This paper summarises a cost optirnisation procedure by minimising the total drill metres and the overbreak that occurs in tunnel excavation. It is an alternative interpretation of the concept of rock fragmentation through seismic waves. The proposed practice was employed in strong rock conditions (calcareous limestone) at Diyarbakir irrigation tunnels in Turkey with a very limited success.
Original Description:
Original Title
Use of Pre-splitting Technique as an Alternative Approach To
This paper summarises a cost optirnisation procedure by minimising the total drill metres and the overbreak that occurs in tunnel excavation. It is an alternative interpretation of the concept of rock fragmentation through seismic waves. The proposed practice was employed in strong rock conditions (calcareous limestone) at Diyarbakir irrigation tunnels in Turkey with a very limited success.
This paper summarises a cost optirnisation procedure by minimising the total drill metres and the overbreak that occurs in tunnel excavation. It is an alternative interpretation of the concept of rock fragmentation through seismic waves. The proposed practice was employed in strong rock conditions (calcareous limestone) at Diyarbakir irrigation tunnels in Turkey with a very limited success.
Use of Pre-splitting Technique as an Alternative Approach to
Cost Optimisation in Tunnel Excavation
T Siimer 1 and H A Giiveni,,2 ABSTRACT Cost of Drilling 32% This paper summarises a cost optirnisation procedure by minimising the total drill metres and the overbreak that occurs in tunnel excavation in medium strength rock (uniaxial compressive strength <80 Mpa). The cost optirnisation approach discussed here is an alternative interpretation of the concept of rock fragmentation through seismic waves (Grand, 1980). The proposed practice is an alternative approach to smooth blasting techniques employed in tunnel excavation, since this approach reduces overbreak and speeds up the excavation. This approach was successfully employed in derivation, energy. and grouting tunnel excavations of Bekrne Dam Project. The on-site experience and the points that should be laken into account in practice are given in the conclusions. The proposed practice was employed in strong rock conditions (calcareous limestone) at Diyarbakir irrigation tunnels in Turkey with a very limited success. Cost of Explosives 32% Cost of supports 25% Cost of transportation 11% INTRODUCTION The perimeter and face stability of any tunnel excavation is dependent on the techniques employed in using explosives as much as it depends on the existing lithology of the rock mass in which the excavation is to be carried out. Smooth blasting techniques and uncontrolled blasting practices not only causes in stability but also excessive overbreak in soft and medium strength rock conditions. This overbreak is reflected as additional cost to contractors that cannot be included in the monthly invoices even though geological conditions are introduced as the main causes. We have also found out that in environments with fluctuating humidity conditions the organic fill materials that are used to fill overbreak volumes and the cavities in the tunnel perimeter cause the generation of poisonous gasses that are flammable. This increases the cost of maintenance and causes insurance problems. In order to find an economical solution to the existing problem, pre-splitting was employed first at the tunnel portal then at the faces. The next step was to optimise the drilling meterage by eliminating reaming holes that were previously designed to be drilled as 102 mm in diameter, and two in number. The third step was to reduce the total drill metres on each face by increasing the drilling diameter from 42 mm up to 89 mm. We have experimented with different set-ups in each step. After six unsuccessful iterative attempts a unique drill pattern was formed. The details of this practice and the cost comparisons with classical drilling and blasting practices are given in the following sections. DETERMINATION OF COST PARAMETERS In order to form the base of this practice a research was performed in 12 different tunnels with face areas of 20-75 m 2 and where drilling and blasting practice is employed with drill holes ranging from 38-45 mm in diameter. The above practice as here in after will be named as 'classical approach'. All the tunnels that are surveyed was chosen to be in calcareous rock formation in the presence of at least one fault line. I. Department of Tendering and Planning, Ceylan Construction Co Ltd, Ankara, Thrkey. 2. Department of Computer Engineering and Information Science, Bilkent University, 06533 Ankara, Thrkey. FIG I - Cost distribution for tunnel excavation. The result of excavation cost (manpower included) calculations of these tunnels that are excavated or are being excavated can be summarised as in Figure I (Stimer and Asenjo, 1993). In order to give a comparison in open cast operations where bore hole diameters of 64-89 mm is used (in calcareous environment), the cost of drilling only is approximately 1.30-1.60 $/m and for each drill metre approximately 12 m 3 of rock can be excavated. On the contrary in tunnel excavation the drilling cost is approximately 2.60-3.20 $/m and only 0.6Q-O.90 m 3 of rock can be excavated per drill metres. In classical approach, after a few experimental blasts the required amount of explosives needed for each face blast can easy be found depending on the existing rock media of concern. Then modifications to theoretical calculations can easily be made to suit the local boundary conditions. Therefore, if one does not take into account the drastic changes in the lithology of the rock environment, the amount of explosives required for each face blast can be assumed to be approximately fixed. Trying to cut down the amount of explosives required to a further degree will decrease the excavation speed and increase the maintenance cost of equipments used. The number of workers needed for excavation depends totally on the past experience of the engineer in charge. Therefore the required work force will be fixed in number, depending on the rate of excavation planned and number of shifts practiced. Trying to reduce the number of worker will require high mechanisation that will bring an additional inve tment, hence the decision on the degree of mechanisation will be made on the basis of local conditions. The cost of supports depends only on the geological conditions that will be faced during excavation, since research drilling cannot be made on every metre of the tunnel alignment. Therefore the cost of supports depends on the amount of risk that will be planned to be undertaken by the contractor. The risk is very limited due to the human life involved. As a result, cost of support can also be considered to be fixed. We therefore are left with only one cost parameter that is the drilling cost. This parameter is interrelated with explosive cost. We all know that no one can blast effectively a wrong drilled tunnel face. We have encountered tunnel face pulls less then 80 per cent of the drilling bore hole length due to miss practices in drilling. EXPLO '95 Conference Brisbane, 4 - 7 September 1995 383 T SUMER AND H A GUVENIR PRELIMINARY COST OPTIMISATION Figure 1 shows the distribution of costs for tunnel excavation. In order to optimise the drilling cost, we programmed on-site control of the drilling activities, considering the tunnel excavation studies we have studied previously. This control saved us 8-12 per cent on overall drilling costs. As the second step of cost optimisation, various drill patterns for pre-splitting in tunnels are trailed. Six out of 23 tunnel face blasts were completely a failure. We then were able to achieve partial success in the following 13 blasts. In the last four blasts we achieved full success. PRE-SPLITTING PRACTICE The theoretical background (which was modified due to present boundary conditions) of this pre-splitting practice was based on the assumption that in order to form a crack pattern within the rock mass, the vibrations thal will be generated from the blast of the explosives that are placed on the perimeter should be kept within the limits given in Table 1. TABLE 1 Critical vibration velocity for rock conditions. ROCK TYPE CRITICAL VIBRATION VELOCITY mrnIsec A) Hard Rock Density >2.8 ton/m 3 >950 ues >220MPa B) Medium Hard Rock Density >2.6 ton/m 3 600--750 70 < ues < 140 MPa C) Soft Rock Density> 2.3 ton/m 3 <400 ues <40MPa Note: ues Uniaxial eompressive Strength The calculation of the expected vibrations can be done (Johansson, 1990) as follows: V = (YIE) *C where V = Critical vibration velocity mm/ sec, Y = Rock Strength (DCS), E = Young Modules, C = P wave velocity mm/sec. A study performed by Berta (1990) also gives a practical background. PRE-SPLITTING AT THE PORTAL An example of pre-splitting practice employed at the portal of a tunnel is shown in Figure 2 (Popouic and Sumer, 1989). Pre-splitting holes of diameter 34--45 mm are drilled at the boundary of the portal with 20-35 cm spacing and loaded with counter explosives as shown in (Table 2). The length of these pre-splitting holes are extended as the RQD (Rock Quality Designation) of the rock gets higher, this ranges from 1.5 m to 5 m in depth. A similar approach w"as mentioned (Mavar 1987) two years after this application was realised. These mentioned counter holes which were drilled and blasted before drilling of the production holes. PRE-SPLITTING AT THE TUNNEL FACE The idea of optimisation of drilled metres in tunnels occurred when we placed a few 60 mm gelatin cartridges in one of the 102 mm reaming holes after experiencing several problem with scaling and blasting. No. of holes: 117 empty: S8 loaded: S9 FIG 2 - Pre-splitting technique applied at the portal of energy tunnel number 2. TABLE 2 Hole spacing, hole diameter, and explosives usedfor various rock conditions at tunnel portals. Type of Rock Hole Spacing Hole Diameter Explosives UCS (MPa) (cm) (mm Used Shale-soft-limest 20 cm 45-49 GURITBI7, ne Kountur Vitezit UeS:30-40 5a 22 Dolamitic 22 43 GURITAII,17, Limestone Kinit20 ues: 60-80 Massive 23-27 41 GURIT BII,17, Limestone Kontur Vitezit ues: 80-110 18 Note: ues Uniaxial eompressive Strength. We found out that scaling is no more a problem. This inspired the idea of increasing the blast hole diameters from 38-45 mm to 52-(j4-76 mm so that we can load fewer holes with a larger amount of explosives per drilled hole. In the first trial only the drillhole diameters are increased and a reasonable reduction in total drilling meters was achieved, but excessive overbreaks occurred. In order to reduce the extent of overbreak, the perimeter of the tunnel face was drilled with pre-splitting holes 50-70 cm apart. These pre-spitting holes were drilled parallel to the axis of the tunnel and loaded with explosives of 4300 m/sec detonating velocity. The loading density of these holes was about 0.2-0.35 kg/m. These perimeter holes were blasted with 25 m/sec delay per 15-25 holes (Fourhaugh and Sumer, 1989), in order to bring down the blast vibrations generated from pre-splitting to the calculated limit. This enabled us to form a crack all around the volume of rock that is planned to be blasted in the next round. The next step was to drill the face that was previously separated from the rock medium with 52-64 mm holes. This saved us 25 per cent in drilling cost. Another ten per cent saving was obtained from blasting since higher loading densities were achieved by employing large diameter holes. The last saving was from the over break which was 65 per cent. Another problem that we have encountered was the uneven tunnel face generated after each blast. This problem was overcome by increasing the loading density of explosives gradually towards the end of the blast holes. By this practice we have found out that we can widen the tip angle of the breaking cone that is formed at the far end of the blast hole. We have seen that the breaking angle totally depends on the velocity of detonation and density of explosives loaded at the tip point. After realising this fact, a piece of gelatin explosive is placed at the end of each pre-splitting holes (Figure 3). 384 Brisbane, 4 - 7 September 1995 EXPLO '95 Conference ElllJLIT ISO 1/2 EIlULIT ISO Sxl GURU ' 32/1100 .. , 40/200 , 17/500 FIG 3 - Loading detail of a pre-split hole. FIG 4 - Classical burn hole drilling detail. USE OF PRE-SPLITIING TECHNIQUE In order to increase the savings from drilling costs to a further level, the design of the classical reaming hole (Figure 4) is changed. This idea is inspired by Bergovists (1990). Seven to ten holes were drilled parallel to the tunnel axis with diameter of 43 mm (Figure 5). These holes were loaded with contour explosives and were connected with detonating cord P5 in a vertical direction and blasted with the delay pattern shown in Figure 5. Three parallel crack lines were formed by this method at just the same location as the previous bum cut used to be drilled. Through this application, in place of two 102 mm holes only ten 43 mm holes were drilled which took only 25 minutes instead of 1.5 hours, partly due to the need to change drill bits and related accessories. This itself caused a saving of 66 per cent. The next step for cost optimisation was to increase the drillhole lengths as we enter a rock media of RQD 85. The drillhole length of 3.2 m was increased to 5 m so a pull of m was realised. Through this application the number of faces that needed to be blasted was decreased by up to 40 per cent. Even longer drillholes were experimented with by use of couplings. Due to the lack of mechanisation (which is now available in the market at a very reasonable price) and due to the complexity involved in the explosive loading and blasting patterns of longer blast holes, the cost of tolerable mistakes was so high that we could not claim to have reached a successful result. We believe that longer blast hole drilling in medium strength rock conditions needs further research. The results of the application of all the techniques mentioned above at the same tunnel face resulted with the following savings: I. Reduction of overbreak was 60-72 per cent. Reduction in support cost was 25-35 per cent. Reduction in shotcrete was 40-50 per cent. 2. Reduction of the fill concrete cost was around 72-81 per cent. 3. The time gain helped us to complete an excavation round within a shift cycle. Firts trial Second trial THE COST ANALYSIS OF THE PRE-SPLITTING APPROACH
No6 Last trial No1 FIG 5 - Alternative bum hole drilling pattern. For a tunnel face with a face area of 40 m 2 and a circumference of 25 m a pull of 2.6 m per blast was practiced. Since the classical approach was used, 71 production holes were drilled per face. The cost of drilling was 71 holes * 3.2 m per hole * $3 Im = $681.6 per face. When the pre-splitting approach was employed 45 holes were enough to pull the face as the first attempt so the drilling cost was 45 holes * 3.2 m * $3.4 Im = $489.6 per face. This means a saving of $191.9 per face. The classical approach causes an overbreak minimum 12 cm, which results in extra 0.1 m * 25 m =3 m of concrete per metre. The cost incurred is 3 m' Im * $65 1m 3 = $195 Im. In the pre-splitting approach 60 per cent of this loss was regained resulting $195 Im * 0.60 = $117 Im of saving per face. In the classical approach I ton/m contact grouting was required however in the pre-splitting approach, 0.70-0.83 ton/m grout was enough. The saving in grouting was $210 Iton * (1-0.83) =$35.7 per metre of tunnel. As a result, a savings of $343.37 per metre of tunnel wa achieved. Please note that the savings discussed above are in terms of only three cost parameters. When all the other cost parameters are considered, approximately a saving of $510 per metre was calculated. If one considers that the total cost of tunnel operation is approximately 2500 per metre, the total savings will be up to 20.4 per cent on cost bases. PRACTICAL CONSIDERATIONS Some of the important points that are needed to be taken care of in the application of pre-splitting approach in weak to medium rock conditions can be listed as follows: EXPLO '95 Conference Brisbane. 4 - 7 September 1995 385 T SUMER AND H A GUVENIR FIG 6 - The relation between type of line joining two adjacent pre-splitting holes and the amount of explosives. * straight lines * correct amount of explosive * convex lines * insufficient amount of explosive * concave lines * excessive amount of explosive Grand, C H, 1980. An Emprical Method of Enegy Distribution in Blast Patterns (Soc of Mining Engineers of AIME). Johanson, M, 1990. Tunnel Blasting Technique Course in Advanced Rock Blasting Techniques, Section 4 (Gytrop: Seweden). Mavar, R, 1987. Results of Channel and Tunnel Po:lJ!.! Excavation Practice, Technical Report No: 2220-1-223,915-87. Popouic, R and Sumer, T, 1989. Project Procedure fo Excavation and Diversion Tunnel Inlets. Enka Cons Report No: DTOO28/01 LOT 4A BEKHMEDAM. Sumer, T and Asenjo, T R, 1993. An Interactive Computer Simulation for Tunnel Cost Calculations, Interm Report no: CICS 0028193 Berke Dam Project, Ankara. Sumer, T and Guvenir, H A, 1993. Cost optimization for controlled blasting, transportation, and crushing, in Proceedings Nineteenth Annual Conference on Explosives and Blasting Technique, pp 13-23 (International Society of Explosives Engineers). REFERENCES I. The diameter of perimeter holes should be gradually increased from 38 mm to 64 mm. The hole spacing should be increased from 35 cm to 70 cm gradually. We have faced several problems when the spacing of pre-splitting holes were increased beyond 60 cm in medium hard rock conditions. 2. Production holes of diameter up to 89 mm should be placed at the middle of the tunnel face and the hole diameters should gradually be decreased near the perimeter to avoid excessive vibrations and overbreaks. The concept of changing drillhole diameters in the same drill pattern was also experienced in open cuts (Stimer and Gtivenir, 1993). 3. In determining the spacing and loading density of perimeter holes, first a conservative spacing should be fixed and perimeter explosive should be changed. When the required amount of explosive per hole is almost determined then the spacing should be optimised. 4. Utmost care and control on the drilling pattern and its compatibility with the calculated drilling patterns should be maintained on-site. 5. In order to reduce the cost of counter explosives which are around $4ooo/ton, low density ANFO (0.3-0.5 kg/dm 3 ) was used. The point to be taken care in the use of ANFO is that the absorption of fuel oil should not be less chan 8.5 per cent, otherwise unobserved fuel-oil dissolves the synthetic spheres introduced to the mixture. 6. In medium-hard rock conditions detonating cord of P50-60 can be used instead of specific counter explosives. The point here is that two lines of P30 will not replace one line ofP60. 7. In any case, all the counter explosives and explosives in production holes should be primed from the bottom of the holes. 8. All the shock tubes and detonators should be carefully checked by an inspector before being sent to a site. 9. The success of pre-splitting blasting can be evaluated by examining the line joining two adjacent pre-splitting holes as follows: if amount of explosive is normal, then the line is straight, if excessive amount of explosive is used, then the line is concave, if insufficient amount of explosive is used, then the line is convex. These cases are illustrated in Figure 6. Ariog1u, E and Tokgoz, N, 1993. Kaya\;larin Tek Eksenli Basin\; Dayanimi Arasinda Ampirik Baglantilar Ozerine Bir Istatikse1 c;aIisma, Geosandjoumal, 23. Bergovists, I, 1990. Tunnel Blasting Lecture Notes. Blasting Application Research (Nitro Nobel ab: Gyttrop Seweden). Becta, G, 1990. Explosives an Engineering Tool (Itallsplosives: Milano) pp 100-110. Fourhaug, M and Summer, T, 1990. An Alternative Aproch to Audio Over Break Problems Experianced at Urfa Tunnels. Sevedofo Consult, Report no: DS0028116 386 Brisbane, 4 - 7 September 1995 EXPLO '95 Conference