No. BID ITEMS UNIT QTY UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT
1 Mobilization (3.5% Maximum) 1 LS 42,737.00 $ 42,737.00 $ 65,000.00 $ 65,000.00 $ 25,000.00 $ 25,000.00 $
2 Maintenance of Traffic (1.5% Maximum) 1 LS 19,500.00 $ 19,500.00 $ 26,000.00 $ 26,000.00 $ 10,000.00 $ 10,000.00 $
3
F&I 3 Communication Conduit HDPE DR11 Pipe by
Horizontal Directional Drill 1,150 LF 9.50 $ 10,925.00 $ 25.00 $ 28,750.00 $ 12.00 $ 13,800.00 $
4
F&I 6 Sanitary Sewer Force Main HDPE DR11 Pipe
by Horizontal Directional Drill 900 LF 23.90 $ 21,510.00 $ 40.00 $ 36,000.00 $ 32.00 $ 28,800.00 $
5
F&I 6 Backwash Water HDPE DR11 Pipe by
Horizontal Directional Drill 1,200 LF 23.90 $ 28,680.00 $ 40.00 $ 48,000.00 $ 30.00 $ 36,000.00 $
6
F&I 8 Raw Water HDPE DR9 Pipe by Horizontal
Directional Drill 420 LF 35.00 $ 14,700.00 $ 55.00 $ 23,100.00 $ 56.00 $ 23,520.00 $
7
F&I 8 Raw Water HDPE DR11 Pipe by Horizontal
Directional Drill 1,300 LF 32.60 $ 42,380.00 $ 55.00 $ 71,500.00 $ 54.00 $ 70,200.00 $
8
F&I 8 Potable Water HDPE DR11 Pipe by Horizontal
Directional Drill 300 LF 32.60 $ 9,780.00 $ 55.00 $ 16,500.00 $ 48.00 $ 14,400.00 $
9
F&I 8 Concentrate Water HDPE DR11 Pipe by
Horizontal Directional Drill 1,800 LF 32.60 $ 58,680.00 $ 55.00 $ 99,000.00 $ 43.00 $ 77,400.00 $
10
F&I 12 Raw Water HDPE DR11 Pipe by Horizontal
Directional Drill 1,250 LF 53.00 $ 66,250.00 $ 78.00 $ 97,500.00 $ 67.00 $ 83,750.00 $
11
F&I 22 Horizontal Directional Drill with 8
Concentrate Water HDPE DR9 Pipe, 6 Backwash
Water HDPE DR9 Pipe and 3" Communication
Conduit HDPE DR9 Pipe 2,070 LF 245.00 $ 507,150.00 $ 300.00 $ 621,000.00 $ 74.50 $ 154,215.00 $
12
F&I 22" Horizontal Directional Drill with 8
Concentrate Water HDPE DR9 Pipe, 6 Backwash
Water HDPE DR9 Pipe and 3" Communication
Conduit HDPE DR9 Pipe 200 LF 7.00 $ 1,400.00 $ 35.00 $ 7,000.00 $ 7.50 $ 1,500.00 $
13
F&I 22" Horizontal Directional Drill with 8
Concentrate Water HDPE DR9 Pipe, 6 Backwash
Water HDPE DR9 Pipe and 3" Communication
Conduit HDPE DR9 Pipe 20 LF 31.00 $ 620.00 $ 65.00 $ 1,300.00 $ 53.00 $ 1,060.00 $
14 F&I 6 Backwash Water HDPE Pipe by Open Cut 130 LF 27.50 $ 3,575.00 $ 75.00 $ 9,750.00 $ 20.00 $ 2,600.00 $
15
F&I 6 Sanitary Sewer Force Main DI Pipe by Open
Cut 20 LF 123.00 $ 2,460.00 $ 300.00 $ 6,000.00 $ 148.00 $ 2,960.00 $
16 F&I 6 Backwash Water DI Pipe by Open Cut 110 LF 57.00 $ 6,270.00 $ 85.00 $ 9,350.00 $ 50.00 $ 5,500.00 $
17 F&I 8 Potable Water HDPE Pipe by Open Cut 15 LF 49.00 $ 735.00 $ 75.00 $ 1,125.00 $ 36.00 $ 540.00 $
18 F&I 8 Raw Water HDPE Pipe by Open Cut 170 LF 30.00 $ 5,100.00 $ 80.00 $ 13,600.00 $ 22.00 $ 3,740.00 $
19 F&I 8 Concentrate Water HDPE Pipe by Open Cut 120 LF 30.00 $ 3,600.00 $ 75.00 $ 9,000.00 $ 22.00 $ 2,640.00 $
20 F&I 8 Concentrate Water DI Pipe by Open Cut 150 LF 67.00 $ 10,050.00 $ 110.00 $ 16,500.00 $ 105.00 $ 15,750.00 $
21 F&I 12 Raw Water HDPE Pipe by Open Cut 20 LF 40.00 $ 800.00 $ 75.00 $ 1,500.00 $ 44.00 $ 880.00 $
22 F&I 12 Raw Water DI Pipe by Open Cut 50 LF 95.00 $ 4,750.00 $ 200.00 $ 10,000.00 $ 90.00 $ 4,500.00 $
23 F&I 6 Restrained J oints for HDPE Pipe 8 EA 552.00 $ 4,416.00 $ 225.00 $ 1,800.00 $ 105.00 $ 840.00 $
24 F&I 6 Restrained J oints for DI Pipe 34 EA 155.00 $ 5,270.00 $ 150.00 $ 5,100.00 $ 55.00 $ 1,870.00 $
25 F&I 8 Restrained J oints for HDPE Pipe 54 EA 578.00 $ 31,212.00 $ 225.00 $ 12,150.00 $ 133.00 $ 7,182.00 $
26 F&I 8 Restrained J oints for DI Pipe 20 EA 150.00 $ 3,000.00 $ 150.00 $ 3,000.00 $ 54.00 $ 1,080.00 $
27 F&I 12 Restrained J oints for HDPE Pipe 2 EA 996.00 $ 1,992.00 $ 325.00 $ 650.00 $ 203.00 $ 406.00 $
28 F&I 12 Restrained J oints for DI Pipe 6 EA 223.00 $ 1,338.00 $ 250.00 $ 1,500.00 $ 92.00 $ 552.00 $
29 F&I 16 Restrained J oints for DI Pipe 10 EA 840.00 $ 8,400.00 $ 650.00 $ 6,500.00 $ 512.00 $ 5,120.00 $
30 F&I Compact DI Fittings 2,500 LB 5.30 $ 13,250.00 $ 12.50 $ 31,250.00 $ 8.20 $ 20,500.00 $
31 F&I 6 Resilient Wedge Gate Valve & Valve Box 5 EA 1,110.00 $ 5,550.00 $ 1,600.00 $ 8,000.00 $ 963.00 $ 4,815.00 $
32 F&I 8 Resilient Wedge Gate Valve & Valve Box 9 EA 1,408.00 $ 12,672.00 $ 2,000.00 $ 18,000.00 $ 1,283.00 $ 11,547.00 $
33 F&I 12 Resilient Wedge Gate Valve & Valve Box 2 EA 2,418.00 $ 4,836.00 $ 3,200.00 $ 6,400.00 $ 2,138.00 $ 4,276.00 $
34
F&I 17" x 30" Pull Boxes for Communication
Conduits 10 EA 2,200.00 $ 22,000.00 $ 4,000.00 $ 40,000.00 $ 980.00 $ 9,800.00 $
WTP #2 - CONTRACT 2: RAW WATER TRANSMISSION MAIN US19 CROSSING PROJECT - 10-0039-UT-(B)
THURSDAY, FEBRUARY 28, 2013 AWARD - THURSDAY, MARCH 21, 2012
WESTRA CONSTRUCTION YOUNGS COMMUNICATION HARRIS-MCBURNEY
BID
No. BID ITEMS UNIT QTY UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT
WTP #2 - CONTRACT 2: RAW WATER TRANSMISSION MAIN US19 CROSSING PROJECT - 10-0039-UT-(B)
THURSDAY, FEBRUARY 28, 2013 AWARD - THURSDAY, MARCH 21, 2012
WESTRA CONSTRUCTION YOUNGS COMMUNICATION HARRIS-MCBURNEY
34A
F&I 30" X 48" Pull Boxes for Communication
Conduits 2 EA 3,597.00 $ 7,194.00 $ 5,000.00 $ 10,000.00 $ 2,004.00 $ 4,008.00 $
35 F&I Combination Air Valve - Type I 7 EA 2,893.00 $ 20,251.00 $ 5,500.00 $ 38,500.00 $ 2,536.00 $ 17,752.00 $
36 F&I Combination Air Valve - Type II 5 EA 2,765.00 $ 13,825.00 $ 5,000.00 $ 25,000.00 $ 2,405.00 $ 12,025.00 $
37 F&I Combination Air Valve - Type III 5 EA 2,360.00 $ 11,800.00 $ 4,000.00 $ 20,000.00 $ 1,887.00 $ 9,435.00 $
38 F&I Combination Air Valve - Type IV 1 EA 5,471.00 $ 5,471.00 $ 7,500.00 $ 7,500.00 $ 4,662.00 $ 4,662.00 $
39 F&I Combination Air Valve - Type V 1 EA 9,753.00 $ 9,753.00 $ 11,000.00 $ 11,000.00 $ 9,500.00 $ 9,500.00 $
40 Root Pruning 1,000 LF 7.00 $ 7,000.00 $ 3.50 $ 3,500.00 $ 3.00 $ 3,000.00 $
41 Tree Barricades 1 LS 13,800.00 $ 13,800.00 $ 7,000.00 $ 7,000.00 $ 1,025.00 $ 1,025.00 $
42 Remove Trees 7 EA 700.00 $ 4,900.00 $ 1,800.00 $ 12,600.00 $ 448.00 $ 3,136.00 $
43
Disconnect Existing 8" WM fromExisting 16" WM at
North Side of S.R. 60 (Sheet C02) 1 LS 1,948.00 $ 1,948.00 $ 6,000.00 $ 6,000.00 $ 500.00 $ 500.00 $
44
Tapping of Existing 8" WM with 8"x8" Tapping
Sleeve and Valve at North Side of S.R. 60 (Sheet C02) 1 0 4,978.00 $ 4,978.00 $ 8,500.00 $ 8,500.00 $ 4,125.00 $ 4,125.00 $
45
Reconnections to Existing 16" RWM and Existing 16"
WM North of Well #53 (Sheet C02) 1 LS 18,400.00 $ 18,400.00 $ 50,000.00 $ 50,000.00 $ 31,138.00 $ 31,138.00 $
46
g g
Brackish RWM to Proposed 8" Fresh RWM (Sheet
C04) 1 LS 5,484.00 $ 5,484.00 $ 12,000.00 $ 12,000.00 $ 5,300.00 $ 5,300.00 $
47
Video Inspect6ion, Pigging, Flushing, Hydrostatic
Testing and Disinfection of Existing 16-inch Piping 3000 LF 9.40 $ 28,200.00 $ 25.00 $ 75,000.00 $ 10.50 $ 31,500.00 $
48
Sod Restoration as Directed by the Owner or the
Owner's Authorized Project Representative 500 SY 4.60 $ 2,300.00 $ 3.00 $ 1,500.00 $ 4.54 $ 2,270.00 $
49
Concrete Driveway Restoration as Directed by the
Owner or the Owner's Authorized Project
Representative 200 SY 43.00 $ 8,600.00 $ 50.00 $ 10,000.00 $ 42.32 $ 8,464.00 $
50
Concrete Sidewalk Restoration as Directed by the
Owner or the Owner's Authorized Project
Representative 200 SY 40.00 $ 8,000.00 $ 48.00 $ 9,600.00 $ 42.32 $ 8,464.00 $
51
Concrete Curb Restoration as Directed by the Owner
or the Owner's Authorized Project Representative 200 LF 25.00 $ 5,000.00 $ 25 5,000.00 $ 26.50 $ 5,300.00 $
52
Underdrain Restoration as Directed by the Owner or
the Owner's Authorized Project Representative 200 LF 18.00 $ 3,600.00 $ 22 4,400.00 $ 16.50 $ 3,300.00 $
53
Asphalt Paving Restoration as Directed by the Owner
or the Owner's Authorized Project Representative 500 SY 30.00 $ 15,000.00 $ 32 16,000.00 $ 22.00 $ 11,000.00 $
54
Unsuitable Material Excavation Below Grade as
Directed by the Owner or the Owner's Authorized
Project Representative 500 CY 5.00 $ 2,500.00 $ 11.00 $ 5,500.00 $ 12.00 $ 6,000.00 $
55
Select Backfill Below Grade as Directed by the Owner
or the Owner's Authorized Project Representative 500 CY 15.00 $ 7,500.00 $ 18.00 $ 9,000.00 $ 25.00 $ 12,500.00 $
56
Asphalt Overlay as Directed by the Owner or the
Owner's Authorized Project Representative 500 SY 40.00 $ 20,000.00 $ 35.00 $ 17,500.00 $ 17.00 $ 8,500.00 $
1,201,092.00 $ 1,716,925.00 $ 849,647.00 $
57 Owners 10% Contingency 1 LS 120,109.20 $ 171,692.50 $ 84,964.70 $
1,321,201.20 $ 1,888,617.50 $ 934,611.70 $
Subtotal Construction Costs (Bid Items Nos. 1 - 56)
Bidders Grand Total (Bid Items Nos. 1 - 57)