Professional Documents
Culture Documents
Registration Examination
September 2008
Attention L.A.R.E. exam candidates:
Thank you.
Table of Contents
Step One – Applying ................................................................................ 1
When to Apply for the Landscape Architect Registration Examination (L.A.R.E.) .... 1
How to Apply for the L.A.R.E. ................................................................. 2
Tools to Help You Apply ........................................................................ 3
Step Two - Preparing for the L.A.R.E. .......................................................... 5
Identifying Your Strengths and Weaknesses ................................................. 5
Non-sponsored Preparation and Review Courses ........................................... 5
Understanding the Content of the L.A.R.E. ................................................. 6
Format .......................................................................................... 6
Using the Content Guide..................................................................... 6
Section A - Project and Construction Administration (70 Items) - Multiple-choice
Section ............................................................................................ 7
Communication (20%) ........................................................................ 7
Standards of Practice (23%) ................................................................. 7
Contract Administration (17%).............................................................. 7
Construction Evaluation (20%) .............................................................. 7
Construction Practices (20%)................................................................ 7
Section B - Inventory, Analysis and Program Development (90 items) - Multiple-
choice Section.................................................................................... 8
Problem Definition (11%) .................................................................... 8
Inventory (29%)................................................................................ 8
Analysis (36%).................................................................................. 8
Programming (24%) ........................................................................... 8
Section C - Site Design (4 Vignette Problems) - Graphic Section ........................ 9
Competencies Tested ........................................................................ 9
Section D - Design and Construction Documentation (120 items) - Multiple-choice
Section ........................................................................................... 10
Design Principles (16%)...................................................................... 10
Resource Conservation and Management (18%) ......................................... 10
Graphic Communication (8%) .............................................................. 10
Construction Documentation (20%) ....................................................... 10
Materials and Methods of Construction (38%) ........................................... 11
Section E - Grading, Drainage and Stormwater Management (4 Vignette Problems) -
Graphic Section ................................................................................. 11
Competencies Tested ....................................................................... 11
Step Three - Taking the L.A.R.E. ............................................................... 12
Introduction ..................................................................................... 12
Multiple-choice Sections ...................................................................... 13
Example 1: .................................................................................... 13
What Materials Will I Need to Bring to the Exam?......................................... 13
Multiple-choice Sections (A, B and D): ...................................................... 13
Required:...................................................................................... 13
Provided: ...................................................................................... 14
Prohibited: .................................................................................... 14
Special Accommodations ................................................................... 14
Frequently Asked Questions About the Exam Procedure................................. 14
Graphic Sections ................................................................................ 15
Problem Statement - Explicit vs. Implicit Instructions ................................ 15
What is Expected? ........................................................................... 16
Completing the Sample Vignette Problems.............................................. 17
Pre-exam Orientation Information ........................................................ 18
The L.A.R.E. Reference Manual ........................................................... 18
What Materials Will I Need to Bring to the Exam?......................................... 18
Graphic Sections (C and E): ................................................................... 18
Required:...................................................................................... 18
Recommended:............................................................................... 18
Prohibited: .................................................................................... 19
Frequently Asked Questions About the Exam Procedure................................. 20
The L.A.R.E. in Metric and Imperial ...................................................... 21
Sample exam item with Canadian reference and Metric conversions: .............. 21
Step Four - After you have taken the L.A.R.E. ............................................... 22
Receiving Your L.A.R.E. Scores............................................................... 22
Multiple-choice Sections (A, B and D): ................................................... 22
Graphic Sections (C and E): ................................................................ 22
Preliminary Scores Available On-line ..................................................... 22
Interpreting Your L.A.R.E. Scores............................................................ 23
Section A – Project and Construction Administration .................................. 23
Section B – Inventory, Analysis and Program Development ........................... 23
Section C – Site Design ...................................................................... 23
Section D – Design and Construction Documentation .................................. 23
Section E – Grading, Drainage and Stormwater Management......................... 24
Review Options Available ..................................................................... 25
Standard Review ............................................................................. 25
Red-line Review .............................................................................. 25
Review Process ............................................................................... 26
Step Five – Getting Your License................................................................ 27
Having Your Exam Scores Transmitted ...................................................... 27
Transmitting your Multiple-choice Scores ............................................... 27
Transmitting with a Council Record ...................................................... 27
Transmitting without a Council Record .................................................. 27
Transmitting your Graphic Scores ......................................................... 28
Transmitting with a Council Record ...................................................... 28
Transmitting without a Council Record .................................................. 28
Appendix 1 - How the L.A.R.E. is Prepared ................................................... 29
Task Analysis Studies of the Profession .................................................. 29
L.A.R.E. Committees ........................................................................ 29
Preparing the Multiple-choice Sections .................................................. 29
Preparing the Graphic Sections............................................................ 30
Evaluation of the L.A.R.E................................................................... 30
Establishing the Raw Score for the Multiple-choice Sections ......................... 30
Scoring the Graphic Solutions.............................................................. 31
An Inside Look at the Grading Session.................................................... 33
The Graphic Grading Process .............................................................. 34
Appendix 2 - Reference Materials for the L.A.R.E. .......................................... 35
The following is a reference material list that has been prepared by the CLARB
Examination Committee. ................................................................... 35
Section A — Project and Construction Administration ................................. 35
Section B — Inventory, Analysis and Program Development .......................... 36
Section C — Site Design ..................................................................... 37
Section D — Design and Construction Documentation ................................. 37
Section E — Grading, Drainage and Stormwater Management........................ 38
Appendix 3 - L.A.R.E. Rules of Conduct ....................................................... 39
Further Examples of Exam Impropriety .................................................. 39
Appendix 4 – The True Cost of the L.A.R.E. .................................................. 41
(Continued from page 2):................................................................... 41
What Does it Take to Produce a Licensure Exam? ...................................... 41
The Total Cost................................................................................ 42
The Cost Per Candidate..................................................................... 42
Is the L.A.R.E. Worth the Cost?............................................................ 43
A Step by Step Guide to the L.A.R.E.
1
A Step by Step Guide to the L.A.R.E.
first, waiting to take the others until you costly and less frustrating to use other
acquire sufficient experience in those areas. sources of information (such as CLARB
sponsored study materials) for education
The L.A.R.E. is not designed to be a and feedback. More importantly, you need
learning experience, so taking the test to to determine objectively when you are truly
see what it is like or to determine your prepared to take the test.
strengths and weaknesses is not
recommended. You will find that it is less
2
A Step by Step Guide to the L.A.R.E.
In order to sit for the L.A.R.E., you must first provide documented evidence
that you have met the education and experience requirements. This evidence
consists of college transcripts, verification from previous and current
employers and references from licensed landscape architects. Once this
documentation is compiled, it is reviewed against the standards in effect in the
jurisdiction for which you wish to take the L.A.R.E.
The best way to apply for the L.A.R.E. and licensure is to complete CLARB’s
on-line application at www.clarb.org. This is a fast and interactive way to
create a permanent, documented history of your professional development. A
CLARB Council Record contains verified documentation of the education,
work experience, examination history and professional references of a
landscape architect. It provides a single, permanent location for all of the
information required to apply for the exam, and initial or reciprocal registration.
So why should you apply for a CLARB Council Record on-line at
www.clarb.org?
Convenience – Completing the on-line application not only saves time, but
allows you to review your application and determine what portions need to be
finished at a later date.
Flexibility – You can elect to take the exam in board-established test centers
or in CLARB test centers across the United States and Canada.
3
A Step by Step Guide to the L.A.R.E.
Security – The Council Record protects against loss of records and the
inability to secure the necessary verifications for application for licensure if, for
example, a previous employer goes out of business. Once established, an
annual renewal fee and update keeps your Council Record current and in an
active status.
CLARB Certification – After licensure and upon meeting the standards for
certification, your credentials and commitment to professionalism can be
formally acknowledged. Not only will you receive a special certificate
commemorating your distinction, but you will also be enabled to use “CLARB
Certified Landscape Architect” logos on marketing materials. Certification also
carries CLARB’s recommendation of reciprocal registration in any member
jurisdiction without further national examination.
4
A Step by Step Guide to the L.A.R.E.
5
A Step by Step Guide to the L.A.R.E.
Format
6
A Step by Step Guide to the L.A.R.E.
Communication (20%)
This subsection will assess your knowledge of communication methods and consensus and team
building techniques as it relates to coordinating and managing consultants and design team
members.
You will be required to show an understanding of the code of conduct for landscape architects and
standards of practice as it relates to administering a project. This subsection includes an
understanding of how to resolve ethical dilemmas and professional liability issues.
This subsection will test your knowledge of construction contracts. This includes your knowledge of
construction law as it relates to the responsibilities of various parties under the construction contract.
You will also be tested on your knowledge of the landscape architect’s role in the design and bidding
processes.
You will be tested on your understanding of the construction administration process including
techniques for construction observation, review of shop drawings, approvals or rejections of
materials and evaluation of the substantial completion of a project. You will also need to understand
the reasons for performing post occupancy evaluations as well as the sequencing of design,
approval, permitting and construction activities.
The Construction Practices subsection tests your knowledge of the technical aspects of construction
administration. You will be expected to understand construction equipment and technologies, quality
control procedures for construction as well as sustainable construction practices.
7
A Step by Step Guide to the L.A.R.E.
Problem Definition will test your knowledge of techniques to elicit client and user intentions and
needs. You will need to understand methods for determination of user values, such as focus
groups and surveys. You will also need to demonstrate your knowledge of a project’s
parameters such as the problem statement, goals, objectives, purpose, needs and outcomes.
Inventory (29%)
In the Inventory subsection, you will be required to demonstrate your knowledge of planning and
land use laws including zoning, development restrictions and design guidelines. You will need
to understand information such as accessibility regulations, natural features, cultural features,
characteristics of plant material, land information sources and the political and regulatory
approval processes.
Analysis (36%)
This subsection tests your knowledge of factors influencing selection of plant materials, human
factors influencing design, natural factors influencing design, patterns of land use and built form,
regional hazard design considerations and social and cultural influences on design. You will be
expected to understand research methods including interpretation, visual resource assessment
and components of site analysis documents.
Programming (24%)
The Programming subsection will test your knowledge of project requirements such as the
relationship and function of elements. You will need to understand how to develop preliminary
project budgets and schedules. You will be required to demonstrate your knowledge of the
process to define relationships among design elements by determining opportunities and
constraints, and the process to develop a design program based on users' needs and clients'
goals and resources. You will also need to show an understanding of how performance criteria
drives a project, such as program and/or project quality level, sustainability or requirements for
water quality.
8
A Step by Step Guide to the L.A.R.E.
You will be tested on your ability to develop design, planning and management solutions
considering on-site and off-site influences and convey the information through text and in
drawings. You will be required to incorporate consultant studies into your design and predict the
implications of your design, planning and management proposals on the natural and cultural
systems both within the site and in the larger context. You must be able to evaluate design
alternatives to determine the appropriate solution and create design alternatives to demonstrate
the range of options. You will also be expected to incorporate the design of circulation systems
into your design solutions.
Competencies Tested:
Evaluate design alternatives to determine the appropriate solution
Design circulation systems
Create design alternatives to demonstrate the range of options
Develop conceptual design, planning and management solutions considering on-site and
off-site influences
Predict implications of design, planning and management proposals on natural and cultural
systems both within the site and in the larger context
Synthesize and make connections between aspects of landscape architecture and
disciplines outside of landscape architecture including consultant studies
9
A Step by Step Guide to the L.A.R.E.
This subsection will test your knowledge of design principles including aesthetic principles of
design, design theory, problem-solving strategies, planning principles, design principles for
safety, security and crime prevention, social responsibility in design and therapeutic aspects of
design. You will be required to understand planting design including the location of plant
material types to meet various requirements, such as strategies for security and crime
prevention.
You will be required to demonstrate your knowledge of resource conservation and management
in this subsection. This includes conservation of natural resources, ecological planning
principles, environmental ethics, floodplain management and land and water reclamation
procedures. You will also need to show an understanding of the relationship between human
and natural systems such as water resource management, habitat restoration and creation,
urban ecology and sustainability.
This subsection will test your knowledge of the roles of visual communication, including
photographic and video documentation and graphic presentation techniques, systems and
symbols including when certain systems are appropriate.
The Construction Documentation subsection will test your knowledge of the administrative
procedures required throughout the construction process. You will be required to demonstrate
your knowledge of the general and supplemental conditions, special provisions and technical
specifications and their organization, including specification types and components for a project.
You must demonstrate an understanding of the construction process, including sequencing,
staging and construction technology. You must have knowledge of the various construction
documents such as layout plans, grading plans, drainage plans, demolition plans, erosion and
10
A Step by Step Guide to the L.A.R.E.
sediment control plans, planting plans and irrigation plans. You will also be required to produce
construction cost computations such as area calculations, volume, quantity and unit prices.
In the Materials and Methods of Construction subsection, you will be required to show your
understanding of various construction materials and how those materials are joined together. In
order to demonstrate your understanding, you will need to have knowledge of typical
construction details and site amenities, construction equipment and technologies, design needs
for special populations, elements of circulation systems and their design requirements, lighting
systems, noise attenuation and mitigation techniques, structural considerations and factors
influencing selection of site construction materials.
You will be tested on your knowledge of erosion and sedimentation control, irrigation systems,
biofiltration and other alternative drainage methods, grading, drainage and stormwater
treatment. You will also need to understand utility systems including the relationships of
different systems to each other and how to perform subsurface storm drain calculations and
determine pipe sizes.
You will be tested on your ability to develop grading and drainage plans considering on-site and
off-site influences and convey the information in drawings. You must be able to manipulate
contours to demonstrate your ability to convey water to meet design requirements while
protecting land and water resources. You will be expected to evaluate existing landforms and
drainage systems to locate program elements minimizing environmental or economic impacts.
You will also be required to think three-dimensionally to manipulate landforms to meet design
requirements.
Competencies Tested:
Synthesize and make connections between aspects of landscape architecture and
disciplines outside of landscape architecture including consultant studies
Design for protection and management of land resources (e.g., land forms, grading,
drainage, vegetation, habitat, erosion and sedimentation control)
Design for protection and management of water resources (e.g., storm water, water supply,
ground water)
11
A Step by Step Guide to the L.A.R.E.
12
A Step by Step Guide to the L.A.R.E.
Multiple-choice Sections
Sections A, B and D of the L.A.R.E. consist other questions. Come back to that
exclusively of multiple-choice type items or question later if you have the time.
questions. Each item addresses one of the
areas of knowledge described in the content After you have decided which of the
of the exam and is worth one point each. answers you feel is correct for a question,
There are two types of multiple-choice items click on the answer box using the mouse
used in the examination. The type most and move on to the next question. You will
widely used is the multiple-choice item with be able to go back to any unanswered
four answer choices. The second type of questions at the end of the test.
item may have up to nine answer choices.
The candidate chooses the answer choice
which best answers the question or
completes the statement.
What Materials Will I Need
to Bring to the Exam?
Example 1:
Use your time effectively, working as rapidly Acceptable forms of Secondary ID:
as you can without losing accuracy. Do not Credit card
spend too much time on a question that is Check, ATM or Debit card
too difficult. Skip that question and go on to
13
A Step by Step Guide to the L.A.R.E.
14
A Step by Step Guide to the L.A.R.E.
Graphic Sections
For each graphic response section of the important for you to review the L.A.R.E.
L.A.R.E., you will be asked to complete a Reference Manual so that you know where
set of vignette problems in a given period of to find information during the examination.
time. Each vignette problem is very It is not necessary to memorize these
straightforward and is intended as a sketch standards, but you must understand the
problem. Some vignette problems will take concepts given and when they must be
longer to complete than others; however, applied.
you will have about an hour to complete
each vignette. You will be responsible for The L.A.R.E. Reference Manual is available
budgeting your time to complete all of the on the CLARB web site at
vignettes in the given time period. http://www.clarb.org/pages/Exams_Prep.as
p?target=cs.
Each vignette includes a problem statement
that describes the context of the site and An updated version of the manual is made
specific requirements that you must address available approximately two months prior to
in your solution. The first thing to do is to the exam administration. You may print the
read the problem statement very carefully. It document from the web site and review it,
is extremely important for you to completely but you may not bring this copy with you to
understand the problem statement before the test site. A copy will be given to you at
attempting to create a solution. Your the beginning of the test administration by
solution must respond to all of the the proctor for use as a reference source.
requirements stated.
Problem Statement - Explicit vs.
The second source of information that you Implicit Instructions
must incorporate into your solution is the
L.A.R.E. Reference Manual. The L.A.R.E.
Reference Manual provides graphic There are two types of requirements in each
standards for portions of the exam as well vignette problem statement that you must
as zoning and construction standards that address in your solution. Explicit
must be followed when completing all of the requirements are those listed directly on the
vignette problems. This manual is similar to page, in bullet format, that you can highlight
a local zoning code that you would use and refer to as you complete your solution
when designing a project in an unfamiliar to the problem. Implicit requirements are
jurisdiction. Although the standards in the those unstated standards that a minimally
L.A.R.E. Reference Manual may differ from competent landscape architect is expected
your local codes, the exam is evaluated to satisfy. A minimally competent
based on the standards provided in this landscape architect is expected to provide a
manual. Most of the standards are taken solution that not only responds to the
directly from widely recognized codes and explicit instructions given on the problem
standards. All the codes have been statement, but also to factors such as
reviewed to ensure that they are similar to safety, efficiency and code regulations.
most U.S. and Canadian codes. It is
15
A Step by Step Guide to the L.A.R.E.
For example, even though you are not told What is expected of you when you sit down
in the problem statement to provide a safe to take the exam?
design, it is expected that a minimally
competent landscape architect would First and foremost, you must follow the
provide such a design. If a client were to instructions that are given in the problem
give you a project, that client would expect requirements. You should read through the
you to follow codes, provide a safe design problem statement, solve the problem and
and not waste money on an over-designed then go back and check to ensure that you
project. have done everything requested. There are
many times when you see problems fail
Similarly, it is expected that a minimally simply because the candidate failed to
competent landscape architect would apply complete everything required in the problem
the codes in the L.A.R.E. Reference statement.
Manual, even if the problem statement does
not specifically direct you there. You must use the L.A.R.E. Reference
Manual codes when solving the problems.
And some degree of efficiency is expected. It helps sometimes to complete a mini site
For example, you would not place 50 cubic analysis and ensure that you identify all the
yards of concrete in a detail that only codes that may apply. You can even add
requires five. Similarly, you would not place things to your drawings to make sure you
parking for a building on the opposite side of remember the codes. Draw the property
a major road, nor would you compromise setbacks if required. You can even place
the safety of a vehicle passenger by notes under the problem statement if that
designing parking that requires the vehicle helps you remember to incorporate all of the
to back into the major flow of traffic. codes.
It is necessary to satisfy the implicit You must not only follow what is written, but
requirements as well as the explicit ones you must also look to your education and
outlined in the problem statement for each training as a landscape architect to ensure
vignette. that your solution is safe.
16
A Step by Step Guide to the L.A.R.E.
set so high, that the water could not possibly get into the drain.
to change your solution to include some
Completing the Sample Vignette element you forgot.
Problems Do not try to embellish your drawings with
additional information. Your solution is
One of the leading causes of anxiety for evaluated based only on the required
exam candidates is "fear of the unknown": elements and how you put them together.
unfamiliarity with the test format, testing Adding information that is not required will
conditions and time constraints. It is helpful only take up time that you could spend
to learn as much as possible about the completing other solutions.
exam format and to practice problems under
test-like conditions to alleviate some of After you have completed all of the sample
these concerns. The sample vignette problems, you should review your solutions
problems are in the same format as the and see which areas you may need to
actual exam, and practicing them will obtain additional knowledge in before the
increase your comfort level. To accustom exam. Included in this publication is a
yourself to the time constraints of the actual reference material list. These publications
exam, you should allow approximately an might not contain all the answers that you
hour and fifteen minutes for each vignette. may need, but they can be good resources.
You should also make note of any problem
that takes you significantly more (or less)
time to complete, and target that subject
matter for further review.
17
A Step by Step Guide to the L.A.R.E.
18
A Step by Step Guide to the L.A.R.E.
Prohibited:
19
A Step by Step Guide to the L.A.R.E.
A. - NO. Using any color will cause your Q. - Who will grade my exam?
solution to be failed without further
evaluation. A. - The performance problems are graded
in a national grading session by licensed
Q. - Can I use a highlighter to mark the landscape architects from across the United
requirements in the problem statement? States and Canada. Each grader must
meet stringent eligibility requirements and
A. - Highlighting the problem statement is participate in a complete training program.
acceptable; however, if you use the marker
on your solution, it will cause your vignette Q. - When will I get my scores?
to fail.
A. - The scores are typically sent to the
Q. - Can I use a non-reproducible blue or Member Boards approximately 10 - 12
purple pencil, or is that considered a color? weeks after the exam administration. If you
took the exam through a registration board,
A. - You may use a non-reproducible blue or they will report your score to you. If you
purple pencil to sketch your solution before took the exam at a CLARB test center,
finalizing it with pencil or ink. Anything CLARB will report your score to you. It is
which is drawn in blue or purple pencil that possible for candidates to receive
has not been re-drawn with pencil or ink will preliminary, unofficial scores several weeks
NOT be evaluated by the graders. earlier on our web site at www.clarb.org. A
couple jurisdictions do not permit
Q. - Do I need to bring a lamp or an candidates to view preliminary scores
extension cord to the test location? online. Check the CLARB web site for
details.
A. - Check the information included with this
booklet or with your registration board for
20
A Step by Step Guide to the L.A.R.E.
The L.A.R.E. is international in scope with equivalents will not be exact conversions,
the U.S. and Canadian registration boards you are warned that converting or switching
participating in the examination process. units within a question to check answers
The examination is therefore produced in may result in an incorrect answer.
the Imperial and Metric dimensional
systems. A standard set of construction U.S. and Canadian examinees are also
codes is also provided. issued the same L.A.R.E. Reference
Manual for use on the exam. This manual
Candidates may prepare themselves for the contains building and related construction
L.A.R.E. using either the Imperial system or codes that will be required to complete the
the Metric system of measurement. In the examination.
examination, questions or problems
requiring a dimension or scale will indicate Sample exam item with Canadian
Imperial values followed by Metric values in reference and Metric conversions:
square brackets ([ ]). References to
Canadian standards will also be presented
in this fashion. Certain vignette problems According to U.S. standards [Canadian
may be presented in both an Imperial scale standards], the minimum width of an
and a Metric scale. You will be required to accessible parking space is
choose the scale you will be working in
when you sign up for the exam. A. 8' [2.5m]
B. 10' [3.1m]
No conversions will be required from one C. 12' [3.7m]
scale to the other. Since the Metric D. 15' [4.6m]
21
A Step by Step Guide to the L.A.R.E.
22
A Step by Step Guide to the L.A.R.E.
23
A Step by Step Guide to the L.A.R.E.
24
A Step by Step Guide to the L.A.R.E.
25
A Step by Step Guide to the L.A.R.E.
Review Process
26
A Step by Step Guide to the L.A.R.E.
Each registration board has additional requirements for licensure that you must satisfy, such as
earning a specific college degree, achieving a certain amount and/or type of work experience
and demonstrating further knowledge of local laws and practice issues. As you fulfill these
requirements over time, you can submit further documentation in support of your pursuit of initial
licensure.
27
A Step by Step Guide to the L.A.R.E.
28
A Step by Step Guide to the L.A.R.E.
More simply, a Task Analysis is a carefully The development of the examination is the
constructed, scientific study of a profession responsibility of the L.A.R.E. Committees,
that asks two questions: “What do these consisting of landscape architects appointed
professionals do?” and “What do they need by the CLARB President. To ensure the
to know?” widest and most representative viewpoint,
the committee members are selected from
When used in conjunction with a licensure various geographical areas and practice
program, such studies provide an accurate situations, and include both genders and
and legally defensible method of defining various ethnic groups.
the knowledge, skills and abilities (KSAs)
required to safely practice that profession. In addition to analyzing and refining the
These same KSAs form the appropriate Task Analysis Results into an exam
content for a licensing examination, in this specification, the L.A.R.E. Committees
case, the Landscape Architect Registration perform the task of drafting and reviewing
Examination (L.A.R.E.). each edition of the L.A.R.E.
29
A Step by Step Guide to the L.A.R.E.
2. The questions are written clearly and Once the final L.A.R.E. has been
in such a way that a “test-wise” assembled, it is reviewed by a professional
candidate would not have an editor for grammar, syntax and other
advantage in responding; and editorial considerations. The editor’s
3. No question content is biased recommendations are reviewed in turn by
against any region, ethnic group, the Exam Committees to ensure that no
race or gender. changes in meaning were unintentionally
made during the editing process.
Questions are selected by category to
ensure that all required subject matter is Evaluation of the L.A.R.E.
covered in accordance with the exam
specification. The statistical performance of
In scoring the multiple-choice and graphic
items is also used to help determine which
response sections of the L.A.R.E., there are
items will be included in the examination.
two distinct tasks that must be
accomplished:
Following a review by the Multiple-choice
Section Committee, some of the new
Raw scores must be established for
questions are chosen to be used as pretest
each portion of the exam. Raw scores
items on the actual examination. These
are the points a candidate earns on
pretest items do not contribute to the score
each portion of the exam.
of a candidate and the candidate does not
Passing levels must be established for
know which of the questions are pretest
each portion of the exam. The passing
items. The statistics gathered from
level is the number of points candidates
pretesting the new items are used to
must earn to pass a given portion of the
determine whether or not they will be
exam.
included as operational items in future
examinations.
Establishing the Raw Score for the
Preparing the Graphic Sections Multiple-choice Sections
The graphic portions of the examination are The raw score for each multiple-choice
prepared in a “vignette” format to give the section is the number of questions a
candidates more than one opportunity to candidate answers correctly. Items that are
demonstrate their ability to perform at a left blank are counted as incorrect.
minimally competent level. The Graphic
Committee is responsible for preparing Establishing the Passing Level for the
multiple vignette problems for each section Multiple-choice Sections
of the examination.
The passing level, or “cut score” for each of
Before they appear on the L.A.R.E., these the multiple-choice sections is based on the
graphic sections are pretested on licensed level of performance expected of minimally
landscape architects. The committee then qualified candidates taking that particular
reviews each item to determine which section.
vignette problems will be used on the
examination. A final review by the There are several steps in the process of
committee produces the final draft of the determining a cut score for a multiple-choice
examination. test. The first step is a cut score analysis
30
A Step by Step Guide to the L.A.R.E.
process completed in the first year of the Scoring the Graphic Solutions
examination.
The vignette problems are evaluated by
Cut Score Process graders who are licensed landscape
• Take Exam architects with at least five years of
• Rate difficulty of the problems experience, working in academic settings
• Process occurs separate from and/or in public or private practice.
grading Representatives from each jurisdiction
• Adjust scoring administering the examination are invited to
• Apply exam results to the new cut serve as graders. The evaluation itself
score takes place at a single grading session
conducted by CLARB where all of the
examinations are scored at one time.
It should be noted that the process for
establishing cut scores occurs without the
The L.A.R.E. Committee is given the exam
knowledge of the candidates’ raw scores.
specifications (the skills and abilities
This avoids any possibility of bias or
designated by the task analysis) and
consideration of passing rates in the
develops problems to test certain items in
process. After the test is administered, the
the specification. The committee then
cut scores are applied to the raw scores to
drafts evaluation criteria for grading the
determine which candidates pass the exam.
problems. The evaluation criteria are
developed so that only the skills and
It is important to recognize that the cut
abilities that the problem was designed to
score is NOT a pre-determined percentage
test will be graded. The committee will
of points, such as a 75%, which candidates
revise the problem if it finds that there are
must achieve. It is simply the minimum
elements in the problem that are irrelevant
number of correct responses required to
to the skills and abilities being evaluated.
pass. This number may vary from section
to section.
31
A Step by Step Guide to the L.A.R.E.
problems, and approach the problems as if Each grader applies the evaluation criteria
they were candidates. If they feel that there to assign the appropriate score for each
are items in the problem statement that are vignette problem. The graders must first
ambiguous or unclear, they will modify the ascertain whether the vignette can be
evaluation criteria accordingly. The Master scored. If the solution is blank or does not
Graders then review a number of actual follow basic problem instructions, the grader
exam solutions to ensure that the criteria will not evaluate the solution further. Next,
fairly evaluates all possible responses to the graders evaluate the critical components
each problem. Finally, the Master Graders of the solution. The critical components
conduct a training session to completely would include life/safety issues. If the
explain the grading process and the solution is scoreable and meets all of the
evaluation criteria to the exam graders. critical components of the problem, then the
They are present at the grading session to qualitative aspects of the solution are
resolve questions that the graders might evaluated.
have about unique solutions.
Each vignette receives one of four scores
Before actually evaluating any candidate for the qualitative evaluation: pass,
solutions, graders become completely borderline pass, borderline fail or fail.
knowledgeable about each problem by Solutions that demonstrate at least
reading and studying the problem minimum competence in the KSAs being
statement, reviewing the base plan and tested receive “pass” or “borderline pass”
thoroughly discussing the evaluation scores. Solutions in which the candidate
criteria. All graders attempt to establish a has failed to demonstrate some ability in the
common understanding of the meaning and primary KSAs are scored as a “borderline
application of the evaluation criteria. fail.” Solutions that fail to demonstrate
Several examples of solutions are scored as minimum competence in the subject area
a group until the graders become are scored as “fail.”
comfortable with the application of the
criteria. Throughout the grading session, If the scores of the first two graders are not
Master Graders “correlate” exams to ensure the same for any one vignette, and if the
that all graders apply the grading criteria resolution of that discrepancy could affect
uniformly to all solutions. If any grader the pass/fail status of the candidate, the
starts to deviate from the established vignette is rescored by a Master Grader.
criteria, the Master Grader provides
additional instruction until the grader is back The graders complete a computer-scanned
on track. score sheet for each exam booklet, using
the evaluation criteria for each problem.
During the grading session, each exam The completed score sheet is removed from
solution is evaluated by two different the test booklet and sent through a
graders. Exam booklets are given to computer scanner to record the grader’s
graders randomly. Graders do not know the score before the exam booklet is sent on to
jurisdiction from which the exam originated receive additional evaluations. This process
nor the identity of the examinee. In ensures that no grader will be biased by
addition, the scores assigned by the first marks recorded from another grader.
grader are concealed from the second
grader.
32
A Step by Step Guide to the L.A.R.E.
33
A Step by Step Guide to the L.A.R.E.
Grader #1
Master Graders
Scores Train Graders
Exam
are to Evaluate
Scanned Solutions
into the Grader #2
Computer
Any Scoring
Differences are
Resolved by a
Master Grader
34
A Step by Step Guide to the L.A.R.E.
35
A Step by Step Guide to the L.A.R.E.
36
A Step by Step Guide to the L.A.R.E.
37
A Step by Step Guide to the L.A.R.E.
38
A Step by Step Guide to the L.A.R.E.
39
A Step by Step Guide to the L.A.R.E.
40
A Step by Step Guide to the L.A.R.E.
41
A Step by Step Guide to the L.A.R.E.
revised repeatedly. Final draft items are satisfaction that they get from knowing that
then reviewed by professional test editors their efforts are helping to ensure the future
who check for appropriateness and clarity of landscape architecture.
and ensure that the exams are not biased
against any candidate sub-population. The Cost Per Candidate
The exams are then printed and securely
As in any business, the cost per unit of a
distributed to test centers for administration.
product is equal to the total production cost
Completed exams are collected for scoring
divided by the number of units produced.
and two more rounds of statistical analysis
For the L.A.R.E., the cost per candidate is
and review. Graphic solutions are graded at
equal to the total production cost divided by
least twice and as many as four times by
the number of exam candidates.
licensed professionals.
Obviously, the costs for producing a high With the exception of the printing and
stakes test like the L.A.R.E. are significant. scoring of graphic exams, however, the cost
Each edition involves more than 8,000 to produce the L.A.R.E. is not volume
hours of labor to produce and grade. There dependent. That is, it takes the same level
are also costs for consultants, meeting of effort to produce a test for 1,000
facilities, printing and shipping, in addition to candidates as it does for 10,000 candidates.
other indirect expenses such as
management, insurance, interest and other Obviously, when we divide the total cost to
overhead items. produce the L.A.R.E. by the number of
candidates, the cost per candidate should
If added together, the cost of producing be in excess of $2,000, not including the
each edition of the L.A.R.E. would exceed cost for application and administration
$1,000,000! Fortunately for exam expenses. Fortunately, due to the
candidates, the actual cost of producing the significant subsidy provided by the
L.A.R.E. is heavily subsidized by licensed landscape architect volunteers, the actual
landscape architects from across the U.S. cost to the candidate for the L.A.R.E. is less
and Canada. These professionals donate than $1,000 and is in keeping with the cost
their time to work on CLARB committees to of licensing exams for many other licensed
prepare and grade the L.A.R.E. In total, professions.
they contribute more than 3,500 hours each
year. Their only compensation is the
42
A Step by Step Guide to the L.A.R.E.
Is the L.A.R.E. Worth the Cost? Licensure is also an important part of your
professional development process. It puts
you on par with other professionals with
The cost to take the Landscape Architect
whom you will interact. It allows you to lead
Registration Examination is significant. You
design teams, to be the decision-maker and
should carefully consider whether you are
to take professional responsibility for your
ready to take the test and you should
work. Licensure allows you to legally call
prepare carefully to do so. In the end, is it
yourself a landscape architect.
worth the time, effort and cost? Most
definitely!
For a person to go through college, acquire
Strictly from a financial point of view, taking the needed practical experience and not get
the L.A.R.E. may be one of the best licensed would be similar to a person not
investments you can make. Studies show getting a degree after completing all but one
that, on average, licensed professionals course in a college curriculum. Given that
make considerably more income each year the cost of the L.A.R.E. is less than the cost
than unlicensed individuals. In addition, of a typical three credit hour course in
licensed professionals have many more college, it is illogical that an individual who
opportunities for employment, advancement is otherwise qualified would not complete
and ownership positions than non-licensed this important step in his/her professional
individuals. Over the course of a development process.
professional career, the licensure process
will return in income many times the amount The bottom line is that the investment in
of money it cost. terms of time and money that you put into
becoming a licensed landscape architect is
one of the best investments that you will
ever make.
43
The Landscape Architect
Registration Examination
September 2008
Table of Contents
Appendix 5 – Understanding the Codes Used on Sections C and E.......................... 1
The L.A.R.E. Reference Manual ............................................................... 1
Codes That Apply to Section C – Site Design ................................................ 2
Setbacks ........................................................................................ 2
Active Recreation Uses ...................................................................... 3
Vehicular Requirements ..................................................................... 3
Codes That Apply to Section E – Grading, Drainage and Stormwater Management ... 4
Curb Ramps .................................................................................... 4
Ramps........................................................................................... 4
Steps ............................................................................................ 5
Appendix 6 – Becoming Familiar with the L.A.R.E. (Sample Items) ........................ 6
Section A – Project and Construction Administration...................................... 6
Section B – Inventory, Analysis and Program Development .............................. 16
Section C – Site Design......................................................................... 27
Practice Problem 1: ......................................................................... 27
Practice Problem 2: ......................................................................... 34
Practice Problem 3: ......................................................................... 40
Section D – Design and Construction Documentation ..................................... 45
Section E – Grading, Drainage and Stormwater Management ........................... 59
Practice Problem 1: ......................................................................... 59
Practice Problem 2: ......................................................................... 65
Practice Problem 3: ......................................................................... 71
Appendix 7 – Now What? ......................................................................... 77
How to Get Prepared........................................................................ 77
A Step by Step Guide to the L.A.R.E.
1
A Step by Step Guide to the L.A.R.E.
Setbacks
Page 1 of the L.A.R.E. Reference Manual
provides information on various setbacks
that you will need to apply to your solutions.
There are property line setbacks for both
circulation routes and buildings. It is
important to remember that when a property
line is shown along a road bordering the
property, it is considered the roads right-of-
way and requires a larger setback.
2
A Step by Step Guide to the L.A.R.E.
Page 2 includes additional pedestrian The code for vehicle turning radii, found on
security and safety codes for sports facility page 3, is one that candidates tend to
orientation. Sports fields are usually forget. A vehicle should be able to drive
oriented to protect the participants from through your entire design while meeting
injuries related to glare from the sun. the minimum radius requirement.
Especially important are entry and exit
points where the lack of a proper radius
Vehicular Requirements would force a car into oncoming traffic.
The vignettes which require you to X = 18' [5.5m] Cars; 30' [9.1m] Large Vehicles
Z
demonstrate an understanding of circulation
Y
3
A Step by Step Guide to the L.A.R.E.
Page 4 includes the requirements for around. How would you like to get in a
stacking at a use with a drive-up window. drive through lane by mistake and not be
Typically cars are waiting in line and there able to get out until everyone in front had
must be sufficient space to accommodate placed their order?
these waiting vehicles.
Pages 5 through 10 refer to accessibility
Drop-off/Pick-up areas and service areas codes that are important to incorporate in
are also described in this section. For both your design. These codes are taken from
the stacking areas and drop-off areas, it is the ADA and you should be familiar with
important to remember to place a bypass current ADA guidelines when designing all
around any stopped vehicles. If you were to of your projects.
create a one-lane road, a vehicle stopped at
a drop-off or waiting in line at a window .
would impede anyone else's ability to get
4
A Step by Step Guide to the L.A.R.E.
5
A Step by Step Guide to the L.A.R.E.
Question 1: During the course of construction, the landscape architect discovers an error in
the construction that may cause a portion of the project used by the public to fail. The
landscape architect informs the client, but the client refuses to allow corrections to be made.
The landscape architect should do which of the following?
A. I only
B. II and III only
C. I, III and IV only
D. I, II, III and IV
6
A Step by Step Guide to the L.A.R.E.
A. Experience and reasonable care, skill and diligence in performing his/her duties
B. Follow the owner's instructions
C. Maintain the trust and confidence owed to the owner
D. Maintain the owner's position in rendering decisions about disputes with the
contractor
A. incompetence.
B. a conflict of interest.
C. turn key.
D. performance bonding.
A. Refuse to contribute
B. Contribute
C. Contribute but inform his client
D. Provide full disclosure and contribute
Question 5: When the nature of a project extends beyond the competence and experience
of the practitioner,
Rationale: Code of Ethics – a professional may only undertake services that he or she is
qualified by education, training and experience to perform.
Exam Subsection: Standards of Practice
7
A Step by Step Guide to the L.A.R.E.
Question 6: A landscape architect has been out of town and is unable to seal a set of
documents. The landscape architect asks a colleague and former business partner to attend to
this responsibility by quickly reviewing the work and applying the seal. If the colleague carries
out this request, the colleague will
Rationale: Code of Ethics – a professional must have direct professional knowledge and direct
supervisory control to seal a drawing.
Exam Subsection: Standards of Practice
Question 9: The basic rights and responsibilities of the landscape architect during the
construction of a project are described in which of the following?
A. General Conditions
B. Special Conditions
C. Division 1
D. Division 2, Part 1
8
A Step by Step Guide to the L.A.R.E.
Question 10: Work that does not conform to the drawings and specifications requires the
landscape architect to
Rationale: Construction Law Principles and Practice, Jervis and Levin, page 71
Exam Subsection: Construction Evaluation
Question 11: Plans and specifications may contain discrepancies or deficiencies that may
lead to which of the following?
A. II only
B. I and III only
C. I, II and III only
D. I, II, III and IV
Question 12: The phrase "The owner shall pay the amounts being determined by actual
measured quantities" suggests which of the following contract types?
A. Unit price
B. Time and materials
C. Prime and target
D. Guaranteed maximum and shared-savings
9
A Step by Step Guide to the L.A.R.E.
Question 13: A construction contract awarded by direct selection and negotiation with a
single contractor could typically offer which of the following advantages?
I. Ensures the best possible price for the work being completed
II. Allows contract negotiations to commence prior to completion of drawings
III. Permits the project to be built with less detailed construction drawings
IV. Reduces the need for construction supervision
Question 14: At what point in the project does the landscape architect first advise bidders
of bonding requirements?
A. Instructions to Bidders
B. General Conditions
C. Bid Form
D. Contract Award
Question 15: Despite a contract requirement to carry out site investigations prior to
commencement of work, a contractor damaged a gas line. The gas line was not shown in the
consultant's contract documents, but was on the survey plan prepared for the project. Who
would most likely be responsible?
A. The contractor
B. The owner of the property
C. The gas company
D. The consultant and contractor
Rationale: The consultant is liable for omissions to the contract documents and the contractor is
liable for failing to carry out site investigations required by the contract.
Exam Subsection: Contract Administration
10
A Step by Step Guide to the L.A.R.E.
Question 16: Which of the following is the most important factor by which to pre-qualify a
bidder?
A. Bonding capacity
B. Number of subs
C. Previous similar experience
D. Size of company
Question 17: Which of the following are typically included in the bid form?
I. Bid price
II. Completion time
III. Verification that bidder visited the site
IV. Acknowledgement of addenda received
A. I and II only
B. III and IV only
C. I, III and IV only
D. I, II, III and IV
Question 18: Which of the following are conditions for potential change orders?
A. I and II only
B. III and IV only
C. I, II and IV only
D. I, II, III and IV
11
A Step by Step Guide to the L.A.R.E.
A. when the owner and contractor agree on the changes in the work, adjustment in contract
sum, and contract time.
B. in the absence of agreement on the adjustment in the contract sum.
C. when changes in the work do not involve adjustments to the contract sum or time.
D. in the absence of total agreement on the terms of the change order.
Rationale: AIA Document A201, Article 7.3, page 15. A. is a change order. B. is a contemplated
change. C. is a field change.
Exam Subsection: Contract Administration
Question 20: Which of the following must the contractor submit before receiving final
payment?
A. I and II only
B. III and IV only
C. I, III and IV only
D. I, II, III and IV
Rationale: AIA Document A201, General Conditions of the Contract for Construction, AIA
Exam Subsection: Construction Evaluation
Question 21: Which type of contract is best used when the drawings and specifications are
not complete at the time of construction contract negotiation?
12
A Step by Step Guide to the L.A.R.E.
A. I and II only
B. III and IV only
C. I, III and IV only
D. I, II, III and IV
Question 24: The pre-qualification of a contractor for bidding would typically entail
documentation of which of the following types of information?
I. Evidence of insurability
II. A corporate roster
III. Bank records
IV. Construction safety records
A. I only
B. I and II only
C. II, III and IV only
D. I, II, III and IV
13
A Step by Step Guide to the L.A.R.E.
Question 25: A general contractor may rescind a bid on a project under which of the
following circumstances?
A. I and II only
B. III and IV only
C. I, II and III only
D. I, II, III and IV
Rationale: Principles and Practices of Construction Law, White, Nancy, page 152
Exam Subsection: Contract Administration
Question 26: Under which of the following circumstance would a change in work performed
require additional payment by the owner to a contractor?
Question 27: Who is responsible for producing a punch list [deficiency list]?
A. The owner
B. The landscape architect
C. The contractor
D. Individual subcontractors
A. the contractor.
B. the landscape architect.
C. the owner.
D. the project prime.
14
A Step by Step Guide to the L.A.R.E.
Question 30: Evaluating construction for conformance at project closeout includes which of
the following?
A. I and II only
B. II and IV only
C. I, III and IV only
D. I, II, III and IV
Rationale: Landscape Architect’s Portable Handbook, Dines and Brown, page 395
Exam Subsection: Construction Evaluation
15
A Step by Step Guide to the L.A.R.E.
Question 1: Which of the following are necessary to determine appropriate plant material
for a project?
I. Hardiness zone
II. Available sunlight
III. Soil conditions
IV. Average rainfall
Rationale: Information of all four conditions is necessary for appropriate selection. Temperature
determines hardiness. Sunlight determines light conditions and availability, soil determines pH
and character (organic matter, clay, loam, well drained etc.); rainfall will affect adaptability to
conditions such as too much or too little moisture; while too little can be supplemented with
irrigation, too much can be detrimental.
Exam Subsection: Inventory
A. A soil survey
B. A quad map
C. A topographic map
D. An aerial survey
16
A Step by Step Guide to the L.A.R.E.
Question 3: What legal document indicates new property lines on a subdivided lot?
Rationale: When searching for a client’s current property lines and/or boundaries, this map is
needed to determine any changes in the property lines.
Exam Subsection: Inventory
Question 4: Transfer of development rights could be used to protect which of the following?
I. Historic landmarks
II. Historic districts
III. Agricultural lands
IV. Natural resources
A. I and II only
B. III and IV only
C. I, II and IV only
D. I, II, III and IV
Question 5: For office and residential projects, density can be controlled by defining which
of the following?
A. I and II only
B. III and IV only
C. I, II and IV only
D. I, II, III and IV
17
A Step by Step Guide to the L.A.R.E.
A. soil types.
B. historic land uses.
C. soil qualities.
D. topography.
I. Property lines
II. Easements
III. Wetlands
IV. Contour lines
A. IV only
B. I and II only
C. I, II and III only
D. I, II, III and IV
18
A Step by Step Guide to the L.A.R.E.
Question 9: Which of the following types of aerial photography would best be utilized as
part of a large-scale site analysis to detect vegetation under stress due to disease?
A. Panchromatic photography
B. Color [colour] infrared photography
C. Thermal infrared imagery
D. Side looking airborne radar
Question 10: Vegetation can affect the perception of air temperatures by reducing
A. air movement.
B. excess particulate matter.
C. humidity.
D. shade.
Question 11: Which of the following may be beneficial when engaged in the mapping of
wetlands as part of the site analysis process?
I. Wetland inventory
II. Soils maps
III. Aerial photography
IV. On-site field assessment
A. I and II only
B. I and IV only
C. III and IV only
D. I, II, III and IV
19
A Step by Step Guide to the L.A.R.E.
Question 12: Which of the following would be requested for a project that proposes higher
densities and mixed uses on some portions of the site and preservation of open space on
others?
A. Spot zoning
B. Variance
C. Planned Unit Development
D. Conditional use permit [site specific zone]
Question 13: Sewer and water services on a street would most often be designed to meet
a
A. subdivision regulation
B. development covenant
C. building code
D. health and safety code
Question 14: Which of the following should be identified to determine surface drainage
characteristics?
I. Watershed
II. Seasonal fluctuations
III. Water table depth
IV. Water quality
A. I and II only
B. II and III only
C. I, III and IV only
D. I, II, III and IV
20
A Step by Step Guide to the L.A.R.E.
Question 15: Which of the following construction systems is best for use in littoral zones?
Question 16: In assessing the potential for flooding on a large site, which of the following
factors should be considered?
A. I and II only
B. I, III and IV only
C. II, III and IV only
D. I, II, III and IV
Question 17: When assessing the drainage characteristics of a site, the landscape
architect's primary consideration should be to
21
A Step by Step Guide to the L.A.R.E.
Question 18: On the site shown, which location would have the most favorable
microclimate for site development in a hot, humid climate?
A.
B.
C.
D.
Rationale: Time-Saver Standards for Landscape Architecture, page 220-7. Sitting near the top
of a slope maximizes exposure to breezes. Eastern orientation minimizes solar heat gain.
Exam Subsection: Analysis
22
A Step by Step Guide to the L.A.R.E.
Question 19: Which of the following attributes can be combined to produce a solar
radiation map?
I. Slope
II. Aspect
III. Vegetation
IV. Soils
A. I and II only
B. III and IV only
C. I, II and III only
D. I, II, III and IV
Question 20: On which coastal site would one expect to find the greatest accumulation of
sand?
A. Site A only
B. Site B only
C. Site C only
D. Approximately equal accumulation on each site
23
A Step by Step Guide to the L.A.R.E.
Question 21: Which of the following proposed locations would typically be the most
economical for a road system?
A. Along ridgeline
B. Within watershed
C. Perpendicular to contours
D. Along drainage swales
Question 22: Which of the following will encourage contact between neighbors
[neighbours]?
Question 23: A water quality analysis of a watershed should develop data and information
about which of the following?
A. vegetative structure
B. soil structure
C. water table
D. elevation
24
A Step by Step Guide to the L.A.R.E.
Question 25: In colder climates, which of the following is considered the favored site?
Question 26: In selecting a site for a sanitary landfill, which of the following criteria is the
most critical to consider in evaluating the potential for negative environmental impacts?
Question 27: In a temperate region, site selection for residential developments should
consider which beneficial climatic factors?
A. High elevations on windward side of slopes; breeze utilization in cool periods; windbreaks
against NE storms
B. SSE slopes; breeze utilization in cool periods; evergreen windbreaks in NE-SW direction
C. SE slopes; breeze utilization in warm periods; windbreaks against NW winter winds
D. NNE slopes; breeze utilization in summer only; windbreaks against SE storms
Question 28: Which of the following conditions would NOT pose a potential limitation on
the siting of a septic leaching field?
Rationale: A. will not allow the leach lines to function properly; C. and D. would allow the
groundwater aquifer to become contaminated
Exam Subsection: Programming
25
A Step by Step Guide to the L.A.R.E.
Question 29: Which of the following sites could reasonably support a tennis club program
requirement of 16 tennis courts, 2,500 ft2 [250 m2] tennis club building and surfaced parking for
50 cars, if no more than 1/3 of the site can be developed into impervious area?
Rationale: Tennis = 2.64 ac.; Bldg. = 0.06 ac.; Parking = approx. 0.35 ac.; Total = 3.05 ac. x 3 =
9.15 ac.
Exam Subsection: Programming
Question 30: A gently sloping 60-acre [24-hectare] site was previously a construction
debris fill site with a cover of soil 4’ to 6' [1.2m - 1.8m] deep. Which development program
would best fit the site with the least disturbance to the debris fill?
26
A Step by Step Guide to the L.A.R.E.
Site planning is important to the protection of the environment. Locating uses that do not fit the
topography or that disturb the existing environment can be devastating to the ecosystem for
decades to come. Good design also benefits the people using it. Proper site planning impacts
the welfare of the public and encourages safer environments.
Practice Problem 1:
You should download the problem and solve it before proceeding on to the problem solutions.
Download from www.clarb.org/Candidates/ExamResources/Documents/SampleC1.pdf.
Included in this chapter are several candidate interpretations of this problem and how the
solutions might be evaluated. You should compare your solution to these other candidate
solutions to see where you may have a weakness and determine what areas you should focus
on before taking the exam.
This problem is testing two distinct competencies from the specifications for Section C:
If you look at the soil information first, you can see that soil types 1 and 3 are acceptable for just
about any type of construction. Soil type 2 has organic soil below 3’ that may be problematic for
building foundations. The water table is also fairly high in this soil profile.
You are required to locate two sports fields and a small building. If you remember the
information from the L.A.R.E. Reference Manual, you will recall that there is information
pertaining to sport field orientation and to setbacks for athlete safety. You should look back to
the L.A.R.E. Reference Manual and make sure you understand how to apply those codes.
27
A Step by Step Guide to the L.A.R.E.
If you compare the site to the soil map from the consultant, you will see that the soil type 2,
which had some issues, is generally located below the 285 contour. You should consider this
when placing your project elements.
You are also constrained by the existing facilities and the existing trees. Although you could
destroy trees to make the site work well, it would be better to be environmentally friendly and
conserve as much as possible.
The site topography is generally flat with the exception of a steep slope between the 285 and
290 contour.
28
A Step by Step Guide to the L.A.R.E.
Candidate Solution 1
This candidate must have been concerned with soil type 2. A decision was made to destroy
existing vegetation over constructing any element on soil type 2.
We can see that the candidate must have consulted the L.A.R.E. Reference Manual based on
the notes for the baseball orientation and the 30’ setback from the parking lot.
The biggest problem is that the candidate failed to indicate a vegetation removal zone that
would ensure the 30’ active recreation setback. If a soccer player were to run off of the field, a
potential injury could occur if there were existing tree trunks in the 30’ setback.
Although the baseball orientation is acceptable, the field is not oriented in the E/NE direction
specified in the L.A.R.E. Reference Manual. The soccer orientation is good and the
maintenance building is located in close proximity to both fields.
29
A Step by Step Guide to the L.A.R.E.
Candidate Solution 2
The second candidate chose to avoid removing trees and placed the soccer field and
maintenance building further south on the site. It is also evident that this candidate referred to
the L.A.R.E. Reference Manual and ensured that the active recreation was provided with a 30’
buffer zone.
Part of the soccer field is located on soil type 2 and the maintenance building is right on the
border of two soil types.
Again, the field orientation for both uses is acceptable; however, the baseball is not optimally
oriented per the L.A.R.E. Reference Manual. The soccer has been placed over the steep slope
on the site which will cause excessive grading and increase the costs of the development. A
small portion of the building has been placed on soil type 2. Although only a portion of the
building is located on poor soils, we have determined that soil type 2 will not support a building
foundation. This error would convince a grader that the candidate has not considered the
implications of the consultant’s information that was provided as part of this project.
30
A Step by Step Guide to the L.A.R.E.
Candidate Solution 3
The third solution avoids the existing trees by placing the entire soccer field on soil type 2. The
maintenance building is placed between the fields above the 290 contour along with the
baseball diamond. The baseball field has been oriented towards the existing high school.
The baseball field orientation is the biggest problem on this solution. The problem statement
asked us to optimize the orientation of the sports fields. In this case, the batters would be
looking into the afternoon sun, which could result in athlete injury.
Although this candidate did not dimension or label the 30’ active recreation zone around the
sports fields, the design adheres to the setback and would be acceptable.
The soccer field is located on soil type 2. Although this is not the best soil, it would be
acceptable for a soccer field. There are no foundations that would be required in the poor soil
layer and the high water table would not be disturbed by grading.
31
A Step by Step Guide to the L.A.R.E.
Candidate Solution 4
The fourth candidate solution locates all of the project elements below the 285 contour. The
maintenance building is directly adjacent to the soccer field and all uses have been located to
avoid tree removal.
This solution fails to take the soil information into account. Both the maintenance building and
the baseball grandstands are located on soil type 2. The soil profile indicates that neither
structure will be properly supported in this location.
This candidate has also failed to consider the active recreation setback. A soccer player
running off the field could be injured by running into the maintenance building or into the existing
trees to the north and east of the field.
32
A Step by Step Guide to the L.A.R.E.
Candidate Solution 5
The last solution locates the baseball field and maintenance building north of contour 290, while
the soccer field is located below 285. The candidate has indicated a 30’ active recreation
setback around both fields as per the L.A.R.E. Reference Manual.
This solution works very well. The candidate has oriented the fields properly and incorporated
the other L.A.R.E. Reference Manual codes into the solution. The design considers the soil
information and locates uses based on the existing site constraints.
33
A Step by Step Guide to the L.A.R.E.
Practice Problem 2:
You should download the problem and solve it before proceeding on to the problem solutions.
Download from www.clarb.org/Candidates/ExamResources/Documents/SampleC2.pdf
Included in this chapter are several candidate interpretations of this problem and how the
solutions might be evaluated. You should compare your solution to these other candidate
solutions to see where you may have a weakness and determine what areas you should focus
on before taking the exam.
This problem is testing two distinct competencies from the specifications for Section C:
You have been given two conceptual diagrams for a regional park office and are asked to
evaluate which solution works better in terms of circulation safety, codes and functional
relationships.
Once you have selected a concept, you will need to draw a final site plan incorporating all of the
code requirements from the L.A.R.E. Reference Manual. Before you start your design, it is a
good idea to think about the codes that may apply to this design.
Applying setbacks will be important to your design solution. You may want to draw them on the
site before you proceed. Circulation must be 10’ from property lines and 15’ from right-of-way
lines such as the property line along Park Road. Buildings must be setback at least 15’ and 25’.
We also have a stream that requires a 50’ setback.
You will want to be familiar with all of the circulation codes, such as minimum turning radius,
intersection offset, parking lot dimensions and the general rules concerning primary circulation
routes. You must provide 12 parking spaces for the park office. Don’t forget to look up how
many accessible parking spaces that you need. You must also locate the park gate and
consider how vehicles can access the park office even if the park is closed.
34
A Step by Step Guide to the L.A.R.E.
Candidate Solution 1
The first solution is based on concept one. The candidate has provided the 12 car parking lot
and has indicated return circulation to show that the parking does not violate the dead end
parking lot code. Visitors can access the parking lot even when the park gate is closed. A turn
around is provided on the park side of the circulation drive as per the given concept.
The biggest problem with this solution is that the candidate chose the wrong solution to refine.
The concept does not allow a vehicle to come into the site and turn around if the park gate is
closed. The vehicle turnaround has been provided on the wrong side of the gate which serves
no purpose when the park gate is closed.
In addition, the concept indicated the park office building too close to the existing stream. The
candidate followed along with the concept and violated the 50’ stream setback required by the
L.A.R.E. Reference Manual. The parking circulation also does not work properly. The radius at
the end of the parking lot does not meet code and will not allow vehicles to turn around. In fact,
because the turning radius does not function and the parking lot circulation is one-way, the
parking lot essentially has been designed as a dead end parking area.
35
A Step by Step Guide to the L.A.R.E.
Candidate Solution 2
The second candidate selected concept two to refine. The solution indicates a one-way parking
lot and a separate drive to bypass the parking.
There are several problems that occur with this solution. A critical problem is that visitors that
enter the site when the park is closed may come to the gate and not be able to turn around to
leave. First they would have to back up to the parking exit only to find that the drive is one-way
out and legally they would not be able to turn around.
Another major problem is that the parking lot aisle is not wide enough. Even though the drive
meets the minimum road width for one-way travel, in a parking lot, 11’ is not sufficient for a car
to be able to back out of a space. One-way circulation is okay in a parking lot as long as the
aisle is wide enough for a car to back out - 20’ minimum.
The extra travel lane in front of the building provides a pedestrian/vehicular conflict because the
pedestrian crossing is not in an expected location. The lane may have been shown to provide a
drop-off location for the building, but at one lane width, a stopped vehicle would back up traffic
which violates the codes on primary circulation routes.
The entry at Park Road also joins without the required 18’ minimum radius. Exiting cars would
be forced into oncoming traffic when leaving the site.
36
A Step by Step Guide to the L.A.R.E.
Candidate Solution 3
The third solution is based on the correct concept and provides the required 12 parking spaces.
This candidate chose to locate the parking spaces directly on the park access road and located
the park gate right at the end of the parking lot.
The biggest problem here is that cars are forced to back into the major traffic flow entering and
exiting the park. This violates the rules concerning primary circulation routes. As per the
concept, parking should be pulled off of the primary circulation route to provide a safer vehicular
traffic pattern. Because the parking is directly on the entry road, the parking also becomes a
dead end lot when the gate to the park is closed.
This solution also fails to incorporate an accessible parking space as required by the L.A.R.E.
Reference Manual. The accessible parking space would be included as one of the 12 required
spaces.
37
A Step by Step Guide to the L.A.R.E.
Candidate Solution 4
This candidate has also refined the second concept. The parking has been pulled off of the
major circulation route to ensure that vehicles would not back into traffic. The parking uses a
one-way circulation system and the candidate has placed the park gate at the beginning of the
stream crossing.
Once again, the visitors entering the site when the park is closed will not be able to turn around
if they drive to the gate. The entry drive prior to the gate is in excess of 100’ without a turn
around and the parking exit is one-way, making it illegal for a vehicle to turn around at the exit
drive.
This candidate also included two accessible spaces when only one is required. This indicates
to the grader that the candidate did not apply the L.A.R.E. Reference Manual code correctly.
Outside of the turn around issue with the one-way parking lot aisle, the parking circulation will
work correctly. The aisle width shown in the parking area is 24’, allowing cars to back out easily
from the parking spaces.
38
A Step by Step Guide to the L.A.R.E.
Candidate Solution 5
The final solution also pulls the parking off of the main road as indicated in the second concept.
In this case the parking lot circulation is two-way and the gate location allows visitors to turn
around when the park is closed. The minimum turning radii have been provided throughout the
design and the accessibility codes have been met in the parking lot.
This solution has met all of the requirements of the problem statement and has incorporated the
necessary codes from the L.A.R.E. Reference Manual. The setback indications are not
necessary for the final solution. However, drawing the setback lines probably helped the
candidate ensure that all of the codes had been met.
39
A Step by Step Guide to the L.A.R.E.
Practice Problem 3:
You should download the problem and solve it before proceeding on to the problem solutions.
Download from www.clarb.org/Candidates/ExamResources/Documents/SampleC3.pdf
Included in this chapter are several candidate interpretations of this problem and how the
solutions might be evaluated. You should compare your solution to these other candidate
solutions to see where you may have a weakness and determine what areas you should focus
on before taking the exam.
This problem is testing two distinct competencies from the specifications for Section C:
You have been asked to create a site plan for a neighborhood park considering the on-site and
off-site conditions.
You will need to draw a final site plan incorporating all of the code requirements from the
L.A.R.E. Reference Manual. Before you start your design, it is a good idea to think about the
codes that may apply to this design.
Applying setbacks will be important to your design solution. You may want to draw them on the
site before you proceed. There is a stream that requires a 50’ setback. You should also
consider the setback and orientation issues associated with sports facilities as they are part of
this design. You will also need to consider the description of each use and make a
determination as to its placement on the site.
To respond to the second competency tested, you will need to provide a summary of the
implications of having this use on this site. The summary must address the implications to the
environment, to the external land uses and to traffic flow.
40
A Step by Step Guide to the L.A.R.E.
Candidate Solution 1
The biggest problem with this solution is that the candidate failed to consider the setback
requirements defined in the L L.A.R.E. Reference Manual. The trail and the playground are
placed within the 50’ stream setback. The 30’ active recreation setback is violated in three
locations. This would cause injuries for those passing by the field or for the players if they ran
off of the field.
Another problem is with the relationship to the off-site uses. The conifers can be used to help
protect the neighbors from the lights of the late night uses. However, the solution locates
elements where they will disturb the adjacent homes.
41
A Step by Step Guide to the L.A.R.E.
Candidate Solution 2
This solution considered all of the required setbacks and even indicated the setbacks on the
plan. The uses are located to help prevent disturbance to the adjacent homeowners and the
trail connects all of the uses to the neighborhood for easy access.
This solution works well and responds to the site planning competency being tested.
42
A Step by Step Guide to the L.A.R.E.
Candidate Solution 3
The playground was located to give the best access to the residential area and parking. The
pool, basketball and tennis courts were located near the commercial area so the lighting would
not be a problem to the residential area.
The soccer area was located in the open area to give access from all points into the park.
The solution to the written summary does not meet the requirements of the competency being
tested. This solution describes why the uses were placed on the site. The problem statement
specifically says not to describe the location of your elements, but to describe the specific
impact this use will have on both on-site and off-site conditions.
The solution does not address the environmental impact or traffic flow at all and does not
address the implications of having a neighborhood park in this location.
Candidate Solution 4
There will be a very low impact on the environment with the addition of the park. Specifically, no
trees will be removed and the creek will be preserved. The park location is in a prime spot
mainly because of the large amount of residential that surrounds the site. Locating more
children oriented activities away from the commercial will keep the younger users away from
busier commercial streets. The park location is also very accessible to users coming in from
five different access points. This spreads out the pedestrian and vehicular traffic.
In summary, the park is in a prime location that caters nicely to the large amount of residential.
This candidate does a better job of describing the predicted implications of having the park on
this site. However, the candidate fails to recognize some of the negative aspects of the park.
The construction of bridges over the stream and the runoff from fertilized fields will have an
impact on the quality of the stream. The candidate also fails to recognize the impact of the
noise and light from the park uses on the adjacent residential homes.
43
A Step by Step Guide to the L.A.R.E.
Candidate Solution 5
The introduction of this neighborhood park will have an environmental impact due to both the
increased use and increase in impervious surface. Some mitigation efforts are recommended to
minimize adverse impact. On the positive side, the type of use will protect the existing
vegetation on the site and will require minimal grading.
Although the park will certainly be an amenity, it will also be felt by the adjacent single family
community. Light and noise will be a problem for the homes that are directly adjacent to the
site.
Traffic flow will certainly increase. Existing parking and surrounding infrastructure may need
analysis during the planning process to avoid future traffic problems.
This solution works very well. The candidate describes both the positive and negative impacts
that this use will place on the site and surrounding properties. The environment, the relationship
to external land uses and the effect on traffic flow have all been addressed.
44
A Step by Step Guide to the L.A.R.E.
Question 2: Which of the following are items that should be considered in designing
signage for roadway usage?
A. I, II and IV only
B. I, II and V only
C. I, III and IV only
D. II, III and IV only
45
A Step by Step Guide to the L.A.R.E.
A. Slope
B. Vegetative cover
C. Water table
D. Soil type
Question 4: Which of the following occurs when excessive sediment settles in a stream
channel?
A. detail number
B. key to the plant list
C. sheet number where the detail is shown
D. revision number
X
Y
Rationale: Time-Saver Standards for Landscape Architecture, Harris and Dines, page 110-9
Exam Subsection: Graphic Communication
46
A Step by Step Guide to the L.A.R.E.
Question 6: Which of the following are appropriate to use when specifying the quality of
workmanship in a specification?
A. I and II only
B. I, II and III only
C. I, III and IV only
D. II, III and IV only
A. Performance
B. Shop drawing preparation
C. A full commissioning of the product
D. A cost plus fee contract
A. I and II only
B. III and IV only
C. I, II and III only
D. I, II, III and IV
Rationale: Time-Saver Standards for Landscape Architecture, Harris and Dines, pages 110-118
Exam Subsection: Construction Documentation
47
A Step by Step Guide to the L.A.R.E.
Rationale: Data Sheets Issued by Scofield Engineered Systems for Coloring and Texturing
Architectural Concrete
Exam Subsection: Construction Documentation
Question 10: Upon evaluation of a newly constructed deck, the deck boards bounce under
load. This is the result of which of the following?
Question 11: Which of the following are characteristics of a well designed wetland area?
A. I and II only
B. II and IV only
C. III and IV only
D. I, II, III and IV
48
A Step by Step Guide to the L.A.R.E.
Question 12: Given the indicated curb height, which of the following items is the most
appropriate for X?
A. 24" [600mm]
B. 26" [650mm]
C. 30" [750mm]
D. 32" [800mm]
E. 34" [850mm]
F. 3' [1.0m]
G. 3½' [1.1m]
H. 4' [1.2m]
I. 5' [1.5m]
Question 13: What is the recommended minimum depth of water in a pool in order to
provide a satisfactory return system, display jets and submerged lights?
A. 4" [10cm]
B. 12" [30cm]
C. 24" [60cm]
D. 36" [90cm]
Rationale: Time-Saver Standards for Landscape Architecture, page 530-15 “Key Points”, item 4
Exam Subsection: Materials and Methods of Construction
49
A Step by Step Guide to the L.A.R.E.
Question 14: For play equipment which is more than 20" [500mm] off the ground, a shock-
absorbing surface should extend no less than
Question 15: Given a frost depth of 23" [575mm], which of the following is the minimum
appropriate dimension for A?
A. 16" [400mm]
B. 18" [450mm]
C. 20" [500mm]
D. 22" [550mm]
E. 24" [600mm]
F. 26" [650mm]
G. 30" [750mm]
H. 32" [800mm]
I. 34" [850mm]
50
A Step by Step Guide to the L.A.R.E.
Question 16: Which of the following erosion control techniques would best be utilized to
direct sediment away from a local street and into a temporary sediment basin?
A. Diversion ditch
B. Hay bales
C. Silt fence
D. Check dam
Question 18: The strength of brick masonry walls depends mainly on which of the
following?
I. Brick pattern
II. Individual strength of masonry units
III. Mortar strength
IV. Shape of the brick
A. I and IV only
B. II and III only
C. II and IV only
D. I, III and IV only
Question 19: How is plant health affected by a reduction in available phosphorous and
potassium?
51
A Step by Step Guide to the L.A.R.E.
Question 20: Evaluate the detail and determine if there is an error in the detail. Which of
the following is the most correct statement concerning the detail shown?
Rationale: The detail is missing a joist hanger. Toenailing will not adequately support the joist.
Exam Subsection: Materials and Methods of Construction
52
A Step by Step Guide to the L.A.R.E.
Question 21: Which of the following table designs is most suitable for wheelchair
accessibility?
A.
B.
C.
D.
Question 22: In determining the amount of available water in fountain design, the amount
of water pressure is calculated in terms of
53
A Step by Step Guide to the L.A.R.E.
Question 23: Which of the following is a shortcoming of poured-in-place concrete for pool
or fountain construction?
Question 24: Which of the following are functions of wall ties and veneer anchors?
54
A Step by Step Guide to the L.A.R.E.
Question 25: Evaluate the detail and determine if there is an error in the detail. Which of
the following is the most correct statement concerning the detail shown?
Rationale: The deck guardrail cannot be safely attached to the wood decking.
Exam Subsection: Materials and Methods of Construction
55
A Step by Step Guide to the L.A.R.E.
Question 26: Evaluate the detail and determine if there is an error in the detail. Which of
the following is the most correct statement concerning the detail shown?
56
A Step by Step Guide to the L.A.R.E.
Question 27: Soils with a high plastic index will generally have which of the following
properties?
A. I and II only
B. II and IV only
C. I, II and IV only
D. I, III and IV only
Rationale: High plastic index soils tend to be clays with low moisture availability for plants due to
high soil suctions. They drain poorly and tend to have high shrink swell ratio. The plastic index
is the best indicator of these properties.
Exam Subsection: Materials and Methods of Construction
Question 28: Which of the following is a temporary measure to reduce erosion and
sedimentation?
A. I and II only
B. II and IV only
C. III and IV only
D. I, II and IV only
Rationale: Beckett, Jackson, Raeder Inc. Soil Erosion and Sediment Control, Environmental
Design Press pages 23-25
Exam Subsection: Materials and Methods of Construction
Question 29: To compensate for velocity loss at manholes, the exiting pipe should be
Rationale: Time-Saver Standards for Landscape Architects, Section 330-33. Since exiting pipes
are larger in diameter than entering pipes, the drop is accomplished by holding the pipe tops
(crowns) at the same elevation.
Exam Subsection: Materials and Methods of Construction
57
A Step by Step Guide to the L.A.R.E.
Question 30: In designing a storm drainage system, piping layouts and inlet locations will
be determined by which of the following?
58
A Step by Step Guide to the L.A.R.E.
Practice Problem 1:
You should download the problem and solve it before proceeding on to the problem solutions.
Download from www.clarb.org/Candidates/ExamResources/Documents/SampleE1.pdf.
Included in this chapter are several candidate interpretations of this problem and how the
solutions might be evaluated. You should compare your solution to these other candidate
solutions to see where you may have a weakness and determine what areas you should focus
on before taking the exam.
This problem is testing two distinct competencies from the specifications for Section E:
The problem statement asks you to provide a new road that links East Road to West Road. The
road should be 24’ wide and should have a minimum centerline curve radius of 200’.
You are asked to show contours within the page limits and conceptually indicate the curb and
crown on the road. This should indicate to you that it is not important to calculate the exact
cross-slope on the contours, however, it is important to convey that the road has a curb and a
crown. You are also asked to provide a 1/2 acre retention pond that is an average of 2’ deep
Looking at the site, you should be able to recognize that there is a distinct ridge and a valley
that should be considered in your road alignment. The drainage through the valley would also
be important to consider when grading your road and designing the proposed retention pond.
Existing trees are shown on the southern part of the property that should be considered when
locating and grading the road.
59
A Step by Step Guide to the L.A.R.E.
Candidate Solution 1
Looking at the first candidate solution, you can see that the road alignment works well with the
existing contours to protect the land forms. Minimal grading is shown to build the road and the
proposed retention pond. A low point is indicated on the road as it passes over the existing
drainage pattern on the western half of the site.
This candidate failed to provide the necessary 200’ centerline curve radius. By not following the
program directions, the candidate has made the problem easier to solve. If we look at the road
contours, you can see that this candidate failed to provide any indication of a crown or curb on
the road. The contours are drawn straight across the road and are not altered at the edge of the
road to indicate a curb line. Although the road follows the existing contours, the candidate failed
to provide a culvert at the low point in the road. All of the existing runoff coming down the valley
is directed across the paving.
A closer look at the proposed 158 contour on the eastern portion of the site also reveals that an
existing tree is destroyed. By cutting the 158 contour away from the tree, there is no way to
save it. This solution also indicates a retaining wall to retain the water for the pond. Although
this will work, the cost to provide the wall will be high. The retention pond could have been
created through landform grading and reduced the costs associated with the development.
60
A Step by Step Guide to the L.A.R.E.
Candidate Solution 2
In the second solution, we can see that the candidate actually drew a double line for the curb
and altered the contours across the pavement edge. The alignment is drawn to protect the
existing landforms and a high and low point have been indicated on the road.
In this case, the candidate used landform grading to provide a dam for the retention pond. An
indication of a 2’ deep pond is shown to meet the problem requirements.
The biggest problem with this solution is with the proposed road grading. The contours on the
road are backwards and indicate a valley down the center of the road, not a crown. The curb
contours are also incorrect and show an inverted curb. The pavement is actually higher than
the surrounding ground creating a safety concern for drivers that may accidentally drive off of
the road edge. This solution also shows runoff flowing directly across the pavement at the low
point in the road.
Although a dashed line is shown to indicate the 1/2 acre water surface, the actual water surface
will follow the 148 contour and will not be located as shown by the candidate. A secondary dam
is also shown that will create a low spot that will fill up with water in addition to the proposed
retention pond.
61
A Step by Step Guide to the L.A.R.E.
Candidate Solution 3
In the third solution, we can see that the candidate proposed a similar road alignment to the first
two solutions. We can see that the centerline curve on the eastern portion of the road will not
meet the 200’ radius requirement as was also the case with the first solution.
The 152 contour and the dashed lines indicate that this candidate used a culvert to
accommodate the existing drainage pattern on the site. The retention pond is indicated through
proposed contours and the road grading provides an indication of a road crown and curbs.
A closer look reveals that although parts of the drawing are correct, some of the details have
been missed. There are several places where the contours are drawn straight across the curb
line indicating the lack of a raised curb. The proposed 158 contour has also been missed. The
candidate should have noticed a problem when he or she was unable to provide connections
back to the existing contour in all places.
An indication of a culvert shows that the candidate has taken into account the large runoff
volume down the valley. However, the road connection to West Road does not meet at the
required 90 degree angle.
62
A Step by Step Guide to the L.A.R.E.
Candidate Solution 4
This candidate chose a different road alignment. The road is located over the saddle to the
northeast of the property and runs through a flatter low point in the valley. The retention pond is
shown to the north of the proposed road and uses the road embankment to dam the water.
Contours accurately indicate a road crown and curbs on both sides of the road. The contours
indicate that the road is steeper on the eastern side of the site, however, the contours are
shown at or below the 8% maximum.
This candidate failed to consider the existing landforms when deciding on the proposed road
alignment. You can see that this alignment created an unnecessary amount of grading which
will damage the environment and add to the costs of development. Although the retention pond
is shown correctly with an average 2’ minimum depth and a half acre surface area, using the
road embankment as the dam will cause high water flows to crest over the paving.
The retention pond should have been located to the south of the road which would also benefit
the environment by trapping sediment from the road runoff. This solution indicates an inability
to analyze the existing environment before moving ahead with a solution.
63
A Step by Step Guide to the L.A.R.E.
Candidate Solution 5
The final solution indicates a good understanding of site analysis. The road alignment protects
the existing landforms and minimal grading was required to create the proposed retention pond.
Proposed contours accurately show a road crown and curbs on either side of the road. The
curve radius requirements have been met and the existing trees have been retained.
This solution meets all of the problem requirements and demonstrates that the candidate has a
good understanding of proposed and existing contours. Existing drainage patterns have been
maintained and the landforms protected.
64
A Step by Step Guide to the L.A.R.E.
Practice Problem 2:
You should download the problem and solve it before proceeding on to the problem solutions.
Download from www.clarb.org/Candidates/ExamResources/Documents/SampleE2.pdf.
Included in this chapter are several candidate interpretations of this problem and how the
solutions might be evaluated. You should compare your solution to these other candidate
solutions to see where you may have a weakness and determine what areas you should focus
on before taking the exam.
This problem is testing two distinct competencies from the specifications for Section E:
This problem requires you to provide a grading plan to divert runoff around the proposed sports
court. Surface runoff must be directed to the proposed drainage system without disturbing the
marsh that is located to the south of the property. Runoff is not permitted to flow from the lawn
areas onto paving and there are minimum and maximum slope tolerances provided that you
must follow when developing your solution.
If you look at the site, you will see that the existing topography slopes from the north property
line to the south. The elevations of the sports court are provided so that you can provide
grading to divert the runoff around the court and into the proposed catch basin. Pipe sizes and
slopes are indicated. You must provide the invert elevations to ensure that the pipe cover is
maintained while meeting the given pipe slopes. Runoff from the proposed development is not
permitted to flow into the protected marsh.
65
A Step by Step Guide to the L.A.R.E.
Candidate Solution 1
The first solution indicates swales that are capturing the runoff coming from the north and
diverting it around the sports court. The proposed catch basin rim is set at 64.57 with the invert
for pipe A at 61.57. That provides 2’ of cover over the 12” pipe. The inverts for pipe B are set at
61.57 at the catch basin and 62.70 at the man hole. That provides the required 1’ of cover over
the 24” pipe from the rim of the drainage structures.
One of the bigger problems we can see is that pipe B does not have positive drainage. It is
pitched back towards the catch basin as opposed to flowing to the man hole and down the
existing pipe system. Another problem is that the high point of swale, although labeled with a
cross, does not indicate an elevation. We do not know if the candidate understood that the high
point must be below the court elevation to ensure that runoff is diverted around the court and
not onto the paving.
In addition, the candidate failed to draw the contours correctly to provide the minimum 2% slope
for drainage. This occurs in the swale around the court as well as in the area leading to the
proposed catch basin. One foot contours must be no more than 50’ apart and you must
calculate the contour location around the catch basin based on the rim elevation.
66
A Step by Step Guide to the L.A.R.E.
Candidate Solution 2
The second solution provides a high point of swale at elevation 67.80. This is below the sports
court elevation and indicates that runoff is being captured and diverted around the court. The
catch basin rim is set at 64.26 with the inverts at 61.57 and 60.57. The invert in at the man hole
is 59.87. The proposed inverts provide ample cover over the pipes and positive drainage
through the pipe system.
You should have noticed that the contours at the sports court were incorrect. This candidate
failed to take the elevations of the court into account. By tying into existing contours instead of
showing the proposed contours around the court, the solution fails to maintain the proposed
court elevations.
This solution also indicates swales that are less than the 2% minimum. It is important to follow
the requirements of the problem statement to demonstrate to the graders that you have the
ability to grade within given tolerances.
67
A Step by Step Guide to the L.A.R.E.
Candidate Solution 3
This candidate has indicated a high point of swale at elevation 68.80. Proposed contours tie
into existing to create swales around the sports court. The proposed catch basin rim is set at
65.80 and the inverts set well below that to provide ample cover over the pipe. Although there
is more than a 5’ drop from the invert in on pipe A to the invert out on pipe B, the system has
positive flow and will function acceptably.
You should have spotted the fact that the high point of swale is set too high. Runoff flowing
over that point will not be entirely diverted around the court and runoff will flow onto the paving.
The high point must be below the paving elevation to ensure that all runoff is directed away from
the court.
A bigger problem, however, is that the runoff is not being directed into the proposed catch basin.
The rim is set so high that the swales actually direct the runoff into the protected marsh off the
property. This is a big mistake that will harm the environment. The catch basin rim must be set
below the 64.80 spot elevation at the property line to ensure that runoff from the proposed
development is captured by the drainage system.
68
A Step by Step Guide to the L.A.R.E.
Candidate Solution 4
This candidate has properly diverted runoff around the upper portion of the sports court. The
high point of swale is lower than the court elevation and runoff is directed away in swales that
are greater than 2%.
The catch basin rim is set at 64.70, below the spot on the property line and the invert elevations
are set well below the rims to provide ample pipe cover.
A closer look around the proposed catch basin reveals that the rim is set too high. There is a 64
contour shown around the rim that indicates that water will puddle until it can reach the 64.70
rim elevation.
Another problem is with the invert in for pipe A. The drawing indicates that the pipe should have
a half percent slope. The inverts shown here indicate a 5% slope on that pipe. It is important to
double check your calculations before completing your solution.
69
A Step by Step Guide to the L.A.R.E.
Candidate Solution 5
The final solution properly sets the high point of swale and indicates swales over the 2%
minimum to divert runoff around the sports court. The catch basin rim is set at 64.00, below the
64.80 elevation indicated at the property line. The invert elevations match the pipe slopes
shown and provide at least the 1’ of cover required over the pipes.
This candidate has met all of the problem requirements. Runoff is diverted around the court and
directed into the proposed catch basin at the proper slope. The subsurface system is designed
properly and runoff is captured before it can flow into the protected marsh.
70
A Step by Step Guide to the L.A.R.E.
Practice Problem 3:
You should download the problem and solve it before proceeding on to the problem solutions.
Download from www.clarb.org/Candidates/ExamResources/Documents/SampleE3.pdf.
Included in this chapter are several candidate interpretations of this problem and how the
solutions might be evaluated. You should compare your solution to these other candidate
solutions to see where you may have a weakness and determine what areas you should focus
on before taking the exam.
This problem is testing two distinct competencies from the specifications for Section E:
This problem requires you to analyze the existing cover over a utility system and prepare a
grading plan to ensure adequate cover with new site features. Surface runoff must be directed
away from the building and into the proposed drainage structures. The walk grades must be set
to ensure that the accessibility requirements for the building are met. Runoff is not permitted to
flow from the lawn areas onto the proposed walk system and there are minimum and maximum
slope tolerances provided that you must follow when developing your solution.
The problem statement requires that you add six inches of cover for any location where the
proposed walk will be atop the existing telecommunications ductbank. Runoff naturally flows
from north to south and must be diverted to avoid flowing onto the walk or into the proposed
building. Accessibility requirements must also be understood to set the grades outside the
building entries and along the proposed walk.
71
A Step by Step Guide to the L.A.R.E.
Candidate Solution 1
The first solution indicates swales that the center walkway serves as an accessible entry for the
building. Drain inlet #1 is set at 853.50 and drain inlet #2 is set at 853.20.
One of the bigger problems we can see is that the proposed walk grading actually causes cut
over the existing telecommunications ductbank. There is only 12” of cover from the walk to the
top of the ductbank instead of the 30” required. The center walk to the building is required to
have steps in order to provide cover over the ductbank. Another big problem is that the runoff
from the building foundation is not directed into the drain inlets. Drain inlet #1 has the same
elevation as the building foundation and will not allow water to flow away from the building. The
area around drain inlet #2 is sheet drained towards the proposed walk and runoff from this area
will not enter the rim.
In addition, the candidate failed to divert runoff away from the proposed walk. Runoff flows from
the north of the property across the walk causing potential safety concerns. The candidate did
not adhere to the minimum and maximum gradients given in the problem statement either. Part
of the walk is shown below 1% while the west side of the walk exceeds 5%.
72
A Step by Step Guide to the L.A.R.E.
Candidate Solution 2
The second solution also indicates that the center walkway is an accessible walk. As seen in
the first example, the center walkway cannot be shown at 5% or under as per the problem
statement requirements and still maintain 30” of cover over the ductbank. This solution does
not address the information supplied by an outside consultant, namely the cover requirement
over the utility.
This solution creates a swale to the north of the proposed walk to divert runoff away from the
walk. Unfortunately, the swale is not deep enough to divert all of the water entering the site
from the north. The swale should be at least six inches deep to adequately divert runoff.
Contours on the east side of the site are incorrect. The 853 contour is shown undercutting the
building foundation instead of connecting to the existing contour at the bottom of the page. The
area near drain inlet #2 does not drain at the 2% minimum as well.
73
A Step by Step Guide to the L.A.R.E.
Candidate Solution 3
This candidate has indicated steps on the center walk to the building and has provided
adequate cover over the ductbank at this point. However, the spot elevation provided over the
ductbank on the east walk is too low and will not provide the necessary cover at this point.
The east walk is intended to be the accessible entry to this building, however, the spot provided
at the building entry does not meet the requirements outlined in the L.A.R.E. Reference Manual.
A mistake at the bottom of steps also causes a violation of the L.A.R.E. Reference Manual
codes. The minimum height for a riser according to the L.A.R.E. Reference Manual is 4”. The
spot shown indicates risers well under 4”. As a result of the spot grade error, runoff is also
being directed into the building entry. Runoff must be directed away from a building, especially
at entry locations.
This candidate also failed to divert runoff away from the proposed walk. A swale must be
shown to the north of the walk to prevent water from flowing onto the paving.
74
A Step by Step Guide to the L.A.R.E.
Candidate Solution 4
This candidate has properly solved the accessibility issue for the building, but has placed the
top of stairs too close to the main walkway. The result is that the required handrail extensions
will cause a hazard for those walking on the proposed walk.
Again, this solution fails to properly divert runoff away from the proposed walk at the northern
portion of the site. Proposed contours are also a problem. The contours along the existing
building façade have been altered against the directions given in the problem statement. The
855 contour does not connect to existing contours and will require grading outside of the
contract limits. The slope in the unpaved area around inlet #2 is also below that required by the
problem.
75
A Step by Step Guide to the L.A.R.E.
Candidate Solution 5
The final solution properly diverts runoff coming from the north away from the proposed walk.
At least 30” of cover is provided over the ductbank where the sidewalk is covering. The building
is provided with an accessible entry on the east side of the site that meets all L.A.R.E.
Reference Manual codes. Drainage is conveyed to the proposed inlets at a 2% minimum and
runoff is directed away from the center entry to a break point below the steps.
76
A Step by Step Guide to the L.A.R.E.
77