Professional Documents
Culture Documents
Control of plant operating conditions has been Control of plant operating conditions has been
achieved. I.e. temperature, pressures, levels and achieved. I.e. temperature, pressures, levels and
analyses are reasonably constant or in the case of a analyses are reasonably constant or in the case of a
batch process, there is repeatability; batch process, there is repeatability;
Daily material and energy balanced can be Daily material and energy balanced can be
performed and that these agree with performed and that these agree with official official
production figures; production figures;
Product specifications are being achieved Product specifications are being achieved
consistently. consistently.
Slide 94
Need to verify
Need to verify
.
.
Physical operation, capability and capacity of plant Physical operation, capability and capacity of plant
and equipment; and equipment;
Energy and mass balance; Energy and mass balance;
Process chemistry; Process chemistry;
Efficiencies, yields and quality; Efficiencies, yields and quality;
All to specification. All to specification.
Slide 95
Acceptance
Acceptance
When the plant has met the Performance and When the plant has met the Performance and
Acceptance test requirements designed by the Acceptance test requirements designed by the
commissioning team there is usually a formal commissioning team there is usually a formal
acceptance process involving signing of acceptance acceptance process involving signing of acceptance
certificates; certificates;
Once the plant is accepted it is officially part of the Once the plant is accepted it is officially part of the
normal operations normal operations - - the responsibility of operations the responsibility of operations
and maintenance; and maintenance;
Commissioning is officially over; Commissioning is officially over;
The may still be outstanding The may still be outstanding punchlist punchlist items items
Slide 96
Acceptance Testing
Acceptance Testing
It is common practice to prove performance It is common practice to prove performance
repeatability and plant integrity as part of the repeatability and plant integrity as part of the
performance test. That is: performance test. That is:
Shutdown and Start Up the plant on several Shutdown and Start Up the plant on several
occasions and bring it up to test conditions to occasions and bring it up to test conditions to
prove repeatability. Also ramp down and ramp up prove repeatability. Also ramp down and ramp up
while online; while online;
Re Re- -inspection of critical process equipment inspection of critical process equipment - -
particularly columns to ensure they have not been particularly columns to ensure they have not been
damaged by the performance run. damaged by the performance run.
Slide 97
Commercial Significant of Acceptance
Commercial Significant of Acceptance
Formal Acceptance represents formal acknowledgment Formal Acceptance represents formal acknowledgment
that the that the
Contractor has full Contractor has full- -filled their contractual filled their contractual
obligations; obligations;
Commissioning team have full Commissioning team have full- -filled their filled their
obligations; obligations;
Completion of the Capital Project and transfer to Completion of the Capital Project and transfer to
Operations; Operations;
Expenses and costs from acceptance onwards are now Expenses and costs from acceptance onwards are now
operating expenses not capital project costs; operating expenses not capital project costs;
All subject to agreed punch All subject to agreed punch- -list items. list items.
Slide 98
Post
Post
-
-
Commissioning
Commissioning
Slide 99
Post Commissioning
Post Commissioning
Preparation and planning
Mechanical Completion
and Integrity checking
Pre-commissioning &
Operational Testing
Start Up & Initial
Operation
Performance and
Acceptance testing
Post Commissioning
From plant on From plant on- -stream to settled stream to settled
down and in regular production; down and in regular production;
Adjustments, modifications and Adjustments, modifications and
fault correction; fault correction;
Completion of outstanding Completion of outstanding
punchlist punchlist items items
Slide 100
Post Commissioning
Post Commissioning
Covers the period immediately after Acceptance; Covers the period immediately after Acceptance;
Outstanding punch Outstanding punch- -list items are completed; list items are completed;
The first routine maintenance checks are performed, The first routine maintenance checks are performed,
findings evaluated and reported; findings evaluated and reported;
Process equipment and items covered by warranty Process equipment and items covered by warranty
are scrutinized for signs of premature wear are scrutinized for signs of premature wear- -out or out or
problems; problems;
Operating data is collected and evaluated to ensure Operating data is collected and evaluated to ensure
consistent plant operations are maintained and consistent plant operations are maintained and
sustainable. sustainable.