DETAILED PROJECT PROPOSAL


I.BASIC INFORMATION

1. Project Title: Establishment of Alegria Ecological Park

2. Proponent(s)
a. Name and Signature: DOMINADOR G. ESMA, JR.
b. Designation: Municipal Mayor
c. Agency: MLGU-Alegria
d. Address: Gamuton Alegria Surigao del Norte

3. Implementing Agency

a. Partner Agency(s) PLGU Surigao del Norte
DENR-Surigao
MLGU - Alegria
4. Project Duration: January 2014 December 2019
5. Project Location: Barangay Ouano Alegria Surigao del Norte
@ 200 meters away from National Highway
6. Total Budget Requirement: Php 2.3 Million
7. Funding Source
a. PLGU - Php 2,000,000.00
b. MLGU - Php 200,000.00
c. DENR - Php 100,000.00

II. TECHNICAL DESCRIPTION
1. RATIONALE

Alegria considered as not highly urbanized municipality or town wherein the problem
of waste management is not yet on its threshold level but considering the population growth
every year, the waste problem may become alarming and it could be adversely affect the
waste disposal problems that may lead to unhealthy environment. We always had an IEC
conducted regarding the management and handling of waste but we found out that it is really
unsustainable due to the absence of a permanent disposal site and recovery facility.
So, with this proposed Eco Park establishment, really meet our needs for the solution
of our present situation now and to the upcoming problems on waste generations might be
mitigated. Here, we could consider that all gathered waste from different sources will be
processed and completely recovered.
This project will not only limit for the management of waste that has been generated
and processed in our Eco Park but also we could produce a highly organically grown
seedlings, flowers and vegetables, we could also have a good ambiance in our Tree Park and
very entertaining land developments and attractions.



2. OBJECTIVES

GENERAL
To promote and be the primary block producing municipality wherein the
primary components is from the waste-collected and has been processed.
To initiate livelihood program that would generate family income for social
and eco-transformation.
To formally utilized the area as one of the Agricultural tourist destination in
Surigao del Norte.
To properly implement the Zero Waste Management Program.
To be considered as one of the Organic Producing Municipality.

SPECIFIC
To lessen the waste disposal problem and apply the proper application of 3Rs.
To train and develop the constituents to practice proper disposal of waste
generated.
To develop a research and recreational Eco Park in Surigao del Norte.
To increase production of vegetables, flowers and seedlings and promote
organic farming method in Alegria.
To generate income from the collected entrance fees, and from the Eco Park
products such as blocks, compost, vegetables, seedlings and flowers.

3. DESCRIPTION OF THE PROJECT

Each area for implementation and verification will include different technological
approaches in agriculture and environment with the ultimate aim of integrating Organic
Agriculture and Solid Waste Management approaches.
Eco Park is established to manage all generated waste in every resident in each
barangay. These projects are made in order to uplift the sustainable environmental
management that protects public health and environment. Thus, it serves as a motivating
force to conduct this environmental related project particularly on waste segregation and
management, seeds propagation and vegetable cultivation, development of the area as a
center of Eco Tourism and Research in Alegria. And this plan will be a vital document that
serves as a guide to all Alegrianon in the community. Relative to this, all outputs will
definitely one of the innovations on conserving and preserving our ecological environment.
LGU Alegria allocates two (2) hectares of vacant lot solely for the purpose of this
Eco Park project establishment. The area is already planted with coconut and bamboo trees.
Other area has already existing trees which good for the tree park and only need enhancement
by planting diptherocarp species.
This Eco Park project enables the LGU to fully implement the Solid Waste
Management municipal wide. Bio-degradable waste turned to Bio- Organic fertilizers by
passing it to shredding machine and vermin-beds while other waste passed to hammer mill,
ball mill, and chopping machine before it is made into blocks as decorative for homes and
pathways.


To ensure availability of organic fertilizers and bio-pesticides production, the first
objective which is the establishment of organic fertilizer production is a must. It is where
composting and vermin-culture will be made.

4. PROJECT MANAGEMENT
Manpower requirement is deemed necessary for the solid waste management facility
and equipments for the operation and maintenance and for the management of nursery, Tree
Park, herbal park, Flower Park as well as the land development in the area. This is to secure,
and properly manage the said proposed project.
The said project is directly managed by the Eco Park Manager and do the immediate
supervision in the Eco Park. There will Eco Park Task Force to be formed and mobilized for
the success and security of the project operations.

5. METHODOLOGY / STRATEGIES
Well trained and fully equipped personnel shall be assigned in the operation of
machineries in all solid waste facility.
Construction of building for the nursery and solid waste implement solid
waste management municipal wide.
Bio-degredable waste turned to biogenic fertilizers by passing it to shredding
machine and vermin-beds.
Non-biodegredable waste will be processed through hand mill, ball mill and
chopping machine.

The project will be divided into the following main activities and components:
A. Formation of the Eco Park task Force with corresponding Executive Order from the
Office of the Municipal Mayor
B. Establishment of the Solid Waste Management Facility Shed
C. Establishment of Nursery
D. Establishment of tree park
E. Construction of Raised Beds for Vegetables Park
F. Establishment of Herbal Park
G. Construction of access road of the Eco Park.
6. EXPECTED GENERAL OUTPUT
Blocks and compost are the primary products of the project which is coming from the
residual and agricultural waste that has been process. There were seedling and vegetables also
because cultivation and propagation are include in the project.




7. MILESTONE

To promote sustainable solid waste management.
To promote sustainable organic farming system.

8. POTENTIAL IMPACT

a. Support Solid Waste Management Program (RA 9003) to ensure the
proper management of waste.
b. Promote, propagate, develop further and implement the practice
organic agriculture in the Philippines; and
c. Improve health condition (human, livestock and ecology)

9. USERS

1. Local Government of Alegria
2. 12 Barangays
3. Farmers
4. Policy maker


10. PROPOSED ECO-PARK OPERATIONS SCHEDULE

a. General Operating Schedule

8:00am 5:00pm Monday to Friday
9:00am 4:00 pm Saturday
Proposed Eco Park entrance fee is Php 10.00 only (but subject for an increase
anytime.)

b. Eco Training Center

Opens Monday to Fridays or depending on requested occasions or seminars.
Php 1,000.00 per day (8:00am 5pm)

c. Ecological Park Rules and Regulation

a. strictly no littering.
b. liquor, alcoholic, beverages and illegal drugs are strictly prohibited.
c. loud music is strictly prohibited.


III. PROJECT MECHANICS

This may involve with this following components:


A. Establishment of Solid Waste Management Facility

This component may accommodate with an area of 2500sq.m including with the shed
and machineries. These are the following equipments and machineries to procure for the strict
compliance of the Zero Waste Management Program in the municipality.

a. Material Recovery Facility (MRF)

This facility is very helpful to us because this could help us to segregate all
mixed waste materials for the preparation of composting and recycling. This is
the main and the center of material recovery and composting facility
operations to processed for composting, recycling prior to another stage of
processing.
There were at least 3 MRF to be established in the Eco Park segregated as
agricultural or residual waste, plastics and bottles.
The proposed designed will be concrete.
The proposed sizes of the three MRF will be 5x5m in dimension.

b. Hammer mill

Hammer mills work on the principle that most materials will crush, shatter, or
pulverize upon impact using a simple four step operation:
Material is fed into the mills chamber typically by gravity.
The material is struck by ganged hammers (generally rectangular pieces of
hardened steel) which are attached to a shaft which rotates at a high speed
inside the chamber. The material is crushed or shattered by the repeated
hammer impacts, collisions with the walls of the grinding chamber as well as
particle on particle impacts.
Perforated metal screens, or bar grates covering the discharge opening of the
mill retain coarse materials for further grinding while allowing properly sized
materials to pass as finished product.
Hard, heavy materials such as glass, stone or metals exit the mill via gravity.
Pneumatic suction we used to assist in the discharge of lighter materials such
as wood, paper or other low bulk density products.
Varying the screen size, shaft speed or hammer configuration can dramatically
alter the finished size of the product being ground. For example, faster speed,
a smaller screen, and more hammers result in a finer end product. Each
component can be changed individually or in any combination to produce the
precise grind required. All of this is determined by taking advantage of our
free test grinding service.






c. Compost Products Center

This facility is designed for compost display and market area of all compost
products. It is also a place where can be used for some trainings to all
interested participants who would do recycling and composting of solid waste.
With that, during trainings the displayed products could be used as
presentation as to prove the good support of such training output.

d. Ball Mill

A ball mill, a type of grinder, is a cylindrical device used in grinding (or
mixing) materials like ores, chemicals, ceramic raw materials and paints. Ball
mills rotate around a horizontal axis, partially filled with the material to be
ground plus the grinding medium.
The ball mill is a key piece of equipment for grinding crushed materials, and it
is widely used in production lines for powders such as cement, silicates,
refractory material, fertilizer, glass ceramics, etc. as well as for ore dressing of
both ferrous non-ferrous metals. The ball mill can grind various ores and other
materials either wet or dry. There are two kinds of ball mill, grate type and
over fall type due to different ways of discharging material. There are many
types of grinding media suitable for use in a ball mill, each material having its
own specific properties and advantages. Key properties of grinding media are
size, density, hardness, and composition.

e. Chopping Machine

A machine that chopped all collected plastics and cellophane to turned into
tiny pieces.

f. Block Making Machine

A machine that could be used as molding blocks and bricks for decorations
and floor decorative.
The proposed amount for block machine is P80, 000.00.
g. Hauling Trucks

This is to be used as garbage hauling truck covering the vicinity barangays.
The proposed truck to buy will be an elf with a proposed budget amount of P
600,000.00. this could be used as delivery trucks for the Eco Park product
such as Fertilizer, vegetables, flowers and seedlings.

h. Solid Waste Shed

The proposed dimension of the shed will be 15x30m.


The proposed designed will be semi concrete

A.1 Number of worker needed

There were only a minimum of 3- 5 workers for this component who will do and
operate the solid waste facility.
A.2 Target Output
Established Solid Waste Shed
Solid waste equipments and machineries such as Hammer mill, Ball Mill, Block
making machine, chopping machine and hauling trucks.
One Compost product center
3 MRFs
A.3 Financial Requirements

The production and implementation cost under the solid waste management including
machinery and equipment is about One Million Three Hundred eighty thousand pesos only
(PhP 1,380,000.00).

A.4 Materials required

For solid waste shed
1. hollow blocks
2. nipa shingles
3. lumber
4. reinforcing bars
For MRFs
1. Hallow blocks
2. Cement
3. Plain sheet
4. Reinforcing bars
5.

A.5 Program of Activity for Solid Waste Management Facility

Activity Bills of Materials Unit Cost /
direct cost
Total Cost Date of
Implementation
1.Site
Selection(Clearing)
Labor and
manpower

- 10,000.00


- 10,000.00

March 2014
2.Canvass of
equipments
Transportation
and handling
- 5,000.00

- 5,000.00

March 2014


3. Purchased of Project
tools and equipments

Hammer mill
Ball mill
Chopping
Machine
Block making
Machine
Hauling trucks

- 100,000.00
- 100,000.00
- 100,000.00

- 80,000.00

- 600,000.00
1,010,000.00


March 2014
4. Establishment of
Vermi Beds
- 30,000.00
30,000.00
March 2014
5. Establishment of
MRF Facility (3 units)
Materials
Labor

- 70,000.00
- 30,000.00

100,000.00

March 2014
6. Solid Waste shed Materials
Labor
- 100,000.00
- 40,000.00

140,000.00

March 2014
6.Solid Waste
Management and Eco-
park office office
Materials
Computer set
Digital cam
- 30,000.00
- 30,000.00
- 15,000.00
- 75,000.00 March 2014
7. Fences

Cyclone Wire
Labor
- 25,000.00
- 10,000.00

- 35,000.00



March 2014
TOTAL 1,380,000.00 1,380,000.00


B. ESTABLISHMENT OF NURSERY

This is the main area where all the plants being applied and tested with
compost will be stored and it is a place where young plants are raised and
taken cared of with special attention and protection.
The proposed area will be 1,500sq.m which intended for the nursery
establishment.
The proposed design of the nursery shed is semi-permanent which enclosed
with hard woods for the construction of the building.
There will also a proposed mini greenhouse in the area.
There will be a dimension of 1x3m seed bed which is elevated from the
ground.
50 seedbeds will be established in the area with a minimum of 50 seedlings in
each seed bed.


The rice hulls will be the proposed beddings of the seed bed to add protection
to the young plants that has been raised.
2,500 seedlings will be raised twice a year with different variety or species.
There were only three worker required to work in the nursery and
maintenance.
There were only minimal amount of seeds required in the nursery because we
are the one who collect seeds and only poly-ethylene cellophane will be
purchased.
The proposed seedbeds/germination beds should have 1m width with about
0.60 meter path between them consisting with three layers.
The pot beds dimension is 1.0 meter width and 5-10 meter length in order to
make weeding and manual watering easier.

B.1 Number of workers needed

There are only a minimum of 3- 5 workers for this component who will do and
maintain the Nursery facility.

B.2 Financial Requirements

The production and implementation cost under the Nursery establishment is
about Two Hundred fifty thousand pesos only (PhP 250,000.00).

B.3 Target Output

2,500 seedling twice a year will be raised
50 seed beds
1 established nursery
1 mini greenhouse
Misting facility
Established deep well

B.4 Materials Needed in the Nursery

The proposed activities in the nursery establishment will be the following:

1. Site clearing and preparation
2. Construction and development of nursery infrastructures and
facilities.
3. Design of nursery beds
4. Plotting shed
5. Fences
Proposed nursery tools



a. For extracting soil, nursery beds preparation and lay out;
1. Pick axe
2. Traditional hoe
3. Shovel
4. Hammer
5. Rake
6. Tracing line
7. Flat-pronged fork
b. For preparation of potting soil and pot filling
1. Sieve
2. Funnel/scoop
c. For watering
1. Watering cans
2. Water hose
3. Sprinklers
d. For transport
1. Wheel barrow
e. For tending of seedlings-pruning equipment and tools for pricking
out;
1. Small shovel
2. Flat piece
3. Wood
4. Spoon

B.5 Program of Activity for Nursery Facility

Activity Bills of Materials Unit Cost /
Direct cost
(Php)
Total Cost
(Php)
Date of
Implementation
1. Site Selection
(Clearing)
Labor /
manpower
- 5,000.00 - 5,000.00 March 2014
2. Purchased of
Project tools and
equipments
Nursery tools
and equipment
- 35,000.00
-
- 35,000.00 March 2014
3. Establishment of
Nursery Building
Materials
Labor
- 80,000.00
- 40,000.00
- 120,000.00 March 2014
5. Misting facility - 20,000.00 - 20,000.00 March 2014
6.Establishment of
deep well

Materials
Labor
- 35,000.00
- 15,000.00
- 50,000.00 March 2014
7.Fences Materials
labor
- 15,000.00
- 5,000.00
- 20,000.00 March 2014
TOTAL

Php 250,000.00 Php 250,000.00




C.ESTABLISHMENT OF TREE PARK

A park is an area of open space provided for recreational use. It can be in its natural or
semi-natural state, or planted, and is set aside for human enjoyment or for the protection of
wildlife or natural habitats.
The area is only need an enhancement and additional tree planting with those
hardwood species. And weeding and clearing of the existing trees also needed.

7,000 sq. m. will be the proposed area for the establishment of the LGU tree
park.
There will be a minimum of 300 trees will be planted in the area.
The spacing dimension will be 4x4m.
There should have 5 different dipterocarp species to be planted.

C.1 Number of worker needed

There were only a minimum of 1-2 workers for this component who will do and
operate the Tree Park.

C.2 Target Output

300 trees were planted and maintain

C.3 Production Cost and Implementation Cost

The production and implementation cost under tree park is about Fifty thousand pesos
only (Php 50, 000.00).

C.4 Program of Activity for Tree Park

Activity Bills of Materials Unit Cost
(Php)
Total Cost
(Php)
Date of
Implementation
1. Site Selection
(Clearing)
Labor - 5,000.00 - 5,000.00 March 2014
2. Purchase /
collection of
seedlings.
Seedlings
Transportation /
handling
- 1,000.00
- 2,000.00
- 3,000.00 March 2014
3. Tree planting

Labor - 5,000.00 - 5,000.00 March 2014
4.Gathering of
raw Materials

- 2,000.00 - 2,000.00 March 2014
5.Fencing Materials
Labor

- 30,000.00
- 10,000.00
- 40,000.00 March 2014

TOTAL

50,000.00

- 50,000.00



D. ESTABLISHMENT OF VEGETABLE PARK

1000sq.m will be the proposed area for vegetable park
A minimum of 20 plots will be prepared and planted with different variety of
vegetables.
Pure organic fertilizers and botanicals applied.

D.1 Number of Worker Needed

There were only a minimum of 3-5 workers for this component who will do and
operate the Vegetable Park.

D.2 Financial Requirements

The production and implementation cost under the solid waste management is about
Fifty thousand pesos only (Php 50,000.00).

D.3 Target Output

20 prepared plots
20 varieties of vegetable plot.

D.4 Materials Required

1. Vegetable seeds
2. Organic Fertilizers (Compost)
3. Botanicals
4. Fences (Cyclone Wire / barb wire)
5. Digging and cultivating tools
6. Sprinkler


D.5 Program of Activity for Vegetable Park

Activity Bills of Materials Unit Cost
(Php)
Total Cost
(Php)
Date of
Implementation
1. Site Selection
(Clearing)
Labor - 3,000.00 - 3,000.00 March 2014
2. Purchased of
Project tools and
seedlings
Seedlings
Tools
- 2,000.00
- 2,000.00
- 4,000.00 March 2014
3. Preparation of
plots and planting
Labor - 15,000.00 - 15,000.00 March 2014
5. Gathering of
raw Materials


- 2,000.00 - 2,000.00 March 2014
6. Fencing Materials - 20,000.00 - 26,000.00 March 2014


labor

- 6,000.00
TOTAL - 50,000.00 - 50,000.00


E.ESTABLISHMENT OF ORNAMENTAL AND FLOWERING PARK

The proposed area will be 800sq.m
There were 20 proposed plots to be prepared and planted with a good variety
which is marketable in the locality of ornamental and flowers to be planted.
Proposed flowers to be planted in the area;
a. Hybrid rose
b. Chrysanthemum with different colors
c. Babies breathe
d. Different mayana variety

E.1 Number of worker needed

There were only a minimum of 2-3 workers for this component who will do the
operation and maintenance of ornamental and flower park.

E.2 Production Cost and Implementation Cost

The production and implementation cost under the solid waste management is about
Fifty thousand pesos only (Php 50, 000.00).

E. 3 Target Output

20 prepared plots
4 plots per flower variety

E. 4 Materials Required

1. Hybrid rose, babies breathe and different mayana variety.
2. Gardening tools
3. Cyclone wire for fencing

E.5 Program of Activity for Ornamental and Flowering Park

Activity Bills of Materials Unit Cost
(Php)
Total Cost
(Php)
Date of
Implementation
1. Site Selection
(Clearing)
Labor - 3,000.00 - 3,000.00 March 2014
2. Purchased of
Project tools and
Tools
Flowers
- 2,000.00
- 10,000.00
- 12,000.00 March 2014


equipments
3. preparation of
plots and planting
labor - 10,000.00 - 10,000.00 March 2014
6. Fencing Materials
labor

- 15,000.00
- 5,000.00
- 20,000.00 March 2014

TOTAL
- 50,000.00 - 50,000.00


F. ESTABLISHMENT OF HERBAL PARK

The proposed area will be 200sq.m
There were 10 proposed plots will be planted with different variety of herbals.

F.1 Number of worker needed

There were only a minimum of 2-3 workers for this component who will operate and
maintain the Herbal Park.

F.2 Production Cost and Implementation Cost

The production and implementation cost under the solid waste management is about
twenty thousand pesos (Php 20, 000.00).

F. 3 Target Output

10 prepared plots
10 variety of Herbals


F. 4 Materials Required

1. Herbal seedlings
2. Digging and Cultivating tools
3. Sprinkler


F.5 Program of Activity for Herbal Park

Activity Bills of Materials Unit Cost
(Php)
Total Cost
Php
Date of
Implementation
1. Site Selection
(Clearing)
Labor - 1,000.00 - 1,000.00 March 2014
2. Purchased of
Project tools and
Tools
herbal
- 500.00
- 1,000.00
- 1,500.00 March 2014


equipments
3. preparation of
plots and planting
labor - 3,000.00 - 3,000.00 March 2014
6. Fencing Materials
labor

- 7,000.00
- 3,000.00
- 10,000.00 March 2014

TOTAL
- 20,000.00 - 20,000.00



G. LAND DEVELOPMENT and HUMAN ATTRACTIONS

The proposed area will be 7000 sq. m. for the construction of roads, spots and
any other development in the area.
There will be a proposed training center in the area which is surrounded with
fishpond.
Construction of Display center of all possible products in the Eco Park.
There will be Gazebo to be established.

G.1 Number of worker needed

There were only a minimum of 5-10 workers for this component who will do the
implementation and only 3 for the operation the Land development and human attractions
facility.

G.2 Financial Requirements

The production and implementation cost under the solid waste management is about
Four Hundred thousand pesos only (Php 500,000.00).


G.3 Target Output

Well constructed roads
1 training center
Fish pond
Display Center
Gazebo

G.4 Materials Required

1. Nipa shingles
2. Hallow blocks
3. Cement


4. Nails
5. Lumber
6. Water pump (for fishpond)
7. Sand and gravel
8. Fences
9. Reinforcing Bars
10. Water pump

G.5 Program of Activity for Road Construction

Activity Bills of Materials Unit Cost/
direct cost
Total Cost Date of
Implementation
1. Site Selection
(Clearing)
Labor
excavation

- 5,000.00

- 5,000.00
March 2014
2. Training center Materials
labor
- 90,000.00
- 40,000.00
- 130,000.00 March 2014
3. Fishpond materials
Labor
- 60,000.00
- 30,000.00
- 90,000.00 March 2014
4.Gazebo Materials
labor
- 30,000.00
- 15,000.00
- 45,000.00 March 2014
5.Fences Materials
labor
- 13,000.00
- 7,000.00
- 20,000.00 March 2014

TOTAL
- 290,000.00 - 290,000.00



G.3 Program of Activity for Road Construction

Activity Bills of Materials Unit Cost Total Cost Date of
Implementation
1. Site Selection
(Clearing)
Labor
excavation
- 10,000.00
- 10,000.00
- 20,000.00 March 2014
2. Purchased of
Project tools and
equipments
materials - 140,000.00 - 140,000.00 March 2014
3. construction of
roads
labor - 50,000.00 - 50,000.00 March 2014
TOTAL - 210,000.00 - 210,000.00


IV. MARKET STUDY

Primary Products Possible Market
Projected
Production
Remarks

1. Blocks
Nearby Barangays and town

200-500 blocks
quarterly.

2. Seedling (TREE) Farmers 2,500 seedling


twice a year
3. Seedling (Vegetables)
Farmers



4. Vegetables
All consumers in the
community
20-50 kls per
harvesting
period.

5. Flowers
Schools, church and
community

6. Bio- Organic Fertilizers
Farmers particularly rice
field owners.
100 bags
quarterly



V.ANALYSIS OF PROJECT OUTPUT DEMAND, AVAILABLE RESOURCES AND
NEED FOR RESOURCES.


Demand Available Resources Action/ Strategies Source of
fund
Machine operator
expert
None

Hired trainers with those kind
of specialization


LGU
Water Supply in the
area
Not yet establish in the
area

Establish deep well as source
of water in the Eco Park

PLGU
FUND
Dipterocarp species
Only falcate and Narra
available

Gather or buy seeds


DENR
Orientation seminar on
Organic farming and
application of 3Rs


Hired speakers at least two. LGU


VI. IMPLEMENTATION PLAN

Target Indicator for
Monitoring
Target /Month Completion
Date
J F M A M J J A S O N D

Solid waste
Facility

Construction
of MRF,
SW Shed
Purchase of
machineries
x


x
x December
2014
Construction x x December


Nursery
Establishment

of nursery shed
Installation of
deep well
Installation of
misting facility
Seed
propagation
Maintenance



x


x
x






x
x







x







x







x







x







x







x







x







x







x
2014

Tree Park

Tree plantation x December
2014

Flower Park

Preparation of
garden beds
Procurement
and
propagation of
flower
seedlings
Maintenance
x

x



x






x






x






x






x






x






x






x









x






x
December
2014

Herbal Park

Preparation of
garden beds
Procurement
and
propagation
Maintainance
x

x
December
2014

Land
Development
Construction
of Training
center with
Fishpond
gazebo
x
December
2014


Road
Construction
Road
Gravelling

x December
2014




VII. SUSTAINABILITY OF THE PROJECT

For the sustainability of this proposed project there should be have an implementation
of environmental laws that could resolves misery that we are facing now regarding on solid
waste and Eco Park Management.
There should be having a closure monitoring on the operation and production of the
Eco Park.
Sustainable Waste Collection in every Baranagay MRFs.
Monthly report will be prepared by the Eco Park manager upon the implementation
and operation of the Eco Park.



VIII.PROJECT IMPLEMENTATION MONITORING AND EVALUATION
SCHEME

Conduct IEC to all vicinity Barangays
Ocular site inspection and validation


IX. ECOLOGICAL PARK TASK FORCE AND MANAGEMENT

























Prepared by:

JOELITO S. SENTURIAS
MENRO- Designate


MARIBEL R. PACLIPAN
MENRO Staff

Approved by:

DOMINADOR G. ESMA, JR.
Municipal Mayor
MUNICIPAL MAYOR
MENRO DESIGNATE
MENRO-STAFF
LABORERS
SW Facility IN-CHARGE GARDENING IN-CHARGE NURSERY IN-CHARGE
ECO PARK MANAGER
ECO PARK ASSISTANTYMANAGER