You are on page 1of 35

TECHNICAL PROPOSAL

FOR
STORAGE TANKS
DATE : J une 18, 10
REV.0


S-Tank Engineering Co., Ltd.
S-TANK ENGINEERING






REQUISITION (CONSTRUCTION)

for

STORAGE TANKS

of

JG Summit Naphtha Cracker Project

in

Batangas, Philippines



Client : JG Summit Petro. Corp.
STE Proposal No. : STE-PROP-10-080-002 (Rev.0)





June 18, 2010 (Rev.0)







TECHNICAL PROPOSAL
FOR
STORAGE TANKS
DATE : June 18, 10
REV.0


S-Tank Engineering Co., Ltd.
S-TANK ENGINEERING





CONTENTS

1. Tank Item List

2. Scope of Supply and Work

3. General Assembly Drawings

4. Project Schedule

5. Painting Specification










TECHNICAL PROPOSAL
FOR
STORAGE TANKS
DATE : J une 18, 10
REV.0


S-Tank Engineering Co., Ltd.
S-TANK ENGINEERING







1. Tank Item List
























TECHNICAL PROPOSAL
FOR
STORAGE TANKS
DATE : J une 18, 10
REV.0


S-Tank Engineering Co., Ltd.
S-TANK ENGINEERING

1. Tank Item List

No Item Product Type
Qt'y
(Set)
Capacity
(/1-Tank)
Size
Main
Material
Dia(mm)
HT (mm)
(G.L to CL)
1 D-0407
Flux Oil

CRT 1 154 5,500 6,500 A283-C
2 D-0516
Wash Oil

CRT 1 411 8,300 7,600 A283-C
3 D-3001A/B
FRN

SDFRT 2 46,770 55,120 19,900
4 D-3021
Raw
Pyrolysis
Gasoline
CIFRT 1 10,615 26,160 19,750
A573-70
A283-C
5 D-3022
Pyrolysis
Gasoline
CRT 1 15,884 32,000 19,750 A283-C
6 D-3031
Pyrolysis
Fuel Oil
CRT 1 471 9,000 7,400 A283-C
7 D-3051
Fresh
Caustic
CRT 1 199 5,850 7,400 A516-60
8 D-3052
Caustic
Day
CIFRT 1 33 2,950 4,900 A283-C
9 D-3141
Desalinated
water
CRT 1 5,360 20,000 17,060 A283-C
10 D-3151
Demi. Water

CRT 1 2,940 16,000 14,620 A283-C
11 D-3201
Spent
Caustic
CRT 1 735 9,750 9,850 A516-60
Total 12




TECHNICAL PROPOSAL
FOR
STORAGE TANKS
DATE : J une 18, 10
REV.0


S-Tank Engineering Co., Ltd.
S-TANK ENGINEERING







2. Scope of Supply and Work
























TECHNICAL PROPOSAL
FOR
STORAGE TANKS
DATE : J une 18, 10
REV.0


S-Tank Engineering Co., Ltd.
S-TANK ENGINEERING
2. Scope of Supply and Work

[ Classification ] :
( S ) Mark means STEs scope
( V ) Mark means Vendors scope
( X ) Mark means out of STEs scope

2.1 Scope of Supply

( S ) Equipment proper
( S ) Internal and external accessories indicated on Inquiry
( S ) Clips for platform/ladder/pipe support directly welded on equipment
( S ) Internal support
( S ) Bolts/nuts, clamps, gaskets for internal
( S ) Blind flanges together with bolts/nuts and gaskets for blinded nozzles & manholes
( S ) Davits and/or hinge for manholes
( S ) Vortex breaker (if required)
( S ) Insulation support rings (required Tank)
( S ) Anchor bolts, nuts and washers (if required)
( S ) Platforms, stairs, ladders & handrails, roof handrail (without roof platform)
( S ) Water spray pipe (1.5m from G.L) with spray nozzles on tank
( S ) Foam pipe (1.0m from G.L) with support
( S ) Emergency vent cover, gauge hatches (required tanks)
( S ) Breather valve with flame arrester (if required)
( S ) Vent with bird screen (if required)
( S ) Name plates (A240-304) with bracket
( S ) Earth lugs
( S ) Settlement check lugs (if required)
( V ) Heavy equipment for construction
( V ) Welding rods for construction
( V ) Tools and jigs for construction
( V ) Consumable material for erection
( V ) Blind flanges together with bolts/nuts and proper gaskets for hydrostatic test
( V ) Corrosion inhibitor for hydrostatic test (if required)
( V ) Painting material for equipment proper
( V ) Sealing between tank bottom and foundation
( V ) Test plate for PQT and WPQT
( S ) Spare parts of gasket and B/N for construction and commissioning
( S ) Spare parts of gasket and B/N for 2-years operation (by option)


TECHNICAL PROPOSAL
FOR
STORAGE TANKS
DATE : J une 18, 10
REV.0


S-Tank Engineering Co., Ltd.
S-TANK ENGINEERING

2.2 Scope of Work

( S ) Mechanical design (strength calculation, stress analysis and detail design)
( S ) Documentations and manufacturing drawings
( S ) Provision of as-built documents and drawings
( S ) Loading data for tank foundation
( S ) Material procurement
( S ) Mechanical guarantee
( S ) Shop fabrication
( V ) Site construction
( V ) PWHTC-3051,C-3052 only
( V ) Inspection & test at shop and test
( V ) Touch-up painting and site as per painting specification
( V ) Dimensional check and acceptance of foundation including minor adjustment work
( V ) WPS with PQR and WPQT
( V ) Hydro-test and water drainage as broom clean condition after hydro-test and drying
( V ) Settlement checking during hydrostatic test
( V ) Rust prevention
( V ) Third party inspection excluded its inspectors fee
( S ) Packing list (packing volume, size & weight, etc.)
( S ) Packing and inland transportation in Korea
( X ) Ocean transportation and inland transportation in Philippine
( V ) Unloading of materials at site
( V ) Temporary work of utility for construction and test
( S ) Documentation for government approval














TECHNICAL PROPOSAL
FOR
STORAGE TANKS
DATE : J une 18, 10
REV.0


S-Tank Engineering Co., Ltd.
S-TANK ENGINEERING


2.3 Out of Scope

( X ) Tank foundation and civil
( X ) Electrical and Instrument
( X ) Process Piping
( X ) Cabling and wiring materials
( X ) Cathodic protection system
( X ) All kinds of valves including shut-off valves for draw-off sumps and external piping
( X ) Companion flanges with bolts/nuts
( X ) Insulation material and work
( X ) Fire protection material and work (if required)
( X ) Grouting for tank bottom
( X ) Utility for construction
( X ) Foam chamber with deflector
( X ) Electricity for construction (will be supplied to the first panel within 100m by Owner)
( X ) Water (will be supplied to the first block valve by Owner)
( X ) Customs clearance and taxes & duties for importation in Thailand
( X ) Government permit and approval (for local regulation)



















TECHNICAL PROPOSAL
FOR
STORAGE TANKS
DATE : J une 18, 10
REV.0


S-Tank Engineering Co., Ltd.
S-TANK ENGINEERING













3. General Assembly Drawings






















TECHNICAL PROPOSAL
FOR
STORAGE TANKS
DATE : J une 18, 10
REV.0


S-Tank Engineering Co., Ltd.
S-TANK ENGINEERING












4. Project Schedule


Project Name : Storage Tank for JG Summit NCC Project Date : Dec. 20. 2010
1. MILESTONES
2. ENGINEERING
-
-
-
3. PROCUREMENT
-
-
-
4. PRE-FABRICATION
-
-
-
5. OCEAN FREIGHT
-
-
-
-
6. CONSTRUCTION
Preparation
- Material and Tool-Consumable Prepare of on site
- Temporary Facillties & shop welder test
Q'ty Weight
I.D(m) H(m) Set Ton
- D-3001A SDFRT 55.12 19.60 1 922 Aug.15
- D-3001B SDFRT 55.12 19.60 1 922 Aug.15
- D-3021 CRT 26.16 19.75 1 264 Jul.14
- D-3022 CIFRT 32.00 19.75 1 354 Jul.14
- D-3031 CRT 9.00 7.40 1 30 Jul.14
- D-3051 CRT 5.85 7.40 1 16 Jul.14
- D-3052 CRT 2.95 4.90 1 8 Jul.14
- D-3141 CRT 20.00 17.06 1 124 Jul.29
- D-3151 CRT 16.00 14.62 1 73 Oct.15
- D-3201 DRT 9.75 9.85 1 34 Jun.15
- D-0407 CRT 5.50 6.50 1 15 May.16
- D-0516 CRT 8.30 7.60 1 24 May.16
5
278Ton
2010 2011 2012
63Ton
1,000Ton
1,000Ton
All Item
S-Tank Engineering Co.,Ltd.
1 7 8
2,652Ton
2,368Ton
362Ton
4
56Ton
Body Detail Drawing
Accessory Detail Drawing
Steel Plate
Steel Shape 405Ton
All Item
All Item
Others Material
Others Material
Steel Plate
3rd Shipment
1st Shipment
2nd Shipment
Steel Shape
3
DESCRIPTION
9 10
Strength Calculation
Gr.
Remarks
12 3 4 6 5 2 11 12
G
r
.
1
G
r
.
2
G
r
.
3
PROJECT MASTER SCHEDULE
Item No Type
Tank Size
6 1 2
ERECTION START FABRICATION START 1ST SHIPMENT HYDRO TEST START MECHANICAL COMPLETE


TECHNICAL PROPOSAL
FOR
STORAGE TANKS
DATE : June 18, 10
REV.0


S-Tank Engineering Co., Ltd.
S-TANK ENGINEERING









5. Painting Specification




PROJ ECT : Storage Tanks for J G Summit NCC Project in Batangas, Philippines
P R I C E F O R M
'11. 01. 26 (Rev.0)
S-TANK ENGINEERING CO., LTD.
Net
Capacity
per Tank
Design
Pressure
C.A (S/B/R)
Shell
Thick.
Internal
Coating
&
Lining
Q'TY W/T Construction
Field
PWHT
Test
and
Inspection
(Excluding
H.T Water)
Site
Painting
&
Epoxy
Coating
Insulation
(Work)
Tank
Calibratio
n
Sub
Total
( C )
Total
D H () (mmH20) (mm) (mm) (Yes/No) SET (TON) (USD) (USD) (USD) (USD) (USD) (USD) (USD) (USD)
1 D-0407 FluxOil Tank CRT API 650 SA283-C 5.50 6.50 154 150/-50 0.950 3.0/3.0/1.5
6.0
9.0/9.0
7.0
No 1 15
2 D-0516
Wash Oil Storage
Tank
CRT API 650 SA283-C 8.30 7.60 411 150/-50 0.950 3.0/3.0/1.5
6.0
9.0/9.0
7.0
No 1 24
3 D-3001A/B FRN Storage Tank SDFRT API 650
SA573-70
SA283-C
55.12 19.60 46,770 F.W 0.720 3.0/3.0/3.0
8.0~26.0
9.0/9.0
8.0
No 2 1,844
4 D-3021
RawPyrolysis
GassolineStorageTank
CRT API 650 SA283-C 26.16 19.75 10,615 F.W+150/-25 0.771 3.0/3.0/1.5
6.0~17.0
9.0/9.0
7.0
No 1 264
5 D-3022
Pyrolysis Gasoline
Storage Tank
CIFRT API 650 SA283-C 32.00 19.75 15,884 F.W+150/-25 0.813 1.5/1.5/1.5
6.0~20.0
8.0/8.0
7.0
No 1 354
6 D-3031
Pyrolysis Fuel Oil
Storage Tank
CRT API 650 SA283-C 9.00 7.40 471 F.W+150/-25 1.011 3.0/3.0/1.5
6.0
9.0/9.0
7.0
No 1 30
7 D-3051
Fresh Caustic
Storage Tank
CRT API 650 SA283-C 5.85 7.40 199 150/-25 1.530 3.0/3.0/1.5
6.0
9.0/9.0
7.0
No 1 16
8 D-3052
Caustic Day
Storage Tank
CRT API 650 SA283-C 2.95 4.90 33 150/-25 1.205 3.0/3.0/1.5
6.0
9.0/9.0
7.0
No 1 8
9 D-3141
Desalinated Water
Tank
CRT API 650 SA283-C 20.00 17.06 5,360 F.W 0.995 0/0/0
6.0~12.0
6.0/6.0
6.0
Epoxy
Coating
1 124
10 D-3151
Demi. Water
Storage Tank
CRT API 650 SA283-C 16.00 14.62 2,940 F.W 1.000 0/0/0
6.0~9.0
6.0/6.0
6.0
Epoxy
Coating
1 73
11 D-3201
Spent Caustic
Tank
CRT API 650 SA283-C 9.75 9.85 735 150/-25 1.089 3.0/3.0/1.5
6.0~7.0
9.0/9.0
7.0
No 1 34
12 2,786
S.G
Total
Remarks NO ITEM NO. Product
Applied
CODE
Main
Material
Tank Size
(m)
Type

You might also like