Professional Documents
Culture Documents
IMN:BTSE BS 240
A30808-X3247-F380-2-7631
IMN:BTSE BS 240
Issue History
Issue Number 1 Date of issue Reason for Update
01/00
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
Contents
1 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 2 2.1 2.2 2.3 2.4 2.5 2.5.1 2.5.2 2.5.3 2.5.4 2.6 2.6.1 2.6.2 2.6.3 2.6.4 2.6.4.1 2.6.4.2 2.6.4.3 2.6.5 2.6.6 2.6.7 2.6.8 2.7 2.7.1 2.7.2 2.7.3 2.7.4 2.8 2.8.1 2.8.2 2.8.3 2.8.4 2.8.5 2.8.6 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Purpose of the Manual . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Tasks of the Base Transceiver Stations . . . . . . . . . . . . . . . . . . . . . . . . . . . Feature Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Types of Base Transceiver Stations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Installation Prerequisites. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Handling of the Modules . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Installation Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Ancilliary Material . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . BS 240 Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Position in the System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Site Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Site Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Construction View of the BS 240 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Equipment Delivery. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Preliminary Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rack Unpacking . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Devices Unpacking . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rack Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . External Cabling Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Ground and Power Supply Connections 230 V AC . . . . . . . . . . . . . . . . . . Ground and Power Supply Connections -48 V DC . . . . . . . . . . . . . . . . . . . Abis-Interface - PCM Link Terminal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Abis-Interface for 120 Ohm Cable Impedance . . . . . . . . . . . . . . . . . . . . . . Abis-Interface for 75 Ohm Cable Impedance . . . . . . . . . . . . . . . . . . . . . . . Abis-Interface without OVPT. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Serial Interface - Signalling Link Terminal . . . . . . . . . . . . . . . . . . . . . . . . . Alarm Collection Terminal - external Signal Sensors . . . . . . . . . . . . . . . . . Local Maintenance Terminal (LMT) Interface . . . . . . . . . . . . . . . . . . . . . . . Antenna Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rack Completion. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Installation of Backup Batteries. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . DC-Cabling between the Racks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . CAN-Bus Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Installation of Link Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Setup of System Cabling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Configuration 1 Cell with DUAMCO 2:2 . . . . . . . . . . . . . . . . . . . . . . . . . . . Configuration 1 Cell with DUAMCO 4:2 . . . . . . . . . . . . . . . . . . . . . . . . . . . Configuration 1 Cell with DUAMCO 8:2 . . . . . . . . . . . . . . . . . . . . . . . . . . . Configuration 2 Cells with DUAMCO 2:2, . . . . . . . . . . . . . . . . . . . . . . . . . Configuration 2 Cells with DUAMCO 4:2 . . . . . . . . . . . . . . . . . . . . . . . . . . Configuration 2 Cells with DUAMCO 2:2/4:2 . . . . . . . . . . . . . . . . . . . . . . . 11 11 11 11 12 12 12 12 13 14 14 14 15 15 19 19 19 20 20 22 22 25 27 29 29 31 33 36 36 44 46 48 50 52 53 54 55 57 58 59 60 61 62
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
Configuration 3 Cells with DUAMCO 2:2 . . . . . . . . . . . . . . . . . . . . . . . . . . . 63 Configuration 3 Cells with DUAMCO 2x2:2, 4:2. . . . . . . . . . . . . . . . . . . . . . 64 Configuration: 1 Cell with FICOM. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65 Configuration: 2 Cells with FICOM (max 4,4,0) . . . . . . . . . . . . . . . . . . . . . . 66 Configuration: 2 Cells with FICOM (max. 2,6,0). . . . . . . . . . . . . . . . . . . . . . 67 Post Installation Notes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68 Abbreviations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
Illustrations
Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. 1.1 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 2.10 2.11 2.12 2.13 2.14 2.15 2.16 2.17 2.18 2.19 2.20 2.21 2.22 2.23 2.24 2.25 2.26 2.27 2.28 2.29 2.30 2.31 2.32 2.33 2.34 2.35 2.36 2.37 2.38 2.39 2.40 2.41 2.42 ESD Symbol. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Position of the BS240 within the SBS . . . . . . . . . . . . . . . . . . . . . . . . . . Site configuration BS240 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Types of BS240 racks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Configuration of a Service rack 1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Configuration of Service rack 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Space necessary for installation of BS240 . . . . . . . . . . . . . . . . . . . . . . Top of the BS240 service shelter. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Top of the BS240 base/extension shelter . . . . . . . . . . . . . . . . . . . . . . . Locations of connection points for external cables . . . . . . . . . . . . . . . . PE-plate at EMI-Panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Ground and AC mains connections of the BS240 (example) . . . . . . . . Pinning of 230 V AC terminal block (Service Rack). . . . . . . . . . . . . . . . Terminal block for -48 V DC input of MSU. . . . . . . . . . . . . . . . . . . . . . . Ground-and power supply connections . . . . . . . . . . . . . . . . . . . . . . . . . OVPT with terminal block (120 Ohm) . . . . . . . . . . . . . . . . . . . . . . . . . . Pinning Abis interface PCM0 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pinning Abis interface PCM1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OVPT with SMA connectors (75 Ohm) . . . . . . . . . . . . . . . . . . . . . . . . . Preparation of 75 Ohm coaxial cable. . . . . . . . . . . . . . . . . . . . . . . . . . . Terminal numbering of the ACTA . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Connector arrangement at ACTC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Location of ACTC. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Cell numbering (top view from the antenna pole) . . . . . . . . . . . . . . . . . Max. dimensions of antenna connectors . . . . . . . . . . . . . . . . . . . . . . . . Routing of antenna jumper cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Cable routing inside the EMC-protected area . . . . . . . . . . . . . . . . . . . . Top cover . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Battery tray during installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Connection of backup batteries . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Overview of Battery Cabling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Routing of DC cabling between the racks . . . . . . . . . . . . . . . . . . . . . . . CAN-Bus cable connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Slot numbering of the BS241 Shelters. . . . . . . . . . . . . . . . . . . . . . . . . . System Cabling DUAMCO 2:2, 1 cell . . . . . . . . . . . . . . . . . . . . . . . . . . System Cabling DUAMCO 4:2, 1 cell . . . . . . . . . . . . . . . . . . . . . . . . . . System Cabling DUAMCO 8:2, 1 cell . . . . . . . . . . . . . . . . . . . . . . . . . . System Cabling DUAMCO 2:2, 2 cell . . . . . . . . . . . . . . . . . . . . . . . . . . System Cabling DUAMCO 4:2, 2 cells. . . . . . . . . . . . . . . . . . . . . . . . . . System Cabling DUAMCO 2:2/4:2, 2 cells. . . . . . . . . . . . . . . . . . . . . . . System Cabling DUAMCO 2:2, 3 cells. . . . . . . . . . . . . . . . . . . . . . . . . . System Cabling DUAMCO 2x2:2, 4:2, 3 cells . . . . . . . . . . . . . . . . . . . . System Cabling FICOM , 1 cell . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12 14 15 16 17 18 21 22 23 24 25 26 27 28 28 29 30 30 31 32 37 41 42 46 47 47 48 49 50 50 51 52 53 56 57 58 59 60 61 62 63 64 65
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
Tables
Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 2.10 2.11 2.12 2.13 2.14 2.15 2.16 2.17 2.18 2.19 2.20 2.21 2.22 2.23 Pinning of Abis interface PCM0, 75 Ohm . . . . . . . . . . . . . . . . . . . . . . . Pinning of Abis interface PCM1, 75 Ohm . . . . . . . . . . . . . . . . . . . . . . . Pinning of the PCM0 interface without OVPT (SubD 25 connector) . . . Pinning of the PCM1 interface without OVPT (SubD 25 connector) . . . Pinning of the monitoring interfaces PCM0 . . . . . . . . . . . . . . . . . . . . . . Pinning of the monitoring interfaces PCM1 . . . . . . . . . . . . . . . . . . . . . . Pinning of the Serial Interface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pinning ACTA Connector X5 Site Inputs . . . . . . . . . . . . . . . . . . . . . . . . Pinning ACTA Connector X6 Site Inputs . . . . . . . . . . . . . . . . . . . . . . . . Pinning ACTA Connector X7 Site Inputs . . . . . . . . . . . . . . . . . . . . . . . . Pinning ACTA Connector X8 Site Inputs . . . . . . . . . . . . . . . . . . . . . . . . Pinning ACTA Connector X4 Site Inputs . . . . . . . . . . . . . . . . . . . . . . . . Pinning ACTA Connector X3 Site Inputs . . . . . . . . . . . . . . . . . . . . . . . . Pinning ACTA Connector X2 Site Inputs . . . . . . . . . . . . . . . . . . . . . . . . Pinning ACTA Connector X1 Site Inputs . . . . . . . . . . . . . . . . . . . . . . . . Environmental Alarms at ACTA and ACTC . . . . . . . . . . . . . . . . . . . . . . Pinning of the LMT interface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pinning of the LMT RJ45 interface. . . . . . . . . . . . . . . . . . . . . . . . . . . . . List of battery cables between the racks . . . . . . . . . . . . . . . . . . . . . . . . List of tempresistor cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . List of DC cable connections between the racks . . . . . . . . . . . . . . . . . . Example for CAN-Bus cabeling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Functionality of system cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31 32 33 34 35 35 36 37 38 38 39 39 40 40 41 42 44 45 52 52 53 54 55
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
10
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
1 Introduction
!
The CE declaration of conformity for the product will be fulfilled if the setup and cabling is undertaken in accordance with the specification in the manual and the documentation listed there, such as mounting instructions, cable lists etc.Where necessary, account should be taken of project-specific documentation. Deviations from the specifications or independent changes during setup, such as use of cable types with lower screening values, for example, can lead to the CE requirements being violatad. In such cases the CE declaration of conformity is invalidated and the responsibility passes to the person who has caused the deviations.
1.1
1.2
1.3
Feature Overview
Rack extension up to 24 carriers per site (max. 12 carriers per cell) and up to 12 cells per site Easy rack extension with up to 2 extension racks without interruption Duplex Combiners, Filter Combiners Full-rate and half-rate channels are supported Integrated Abis cross connect LMT-operation with full O&M functionality at a transmission rate of 64 kBit Integrated NTPM and/or microwave-equipment, battery backup in service
A30808-X3247-F380-1-7631
11
IMN:BTSE BS 240
1.4
1.5
Installation Prerequisites
It is absolute required that the installer pays attention to the valid EMC instructions. All other equipment on site must be CE designated and must provide interfaces for connecting of external cables conformable to EMC instructions.
1.6
Fig. 1.1
ESD Symbol
These are sensitive to static discharge. Notice: Avoid handling the modules in a high-static environment When handling the modules, do not touch connector contacts An earthed high-impedance wrist strap must be worn when handling modules. Use the socket at the racks for wrist strap connection. The modules must be transported in appropriate packing
1.7
Installation Tools
The correct installation is carried out with the aid of the following tools: Standard toolkit for BSS-installation
12
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
Spirit-level Plumb bob Torque spanner for SMA connectors (35 N/cm) Torque spanner for SMC connectors (100 N/cm) Screw driver for torx screws M2.5, M3, M4, M5, M6 (length 200 mm) Long screw driver for torx screws M6 (length 400 mm) Engineers wrenches for M12, M42 (SW 19, 65 mm) Ratchet with insets for nuts M4, M5, M6, M8, M10 (SW 7, 8, 10, 13, 17 mm) Screw drivers for security screw (internal torx screws with pin) M3 and M5 Screw drivers for hexagon socket screw or hexagon socket screw key SW 4 mm Screw driver for slotted screw M3, M4, M5 Screw driver for pozi drive screws M3,M4, M5 A pair of scissors Stripping knife for RF cables
For installation of power supply, transmission equipment, antennas, cableways and other infrastructure equipment, additional tools could be necessary.
1.8
Ancilliary Material
The following ancilliary materials are needed : plumb line colophony adhesive tape (yellow/green, green, blue, red, orange, white) cable fasteners wire end sleeves for 16 mm copper wires cable lugs M8 wire end sleeves
A30808-X3247-F380-1-7631
13
IMN:BTSE BS 240
2 BS 240 Installation
2.1 Position in the System
Like all other base stations the BS240 interconnects the MS via the Um interface with the trunk network via the Abis interface.
Um interface
TRAU A interface
MSC
SBS
Position of the BS240 within the SBS
Fig. 2.1
2.2
Site Requirements
Prior to the commencement of installation, the construction of the room in which the base transceiver station is to be housed must be complete and the room in good condition and dry heaters, if necessary, should be put up in the room. The BS240 is intended to be installed in a restricted access area. Doors and windows must already have been installed and must be lockable. Openings in wall or ceiling of oor - if required - must be complete. The oor coverings must have been laid. Room lighting and wall sockets must have been installed. Heating or air-conditioning systems should be ready for operation. Walls and ceilings should have been painted.The room must be clean. A power supply unit with 1300 W/3,5 A must be installed. A minimum oor space of 1,70 m x 1,10 m should be provided (later extension not possible). The oor load of the construction room must be not less than 7500 N/m2. To prevent subsequent accumulation of dust and dirt, the parts and equipment units to be installed must be unpacked outside the room (if possible). After that it is advantageous to install the BTS, after all other installation works to create the required infrastructure (power supply, antenna cabling, PCM line...) are complete.
14
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
2.3
Site Conguration
Operation of the BS 240 requires additional equipment on site: TX/RX antennas microwave outdoor unit *
external alarms**
ground connection
*dependent on type of network integration **optional
Fig. 2.2
2.4
A30808-X3247-F380-1-7631
15
IMN:BTSE BS 240
SIEMENS
LMT ETHERNET
SIEMENS
LMT ETHERNET
SIEMENS
LMT ETHERNET
DC-PANEL ACT-C
DC-PANEL ACT-C
DC-PANEL ACT-C
CU CU #2 #3
CU #6
CU #7
CU CU #2 #3
CU #6
CU #7
LE 0 LE 1 LE 2 LE 3 LE 4 LE 5
MUCO #0
MUCO #0
MUCO #1
CU CU #0 #1
CU #4
CU #5
CU CU #0 #1
MUCO #1
CU #4
CU #5
Base Rack
Extension Rack
Service Rack
Fig. 2.3
The first rack is called Base rack and contains the following modules: Generic Modules: Core Basis (COBA; essential components are the Base Core Controller, Advanced Clock Generation and the Carrier Unit Interfaces Core Satellite (COSA; can handle 2 PCM lines and up to 8 Carrier units) Alarm Collection Terminal; collect all alarms for those units having no access to the CAN-Bus and pass them via CAN-Bus interface to COBA) Overvoltage Protection and Tracer (OVPT; protect the PMC30 ports of core boards from overvoltage and provide a monitoring interface for connected Abis-lines) Carrier related Modules: Carrier Unit (CU; consists of a receiving and transmitting part with syntheziser and power amplifier, a signal processing unit as well as a power supply unit) Antenna System Modules: Antenna Combiners (ACOM; can be Duplexer Amplifier Multicoupler-DUAMCO or Filter Combiner-FICOM) Antenna Multicoupler (MUCO; called DI-Amplifier Multicoupler, DIAMCO)
16
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
The types and numbers of modules are subject to modification, it depends on the cell configuration and the type of antenna combination. For the Base rack to function a Service rack is required which will be installed close beside to the Base rack. If only one Service rack islocated on site, it contains all infrastructure equipment: AC/DC Converter (ACDC; converts the mains voltage of 230 V AC into the -48 V DC supply voltage) Link Equipment (LE; can be NTPM if terrestrial line is used for connection to BSC or microwave) Backup Batteries (guarantees continuous operation for a certain time in case of mains breakdown of AC/DC failure. The number of Service racks depends on the number of installed carriers on site, the volume of required link equipment and the expected backup time of batteries. The following figures shows the most interesting configurations of the Service rack.
SIEMENS
LMT ETHERNET
DC-PANEL ACT-C
AC/AC/AC/AC/AC/AC/AC/ DC DC DC DC DC DC DC 00 01 02 03 04 05 06 AC + DC Distribution
AC/AC/AC/AC/AC/AC/AC/ DC DC DC DC DC DC DC 00 01 02 03 04 05 06 AC + DC Distribution
AC/AC/AC/AC/AC/AC/AC/ DC DC DC DC DC DC DC 00 01 02 03 04 05 06 AC + DC Distribution
AC/AC/AC/AC/AC/AC/AC/ DC DC DC DC DC DC DC 00 01 02 03 04 05 06 AC + DC Distribution
LE 0 LE 1 LE 2 LE 3 LE 4 LE 5
LE 0 LE 1 LE 2 LE 3 LE 4 LE 5
LE 0 LE 1 LE 2 LE 3 LE 4 LE 5 LE 6 LE 7 LE 8 LE 9 LE 10 LE 11
Fig. 2.4
A30808-X3247-F380-1-7631
17
IMN:BTSE BS 240
SIEMENS
LMT ETHERNET
DC-PANEL ACT-C
LE 0 LE 1 LE 2 LE 3 LE 4 LE 5
LE 0 LE 1 LE 2 LE 3 LE 4 LE 5 LE 6 LE 7 LE 8 LE 9 LE 10 LE 11
LE 0 LE 1 LE 2 LE 3 LE 4 LE 5 LE 0 LE 1 LE 2 LE 3 LE 4 LE 5 LE 6 LE 7 LE 8 LE 9 LE 10 LE 11
Fig. 2.5
Configuration of Service rack 2 If more than 8 Carrier Units are installed or in case of later extension of a BS240 with 8 Carrier Units, Extension racks will be used. The equipment in an Extension rack is equal to those of the Base rack (without core modules). Fig.2.3 shows a fully equipped Extension rack. Note: All unequipped slots must be closed with cover plates, so that the air flow inside the rack will not be affected.
18
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
2.5
Equipment Delivery
The BS240 racks are shipped vertically in wooden crates.The crates dimensions are 1800 mm x 800 mm x 650 mm (HxWxD). Depending on the pre-installed modules inside the racks, the crate can weigh up to approx. 150 kg. Depending on customers requirements, the Service racks can be delivered without backup batteries (weight aspects). In this case an additional crate contains the batteries. All crates have the following information printed on them for identification of delivery: trade mark customer order number serial number of rack or other supplied equipment destination gross and net weight overall dimensions (cm) symbol or inprint to identify the "Top" and the "Bottom" For transportation of the crates from the unloading area into the construction room use handling aids (for example: fork-lift truck, goods elevator), a second person is needed for help.
2.5.1
Preliminary Checks
Check that the crates are not damaged. In case of evident damage due to transport, unpack the equipment in presence of an insurance company representative and promptly claim any damage and inform the shipper for specifying the damage. Check whether the package is actually adressed to the site and complete. Open it and take the contents out carefully. After having removed all contents from the packing material, check for deformation to the devices, of torn or unwelded wiring, of oxidized connectors, as well as deformed front sides of the units, loose screws, damage to paint work etc.
2.5.2
Rack Unpacking
During the unpacking steps great care must be taken to ensure that the rack is not scratched or damaged in any way. Proceed as follows: Cut the straps and remove the top of the crate. Take out the proles protecting the rack edges. Remove the protection to the head and to the base of the rack. Take out the rack from the crate. Use the straps around the rack. Lay down the rack and open the tubular PE shrink-wrap protecting the rack and take it out. Lift the rack in vertical position.
A30808-X3247-F380-1-7631
19
IMN:BTSE BS 240
2.5.3
Devices Unpacking
Proceed as follows: Open the PVC wrap protecting the carton and withdraw it. Remove the dehydrating material bag from the box. Cut with a suitable knife the adhesive tape sealing the box. Take the device out. Open the PVC wrap protecting the device/board and withdraw it. The packing material should be preserved for possible future re-packing. For this purpose, reverse the procedure described above, taking into account the warnings specified for the packing. If the packing material is supplied by the customer, special care should be taken to avoid damage during the transport and storage of the devices.
2.5.4
Rack Installation
Prior to the commencement of rack installation, consult the site documentation to locate the installation point of the BS240, the PCM30 network termination power supply unit (if -48V will be provided from external equipment) and the access of the antenna cables into the construction room. After that check the proper installation of the earthing bar and the necessary cable runways. Mark the rack-outlines on the oor according to the site conguration oor. (If the construction room is equipped with a raised oor and cabling access is required from below, mark the position of the required opening.) Cut out the opening, making sure that the rack and all nearby equipment are dust protected ! Move the rack to the marked installation point. Check the correct rack position, using the spirit-level. In case, the position is incorrect, equalize differences in the oor height by adjusting the screwed adjuster feeds. Fix the rack to wall to prevent fallover.
20
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
600 mm 1200 mm
450 mm
1200 mm
1600 mm min. dimensions for double rack solution Fig. 2.6 Space necessary for installation of BS240
450 mm
A30808-X3247-F380-1-7631
21
IMN:BTSE BS 240
2.6
2.6.1
CAN-bus interfaces
Fig. 2.7
22
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
PCM 0
PCM 1
LPA
OVPT
MSU
ACK
PE-plate
Fig. 2.8
Some additional hints for the installation of external cabling: The rst cable that has to be installed is the ground cable between the main ground stud on top of the rack and the nearest ground bar on site. The second installation step is to connect the ground stud of the different racks in series. After that all other cables like AC mains, RF cabling or alarm wires can be installed. The screen of the RF jumpers has to be grounded before entering the BTSE at the EMI panel. If cables are fed through coaxial cable access located at the top of the rack at the front,the screen has to be grounded like all other coaxial cables. The following figure shows the location of the external interfaces of a 3-rack solution of the BS240.
A30808-X3247-F380-1-7631
23
IMN:BTSE BS 240
serial interface cable external alarms / commands Abis lines (OVPT PCM0, PCM1) antenna cables 3 x 230 V AC mains ground cable microwave
SIEMENS
LMT ETHERNET
-48 V DC*
DC-PANEL ACT-C
LE 0 LE 1 LE 2 LE 3 LE 4 LE 5
MUCO #0
MUCO #1
MUCO #0
CU CU #2 #3
CU #6
CU #7
CU CU #2 #3
MUCO #1
CU #6
CU #7
CU CU #0 #1
CU #4
CU #5
CU CU #0 #1
CU #4
CU #5
*) only in case of external power supply Service rack Base rack Extension rack
Fig. 2.9
24
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
2.6.2
Fig. 2.10
PE-plate at EMI-Panel
A30808-X3247-F380-1-7631
25
IMN:BTSE BS 240
3 x 230 V AC mains
Fig. 2.11
Ground and AC mains connections of the BS240 (example) A 5pole WAGO terminal block, located in the top of Service rack 1, is the connection point for the AC mains cable. The BS240 will be powered by 3 x 230 V, 50 Hz, 20 A per phase. An easily accessible disconnect device is incorporated into the AC mains supply wiring. To isolate the mains supply 3 40A circuit breakers are connected (one per phase), and are installed in the AC distribution box close to the BS240. The disconnect device shall simultaneously interrupt all phase conductors. The figure above shows the recommended cabling for the power supply and ground connections. The recommended cable types guarantees the proper function of the BS240, equipped with up to 24 carriers. This warning must appear in the original German text: Vor Anschlu des 3 x 230 V Einspeisungskabels ist sicherzustellen, da das Kabel spannungsfrei ist. Die Hauptsicherungen sind zu unterbrechen. Es sind geeignete Manahmen gegen unbefugtes Einschalten der Netzspannung zu treffen. To connect the BS240 with the AC mains connection point proceed with the following steps: Unscrew the bolts in the top extrusions for opening the roof. Remove the roof sections carefully, avoid damages to the paint work. Refer to the site documentation for the required information about type and location of the AC distribution. Check the actual distance between WAGO terminal and AC distribution. Remove the insulation of the cable and cut back the wire insulation at the end; that is to be connected to the terminal block. The wires must be equipped with wire end sleeves. Fix the cables at the strain relief by the clamp. Insert the wires into the WAGO terminals and screw them down. Check that all wires are in xed position. Lead the main cable to the AC distribution.
26
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
PE L3 L2
L1
Fig. 2.12
2.6.3
A30808-X3247-F380-1-7631
27
IMN:BTSE BS 240
-48 V +0 V
Fig. 2.13
ground wires
backup batteries
50 A fuses
16 A fuses
BS240
50 mm
ground bar
Fig. 2.14
Ground-and power supply connections For installation of the ground connection proceed as described in section 2.6.2 of this manual.
28
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
2.6.4
2.6.4.1
Fig. 2.15
Connect the Abis-interface with twisted pair cable to the PCM link terminal as follows: Cut the cable to the required length and cut back the outer insulation (approx.19 cm). Remove the wire insulation (8 mm). Wrap the exposed cable screen, which will be xed at the stress relieving. Fix the prepared cable close to the strain relieving by straps. Insert the wires into the terminals of the OVPT. Insert the additional wire (shielding potential) into one of the ground terminals (e.g. no. 24).
A30808-X3247-F380-1-7631
29
IMN:BTSE BS 240
Lead the additional wire and the uplink and downlink wires on the shortest route (that means without sleeves) between the stress relieving and the screw terminals. All unconnected PCM lines (4 wires per line) must be connected to one of the ground terminals.
It is advantageous to protect the short part of the cable between stress relieving and terminal block with a shrink tube or adhesive tape. EXT SYNC B EXT SYNC A
Down Link = RX
B A 1 3 5
B 7
B 19
9 11 13 15 17
21 23 25 27
8 10 12 14 16 18
20
22 24 26 28
B PCM 4
PCM 3
PCM 2
PCM 1 Up Link = TX
Fig. 2.16
Down Link = RX
B A 1 3 5
B 7
B 19
A 21 23 25 27
9 11 13 15 17
8 10 12 14 16 18
20
22 24 26 28
B PCM 8
PCM 7
PCM 6
PCM 5 Up Link = TX
Fig. 2.17
30
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
2.6.4.2
monitoring interface
6 5 4 3 2 1 6 5 4 3 2 1 6 5 4 3 2 1
connector 3
connector 2
connector 1
PCM lines
Fig. 2.18
For Abis cabling with 75 Ohm impedance use coaxial cable e.g. S-09YS(ST)CY 8x2x0.6/1.2.The coaxial cables will be prepared as follows: Cut back the outer insulation(length approx. 120 mm). Unbraid the main cable screen. Twist and tinn the screen wires and the additional wire. Insulate the screening with insulation sleeve. Fix a SMA-female connector for each PCM-up and down line at the end to be connected to the OVPT. Connect the prepared cable to the matching connectors. Use a torque spanner for SMA connector (35 N/cm). Fix the screening at the strain relief of OVPTCOAX. signal PCM1-ULA PCM1-DLA PCM2-ULA PCM2-DLA Tab. 2.1 1 2 3 4 coax connector signal PCM3-DLA PCM4-ULA PCM4-DLA EXTSYNCA 6 7 8 9 coax connector
A30808-X3247-F380-1-7631
31
IMN:BTSE BS 240
signal ---
coax connector
coax connector
coax connector
approx. 120 mm
Fig. 2.19
32
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
2.6.4.3
A30808-X3247-F380-1-7631
33
IMN:BTSE BS 240
Signal name PCM 5 - ULA PCM 5- ULB GND/G PCM 5 - DLA PCM 5 - DLB GND/G PCM 6 - ULA PCM 6 - ULB GND/G PCM 6 - DLA PCM 6 - DLB GND/G PCM 7 - ULA PCM 7 - ULB GND/G PCM 7 - DLA PCM 7 - DLB GND/G PCM 8 - ULA PCM 8 - ULB GND/G PCM 8 - DLA PCM 8 - DLB GND/G ----GND/G GND/G main cable shield
Function PCM Line 5 Up Link A PCM Line 5 Up Link B shield pair 1 PCM Line 5 Down Link A PCM Line 5Down Link B shield pair 2 PCM Line 6 Up Link A PCM Line 6 Up Link B shield pair 3 PCM Line 6 Down Link A PCM Line 6 Down Link B shield pair 4 PCM Line 7 Up Link A PCM Line 7 Up Link B shield pair 5 PCM Line 7 Down Link A PCM Line 7 Down Link B shield pair 6 PCM Line 8 Up Link A PCM Line 8 Up Link B shield pair 7 PCM Line 8 Down Link A PCM Line 8 Down Link B shield pair 8
The Overvoltage Protection carries 3 6pin DIN41616 test connectors for monitoring the PCM lines. The following tables show the pinning of the tracing interfaces. The pin arrangement is shown in Fig.2.18.
34
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
Signal name PCM 1 - ULA GND/G PCM 1 - DLA PCM 1 - DLB PCM 2 - ULA GND/G PCM 2 - DLA PCM 2 - DLB PCM 3 - ULA GND/G PCM 3 - DLA PCM 3 - DLB PCM 4 - ULA GND/G PCM 4- DLA PCM 4- DLB EXTSYNCA EXTSYNCB
Function PCM Line 1 Up Link A shield pair 1 PCM Line 1 Down Link A PCM Line 1 Down Link B PCM Line 2 Up Link A shield pair 2 PCM Line 2 Down Link A PCM Line 2 Down Link B PCM Line 3 Up Link A shield pair 3 PCM Line 3 Down Link A PCM Line 3 Down Link B PCM Line 4 Up Link A shield pair 4 PCM Line 4 Down Link A PCM Line 4 Down Link B
Signal name PCM 5 - ULA GND/G PCM 5 - DLA PCM 5 - DLB PCM 6 - ULA GND/G PCM 6 - DLA PCM 6 - DLB PCM 7 - ULA GND/G PCM 7 - DLA PCM 7 - DLB
Function PCM Line 1 Up Link A shield pair 1 PCM Line 1 Down Link A PCM Line 1 Down Link B PCM Line 2 Up Link A shield pair 2 PCM Line 2 Down Link A PCM Line 2 Down Link B PCM Line 3 Up Link A shield pair 3 PCM Line 3 Down Link A PCM Line 3 Down Link B
A30808-X3247-F380-1-7631
35
IMN:BTSE BS 240
Signal name PCM 8 - ULA GND/G PCM 8 - DLA PCM 4 - DLB -----
Function PCM Line 4 Up Link A shield pair 4 PCM Line 4 Down Link A PCM Line 4 Down Link B
2.6.5
2.6.6
36
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
The WAGO terminals are labelled X1 ... X10, the terminal blocks X1...X8 are used for connection of site inputs. The following tables give information on the pinning of the terminals. After all wiring works are finished, the ACTA must be screwed at EMI panel in its original position.
X5 X1 X2 X3 X4 X9 X10 X6 X7 X8
Fig. 2.20
Pin no. 1 2 3 4 5 6 7 8 9 10 Tab. 2.8 AL0P AL0M (GND) AL1P AL1M (GND) AL2P AL2M (GND) AL3P AL3M (GND) AL4P AL4M (GND)
Signal name
A30808-X3247-F380-1-7631
37
IMN:BTSE BS 240
Signal name
Pin no. 1 2 3 4 5 6 7 8 9 10 11 12 Tab. 2.9 AL6P AL6M (GND) AL7P AL7M (GND) AL8P AL8M (GND) AL9P AL9M (GND) AL10P AL10M AL11P AL11M
Signal name
Pin no. 1 2 3 4 5 6 7 8 9 10 11 12 Tab. 2.10 AL12P AL12M (GND) AL13P AL13M (GND) AL14P AL14M (GND) AL15P AL15M (GND) AL16P AL16M (GND) AL17P AL17M (GND)
Signal name
38
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
Pin no. 1 2 3 4 5 6 7 8 9 10 11 12 Tab. 2.11 AL18P AL18M (GND) AL19P AL19M (GND) AL20P AL20M (GND) AL21P AL21M (GND) AL22P AL22M (GND) AL23P AL23M (GND)
Signal name
Pin no. 1 2 3 4 5 6 7 8 9 10 11 12 Tab. 2.12 AL24P AL24M (GND) AL25P AL25M (GND) AL26P AL26M (GND) AL27P AL27M (GND) AL28P AL28M (GND) AL29P AL29M (GND)
Signal name
A30808-X3247-F380-1-7631
39
IMN:BTSE BS 240
Pin no. 1 2 3 4 5 6 7 8 9 10 11 12 Tab. 2.13 AL30P AL30M (GND) AL31P AL31M (GND) AL32P AL32M (GND) AL33P AL33M (GND) AL34P AL34M (GND) AL35P AL35M (GND)
Signal name
Pin no. 1 2 3 4 5 6 7 8 9 10 11 12 Tab. 2.14 AL36P AL36M (GND) AL37P AL37M (GND) AL38P AL38M (GND) AL39P AL39M (GND) AL40P AL40M (GND) AL41P AL41M (GND)
Signal name
40
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
Pin no. 1 2 3 4 5 6 7 8 9 10 11 12 Tab. 2.15 AL42P AL42M (GND) AL43P AL43M (GND) AL44P AL44M (GND) AL45P AL45M (GND) AL46P AL46M (GND) AL47P AL47M (GND)
Signal name
Additionalnally to the site inputs at ACTA, there exists the ACTC board, used as a connection board to support single connectors for the internal alarms (FAN, heatexchanger, temperatur sensor, sheler in service...) and the DC supply for the FANs, heatexchangers, microwave equipment, smoke sensor and ACT. The ACTC is located in the DC panel of each shelter (see Fig.2.22).
HX0
HX1 mWave 2
mWave 1
mWave 3
HX2
mWave 4
mWave 5
mWave 6
meaning of abbreviations: HX0...2: heat exchanger 0...2 mWave 0...9: microwave 0...9 SMOKE: smoke sensor SIS: shelter in service BB0-2: battery fuse 0...2 SMOKE RDO SIS 24 ALARM_IN 1
mWave 7
mWave 8
mWave 9
BB0
BB1
BB2
DC panel
Fig. 2.21 Connector arrangement at ACTC
A30808-X3247-F380-1-7631
41
IMN:BTSE BS 240
Fig. 2.22
Location of ACTC
The following table gives information on the connecting of enviromental alarms at ACTA and ACTC. ENVA Alarms at WAGO- block PIN 11, 12 9, 10 7, 8 Indication at LMT Alarm Alarm-Board Connector PIN
0 1 2 3 4 5 6 7 8 9 10 11
5, 6
Tab. 2.16
42
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
ENVA
Indication at LMT
Alarm
Alarm-Board
Connector
PIN
AL-3 AL-4 AL-5 AL-6 AL-7 AL-8 AL-9 AL-10 AL-11 AL-12 AL-13 AL-14 AL-15 AL-16 AL-17 AL-18 AL-19 AL-20 AL-21 AL-22 AL-23 AL-24 AL-25 AL-26 AL-27 AL-28 AL-29 AL-30 AL-31 AL-32 AL-33 AL-34 AL-35
ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA
X5 X5 X5 X6 X6 X6 X6 X6 X6 X7 X7 X7 X7 X7 X7 X8 X8 X8 X8 X8 X8 X4 X4 X4 X4 X4 X4 X3 X3 X3 X3 X3 X3
7,8 9,10 11,12 1,2 3,4 5,6 7,8 9,10 11,12 1,2 3,4 5,6 7,8 9,10 11,12 1,2 3,4 5,6 7,8 9,10 11,12 1,2 3,4 5,6 7,8 9,10 11,12 1,2 3,4 5,6 7,8 9,10 11,12
A30808-X3247-F380-1-7631
43
IMN:BTSE BS 240
ENVA
Indication at LMT
Alarm
Alarm-Board
Connector
PIN
45 46 47 48 49 50 51 52 53 54 55 56 Note:
AL-36 AL-37 AL-38 AL-39 AL-40 AL-41 AL-42 AL-43 AL-44 AL-45 AL-46 AL-47
ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA ACTA
X2 X2 X2 X2 X2 X2 X1 X1 X1 X1 X1 X1
1,2 3,4 5,6 7,8 9,10 11,12 1,2 3,4 5,6 7,8 9,10 11,12
1.The Indication at LMT has to be defined by Customer. It will be recommended to use the proposed Indication. 2.Connector X9 and X10 are not used Environmental Alarms at ACTA and ACTC
Tab. 2.16
2.6.7
44
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
A30808-X3247-F380-1-7631
45
IMN:BTSE BS 240
2.6.8
Antenna Connections
The BTSE has to be connected to the transmit and receive antennas. The antenna configuration and the required cabling are dependent on the site and the type of combining. For detailed information refer to the site-specific documentation or use the corresponding customer documents. For installation and service purposes it is useful to know, which hardware is connected to which cell. The numbering, seen from the top of the antenna pole, starts at an azimuth angle of 0 (north) and rotates clockwise. The first existing cell whose beam centre line lies at 0 or more is defined as cell 0 or sector 0. The next one following in the same direction cell is cell 1 etc. In case of omni cell the cell no. is 0. 0
sector 2
sector angle
directional antenna
N sector 1
sector 0
Fig. 2.23
Jumper cable with a max. diameter 1/2 have to be used because the thick cables from the antenna are not able to enter the racks. With regard to overvoltage protection it is recommended to ground the outer conductor of antenna feeder cables where they are connected with the jumper cables outside the BS240. The antenna cables must be routed through the EMI panel forward to the 7/16 front connectors of DUAMCO/FICOM and to N-type male connector of DIAMCO.
Note that being able to close the doors means that the depth of the right angle connector is not allowed to exeed 45 mm.
46
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
max. 45 mm
SW 32
Fig. 2.24
Connect the antenna cables to the combining equipment as follows: Unscrew the front parts of the cable feeding module and take them out. Remove the packing material. Route the antenna jumpers to the rack, which has to be connected. Feed the jumpers through the cable feeding module forward to the front connectors of antenna combiners. Fix the jumpers at the connectors TX/RX of combiners. Bend the jumpers into the correct position for easy closing of cable feeding module. Put the packing material back into the removed front parts of feeding module and screw them in their original position.
Fig. 2.25
A30808-X3247-F380-1-7631
47
IMN:BTSE BS 240
2.7
Rack Completion
The BS240 racks are shipped including equipment components, pre-installed by the manufacturer in accordance with customer configuration: sub-rack, which holds several boards and modules DC panel backplanes (multilayer PC-boards, which are mounted at the rear side of the subrack) the rack internal cabling heaters and fan unit core modules carrier related modules (Carrier Units, Antenna Combiners) AC/DC converters semi-rigid cables for setup of the system cabling The following items are foreseen for installation after setup of the racks on site: backup batteries cabling between the racks (battery cabling, DC-cabling, CAN-BUS) link equipment For cable routing from one rack into another one (eg. DC power supply, CAN-Bus, battery cables) two ways can be used. Without leaving the EMC-protected area, a cabling channel is provided. For this reason holes that are covered by plates for single racks and the endracks of a row are provided at both sides of a rack. These coverplates have to be removed by unscrewing the security screws M3. Four plug-in seal strips per rack have to be mounted at the cutout. Racks stand side by side and must be screwed together to one common unit with one nut and screw M8x20.
Fig. 2.26
48
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
For connections outside the EMC-protected area (e.g. CAN-bus, antenna jumpers, site inputs...), the routing of these cables directly below the roof section is possible. Dependend on the number and diameter of the cables, pieces of the top cover can be removed in easy manner.
removable pieces
Fig. 2.27
Top cover
A30808-X3247-F380-1-7631
49
IMN:BTSE BS 240
2.7.1
2
4
Fig. 2.28
Fig. 2.29
50
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
Install and connect the backup batteries in accordance with Fig.2.28 and Fig.2.29 in steps as follows: Setup the 4 batteries on the battery tray. Close and tighten both xing straps (1). Setup the gas-outlet kit (3). Connect the batteries by pre-fabricated short wire bridges (2). Connect the battery cables coming from AC/DC converters(4).
Service 2/3
top cover air vent
Service 2/2
air vent
Service2/1
air vent
Service1
air vent
112/2
tempresistor cable
110/2 111/2
frame AC/DC 1
112/4
112/3
110/3 111/3
110/1 111/1
T1 T0
t
frame AC/DC 2
112/1
110/4 111/4
T1
T0
t
BAT4
t
BAT3
t
BAT2
t
BAT1
A30808-X3247-F380-1-7631
51
IMN:BTSE BS 240
battery cable no. 110/1 111/1 110/2 111/2 110/3 111/3 110/4 111/4 Tab. 2.19
to S1/BAT1/- (-48V) S1/BAT1/+ (+0V) S2/1 BAT2 -2a S2/1 BAT2 -1a S2/2 BAT3 -2a S2/2 BAT3 -1a S2/3 BAT4 -2a S2/3 BAT4 -1a
from S1/BAT1 (+) S2/1 BAT2 (+) S2/2 BAT3 (+) S2/3 BAT4 (+)
2.7.2
Service Rack 1
Base Rack
Extension Rack 1
Extension Rack 2
DC-Panel 34
DC-Panel
35
DC-Panel
33
36
Fig. 2.31
52
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
cable no. 33 34 35 36
Tab. 2.21
2.7.3
CAN-Bus Connections
The CAN-Bus will be routed in loop configuration through the racks to collect external and internal alarms and lead them to ACT of the Base rack. The CAN-Bus must be terminated at the end with the terminating resistor S30861-K2047-K (component of the base rack). The following figure gives information on routing of the Bus links. top view
CAN OUT
- 48 V SERIAL IF
CAN TEST
231
230
Service 2/2
Service 2/1
Service 1
Fig. 2.32
A30808-X3247-F380-1-7631
53
IMN:BTSE BS 240
from CAN BUS OUT Base Service 1 Extension 1 Service 2/1 Extension 2
2.7.4
54
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
2.8
For setup of the sytem cabling connections on site in case of installation or later extension, the cables will be shipped in a box, to avoid twisting and damage. Before starting the connection procedure, refer to the site documentation and determine the types and number of cables. The list of variant numbers (content of the site specific documentation) is needed for the correct setup of the cabling between the modules. Pay attention to the minimum bending radius of 10 mm, a bending tool should be used. The following sections are intended to give an overview about the most interesting configurations with different combining modules.
A30808-X3247-F380-1-7631
55
IMN:BTSE BS 240
MUCO # 1
CU #3
MUCO # 0
CU #2
CU #6
CU
#7
MUCO # 1
CU #3
MUCO # 0
CU #2
CU #6
CU
#7
CU #0
CU #1
CORE # 0 CORE # 1 CORE # 2 CORE # 3
CU #4
CU #5
CU #0
CU #1
CU #4
CU #5
Base Shelter
Extension Shelter
Fig. 2.33
56
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
2.8.1
DUAMCO 0 2:2 Module 0
RX0 RX1
Module 0
RX
CU 0
TX0
SLOT 0
Module 1
RX RXdiv
CU 1
TX0
Module 0
TX0
SLOT 1
Module 1
108 RX RXdiv
CU 3
TX0
110
RXdiv
Module 0
RX
TX0
SLOT 2
Module 1
112
RX RXdiv
CU 7
TX0
114
RXdiv
Module 0
RX
CU 4
TX0
SLOT 3
Module 1
116
RX RXdiv
CU 5
TX0
Fig. 2.34
Module 1
RX0 RX1
008
Carrier 8
115
SLOT 3
Carrier 7
113
007
DUAMCO 3 2:2
Module 1
RX0 RX1
006
Carrier 6
111
SLOT 2
Carrier 5
109
CU 6
005
DUAMCO 2 2:2
Module 1
RX0 RX1
004
Carrier 4
107
SLOT 1
Carrier 3
CU 2
003
DUAMCO 1 2:2
Module 1
002
Carrier 2
SLOT 0
Carrier 1
101 102
001
A30808-X3247-F380-1-7631
57
IMN:BTSE BS 240
2.8.2
DUAMCO 0 4:2 Module 0
RX0 RX1 RX2 RX3 RX0
SLOT 0
Module 1
RX CU 3 RXdiv
014
TX1
Module 1
RX CU 2 RXdiv
013
TX0
SLOT 0
RX CU 1 RXdiv
012
TX1
Module 0
RX CU 0 RXdiv
011
TX0
SLOT 1
SLOT 1
SLOT 2
017 018
TX0 TX1
Module 1
Module 1
Fig. 2.35
SLOT 3
58
A30808-X3247-F380-1-7631
SLOT 3
SLOT 2
IMN:BTSE BS 240
2.8.3
DUAMCO 0 8:2
RX0 301 302 RX1 RX2 303 RX3 304 RX4 305 306 RX5 307 RX6 RX7 RX0 RX1 RX2
308
RX CU 2 311 RXdiv RX CU 3 312 RXdiv 313 314 RX CU 6 RXdiv RX CU 7 RXdiv RX CU 4 RXdiv RX CU 5 RXdiv
033 034
TX2 TX3
035 036
TX0 TX1
Module 1
SLOT 1
037 038
SLOT 1
315 316
TX2 TX3
SLOT 2
Fig. 2.36
SLOT 3
SLOT 3
SLOT 2
Module 0
SLOT 0
A30808-X3247-F380-1-7631
Module 0
SLOT 0
IMN:BTSE BS 240
2.8.4
DUAMCO 0 2:2 Module 0
RX0 RX1
Module 0
RX
CU 0
TX0
SLOT 0
Module 1
RX RXdiv
CU 1
TX0
Module 0
TX0
SLOT 1
Module 1
108 RX RXdiv
CU 3
TX0
110
RXdiv
Module 0
RX
TX0
SLOT 2
Module 1
112
RX RXdiv
CU 7
TX0
Module 1
RX0 RX1
006
Carrier 3
111
SLOT 2
Carrier 4
109
CU 6
005
DUAMCO 3 2:2
Module 1
RX0 RX1
004
Carrier 4
107
SLOT 1
Carrier 3
CU 2
003
DUAMCO 1 2:2
Module 1
002
Carrier 2
SLOT 0
Carrier 1
101 102
001
114
RXdiv
Module 0
RX
CU 4
TX0
SLOT 3
Module 1
116
RX RXdiv
CU 5
TX0
Fig. 2.37
60
A30808-X3247-F380-1-7631
Module 1
RX0 RX1
008
Carrier 1
115
SLOT 3
Carrier 2
113
007
DUAMCO 2 2:2
IMN:BTSE BS 240
2.8.5
DUAMCO 0 4:2 Module 0
RX0 RX1 RX2 RX3 RX0
SLOT 0
Module 1
RX CU 3 RXdiv
014
TX1
Module 1
RX CU 2 RXdiv
013
TX0
SLOT 0
RX CU 1 RXdiv
012
TX1
Module 0
RX CU 0 RXdiv
011
TX0
SLOT 1
SLOT 1
017 018
TX0 TX1
Fig. 2.38
SLOT 3
SLOT 3
SLOT 2
Module 1
A30808-X3247-F380-1-7631
Module 1
SLOT 2
IMN:BTSE BS 240
2.8.6
DUAMCO 0 2:2 Module 0
RX0 RX1
Module 0
RX
CU 0
TX0
SLOT 0
Module 1
RX RXdiv
CU 1
TX0
Module 0
TX0
SLOT 1
Module 1
108 RX RXdiv
CU 3
TX1
Module 1
RX0 RX1
004
Carrier 4
107
SLOT 1
Carrier 3
CU 2
003
DUAMCO 1 2:2
Module 1
002
Carrier 2
SLOT 0
Carrier 1
101 102
001
017 018
TX0 TX1
Fig. 2.39
SLOT 3
62
A30808-X3247-F380-1-7631
SLOT 3
SLOT 2
Module 1
Module 1
SLOT 2
IMN:BTSE BS 240
2.8.7
DUAMCO 0 2:2 Module 0
RX0 RX1
Module 0
RX
CU 0
TX0
SLOT 0
Module 1
RX RXdiv
CU 1
TX0
Module 0
TX0
SLOT 1
Module 1
108 RX RXdiv
CU 3
TX0
Module 1
RX0 RX1
004
SLOT 2
114
RXdiv
Module 0
RX
CU 4
TX0
SLOT 3
Module 1
116
RX RXdiv
CU 5
TX0
Fig. 2.40
A30808-X3247-F380-1-7631
Module 1
RX0 RX1
008
Carrier 1
115
SLOT 3
Carrier 2
113
007
DUAMCO 2 2:2
SLOT 2
Carrier 2
107
SLOT 1
Carrier 1
CU 2
003
DUAMCO 2 2:2
Module 1
002
Carrier 2
SLOT 0
Carrier 1
101 102
001
IMN:BTSE BS 240
2.8.8
DUAMCO 0 2:2 Module 0
RX0 RX1
Module 0
RX
CU 0
TX0
SLOT 0
Module 1
RX RXdiv
CU 1
TX0
Module 0
TX0
SLOT 1
Module 1
108 RX RXdiv
CU 3
TX0
Module 1
RX0 RX1
004
017 018
TX0 TX1
Fig. 2.41
SLOT 3
64
A30808-X3247-F380-1-7631
SLOT 3
SLOT 2
Module 1
Module 1
SLOT 2
Carrier 2
107
SLOT 1
Carrier 1
CU 2
003
DUAMCO 1 2:2
Module 1
002
Carrier 2
SLOT 0
Carrier 1
101 102
001
IMN:BTSE BS 240
2.8.9
RX RXdiv
CU 0
TX0
502
503 504
TX1 RX RXdiv
CU 1
506
Expansion
RX1 RX2
RXdiv
RX3 RX4 RX5 RX6 RX7 RX0 RX2 RX RXdiv 507 506 RX RXdiv 404 TX1
CU 3
Module 1
510
CU 6
Expansion
SLOT 2
CU 7
TX1
RX RXdiv
514
Expansion
CU 5
Fig. 2.42
Carrier 8
TX1
SLOT3
Carrier 7
513
407
CU 4
TX0
Carrier 6
Carrier 5
RX1
509
405
TX0
RX0
RX
CU 2
TX0
Module 0
SLOT 1
A30808-X3247-F380-1-7631
Carrier 4
Carrier 3
DIAMCO 0
505
403
Carrier 2
402
SLOT 0
Base
Carrier 1
501
401
IMN:BTSE BS 240
2.8.10
RX RXdiv
CU 0
401
502
TX 0
Module 0
RX3 RX4 RX5 RX6 RX7 505 506 RX RXdiv 403 504 503 RX RXdiv
SLOT 0
Base
CU 1
402
TX 1
RX1 RX2
TX 0 Expansion
Module 1
SLOT 1
RX3
CU 3
404
TX 1
RX RXdiv
526
405
TX 0 Expansion
Module 0
SLOT 2
Carrier 4
DIAMCO 1
525
CU 6
Carrier 4
Carrier 3 Base
RX0
CU 2
Carrier 2
501
RX3 RX4 RX5 RX6 RX7 RX0 RX1 RX2 529 530 RX RXdiv 408 527 528 RX RXdiv
CU 7
406
TX 1
CU 4
407
TX 0
CU 5 TX 1
Fig. 2.43
66
A30808-X3247-F380-1-7631
Module 1
SLOT3
DIAMCO 0
IMN:BTSE BS 240
2.8.11
Configuration: 2 Cells with FICOM (max. 2,6,0) Logical numbering of carrier (cell 0) Logical numbering of carrier (cell 1)
67
RX RXdiv
CU 0
401
502
TX 0
Module 0
RX3 RX4 RX5 RX6 RX7 RX RXdiv 403 504 503 RX RXdiv
Base
CU 1
402
TX 1
RX1 RX2
522
TX 0 Expansion
Module 1
CU 3
404
TX 1
RX RXdiv
526
405
TX 0 Expansion
Module 0
CU 7
406
TX 1
RX1 RX2
530
TX 0
Module 1
Base
CU 5 TX 1
Fig. 2.44
A30808-X3247-F380-1-7631
Carrier 1
Carrier 2
RX0
529
CU 4
407
Carrier 3
Carrier 4
DIAMCO 1
525
CU 6
Carrier 5
Carrier 6
RX0
521
CU 2
Carrier 2
Carrier 1
DIAMCO 0
501
IMN:BTSE BS 240
2.9
68
A30808-X3247-F380-1-7631
IMN:BTSE BS 240
3
AC ACOM ACTA ACTC ACTM BS BSC BSS BTS BTS BTSE CAN COBA COSA CU DC DC
Abbreviations
Alternating Current Antenna Combiner Alarm Collection Terminal Alarm Board Alarm Collection Terminal Connection Board Alarm Collection Terminal for Base/Shelter Base Station Base Station Controller Base Station System Base Transceiver Station Base Transceiver Station Base Station Transceiver Equipment Controller Area Network Core Basis Core Satellite Carrier Unit Dircect Current Direct Current Dual Inline Amplifier Multicoupler Duplexer Amplifier Multiplexer Electro Magnetic Interference Electrostatically Sensitive Device Filter Combiner Global System for Mobile Communication Heat Exchanger Link Equipment Local Maintenance Terminal Mobile Station Mobile Subscriber Antenna Multicoupler Network Termination for PCM30 Operation and Maintenance over voltage protection Pulse Code Modulation
DIAMCO DUAMCO EMI ESD FICOM GSM HX LE LMT MS MS MUCO NTPM O&M OVPT PCM PE RF SBS
A30808-X3247-F380-1-7631
69
IMN:BTSE BS 240
70
A30808-X3247-F380-1-7631