unit

Initial Cost

Conveyance Charges TOTAL DISTANCE RATE 3.00 3.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 0.00 0.00 0.00 12.00 0.00 0.00 37.00 50.00 900.00 22.81 22.81 482.51 482.51 482.51 482.51 482.51 482.51 482.51 482.51 482.51 482.51 482.51 482.51 482.51 482.51 482.51 482.51 3.00 3.00 3.00 188.48 0.00 0.00 368.50 482.51 1350.00

Loading charges 13.31 13.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 36.60 0.00 0.00 13.31 13.31 0.00

Unloading charges 6.65 6.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 36.60 0.00 0.00 6.65 6.65 0.00

M-005 M-004

Krishna River Krishna River Lam Lam Lam Lam Lam Lam Lam Lam Lam Lam Lam Lam Lam Lam Lam Lam

Cu.m Cu.m Cu.m Cu.m Cu.m Cu.m Cu.m Cu.m Cu.m Cu.m Cu.m Cu.m Cu.m Cu.m Cu.m Cu.m Cu.m Cu.m 1 No 1 No 1 No 1000 No 1kg KL 1 Cu. 1 Cum ton 1mt

425.00 325.00 539.00 576.00 708.00 276.00 165.00 186.00 855.00 1300.00 1350.00 1095.00 940.00 750.00 505.00 532.50 424.00 499.00 16.00 12.00 10.00 3707.00 5.70 0.00 120.00 390.00 43000 35829.93

Area allowence on loading & unloading charges 0% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total

467.77 367.77 1021.51 1058.51 1190.51 758.51 647.51 668.51 1337.51 1782.51 1832.51 1577.51 1422.51 1232.51 987.51 1015.01 906.51 981.51 19.00 15.00 13.00 3968.68 5.70 0.00 508.46 892.47 43000.00 37179.93

BMT-A11 BMT-A12

Local Local

24 FAL-G.block (290x100x140) BMT-A13 Local 25 2nd class Country brick BMT-A01 Kollipara 26 Cement 0 Local 27 Water 0 Local 28 Gravel M-008 Vejandla 29 Stone crusher dust M-021 Lam 30 Mild steel Local 31 Bitumen Vishakhapatnam Conveyance of Bitumen for Bulk and packed Rs.1.50 KM/MT 1. Certified that the above leads are corrcet and best of my knowledge.

APSHCL, Duggirala

APSHCL, Mangalagiri

APSHCL, Guntur

Seigniorage charges

50.00 ROAD METAL RATES Initial cost Including stacking Blasting charges 70.00 419.00 456.00 588.00 156.00 45.00 66.00 588.00 944.00 984.00 780.00 656.00 504.00 308.00 330.00 304.00 379.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00 70.00

Sl. No

Description of Metal

A) FOR ROAD WORKS 1 2 3 4 5 6 4 5 6 7 9 60 to 63 mm IRC and MoRTH HBG metal 50 to 55 mm IRC and MoRTH HBG metal 40 to 45 mm IRC and MoRTH HBG metal SS Revetment work 300mm Quarry spall (Field picked metal) Av. of rate 25mm & 40mm 150 mm soling stone HBG metal 40 to 45 mm IRC and MoRTH HBG M/C metal 25 to 27 mm IRC and MoRTH HBG M/C metal 19 to 22 mm IRC and MoRTH HBG M/C metal 12 to 14 mm IRC and MoRTH HBG M/C metal 9.5 to 11.20 mm IRC and MoRTH HBG M/C metal

10 5 to 7 mm IRC and MoRTH HBG M/C metal 11 2.36 to 5 mm IRC and MoRTH HBG M/C metal 12 HBG Stone chips 2.36mm and below 13 75mm size IRC and Morth HBG metal 13 65mm size IRC and Morth HBG metal

RATES Machine crushing charges 25% 0.00 0.00 0.00 0.00 0.00 0.00 147.00 236.00 246.00 195.00 164.00 126.00 77.00 82.50 0.00 0.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 539.00 576.00 708.00 276.00 165.00 186.00 855.00 1300.00 1350.00 1095.00 940.00 750.00 505.00 532.50 424.00 499.00 Seigniorage charges Deduct stacking charges for conveyance Toal Cost per Cum

a) b) c) d) e)

LEAD, LOADING & UNLOADING STATEMENT HIRE CHARGES OF MACHINERY Hire Fuel Crew Total Charges Charges Charges Hire charges of Tipper 5.00 456.20 280.70 140.40 877.30 Cum capacity Hire charges of Tipper 10 422.80 280.70 140.40 843.90 Tonnes capacity Hire charges of Water Tanker 411.00 280.70 140.40 832.10 8000 Ltrs capacity Hire charges of Truck 10 422.80 280.70 140.40 843.90 Tonnes capacity Hire charges of FE loader 422.80 280.70 140.40 843.90 1.00 Cum bucket capacity @ 45 Cum 120.30 7.80 54.60 114.10 19.00 74.30 269.50 125.40 174.20 503.90 152.20 303.10

Per Hour Hour Hour Hour Hour

f) Batching plant 0.5 cum vibrator 40mm g) Needle (petrol) mixer 300/200 g) Concrete (diesel) SSR hire charges Pg.no.325, Sl. No.16

Hour Hour Hour

Hire Charges Roads & Irrigation Works Machinery Hydraulic Excavator Tipper 5.5 Cum Motar Grader Vibratory roller 8 tonnes Water tanker 6KL capacity 2754.50 877.30 3216.00 2541.40 624.00 Mechanical Broom Hydraulic 357.00 Emulson Pressure Distributor 860.00 Hot mix plant 40 to 60 TPH Capacity 19120.00 Electric Generator 125 KVA 1320.00 Front End loader 1646.00 Paver finisher Mechanical 100 TPH 2249.00 Penumatic Road Roller (Static Roller 1283.00 Bitumen boiler oil fired (Bitumen Spraying) 209.00 Concrete Mixer 0.28 Cum 417.40 Air Compressor 499.40 Tractor with ripper attachment 422.00 Three wheel 80-100 kN Static Roller 1704.60 RATES FOR CONVEYANCE BY MACHINERY Mincipal area allowance Industrial area allowance Agency area allowance Allowable allowance Add Overhead Charges & Contractor's Profit For Earth/Gravel/Sand/Morrum/Lime/Surki (per Cum): Lead up to 1 Km: Out put = 5.00 Cum Rate Per 0.15 Hrs. hire charges of Tipper 5.00 Cum @ Rs. 456.20 Hour 0.15 Hrs. fuel charges of Tipper 5.00 Cum @ Rs. 280.70 Hour 0.15 Hrs. crew charges of Tipper 5.00 Cum @ Rs. 140.40 Hour 0.00 add area allowance at 0% on Rs. 21.06 Rate for 5.00 Cum Rate for 1.00 Cum Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour 0.00% 0.00% 0.00% 0.00% 0.00%

1 2 3 4 5 A) 1

Rs. Rs. Rs. Rs. Rs. Rs.

Amount 68.43 42.11 21.06 0.00 131.60 26.32

0.00 add overheads and contractors profit at 0% on Rs. Total rate for 1.00 Cum

26.32

Rs. Rs. Per Hour Hour Hour

0.00 26.32 Amount 95.80 58.95 29.48 0.00 184.23 36.85 0.00 36.85

2 Lead up to 2 Km: Out put = 5.00 Cum Rate 0.21 Hrs. hire charges of Tipper 5.00 Cum @ Rs. 456.20 0.21 Hrs. fuel charges of Tipper 5.00 Cum @ Rs. 280.70 0.21 Hrs. crew charges of Tipper 5.00 Cum @ Rs. 140.40 0.00 add area allowance at 0% on Rs. 29.48 Rate for 5.00 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% 36.85 on Rs. Total rate for 1.00 Cum 3 Lead up to 3 Km: Out put = 5.00 Cum Rate 456.20 280.70 140.40 39.31

Hour

Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

Per Hour Hour Hour Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Per Hour Hour Hour

Amount 127.74 78.60 39.31 0.00 245.65 49.13 0.00 49.13 Amount 155.11 95.44 47.74 0.00 298.29 59.66 0.00 59.66 Amount 182.48 112.28 56.16 0.00 350.92 70.18 0.00 70.18 Amount 27.37 16.84 8.42 0.00 52.63

0.28 Hrs. hire charges of Tipper 5.00 Cum @ Rs. 0.28 Hrs. fuel charges of Tipper 5.00 Cum @ Rs. 0.28 Hrs. crew charges of Tipper 5.00 Cum @ Rs. 0.00 add area allowance at 0% on Rs. Rate for 5.00 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% on Rs. Total rate for 1.00 Cum

49.13

Hour

4 Lead up to 4 Km: Out put = 5.00 Cum Rate 0.34 Hrs. hire charges of Tipper 5.00 Cum @ Rs. 456.20 0.34 Hrs. fuel charges of Tipper 5.00 Cum @ Rs. 280.70 0.34 Hrs. crew charges of Tipper 5.00 Cum @ Rs. 140.40 0.00 add area allowance at 0% on Rs. 47.74 Rate for 5.00 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% 59.66 on Rs. Total rate for 1.00 Cum 5 Lead up to 5 Km: Out put = 5.00 Cum Rate 0.40 Hrs. hire charges of Tipper 5.00 Cum @ Rs. 456.20 0.40 Hrs. fuel charges of Tipper 5.00 Cum @ Rs. 280.70 0.40 Hrs. crew charges of Tipper 5.00 Cum @ Rs. 140.40 0.00 add area allowance at 0% on Rs. 56.16 Rate for 5.00 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% 70.18 on Rs. Total rate for 1.00 Cum 6 Lead for every Km from 5 to 30 Km: Out put = 5.00 Cum 0.06 Hrs. hire charges of Tipper 5.00 Cum @ Rs. 0.06 Hrs. fuel charges of Tipper 5.00 Cum @ Rs. 0.06 Hrs. crew charges of Tipper 5.00 Cum @ Rs. 0.00 add area allowance at 0% on Rs. Rate for 5.00 Cum Rate 456.20 280.70 140.40 8.42

Hour

Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

Per Hour Hour Hour

Hour

Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

Per Hour Hour Hour

Rs. Rs. Rs. Rs. Rs.

Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% on Rs. Total rate for 1.00 Cum

10.53

Hour

Rs. Rs. Rs.

10.53 0.00 10.53 Amount 22.81 14.04 7.02 0.00 43.87 8.77 0.00 8.77

7 Lead for every Km beyond 30 Km: Out put = 5.00 Cum Rate 0.05 Hrs. hire charges of Tipper 5.00 Cum @ Rs. 456.20 0.05 Hrs. fuel charges of Tipper 5.00 Cum @ Rs. 280.70 0.05 Hrs. crew charges of Tipper 5.00 Cum @ Rs. 140.40 0.00 add area allowance at 0% on Rs. 7.02 Rate for 5.00 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% 8.77 on Rs. Total rate for 1.00 Cum

Per Hour Hour Hour

Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

B) For Rubble/Size stones/Cut stones/Coarse aggregates (per Cum): 1 Lead up to 1 Km: Out put = 5.00 Cum Rate 0.15 Hrs. hire charges of Tipper 5.00 Cum @ Rs. 456.20 0.15 Hrs. fuel charges of Tipper 5.00 Cum @ Rs. 280.70 0.15 Hrs. crew charges of Tipper 5.00 Cum @ Rs. 140.40 0.00 add area allowance at 0% on Rs. 21.06 Rate for 5.00 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% 26.32 on Rs. Total rate for 1.00 Cum 2 Lead up to 2 Km: Out put = 5.00 Cum Rate 0.21 Hrs. hire charges of Tipper 5.00 Cum @ Rs. 456.20 0.21 Hrs. fuel charges of Tipper 5.00 Cum @ Rs. 280.70 0.21 Hrs. crew charges of Tipper 5.00 Cum @ Rs. 140.40 0.00 add area allowance at 0% on Rs. 29.48 Rate for 5.00 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% 36.85 on Rs. Total rate for 1.00 Cum 3 Lead up to 3 Km: Out put = 5.00 Cum Rate 0.28 Hrs. hire charges of Tipper 5.00 Cum @ Rs. 456.20 0.28 Hrs. fuel charges of Tipper 5.00 Cum @ Rs. 280.70 0.28 Hrs. crew charges of Tipper 5.00 Cum @ Rs. 140.40 0.00 add area allowance at 0% on Rs. 39.31 Rate for 5.00 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% 49.13 on Rs. Total rate for 1.00 Cum 4 Lead up to 4 Km: Out put = 5.00 Cum 0.34 Hrs. hire charges of Tipper 5.00 Cum @ Rs. 0.34 Hrs. fuel charges of Tipper 5.00 Cum @ Rs. 0.34 Hrs. crew charges of Tipper 5.00 Cum @ Rs. 0.00 add area allowance at 0% on Rs. Rate for 5.00 Cum Rate 456.20 280.70 140.40 47.74 Per Hour Hour Hour Amount 68.43 42.11 21.06 0.00 131.60 26.32 0.00 26.32 Amount 95.80 58.95 29.48 0.00 184.23 36.85 0.00 36.85 Amount 127.74 78.60 39.31 0.00 245.65 49.13 0.00 49.13 Amount 155.11 95.44 47.74 0.00 298.29

Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

Per Hour Hour Hour

Hour

Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

Per Hour Hour Hour

Hour

Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

Per Hour Hour Hour

Rs. Rs. Rs. Rs. Rs.

Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% on Rs. Total rate for 1.00 Cum

59.66

Hour

Rs. Rs. Rs.

59.66 0.00 59.66 Amount 182.48 112.28 56.16 0.00 350.92 70.18 0.00 70.18 Amount 27.37 16.84 8.42 0.00 52.63 10.53 0.00 10.53 Amount 22.81 14.04 7.02 0.00 43.87 8.77 0.00 8.77

5 Lead up to 5 Km: Out put = 5.00 Cum Rate 0.40 Hrs. hire charges of Tipper 5.00 Cum @ Rs. 456.20 0.40 Hrs. fuel charges of Tipper 5.00 Cum @ Rs. 280.70 0.40 Hrs. crew charges of Tipper 5.00 Cum @ Rs. 140.40 0.00 add area allowance at 0% on Rs. 56.16 Rate for 5.00 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% 70.18 on Rs. Total rate for 1.00 Cum 6 Lead for every Km from 5 to 30 Km: Out put = 5.00 Cum 0.06 Hrs. hire charges of Tipper 5.00 Cum @ Rs. 0.06 Hrs. fuel charges of Tipper 5.00 Cum @ Rs. 0.06 Hrs. crew charges of Tipper 5.00 Cum @ Rs. 0.00 add area allowance at 0% on Rs. Rate for 5.00 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% on Rs. Total rate for 1.00 Cum Rate 456.20 280.70 140.40 8.42

Per Hour Hour Hour

Hour

Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

Per Hour Hour Hour

Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

10.53

Hour

7 Lead for every Km beyond 30 Km: Out put = 5.00 Cum Rate 0.05 Hrs. hire charges of Tipper 5.00 Cum @ Rs. 456.20 0.05 Hrs. fuel charges of Tipper 5.00 Cum @ Rs. 280.70 0.05 Hrs. crew charges of Tipper 5.00 Cum @ Rs. 140.40 0.00 add area allowance at 0% on Rs. 7.02 Rate for 5.00 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% 8.77 on Rs. Total rate for 1.00 Cum F) For Bricks (per 1000 Nos): 1 Lead up to 1 Km: Out put = 3000 Nos 0.15 Hrs. hire charges of Truck 10 Tonnes capacity @ Rs. 0.15 Hrs. fuel charges of Truck 10 Tonnes capacity @ Rs. 0.15 Hrs. crew charges of Truck 10 Tonnes capacity @ Rs. 0.00 add area allowance at 0% on Rs. Rate for 3000 Nos Rate for 1000 Nos 0.00 add overheads and contractors profit at 0% on Rs. Total rate for 1000 Nos 2 Lead up to 2 Km: Out put = 3000 Nos 0.21 Hrs. hire charges of Truck 10 Tonnes capacity @ Rs.

Per Hour Hour Hour

Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

Rate 422.80 280.70 140.40 21.06 42.20

Per Hour Hour Hour

Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

Amount 63.42 42.11 21.06 0.00 126.59 42.20 0.00 42.20 Amount 88.79

Rate 422.80

Per Hour

Rs.

0.21 Hrs. fuel charges of Truck 10 Tonnes capacity 280.70 @ Rs. 0.21 Hrs. crew charges of Truck 10 Tonnes 140.40 capacity @ Rs. 0.00 add area allowance at 0% on Rs. 29.48 Rate for 3000 Nos Rate for 1000 Nos 0.00 add overheads and contractors profit at 0% 59.07 on Rs. Total rate for 1000 Nos 3 Lead up to 3 Km: Out put = 3000 Nos Rate 0.28 Hrs. hire charges of Truck 10 Tonnes capacity 422.80 @ Rs. 0.28 Hrs. fuel charges of Truck 10 Tonnes capacity 280.70 @ Rs. 0.28 Hrs. crew charges of Truck 10 Tonnes 140.40 capacity @ Rs. 0.00 add area allowance at 0% on Rs. 39.31 Rate for 3000 Nos Rate for 1000 Nos 0.00 add overheads and contractors profit at 0% 78.76 on Rs. Total rate for 1000 Nos

Hour Hour

Rs. Rs. Rs. Rs. Rs. Rs. Rs.

58.95 29.48 0.00 177.22 59.07 0.00 59.07 Amount 118.38 78.60 39.31 0.00 236.29 78.76 0.00 78.76

Per Hour Hour Hour

Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

4 Lead up to 4 Km: Out put = 3000 Nos Rate 0.34 Hrs. hire charges of Truck 10 Tonnes capacity 422.80 @ Rs. 0.34 Hrs. fuel charges of Truck 10 Tonnes capacity 280.70 @ Rs. 0.34 Hrs. crew charges of Truck 10 Tonnes 140.40 capacity @ Rs. 0.00 add area allowance at 0% on Rs. 47.74 Rate for 3000 Nos Rate for 1000 Nos 0.00 add overheads and contractors profit at 0% 95.64 on Rs. Total rate for 1000 Nos 5 Lead up to 5 Km: Out put = 3000 Nos 0.40 Hrs. hire charges of Truck 10 Tonnes capacity @ Rs. 0.40 Hrs. fuel charges of Truck 10 Tonnes capacity @ Rs. 0.40 Hrs. crew charges of Truck 10 Tonnes capacity @ Rs. 0.00 add area allowance at 0% on Rs. Rate for 3000 Nos Rate for 1000 Nos 0.00 add overheads and contractors profit at 0% on Rs. Total rate for 1000 Nos Rate 422.80 280.70 140.40 56.16 112.52

Per Hour Hour Hour

Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

Amount 143.75 95.44 47.74 0.00 286.93 95.64 0.00 95.64 Amount 169.12 112.28 56.16 0.00 337.56 112.52 0.00 112.52 Amount 25.37 16.84 8.42 0.00 50.63 16.88 0.00 16.88 Amount 21.14 14.04 7.02 0.00 42.20 14.07 0.00 14.07

Per Hour Hour Hour

Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

6 Lead for every Km beyond 5 Kms up to 30 Kms: Out put = 3000 Nos Rate 0.06 Hrs. hire charges of Truck 10 Tonnes capacity 422.80 @ Rs. 0.06 Hrs. fuel charges of Truck 10 Tonnes capacity 280.70 @ Rs. 0.06 Hrs. crew charges of Truck 10 Tonnes 140.40 capacity @ Rs. 0.00 add area allowance at 0% on Rs. 8.42 Rate for 3000 Nos Rate for 1000 Nos 0.00 add overheads and contractors profit at 0% 16.88 on Rs. Total rate for 1000 Nos 7 Lead for every Km beyond 30 Kms: Out put = 3000 Nos Rate 0.05 Hrs. hire charges of Truck 10 Tonnes capacity 422.80 @ Rs. 0.05 Hrs. fuel charges of Truck 10 Tonnes capacity 280.70 @ Rs. 0.05 Hrs. crew charges of Truck 10 Tonnes 140.40 capacity @ Rs. 0.00 add area allowance at 0% on Rs. 7.02 Rate for 3000 Nos Rate for 1000 Nos 0.00 add overheads and contractors profit at 0% 14.07 on Rs. Total rate for 1000 Nos

Per Hour Hour Hour

Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

Per Hour Hour Hour

Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

LOADING & UNLOADING CHARGES BY MANUAL MEANS (EXCLUDING IDLE HIRE CHARGES OF TRUCKS) A) For Earth, Sand, Morrum, Manure, Fly Ash (per Cum): (i) Loading charges: Out put = 5.50 Cum Rate a) Labour: 0.01 day Head mazdoor 320.00 0.25 day Mazdoor 280.00 0.00 add area allowance at 0% on Rs. Total labour charges Rate for 5.50 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% on Rs. Total rate for 1.00 Cum (ii) Unloading charges: Out put = 5.50 Cum a) Labour: 0.005 day Head mazdoor 0.125 day Mazdoor 0.00 add area allowance at 0% on Rs. Total labour charges Rate for 5.50 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% on Rs. Total rate for 1.00 Cum 73.20

Per day day Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

Amount 3.20 70.00 73.20 0.00 73.20 73.20 13.31 0.00 13.31 Amount Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. 1.60 35.00 36.60 0.00 36.60 36.60 6.65 0.00 6.65

13.31

Rate 320.00 280.00 36.60

Per day day

6.65

B) For Lime, Agrregate, Stone Boulder, Brick aggregate, Kankar, Building rubbish, Crushed slag, Stone for masonry work (per Cum): (i) Loading charges: Out put = 5.50 Cum a) Labour: 0.02 day Head mazdoor 0.50 day Mazdoor Rate 320.00 280.00 Per day day Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Per day day Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Amount 6.40 140.00 146.40 0.00 146.40 146.40 26.62 0.00 26.62 Amount 3.20 70.00 73.20 0.00 73.20 73.20 13.31 0.00 13.31

0.00 add area allowance at 0% on Rs. 146.40 Total labour charges Rate for 5.50 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% 26.62 on Rs. Total rate for 1.00 Cum (ii) Unloading charges: Out put = 5.50 Cum a) Labour: 0.01 day Head mazdoor 0.25 day Mazdoor 0.00 add area allowance at 0% on Rs. Total labour charges Rate for 5.50 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% on Rs. Total rate for 1.00 Cum Rate 320.00 280.00 73.20

13.31

C) For Cement (per Tonne): (i) Loading charges: Out put = 10.00 MT a) Labour: 0.06 day Head mazdoor 1.50 day Mazdoor

Rate 320.00 280.00

Per day day Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

Amount 19.20 420.00 439.20 0.00 439.20 439.20 43.92 0.00 43.92

0.00 add area allowance at 0% on Rs. 439.20 Total labour charges Rate for 10.00 MT Rate for 1.00 MT 0.00 add overheads and contractors profit at 0% 43.92 on Rs. Total rate for 1.00 MT (ii) Unloading & Stacking charges: Out put = 10.00 MT Rate 320.00 280.00 439.20 Per day day

Amount Rs. Rs. Rs. Rs. Rs. Rs. Rs. 19.20 420.00 439.20 0.00 439.20 439.20 43.92 0.00 43.92

a) Labour: 0.06 day Head mazdoor 1.50 day Mazdoor 0.00 add area allowance at 0% on Rs. Total labour charges Rate for Rate for 10.00 MT 1.00 MT

0.00 add overheads and contractors profit at 0% on Rs. Total rate for 1.00 MT D) For Structural steel, Steel bars (per Tonne): (i) Loading charges: Out put = 10.00 MT a) Labour: 0.07 day Head mazdoor 1.80 day Mazdoor

43.92

Rs. Rs.

Rate 320.00 280.00

Per day day Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Per day day Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

Amount 22.40 504.00 526.40 0.00 526.40 526.40 52.64 0.00 52.64 Amount 22.40 504.00 526.40 0.00 526.40 526.40 52.64 0.00 52.64

0.00 add area allowance at 0% on Rs. 526.40 Total labour charges Rate for 10.00 MT Rate for 1.00 MT 0.00 add overheads and contractors profit at 0% 52.64 on Rs. Total rate for 1.00 MT (ii) Unloading & Stacking charges: Out put = 10.00 MT a) Labour: 0.07 day Head mazdoor 1.80 day Mazdoor Rate 320.00 280.00

0.00 add area allowance at 0% on Rs. 526.40 Total labour charges Rate for 10.00 MT Rate for 1.00 MT 0.00 add overheads and contractors profit at 0% 52.64 on Rs. Total rate for 1.00 MT

E) For Bricks of size 225 x 140 x 70mm (per 1000 Nos): (i) Loading charges: Out put = 2000.00 Nos Rate a) Labour: 0.01 day Head mazdoor 320.00 0.25 day Mazdoor 280.00 0.00 add area allowance at 0% on Rs. Total labour charges Rate for 2000 Nos Rate for 1000 Nos 0.00 add overheads and contractors profit at 0% on Rs. Total rate for 1000 Nos (ii) Unloading & Stacking charges: Out put = 2000.00 Nos a) Labour: 0.01 day Head mazdoor 0.25 day Mazdoor 0.00 add area allowance at 0% on Rs. Total labour charges Rate for Rate for 2000 Nos 1000 Nos 36.60 73.20

Per day day Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

Amount 3.20 70.00 73.20 0.00 73.20 73.20 36.60 0.00 36.60 Amount Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. 3.20 70.00 73.20 0.00 73.20 73.20 36.60 0.00 36.60

36.60

Rate 320.00 280.00 73.20

Per day day

0.00 add overheads and contractors profit at 0% on Rs. Total rate for 1000 Nos

LOADING & UNLOADING CHARGES BY MANUAL MEANS (INCLUDING IDLE HIRE CHARGES OF TRUCKS) A) For Earth, Sand, Morrum, Manure, Fly Ash (per Cum): (i) Loading charges: Out put = 5.50 Cum Rate a) Labour: 0.01 day Head mazdoor 320.00 0.25 day Mazdoor 280.00 0.00 add area allowance at 0% on Rs. 73.20 Total labour charges b) Machinery: 0.50 Hrs. hire charges of Truck 10 Tonnes capacity 422.80 @ Rs. 0.50 Hrs. fuel charges of Truck 10 Tonnes capacity 280.70 @ Rs. 0.50 Hrs. crew charges of Truck 10 Tonnes 140.40 capacity @ Rs. 0.00 add area allowance at 0% on Rs. 70.20 Total machinery charges Total labour and machinery charges Rate for 5.50 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% 90.03 on Rs. Total rate for 1.00 Cum

Per day day Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

Amount 3.20 70.00 73.20 0.00 73.20 211.40 140.35 70.20 0.00 421.95 495.15 495.15 90.03 0.00 90.03

Hour Hour Hour

(ii) Unloading charges: Out put = 5.50 Cum a) Labour: 0.005 day Head mazdoor 0.125 day Mazdoor

Rate 320.00 280.00

Per day day Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

Amount 1.60 35.00 36.60 0.00 36.60 70.18 46.60 23.31 0.00 140.09 176.69 176.69 32.13 0.00 32.13

0.00 add area allowance at 0% on Rs. 36.60 Total labour charges b) Machinery: 0.166 Hrs. hire charges of Truck 10 Tonnes capacity 422.80 @ Rs. 0.166 Hrs. fuel charges of Truck 10 Tonnes capacity 280.70 @ Rs. 0.166 Hrs. crew charges of Truck 10 Tonnes 140.40 capacity @ Rs. 0.00 add area allowance at 0% on Rs. 23.31 Total machinery charges Total labour and machinery charges Rate for 5.50 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% 32.13 on Rs. Total rate for 1.00 Cum

Hour Hour Hour

B) For Lime, Agrregate, Stone Boulder, Brick aggregate, Kankar, Building rubbish, Crushed slag, Stone for machinery work (per Cum): (i) Loading charges: Out put = a) Labour: 5.50 Cum Rate 320.00 280.00 146.40 422.80 280.70 140.40 70.20 Hour Hour Hour Per day day Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rate 320.00 280.00 73.20 Per day day Rs. Rs. Rs. Rs. Rs. Amount 6.40 140.00 146.40 0.00 146.40 211.40 140.35 70.20 0.00 421.95 568.35 568.35 103.34 0.00 103.34 Amount 3.20 70.00 73.20 0.00 73.20

0.02 day Head mazdoor 0.50 day Mazdoor 0.00 add area allowance at 0% on Rs. Total labour charges b) Machinery: 0.50 Hrs. hire charges of Truck 10 Tonnes capacity @ Rs. 0.50 Hrs. fuel charges of Truck 10 Tonnes capacity @ Rs. 0.50 Hrs. crew charges of Truck 10 Tonnes capacity @ Rs. 0.00 add area allowance at 0% on Rs. Total machinery charges Total labour and machinery charges Rate for 5.50 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% on Rs. Total rate for 1.00 Cum (ii) Unloading charges: Out put = 5.50 Cum a) Labour: 0.01 day Head mazdoor 0.25 day Mazdoor 0.00 add area allowance at 0% on Rs. Total labour charges

103.34

b) Machinery: 0.25 Hrs. hire charges of Truck 10 Tonnes capacity 422.80 @ Rs. 0.25 Hrs. fuel charges of Truck 10 Tonnes capacity 280.70 @ Rs. 0.25 Hrs. crew charges of Truck 10 Tonnes 140.40 capacity @ Rs. 0.00 add area allowance at 0% on Rs. 35.10 Total machinery charges Total labour and machinery charges Rate for 5.50 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% 51.67 on Rs. Total rate for 1.00 Cum E) For Bricks of size 225 x 140 x 70mm (per 1000 Nos): (i) Loading charges: Out put = 2000.00 Nos Rate a) Labour: 0.01 day Head mazdoor 320.00 0.25 day Mazdoor 280.00 0.00 add area allowance at 0% on Rs. Total labour charges b) Machinery: 0.33 Hrs. hire charges of Truck 10 Tonnes capacity @ Rs. 0.33 Hrs. fuel charges of Truck 10 Tonnes capacity @ Rs. 0.33 Hrs. crew charges of Truck 10 Tonnes capacity @ Rs. 0.00 add area allowance at 0% on Rs. Total machinery charges Total labour and machinery charges Rate for 2000 Nos Rate for 1000 Nos 0.00 add overheads and contractors profit at 0% on Rs. Total rate for 1000 Nos (ii) Unloading & Stacking charges: Out put = 2000.00 Nos a) Labour: 0.01 day Head mazdoor 0.25 day Mazdoor 73.20 422.80 280.70 140.40 46.33

Hour Hour Hour

Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

105.70 70.18 35.10 0.00 210.98 284.18 284.18 51.67 0.00 51.67

Per day day Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

Amount 3.20 70.00 73.20 0.00 73.20 139.52 92.63 46.33 0.00 278.48 351.68 351.68 175.84 0.00 175.84 Amount Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. 3.20 70.00 73.20 0.00 73.20 139.52 92.63 46.33 0.00 278.48 351.68 351.68

Hour Hour Hour

175.84

Rate 320.00 280.00

Per day day

0.00 add area allowance at 0% on Rs. 73.20 Total labour charges b) Machinery: 0.33 Hrs. hire charges of Truck 10 Tonnes capacity 422.80 @ Rs. 0.33 Hrs. fuel charges of Truck 10 Tonnes capacity 280.70 @ Rs. 0.33 Hrs. crew charges of Truck 10 Tonnes 140.40 capacity @ Rs. 0.00 add area allowance at 0% on Rs. 46.33 Total machinery charges Total labour and machinery charges Rate for 2000 Nos

Hour Hour Hour

Rate for 1000 Nos 0.00 add overheads and contractors profit at 0% 175.84 on Rs. Total rate for 1000 Nos

Rs. Rs. Rs.

175.84 0.00 175.84

LOADING & UNLOADING CHARGES BY MECHANICAL MEANS (INCLUDING IDLE HIRE CHARGES OF TRUCKS) A) For Earth, Sand, Morrum, Manure, Fly Ash (per Cum): (i) Loading charges: Out put = 5.50 Cum Rate a) Machinery: 0.11 Hrs. hire charges of Tipper 10 Tonnes 422.80 capacity @ Rs. 0.11 Hrs. fuel charges of Tipper 10 Tonnes 280.70 capacity @ Rs. 0.11 Hrs. crew charges of Tipper 10 Tonnes 140.40 capacity @ Rs. 0.06 Hrs. hire charges of FE loader 1.00 Cum 422.80 bucket capacity @ 45 Cum @ Rs. 0.06 Hrs. fuel charges of FE loader 1.00 Cum 280.70 bucket capacity @ 45 Cum @ Rs. 0.06 Hrs. crew charges of FE loader 1.00 Cum 140.40 bucket capacity @ 45 Cum @ Rs. 0.00 add area allowance at 0% on Rs. 23.86 Total machinery charges Rate for 5.50 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% 26.08 on Rs. Total rate for 1.00 Cum (ii) Unloading charges: Out put = 5.50 Cum Rate a) Machinery: 0.08 Hrs. hire charges of Tipper 10 Tonnes 422.80 capacity @ Rs. 0.08 Hrs. fuel charges of Tipper 10 Tonnes 280.70 capacity @ Rs. 0.08 Hrs. crew charges of Tipper 10 Tonnes 140.40 capacity @ Rs. 0.00 add area allowance at 0% on Rs. 11.23 Total machinery charges Rate for 5.50 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% 12.27 on Rs. Total rate for 1.00 Cum

Per Hour Hour Hour Hour Hour Hour Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Per Hour Hour Hour Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

Amount 46.51 30.88 15.44 25.37 16.84 8.42 0.00 143.46 143.46 26.08 0.00 26.08 Amount 33.82 22.46 11.23 0.00 67.51 67.51 12.27 0.00 12.27

B) For Lime, Agrregate, Stone Boulder, Brick aggregate, Kankar, Building rubbish, Crushed slag, Stone for machinery work (per Cum): (i) Loading charges: Out put = 5.50 a) Machinery: 0.17 Hrs. hire charges capacity @ Rs. 0.17 Hrs. fuel charges capacity @ Rs. 0.17 Hrs. crew charges capacity @ Rs. Cum of of Tipper Tipper 10 10 Rate Tonnes 422.80 Tonnes 280.70 Per Hour Hour Hour Rs. Rs. Rs. Amount 71.88 47.72 23.87

of Tipper 10 Tonnes 140.40

0.12 Hrs. hire charges of FE loader 1.00 Cum 422.80 bucket capacity @ 45 Cum @ Rs. 0.12 Hrs. fuel charges of FE loader 1.00 Cum 280.70 bucket capacity @ 45 Cum @ Rs. 0.12 Hrs. crew charges of FE loader 1.00 Cum 140.40 bucket capacity @ 45 Cum @ Rs. 0.00 add area allowance at 0% on Rs. 40.72 Total machinery charges Rate for 5.50 Cum Rate for 1.00 Cum 0.00 add overheads and contractors profit at 0% 44.50 on Rs. Total rate for 1.00 Cum

Hour Hour Hour

Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs. Rs.

50.74 33.68 16.85 0.00 244.74 244.74 44.5 0.00 44.50

Executive Engineer Urban Projects Rajahmundry

Dy. Executive Engineer Urban Projects Rajahmundry

Assistant Engineer Urban Projects Rajahmundry

REQUIREMENT OF CEMENT S.No. 1 Description of Item Laying PCC (1:4:8) prop.using 40mm For Footings and Flooring VRCC M20 grade mix for Footings VRCC M25 grade mix for Columns For Ground Floor For 1st floor For 2nd floor For 3rd floor 4 5 VRCC M25 grade mix for Plinth beamColumns Fal G Brick Msonary in C.M.(1:8) using Fal G bricks For Ground floor For 1st floor For 2nd floor 3 rd Floor 6 Fal G Brick Msonary in C.M.(1:8) using Flyash bricks For Ground floor For 1st floor For 2nd floor 3 rd Floor 7 Brick Msonary in C.M.(1:8) using 2nd class bricks For Ground floor For 1st floor For 2nd floor 3 rd Floor 8 VRCC M25 grade mix for Lintels For Ground floor For 1st floor For 2nd floor 9 VRCC M25 grade mix For Sunshades / Lofts For Ground floor For 1st floor Qty 48.33 26.55 coeff 165.00 330.00 Per Cum. Cum. Cement in Kgs 7974 8762

2 3

7.91 4.71 7.71 0.89 11.16

330.00 330.00 330.00 330.00 330.00

Cum. Cum. Cum. Cum. Cum.

2610 1554 2544 294 3683

#REF! 40.46 40.46 7.52

18.00 18.00 18.00 18.00

Cum. Cum. Cum. Cum.

#REF! 728 728 135

13.24 13.24 13.24 8.38

18.00 18.00 18.00 18.00

Cum. Cum. Cum. Cum.

238 238 238 151

1.39 1.39 1.39 1.39

36.00 36.00 36.00 36.00

Cum. Cum. Cum. Cum.

50 50 50 50

1.60 1.60 1.60

330.00 330.00 330.00

Cum. Cum. Cum.

528 528 528

68.80 68.80

10.72 10.72

RM RM

738 738

S.No. For 2nd floor 10

Description of Item

Qty #REF!

coeff 10.72

Per

Cement in Kgs RM #REF!

VRCC M20 grade mix For Roof Beams For Ground floor For 1st floor For 2nd floor For 3rd floor

9.93 9.93 9.93 1.18

330.00 330.00 330.00 330.00

Cum. Cum. Cum. Cum.

3277 3277 3277 389

11

VRCC M20 grade mix For Roof Slab For Ground floor For 1st floor For 2nd floor For 3rd floor

23.93 23.93 23.93 2.79

330.00 330.00 330.00 330.00

Cum. Cum. Cum. Cum.

7897 7897 7897 921

12

Plastering in C.M.(1:4) prop. 12mm thick Impervious Coat Plastering 12mm thick C.M.(1:6) prop. Inside For Ground Floor For 1st floor For 2nd floor For 3rd floor

216.14

54.00

10 Sqm

1167

13

1127.4 1127.44 1127.44 57.57

36.00 36.00 36.00 36.00

10 Sqm 10 Sqm 10 Sqm 10 Sqm

4059 4059 4059 207

14

Plastering 12mm thick C.M.(1:5) prop. Out side For Ground Floor For 1st floor For 2nd floor For 3rd floor

354.50 298.97 298.97 216.04

43.20 43.20 43.20 43.20

10 Sqm 10 Sqm 10 Sqm 10 Sqm

1531 1292 1292 933

15

Plastering in C.M.(1:4) prop. 20mm thick Floor finish Floor finish For Ground floor For 1st floor For 2nd floor TOTAL QUANTITY REQUIRED ( IN KG ) TOTAL QUANTITY REQUIRED ( IN BAGS )

172.90 172.90 172.90

75.60 75.60 75.60

10 Sqm 10 Sqm 10 Sqm

1307 1307 1307

Assistant Engineer(H) Urban Projects :: Rajahmundry

10.725

SSR "13-14 Muncipal Allowancwe 0% Overheads & Contractor's 14% Profit

Seignorage charges
Sand HBG Metal
Initial Cost including Stacking & Seignorage charges

40.00 Gravel 50.00 Earth


Unloading charges Source of supply

Lead Statement Particulars Particularss Item Code


Loading charges

Sl.N O.

1 Sand for Mortor(27-a/286) 2 Sand for Filling(27-b/286) 3 6mm HBG Metal 4 10 mm HBG metal 5 12 mm HBG metal 6 20 mm HBG metal 7 40 mm HBG metal

M-005 M-004 M-050 M-051 M-052 M-053 M-055

385.00 285.00 700.00 890.00 1045.00 1300.00 805.00 16.00 12.00 10.00 3707.00 5.700

13.50 13.50

6.75 6.75

Krishna River Krishna River

27.10 27.10 27.10 27.10 27.10

13.55 Lam 13.55 Lam 13.55 Lam 13.55 Lam 13.55 Lam

8 FAL-G.block (290x200x140) BMT-A11 9 FAL-G.block (290x150x140) BMT-A12 10 FAL-G.block (290x100x140) BMT-A13 11 12 13 14 15 16 17 2nd class Country brick Cement Water Steel Gravel Stone crusher dust Quarry Rubbish

Local Local Local


37.30 37.30 Kollipara

BMT-A01 LR LR LR 43000.00 M-008 98.00 M-021 340.00 M-148 245.00

Local Local Local Vejandla Lam Vejandla

A) FOR ROAD WORKS 60 to 63 mm IRC and MoRTH HBG metal 50 to 55 mm IRC and MoRTH HBG metal 40 to 45 mm IRC and MoRTH HBG metal SS Revetment work 300mm Quarry spall (Field picked metal) Av. of rate 25mm & 40mm 150 mm soling stone other than Granite 40 to 45 mm IRC and MoRTH HBG M/C metal 25 to 27 mm IRC and MoRTH HBG M/C metal 19 to 22 mm IRC and MoRTH HBG M/C metal 12 to 14 mm IRC and MoRTH HBG M/C metal

Machine Crushing 419.00 456.00 588.00 156.00 45.00 66.00 588.00 944.00 984.00 780.00

25%

Blasting Charges

Lam Lam Lam Lam Lam Lam Lam Lam Lam Lam

9.5 to 11.20 mm IRC and MoRTH HBG M/C metal 5 to 7 mm IRC and MoRTH HBG M/C metal 2.36 to 5 mm IRC and MoRTH HBG M/C metal HBG Stone chips 2.36mm and below

656.00 504.00 308.00 330.00

Lam Lam Lam Lam Lam Lam

75mm size IRC and Morth HBG metal 304.00 65mm size IRC and Morth HBG metal 379.00

Bitumen

35829.93

old rate

Vishakhapatnam

Scaffolding Hire & Labour Charges Pnos 93 & 94 Mate. Hire Labour Per Sl.No. Particulars/Floor Charges charges Brick Masonry 1 st Floor 8.99 54.34 1 Cu,m 2 nd Floor 3 rd Floor 4 th Floor Plastering Work 1 st Floor 2 nd Floor 3 rd Floor 4 th Floor Ceiling Plastering Work 1 st Floor 2 nd Floor 3 rd Floor 4 th Floor 0.90 0.90 0.90 0.90 5.43 7.70 9.97 12.24 1 Sq.m 1 Sq.m 1 Sq.m 1 Sq.m 8.99 8.99 8.99 77.01 1 Cu,m 99.69 1 Cu,m 122.36 1 Cu,m

2.11 2.11 2.11 2.11

11.08 1 Sq.m 15.57 1 Sq.m 20.05 1 Sq.m 24.54 1 Sq.m

HIRE CHARGES FOR CENTERING & SCAFFOLDING - Unsupported Height upto 3.66 M Casurina Ballies, Bamboos, Wooden R Plates etc P Nos 94 & 97, Mate. Hire Labour Floor Wise Labour Charges for centering (97) Sl.No. Particulars/Floor Charges charges (94) (94) 1 st Floor 1 FOOTINGS 2 PEDESTALS 3 PLINTH BEAMS 2 nd Floor 3 rd Floor

137.00 109.00 1158.00

415.00 660.00 1000.00

4 LINTELS 5 CHAJJAS - SUNSHADES 6 COLUMNS 7 BEAMS 8 SLABS - Up to 150 mm thick 9 SLABS - above 150 mm - Up to 300 mm thick

680.00 134.00 205.00 1201.00 136.00 140.00 146.00

834.00 128.00

834.00 128.00

917.00 141.00

1001.00 154.00 1405.00 1178.00 133.00 137.00 144.00

1171.00 1171.00 1288.00 982.00 111.00 114.00 120.00 982.00 1080.00 111.00 114.00 120.00 122.00 125.00 132.00

10 SLABS - above 300 mm thick

Sanitary & Water Supply Items


Sl. no. Item

Item Code
BMW-A. 02 BMW-A. 04

Rate

PER

101.60 mm SWG SP 1 pipe 152.4 mm SWG SP 1 pipe

262.00 1 Rm 407.00 1 Rm

labour charges only for laying, jointing and testing SWG pipes of BMW-A. 05 any dia BMW-A. 39 SWG 100mm bend BMW-A. 40 SWG 150mm bend 914.4mm x 457.2 mm Inspection BMW-B 05 chamber 457.2 mm x 457.2 mm Inspection BMW-B 06 chamber S & f 580 mm x 440 mm long BMW-D04 Orissa pan B) Providing brick masonry seat BMW-D09 BMW-E 01 300 grams NP Stop cock BMW-E 02 Labour charges(Stop cock) BMW-F 01 Union 12.70 mm BMW-F 02 Union 19.05 mm BMW-F 03 Union 25.4 mm BMW-F 04 Union 31.75 mm BMW-F 05 Union 38.1 mm BMW-F 06 Union 50.80 mm BMW-F17 25mm Gate Valve BMW-F18 Labour charges(25mm Gate valve)) BMW-F25 40mm Gate Valve BMW-F26 Labour charges(40mm Gate valve)) BMW-F27 50mm Gate Valve BMW-F28 Labour charges(50mm Gate valve)) BMW-F79 15mm Nominal bore

113.00 1 Rm 85.00 1 No 157.00 1 No 5148.00 1 No 3104.00 1 No 1157.00 278.00 443.00 26.00 38.00 46.00 70.00 87.00 104.00 128.00 698.00 40.00 1423.00 61.00 2055.00 82.00 173.00 1 No 1 No 1 No 1 No 1 No 1 No 1 No 1 No 1 No 1 No 1 No 1 No 1 No 1 No 1 No 1 No 1 Rm

Labour charges(15mm)

BMW-F 80

37.00 1 Rm

20mm Nominal bore

BMW-F81

192.00 1 Rm

Labour charges(20mm) 25mm Nominal bore Labour charges(25mm) 32mm Nominal bore Labour charges(32mm) 40mm Nominal bore Labour charges(40mm) 50mm Nominal bore

BMW-F82 BMW-F83 BMW-F84 BMW-F85 BMW-F86 BMW-F87 BMW-F88 BMW-F89

37.00 252.00 37.00 354.00 37.00 396.00 40.00

1 Rm 1 Rm 1 Rm 1 Rm 1 Rm 1 Rm 1 Rm

427.00 1 Rm

Labour charges(50mm) 75mm dia 3 Mts single socket 110mm dia 3 Mts single socket 160mm dia 3 Mts single socket 75mm PVC plain bend 110mm PVC plain bend 75mm PVC Door Bend of 87.5 degrees 75mm dia single T with door 110mm dia single T with door

BMW-F 90 BMW-G11 BMW-G13 BMW-G 54 BMW-G55 BMW-G57 BMW-G58 BMW-G70 BMW-G72

61.00 1 Rm 255.00 3m 484.00 1885.00 50.00 83.00 3m 3m 1 No 1 No

67.00 1 No 73.00 1 No 130.00 1 No

75mm PVC Single 'Y' with door


BMW-G 82 BMW-G 88 BMW-G98 BMW-G100 BMW-G104 BMW-G106 BMW-G112 BMW-G118 BMW-G-152 LR BMW-D.22 BMW-D.34 BMW-E.28 BMW-G.01

75mm PVC Double 'Y' with door 75mm Vent Cowl 110mm Vent Cowl 75mm PVC Clamps 110mm PVC Clamps 110mm PVC Floor trapl (Bel mouth) 75mm PVC Nahany trap Labour charges for laying, fixing PVC Pipes(all Dia.) 160mm dia single T with door Indian make Flat Back Wash Hand Basin white glazed flat back half stall urinals 12.7 mm dia NP pillar cock heavy duty polyethylene water storage tank

95.00 132.00 14.00 19.00 15.00 18.00

1 No 1 No 1 No 1 No 1 No 1 No

227.00 1 No 102.00 1 No 65.00 1 No 1 No 1961.00 1 No 2277.00 1 No 570.00 1 No 6.00 1 Lt

charges
22.00 22.00
Labour Charges P.Nos 278 to 283
Distance

Machinery Hire Charges P.Nos 404 to 407 Hire Charges


Hire charges of Tipper 5.00 Cum capacity Hire charges of Tipper 10 Tonnes capacity Hire charges of Water Tanker 8000 Ltrs capacity Hire charges of Truck 10 Tonnes capacity Hire charges of FE loader 1.00 Cum bucket capacity @ 45 Cum Batching plant 0.5 cum Needle vibrator 40mm (petrol) Concrete mixer 300/200 (diesel) SSR hire charges 456.20 422.80 411.00 422.80 422.80 120.30 7.80 54.60

Particularss skilled electrician 1st class mason 1st class Painter Head mazdoor semiskilled electrician 2nd class Brick layer 2nd class Painter Man mazdoor Woman mazdoor Cost of binding wire

Item Code Amount

3.00 3.00 50.00 50.00 50.00 50.00 50.00 0.00 0.00 0.00 12.00 0.00 0.00 0.00 37.00 50.00 37.00

I-5 I-11 I-35 II-10 II-34 II-35 II-37 III-3 III-4

400.00 350.00 400.00 320.00 320.00 320.00 320.00 280.00 280.00 70.00

Hire Charges Roads & Irrigation Works Mac

Hydraulic Excavator Tipper 5.5 Cum Motar Grader Vibratory roller 8 tonnes Water tanker 6KL capacity Mechanical Broom Hydraulic Emulson Pressure Distributor

Hot mix plant 40 to 60 TPH Capacity

70.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00 50.00

Electric Generator 125 KVA

Front End loader

Paver finisher Mechanical 100 TPH

Penumatic Road Roller (Static Roller

Bitumen boiler oil fired (Bitumen Spraying)

Concrete Mixer 0.28 Cum

Air Compressor

Tractor with ripper attachment

Three wheel 80-100 kN Static Roller

Diesel generating set 30 KVA

Diesel generating set 50 KVA

50.00 50.00 50.00 50.00 50.00 50.00 900.00 To & Fro

Hydraulic Excavator

M Casurina Ballies, Bamboos, Wooden Reapers, Runners, Wood Posts, Wall 94 & 97, Charges for centering (97) 4 th Floor per 1 cum per 1 cum per 1 cum PER

Electrical Items
Item

P.nos 144 to 266 Item Code Elec-1.2.1 Elec-1.2.2 Elec-1.2.3 Elec-1.2.4

20mm dia 1.5mm thick PVC pipe 20mm dia 2mm thick PVC pipe 25mm dia 1.5mm thick PVC pipe 25mm dia 2mm thick PVC pipe

1084.00 166.00 1522.00 1277.00 144.00 148.00 156.00

per 1 cum per 1 sqm per 1 cum per 1 cum per 1 sqm per 1 sqm per 1 sqm

20mm dia 1,2,3 & 4 way deep Junction Box 20mm PVC bends 20 x 15 cms (8" x6") Wooden switch deep box 8"x10" Deep Box 21.6 x 16.6 cms (8.5 x 6.5") 3mm thick Decolam sheet 25 x 20 cms (10" x8") Decolam sheet 3mm thick 14/0.3mm PVC FR flexible copper wire 2.5 sq.mm wire (36/0.3mm) 6A Switch (olive model) 6A 3 pin / 2 pin Socket 16A 3 pin / 6A 3pin plug socket (5 in 1) 6A 3 way Ceiling Rose PVC batten holder 32 A DP switch 32A 240V Porcelain Rewirable Fuse Unit 32A 415V Porcelain Rewirable Fuse Unit 40W bulb 4core 16 sqm PVC XLPE armoured cable 3.5 Core 25.00 Sq.mm.

Elec-1.2.38 Elec-1.2.43 Elec-1.4-11 Elec-1.4-12 Elec-1.4-25 Elec-1.4-26 Elec-1.5.1 Elec-1.5.3 Elec-1.7.1 Elec-1.7.4 Elec-1.7.11 Elec-1.7.15 Elec-1.7.16 Elec-1.7.21 Elec-2.6.1 Elec-2.6.2 Elec- 3.7.1 Elec- 4.1.21 Elec- 4.1.24 Elec- 5.1.3 Elec- 6.2.3 Elec- 8.1.10 Elec- 8.1.16 Elec- 8.1.17 Elec- 8.1.45 Elec- 8.1.56

48" (1200mm) Sweep ceiling Fan 18 SWG (2mm) CRCA sheet U Nails Hard Coke Salt G.I. Strip / Plate / Wire (per K. G) Earth work excacvation including all soils for trench, Pole Pit and Earth Pit. Drilling of 16 Nos through holes of 12mm dia to G.I pipe G.I Nuts, Bolts an Washers each set 18" dia 2" thick hume pipe ring

Elec- 8.1.63 Elec- 8.1.64 Elec- 8.1.65

Miscallaneous Materials Sl. No. 1 1 Description of Item 2 White Cement P. No.


SSR Sl. No.

3 BMS-W.68

2 Surya Cem or Equivalent Quality 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 22 23 Water proof Cement Superior Quality Snowcem or Equv. Quality Oil Bound Distemper POWDER Oil Bound Distemper Wood Primer Red Oxide Primer Paint Grade-I Cement Primer Grade - I Synthetic enamel paint 1st quality (All Plastic emulsion paint Impervious Water proofing compound Cost of binding wire Cement Jally 50mm thick Cement Jally 40mm thick Ceramic tiles 7.3mm thick White Glazed Tiles of any Size 1st. Quality Vitrified floor tiles 600 x 600 mm normal Mastic Pad 0.60 x 1.20 Mts, 25.4mm thick Mastic Pad 0.60 x 1.20 Mts, 12.7mm thick Polished kadapa slabs Polished kadapa slabs 25mm thick Rabbit wire mesh RCC Door Frame size 3' 6"x 6' 6" 0.98 X1.98 mt (NK Materials) RCC Door Frame size 2' 6"x 6' 6" 0.75 X1.98 mt (NK Materials) RCC Window Frame 3' 0"x4' 0" size 0.90 X1.20 mt (NK Materials) Set accelerator and plasticizer: Roofplast Mastic pad 2'0 " x 4'0" (0.60M x 1.2M) of 1" (25.4 mm ) thick Mastic pad 2'0 " x 4'0" (0.60M x 1.2M) of 1/2" (12.7 mm ) thick

BMT.J.27

BMT.J.24 BMT.J.26 BMT.J.20 BMT.J.21 BMT.J.05 BMT.J.03 BMT.J.01 BMT.J.30 BMT.J.22 BMT.H.01 BMS.W.17 BMS.W.16 BMT.C.01 BMT.C.06 BMT.C.15 BMS.W.20 BMS.W.21 BMT.B.05 BMT-F.28

24

25

26 27 28

BMT-H.11 BMS-W.20 BMS-W.21

Standard Schedule of Rates For the YEAR 2013-14


RCC Pipes ( Plain ended ) NP2 NP3

300MM dia 450MM dia 600MM dia 900MM dia

Convey charges/KM/RM Beyond initial Cost upto 5KM 5KM 348.00 13.00 0.48 611.00 26.00 1.45 993.00 41.00 2.66 1972.00 70.00 3.75

initial Cost 791.00 1235.00 2019.00 4171.00

Conv charges/KM/RM upto 5KM 35.00 49.00 81.00 142.00

RCC Collors and Rings 300MM dia 450MM dia 600MM dia 900MM dia

NP2

NP3

Collors 87 185 285 626

Rings

Collors 124 233 364 726

Rings

achinery Hire Charges P.Nos 404 to 407 Fuel Crew Charges Charges
280.70 280.70 280.70 280.70 280.70 114.10 19.00 74.30

Total

Per Hour Hour Hour Hour Hour Hour Hour Hour

140.40 140.40 140.40 140.40 140.40 269.50 125.40 174.20

877.30 843.90 832.10 843.90 843.90 503.90 152.20 303.10

arges Roads & Irrigation Works Machinery


Hydraulic Excavator Tipper 5.5 Cum Motar Grader Vibratory roller 8 tonnes Water tanker 6KL capacity Mechanical Broom Hydraulic Emulson Pressure Distributor 2754.50 877.30 3216.00 2541.40 624.00 357.00 860.00 19120.00 1320.00 1646.00 2249.00 1283.00 209.00 417.40 499.40 422.00 1704.60 766.40 1083.30 Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour Hour

Sl. No. 1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Description Mechine 2 Dozer( D 80 ) Dozer( D 50 ) Mortor Grader Hydraulic Excavator Front end loader Tipper- 5.5 Cum Vibratory roller 8 tonne Smooth wheeled roller 8 tonne Water tanker 8 Kilolitre Water tanker 6 Kilolitre Tractor Tractor with rotavator Tractor with ripper attachment Air Compressor 5 cmm ( Electric) Wet mix plant 60 TPH Mechanical broom Hydraulic Bitumen Pressure Distributor

t mix plant 40 to 60 TPH Capacity Electric Generator 125 KVA Front End loader

aver finisher Mechanical 100 TPH

numatic Road Roller (Static Roller

oiler oil fired (Bitumen Spraying) Concrete Mixer 0.28 Cum Air Compressor Tractor with ripper attachment

ee wheel 80-100 kN Static Roller Diesel generating set 30 KVA Diesel generating set 50 KVA

18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 a 32 b 33 34 35 a 35 b 35 c 36

Emulsion Pressure Distributor Hot mix Plant 120 TPH capacity Hot mix Plant 100 TPH capacity Hot mix Plant 60 TPH capacity Hot mix Plant 40 to 60 TPH capacity Paver Finisher Hydrostatic with sensor control 100 TPH Paver finisher Mechanical 100 Hydraulic Chip Spreader Tandem Road roller Pneumatic Road roller Pot-Hole repair machine Bitumen boiler oil fired GSB Plant 50 Cum Mastic Cooker a) Batching and Mixing Plant 50 Cum capacity (b) Batching and Mixing Plant 15 Cum capacity Transit mixer Concrete pump of 45 and 30 cum Cranes (a) 80 tonnes (b) 35 tonnes (c) 3 tonnes (d)Crane with grab bucket 0.75 cum (e)Crane with grab bucket 1 cum Concrete bucket Kerb casting machine Concrete mixer (a)0.28 cum (b) 1.0 cum Piling rig with bantonite pump Concrete paver finisher with 40 HP motor Integrated stone crusher Integrated stone crusher

37 38 P.nos 144 to 266 Rate 18.20 1 Rm 23.00 1 Rm 24.20 1 Rm 30.30 1 Rm PER 39 a 39 b 41 40 41 41 a

ems

21.00 1 No 4.00 27.00 44.00 40.00 66.00 1001.00 2390.00 18.00 27.00 100 Mts 100 Mts 1 No 1 No ssr 12-13

42 43

Pre stressing jack with pump and access Generator Generator 250 KVA Generator 125 KVA Generator 100 KVA Generator 30 KVA

44 45 46 47 48 49

Pneumatic sinking of Plants Truck 5.5 cum per 10 tonnes Road marking machine Mobile slurry seal equipment Plate compacter

146.00 1 No 21.00 1 No 20.00 1 No 106.00 1 No 99.00 1 No 123.00 1 No 12.00 1 No 131.00 166.00 2020.00 1.90 40.00 8.00 4.00 1 Rm 1 Rm 1 No 1 sq.inch 100 Nos 1 Kg 1 Kg

Drilling equipment Note: The above hire charges of machinery & plant inc

62.00 1 Kg

200.00 1 Cu.m 5.00 1 No 10.00 1 Set 200.00 1No

Unit 4 Kg

Rate 5 27.00

Kg

20.60 515/25=20.60 47.00 44.24 1106/25=44.24 40.00 81.00 135.00 121.00 134.00 230.00 244.00 24.00 70.00 375.00 274.00 447.00 335.00 1008.00 925.00 530.00 1544.00 3603.00 16.00

Kg Kg Ltr Kg Ltr Ltr Kg Ltr Ltr Kg Kg Sqmt. Sqmt. Sqmt. Sqmt. Sqmt. Sqmt. Sqmt. 10Sqmt. Sqmt. Sqmt. 1 No

1 No

1 No

Ltr Sqmt. Sqmt.

70.00 925.00 530.00

013-14

P3

Conv charges/KM/RM Beyond 5KM 0.97 1.69 3.75 8.23

P3

Activity 3 Spreading Spreading Clearing Soil Ordinary Soil loading Transportation of soil, GSB,WMM, Hot mix etc Earth/Soil, GSB, Soil compaction ,BM compaction Water transport Water transport Pulling Scarifying Scarifying General purpose Wet mix Surface cleaning Applying bitumen tack coat Cutting Cutting Spreading Soil Marshy Aggregate loading Cleaning Cleaning GSB Soil unsuitable

Unit 4 Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour

WMM

WMM

Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour

Applying emulsion tack coat DBM/BM/SDC DBM/BM/SDC DBM/BM/SDC DBM/BM/SDC DBM/BM/SDC


Paving of WMM, paving of DLC

Per Hour /Premix /Premix /Premix /Premix /Premix Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour Per Hour

Surface dressing Rolling of Asphaltic surface Rolling of Asphaltic surface Repair of pot-holes Bitumen Spraying Producing GSB Mastic wearing coat Concrete mixing Concrete mixing Transportation of concrete mix Pumping of Concrete Lifting purpose Lifting purpose Lifting purpose Well foundation Well foundation For pouring concrete Kerb making Concrete mixing Concrete mixing
0.75 m dia to 1.20 m dia boring attachment

Paving of concrete surface Crushing of spalls 100 TPH

Crushing of spalls 200 TPH

Stressing of steel wires/ stands Generation of electric energy Generation of electric energy Generation of electric energy Generation of electric energy Pneumatic sinking of wells Material transport Road marking
Mixing and laying slurry seal For compacting in medians

Per Hour

per hour per hour per hour per hour Per K.m. per hour Per Hour Per Hour Per Hour

For drilling Per Hour bove hire charges of machinery & plant includes crew, oils, conveyance of machinery to site and all other incidental charges.

SoRate for 201314 ( Rupees) 5 2511.70 1570.00 3216.00 2754.50 1646.00 877.30 2541.40 1038.40 832.10 624.00 415.00 422.00 422.00 499.40 1646.00 357.00 1498.00

860.00 28175.00 24171.00 21668.00 19120.00 11441.00 2249.00 2567.00 1646.00 1283.00 845.00 209.00 1143.00 65.00 1231.90 1037.20 1819.10 803.00 1171.00 791.00 352.00 2160.00 3532.00 16.20 311.00 417.40 649.00 5475.00 2900.00 8712.00 18369.00

141.00

1850.00 1320.00 1126.00 766.40 56.00 843.90 111.00 1126.00 48.00 775.70

nd all other incidental charges.

You might also like