MINUTES OF THE WEEKLY PROGRESS REVIEW MEETING ON 4th December 2009

PRESENT

SAPL Agencies
Subhash C Singh, Ray Construction- Mr.Anil, Mr. Kutty.
Y.P.Singh. Krishna Construction: Mr.Phatak.
Nilesh Patel Venu Engineers- Mr. Jasmin.
Umesh Yadav Laxman Appa & Co. – Mr.Joshi
A.N.Pandye MCK Kutty- Abdul Razak
Ashok Kumar Universal Enterprises- Mr. Paul.
Shoaib Mulla VKS Project- Mr Girish.
Vivek Pawar
Ravi Dhotre.

REVIEW OF CIVIL WORKS

1. RAY CONSTRUCTION.

1
EARLIER
SR. REVISED
UNIT ACTIVITY COMMITMEN REMARKS
NO COMMITMENT
T
1 Shifting of labour Up to 6.12.09 Up to 10.12.09 In progress
- hutment
2 Increase of By 10.12.09
manpower up Existing manpower is
to 400 by 349.
6.12.09
- -

3 Scaffolding 1st load to arrive 6.12.09


Material 2nd loadto arreve
8.12.09
runners

9.12.09
4 Stock House. A) Completion of 5.12.09 7.12.09
3rd&4th hoppers

B)Completion of 13.12.09 13.12.09 56 Labors deployed in


5th,6th&7th hoppers Stock House,
Agreed to increase to 73
C) Completion of 5 from 1.12.09
hoppers and slab In
part-2 15.1209- 25.12.09
19.12.09
D) Stair case of Skip
Pit 29.11.09- 15.12.09-19.12.09
3.12.09

E) 1st Slab of Skip Pit 6.12.09-13.12.09


8.12.09
F) 2nd slab of skip pit.
25.12.09
G) Bottom 25.12.09
Foundation of 2nd
Part
10.12.09
H) Bottom 30.11.09
Foundation of 1stPart
15.12.09
15.12.09

5 Cast House Mudgun Room Slab 29.11.09 completed


Back Filling of Cast Partially completed and
House area 30.11.09 In progress further put on hold
.
6 B.F.Pump A)Columns of one 30.11.09 completed
House row

B) Wall up to ground 07.12.09 07.12.09


level
2
C) Column of Second 10.12.09 10.12.09 Agency committed to
Row arrange 8 sleeves by
2 VENU ENGINEERS.

SR. EARLIER REVISED


UNIT ACTIVITY REMARKS
NO COMMITMENT COMMITMENT
1 Manpower A)Increase of 200nos Deployed 157 Agreed to
manpower increase
further 25
nos. by
5.12.09
2 Blower House A)Completion
of columns
completed
D-row 22.11.09
C-row 26.11.09 30.11.09

B)Back filling
with 1512.09
compaction

C)Deshutterin 5.12.09 5.12.09


g

D) Gable end 15.12.09 5.12.09-15.12.09


in totality

E)Tie beam, 30.11.09-


plat-form & 15.12.09 5.12.09-20.12.09
brick work
3 Electrical A) Brick Work 7.12.09 10.12.09
Distribution &
Room 1st Slab
Casting

B) Brick work 15.12.09- 15.12.09-25.12.09


2nd Slab of 1st 25.12.09
Part

4 Compressor A) PCC 30.11.09 7.12.09


House

B) RCC up to 2.12.09 10.12.09


G.L

C) RCC column 15.12.09


up to slab
level

3
D) Brick work 30.12.09 30.12.09
& Slab

5 C.A.Fan A) 2nd foundation


PCC 7.12.09
B) RCC 15.12.09
C)
D) 2nd slab 12.12.09 15.12.09
casting 25.12.09

6 E) Laboratory F) A)-1.2mtr I) 28.11.09 J) 6.12.09 L)


Building level K)
G)
H) B) Up to G.L. 15.12.09 6.12.09-
15.12.09
C) Brick Work ---
plus
Slab Casting 25.12.09 25.12.09

7 M) Raw Water N) 3rd lift up to 02.12.09 6.12.09


Reservoir 3.4 m level
14.12.09
TH
4 lift
23.12.09
5th lift

6th lift 30.12.09


Completion
FF Tank Raft 31.12.09
Two tanks
8 ODPL Trestle A) PCC Will start Will start 20.12.09
Foundation 30.11.09 10.12.09
B) 2nd pocklain
will arrive on 5.12.09
site
C) All bolts by 20.12.09
9 RMHS Tunnel PCC Will start by Electrical
7.12.09 point
provided on
5.12.09

2. KRISHNA CONSTRUCTION

SR. EARLIER REVISED


UNIT ACTIVITY REMARKS
NO COMMITMENT COMMITMENT
1 Admin Casting of 1st ……………… 28.11.09 Completed

4
Building slab
2nd slab ................ 18.12.09

Brickwork Will start Agency will


15.12.09 submit brick
sample

3rd slab 10.01.10 10.01.10

The agency was asked to increased the manpower for SGP and Water Treatment Plant where works
Are lagging behind the schedule. The agency requires at least 60 manpower in SGP and &70 in WTP.
The agency will submit the plan for increasing the manpower.
It is felt shortage of other resources like pipes and shuttering materials.
The completion schedule of SGP & WTP will be discussed with the agency separately in totality.

4LAXMAN APPA & CO. ( Representative absent.)


Improvement in the working of agency is observed with increase of manpower

EARLIER REVISED
SR.
UNIT ACTIVITY COMMITME COMMIT REMARKS
NO
NT MENT
1 Structural Foundation A)All column ……………… 10.12.09 In progress
Equipment foundation foundation
1
2

B) Equipment …………….. 16.12.09


foundation.

3 UG Tank near C-grid Casting ………………. 27.12.09

4 Detail
programme for
PCC & RCC with
concrete
quantity
submitted.

5. ASSET CONSTRUCTION (MSEB) (Representative absent)


5
EARLIER REVISED
SR.
UNIT ACTIVITY COMMITME COMMIT REMARKS
NO
NT MENT
1 Out door foundation 35Bolt lift ………………. 07.12.09 200 bolts
completion received out of
500 bolts.
15.12.09
Balance 27 Available bolts
bolts are sufficient for
35 bolt lift.
2 Control Room 1st slab 30.11.09 08.12.09
Brick work ……………. 2.12.09 to
15.12.09
3

STRUCTURAL & EQUIPMENT WORK


1. MCK Kutty :

A) Erection:
Activities Target Date
rd
Erection of 4 poles 3 part agreed to start from 6.12.09
Erection of stock house structure agreed to start from 5.12.09
Head ESP- shifting of equipment to site. By 5.12.09
Main building structure 7.12.09
Checkered supporting system of HBS-1 completion 8.12.09
Chucker supporting system of HBS-2 start 10.12.09
Erection of stave cooler to start from 7.12.09
Stair to access BF building by 5.12.09

2. UNIVERSAL ENTERPRIZES:
Activities Target Date
Radiography 5.12.09
HBS Stove no. 2 Earlier Commitment 06.12.09 Revised Commitment 07.12.09
HBS Stove no. 3 Earlier Commitment 10.12.09 Revised Commitment 14.12.09
Pressure Testing of stoves 12.12.09 Planned to start
Grouting in all HBS 9.12.09, on that day all structural works in HBS will remain clos.ed
Screening room & crushing room Sr. GM Project warned to agency if progress will not improved
by Monday further work will not given to agency.
Mixing chamber 2nd shell erection 10.12.09
3rd & 4th uptake 5.12.09

3. LAXMAN APPA AND COMPNAY:


Activities Target Date.
Fabrication programme
Month Dec-09 250 tones

6
Erection of oxygen plant to start 16.12.09
Agency committed to bring crane on 7.12.09 for erection of structures in Cast House, Blower House <Galleries
And chimney inSP where fronta are ready.

4. VKS PROJECTS:

Activities Target Date


Manpower Committed to increase up to 30 nos
Sr. GM Project suggested Mr. Girish to discuss with his M.D. about increase manpower to 50. As they have to do
fabrication at the rate of 200t /month