ROAD FURNITURES

MAINTENANCE OF GUARDRAIL AND CRASH CUSHION


Removal, Dismantle and Replace of Damage Components Item a, page 29
Removal, dismantle and dispose the damaged guardrail beam.

A) Machinery.

i) Pick-up truck (3.0T) for carring,materials, workers and tools :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Backhoe :
1 x 1 Day @ RM 270.00 Per day = RM 270.00

iii) Tipper truck (6-wheeler) :


1 x 1 Day @ RM 250.00 Per day = RM 250.00

iv) Miscellaneous items (e.g. oxy-cutter,crowbar, hammer and hardware tools):


Allow sum (per day) = RM 100.00
Total = RM 770.00

Productivity Per Day : 91 M


Machinery Cost Per M : RM 770.00 / 91 = RM 8.51

B) Workmen

i) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General Worker :


5 x 1 Day @ RM 38.00 Per day = RM 190.00
RM 255.00

Productivity Per Day : 91 M


Workmen Cost Per M : RM 255.00 / 91 = RM 2.82

Row cost Per M = RM 11.33

ADD: P& O : 15% = RM 1.70

Rate Per M = RM 13.02


Take RM 13.00

Guard Rails
ROAD FURNITURES
MAINTENANCE OF GUARDRAIL AND CRASH CUSHION
Remove, Dismantle and Replace of Damaged Components Item b i, page 29
Removal, dismantle and dispose the damaged End Wing or Fish Tail (Terminal end Type 1)

A) Machinery.

I) Pick-up truck (3.0T) for carring,materials, workers and tools :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (e.g. oxy-cutter,crowbar, hammer and hardware tools):


Allow sum (per day) = RM 100.00
Total = RM 250.00

Productivity Per Day : 33 NO


Machinery Cost Per NO : RM 250.00 / 33 = RM 7.69

B) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00
RM 217.00

Productivity Per Day : 33 NO


Workmen Cost Per NO : RM 217.00 / 33 = RM 6.68

Row cost Per NO = RM 14.37

ADD: P& O : 15% = RM 2.16

Rate Per NO. = RM 16.52


Take RM 16.50

Guard Rails
ROAD FURNITURES
MAINTENANCE OF GUARDRAIL AND CRASH CUSHION
Remove, Dismantle and Replace of Damaged Components Item b ii, page 29
Removal, dismantle and dispose the damaged Terminal Anchorage Unit Type 2)

A) Machinery.

I) Pick-up truck (3.0T) for carring,materials, workers and tools :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (e.g. oxy-cutter,crowbar, hammer and hardware tools):


Allow sum (per day) = RM 100.00
Total = RM 250.00

Productivity Per Day : 17 NO


Machinery Cost Per NO : RM 250.00 / 17 = RM 14.71

B) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00
RM 217.00

Productivity Per Day : 17 NO


Workmen Cost Per NO : RM 217.00 / 17 = RM 12.76

Row cost Per NO = RM 27.47

ADD: P& O : 15% = RM 4.12

Rate Per NO. = RM 31.59


Take RM 31.50

Guard Rails
ROAD FURNITURES
MAINTENANCE OF GUARDRAIL AND CRASH CUSHION
Remove, Dismantle and Replace of Damaged Components Item b iii, page 29
Removal, dismantle and dispose the damaged 90 degrees Twist Unit Type 3

A) Machinery.

I) Pick-up truck (3.0T) for carring,materials, workers and tools :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (e.g. oxy-cutter,crowbar, hammer and hardware tools):


Allow sum (per day) = RM 100.00
Total = RM 250.00

Productivity Per Day : 17 NO


Machinery Cost Per NO : RM 250.00 / 17 = RM 14.71

B) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00
RM 217.00

Productivity Per Day : 17 NO


Workmen Cost Per NO : RM 217.00 / 17 = RM 12.76

Row cost Per NO = RM 27.47

ADD: P& O : 15% = RM 4.12

Rate Per NO. = RM 31.59


Take RM 31.50

Guard Rails
ROAD FURNITURES
MAINTENANCE OF GUARDRAIL AND CRASH CUSHION
Remove, Dismantle and Replace of Damaged Components Item b iv, page 29
Removal, dismantle and dispose the damaged Terminal 1 : 6 / Sloping End Unit Type 4

A) Machinery.

I) Pick-up truck (3.0T) for carring,materials, workers and tools :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (e.g. oxy-cutter,crowbar, hammer and hardware tools):


Allow sum (per day) = RM 100.00
Total = RM 250.00

Productivity Per Day : 17 NO


Machinery Cost Per NO : RM 250.00 / 17 = RM 14.71

B) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00
RM 217.00

Productivity Per Day : 17 NO


Workmen Cost Per NO : RM 217.00 / 17 = RM 12.76

Row cost Per NO = RM 27.47

ADD: P& O : 15% = RM 4.12

Rate Per NO. = RM 31.59


Take RM 31.50

Guard Rails
ROAD FURNITURES
MAINTENANCE OF GUARDRAIL AND CRASH CUSHION
Remove, Dismantle and Replace of Damaged Components Item c, page 29
Removal, dismantle and dispose the damaged guardrail post

A) Machinery.

I) Pick-up truck (3.0T) for carring,materials, workers and tools :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Backhoe :
1 x 1 Day @ RM 270.00 Per day = RM 270.00

iii) Miscellaneous items (e.g. oxy-cutter,crowbar, hammer and hardware tools):


Allow sum (per day) = RM 100.00
Total = RM 520.00

Productivity Per Day : 27 NO


Machinery Cost Per NO : RM 520.00 / 27 = RM 19.40

B) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General Worker :


3 x 1 Day @ RM 38.00 Per day = RM 114.00
RM 179.00

Productivity Per Day : 27 NO


Workmen Cost Per NO : RM 179.00 / 27 = RM 6.68

Row cost Per NO = RM 26.08

ADD: P& O : 15% = RM 3.91

Rate Per NO. = RM 29.99


Take RM 30.00

Guard Rails
ROAD FURNITURE
MAINTENANCE OF GUARDRAIL AND CRASH CUSHION
Remove, Dismantle and Replace of Damaged Components Item d, page 29
Dismantle and removed existing damaged nose yellow

A) Machinery.

I) Backhoe
1 x 1 Day @ RM 270.00 Per day = RM 270.00

ii) Miscellaneous
Allow sum (per day) = RM 150.00

iii) Pick-up truck (3.0T) for carrying, materials, workers and tools :
1 x 1 Day @ RM 280.00 Per day = RM 280.00
Total = RM 700.00

Productivity Per Day : 6 NO


Machinery Cost Per NO : RM 700.00 / 6 = RM 114.27

B) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General Worker :


3 x 1 Day @ RM 38.00 Per day = RM 114.00
RM 179.00

Productivity Per Day : 6 NO


Workmen Cost Per NO : RM 179.00 / 6 = RM 29.22

Row cost Per NO = RM 143.49

ADD: P& O : 15% = RM 21.52

Rate Per NO. = RM 165.01


Take RM 165.00

Guard Rails
ROAD FURNITURE
MAINTENANCE OF GUARDRAIL AND CRASH CUSHION
Remove, Dismantle and Replace of Damaged Components Item e, page 29
Dismantle and removed existing damaged cartridge

A) Machinery.

I) Backhoe
1 x 1 Day @ RM 270.00 Per day = RM 270.00

ii) Miscellaneous
Allow sum (per day) = RM 150.00

iii) Pick-up truck (3.0T) for carrying, materials, workers and tools :
1 x 1 Day @ RM 150.00 Per day = RM 150.00
Total = RM 570.00

Productivity Per Day : 3 NO


Machinery Cost Per NO : RM 570.00 / 3 = RM 165.46

B) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General Worker :


3 x 1 Day @ RM 38.00 Per day = RM 114.00
RM 179.00

Productivity Per Day : 3 NO


Workmen Cost Per NO : RM 179.00 / 3 = RM 51.96

Row cost Per NO = RM 217.42

ADD: P& O : 15% = RM 32.61

Rate Per NO. = RM 250.03


Take RM 250.00

Guard Rails
ROAD FURNITURE
MAINTENANCE OF GUARDRAIL AND CRASH CUSHION
Remove, Dismantle and Replace of Damaged Components Item f, page 29
Dismantle and removed existing beam panel

A) Machinery.

I) Backhoe
1 x 1 Day @ RM 270.00 Per day = RM 270.00

ii) Miscellaneous
Allow sum (per day) = RM 150.00

iii) Pick-up truck (3.0T) for carrying, materials, workers and tools :
1 x 1 Day @ RM 150.00 Per day = RM 150.00
Total = RM 570.00

Productivity Per Day : 5 NO


Machinery Cost Per NO : RM 570.00 / 5 = RM 109.20

B) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General Worker :


3 x 1 Day @ RM 38.00 Per day = RM 114.00
RM 179.00

Productivity Per Day : 5 NO


Workmen Cost Per NO : RM 179.00 / 5 = RM 34.29

Row cost Per NO = RM 143.49

ADD: P& O : 15% = RM 21.52

Rate Per NO. = RM 165.01


Take RM 165.00

Guard Rails
ROAD FURNITURES
MAINTENANCE OF GUARDRAIL AND CRASH CUSHION
Realigning of existing (line & level) Item g, page 29
Realign and straighten the line of existing guardrail including correct the level and verticality position of
existing guardrail post.

A) Machinery.

I) Pick-up truck (3.0T) for carring,materials, workers and tools :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Hydraulic jack


1 x 1 Day @ RM 100.00 Per day = RM 100.00

iii) Backhoe :
1 x 1 Day @ RM 270.00 Per day = RM 270.00
Total = RM 520.00

Productivity Per Day : 97 M


Machinery Cost Per M : RM 520.00 / 97 = RM 5.36

B) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General Worker :


5 x 1 Day @ RM 38.00 Per day = RM 190.00
RM 255.00

Productivity Per Day : 97 M


Workmen Cost Per M : RM 255.00 / 97 = RM 2.63

Row cost Per M = RM 7.99

ADD: P& O : 15% = RM 1.20

Rate Per M = RM 9.19


Take RM 9.20

Guard Rails
ROAD FURNITURES
MAINTENANCE OF GUARDRAIL AND CRASH CUSHION
Realigning of existing (line & level) Item h, page 29
Supply and replace missing delinator piece on guardrail

A) Material

I) G.I strip, c/w, clip, washer, bolt and nuts (supply price/Set) = RM 5.00

B) Machinery

I) Pick-up truck (3.0T) for carrying materials, workers , tools and equipments :

1 x 1 Day @ RM 150.00 per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, cleaning tools and equipments)

Allow sum : = RM 80.00

C) Workmen

I) General worker

3 x 1 Day @ RM 38.00 per day = RM 114


Total RM 344.00

Productivity Per day : 43 NO


Workmen Cost Per No. : RM 344.00 / 43 = RM 8.06

Raw cost per No. = RM 13.06

ADD : P&O : 15% = RM 1.96

Rate Per No. = RM 15.01


Take RM 15.00

Guard Rails
ROAD FURNITURES
MAINTENANCE OF GUARDRAIL AND CRASH CUSHION
Installation of New Sections Item a, page 30
Supply and install galvanised new guardrail beams

A) Material

I) Guardrail (supply price/M) : = RM 35.00

ii) Transportation(per M) : RM 10.00

iii) Material cost (per M) : = RM 45.00

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, workers and tools :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (e.g. oxy-cutter, crowbar, hammer and hardware tools):
Allow sum (per day) = RM 100.00
Total = RM 250.00

Productivity Per Day : 71 M


Machinery Cost Per M : RM 250.00 / 71 = RM 3.55

C) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General Worker :


5 x 1 Day @ RM 38.00 Per day = RM 190.00
RM 255.00

Productivity Per Day : 71 M


Workmen Cost Per M : RM 255.00 / 71 = RM 3.62

Row cost Per M = RM 52.16

ADD: P& O : 15% = RM 7.82

Rate Per M = RM 59.99


Take RM 60.00

Guard Rails
ROAD FURNITURE
MAINTENANCE OF GUARDRAIL AND CRASH CUSHION
Installation of New Sections Item b i, page 30
Supply and install galvanised End wing or Fish Tail (Terminal unitType 1)

A) Material

I) Terminal End Type l (supply price/No) = RM 58.00

ii) Transportation(per No) : = RM 5.00

iii) Material cost (per No) : : = RM 63.00

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (e.g. oxy-cutter, crowbar, hammer and hardware tools):
Allow sum (per day) = RM 100.00
Total = RM 250.00

Productivity Per Day : 29 NO


Machinery Cost Per No : RM 250.00 / 29 = RM 8.68

C) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General Worker :


5 x 1 Day @ RM 38.00 Per day = RM 190.00
RM 255.00

Productivity Per Day : 29 NO


Workmen Cost Per No : RM 190.00 / 29 = RM 6.60

Row cost Per No = RM 78.28

ADD: P& O : 15% = RM 11.74

Rate Per NO. = RM 90.02


Take RM 90.00

Guard Rails
ROAD FURNITURE
MAINTENANCE OF GUARDRAIL AND CRASH CUSHION
Installation of New Sections Item b ii, page 30
Supply and install galvanised Terminal anchorage unit Type 2

A) Material

i) Terminal anchorage unit Type 2 (supply price/No) = RM 380.00

ii) Transportation(per No) : = RM 5.00

iii) Material cost (per No) : : = RM 385.00

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (e.g. oxy-cutter, crowbar, hammer and hardware tools):
Allow sum (per day) = RM 100.00
Total = RM 250.00

Productivity Per Day : 80 NO


Machinery Cost Per No : RM 250.00 / 80 = RM 3.13

C) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General Worker :


5 x 1 Day @ RM 38.00 Per day = RM 190.00
RM 255.00

Productivity Per Day : 80 NO


Workmen Cost Per No : RM 255.00 / 80 = RM 3.19

Row cost Per No = RM 391.31

ADD: P& O : 15% = RM 58.70

Rate Per NO. = RM 450.01


Take RM 450.00

Guard Rails
ROAD FURNITURE
MAINTENANCE OF GUARDRAIL AND CRASH CUSHION
Installation of New Sections Item b iii, page 30
Supply and install galvanised 90 degrees Twist Unit Type 3

A) Material

I) Twist unit type 3 (supply price/No) = RM 550.00

ii) Transportation(per No) : RM 5.00

iii) Material cost (per No) : : = RM 555.00

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (e.g. oxy-cutter, crowbar, hammer and hardware tools):
Allow sum (per day) = RM 100.00
Total = RM 250.00

Productivity Per Day : 9 NO


Machinery Cost Per No : RM 250.00 / 9 = RM 26.60

C) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General Worker :


5 x 1 Day @ RM 38.00 Per day = RM 190.00
RM 255.00

Productivity Per Day : 9 NO


Workmen Cost Per No : RM 255.00 / 9 = RM 27.13

Row cost Per No = RM 608.72

ADD: P& O : 15% = RM 91.31

Rate Per NO. = RM 700.03


Take RM 700.00

Guard Rails
ROAD FURNITURE
MAINTENANCE OF GUARDRAIL AND CRASH CUSHION
Installation of New Sections Item b iv, page 30
Supply and install galvanised Terminal section 1:6 / Sloping End Type 4

A) Material

I) Terminal Anchorage Type 4 (supply price/No) = RM 158.00

ii) Transportation(per No) : RM 5.00

iii) Material cost (per No) : : = RM 163.00

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (e.g. oxy-cutter, crowbar, hammer and hardware tools):
Allow sum (per day) = RM 100.00
Total = RM 250.00

Productivity Per Day : 14 NO


Machinery Cost Per No : RM 250.00 / 14 = RM 18.32

C) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General Worker :


5 x 1 Day @ RM 38.00 Per day = RM 190.00
RM 255.00

Productivity Per Day : 14 NO


Workmen Cost Per No : RM 255.00 / 14 = RM 18.68

Row cost Per No = RM 200.00

ADD: P& O : 15% = RM 30.00

Rate Per NO. = RM 230.00


Take RM 230.00

Guard Rails
ROAD FURNITURE
MAINTENANCE OF GUARDRAIL AND CRASH CUSHION
Installation of New Sections Item c, page 30
Supply and install galvanised guadrail post complete with packer

A) Material

I) Guardrail post (supply price / No) = RM 87.00

ii) Transportation(per No) : RM 2.00

iii) Material cost (per No) : : = RM 89.00

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Arrow Rammer :


1 x 1 Day @ RM 300.00 Per day = RM 300.00

iii) Miscellaneous items (e.g. oxy-cutter, crowbar, hammer and hardware tools):
Allow sum (per day) = RM 100.00
Total = RM 550.00

Productivity Per Day : 52 NO


Machinery Cost Per No : RM 550.00 / 52 = RM 10.50

C) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General Worker :


5 x 1 Day @ RM 38.00 Per day = RM 190.00
RM 255.00

Productivity Per Day : 52 NO


Workmen Cost Per No : RM 255.00 / 52 = RM 4.87

Row cost Per No = RM 104.36

ADD: P& O : 15% = RM 15.65

Rate Per NO. = RM 120.02


Take RM 120.00

Guard Rails
ROAD FURNITURE
MAINTENANCE OF GUARDRAIL AND CRASH CUSHION
Installation of New Sections Item d, page 30
Supply and replace new yellow nose for the crash cushion inclusive of all necessary preparatory work.

I) Nose Yellow = RM 21,090.00

ADD: P& O : 15% = RM 3,163.50

Rate Per NO. = RM 24,253.50


Take RM 24,250.00

Guard Rails
ROAD FURNITURE
MAINTENANCE OF GUARDRAIL AND CRASH CUSHION
Installation of New Sections Item e, page 30
Supply and replace new cartridge for the crash cushion inclusive of all necessary preparatory work.

A) Material

I) Cartridge = RM 2,740.00

ADD: P& O : 15% = RM 411.00

Rate Per NO. = RM 3,151.00


Take RM 3,150.00

Guard Rails
ROAD FURNITURE
MAINTENANCE OF GUARDRAIL AND CRASH CUSHION
Installation of New Sections Item g, page 30
Supply and replace new beam panel.

A) Material

I) Cartridge = RM 2,892.00

ADD: P& O : 15% = RM 433.80

Rate Per NO. = RM 3,325.80


Take RM 3,325.00

Guard Rails
ROAD FURNITURE
MAINTENANCE OF STUDS
Reinstallation of existing studs Item a,page 31
To reinstall the missing road stud at existing location with new single - sided Road stud

A) Material

I) Road stud (Supply price / No) : = RM 16.20

ii) Epoxy in-fill (per no) : = RM 1.50

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment):
Allow sum Per day = RM 100.00
Total = RM 250.00

Productivity Per Day : 55 No


Machinery Cost Per No : RM 250.00 / 55 = RM 4.55

C) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General Worker :


2 x 1 Day @ RM 38.00 Per day = RM 76.00

iii) Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 211.00

Productivity Per Day : 55 No


Workmen Cost Per No : RM 211.00 / 55 = RM 3.84
Row cost Per No = RM 26.08

ADD: P& O : 15% = RM 3.91

Rate Per NO. = RM 29.99


Take RM 30.00

Road Stud
ROAD FURNITURE
MAINTENANCE OF STUDS
Reinstallation of existing studs Item b,page 31
To reinstall the missing road stud at existing location with new double - sided Road stud

A) Material

I) Prismo II Road stud (Supply price / No) : = RM 21.40

ii) Epoxy in-fill (per no) : = RM 1.50

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment):
Allow sum Per day = RM 100.00
Total = RM 250.00

Productivity Per Day : 55 No


Machinery Cost Per No : RM 250.00 / 55 = RM 4.56

C) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General Worker :


2 x 1 Day @ RM 38.00 Per day = RM 76.00

iii) Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 211.00

Productivity Per Day : 55 No


Workmen Cost Per No : RM 211.00 / 55 = RM 3.85
Row cost Per No = RM 31.31

ADD: P& O : 15% = RM 4.70

Rate Per NO. = RM 36.01


Take RM 36.00

Road Stud
ROAD FURNITURE
MAINTENANCE OF STUDS
Replacement of Existing Studs Item c,page 31
To replace the damaged road stud at existing location with new single - sided Road stud

A) Material

I) Prismo II Road stud (Supply price / No) : = RM 16.20

ii) Epoxy in-fill (per no) : RM 1.50

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment):
Allow sum Per day = RM 100.00
Total = RM 250.00

Productivity Per Day : 39 No


Machinery Cost Per No : RM 250.00 / 39 = RM 6.44

C) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General Worker :


2 x 1 Day @ RM 38.00 Per day = RM 76.00

iii) Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 211.00

Productivity Per Day : 39 No


Workmen Cost Per No : RM 211.00 / 39 = RM 5.44
Row cost Per No = RM 29.58

ADD: P& O : 15% = RM 4.44

Rate Per NO. = RM 34.02


Take RM 34.00

Road Stud
ROAD FURNITURE
MAINTENANCE OF STUDS
Replacement of Existing Studs Item d,page 31
To replacel the damaged road stud at existing location with new double - sided Road stud

A) Material

I) Road stud (Supply price / No) : = RM 21.40

ii) Epoxy in-fill (per no) : = RM 1.50

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment):
Allow sum Per day = RM 100.00
Total = RM 250.00

Productivity Per Day : 39 No


Machinery Cost Per No : RM 250.00 / 39 = RM 6.44

C) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General Worker :


2 x 1 Day @ RM 38.00 Per day = RM 76.00

iii) Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 211.00

Productivity Per Day : 39 No


Workmen Cost Per No : RM 211.00 / 39 = RM 5.44
Row cost Per No = RM 34.78

ADD: P& O : 15% = RM 5.22

Rate Per NO. = RM 40.00


Take RM 40.00

Road Stud
ROAD FURNITURE
MAINTENANCE OF STUDS
Replacement of Existing Studs Item e,page 31
To remove existing road stud and refix at same position

A) Material

I) Road stud (Supply price / No) : = RM 16.20

ii) Epoxy in-fill (per no) : = RM 1.50

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment):
Allow sum Per day = RM 100.00
Total = RM 250.00

Productivity Per Day : 55 No


Machinery Cost Per No : RM 250.00 / 55 = RM 4.55

C) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General Worker :


2 x 1 Day @ RM 38.00 Per day = RM 76.00

iii) Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 211.00

Productivity Per Day : 55 No


Workmen Cost Per No : RM 211.00 / 55 = RM 3.84
Row cost Per No = RM 26.08

ADD: P& O : 15% = RM 3.91

Rate Per NO. = RM 29.99


Take RM 30.00

Road Stud
ROAD FURNITURE
MAINTENANCE OF STUDS
Installation of New Studs Item f,page 31
Supply and lay new single -side Road in accordance to specification.

A) Material

I) Road stud (Supply price / No) : = RM 16.20

ii) Epoxy in-fill (per no) : = RM 1.50

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment):
Allow sum Per day = RM 100.00
Total = RM 250.00

Productivity Per Day : 42 No


Machinery Cost Per No : RM 250.00 / 42 = RM 5.91

C) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) Semi-skiller worker :


1 x 1 Day @ RM 40.00 Per day = RM 40.00

iii) General Worker :


3 x 1 Day @ RM 38.00 Per day = RM 114.00

iv) Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 289.00

Productivity Per Day : 42 No


Workmen Cost Per No : RM 289.00 / 42 = RM 6.83
Row cost Per No = RM 30.44

ADD: P& O : 15% = RM 4.57

Rate Per NO. = RM 35.01


Take RM 35.00

Road Stud
ROAD FURNITURE
MAINTENANCE OF STUDS
Installation of New Studs Item g,page 31
Supply and lay new double-side Road stud in accordance to specification.

A) Material

I) Prismo II Road stud (Supply price / No) : = RM 21.40

ii) Epoxy in-fill (per no) : = RM 1.50

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment):
Allow sum Per day = RM 100.00
Total = RM 250.00

Productivity Per Day : 35 No


Machinery Cost Per No : RM 250.00 / 35 = RM 7.12

C) Workmen

I) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) Semi-skiller worker :


1 x 1 Day @ RM 40.00 Per day = RM 40.00

iii) General Worker :


3 x 1 Day @ RM 38.00 Per day = RM 114.00

iv) Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 289.00

Productivity Per Day : 35 No


Workmen Cost Per No : RM 289.00 / 35 = RM 8.23
Row cost Per No = RM 38.26

ADD: P& O : 15% = RM 5.74

Rate Per NO. = RM 43.99


Take RM 44.00

Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
Road Stud
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Repainting of Existing Marking Item a,page 32
Prepare and apply white or yellow temporary roadline paint for pavement markings for 150mm
wide single continous edge line marking

A) Material

I) Roadline paint (white/yellow) - Cost @ Per Drum (20 litres) = RM 300.00


a) Approx. Coverage / Drum : 200 M2
b) Cost (per M2) RM 300.00 / 200 = RM 1.50

ii) ADD : Wastage : 10% = RM 0.15

iii)Material cost (per M2) = RM 1.65

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Setting equipments and Tools (1 set) :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment):
Allow sum Per day = RM 100.00
Total = RM 370.00

Productivity Per Day : 124 M2


Machinery Cost Per M2 : RM 370.00 / 124 = RM 2.98

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 124 M2


Workmen Cost Per M2 : RM 262.00 / 124 = RM 2.11

Row cost Per M2 = RM 6.75

ADD: P& O : 15% = RM 1.01

Rate Per M2. = RM 7.76


Take RM 7.75

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Repainting of Existing Marking Item b,page 32
Prepare and apply white temporary roadline paint for pavement markings for 150mm wide
single continous center line and lane markings

A) Material

I) Roadline paint (white/yellow) - Cost @ Per Drum (20 litres) = RM 300.00


a) Approx. Coverage / Drum : 200 M2
b) Cost (per M2) RM 300.00 / 200 = RM 1.50

ii) ADD : Wastage : 10% = RM 0.15

iii)Material cost (per M2) = RM 1.65

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Setting equipments and Tools (1 set) :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment):
Allow sum Per day = RM 100.00
Total = RM 370.00

Productivity Per Day : 124 M2


Machinery Cost Per M2 : RM 370.00 / 124 = RM 2.98

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 124 M2


Workmen Cost Per M2 : RM 262.00 / 124 = RM 2.11

Row cost Per M2 = RM 6.75

ADD: P& O : 15% = RM 1.01

Rate Per M2. = RM 7.76


Take RM 7.75

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Repainting of Existing Marking Item c,page 32
Prepare and apply white temporary roadline paint for pavement markings for 100mm wide
intermittent center line and lane marking

A) Material

I) Roadline paint (white/yellow) - Cost @ Per Drum (20 litres) = RM 300.00


a) Approx. Coverage / Drum : 200 M2
b) Cost (per M2) RM 300.00 / 200 = RM 1.50

ii) ADD : Wastage : 10% = RM 0.15

iii)Material cost (per M2) = RM 1.65

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Setting equipments and Tools (1 set) :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment):
Allow sum Per day = RM 100.00
Total = RM 370.00

Productivity Per Day : 124 M2


Machinery Cost Per M2 : RM 370.00 / 124 = RM 2.98

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 124 M2


Workmen Cost Per M2 : RM 262.00 / 124 = RM 2.11

Row cost Per M2 = RM 6.75

ADD: P& O : 15% = RM 1.01

Rate Per M2. = RM 7.76


Take RM 7.75

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Repainting of Existing Marking Item d,page 32
Prepare and apply white temporary roadline paint for pavement markings for 150mm wide
yellow edge marking

A) Material

I) Roadline paint (white/yellow) - Cost @ Per Drum (20 litres) = RM 300.00


a) Approx. Coverage / Drum : 200 M2
b) Cost (per M2) RM 300.00 / 200 = RM 1.50

ii) ADD : Wastage : 10% = RM 0.15

iii)Material cost (per M2) = RM 1.65

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Setting equipments and Tools (1 set) :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment):
Allow sum Per day = RM 100.00
Total = RM 370.00

Productivity Per Day : 124 M2


Machinery Cost Per M2 : RM 370.00 / 124 = RM 2.98

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 124 M2


Workmen Cost Per M2 : RM 262.00 / 124 = RM 2.11

Row cost Per M2 = RM 6.75

ADD: P& O : 15% = RM 1.01

Rate Per M2. = RM 7.76


Take RM 7.75

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Repainting of Existing Marking Item e,page 32
Prepare and apply white temporary roadline paint for pavement markings 200mm wide
intermitent give-way line wide with 300mm length each and at 200mm gap

A) Material

I) Roadline paint (white/yellow) - Cost @ Per Drum (20 litres) = RM 300.00


a) Approx. Coverage / Drum : 200 M2
b) Cost (per M2) RM 300.00 / 200 = RM 1.50

ii) ADD : Wastage : 10% = RM 0.15

iii)Material cost (per M2) = RM 1.65

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Setting equipments and Tools (1 set) :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment):
Allow sum Per day = RM 100.00
Total = RM 370.00

Productivity Per Day : 124 M2


Machinery Cost Per M2 : RM 370.00 / 124 = RM 2.98

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 124 M2


Workmen Cost Per M2 : RM 262.00 / 124 = RM 2.11

Row cost Per M2 = RM 6.75

ADD: P& O : 15% = RM 1.01

Rate Per M2. = RM 7.76


Take RM 7.75

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Repainting of Existing Marking Item f, page32
Prepare and apply white temporary roadline paint for pavement markings for 300mm wide
continous stop line marking

A) Material

I) Roadline paint (white/yellow) - Cost @ Per Drum (20 litres) = RM 300.00


a) Approx. Coverage / Drum : 200 M2
b) Cost (per M2) RM 300.00 / 200 = RM 1.50

ii) ADD : Wastage : 10% = RM 0.15

iii)Material cost (per M2) = RM 1.65

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Setting equipments and Tools (1 set) :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment):
Allow sum Per day = RM 100.00
Total = RM 370.00

Productivity Per Day : 124 M2


Machinery Cost Per M2 : RM 370.00 / 124 = RM 2.98

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 124 M2


Workmen Cost Per M2 : RM 262.00 / 124 = RM 2.11

Row cost Per M2 = RM 6.75

ADD: P& O : 15% = RM 1.01

Rate Per M2. = RM 7.76


Take RM 7.75

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Repainting of Existing Marking Item g, page32
Prepare and apply white temporary roadline paint for pavement markings for 300mm wide
chevron hatching for merging / diverging traffic and cross hatching

A) Material

I) Roadline paint (white/yellow) - Cost @ Per Drum (20 litres) = RM 300.00


a) Approx. Coverage / Drum : 200 M2
b) Cost (per M2) RM 300.00 / 200 = RM 1.50

ii) ADD : Wastage : 10% = RM 0.15

iii)Material cost (per M2) = RM 1.65

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Setting equipments and Tools (1 set) :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment):
Allow sum Per day = RM 100.00
Total = RM 370.00

Productivity Per Day : 124 M2


Machinery Cost Per M2 : RM 370.00 / 124 = RM 2.98

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 124 M2


Workmen Cost Per M2 : RM 262.00 / 124 = RM 2.11

Row cost Per M2 = RM 6.75

ADD: P& O : 15% = RM 1.01

Rate Per M2. = RM 7.76


Take RM 7.75

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Repainting of Existing Marking Item h, page32
Prepare and apply white temporary roadline paint for pavement markings for "AWAS" and
other pavement lattering marking

A) Material

I) Roadline paint (white) - Cost @ Per Drum (20 litres) = RM 300.00


a) Approx. Coverage / Drum : 200 M2
b) Cost (per M2) RM 300.00 / 200 = RM 1.50

ii) ADD : Wastage : 10% = RM 0.15

iii)Material cost (per M2) = RM 1.65

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Setting equipments and Tools (1 set) :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment):
Allow sum Per day = RM 100.00
Total = RM 370.00

Productivity Per Day : 83 M2


Machinery Cost Per M2 : RM 370.00 / 83 = RM 4.46

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 83 M2


Workmen Cost Per M2 : RM 262.00 / 83 = RM 3.16

Row cost Per M2 = RM 9.26

ADD: P& O : 15% = RM 1.39

Rate Per M2. = RM 10.65


Take RM 10.65

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Repainting of Existing Marking Item i, page32
Prepare and apply white temporary roadline paint for pavement markings for pavement
directional arrow marking

A) Material

I) Roadline paint (white) - Cost @ Per Drum (20 litres) = RM 300.00


a) Approx. Coverage / Drum : 200 M2
b) Cost (per M2) RM 300.00 / 200 = RM 1.50

ii) ADD : Wastage : 10% = RM 0.15

iii)Material cost (per M2) = RM 1.65

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Setting equipments and Tools (1 set) :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment):
Allow sum Per day = RM 100.00
Total = RM 370.00

Productivity Per Day : 83 M2


Machinery Cost Per M2 : RM 370.00 / 83 = RM 4.46

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 83 M2


Workmen Cost Per M2 : RM 262.00 / 83 = RM 3.16

Row cost Per M2 = RM 9.26

ADD: P& O : 15% = RM 1.39

Rate Per M2. = RM 10.65


Take RM 10.65

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Repainting of Existing Marking Item j, page32
Prepare and apply black temporary roadline paint to erase and correct including necessary
adjustment of existing pavement markings

A) Material

I) Roadline paint (black) - Cost @ Per Drum (20 litres) = RM 300.00


a) Approx. Coverage / Drum : 200 M2
b) Cost (per M2) RM 300.00 / 200 = RM 1.50

ii) ADD : Wastage : 10% = RM 0.15

iii)Material cost (per M2) = RM 1.65

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Setting equipments and Tools (1 set) :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

ii) Miscellaneous items (Temporary traffic, signs, pickaxe, drilling tools & equipment):
Allow sum Per day = RM 100.00
Total = RM 370.00

Productivity Per Day : 102 M2


Machinery Cost Per M2 : RM 370.00 / 102 = RM 3.63

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 102 M2


Workmen Cost Per M2 : RM 262.00 / 102 = RM 2.57

Row cost Per M2 = RM 7.85

ADD: P& O : 15% = RM 1.18

Rate Per M2. = RM 9.02


Take RM 9.00

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Painting of New Markings Item a,page 33
Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings
or sizes100mm to 150mm wide single continuos edge line marking

A) Material

I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00


a) Approx. Coverage / MT 308 M2
b) Cost (per M2) RM 2,200.00 / 308 = RM 7.14

ii) Glass bead - Cost @ Per Mt RM 2,600.00


a) Approx. Coverage / Mt : 1,250 M2
b) Cost (per M2) RM 2,600.00 / 1250 = RM 2.08
= RM 9.22
ii) ADD : Wastage : 10% 0.92

iii)Material cost (per M2) = RM 10.15

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Pick-up truck (1T) for carrying Boiler:


1 x 1 Day @ RM 130.00 Per day = RM 130.00

iii)Boiler and heater :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

iv)Screeding machine :
1 x 1 Day @ RM 100.00 Per day = RM 100.00

v) Setting equipment and Tools (1 set)


1 x 1 Day @ RM 120.00 Per day = RM 120.00
Total = RM 620.00

Productivity Per Day : 160 M2


Machinery Cost Per M2 : RM 620.00 / 160 = RM 3.88

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 160 M2


Workmen Cost Per M2 : RM 262.00 / 160 = RM 1.64

Row cost Per M2 = RM 15.66

ADD: P& O : 15% = RM 2.35

Rate Per M2. = RM 18.01


Take RM 18.00

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Painting of New Markings Item b,page 33
Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings
of 150mm width single continuos center line and lane marking

A) Material

I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00


a) Approx. Coverage / MT 308 M2
b) Cost (per M2) RM 2,200.00 / 308 = RM 7.14

ii) Glass bead - Cost @ Per Mt RM 2,600.00


a) Approx. Coverage / Mt : 1,250 M2
b) Cost (per M2) RM 2,600.00 / 1250 = RM 2.08
= RM 9.22
ii) ADD : Wastage : 10% 0.92

iii)Material cost (per M2) = RM 10.15

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Pick-up truck (1T) for carrying Boiler:


1 x 1 Day @ RM 130.00 Per day = RM 130.00

iii)Boiler and heater :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

iv)Screeding machine :
1 x 1 Day @ RM 100.00 Per day = RM 100.00

v) Setting equipment and Tools (1 set)


1 x 1 Day @ RM 120.00 Per day = RM 120.00
Total = RM 620.00

Productivity Per Day : 160 M2


Machinery Cost Per M2 : RM 620.00 / 160 = RM 3.88

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 160 M2


Workmen Cost Per M2 : RM 262.00 / 160 = RM 1.64

Row cost Per M2 = RM 15.66

ADD: P& O : 15% = RM 2.35

Rate Per M2. = RM 18.01


Take RM 18.00

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Painting of New Markings Item c,page 33
Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings
for intermittent center line and lane marking of 100mm wide

A) Material

I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00


a) Approx. Coverage / MT 308 M2
b) Cost (per M2) RM 2,200.00 / 308 = RM 7.14

ii) Glass bead - Cost @ Per Mt RM 2,600.00


a) Approx. Coverage / Mt : 1,250 M2
b) Cost (per M2) RM 2,600.00 / 1250 = RM 2.08
= RM 9.22
ii) ADD : Wastage : 10% 0.92

iii)Material cost (per M2) = RM 10.15

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Pick-up truck (1T) for carrying Boiler:


1 x 1 Day @ RM 130.00 Per day = RM 130.00

iii)Boiler and heater :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

iv)Screeding machine :
1 x 1 Day @ RM 100.00 Per day = RM 100.00

v) Setting equipment and Tools (1 set)


1 x 1 Day @ RM 120.00 Per day = RM 120.00
Total = RM 620.00

Productivity Per Day : 160 M2


Machinery Cost Per M2 : RM 620.00 / 160 = RM 3.88

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 160 M2


Workmen Cost Per M2 : RM 262.00 / 160 = RM 1.64

Row cost Per M2 = RM 15.66

ADD: P& O : 15% = RM 2.35

Rate Per M2. = RM 18.01


Take RM 18.00

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Painting of New Markings Item d,page 33
Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement marking for
150mm wide single continuos edge marking

A) Material

I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00


a) Approx. Coverage / MT 308 M2
b) Cost (per M2) RM 2,200.00 / 308 = RM 7.14

ii) Glass bead - Cost @ Per Mt RM 2,600.00


a) Approx. Coverage / Mt : 1,250 M2
b) Cost (per M2) RM 2,600.00 / 1250 = RM 2.08
= RM 9.22
ii) ADD : Wastage : 10% 0.92

iii)Material cost (per M2) = RM 10.15

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Pick-up truck (1T) for carrying Boiler:


1 x 1 Day @ RM 130.00 Per day = RM 130.00

iii)Boiler and heater :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

iv)Screeding machine :
1 x 1 Day @ RM 100.00 Per day = RM 100.00

v) Setting equipment and Tools (1 set)


1 x 1 Day @ RM 120.00 Per day = RM 120.00
Total = RM 620.00

Productivity Per Day : 160 M2


Machinery Cost Per M2 : RM 620.00 / 160 = RM 3.88

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 160 M2


Workmen Cost Per M2 : RM 262.00 / 160 = RM 1.64

Row cost Per M2 = RM 15.66

ADD: P& O : 15% = RM 2.35

Rate Per M2. = RM 18.01


Take RM 18.00

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Painting of New Markings Item e, page33
Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings
for intermittent give-way line 200mm wide, with 300mm length each and 200mm gap

A) Material

I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00


a) Approx. Coverage / MT 308 M2
b) Cost (per M2) RM 2,200.00 / 308 = RM 7.14

ii) Glass bead - Cost @ Per Mt RM 2,600.00


a) Approx. Coverage / Mt : 1,250 M2
b) Cost (per M2) RM 2,600.00 / 1250 = RM 2.08
= RM 9.22
ii) ADD : Wastage : 10% 0.92

iii)Material cost (per M2) = RM 10.15

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Pick-up truck (1T) for carrying Boiler:


1 x 1 Day @ RM 130.00 Per day = RM 130.00

iii)Boiler and heater :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

iv)Screeding machine :
1 x 1 Day @ RM 100.00 Per day = RM 100.00

v) Setting equipment and Tools (1 set)


1 x 1 Day @ RM 120.00 Per day = RM 120.00
Total = RM 620.00

Productivity Per Day : 160 M2


Machinery Cost Per M2 : RM 620.00 / 160 = RM 3.88

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 160 M2


Workmen Cost Per M2 : RM 262.00 / 160 = RM 1.64

Row cost Per M2 = RM 15.66

ADD: P& O : 15% = RM 2.35

Rate Per M2. = RM 18.01


Take RM 18.00

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Painting of New Markings Item f, page 33
Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings
for continuos stop line of 300mm wide

A) Material

I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00


a) Approx. Coverage / MT 308 M2
b) Cost (per M2) RM 2,200.00 / 308 = RM 7.14

ii) Glass bead - Cost @ Per Mt RM 2,600.00


a) Approx. Coverage / Mt : 1,250 M2
b) Cost (per M2) RM 2,600.00 / 1250 = RM 2.08
= RM 9.22
ii) ADD : Wastage : 10% 0.92

iii)Material cost (per M2) = RM 10.15

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Pick-up truck (1T) for carrying Boiler:


1 x 1 Day @ RM 130.00 Per day = RM 130.00

iii)Boiler and heater :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

iv)Screeding machine :
1 x 1 Day @ RM 100.00 Per day = RM 100.00

v) Setting equipment and Tools (1 set)


1 x 1 Day @ RM 120.00 Per day = RM 120.00
Total = RM 620.00

Productivity Per Day : 160 M2


Machinery Cost Per M2 : RM 620.00 / 160 = RM 3.88

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 160 M2


Workmen Cost Per M2 : RM 262.00 / 160 = RM 1.64

Row cost Per M2 = RM 15.66

ADD: P& O : 15% = RM 2.35

Rate Per M2. = RM 18.01


Take RM 18.00

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Painting of New Markings Item g, page 33
Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings
for 300mm width chevron hatching for merging / diverging tracffic and cross hatching

A) Material

I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00


a) Approx. Coverage / MT 308 M2
b) Cost (per M2) RM 2,200.00 / 308 = RM 7.14

ii) Glass bead - Cost @ Per Mt RM 2,600.00


a) Approx. Coverage / Mt : 1,250 M2
b) Cost (per M2) RM 2,600.00 / 1250 = RM 2.08
= RM 9.22
ii) ADD : Wastage : 10% 0.92

iii)Material cost (per M2) = RM 10.15

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Pick-up truck (1T) for carrying Boiler:


1 x 1 Day @ RM 130.00 Per day = RM 130.00

iii)Boiler and heater :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

iv)Screeding machine :
1 x 1 Day @ RM 100.00 Per day = RM 100.00

v) Setting equipment and Tools (1 set)


1 x 1 Day @ RM 120.00 Per day = RM 120.00
Total = RM 620.00

Productivity Per Day : 122 M2


Machinery Cost Per M2 : RM 620.00 / 122 = RM 5.10

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 122 M2


Workmen Cost Per M2 : RM 262.00 / 122 = RM 2.16

Row cost Per M2 = RM 17.40

ADD: P& O : 15% = RM 2.61

Rate Per M2. = RM 20.02


Take RM 20.00

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Painting of New Markings Item h, page 33
Prepare and apply Transverse yellow reflective thermoplastic of 5.0 mm thick 600mm

A) Material

I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00


a) Approx. Coverage / MT 200 M2
b) Cost (per M2) RM 2,200.00 / 200 = RM 11.00

ii) Glass bead - Cost @ Per Mt RM 2,600.00


a) Approx. Coverage / Mt : 1,250 M2
b) Cost (per M2) RM 2,600.00 / 1,250 = RM 2.08
= RM 13.08
ii) ADD : Wastage : 10% 1.31

iii)Material cost (per M2) = RM 14.39

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Pick-up truck (1T) for carrying Boiler:


1 x 1 Day @ RM 130.00 Per day = RM 130.00

iii)Boiler and heater :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

iv)Screeding machine :
1 x 1 Day @ RM 100.00 Per day = RM 100.00

v) Setting equipment and Tools (1 set)


1 x 1 Day @ RM 120.00 Per day = RM 120.00
Total = RM 620.00

Productivity Per Day : 120 M2


Machinery Cost Per M2 : RM 620.00 / 120 = RM 5.17

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 120 M2


Workmen Cost Per M2 : RM 262.00 / 120 = RM 2.18

Row cost Per M2 = RM 21.74

ADD: P& O : 15% = RM 3.26

Rate Per M2. = RM 25.00


Take RM 25.00

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Painting of New Markings Item i, page 33
Prepare and apply Transverse yellow reflective thermoplastic of 5.0 mm thick and 500mm wide

A) Material

I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00


a) Approx. Coverage / MT 200 M2
b) Cost (per M2) RM 2,200.00 / 200 = RM 11.00

ii) Glass bead - Cost @ Per Mt RM 2,600.00


a) Approx. Coverage / Mt : 1,250 M2
b) Cost (per M2) RM 2,600.00 / 1,250 = RM 2.08
= RM 13.08
ii) ADD : Wastage : 10% 1.31

iii)Material cost (per M2) = RM 14.39

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Pick-up truck (1T) for carrying Boiler:


1 x 1 Day @ RM 130.00 Per day = RM 130.00

iii)Boiler and heater :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

iv)Screeding machine :
1 x 1 Day @ RM 100.00 Per day = RM 100.00

v) Setting equipment and Tools (1 set)


1 x 1 Day @ RM 120.00 Per day = RM 120.00
Total = RM 620.00

Productivity Per Day : 120 M2


Machinery Cost Per M2 : RM 620.00 / 120 = RM 5.17

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
Total RM 262.00

Productivity Per Day : 120 M2


Workmen Cost Per M2 : RM 262.00 / 120 = RM 2.18

Row cost Per M2 = RM 21.74

ADD: P& O : 15% = RM 3.26

Rate Per M2. = RM 25.00


Take RM 25.00

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Painting of New Markings Item j,page 33
Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings
of "AWAS" or other lattering on pavement marking

A) Material

I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00


a) Approx. Coverage / MT 308 M2
b) Cost (per M2) RM 2,200.00 / 308 = RM 7.14

ii) Glass bead - Cost @ Per Mt RM 2,600.00


a) Approx. Coverage / Mt : 1,250 M2
b) Cost (per M2) RM 2,600.00 / 1250 = RM 2.08
= RM 9.22
ii) ADD : Wastage : 10% 0.92

iii)Material cost (per M2) = RM 10.15

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Pick-up truck (1T) for carrying Boiler:


1 x 1 Day @ RM 130.00 Per day = RM 130.00

iii)Boiler and heater :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

iv)Screeding machine :
1 x 1 Day @ RM 100.00 Per day = RM 100.00

v) Setting equipment and Tools (1 set)


1 x 1 Day @ RM 120.00 Per day = RM 120.00
Total = RM 620.00

Productivity Per Day : 160 M2


Machinery Cost Per M2 : RM 620.00 / 160 = RM 3.88

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 160 M2


Workmen Cost Per M2 : RM 262.00 / 160 = RM 1.64

Row cost Per M2 = RM 15.66

ADD: P& O : 15% = RM 2.35

Rate Per M2. = RM 18.01


Take RM 18.00

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Painting of New Markings Item k, page 33
Prepare and apply 3.0 mm thick white or yellow reflective thermoplastic pavement markings
of pavement direction arrow

A) Material

I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00


a) Approx. Coverage / MT 308 M2
b) Cost (per M2) RM 2,200.00 / 308 = RM 7.14

ii) Glass bead - Cost @ Per Mt RM 2,600.00


a) Approx. Coverage / Mt : 1,250 M2
b) Cost (per M2) RM 2,600.00 / 1250 = RM 2.08
= RM 9.22
ii) ADD : Wastage : 10% 0.92

iii)Material cost (per M2) = RM 10.15

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Pick-up truck (1T) for carrying Boiler:


1 x 1 Day @ RM 130.00 Per day = RM 130.00

iii)Boiler and heater :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

iv)Screeding machine :
1 x 1 Day @ RM 100.00 Per day = RM 100.00

v) Setting equipment and Tools (1 set)


1 x 1 Day @ RM 120.00 Per day = RM 120.00
Total = RM 620.00

Productivity Per Day : 160 M2


Machinery Cost Per M2 : RM 620.00 / 160 = RM 3.88

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 160 M2


Workmen Cost Per M2 : RM 262.00 / 160 = RM 1.64

Row cost Per M2 = RM 15.66

ADD: P& O : 15% = RM 2.35

Rate Per M2. = RM 18.01


Take RM 18.00

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Painting of New Markings Item I,page 33
Prepare, supply and apply Tranverse raised rib thermoplastic on pavement of intermittent
center line100mm wide and 3.0mm thick

A) Material

I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00


a) Approx. Coverage / MT 308 M2
b) Cost (per M2) RM 2,200.00 / 308 = RM 7.14

ii) Glass bead - Cost @ Per Mt RM 2,600.00


a) Approx. Coverage / Mt : 1,250 M2
b) Cost (per M2) RM 2,600.00 / 1250 = RM 2.08
= RM 9.22
ii) ADD : Wastage : 10% 0.92

iii)Material cost (per M2) = RM 10.15

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Pick-up truck (1T) for carrying Boiler:


1 x 1 Day @ RM 130.00 Per day = RM 130.00

iii)Boiler and heater :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

iv)Screeding machine :
1 x 1 Day @ RM 100.00 Per day = RM 100.00

v) Setting equipment and Tools (1 set)


1 x 1 Day @ RM 120.00 Per day = RM 120.00
Total = RM 620.00

Productivity Per Day : 43 M2


Machinery Cost Per M2 : RM 620.00 / 43 = RM 14.27

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 43 M2


Workmen Cost Per M2 : RM 262.00 / 43 = RM 6.03

Row cost Per M2 = RM 30.44

ADD: P& O : 15% = RM 4.57

Rate Per M2. = RM 35.01


Take RM 35.00

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Painting of New Markings Item n, page 33
Prepare, supply and apply Tranverse raised rib thermoplastic on pavement of continuos
edge line 150mm and 3.0mm thick

A) Material

I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00


a) Approx. Coverage / MT 308 M2
b) Cost (per M2) RM 2,200.00 / 308 = RM 7.14

ii) Glass bead - Cost @ Per Mt RM 2,600.00


a) Approx. Coverage / Mt : 1,250 M2
b) Cost (per M2) RM 2,600.00 / 1250 = RM 2.08
= RM 9.22
ii) ADD : Wastage : 10% 0.92

iii)Material cost (per M2) = RM 10.15

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Pick-up truck (1T) for carrying Boiler:


1 x 1 Day @ RM 130.00 Per day = RM 130.00

iii)Boiler and heater :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

iv)Screeding machine :
1 x 1 Day @ RM 100.00 Per day = RM 100.00

v) Setting equipment and Tools (1 set)


1 x 1 Day @ RM 120.00 Per day = RM 120.00
Total = RM 620.00

Productivity Per Day : 43 M2


Machinery Cost Per M2 : RM 620.00 / 43 = RM 14.27

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 43 M2


Workmen Cost Per M2 : RM 262.00 / 43 = RM 6.03

Row cost Per M2 = RM 30.44

ADD: P& O : 15% = RM 4.57

Rate Per M2. = RM 35.01


Take RM 35.00

Road Marking
ROAD FURNITURES
MAINTENANCE OF ROAD MARKINGS
Painting of New Markings Item o, page 33
Prepare, supply and apply Tranverse raised rib thermoplastic on pavement of double line
100mm wide and 3.0mm thick

A) Material

I) Thernoplastic paint (White / Yellow ) - Cost @ Per MT= RM 2,200.00


a) Approx. Coverage / MT 308 M2
b) Cost (per M2) RM 2,200.00 / 308 = RM 7.14

ii) Glass bead - Cost @ Per Mt RM 2,600.00


a) Approx. Coverage / Mt : 1,250 M2
b) Cost (per M2) RM 2,600.00 / 1250 = RM 2.08
= RM 9.22
ii) ADD : Wastage : 10% 0.92

iii)Material cost (per M2) = RM 10.15

B) Machinery.

I) Pick-up truck (3.0T) for carrying, materials, tools and equipments :


1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Pick-up truck (1T) for carrying Boiler:


1 x 1 Day @ RM 130.00 Per day = RM 130.00

iii)Boiler and heater :


1 x 1 Day @ RM 120.00 Per day = RM 120.00

iv)Screeding machine :
1 x 1 Day @ RM 100.00 Per day = RM 100.00

v) Setting equipment and Tools (1 set)


1 x 1 Day @ RM 120.00 Per day = RM 120.00
Total = RM 620.00

Productivity Per Day : 43 M2


Machinery Cost Per M2 : RM 620.00 / 43 = RM 14.27

C) Workmen

I) Semi-killed worker (for setting)


1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General Worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii)Flagman
2 x 1 Day @ RM 35.00 Per day = RM 70.00
RM 262.00

Productivity Per Day : 43 M2


Workmen Cost Per M2 : RM 262.00 / 43 = RM 6.03

Row cost Per M2 = RM 30.44

ADD: P& O : 15% = RM 4.57

Rate Per M2. = RM 35.01


Take RM 35.00

Road Marking
ROAD FURNITURES
MAINTENANCE OF KERBS
Realignment of Existing Kerbs Item a Page 34
Excavate, dismantle and reinstall the existing concrete road kerb for straightening of misaligned kerbs

A) Material

i) Concrete blinding & haunching (per M) = RM 5.00

B) Workmen

i) General worker :
6 x 1 Day @ RM 38.00 Per day = RM 228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & equipments) :
Allow sum Per day = RM 100.00
Total RM 478.00

Productivity Per Day : 76 M M


Workmen Cost Per M : RM 478.00 / 76 = RM 6.32

Raw cost Per M = RM 11.32

ADD : P&O : 15% = RM 1.70

Rate Per M = RM 13.02


Take RM 13.00

Road Kerbs
ROAD FURNITURES
MAINTENANCE OF KERBS
Realignment of Existing Kerbs Item b(i) Page 34
Excavate, remove, dismantle and replace the damaged or missing concrete road kerb with new
concrete kerb Type I
A) Material

i) Kerb Type I (supply price / M) = RM 30.00

ii) Concrete blinding & haunching (per M) = RM 5.00

B) Workmen

i) General worker :
6 x 1 Day @ RM 38.00 Per day = RM 228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) :
Allow sum Per day = RM 100.00
Total RM 478.00

Productivity Per Day : 116 M


Workmen Cost Per M : RM 478.00 / 116 = RM 4.12

Raw cost Per M = RM 39.12

ADD : P&O : 15% = RM 5.87

Rate Per M = RM 44.99


Take RM 45.00

Road Kerbs
ROAD FURNITURES
MAINTENANCE OF KERBS
Realignment of Existing Kerbs Item b(ii) Page 34
Excavate, remove, dismantle and replace the damaged or missing concrete road kerb with new
concrete kerb Type II

A) Material

i) Kerb Type II (supply price / M) = RM 27.00

ii) Concrete blinding & haunching (per M) = RM 5.00

B) Workmen

i) General worker :
6 x 1 Day @ RM 38.00 Per day = RM 228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) :
Allow sum Per day = RM 100.00
Total RM 478.00

Productivity Per Day : 320 M M


Workmen Cost Per M : RM 478.00 / 320 = RM 1.49

Raw cost Per M = RM 33.49

ADD : P&O : 15% = RM 5.02

Rate Per M = RM 38.52


Take RM 38.50

Road Kerbs
ROAD FURNITURES
MAINTENANCE OF KERBS
Realignment of Existing Kerbs Item b(iii) Page 34
Excavate, remove, dismantle and replace the damaged or missing concrete road kerb with new
concrete kerb Type III

A) Material

i) Kerb Type III (supply price / M) = RM 29.00

ii) Concrete blinding & haunching (per M) = RM 5.00

B) Workmen

i) General worker :
6 x 1 Day @ RM 38.00 Per day = RM 228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) :
Allow sum Per day = RM 100.00
Total RM 478.00

Productivity Per Day : 141 M


Workmen Cost Per M : RM 478.00 / 141 = RM 3.39

Raw cost Per M = RM 37.39

ADD : P&O : 15% = RM 5.61

Rate Per M = RM 43.00


Take RM 43.00

Road Kerbs
ROAD FURNITURES
MAINTENANCE OF KERBS
Realignment of Existing Kerbs Item b(iv) Page 34
Excavate, remove, dismantle and replace the damaged or missing concrete road kerb with new
concrete kerb Type IV

A) Material

i) Kerb Type IV (supply price / M) = RM 23.00

ii) Concrete blinding & haunching (per M) = RM 5.00

B) Workmen

i) General worker :
6 x 1 Day @ RM 38.00 Per day = RM 228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) :
Allow sum Per day = RM 100.00
Total RM 478.00

Productivity Per Day : 128 M


Workmen Cost Per M : RM 478.00 / 128 = RM 3.73

Raw cost Per M = RM 31.73

ADD : P&O : 15% = RM 4.76

Rate Per M = RM 36.49


Take RM 36.50

Road Kerbs
ROAD FURNITURES
MAINTENANCE OF KERBS
Realignment of Existing Kerbs Item b(v) Page 34
Excavate, remove, dismantle and replace the damaged or missing concrete road kerb with new
concrete kerb Type V

A) Material

i) Kerb Type V (supply price / M) = RM 28.00

ii) Concrete blinding & haunching (per M) = RM 5.00

B) Workmen

i) General worker :
6 x 1 Day @ RM 38.00 Per day = RM 228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) :
Allow sum Per day = RM 100.00
Total RM 478.00

Productivity Per Day : 109 M


Workmen Cost Per M : RM 478.00 / 109 = RM 4.39

Raw cost Per M = RM 37.39

ADD : P&O : 15% = RM 5.61

Rate Per M = RM 42.99


Take RM 43.00

Road Kerbs
ROAD FURNITURES
MAINTENANCE OF KERBS
Installation of New Kerbs Item c(i) Page 34
Supply and install precast concrete road kerb of Type I including concrete bedding

A) Material

i) Kerb Type I (supply price / M) = RM 30.00

ii) Concrete blinding & haunching (per M) = RM 5.00

B) Workmen

i) General worker :
6 x 1 Day @ RM 38.00 Per day = RM 228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) :
Allow sum Per day = RM 100.00
Total RM 478.00

Productivity Per Day : 71 M


Workmen Cost Per M : RM 478.00 / 71 = RM 6.75

Raw cost Per M = RM 41.75

ADD : P&O : 15% = RM 6.26

Rate Per M = RM 48.01


Take RM 48.00

Road Kerbs
ROAD FURNITURES
MAINTENANCE OF KERBS
Installation of New Kerbs Item c(ii) Page 34
Supply and install precast concrete road kerb of Type II including concrete bedding

A) Material

i) Kerb Type II (supply price / M) = RM 27.00

ii) Concrete blinding & haunching (per M) = RM 5.00

B) Workmen

i) General worker :
6 x 1 Day @ RM 38.00 Per day = RM 228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) :
Allow sum Per day = RM 100.00
Total RM 478.00

Productivity Per Day : 105 M


Workmen Cost Per M : RM 478.00 / 105 = RM 4.55

Raw cost Per M = RM 36.55

ADD : P&O : 15% = RM 5.48

Rate Per M = RM 42.04


Take RM 42.00

Road Kerbs
ROAD FURNITURES
MAINTENANCE OF KERBS
Installation of New Kerbs Item c(iii) Page 34
Supply and install precast concrete road kerb of Type III including concrete bedding

A) Material

i) Kerb Type III (supply price / M) = RM 29.00

ii) Concrete blinding & haunching (per M) = RM 5.00

B) Workmen

i) General worker :
6 x 1 Day @ RM 38.00 Per day = RM 228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) :
Allow sum Per day = RM 100.00
Total RM 478.00

Productivity Per Day : 93 M


Workmen Cost Per M : RM 478.00 / 93 = RM 5.14

Raw cost Per M = RM 39.14

ADD : P&O : 15% = RM 5.87

Rate Per M = RM 45.01


Take RM 45.00

Road Kerbs
ROAD FURNITURES
MAINTENANCE OF KERBS
Installation of New Kerbs Item c(iv) Page 34
Supply and install precast concrete road kerb of Type IV including concrete bedding

A) Material

i) Kerb Type IV (supply price / M) = RM 23.00

ii) Concrete blinding & haunching (per M) = RM 5.00

B) Workmen

i) General worker :
6 x 1 Day @ RM 38.00 Per day = RM 228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) :
Allow sum Per day = RM 100.00
Total RM 478.00

Productivity Per Day : 95 M


Workmen Cost Per M : RM 478.00 / 95 = RM 5.06

Raw cost Per M = RM 33.06

ADD : P&O : 15% = RM 4.96

Rate Per M = RM 38.02


Take RM 38.00

Road Kerbs
ROAD FURNITURES
MAINTENANCE OF KERBS
Installation of New Kerbs Item c(v) Page 34
Supply and install precast concrete road kerb of Type V including concrete bedding

A) Material

i) Kerb Type V (supply price / M) = RM 28.00

ii) Concrete blinding & haunching (per M) = RM 5.00

B) Workmen

i) General worker :
6 x 1 Day @ RM 38.00 Per day = RM 228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) :
Allow sum Per day = RM 100.00
Total RM 478.00

Productivity Per Day : 99 M


Workmen Cost Per M : RM 478.00 / 99 = RM 4.83

Raw cost Per M = RM 37.83

ADD : P&O : 15% = RM 5.67

Rate Per M = RM 43.50


Take RM 43.50

Road Kerbs
ROAD FURNITURES
MAINTENANCE OF KERBS
Installation of New Kerbs Item c(vi) Page 34
Supply and install precast concrete road kerb of Type VI including concrete bedding

A) Material

i) Kerb Type VI (supply price / M) = RM 20.00

ii) Concrete blinding & haunching (per M) = RM 5.00

B) Workmen

i) General worker :
6 x 1 Day @ RM 38.00 Per day = RM 228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) :
Allow sum Per day = RM 100.00
Total RM 478.00

Productivity Per Day : 105 M


Workmen Cost Per M : RM 478.00 / 105 = RM 4.55

Raw cost Per M = RM 29.55

ADD : P&O : 15% = RM 4.43

Rate Per M = RM 33.99


Take RM 34.00

Road Kerbs
ROAD FURNITURES
MAINTENANCE OF KERBS
Installation of New Kerbs Item c(vii) Page 34
Supply and install precast concrete road kerb of Type VII including concrete bedding

A) Material

i) Kerb Type VII (supply price / M) = RM 30.00

ii) Concrete blinding & haunching (per M) = RM 5.00

B) Workmen

i) General worker :
6 x 1 Day @ RM 38.00 Per day = RM 228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) :
Allow sum Per day = RM 100.00
Total RM 478.00

Productivity Per Day : 40 M


Workmen Cost Per M : RM 478.00 / 40 = RM 11.95

Raw cost Per M = RM 46.95

ADD : P&O : 15% = RM 7.04

Rate Per M = RM 53.99


Take RM 52.00

Road Kerbs
ROAD FURNITURES
MAINTENANCE OF KERBS
Installation of New Kerbs Item c(viii) Page 34
Supply and install precast concrete road kerb of Type VIII including concrete bedding

A) Material

i) Kerb Type VIII (supply price / M) = RM 18.00

ii) Concrete blinding & haunching (per M) = RM 5.00

B) Workmen

i) General worker :
6 x 1 Day @ RM 38.00 Per day = RM 228.00

ii) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

iii) Miscellaneous items (Temporary traffic signs, pickaxe, masonry tools & fitting equipments) :
Allow sum Per day = RM 100.00
Total RM 478.00

Productivity Per Day : 73 M M


Workmen Cost Per M : RM 478.00 / 73 = RM 6.59

Raw cost Per M = RM 29.59

ADD : P&O : 15% = RM 4.44

Rate Per M = RM 34.03


Take RM 34.00

Road Kerbs
ROAD FURNITURES
MAINTENANCE OF KERBS Item d Page 34
Supply and apply one coat primer and two coats of approved weatherproof paint to existing concrete kerbs

A) Material

i) Roadline paint (White/Black) - Cost @ Per Can (5 litres) = RM 65.00


a) Approx. Coverage/Ca : 40 M
b) Cost (per M) : RM 65.00 / 40 = RM 1.63

ii) ADD
: Wastage : 10% = RM 0.16

iii) Material cost (per M) = RM 1.79

B) Machinery

i) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, wire brush, scraper and burner)
Allow sum Per day = RM 100.00

C) Workmen

i) Semi-skilled worker :
1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii) Flagman :
2 x 1 Day @ RM 35.00 Per day = RM 70.00
Total RM 512.00

Productivity Per Day : 149 M


Workmen Cost Per M : RM 512.00 / 149 = RM 3.44

Raw cost Per M = RM 5.22

ADD : P&O : 15% = RM 0.78

Rate Per M = RM 6.01


Take RM 6.00

Road Kerbs
ROAD FURNITURES
MAINTENANCE OF KERBS
Repainting of Existing Kerbs Item e Page 34
Scrape, brush, clean, prepare and apply one coat primer and two coats of approved weatherproof paint to existing
concrete kerbs

A) Material

i) Roadline paint (White/Black) - Cost @ Per Can (5 litres) = RM 65.00


a) Approx. Coverage/Ca : 40 M
b) Cost (per M) : RM 65.00 / 40 = RM 1.63

ii) ADD
: Wastage : 10% = RM 0.16

iii) Material cost (per M) = RM 1.79

B) Machinery

i) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, wire brush, scraper and burner)
Allow sum Per day = RM 100.00

C) Workmen

i) Semi-skilled worker :
1 x 1 Day @ RM 40.00 Per day = RM 40.00

ii) General worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii) Flagman :
2 x 1 Day @ RM 35.00 Per day = RM 70.00
Total RM 512.00

Productivity Per Day : 132 M


Workmen Cost Per M : RM 512.00 / 132 = RM 3.88

Raw cost Per M = RM 5.67

ADD : P&O : 15% = RM 0.85

Rate Per M = RM 6.52


Take RM 6.50

Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
Road Kerbs
ROAD FURNITURES
MAINTENANCE OF SIGNS
Installation of New Sign Item a Page35
Supply, erect and install 76 mm external diameter mild steel post complete with mounting frames, clips, bolts
and nuts, ledge angle, U-bolts, painting, concrete footing and excavation

A) Material

i) M.S. post (supply price) : RM 12.00 / M


: RM 12.00 x 4.00 M = RM 48.00

ii) Concrete footing :


0.75 x 1.50 x 0.75 @ RM ### = RM 182.69

iii) Excavation :
0.75 x 1.50 x 0.75 @ RM 7.35 = RM 6.20
RM 236.89

iv) Cost (per M) : RM 236.89 / 4.00 M = RM 59.22

B) Machinery

i) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) :
Allow sum Per day = RM 100.00
RM 250.00

Productivity Per Day : 52 M


Machinery Cost Per M : RM 250.00 / 52 = RM 4.81

C) Workmen

i) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii) Flagman :
2 x 1 Day @ RM 35.00 Per day = RM 70.00
Total = RM 287.00

Productivity Per Day : 52 M


Workmen Cost Per M : RM 287.00 / 52 = RM 5.52
Raw cost Per M = RM 69.55

ADD : P&O : 15% = RM 10.43

Rate Per M = RM 79.98


Take RM 80.00

Road Sign
ROAD FURNITURES
MAINTENANCE OF SIGNS
Installation of New Sign Item b Page35
Supply, erect and install 89 mm external diameter mild steel post complete with mounting frames, clips, bolts
and nuts, ledge angle, U-bolts, painting and concrete footing

A) Material

i) M.S. post (supply price) : RM 14.00 / M


: RM 14.00 x 5.00 M = RM 70.00

ii) Concrete footing :


0.75 x 1.80 x 0.75 @ RM ### = RM 219.23

iii) Excavation :
0.75 x 1.80 x 0.75 @ RM 7.35 = RM 7.44
RM 296.67

iv) Cost (per M) : RM 296.67 / 5.00 M = RM 59.33

B) Machinery

i) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) :
Allow sum Per day = RM 100.00
RM 250.00

Productivity Per Day : 53 M


Machinery Cost Per M : RM 250.00 / 53 = RM 4.76

C) Workmen

i) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii) Flagman :
2 x 1 Day @ RM 35.00 Per day = RM 70.00
Total = RM 287.00

Productivity Per Day : 53 M


Workmen Cost Per M : RM 287.00 / 53 = RM 5.47
Raw cost Per M = RM 69.56

ADD : P&O : 15% = RM 10.43

Rate Per M = RM 80.00


Take RM 80.00

Road Sign
ROAD FURNITURES
MAINTENANCE OF SIGNS
Installation of New Sign Item c Page35
Supply, erect and install 114 mm external diameter mild steel post complete with mounting frames, clips, bolts
and nuts, ledge angle, U-bolts, painting, and concrete footing

A) Material

i) M.S. post (supply price) : RM 16.00 / M


: RM 16.00 x 5.00 M = RM 80.00

ii) Concrete footing :


0.80 x 1.80 x 0.75 @ RM ### = RM 233.84

iii) Excavation :
0.80 x 1.80 x 0.75 @ RM 7.35 = RM 7.94
RM 321.78

iv) Cost (per M) : RM 321.78 / 5.00 M = RM 64.36

B) Machinery

i) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) :
Allow sum Per day = RM 100.00
RM 250.00

Productivity Per Day : 56 M


Machinery Cost Per M : RM 250.00 / 56 = RM 4.44

C) Workmen

i) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii) Flagman :
2 x 1 Day @ RM 35.00 Per day = RM 70.00
Total = RM 287.00

Productivity Per Day : 56 M


Workmen Cost Per M : RM 287.00 / 56 = RM 5.10
Raw cost Per M = RM 73.89

ADD : P&O : 15% = RM 11.08

Rate Per M = RM 84.98


Take RM 85.00

Road Sign
ROAD FURNITURES
MAINTENANCE OF SIGNS
Installation of New Sign Item d Page35
Supply, erect and install 140 mm external diameter mild steel post complete with mounting frames, clips, bolts
and nuts, ledge angle, U-bolts, painting and concrete footing

A) Material

i) M.S. post (supply price) : RM 20.00 / M


: RM 20.00 x 6.30 M = RM 126.00

ii) Concrete footing :


0.80 x 2.00 x 0.75 @ RM ### = RM 259.82

iii) Excavation :
0.80 x 2.00 x 0.75 @ RM 7.35 = RM 8.82
RM 394.64

iv) Cost (per M) : RM 394.64 / 6.30 M = RM 62.64

B) Machinery

i) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) :
Allow sum Per day = RM 100.00
RM 250.00

Productivity Per Day : 48 M


Machinery Cost Per M : RM 250.00 / 48 = RM 5.25

C) Workmen

i) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii) Flagman :
2 x 1 Day @ RM 35.00 Per day = RM 70.00
Total = RM 287.00

Productivity Per Day : 48 M


Workmen Cost Per M : RM 287.00 / 48 = RM 6.03
Raw cost Per M = RM 73.92

ADD : P&O : 15% = RM 11.09

Rate Per M = RM 85.01


Take RM 85.00

Road Sign
ROAD FURNITURES
MAINTENANCE OF SIGNS
Installation of New Sign Item e Page35
Supply, erect and install 168 mm external diameter mild steel post complete with mounting frames, clips, bolts
and nuts, ledge angle, U-bolts, painting and concrete footing

A) Material

i) M.S. post (supply price) : RM 23.00 / M


: RM 23.00 x 6.30 M = RM 144.90

ii) Concrete footing :


0.80 x 2.00 x 0.75 @ RM ### = RM 259.82

iii) Excavation :
0.80 x 2.00 x 0.75 @ RM 7.35 = RM 8.82
RM 413.54

iv) Cost (per M) : RM 413.54 / 6.30 M = RM 65.64

B) Machinery

i) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) :
Allow sum Per day = RM 100.00
RM 250.00

Productivity Per Day : 43 M


Machinery Cost Per M : RM 250.00 / 43 = RM 5.88

C) Workmen

i) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii) Flagman :
2 x 1 Day @ RM 35.00 Per day = RM 70.00
Total = RM 287.00

Productivity Per Day : 43 M


Workmen Cost Per M : RM 287.00 / 43 = RM 6.75
Raw cost Per M = RM 78.28

ADD : P&O : 15% = RM 11.74

Rate Per M = RM 90.02


Take RM 90.00

Road Sign
ROAD FURNITURES
MAINTENANCE OF SIGNS
Installation of New Sign Item f Page35
Supply, erect and install 194 mm external diameter mild steel post complete with mounting frames, clips, bolts
and nuts, ledge angle, U-bolts, painting and concrete footing

A) Material

i) M.S. post (supply price) : RM 25.00 / M


: RM 25.00 x 8.00 M = RM 200.00

ii) Concrete footing :


0.90 x 2.00 x 0.90 @ RM ### = RM 350.76

iii) Excavation :
0.90 x 2.00 x 0.90 @ RM 7.35 = RM 11.91
RM 562.67

iv) Cost (per M) : RM 562.67 / 8.00 M = RM 70.33

B) Machinery

i) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) :
Allow sum Per day = RM 100.00
RM 250.00

Productivity Per Day : 44 M


Machinery Cost Per M : RM 250.00 / 44 = RM 5.72

C) Workmen

i) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General worker :


4 x 1 Day @ RM 38.00 Per day = RM 152.00

iii) General worker :


2 x 1 Day @ RM 35.00 Per day = RM 70.00
Total = RM 287.00

Productivity Per Day : 44 M


Workmen Cost Per M : RM 287.00 / 44 = RM 6.57
Raw cost Per M = RM 82.62

ADD : P&O : 15% = RM 12.39

Rate Per M = RM 95.02


Take RM 95.00

Road Sign
ROAD FURNITURES
MAINTENANCE OF SIGNS
Installation of New Sign Item g(I) Page35
Supply and install 600 mm aluminium Ragulatory and Warning sign plates inclusive of fabrication, mounting
frames, clips, U-bolts, spot welding to post and ancillary materials with high intensity reflective sheeting

A) Material

i) Sign plate (supply price / No.) : = RM 300.00

B) Machinery

i) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) :
Allow sum Per day = RM 100.00
RM 250.00

Productivity Per Day : 5 Nos


Machinery Cost Per No. : RM 250.00 / 5 = RM 51.02

C) Workmen

i) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General worker :


5 x 1 Day @ RM 38.00 Per day = RM 190.00

iii) Flagman :
2 x 1 Day @ RM 35.00 Per day = RM 70.00
Total = RM 325.00

Productivity Per Day : 5 Nos.


Workmen Cost Per No. : RM 325.00 / 5 = RM 66.33
Raw cost Per No. = RM 417.35

ADD : P&O : 15% = RM 62.60

Rate Per No. = RM 479.95


Take RM 480.00

Road Sign
ROAD FURNITURES
MAINTENANCE OF SIGNS
Installation of New Sign Item g(ii) Page35
Supply and install aluminium Directional and information sign plates inclusive of fabrication, mounting frames,
clips, U-bolts, spot welding to post and ancillary materials with high intensity reflective sheeting

A) Material

i) Sign plate (supply price / M2) : = RM 539.50

B) Machinery

i) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Backhoe :
1 x 1 Day @ RM 270.00 Per day = RM 270.00

iii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) :
Allow sum Per day = RM 100.00
RM 520.00

Productivity Per Day : 12 M2


Machinery Cost Per M2 : RM 520.00 / 12 = RM 42.62

C) Workmen

i) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General worker :


5 x 1 Day @ RM 38.00 Per day = RM 190.00

iii) Flagman :
2 x 1 Day @ RM 35.00 Per day = RM 70.00
Total = RM 325.00

Productivity Per Day : 12 M2


Workmen Cost Per M2 : RM 325.00 / 12 = RM 26.64
Raw cost Per M2 = RM 608.76

ADD : P&O : 15% = RM 91.31

Rate Per M2 = RM 700.08


Take RM 700.00

Road Sign
ROAD FURNITURES
MAINTENANCE OF SIGNS
Installation of New Sign Item h(I) Page35
Supply and install 600 mm aluminium Warning and Regulatory sign plates inclusive of fabrication, mounting
frames, clips, U-bolts, spot welding to post and ancillary materials with engineering grade reflective sheeting

A) Material

i) Sign plate (supply price / No.) : = RM 250.00

B) Machinery

i) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

iii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) :
Allow sum Per day = RM 100.00
RM 250.00

Productivity Per Day : 7 Nos.


Machinery Cost Per No. : RM 250.00 / 7 = RM 34.97

C) Workmen

i) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General worker :


5 x 1 Day @ RM 38.00 Per day = RM 190.00

iii) Flagman :
2 x 1 Day @ RM 35.00 Per day = RM 70.00
Total = RM 325.00

Productivity Per Day : 7 Nos.


Workmen Cost Per No. : RM 325.00 / 7 = RM 45.45
Raw cost Per No. = RM 330.42

ADD : P&O : 15% = RM 49.56

Rate Per No. = RM 379.98


Take RM 380.00

Road Sign
ROAD FURNITURES
MAINTENANCE OF SIGNS
Installation of New Sign Item h(ii) Page35
Supply and install aluminium Directional and information sign plates inclusive of fabrication, mounting frames,
clips, U-bolts, spot welding to post and ancillary materials with engineering grade reflective sheeting

A) Material

i) Sign plate (supply price / M2) : = RM 479.50

B) Machinery

i) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Backhoe :
1 x 1 Day @ RM 270.00 Per day = RM 270.00

iii) Miscellaneous items (Temporary traffic signs, oxy-cutter, crowbar, pickaxe and hammer) :
Allow sum Per day = RM 100.00
RM 520.00

Productivity Per Day : 9 M2


Machinery Cost Per M2 : RM 520.00 / 9 = RM 58.10

C) Workmen

i) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General worker :


5 x 1 Day @ RM 38.00 Per day = RM 190.00

iii) Flagman :
2 x 1 Day @ RM 35.00 Per day = RM 70.00
Total = RM 325.00

Productivity Per Day : 9 M2


Workmen Cost Per M2 : RM 325.00 / 9 = RM 36.31
Raw cost Per M2 = RM 573.91

ADD : P&O : 15% = RM 86.09

Rate Per M2 = RM 660.00


Take RM 660.00

Road Sign
ROAD FURNITURES
MAINTENANCE OF SIGNS
Repair and Adjustment of Existing Sign Item a Page36
Dismantle and repair the dented portion of sign panel, and reinstall existing warning and regulatory signboard
panels of size not exceeding 1.0 m2 inclusive of new mounting, clips, U-bolts and other incidentals necessary

A) Material

i) Mounting bracket, clips and U-bolts (supply price / Set) = RM 19.30

B) Machinery

i) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, power drill tools & fitting equipments) :
Allow sum Per day = RM 100.00

C) Workmen

i) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General worker :


5 x 1 Day @ RM 38.00 Per day = RM 190.00
Total RM 505.00

Productivity Per Day : 10 Nos.


Workmen Cost Per No. : RM 505.00 / 10 = RM 51.17
Raw cost Per No. = RM 70.47

ADD : P&O : 15% = RM 10.57

Rate Per No. = RM 81.03


Take RM 81.00

Road Sign
ROAD FURNITURES
MAINTENANCE OF SIGNS
Repair and Adjustment of Existing Sign Item b Page36
Dismantle and repair the dented portion of sign panel, and reinstall existing Warning and Regulatory signboard
panels of size exceeding 1.0 m2 but not exceeding 3.0 m2 inclusive of new mounting, clips, U-bolts and other
incidentals necessary

A) Material

i) Mounting bracket, clips and U-bolts (supply price / Set) = RM 30.00

B) Machinery

i) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, power drill tools & fitting equipments) :
Allow sum Per day = RM 100.00

C) Workmen

i) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General worker :


5 x 1 Day @ RM 38.00 Per day = RM 190.00
Total RM 505.00

Productivity Per Day : 5 Nos.


Workmen Cost Per No. : RM 505.00 / 5 = RM 109.31
Raw cost Per No. = RM 139.31

ADD : P&O : 15% = RM 20.90

Rate Per No. = RM 160.20


Take RM 160.00

Road Sign
ROAD FURNITURES
MAINTENANCE OF SIGNS
Repair andand
Dismantle Adjustment
repair theof dented
Existing Sign of sign panel, and reinstall existing Directional
portion Item c Page36
and Information
signboard panels of size not exceeding 1.0 m2 inclusive of new mounting, clips, U-bolts and other incidentals
necessary

A) Material

i) Mounting bracket, clips and U-bolts (supply price / Set) = RM 20.00

B) Machinery

i) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, power drill tools & fitting equipments) :
Allow sum Per day = RM 100.00

C) Workmen

i) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General worker :


5 x 1 Day @ RM 38.00 Per day = RM 190.00
Total RM 505.00

Productivity Per Day : 8 Nos.


Workmen Cost Per No. : RM 505.00 / 8 = RM 66.98
Raw cost Per No. = RM 86.98

ADD : P&O : 15% = RM 13.05

Rate Per No. = RM 100.02


Take RM 100.00

Road Sign
ROAD FURNITURES
MAINTENANCE OF SIGNS
Repair and Adjustment of Existing Sign Item d Page36
Dismantle and repair the dented portion of sign panel, and reinstall existing Directional and Information
signboard panels of size exceeding 1.0 m2 but not exceeding 3.0 m2 inclusive of new mounting, clips, U-bolts
and other incidentals necessary

A) Material

i) Mounting bracket, clips and U-bolts (supply price / Set) = RM 30.00

B) Machinery

i) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, power drill tools & fitting equipments) :
Allow sum Per day = RM 100.00

C) Workmen

i) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General worker :


7 x 1 Day @ RM 38.00 Per day = RM 266.00
Total RM 581.00

Productivity Per Day : 4 Nos.


Workmen Cost Per No. : RM 581.00 / 4 = RM 144.17
Raw cost Per No. = RM 174.17

ADD : P&O : 15% = RM 26.13

Rate Per No. = RM 200.29


Take RM 200.00

Road Sign
ROAD FURNITURES
MAINTENANCE OF SIGNS
Repair and Adjustment of Existing Sign Item e Page36
Dismantle and repair the dented portion of sign panel, and reinstall existing Directional and Information
signboard panels of size exceeding 3.0 m2 but not exceeding 6.0 m2 inclusive of new mounting, clips, U-bolts
and other incidentals necessary

A) Material

i) Mounting bracket, clips and U-bolts (supply price / Set) = RM 50.00

B) Machinery

i) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, power drill tools & fitting equipments) :
Allow sum Per day = RM 100.00

C) Workmen

i) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General worker :


7 x 1 Day @ RM 38.00 Per day = RM 266.00
Total RM 581.00

Productivity Per Day : 3 Nos.


Workmen Cost Per No. : RM 581.00 / 3 = RM 211.27
Raw cost Per No. = RM 261.27

ADD : P&O : 15% = RM 39.19

Rate Per No. = RM 300.46


Take RM 300.00

Road Sign
ROAD FURNITURES
MAINTENANCE OF SIGNS
Repair and Adjustment of Existing Sign Item f Page36
Dismantle and repair the dented portion of sign panel, and reinstall existing Directional and Information
signboard panels of size exceeding 6.0 m2 but not exceeding 9.0 m2 inclusive of new mounting, clips, U-bolts
and other incidentals necessary

A) Material

i) Mounting bracket, clips and U-bolts (supply price / Set) = RM 70.00

B) Machinery

i) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, power drill tools & fitting equipments) :
Allow sum Per day = RM 100.00

C) Workmen

i) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General worker :


7 x 1 Day @ RM 38.00 Per day = RM 266.00
Total RM 581.00

Productivity Per Day : 2 Nos.


Workmen Cost Per No. : RM 581.00 / 2 = RM 234.27
Raw cost Per No. = RM 304.27

ADD : P&O : 15% = RM 45.64

Rate Per No. = RM 349.92


Take RM 350.00

Road Sign
ROAD FURNITURES
MAINTENANCE OF SIGNS
Repair and Adjustment of Existing Sign Item g Page36
Dismantle and repair the dented portion of sign panel, and reinstall existing Directional and Information
signboard panels of size exceeding 9.0 m2 but not exceeding 12.0 m2 inclusive of new mounting, clips, U-
bolts and other incidentals necessary

A) Material

i) Mounting bracket, clips and U-bolts (supply price / Set) = RM 90.00

B) Machinery

i) Pick-up truck (3T) for carrying workers, materials, tools and equipments :
1 x 1 Day @ RM 150.00 Per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, power drill tools & fitting equipments) :
Allow sum Per day = RM 100.00

C) Workmen

i) Ganger :
1 x 1 Day @ RM 65.00 Per day = RM 65.00

ii) General worker :


7 x 1 Day @ RM 38.00 Per day = RM 266.00
Total RM 581.00

Productivity Per Day : 2 Nos.


Workmen Cost Per No. : RM 581.00 / 2 = RM 284.80
Raw cost Per No. = RM 374.80

ADD : P&O : 15% = RM 56.22

Rate Per No. = RM 431.02


Take RM 431.00
.

Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;

Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;
;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;

Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
Road Sign
ROAD FURNITURES
MAINTENANCE OF KILOMETER POSTS
Replacement / Install of Kilometer Posts Item a Page 37
Provide everything necessary for dismantle, remove and dispose the damaged existing
Kilometre and replace with new Kilometre post Type "A"

A) Material

I) Precast r.c. Kilometre post (supply price / No.) = RM 300.00

B) Machinery

I) Pick-up truck (3.0T) for carrying materials, workers and tools :

1 x 1 Day @ RM 150.00 per day = RM 150.00

ii) Jackhammer :

1 x 1 Day @ RM 100.00 per day = RM 100.00

iii) Miscellaneous items (Temporary traffic signs, cleaning tools and equipments)

Allow sum : per day = RM 100.00

C) Workmen

i) Ganger :

1 x 1 Day @ RM 65.00 per day = RM 65.00

ii) General worker

5 x 1 Day @ RM 38.00 per day = RM 190.00


RM 605.00

Productivity Per day : 2 Nos


Workmen Cost Per No. : RM 605.00 / 2 = RM 273.76
Raw cost per No. = RM 573.76

ADD : P&O : 15% = RM 86.06

Rate Per No. = RM 659.82


Take RM 660.00

Kilometer Post
ROAD FURNITURES
MAINTENANCE OF KILOMETER POSTS
Replacement / Install of Kilometer Posts Item b Page 37
Provide everything necessary for dismantle, remove and dispose the damaged existing
Kilometre and replace with new Kilometre post Type "B"

A) Material

I) Precast r.c. Kilometre post (supply price / No.) = RM 200.00

B) Machinery

I) Pick-up truck (3.0T) for carrying materials, workers and tools :

1 x 1 Day @ RM 150.00 per day = RM 150.00

ii) Jackhammer :

1 x 1 Day @ RM 100.00 per day = RM 100.00

iii) Miscellaneous items (Temporary traffic signs, cleaning tools and equipments)

Allow sum : per day = RM 100.00

C) Workmen

I) Ganger :

1 x 1 Day @ RM 65.00 per day = RM 65.00

ii) General worker

5 x 1 Day @ RM 38.00 per day = RM 190.00


RM 605.00

Productivity Per day : 3 Nos


Workmen Cost Per No. : RM 605.00 / 3 = RM 182.78
Raw cost per No. = RM 382.78

ADD : P&O : 15% = RM 57.42

Rate Per No. = RM 440.20


Take RM 440.00

Kilometer Post
ROAD FURNITURES
MAINTENANCE OF DELINATOR POSTS Item a Page 38
Replacement of Existing Delinator Posts
Remove, dismantle and dispose the damaged delineator post

A) Machinery

I) Pick-up truck (3.0T) for carrying materials, workers and tools :

1 x 1 Day @ RM 150.00 per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, cleaning tools and equipments)

Allow sum : = RM 80.00

B) Workmen

I) General worker

4 x 1 Day @ RM 38.00 per day = RM 152.00


Total = 382.00

Productivity Per day : 55 Nos


Workmen Cost Per No. : RM 382.00 / 55 = RM 6.95
Raw cost per No. = RM 6.95

ADD : P&O : 15% = RM 1.04

Rate Per No. RM 7.99


Take RM 8.00

Delineator Post
ROAD FURNITURES
MAINTENANCE OF DELINATOR POSTS
Replacement of Existing Delinator Posts Item b Page 38
Supply and install new 36" Type 2 (Flat top - SH236SMA) flexible delineator post complete with anchor to
replace the existing damaged or missing post

A) Material

I) Flexible delineator post (supply price / No.) = RM 125.00

B) Machinery

I) Pick-up truck (3.0T) for carrying materials, workers and tools :

1 x 1 Day @ RM 150.00 per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, cleaning tools and equipments)

Allow sum : = RM 100.00

C) Workmen

I) Ganger :

1 x 1 Day @ RM 65.00 per day = RM 65.00

I) General worker

4 x 1 Day @ RM 38.00 per day = RM 152.00


Total = RM 467.00

Productivity Per day : 33 Nos


Workmen Cost Per No. : RM 467.00 / 33 = RM 14.15
Raw cost per No. = RM 139.15

ADD : P&O : 15% = RM 20.87

Rate Per No. = RM 160.02


Take RM 160.00

Delineator Post
ROAD FURNITURES
MAINTENANCE OF DELINATOR POSTS
Replacement of Existing Delinator Posts Item c Page 38
Supply and install new reflector strips complete with bolts and nuts to replace the missing
and damaged existing delinator strips

A) Material

I) G.I strip, c/w, clip, washer, bolt and nuts (supply price/Set) = RM 5.00

B) Machinery

I) Pick-up truck (3.0T) for carrying materials, workers , tools and equipments :

1 x 1 Day @ RM 150.00 per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, cleaning tools and equipments)

Allow sum : = RM 80.00

C) Workmen

I) General worker

3 x 1 Day @ RM 38.00 per day = RM 114.00


Total = RM 344.00

Productivity Per day : 58 Nos


Workmen Cost Per No. : RM 344.00 / 58 = RM 5.96
Raw cost per No. = RM 10.96

ADD : P&O : 15% = RM 1.64

Rate Per No. = RM 12.61


Take RM 12.60

Delineator Post
ROAD FURNITURES
MAINTENANCE OF DELINATOR POSTS
Installation of New Posts and Reflector Units Item d Page 38

Remove, dismantle, disposed and install new timber post to replace the existing damaged or missing post

A) Material

I) Delineator post (supply price / No) = RM 18.20

B) Machinery

I) Pick-up truck (3.0T) for carrying materials, workers and tools :

1 x 1 Day @ RM 150.00 per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, cleaning tools and equipments)

Allow sum : Per day = RM 80.00

C) Workmen

I) Ganger :

1 x 1 Day @ RM 65.00 per day = RM 65.00

I) General worker

4 x 1 Day @ RM 38.00 per day = RM 152.00


Total = RM 447.00

Productivity Per day : 51 Nos


Workmen Cost Per No. : RM 447.00 / 51 = RM 8.78
Raw cost per No. = RM 26.98

ADD : P&O : 15% = RM 4.05

Rate Per No. = RM 31.03

Take RM 31.00

Delineator Post
ROAD FURNITURES
MAINTENANCE OF DELINATOR POSTS
Installation of New Posts and Reflector Units Item e Page 38
Supply and install new delineator timber post

A) Material

I) Delineator post (supply price / No) = RM 18.20

B) Machinery

I) Pick-up truck (3.0T) for carrying materials, workers and tools :

1 x 1 Day @ RM 150.00 per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, cleaning tools and equipments)

Allow sum : Per day = RM 80.00

C) Workmen

I) Ganger :

1 x 1 Day @ RM 65.00 per day = RM 65.00

I) General worker

4 x 1 Day @ RM 38.00 per day = RM 152.00


Total = RM 447.00

Productivity Per day : 51 Nos


Workmen Cost Per No. : RM 447.00 / 51 = RM 8.78
Raw cost per No. = RM 26.98

ADD : P&O : 15% = RM 4.05

Rate Per No. = RM 31.03


Take RM 31.00

Delineator Post
ROAD FURNITURES
MAINTENANCE OF DELINATOR POSTS
Installation of New Posts and Reflector Units Item f Page 38
Supply and install new 36" Type 2 (Flat top - SH236SMA) flexible delineator post complete with anchor
soil anchor

A) Material

I) Delineator post (supply price / No) = RM 125.00

B) Machinery

I) Pick-up truck (3.0T) for carrying materials, workers and tools :

1 x 1 Day @ RM 150.00 per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, cleaning tools and equipments)

Allow sum : Per day = RM 100.00

C) Workmen

I) Ganger :

1 x 1 Day @ RM 65.00 per day = RM 65.00

I) General worker

4 x 1 Day @ RM 38.00 per day = RM 152.00


Total = RM 467.00

Productivity Per day : 52 Nos


Workmen Cost Per No. : RM 467.00 / 52 = RM 8.93
Raw cost per No. = RM 133.93

ADD : P&O : 15% = RM 20.09

Rate Per No. = RM 154.02


Take RM 154.00

Delineator Post
ROAD FURNITURES
MAINTENANCE OF DELINATOR POSTS
Installation of New Posts and Reflector Units Item g Page 38
Supply and install new delineator strips complete with bolts, nuts and fittings

A) Material

I) G.I. Strip, c/w. clip, washer, bolt and nuts (supply price/Set) = RM 5.00

B) Machinery

I) Pick-up truck (3.0T) for carrying materials, workers and tools :

1 x 1 Day @ RM 150.00 per day = RM 150.00

ii) Miscellaneous items (Temporary traffic signs, cleaning tools and equipments)

Allow sum : Per day = RM 80.00

C) Workmen

I) Ganger :

1 x 1 Day @ RM 65.00 per day = RM 65.00

I) General worker

3 x 1 Day @ RM 38.00 per day = RM 114.00


Total = RM 409.00

Productivity Per day : 75 Nos


Workmen Cost Per No. : RM 409.00 / 75 = RM 5.45
Raw cost per No. = RM 10.45

ADD : P&O : 15% = RM 1.57

Rate Per No. = RM 12.02


Take RM 12.00

Delineator Post
ROAD FURNITURES
MISCELLANEOUS
Hidro Cell Item a Page39
Supply and install Hidro Cell Cluster containing 37 tubes complete with safety belt, bolts,
washers, nuts, support legs and hidro cells and all neceassary fittings

A) Material

I) Hidro Cell = = RM 22,851.00

ADD : P&O : 15% = RM 3,427.65

Rate Per No. = RM 26,278.65

Take RM 26,278.00

Misc
ROAD FURNITURES
MISCELLANEOUS
Hidro Cell Item b Page39
Provide everything necessary for refilling fluid in the Hidro cell cluster

A) Machinery

I) Water pump (3" dia.)


1 x 1 Day @ RM 100.00 per day = RM 100.00

ii) Miscellaneous
Allow sum : RM 50.00

iii) Pick-up truck c/w water tank


1 x 1 Day @ RM 150.00 per day = RM 150.00
RM 300.00
Productivity Per Day : 1 No
Machinery Cost Per No : RM 300.00 / 1 RM 352.94

B) Workmen

I) Ganger

1 x 1 Day @ RM 65.00 per day =RM 65.00

ii) General worker

2 x 1 Day @ RM 38.00 per day =RM 76.00


Total =RM 141.00

Productivity Per day : 1 Nos


Workmen Cost Per No. : RM 141.00 / 1 = RM 131.90

Raw cost per No. = RM 484.84

ADD : P&O : 15% = RM 72.73

Rate Per No. = RM 557.57

Take RM 557.00