You are on page 1of 2

Overhauling Flash Report

KAWAS OVERHAUL FOR FY 2013-14 MINOR/R&M of ST 1C A. OH Activity Progress Report: A1. OH Completion Score:
SNo Dept/Section Total Act. Plan Act. to be Act. Incomplete Activities Compl. till Compl. Yesterday

Date :16.07.2013 15:36:13 Page : 1 of 2

% Remark Compl.

Act Status Last not Updated Update on /Not Started

1 2 3 4

MM-ST TURBINE & AUXILLARIES ELECTRICAL ACTIVITIES C&I ACTIVITIES COMMISSIONING ACTIVITIES TOTAL

14 14 40 6 74

0 0 0 2 2

0 0 0 2 2

0 0 0 0 0

0 0 0 0 0

15.07.2013

A2. Other Activities Status: SNo 1 2 3 Description Activities to be completed today or later but already completed Activities to be completed today or later and are in progress Activities which should have started till yesterday but not started
Total no of Activities

0 9 1

B. Milestones Report: SNo 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 Milestone Stopping of turning gear Desynchronisation Decoupling of HP-LP Decoupling of LP-Gen ST Field equipment upgradation ST Gen Rotor threadout Bearing Boxup Stop Valve/ Control Valve servicing Testing of Gen Rotor and Stator ST BOP Mark VIe Panel Commissioning Installation of numerical Relay ST Generator Rotor thread in ST Mark VIe Turbine Control Panel Comm Final Alignment Correction BOP Control Upgrade Coupling of LP-Gen Coupling of HP-LP UPS Installation Final Box-up Control Room Upgrade Machine on Turning gear

here finish date may be added with Planned and Actual, to understand correctly

Planned Rev. Plan 15.07.2013 15.07.2013 18.07.2013 18.07.2013 21.07.2013

Actual Reason for delay, if any 15.07.2013 15.07.2013 15.07.2013 15.07.2013 These activities are just started on the mentioned date, it is showing here as 15.07.2013
finish this is creating descripancy in feedback regarding completed and pending activities.

21.07.2013 21.07.2013 25.07.2013 15.07.2013 27.07.2013 15.07.2013 30.07.2013 30.07.2013 01.08.2013 01.08.2013 01.08.2013 01.08.2013 01.08.2013 01.08.2013 03.08.2013 03.08.2013 05.08.2013 07.08.2013 07.08.2013 07.08.2013 10.08.2013 10.08.2013 11.08.2013 12.08.2013 05.08.2013 07.08.2013 07.08.2013 07.08.2013 10.08.2013 10.08.2013 11.08.2013 12.08.2013

Overhauling Flash Report


KAWAS OVERHAUL FOR FY 2013-14 MINOR/R&M of ST 1C SNo Milestone 22 Synchronisation C. Joints Work Progress :
SNo Section

Date :16.07.2013 15:36:13 Page : 2 of 2

Planned Rev. Plan Actual 12.08.2013 12.08.2013

Reason for delay, if any

Joints Ident. Total 0

Joints Radiography Joints failed R/T Failed Compl. Completed in Radiography Joints yet to & accepted be rectified

Remark

D. Major Surprises / Observations SNo Area E. Physical Systems Overhauling Status : SNo Description 1 Physical Systems whose OH Completed 2 Physical Systems whose OH yet to be Completed F. Constraints (if any) Areawise : SNo Area Description Total no of Activities 0 4 Major Surprises / Observations

You might also like