Based on Managing Successful Projects with PRINCE2, by the Cabinet
Office. Text in italics is from Managing Successful Projects with PRINCE2 Crown copyright 2009. Reproduced under licence from the Cabinet Office Simplilearn Solutions Agenda What are the Themes? The PRINCE2 Themes Applying the Themes Format of the Themes Simplilearn Solutions What are the Themes? The PRINCE2 themes describe aspects of project management that must be addressed continually.
Any project manager who gives thorough attention to these themes will fulfill the role in a professional manner. Simplilearn Solutions Theme Answers Describes Business Case Why? Justification for undertaking the project Organisation Who? Roles and Responsibilities Quality What? Quality attributes of the product to be delivered Plans How? How much? When? The steps required to develop plans and apply PRINCE2 techniques. The control and communication mechanisms. Risk What if? The plans for managing uncertainties Change What's the impact? The steps for assessing impact of change and managing the change Progress Where are we now? Where are we going? Should we carry on? Decision-making process for approving plans and monitoring the actual performance The PRINCE2 Themes Simplilearn Solutions Applying the Themes All seven themes must be applied in a project but they should be tailored according to the scale, nature and complexity of the project concerned.
Themes can be tailored up or down. Simplilearn Solutions Format of the Themes Purpose Theme definition The PRINCE2 approach to the theme Responsibilities Simplilearn Solutions Quiz Match the two columns. S.No. Column 1 S.No. Column 2 1 Which PRINCE2 theme ensures that there is an escalation process in place if things do not go according to the project plan? A Plans 2 Which PRINCE2 theme ensures that projects proceed on the basis of a series of approved plans? B Organisation 3 The ____________ theme describes the roles and responsibilities in the PRINCE2 project management team required to manage the project effectively. C Change 4 Which PRINCE2 theme ensures that there is an plan to manage uncertainties'? D Progress 5 The ____________ theme describes the steps for assessing impact of change and managing the change. E Risk
Answer: 1-D, 2-A, 3-B, 4-E, 5-C Simplilearn Solutions Quiz-1 1. Which PRINCE2 theme ensures that there is an escalation process in place if things do not go according to the project plan?
A. Plans B. Organisation C. Change D. Progress Simplilearn Solutions Quiz-2 2. Which PRINCE2 theme ensures that projects proceed on the basis of a series of approved plans? A. Plans B. Change C. Progress D. Risk Simplilearn Solutions Quiz-3 3. The ____________ theme describes the roles and responsibilities in the PRINCE2 project management team required to manage the project effectively. A. organisation B. risk C. plans D. progress Simplilearn Solutions Quiz-4 4. Which PRINCE2 theme ensures that there is an plan to manage uncertainties? A. Business case B. Change C. Progress D. Risk Simplilearn Solutions Quiz-5 5. The ____________ theme describes the steps for assessing impact of change and managing the change.
A. progress B. organisation C. plans D. change Simplilearn Solutions Quiz-1 1. Which PRINCE2 theme ensures that there is an escalation process in place if things do no go according to the project plan?
A. Plans B. Organisation C. Change D. Progress Correct answer: D Progress theme ensures that there is an escalation process. Simplilearn Solutions Quiz-2 2. Which PRINCE2 theme ensures that projects proceed on the basis of a series of approved plans? A. Plans B. Change C. Progress D. Risk Correct answer: A Plans theme ensures that a project proceeds on the basis of series of approved plans. Simplilearn Solutions Quiz-3 3. The ____________ theme describes the roles and responsibilities in the PRINCE2 project management team required to manage the project effectively. A. organisation B. risk C. plans D. progress Correct answer: A PRINCE2 organisation theme describes the roles and responsibilities. Simplilearn Solutions Quiz-4 4. Which PRINCE2 theme ensures that there is an plan to manage uncertainties? A. Business case B. Change C. Progress D. Risk Correct answer: D PRINCE2 risk theme ensures that there is a plan to manage uncertainties. Simplilearn Solutions Quiz-5 5. The ____________ theme describes the steps for assessing impact of change and managing the change.
A. progress B. organisation C. plans D. change Correct answer: D PRINCE2 change theme describes the steps for assessing impact of change and managing the change. Simplilearn Solutions Thank You Simplilearn Solutions