You are on page 1of 10

Delay Event 1

Has an event occurred within this section of the project which requires a delay/extension of time to be allowed for? No Please Enter the Unque Code for the Item in Question: Current Time for Completion: Please Enter Item's Code Above Current Cost for Completion: Please Enter Item's Code Above Name of Event in Question: Please Enter Item's Code Above None Extension of Time Required: Required None Adjustment to Contarct Sum Required: Required Adjusted Time for Completion: Please Enter Item's Code Above Adjsuted Cost for Completion: Please Enter Item's Code Above Contractor Contractor's Personell Ommission in Contract No Further Action Required No Need to Proceed With Documentation Please Provide a Brief Desciption of the claim No No No

Is the delay event the fault of:

Calculation of Adjustments Required to Schedule Adustment to Period Allowed Programme Contingency Calculations Delay Extension First Threshold (T1 ) Second Threshold (T2) Rule 1 Rule 2 Rule 3 D T1 T1 < D D > (T1 + 2T2) Adjsutments to the Contract Sum There are Three Accpetable to Calculate the Adjustment to Contract Sum Required for this Delay. Please Select One of these from the Dropdown Below. Do the Additional Works Required Currently Exist within the Original BOQ? Please Continue the Documentation of this Delay Event as indicated Below: Enter the Information in the Indicated Field, Do not Proceed with this Section Please Enter the ID Number from the BOQ for the Activity to Replicate Here: Enter the Information in the Indicated Field, Enter the Information in the Indicated Field, Do not Proceed Do not Proceed with this Section with this Section Given that no Similar Works Exist in the BOQ, this Delay will Please Enter the ID Number from the BOQ Require a Complete Recalculation of Cost. Please enter the for the Activity to Replicate Here: Information required below for Labour, Material, Plant and Design Costs as Shown. Cost of Labour E=0 E=(D-T1)/2 E=D-T1-T2 0 0 3 0 0 -3

Please Enter the Proprtional Amount of These Please Enter the Proprtional Amount of Wokrs required in comparasion to the Amount These Wokrs required in comparasion to the Already Listed in the BOQ. E.g. If the Delay Amount Already Listed in the BOQ. E.g. If the Requires 10 Days of an Activity which is Listed Delay Requires 10 Days of an Activity which as Taking 20 then enter 0.5 below (20/10 = is Listed as Taking 20 then enter 0.5 below 0.5). (20/10 = 0.5). Re-Caluculated Cost of Activity Adjustment to Contract Sum Required None Required

Please select a value for the hourly rate of the Craftsmen on this project. All other values are automatically calculated as per the current Construction Industry Registered Employment (Craftsmen rate automatically set to min. of 17.21) 1 Type of Employee No. Rate/hr Total Cost Craftsmen 17.21 0.00 16.69 0.00 Please Enter the Corelation Factor Between Technical Operative 15.66 0.00 these Works and Those Required. E.g. if the Skilled Operative Works required Here will cost 50% more than that Listed in the BOQ the Enter 1.5 Semi-Skilled Operative 15.14 0.00 Below (If Left Blank = 1). Basic Operative 13.77 0.00 1st Year Apprentice 5.73 0.00 1 2nd Year Apprentice 8.61 0.00 Re-Caluculated Cost of Activity 3rd Year Apprentice 12.91 0.00 4th Year Apprentice 15.49 0.00 Adjustment to Contract Sum Required Total Cost of Labour 0.00 None Required Please enter the required details in relation to materials required for pallned works. All figures to be entered exlcuding VAT. Percentage adj. as stated to in Schedule Part 2D must not be greater than 100%. Cost of Materials Cost per Unit (Exl. VAT) No. % Adj.

Name

Total Cost

Total Cost of Materials

0.00

Please enter the required details in relation to plant required for pallned works. All figures to be entered exlcuding VAT. Percentage adj. as stated to in Schedule Part 2D must not be greater than 100%. Cost of Plant Cost per Unit (Exl. VAT)

Name

No.

% Adj.

Total Cost

Total Cost of Plant Cost of Design Works Total Recalculated Cost of Section of Works Total Adjustment to Contract Sum Required

0.00

0.00 None Required

Delay Event 2
Has an event occurred within this section of the project which requires a delay/extension of time to be allowed for? No Please Enter the Unque Code for the Item in Question: Current Time for Completion: Please enter Item's Code Above Current Cost for Completion: Please enter Item's Code Above Name of Event in Question: Please enter Item's Code Above None Extension of Time Required: Required None Adjustment to Contarct Sum Required: Required Adjusted Time for Completion: Please enter Item's Code Above Adjsuted Cost for Completion: Please enter Item's Code Above Contractor Contractor's Personell Ommission in Contract No Further Action Required No Need to Proceed With Documentation Please Provide a Brief Desciption of the claim No No No

Is the delay event the fault of:

Calculation of Adjustments Required to Schedule Adustment to Period Allowed Programme Contingency Calculations Delay Extension First Threshold (T1 ) Second Threshold (T2) Rule 1 Rule 2 Rule 3 D T1 T1 < D D > (T1 + 2T2) E=0 E=(D-T1)/2 E=D-T1-T2 0

0 0 0

Adjsutments to the Contract Sum There are Three Accpetable to Calculate the Adjustment to Contract Sum Required for this Delay. Please Select One of these from the Dropdown Below. Do the Additional Works Required Currently Exist within the Original BOQ? Please Continue the Documentation of this Delay Event as indicated Below: Enter the Information in the Indicated Field, Enter the Information in the Indicated Field, Enter the Information in the Indicated Field, Do not Do not Proceed with this Section Do not Proceed with this Section Proceed with this Section Given that no Similar Works Exist in the BOQ, this Delay Please Enter the ID Number from the BOQ Please Enter the ID Number from the BOQ will Require a Complete Recalculation of Cost. Please for the Activity to Replicate Here: for the Activity to Replicate Here: enter the Information required below for Labour, Material, Plant and Design Costs as Shown. Cost of Labour Please Enter the Proprtional Amount of Please Enter the Proprtional Amount of These Wokrs required in comparasion to the These Wokrs required in comparasion to the Please select a value for the hourly rate of Amount Already Listed in the BOQ. E.g. If the Amount Already Listed in the BOQ. E.g. If the the Craftsmen on this project. Delay Requires 10 Days of an Activity which Delay Requires 10 Days of an Activity which All other values are automatically calculated as per the is Listed as Taking 20 then enter 0.5 below is Listed as Taking 20 then enter 0.5 below current Construction Industry Registered Employment (20/10 = 0.5). (20/10 = 0.5). (Craftsmen rate automatically set to min. of 17.21) 1 1 Type of Employee No. Rate/hr Total Cost Re-Caluculated Cost of Activity Craftsmen 17.21 0.00 16.69 0.00 Please Enter the Corelation Factor Between Technical Operative Adjustment to Contract Sum Required 15.66 0.00 these Works and Those Required. E.g. if the Skilled Operative Works required Here will cost 50% more Semi-Skilled None Required than that Listed in the BOQ the Enter 1.5 Operative 15.14 0.00 Below (If Left Blank = 1). Basic Operative 13.77 0.00 1st Year Apprentice 5.73 0.00 1 2nd Year Apprentice 8.61 0.00 Re-Caluculated Cost of Activity 3rd Year Apprentice 12.91 0.00 4th Year Apprentice 15.49 0.00 Adjustment to Contract Sum Required Total Cost of Labour 0.00 None Required Please enter the required details in relation to materials required for pallned works. All figures to be entered exlcuding VAT. Percentage adj. as stated to in Schedule Part 2D must not be greater than 100%. Cost of Materials Cost per Unit (Exl. VAT) No. % Adj.

Name

Total Cost

Total Cost of Materials

0.00

Please enter the required details in relation to plant required for pallned works. All figures to be entered exlcuding VAT. Percentage adj. as stated to in Schedule Part 2D must not be greater than 100%. Cost of Plant Cost per Unit (Exl. VAT) % Adj.

Name

No.

Total Cost

Total Cost of Plant Cost of Design Works Total Recalculated Cost of Section of Works

0.00

0.00 None Total Adjustment to Contract Sum Required Required

Delay Event 3
Has an event occurred within this section of the project which requires a delay/extension of time to be allowed for? No Please Enter the Unque Code for the Item in Question: Current Time for Completion: Please enter Item's Code Above Current Cost for Completion: Please enter Item's Code Above Name of Event in Question: Please enter Item's Code Above None Extension of Time Required: Required None Adjustment to Contarct Sum Required: Required Adjusted Time for Completion: Please enter Item's Code Above Adjsuted Cost for Completion: Please enter Item's Code Above Contractor Contractor's Personell Ommission in Contract No Further Action Required No Need to Proceed With Documentation Please Provide a Brief Desciption of the claim No No No

Is the delay event the fault of:

Calculation of Adjustments Required to Schedule Adustment to Period Allowed Programme Contingency Calculations Delay Extension First Threshold (T1 ) Second Threshold (T2) Rule 1 Rule 2 Rule 3 D T1 T1 < D D > (T1 + 2T2) E=0 E=(D-T1)/2 E=D-T1-T2 0

0 0 0

Adjsutments to the Contract Sum There are Three Accpetable to Calculate the Adjustment to Contract Sum Required for this Delay. Please Select One of these from the Dropdown Below. Do the Additional Works Required Currently Exist within the Original BOQ? Please Continue the Documentation of this Delay Event as indicated Below: Enter the Information in the Indicated Field, Enter the Information in the Indicated Field, Enter the Information in the Indicated Field, Do not Do not Proceed with this Section Do not Proceed with this Section Proceed with this Section Given that no Similar Works Exist in the BOQ, this Delay Please Enter the ID Number from the BOQ Please Enter the ID Number from the BOQ will Require a Complete Recalculation of Cost. Please for the Activity to Replicate Here: for the Activity to Replicate Here: enter the Information required below for Labour, Material, Plant and Design Costs as Shown. Cost of Labour Please Enter the Proprtional Amount of Please Enter the Proprtional Amount of These Wokrs required in comparasion to the These Wokrs required in comparasion to the Please select a value for the hourly rate of Amount Already Listed in the BOQ. E.g. If the Amount Already Listed in the BOQ. E.g. If the the Craftsmen on this project. Delay Requires 10 Days of an Activity which Delay Requires 10 Days of an Activity which All other values are automatically calculated as per the is Listed as Taking 20 then enter 0.5 below is Listed as Taking 20 then enter 0.5 below current Construction Industry Registered Employment (20/10 = 0.5). (20/10 = 0.5). (Craftsmen rate automatically set to min. of 17.21) 1 1 Type of Employee No. Rate/hr Total Cost Re-Caluculated Cost of Activity Craftsmen 17.21 0.00 16.69 0.00 Please Enter the Corelation Factor Between Technical Operative Adjustment to Contract Sum Required 15.66 0.00 these Works and Those Required. E.g. if the Skilled Operative Works required Here will cost 50% more Semi-Skilled None Required than that Listed in the BOQ the Enter 1.5 Operative 15.14 0.00 Below (If Left Blank = 1). Basic Operative 13.77 0.00 1st Year Apprentice 5.73 0.00 1 2nd Year Apprentice 8.61 0.00 Re-Caluculated Cost of Activity 3rd Year Apprentice 12.91 0.00 4th Year Apprentice 15.49 0.00 Adjustment to Contract Sum Required Total Cost of Labour 0.00 None Required Please enter the required details in relation to materials required for pallned works. All figures to be entered exlcuding VAT. Percentage adj. as stated to in Schedule Part 2D must not be greater than 100%. Cost of Materials Cost per Unit (Exl. VAT) No. % Adj.

Name

Total Cost

Total Cost of Materials

0.00

Please enter the required details in relation to plant required for pallned works. All figures to be entered exlcuding VAT. Percentage adj. as stated to in Schedule Part 2D must not be greater than 100%. Cost of Plant Cost per Unit (Exl. VAT) % Adj.

Name

No.

Total Cost

Total Cost of Plant Cost of Design Works Total Recalculated Cost of Section of Works

0.00

0.00 None Total Adjustment to Contract Sum Required Required

Delay Event 4
Has an event occurred within this section of the project which requires a delay/extension of time to be allowed for? No Please Enter the Unque Code for the Item in Question: Current Time for Completion: Please enter Item's Code Above Current Cost for Completion: Please enter Item's Code Above Name of Event in Question: Please enter Item's Code Above None Extension of Time Required: Required None Adjustment to Contarct Sum Required: Required Adjusted Time for Completion: Please enter Item's Code Above Adjsuted Cost for Completion: Please enter Item's Code Above Contractor Contractor's Personell Ommission in Contract No Further Action Required No Need to Proceed With Documentation Please Provide a Brief Desciption of the claim No No No

Is the delay event the fault of:

Calculation of Adjustments Required to Schedule Adustment to Period Allowed Programme Contingency Calculations Delay Extension First Threshold (T1 ) Second Threshold (T2) Rule 1 Rule 2 Rule 3 D T1 T1 < D D > (T1 + 2T2) E=0 E=(D-T1)/2 E=D-T1-T2 0

0 0 0

Adjsutments to the Contract Sum There are Three Accpetable to Calculate the Adjustment to Contract Sum Required for this Delay. Please Select One of these from the Dropdown Below. Do the Additional Works Required Currently Exist within the Original BOQ? Please Continue the Documentation of this Delay Event as indicated Below: Enter the Information in the Indicated Field, Enter the Information in the Indicated Field, Enter the Information in the Indicated Field, Do not Do not Proceed with this Section Do not Proceed with this Section Proceed with this Section Given that no Similar Works Exist in the BOQ, this Delay Please Enter the ID Number from the BOQ Please Enter the ID Number from the BOQ will Require a Complete Recalculation of Cost. Please for the Activity to Replicate Here: for the Activity to Replicate Here: enter the Information required below for Labour, Material, Plant and Design Costs as Shown. Cost of Labour Please Enter the Proprtional Amount of Please Enter the Proprtional Amount of These Wokrs required in comparasion to the These Wokrs required in comparasion to the Please select a value for the hourly rate of Amount Already Listed in the BOQ. E.g. If the Amount Already Listed in the BOQ. E.g. If the the Craftsmen on this project. Delay Requires 10 Days of an Activity which Delay Requires 10 Days of an Activity which All other values are automatically calculated as per the is Listed as Taking 20 then enter 0.5 below is Listed as Taking 20 then enter 0.5 below current Construction Industry Registered Employment (20/10 = 0.5). (20/10 = 0.5). (Craftsmen rate automatically set to min. of 17.21) 1 1 Type of Employee No. Rate/hr Total Cost Re-Caluculated Cost of Activity Craftsmen 17.21 0.00 16.69 0.00 Please Enter the Corelation Factor Between Technical Operative Adjustment to Contract Sum Required 15.66 0.00 these Works and Those Required. E.g. if the Skilled Operative Works required Here will cost 50% more Semi-Skilled None Required than that Listed in the BOQ the Enter 1.5 Operative 15.14 0.00 Below (If Left Blank = 1). Basic Operative 13.77 0.00 1st Year Apprentice 5.73 0.00 1 2nd Year Apprentice 8.61 0.00 Re-Caluculated Cost of Activity 3rd Year Apprentice 12.91 0.00 4th Year Apprentice 15.49 0.00 Adjustment to Contract Sum Required Total Cost of Labour 0.00 None Required Please enter the required details in relation to materials required for pallned works. All figures to be entered exlcuding VAT. Percentage adj. as stated to in Schedule Part 2D must not be greater than 100%. Cost of Materials Cost per Unit (Exl. VAT) No. % Adj.

Name

Total Cost

Total Cost of Materials

0.00

Please enter the required details in relation to plant required for pallned works. All figures to be entered exlcuding VAT. Percentage adj. as stated to in Schedule Part 2D must not be greater than 100%. Cost of Plant Cost per Unit (Exl. VAT) % Adj.

Name

No.

Total Cost

Total Cost of Plant Cost of Design Works Total Recalculated Cost of Section of Works

0.00

0.00 None Total Adjustment to Contract Sum Required Required

Delay Event 5
Has an event occurred within this section of the project which requires a delay/extension of time to be allowed for? No Please Enter the Unque Code for the Item in Question: Current Time for Completion: Please enter Item's Code Above Current Cost for Completion: Please enter Item's Code Above Name of Event in Question: Please enter Item's Code Above None Extension of Time Required: Required None Adjustment to Contarct Sum Required: Required Adjusted Time for Completion: Please enter Item's Code Above Adjsuted Cost for Completion: Please enter Item's Code Above Contractor Contractor's Personell Ommission in Contract No Further Action Required No Need to Proceed With Documentation Please Provide a Brief Desciption of the claim No No No

Is the delay event the fault of:

Calculation of Adjustments Required to Schedule Adustment to Period Allowed Programme Contingency Calculations Delay Extension First Threshold (T1 ) Second Threshold (T2) Rule 1 Rule 2 Rule 3 D T1 T1 < D D > (T1 + 2T2) E=0 E=(D-T1)/2 E=D-T1-T2 0

0 0 0

Adjsutments to the Contract Sum There are Three Accpetable to Calculate the Adjustment to Contract Sum Required for this Delay. Please Select One of these from the Dropdown Below. Do the Additional Works Required Currently Exist within the Original BOQ? Please Continue the Documentation of this Delay Event as indicated Below: Enter the Information in the Indicated Field, Enter the Information in the Indicated Field, Enter the Information in the Indicated Field, Do not Do not Proceed with this Section Do not Proceed with this Section Proceed with this Section Given that no Similar Works Exist in the BOQ, this Delay Please Enter the ID Number from the BOQ Please Enter the ID Number from the BOQ will Require a Complete Recalculation of Cost. Please for the Activity to Replicate Here: for the Activity to Replicate Here: enter the Information required below for Labour, Material, Plant and Design Costs as Shown. Cost of Labour Please Enter the Proprtional Amount of Please Enter the Proprtional Amount of These Wokrs required in comparasion to the These Wokrs required in comparasion to the Please select a value for the hourly rate of Amount Already Listed in the BOQ. E.g. If the Amount Already Listed in the BOQ. E.g. If the the Craftsmen on this project. Delay Requires 10 Days of an Activity which Delay Requires 10 Days of an Activity which All other values are automatically calculated as per the is Listed as Taking 20 then enter 0.5 below is Listed as Taking 20 then enter 0.5 below current Construction Industry Registered Employment (20/10 = 0.5). (20/10 = 0.5). (Craftsmen rate automatically set to min. of 17.21) 1 1 Type of Employee No. Rate/hr Total Cost Re-Caluculated Cost of Activity Craftsmen 17.21 0.00 16.69 0.00 Please Enter the Corelation Factor Between Technical Operative Adjustment to Contract Sum Required 15.66 0.00 these Works and Those Required. E.g. if the Skilled Operative Works required Here will cost 50% more Semi-Skilled None Required than that Listed in the BOQ the Enter 1.5 Operative 15.14 0.00 Below (If Left Blank = 1). Basic Operative 13.77 0.00 1st Year Apprentice 5.73 0.00 1 2nd Year Apprentice 8.61 0.00 Re-Caluculated Cost of Activity 3rd Year Apprentice 12.91 0.00 4th Year Apprentice 15.49 0.00 Adjustment to Contract Sum Required Total Cost of Labour 0.00 None Required Please enter the required details in relation to materials required for pallned works. All figures to be entered exlcuding VAT. Percentage adj. as stated to in Schedule Part 2D must not be greater than 100%. Cost of Materials Cost per Unit (Exl. VAT) No. % Adj.

Name

Total Cost

Total Cost of Materials

0.00

Please enter the required details in relation to plant required for pallned works. All figures to be entered exlcuding VAT. Percentage adj. as stated to in Schedule Part 2D must not be greater than 100%. Cost of Plant Cost per Unit (Exl. VAT) % Adj.

Name

No.

Total Cost

Total Cost of Plant Cost of Design Works Total Recalculated Cost of Section of Works

0.00

0.00 None Total Adjustment to Contract Sum Required Required

Delay Event 6
Has an event occurred within this section of the project which requires a delay/extension of time to be allowed for? No Please Enter the Unque Code for the Item in Question: Current Time for Completion: Please enter Item's Code Above Current Cost for Completion: Please enter Item's Code Above Name of Event in Question: Please enter Item's Code Above None Extension of Time Required: Required None Adjustment to Contarct Sum Required: Required Adjusted Time for Completion: Please enter Item's Code Above Adjsuted Cost for Completion: Please enter Item's Code Above Contractor Contractor's Personell Ommission in Contract No Further Action Required No Need to Proceed With Documentation Please Provide a Brief Desciption of the claim No No No

Is the delay event the fault of:

Calculation of Adjustments Required to Schedule Adustment to Period Allowed Programme Contingency Calculations Delay Extension First Threshold (T1 ) Second Threshold (T2) Rule 1 Rule 2 Rule 3 D T1 T1 < D D > (T1 + 2T2) E=0 E=(D-T1)/2 E=D-T1-T2 0

0 0 0

Adjsutments to the Contract Sum There are Three Accpetable to Calculate the Adjustment to Contract Sum Required for this Delay. Please Select One of these from the Dropdown Below. Do the Additional Works Required Currently Exist within the Original BOQ? Please Continue the Documentation of this Delay Event as indicated Below: Enter the Information in the Indicated Field, Enter the Information in the Indicated Field, Enter the Information in the Indicated Field, Do not Do not Proceed with this Section Do not Proceed with this Section Proceed with this Section Given that no Similar Works Exist in the BOQ, this Delay Please Enter the ID Number from the BOQ Please Enter the ID Number from the BOQ will Require a Complete Recalculation of Cost. Please for the Activity to Replicate Here: for the Activity to Replicate Here: enter the Information required below for Labour, Material, Plant and Design Costs as Shown. Cost of Labour Please Enter the Proprtional Amount of Please Enter the Proprtional Amount of These Wokrs required in comparasion to the These Wokrs required in comparasion to the Please select a value for the hourly rate of Amount Already Listed in the BOQ. E.g. If the Amount Already Listed in the BOQ. E.g. If the the Craftsmen on this project. Delay Requires 10 Days of an Activity which Delay Requires 10 Days of an Activity which All other values are automatically calculated as per the is Listed as Taking 20 then enter 0.5 below is Listed as Taking 20 then enter 0.5 below current Construction Industry Registered Employment (20/10 = 0.5). (20/10 = 0.5). (Craftsmen rate automatically set to min. of 17.21) 1 1 Type of Employee No. Rate/hr Total Cost Re-Caluculated Cost of Activity Craftsmen 17.21 0.00 16.69 0.00 Please Enter the Corelation Factor Between Technical Operative Adjustment to Contract Sum Required 15.66 0.00 these Works and Those Required. E.g. if the Skilled Operative Works required Here will cost 50% more Semi-Skilled None Required than that Listed in the BOQ the Enter 1.5 Operative 15.14 0.00 Below (If Left Blank = 1). Basic Operative 13.77 0.00 1st Year Apprentice 5.73 0.00 1 2nd Year Apprentice 8.61 0.00 Re-Caluculated Cost of Activity 3rd Year Apprentice 12.91 0.00 4th Year Apprentice 15.49 0.00 Adjustment to Contract Sum Required Total Cost of Labour 0.00 None Required Please enter the required details in relation to materials required for pallned works. All figures to be entered exlcuding VAT. Percentage adj. as stated to in Schedule Part 2D must not be greater than 100%. Cost of Materials Cost per Unit (Exl. VAT) No. % Adj.

Name

Total Cost

Total Cost of Materials

0.00

Please enter the required details in relation to plant required for pallned works. All figures to be entered exlcuding VAT. Percentage adj. as stated to in Schedule Part 2D must not be greater than 100%. Cost of Plant Cost per Unit (Exl. VAT) % Adj.

Name

No.

Total Cost

Total Cost of Plant Cost of Design Works Total Recalculated Cost of Section of Works

0.00

0.00 None Total Adjustment to Contract Sum Required Required

Delay Event 7
Has an event occurred within this section of the project which requires a delay/extension of time to be allowed for? No Please Enter the Unque Code for the Item in Question: Current Time for Completion: Please enter Item's Code Above Current Cost for Completion: Please enter Item's Code Above Name of Event in Question: Please enter Item's Code Above None Extension of Time Required: Required None Adjustment to Contarct Sum Required: Required Adjusted Time for Completion: Please enter Item's Code Above Adjsuted Cost for Completion: Please enter Item's Code Above Contractor Contractor's Personell Ommission in Contract No Further Action Required No Need to Proceed With Documentation Please Provide a Brief Desciption of the claim No No No

Is the delay event the fault of:

Calculation of Adjustments Required to Schedule Adustment to Period Allowed Programme Contingency Calculations Delay Extension First Threshold (T1 ) Second Threshold (T2) Rule 1 Rule 2 Rule 3 D T1 T1 < D D > (T1 + 2T2) E=0 E=(D-T1)/2 E=D-T1-T2 0

0 0 0

Adjsutments to the Contract Sum There are Three Accpetable to Calculate the Adjustment to Contract Sum Required for this Delay. Please Select One of these from the Dropdown Below. Do the Additional Works Required Currently Exist within the Original BOQ? Please Continue the Documentation of this Delay Event as indicated Below: Enter the Information in the Indicated Field, Enter the Information in the Indicated Field, Enter the Information in the Indicated Field, Do not Do not Proceed with this Section Do not Proceed with this Section Proceed with this Section Given that no Similar Works Exist in the BOQ, this Delay Please Enter the ID Number from the BOQ Please Enter the ID Number from the BOQ will Require a Complete Recalculation of Cost. Please for the Activity to Replicate Here: for the Activity to Replicate Here: enter the Information required below for Labour, Material, Plant and Design Costs as Shown. Cost of Labour Please Enter the Proprtional Amount of Please Enter the Proprtional Amount of These Wokrs required in comparasion to the These Wokrs required in comparasion to the Please select a value for the hourly rate of Amount Already Listed in the BOQ. E.g. If the Amount Already Listed in the BOQ. E.g. If the the Craftsmen on this project. Delay Requires 10 Days of an Activity which Delay Requires 10 Days of an Activity which All other values are automatically calculated as per the is Listed as Taking 20 then enter 0.5 below is Listed as Taking 20 then enter 0.5 below current Construction Industry Registered Employment (20/10 = 0.5). (20/10 = 0.5). (Craftsmen rate automatically set to min. of 17.21) 1 1 Type of Employee No. Rate/hr Total Cost Re-Caluculated Cost of Activity Craftsmen 17.21 0.00 16.69 0.00 Please Enter the Corelation Factor Between Technical Operative Adjustment to Contract Sum Required 15.66 0.00 these Works and Those Required. E.g. if the Skilled Operative Works required Here will cost 50% more Semi-Skilled None Required than that Listed in the BOQ the Enter 1.5 Operative 15.14 0.00 Below (If Left Blank = 1). Basic Operative 13.77 0.00 1st Year Apprentice 5.73 0.00 1 2nd Year Apprentice 8.61 0.00 Re-Caluculated Cost of Activity 3rd Year Apprentice 12.91 0.00 4th Year Apprentice 15.49 0.00 Adjustment to Contract Sum Required Total Cost of Labour 0.00 None Required Please enter the required details in relation to materials required for pallned works. All figures to be entered exlcuding VAT. Percentage adj. as stated to in Schedule Part 2D must not be greater than 100%. Cost of Materials Cost per Unit (Exl. VAT) No. % Adj.

Name

Total Cost

Total Cost of Materials

0.00

Please enter the required details in relation to plant required for pallned works. All figures to be entered exlcuding VAT. Percentage adj. as stated to in Schedule Part 2D must not be greater than 100%. Cost of Plant Cost per Unit (Exl. VAT) % Adj.

Name

No.

Total Cost

Total Cost of Plant Cost of Design Works Total Recalculated Cost of Section of Works

0.00

0.00 None Total Adjustment to Contract Sum Required Required

Delay Event 8
Has an event occurred within this section of the project which requires a delay/extension of time to be allowed for? No Please Enter the Unque Code for the Item in Question: Current Time for Completion: Please enter Item's Code Above Current Cost for Completion: Please enter Item's Code Above Name of Event in Question: Please enter Item's Code Above None Extension of Time Required: Required None Adjustment to Contarct Sum Required: Required Adjusted Time for Completion: Please enter Item's Code Above Adjsuted Cost for Completion: Please enter Item's Code Above Contractor Contractor's Personell Ommission in Contract No Further Action Required No Need to Proceed With Documentation Please Provide a Brief Desciption of the claim No No No

Is the delay event the fault of:

Calculation of Adjustments Required to Schedule Adustment to Period Allowed Programme Contingency Calculations Delay Extension First Threshold (T1 ) Second Threshold (T2) Rule 1 Rule 2 Rule 3 D T1 T1 < D D > (T1 + 2T2) E=0 E=(D-T1)/2 E=D-T1-T2 0

0 0 0

Adjsutments to the Contract Sum There are Three Accpetable to Calculate the Adjustment to Contract Sum Required for this Delay. Please Select One of these from the Dropdown Below. Do the Additional Works Required Currently Exist within the Original BOQ? Please Continue the Documentation of this Delay Event as indicated Below: Enter the Information in the Indicated Field, Enter the Information in the Indicated Field, Enter the Information in the Indicated Field, Do not Do not Proceed with this Section Do not Proceed with this Section Proceed with this Section Given that no Similar Works Exist in the BOQ, this Delay Please Enter the ID Number from the BOQ Please Enter the ID Number from the BOQ will Require a Complete Recalculation of Cost. Please for the Activity to Replicate Here: for the Activity to Replicate Here: enter the Information required below for Labour, Material, Plant and Design Costs as Shown. Cost of Labour Please Enter the Proprtional Amount of Please Enter the Proprtional Amount of These Wokrs required in comparasion to the These Wokrs required in comparasion to the Please select a value for the hourly rate of Amount Already Listed in the BOQ. E.g. If the Amount Already Listed in the BOQ. E.g. If the the Craftsmen on this project. Delay Requires 10 Days of an Activity which Delay Requires 10 Days of an Activity which All other values are automatically calculated as per the is Listed as Taking 20 then enter 0.5 below is Listed as Taking 20 then enter 0.5 below current Construction Industry Registered Employment (20/10 = 0.5). (20/10 = 0.5). (Craftsmen rate automatically set to min. of 17.21) 1 1 Type of Employee No. Rate/hr Total Cost Re-Caluculated Cost of Activity Craftsmen 17.21 0.00 16.69 0.00 Please Enter the Corelation Factor Between Technical Operative Adjustment to Contract Sum Required 15.66 0.00 these Works and Those Required. E.g. if the Skilled Operative Works required Here will cost 50% more Semi-Skilled None Required than that Listed in the BOQ the Enter 1.5 Operative 15.14 0.00 Below (If Left Blank = 1). Basic Operative 13.77 0.00 1st Year Apprentice 5.73 0.00 1 2nd Year Apprentice 8.61 0.00 Re-Caluculated Cost of Activity 3rd Year Apprentice 12.91 0.00 4th Year Apprentice 15.49 0.00 Adjustment to Contract Sum Required Total Cost of Labour 0.00 None Required Please enter the required details in relation to materials required for pallned works. All figures to be entered exlcuding VAT. Percentage adj. as stated to in Schedule Part 2D must not be greater than 100%. Cost of Materials Cost per Unit (Exl. VAT) No. % Adj.

Name

Total Cost

Total Cost of Materials

0.00

Please enter the required details in relation to plant required for pallned works. All figures to be entered exlcuding VAT. Percentage adj. as stated to in Schedule Part 2D must not be greater than 100%. Cost of Plant Cost per Unit (Exl. VAT) % Adj.

Name

No.

Total Cost

Total Cost of Plant Cost of Design Works Total Recalculated Cost of Section of Works

0.00

0.00 None Total Adjustment to Contract Sum Required Required

Delay Event 9
Has an event occurred within this section of the project which requires a delay/extension of time to be allowed for? No Please Enter the Unque Code for the Item in Question: Current Time for Completion: Please enter Item's Code Above Current Cost for Completion: Please enter Item's Code Above Name of Event in Question: Please enter Item's Code Above None Extension of Time Required: Required None Adjustment to Contarct Sum Required: Required Adjusted Time for Completion: Please enter Item's Code Above Adjsuted Cost for Completion: Please enter Item's Code Above Contractor Contractor's Personell Ommission in Contract No Further Action Required No Need to Proceed With Documentation Please Provide a Brief Desciption of the claim No No No

Is the delay event the fault of:

Calculation of Adjustments Required to Schedule Adustment to Period Allowed Programme Contingency Calculations Delay Extension First Threshold (T1 ) Second Threshold (T2) Rule 1 Rule 2 Rule 3 D T1 T1 < D D > (T1 + 2T2) E=0 E=(D-T1)/2 E=D-T1-T2 0

0 0 0

Adjsutments to the Contract Sum There are Three Accpetable to Calculate the Adjustment to Contract Sum Required for this Delay. Please Select One of these from the Dropdown Below. Do the Additional Works Required Currently Exist within the Original BOQ? Please Continue the Documentation of this Delay Event as indicated Below: Enter the Information in the Indicated Field, Enter the Information in the Indicated Field, Enter the Information in the Indicated Field, Do not Do not Proceed with this Section Do not Proceed with this Section Proceed with this Section Given that no Similar Works Exist in the BOQ, this Delay Please Enter the ID Number from the BOQ Please Enter the ID Number from the BOQ will Require a Complete Recalculation of Cost. Please for the Activity to Replicate Here: for the Activity to Replicate Here: enter the Information required below for Labour, Material, Plant and Design Costs as Shown. Cost of Labour Please Enter the Proprtional Amount of Please Enter the Proprtional Amount of These Wokrs required in comparasion to the These Wokrs required in comparasion to the Please select a value for the hourly rate of Amount Already Listed in the BOQ. E.g. If the Amount Already Listed in the BOQ. E.g. If the the Craftsmen on this project. Delay Requires 10 Days of an Activity which Delay Requires 10 Days of an Activity which All other values are automatically calculated as per the is Listed as Taking 20 then enter 0.5 below is Listed as Taking 20 then enter 0.5 below current Construction Industry Registered Employment (20/10 = 0.5). (20/10 = 0.5). (Craftsmen rate automatically set to min. of 17.21) 1 1 Type of Employee No. Rate/hr Total Cost Re-Caluculated Cost of Activity Craftsmen 17.21 0.00 16.69 0.00 Please Enter the Corelation Factor Between Technical Operative Adjustment to Contract Sum Required 15.66 0.00 these Works and Those Required. E.g. if the Skilled Operative Works required Here will cost 50% more Semi-Skilled None Required than that Listed in the BOQ the Enter 1.5 Operative 15.14 0.00 Below (If Left Blank = 1). Basic Operative 13.77 0.00 1st Year Apprentice 5.73 0.00 1 2nd Year Apprentice 8.61 0.00 Re-Caluculated Cost of Activity 3rd Year Apprentice 12.91 0.00 4th Year Apprentice 15.49 0.00 Adjustment to Contract Sum Required Total Cost of Labour 0.00 None Required Please enter the required details in relation to materials required for pallned works. All figures to be entered exlcuding VAT. Percentage adj. as stated to in Schedule Part 2D must not be greater than 100%. Cost of Materials Cost per Unit (Exl. VAT) No. % Adj.

Name

Total Cost

Total Cost of Materials

0.00

Please enter the required details in relation to plant required for pallned works. All figures to be entered exlcuding VAT. Percentage adj. as stated to in Schedule Part 2D must not be greater than 100%. Cost of Plant Cost per Unit (Exl. VAT) % Adj.

Name

No.

Total Cost

Total Cost of Plant Cost of Design Works Total Recalculated Cost of Section of Works

0.00

0.00 None Total Adjustment to Contract Sum Required Required

Delay Event 10
Has an event occurred within this section of the project which requires a delay/extension of time to be allowed for? No Please Enter the Unque Code for the Item in Question: Current Time for Completion: Please enter Item's Code Above Current Cost for Completion: Please enter Item's Code Above Name of Event in Question: Please enter Item's Code Above None Extension of Time Required: Required None Adjustment to Contarct Sum Required: Required Adjusted Time for Completion: Please enter Item's Code Above Adjsuted Cost for Completion: Please enter Item's Code Above Contractor Contractor's Personell Ommission in Contract No Further Action Required No Need to Proceed With Documentation Please Provide a Brief Desciption of the claim No No No

Is the delay event the fault of:

Calculation of Adjustments Required to Schedule Adustment to Period Allowed Programme Contingency Calculations Delay Extension First Threshold (T1 ) Second Threshold (T2) Rule 1 Rule 2 Rule 3 D T1 T1 < D D > (T1 + 2T2) E=0 E=(D-T1)/2 E=D-T1-T2 0

0 0 0

Adjsutments to the Contract Sum There are Three Accpetable to Calculate the Adjustment to Contract Sum Required for this Delay. Please Select One of these from the Dropdown Below. Do the Additional Works Required Currently Exist within the Original BOQ? Please Continue the Documentation of this Delay Event as indicated Below: Enter the Information in the Indicated Field, Enter the Information in the Indicated Field, Enter the Information in the Indicated Field, Do not Do not Proceed with this Section Do not Proceed with this Section Proceed with this Section Given that no Similar Works Exist in the BOQ, this Delay Please Enter the ID Number from the BOQ Please Enter the ID Number from the BOQ will Require a Complete Recalculation of Cost. Please for the Activity to Replicate Here: for the Activity to Replicate Here: enter the Information required below for Labour, Material, Plant and Design Costs as Shown. Cost of Labour Please Enter the Proprtional Amount of Please Enter the Proprtional Amount of These Wokrs required in comparasion to the These Wokrs required in comparasion to the Please select a value for the hourly rate of Amount Already Listed in the BOQ. E.g. If the Amount Already Listed in the BOQ. E.g. If the the Craftsmen on this project. Delay Requires 10 Days of an Activity which Delay Requires 10 Days of an Activity which All other values are automatically calculated as per the is Listed as Taking 20 then enter 0.5 below is Listed as Taking 20 then enter 0.5 below current Construction Industry Registered Employment (20/10 = 0.5). (20/10 = 0.5). (Craftsmen rate automatically set to min. of 17.21) 1 1 Type of Employee No. Rate/hr Total Cost Re-Caluculated Cost of Activity Craftsmen 17.21 0.00 16.69 0.00 Please Enter the Corelation Factor Between Technical Operative Adjustment to Contract Sum Required 15.66 0.00 these Works and Those Required. E.g. if the Skilled Operative Works required Here will cost 50% more Semi-Skilled None Required than that Listed in the BOQ the Enter 1.5 Operative 15.14 0.00 Below (If Left Blank = 1). Basic Operative 13.77 0.00 1st Year Apprentice 5.73 0.00 1 2nd Year Apprentice 8.61 0.00 Re-Caluculated Cost of Activity 3rd Year Apprentice 12.91 0.00 4th Year Apprentice 15.49 0.00 Adjustment to Contract Sum Required Total Cost of Labour 0.00 None Required Please enter the required details in relation to materials required for pallned works. All figures to be entered exlcuding VAT. Percentage adj. as stated to in Schedule Part 2D must not be greater than 100%. Cost of Materials Cost per Unit (Exl. VAT) No. % Adj.

Name

Total Cost

Total Cost of Materials

0.00

Please enter the required details in relation to plant required for pallned works. All figures to be entered exlcuding VAT. Percentage adj. as stated to in Schedule Part 2D must not be greater than 100%. Cost of Plant Cost per Unit (Exl. VAT) % Adj.

Name

No.

Total Cost

Total Cost of Plant Cost of Design Works Total Recalculated Cost of Section of Works

0.00

0.00 None Total Adjustment to Contract Sum Required Required

You might also like