Reviewed by:

Linag /Ibrahim Omer


D&P Department
Approved by: Approved by:
Liang Jianye
Field Production Manager
D&P Department
Mogren . Area, KHARTOUM, SUDAN, TEL: 249-11-460921/465873, FAX: 249-11-4658
D&P Department
Tilal / Zhu Cheming
SH Reservoir /Well testing
D&P /OP Department
Development & Production Department
Issued on: Nov.06, 2013
Verticall Well
Prepared by:
Hazim Salah
Workover Engineer Well tes /Production Sup
BLOCK 6 - SUDAN
WELL WORK OVER PROGRAM (1)
FOR
FN-132
Petro-Energy E&P Co., Ltd.

ID
Thick
(mm)
Grade
Casing
depth
Casing shoe
Depth
in mm (mm) Kg/m Ib/ft (m) (m)
10-3/4" 273.05 255.27 8.89 K55 60.27 40.50 0-204.85 205.35
7" 177.80 157.08 10.36 N80 43.16 29.00 0-1445.53 1445.83
Pressure
Rating
Color Manufacturer Remark
3000psi Red Daqing Good
3000psi Red
3000psi Red
Formation Zone No. Top Bottom
Net
reservoir
Net Pay
thick
Phi VCL Sw Result
(m) (m) (m) (m) % % %
Bentiu 2 1302 1313 11 10 27 16 25 Oil
Total 11 10
1
2
3
71/16"
GLB300-27 Stator and Rotor
DP127-32-45 was used for production
2.4 Perforated production Interval
Integrated BOP
PCP Drive Head
Other Equipment
11" x 71/16"
2.3 Wellhead Information
2.2 Casing Data
Kelly Bushing (KB)(m)
1450.00
Tubing Head
Items
Casing spool
Size of top flange
December 17, 2011
563.066
Casing
Surface
Production
Weight
Ground Level(GL)(m) 557.866
2.0 Basic Information
2.1 Drilling Data
Max Deviation (@mKB)
KB to 9-5/8" Casing head 4.85
1.84 degree at 1302mKB 1421.97 PBTD (Landing collar)(mKB)
TVD (mKB)
Release Date
Well Name: FN-132
Type:Vertical development well
FN
January 12, 2012
Drilling Rig
Spud Date
Field Area
1.0 INTRODUCTION
DQ 43
Fula Northt-132 is proposed as a vertical development well to further evaluate the hydrocarbon potential and productivity of Bentiu and
Aradeiba reservoir in block FN.
FN-132 was spuded in on Dec 17, 2011; rig was released on Jan 12, 2012.
11"xR54
11"
OD
specification
11"X7"
JakeS-11 Completion Final Report
Top Bottom Net reservoir Net Pay thick Phi VCL Sw
(m) (m) (m) (m) % % %
Bentiu 2 1302.0 1313.0 11 10 27 16 25 Oil
Total 11 10
3.2 Test Result:
No
4.0COMPLETION PROGRAM:
4.1Completion Intervals:
Based on Mud logging and Wireline logging interpretation result, one interval of FN-132 completed in Bentiu formation
(Table 2):
Table 2 FN-132 Well Completion Plan
Formation
Zone
No.
Net reservoir Net pay
Result
Table-3 Gun Specification.
Formation Bentiu
Perforation Interval(mKB) 1302.0-1313.0
Perforate thickness(m) 11.0m
Weight of Charge 25g
Charge Name DP36RDX-3
Gun Type DP127-32-45
Shot Density 32 shots per meter
Phasing
45
o
5.0 Completion Operation Summary:-
JakeS-11 Completion Final Report
5.2.3 RIH CNLC GR/CCL/CBL/VDL
5.2.4 RIH TCP string, RIH GR/CCL and correlate depth droped the bar and perforated Bentiu:1302.0-1313.0 /11m/1zone,
Gun Type:127-32-45, DP36RDX-3 Observe
5.2.5 RIH PCP String and set anchor at:1151.1mKB, GLB300-27 stator at @1149.33mKB , No-go@1149.85mKB.
5.2.6 RIH total 147jts of 28mm sucker rod and 17Pcs of centralizers, space out 0.8m.
5.2.7 Install drive head, Connect power cable with a portable VSD device, start pump @ 25rpm, frequency 5Hz,
current:32.5A, recovered 0.45m3 of light oil in 1Hr, pump efficiency: 99%, stop pump
5.2.1 Rig move from FC-1 to FN-132
5.2.2 RIH 7 casing tool gauge to PBTD, Wash well until clean. Pressure test casing to 14MPa for 30min, OK, POOH.
anchor@1151.1mKB,
5.2.8 Make all the machines are in good and safe condition.
5.2.9 Rig down and clean well site
JakeS-11 Completion Final Report
7.2.12 Rig down and clean well site.
Note:
1. According to the workover real states on site, the program may be changed by the production superintendent and well testing
superintendent.
2. Test the pump efficiency before Rig move
7.2.4 RIH 1 jt+ anchor (7 casing) + no-go + GLB300-27 stator + pup joint + 3-1/2 EUE tubing, shallow test tubing anchor or No-
turn tools, set stator at depth 11505mKB.
7.2.5 RIH rotor with 36mm sucker rod and centralizers, one centralizer should be placed above the 2m pony rod above the rotor
head, and one centralizer after the first single jnt sucker rod and one centralizer after the second single jnt sucker rod, then each 10
Jts sucker rod and one bleow the ploshed rod and one below the adjustment pony rod .
7.2.6 Install drive head, connect frequency converter and flow line, start pump at low speed about 20rpm and increase frequency,
until un load all Completion fluid then oil come to confim the fluid type , check pump efficiency and test pressure switch and surface
line for 2.5Mpa, continuing run the pump
7.2.11 Hand over well to D&P Department.
7.2.1 Check if the polished rod is fully released (before loosening the polished rod slips, always check that the anti-reverse-rotation
braking unit is in the fully released position) and make sure the polished rod is free of any torque.
7.2.2 Remove the drive head, the integrated BOP, install service rig work spool and BOP. POOH PCP string Checking the rotor,
stator, sucker rod and report any problems in detail in the daily report.
7.2.3 RIH tubing tag sand level and report to D&P ( if sand level above 1330 mKB wash sand to PBTD)
7.0 Well Workover Procedure:-
7.1 Pre-workover job:-
7.1.1 Move in and rig up service rig according to all Petro Energys rules and regulations.
7.1.2 Check if the surface pipeline was shut and the fluid was drained completely before removing it.
7.1.3 Make sure the power for the motor was turned off.
7.2 workover operation:-
(3) RIH PCP GLB300-27.
(4) Start production and confirm the well producing pure oil .
6.1 Workover Cause:-
the well after put into production , not produce any liquid ,
6.2 Workover Objective & Requirement:-
(1) POOH the existing PCP string, checking.
(2) RIH tubing tag sand level if sand level around 1330 mKB.
3. 0Tested Result.
4. Previous Well Production Condition:
FN-132 was completed on Aug .14,2013 and put into production on but the well stop due to no flow
5.0 Previous Workover Condition:-
No workover
6.0 Workover Cause and Objective & Requirement:-
ID OD Length Depth
(mm) (mm) (m) (m)
/ / / 2.9 2.9
/ 278 1 0.28 3.18
100 121 1 0.14 3.32
100 114 119 1138.32 1141.64
100 121 1 1.26 1142.9
/ 142 0 0.1 1143
/ 110 1 6.33 1149.33
76 115 1 0.52 1149.85
76 89 1 0.29 1150.14
57 142 1 0.96 1151.1
76 89 1 0.51 1151.61
76 89 1 9.5 1161.11
NO OD(mm) QTY length(mKB) Depth (mKB)
1 1.76 1.76
2 1" (P) 38(1-1/2") 1 10.12 11.88
3 1 0.12 12
4 44 1 0.24 12.24
5 36 2 3.5 15.74
6 44 1 0.24 15.98
7 36 7 53.34 69.32
8 44 1 0.24 69.56
9 36 10 76.2 145.76
10 44 1 0.24 146
11 36 10 76.2 222.2
12 44 1 0.24 222.44
13 36 10 76.2 298.64
14 44 1 0.24 298.88
15 36 10 76.2 375.08
16 44 1 0.24 375.32
17 36 10 76.2 451.52
18 44 1 0.24 451.76
19 36 10 76.2 527.96
20 44 1 0.24 528.2
21 36 10 76.2 604.4
22 44 1 0.24 604.64
23 36 10 76.2 680.84
24 44 1 0.24 681.08
25 36 10 76.2 757.28
26 44 1 0.24 757.52
27 36 10 76.2 833.72
28 44 1 0.24 833.96
29 1-9/16" (B) X (P) 36 10 76.2 910.16
30 44 1 0.24 910.4
31 36 10 76.2 986.6
32 44 1 0.24 986.84
33 36 10 76.2 1063.04
34 44 1 0.24 1063.28
35 1-9/16" (B) X (P) 36 10 76.2 1139.48
36 1-9/16" (B) X (P) 44 1 0.24 1139.72
37 1-9/16" (B) X (P) 36 1 2.46 1142.18
38 1-9/16" (B) X 1-1/8"(B) 1 0.14 1142.32
39 1 6.62 1148.94
3-1/2" EUE tubing 3-1/2"EUE(B)(P)
Note: PCP Model:GLB300-27
Sucker Rod String(FN-132)
Description thread
X-Over 2-7/8" EUE(B)3-1/2"(P)
Anchor 2-7/8" EUE(B)(P)
X-Over 2-7/8" EUE(B)3-1/2"(P)
Lifting sub 3-1/2"EUE(B)3-1/2"(P)
X-Over
Stator 4-1/2" EU(P)(P)
No-go 4-1/2"EU(B)2-7/8"EUE(P)
3-1/2"EUE(B)x4-1/2"NU(B)
Rotor 1-1/8" (P)
36mm sucker rod: 147jts, 3-1/2" centeralizer:17pcs.
Tubing hanger 4-1/2"EUE(B)(B)
Cross over 4-1/2"EUE(B)3-1/2"(P)
3-1/2" EUE tubing 3-1/2"EUE(B)(P)
FN-132 Completion:
PCP String
Description Thread Qty.
KB-tubing spool
KB - top of polish rod
Polish rod
cross over
centrlizer 1-9/16" (B) X (P)
Pony rod 1-9/16" (B) X (P)
1" (B) X 1-9/16"(P)
centrlizer 1-9/16" (B) X (P)
sucker rod 1-9/16" (B) X (P)
centrlizer 1-9/16" (B) X (P)
sucker rod 1-9/16" (B) X (P)
centrlizer 1-9/16" (B) X (P)
sucker rod 1-9/16" (B) X (P)
centrlizer 1-9/16" (B) X (P)
sucker rod 1-9/16" (B) X (P)
centrlizer 1-9/16" (B) X (P)
sucker rod 1-9/16" (B) X (P)
centrlizer 1-9/16" (B) X (P)
sucker rod 1-9/16" (B) X (P)
centrlizer 1-9/16" (B) X (P)
sucker rod 1-9/16" (B) X (P)
centrlizer 1-9/16" (B) X (P)
sucker rod 1-9/16" (B) X (P)
centrlizer 1-9/16" (B) X (P)
sucker rod 1-9/16" (B) X (P)
centrlizer 1-9/16" (B) X (P)
sucker rod 1-9/16" (B) X (P)
centrlizer 1-9/16" (B) X (P)
sucker rod 1-9/16" (B) X (P)
centrlizer 1-9/16" (B) X (P)
sucker rod
centrlizer 1-9/16" (B) X (P)
sucker rod 1-9/16" (B) X (P)
centrlizer 1-9/16" (B) X (P)
sucker rod 1-9/16" (B) X (P)
centrlizer 1-9/16" (B) X (P)
sucker rod
centrlizer
Pony rod
cross over
226704063.xls.ms_office
10-3/4" surface casing
7" production csg
36mm sucker rod:147jts
3-1/2"EUE tbg:119jts
Anchor at:1151.1 mKB
1302 mKB
Bentiu
1313 mKB
PBTD:1421.97mKBmKB
TD:1450mKB
FN-132 Well Compltion Profile
11 m/2zones
stator(GLB300-27) at:1149.33 mKB
no-go at:1149.85mKB
Tubing end:1161.11mKB
Ground
226704063.xls.ms_office