Drawworks Lowering
Check fuel level in fuel tanks. Should be good enough to run engines.
Check VFD, Two Generators must be on line.
Check Drawworks clutch air pressure. Air Pressure should be above
100 Psi.
Check at least one Air compressor should be running with required air
pressure and other unit ready to start.
Check the functioning of hydraulic power unit (HPU) of Drawworks
braking system and its oil level.
Check the functioning of Drawworks braking system.
Make sure cooling water is running to circulating to HPU, DWKS and
Elamagco Brake.
Check Drawworks and Auxiliary brake Linkage is engaged (must be
Engaged).
Check proper greasing of all sheaves (A-Frame, Mast, Crown block;
Drawworks frame).Observe the pulleys while lowering mast, make sure
pulley are rotating when lowering DWKS.
Check raising line properly wrapped in sheaves and line guards
properly inserted.
Check all drilling floor foldable/removable covers (drawworks side) have
been folded/removed, to avoid any interference during drawworks
lowering.
Check Grasshopper properly fixed, free from any obstacles. One
person should keep eye on grasshopper cables while lowering DWKS.
Make sure all cables/ Hoses around /under DWKS are free from any
obstruction with any beam or Pipe.



Author : P.
Kashirskiy /
G. Gonsalves / I. Barkat
DWKS and Mast
Lowering
REF: Drillmec Checklist
Checked By: Sanjeev
Kapoor
Checklist
Page 2 of 4
Approved By: Azzedine
Smida

Issued: April 2011

RIG- IDC 36,37,38
Version 1.0











Check the functioning of Main HPU for Hydraulic Jack (Snubbing Unit)
to push the DWKS for lowering.
Make sure that the Pins on DWKS side of BOP Trolley beams are fully
IN from DWKS side to facing Mast side. These Pins may get stuck at
the lowering point with cross H Beam if not fully In.
Ensure that the RT beams remain pinned to mast side. The pins on
DWKS side should be removed.
Removed the water inlet line, Elamagco side, as its get tension with
DWKS raising line.
Make sure remove 02 each diagonal H beams below DWKS (01 DS
and 01 ODS)
Check proper connection of dead line anchors load cell and weight
indicator.
One crane should be ready on Driller side and one crane should be
ready off driller side, in case of some problem.
Safety meeting.
Check the only presence of authorized personnel surrounding rig down
area.



DWKS LOWERING START: ....................
DWKS LOWERING STOP: ....................
MAX LOAD: ....................






Author : P.
Kashirskiy /
G. Gonsalves / I. Barkat
DWKS and Mast
Lowering
REF: Drillmec Checklist
Checked By: Sanjeev
Kapoor
Checklist
Page 3 of 4
Approved By: Azzedine
Smida

Issued: April 2011

RIG- IDC 36,37,38
Version 1.0











Mast Lowering


After Drawworks lowering, its required the execution of the following
operations:

Make sure the raising lines has been changed from DWKS to Mast
Lowering Position (raising line properly wrapped in sheaves)
Make sure that front cover of DWKS has been removed. Drill Line will
touch with front cover, if not removed while lowering Mast.
Check proper installation of all pins and related sheave pins.
Check the functioning of Mast snubbing cylinders with main HPU.
Make sure the derrick board plat form is fold back and secured with
rope properly. If not, block will touch to the center working platform of
Derrick man.
Check absence of any interference with pipes and electrical cables.
Make sure the TDS Loops are free hanging. If the end of loops left on
rig floor, it will fall down to the ground during lowering.
Make sure the TDS Torque tube (Monorail) hang off link is secured on
the crown block.
Make sure the main Tie back beam of TDS on main Spreader beam is
secured. If loose, will fall down during mast lowering.
Check proper installation of high Hose stand.
Check the presence of utilities around rig up area (one crane on Driller
side and 2
nd
crane off driller side should be available).
Place one section of catwalk 5ft from setback level for Travelling Block
to set down on.



Author : P.
Kashirskiy /
G. Gonsalves / I. Barkat
DWKS and Mast
Lowering
REF: Drillmec Checklist
Checked By: Sanjeev
Kapoor
Checklist
Page 4 of 4
Approved By: Azzedine
Smida

Issued: April 2011

RIG- IDC 36,37,38
Version 1.0











Team of two operators, A/D & Derrick man in charge by Rig
Manager/Tool Pusher, must check all rig components (mast, crown
block, racking board, casing stabbing board, belly board, rest platforms
and caged ladders, tong counterweights, and all completions) to avoid
the presence of:
Un-tightened bolts;
Bolts, wrenches, cables and any objects not fixed that could fall
during mast lowering.
If any component nut/bolt/ spanners fell down from mast, during
lowering, the two persons inspected the mast will be responsible.
Make sure that both mast legs area is clear from underneath, when the
mast legs will be close to floor plates at lowering position.
Ensure to remove all air hoists from rig floor and make sure that the
base of air hoist on the driller side is removed. The mast leg will touch it
if not removed.
Have winch truck (kenworth) standing by in case snubbing unit is
unable to push the mast.
Safety meeting.
Check the only presence of authorized personnel surrounding mast
lowering area.


MAST LOWERING START: ....................
MAST LOWERING STOP: ....................
MAX LOAD: ....................



Author : P.
Kashirskiy /
G. Gonsalves / I. Barkat
DWKS and Mast
Lowering
REF: Drillmec Checklist
Checked By: Sanjeev
Kapoor
Checklist
Page 5 of 4
Approved By: Azzedine
Smida

Issued: April 2011

RIG- IDC 36,37,38
Version 1.0











The Rig manager shall choose suitable operators to follow this task:
Driller:
Name_____________ Signature_____________

Chief Electrician in charge to check the generators and set all electrical parts.
Name_____________ Signature_____________

Chief Mechanic in charge to control Masts snubbing cylinder.
Name_____________ Signature_____________

Verify that in the perimeter surroundings the raising area doesnt have any
obstacles for an emergency escapes.

Place: _______________________________
Date: _______________________________
Tool Pusher: _______________________________
Rig Manager: _______________________________

You might also like