You are on page 1of 9

How to Calculate Critical Path, Float, Early Start &

Late Start, and Early Finish & Late Finish


This is a part-post from Develop
Schedule process post, part of the Tools and Techniques for the process.
I suggest you get yourself a cup of coffee, this one is going to be a long one.
As we saw in Develop Schedule process, Critical path is made up of series of activities from beginning to the
end, where each activity has a dependency over previous activity in such a way that delay in any one activity
causes delay in all subsequent activities, causing the project to slip.
In other words, critical path is the longest path in your projects schedule network diagram, and is the
SHORTEST possible duration for the project.
How to Calculate Critical Path
Let us take a simpler example than Johns home construction example we saw in previous lessons. This project
involves assembling a train set (refer to the picture above).
Calculating Critical Path is a simple 4-step process.
Step 1: Find Activities
Activities for this project are as below (output from Define Activities process) -
A. Assemble two-tier bridge B. Join winding tracks C. Assemble and add train station D. Place standalone items
around E. Assemble and add construction site F. Join train engine and bogies G. Place the train on the track H.
Start the engine and let it chug!
Step 2: Build Schedule Network Diagram
Formatted: Font: (Default) Times New
Roman, 12 pt
Sequence activities and build schedule network diagram (output from Sequence Activities process) . This is
how it looks, with individual activity duration in minutes -
Figure 2: Assemble train set schedule network diagram
Step 3: Find all Possible Paths
Find all possible paths through the diagram, there are 3 in our case -
A -> B -> F -> G -> H
A -> B -> C -> D -> G -> H
A -> B -> C -> E -> G -> H
Step 4: Calculate Duration for Each Path
Let us see the duration for each of these paths -
A -> B -> F -> G -> H > 10+20+4+2+2 = 38 minutes
A -> B -> C -> D -> G -> H > 10+20+5+10+2+2 = 49 minutes
A -> B -> C -> E -> G -> H > 10+20+5+2+2+2= 41 minutes
The network path with longest total duration is the critical path!
Formatted: Font: (Default) Times New
Roman, 12 pt
Critical path is the shortest duration required to complete the project successfully.
In our example this is the second path: A -> B -> C -> D -> G -> H, which comes to 49 minutes.
Figure 3: Assemble train set Critical Path
Note that sum of durations of all activities on critical path comes 49 minutes, and sum of duration of ALL
activities on the project is much longer. If managed well, the whole project can be completed within the critical
paths duration.

How to Calculate Critical Path, Float, Early Start &
Late Start, and Early Finish & Late Finish
Calculating Float for Activities
Now, any schedule will have some flexibility, or elbow room, called Float.
Float of an activity is the duration that it can slip by without delaying the subsequent task or completion of the
project, or violating schedule constraint.
It is the elbow room that a task has. Amount of time an activity on a network path can slip without causing a
delay in early start of any successor activity and without violating schedule constraint is called Free Float.
Total amount of time an activity can slip from its early start date without causing delay to project completion or
violating schedule constraint is called Total Float.
The simple 3-step process to calculate float of ALL activities in your schedule network diagram -
Formatted: Font: (Default) Times New
Roman, 12 pt
Step 1: Arrange the paths in decreasing order of their total duration,
starting with Critical path
For the above example it would be as below, the first being critical path itself -
A -> B -> C -> D -> G -> H > 10+20+5+10+2+2 = 49
A -> B -> C -> E -> G -> H > 10+20+5+2+2+2= 41
A -> B -> F -> G -> H > 10+20+4+2+2 = 38
The float for each activity on the critical path is zero.
Step 2: Find float for activities on the second longest path
This would be the difference between total duration of critical path and next longest path. In our example this
would be 49-41= 8 minutes. Assign this to ALL activities on this path, which do not already have a float. In this
example that would be only activity.
Figure 4: Float for second path
Step 3: Do the same to all remaining paths, for unassigned activities
Now calculate difference between critical path and third paths total duration, and assign this to activities on the
third path excluding any which already have a float assigned in previous step. In our example this would be
49-38 = 11 minutes.
Do this step for rest of the identified paths and you have float for all activities.

How to Calculate Critical Path, Float, Early Start &
Late Start, and Early Finish & Late Finish
Early Start, Early Finish and Late Start, Late Finish
Why do we need to know the early and late number for an activity? By knowing how early an activity can start
and how late it can finish gives you the flexibility to juggle resources between other activities that can
potentially impact critical path, and hence the project completion date. The shorter a network path is in relation
to critical path, more schedule flexibility you will have on activities on that path.
Early start and Early finish
Indicates the earliest time an activity on a network path can start and earliest it can finish. If you decide to start
an activity on its early start (assuming previous activities on that network path are completed on their early
finishes), that activity can finish on its early finish (if it does not slip). And when the last activity on a network
path is completed by its early finish, you have all the resources of those activities at your disposal to deploy on
other high risk activities.
Calculating Early start and finish (take a FORWARD pass through network path)
Remember!: Always start with the critical path and then go with paths with descending order of their total
duration.
Step 1: Early start of first activity on critical path is always 1. Write it at the top left corner of that activity box
(see the image below).
Step 2: Add its activity duration to this early start number and reduce it by one. Write the resulting number on
the top right corner of activity box.
Step 3: Take the subsequent number of this early finish and write as early start for next activity. Continue this
till you reach the end of critical path.
Step 4: Select the network path with second highest total duration, and calculate early starts and finishes. If you
find an activity with early start and finish already written do not overwrite them. Do the same for remaining
network paths.
Note: If you find two activities converging on a single activity (say, activity-G), it indicates that the activity-G
will start only AFTER converging activities finish. So, you will take the largest value amongst the early finish
of these two activities and write subsequent number as early start of the activity-G.
Why add duration to early start and then reduce by one, to get early finish? Because the duration of an activity
includes both start and finish days (or any other unit of measurement you use). So, if first activity duration is 5
days, and early start is 1 then early finish is 1+6-1 = 6. That is 6 days including the start and finish days.
Figure 6: Early start and finish
As you noticed, early start number is written at the top left corner of activity box, and early finish on the
top right corner. The critical path with early start and early finish days will look like this -
Formatted: Font: (Default) Times New
Roman, 12 pt
Figure 7: Early start and early finish for critical path
Late start and Late finish
Indicates the latest time an activity on a network path can start and latest it can finish. Knowing how late the last
activity on the network path can start and still finish within the time to not impact critical path, will let you
decide how much of flexibility you want to exercise on its schedule. However, once the last activity on the
network path starts on its late start day it should not slip, else it will impact project completion date.
Calculating Late start and finish (take BACKWARD pass through network path)
Remember!: Start with the critical path, beginning at the last activitys late finish.
Step 1: Late finish of last activity on the critical path is same as its early finish. Write this number at the bottom
right corner. Step 2: Calculate late start of this activity as the late finish minus activity duration plus 1. This
calculation has the same reason start and finish are both included in the duration. Write this number at the
bottom left corner. Step 3: Write this late start of the activity minus 1, as the late finish of previous activity.
Continue this way all way till you reach the late start of first activity on the critical path. Step 4: Select the
network path with second highest total duration, and write late starts and finishes beginning at the last activity
of that path. Do the same for remaining network paths.
Notes:
If you find two activities converging on a single activity (say, activity-C), take the smallest value
amongst the late start of these activities and write previous number as late finish of the activity-C.
If you find an activity with late start and finish already written do not overwrite them.
Formatted: Font: (Default) Times New
Roman, 12 pt
Figure 8: Late start and Late finish
Late start number is written at the bottom left corner of activity box, and late finish on the bottom right
corner. The critical path of our example with late starts and late finishes will look like this -
Figure 9: Late start, finish for the critical path
Let us go back to our example and calculate early/late start/finish for the entire schedule network diagram.
Formatted: Font: (Default) Times New
Roman, 12 pt
Formatted: Font: (Default) Times New
Roman, 12 pt
Figure 10: Early start, finish and Late start, finish for the entire schedule network diagram

Formatted: Font: (Default) Times New
Roman, 12 pt

You might also like