You are on page 1of 205

0

Memo No (972)

Introducing Microsoft Project 2007

by

Dr. Abdalla ElDaoushy

Feb, 2009
Dec, 2009
1

Contents
Page

Exploring Microsoft Project Environment. . . 4


 MS Project 2007 Screen . . . . . . 4
 Standard Toolbar . . . . . . . 4
 Formatting Toolbar . . . . . . . 6
 View Bar . . . . . . . . 7

Creating a New Project . . . . . . 7


 Create New Blank Project . . . . . . 7
 Create a New Project based on a Template . . . . 7
 Setting Up a Project Calendar . . . . . . 11
o Create a New Calendar . . . . . 12
o Set Up a Working Time Exception . . . . 14
o Global Calendar . . . . . . 17
 Create MileStone Tasks . . . . . . 20
 Change the Date Format . . . . . . 20
 Setting Schedule Options . . . . . . 20
 Saving Project Files . . . . . . . 21
 Saving Files as Templates . . . . . . 21
 Protecting Files . . . . . . . 22
 Entering Tasks . . . . . . . 23
 Creating Summary Tasks . . . . . . 25
 Displaying and Hiding Tasks . . . . . . 26
 Project Summary Task . . . . . . 26
 Using Recurring Tasks . . . . . . 27
 Recurring Tasks: Application . . . . . . 36
 Task Notes . . . . . . . . 41

Manipulating Tasks & Constraints . . . . 42


 Using Deadline Dates . . . . . . . 43
 Adding Constraints . . . . . . . 45
 Editing Tasks . . . . . . . . 47
 Deleting Tasks . . . . . . . 47
 Moving Tasks . . . . . . . . 47

Tasks Relationships (Dependences) . . . . 49

1
2

Page

Resources . . . . . . . . . 52
 What are Resources . . . . . . . 52
 Creating Resource List (Example) . . . . . 52
 Working Time for Resources . . . . . . 53
 Rates for Resources . . . . . . . 55
 Resource Notes . . . . . . . 56
 Assigning Resources (Example) . . . . . 57

View Information . . . . . . . 61
 Gantt Chart View . . . . . . . 62
 Calendar View . . . . . . . 64
 Task Usage View . . . . . . . 65
 Resource Graph View . . . . . . . 68
 Resource Sheet View . . . . . . . 69
 Resource Usage View . . . . . . . 70

Quick Viewing & Printing Reports . . . . 71


 Using “Print Preview”. . . . . . . 71

Reports . . . . . . . . . 72
 Overview Reports . . . . . . . 73
 Current Activity Reports . . . . . . 74
 Costs Reports . . . . . . . . 75
 Workload Reports . . . . . . . 76
 Assignment Reports . . . . . . . 76
 Visual Reports . . . . . . . . 77

Case Studies . . . . . . . . 79
 Case Study No 1 . . . . . . . 80
o Basic Data . . . . . . . 80
o Resources: Standard Rate & Overtime Rate . . . 81
o Working Steps . . . . . . . 82

2
3

Page

 Case Study No 2 (Arabic) . . . . . 97


o Background . . . . . . . 97
o Working Steps . . . . . . . 99
1. Create New Project . . . . . 99
2. Change the Start Date & Current Date of the Project . 99
3. Create a New Calendar . . . . . 100
4. Assign the New Calendar to the Project . . . 101
5. Make New Calendar as a “Global Calendar” . . 101
6. Enter Tasks, Durations & Relationships . . . 101
7. Coding & Organization . . . . . 106
8. Record the Resources in the “Resource Sheet” . . 113
9. Assign different Resources to different Tasks . . 116
10. Project’s Resources . . . . . 120
11. Design and Display the different Reports . . . 127

 Case Study No 2 (English) . . . . . 128

Tracking (Follow Up) . . . . . . 175

 Understanding Tracking . . . . . . 175


 Updating Form . . . . . . . 175

 Tracking Process . . . . . . . 179


1. Setting BaseLine . . . . . . 180
2. Tracking Progress . . . . . . 183
3. Status Date . . . . . . . 187
4. Reviewing Progress & Progress Line . . . . 188
5. Reschedule Uncompleted Work (F9 in P3e) . . . 190
6. Reviewing Progress . . . . . . 191
7. Group . . . . . . . . 191
8. Filter . . . . . . . . 193
9. View . . . . . . . . 196
10. Reporting on Project’s Progress . . . . 197

Coordinating Multiple Projects & Sharing Resources Among


Projects . . . . . . . . . 198
References . . . . . . . . 203

3
4

Exploring Microsoft Project Environment

MS Project 2007 Screen:

Standard Toolbar:
 New
 Open
 Save
 Print
 Search
 Print Preview
 Spelling
 Cut
 Copy
 Paste
 Format Painter
 Undo & Redo
 Hyperlink

4
5

 Link Tasks
 Unlink Tasks
 Split Task
 Task Information
 Task Notes
 Task Drivers
 Assign Resources
 Publish All Information
 Group by
 Zoom IN
 Zoom Out
 Go to Selected Task
 Copy Picture
 Microsoft Project Help

5
6

Formatting Toolbar: (View/Toolbars…/Formatting)


 Outdent
 Indent
 Show Subtasks
 Hide Subtasks
 Hide Assignments
 Show
o Font
o Bold
o Italic
o Underline
o Align Left
o Center
o Align Right
o Filter
o Gantt Chart Wizard

6
7

View Bar: (View/View Bar)

Creating a New Project:


 Create New Blank Project:

o Click on the “New” icon.

 Create a New Project based on a Template:

o Click “File/New”, the New Project Task Pane displays


towards the left edge of the window:

7
8

o To use a Template that is already installed on the computer’s


hard disk, click on the “On Computer…” link, the
“Templates” window appears:

8
9

o Click on the “Project Templates” tab, a range of templates


appears:

o Select and double-click the desired Template and continue


modifying and adding activities as we will explain later on.

 Inputting Start & Finish Dates:


o Click “Project/Project Information…”, the “Project
Information” window appears:

9
10

o Use the drop-down calendar in the “Start date:” to select the


Start date of the Project (for example 1/1/2010).

o Use the drop-down calendar in the “Current date:” to change


the date to for example 1/1/2010.

10
11

 Setting Up a Project Calendar:


o Click “Project/Project Information…”

o Confirm that “Standard” is selected from the Calendar drop-


down menu in the “Project Information” dialog box:

Hint:

Be sure that “Project Start Date” is selected from the “Schedule


from:” drop-down menu (“Project Start Date” is the default).

11
12

 To Create a New Calendar:


o Click “Tools/Change Working Time”

o Click on the “Create New Calendar…” button, the “Create


New Base Calendar” dialog box appears:

12
13

o Enter a name (for example My Calendar) for the new calendar


in the “Name” field.

o Press OK.

13
14

 To Set Up a Working Time Exception:


1. Use “Exception” & “Work Weeks” tabs to determine
the holidays (from “Exception” tab) & exceptions for
default holidays to become working days (from “Work
Weeks” tab).
2. In the “Name” column on the “Exception” tab, type a
name that helps you remembers the purpose of the
exception (holidays/non-default workdays).

3. In the “Start” column, select the date on which the


exception starts.

4. In the “Finish” column, select the date on which the


exception ends. Project sets every day between the
starting and ending dates as an exception on the calendar,
and the “Details” button and the “Delete” button become
available.

5. Click the “Details” button. Project displays the details


dialog box. Use this dialog box to define the working
time exception.

6. In the top section of the dialog box, click the “Working


Times” option button and then set the working times.

7. To repeat this working time pattern every Wednesday for


example, click “Weekly” in the “Recurrence pattern”
section and check the “Wednesday check box.

8. In the “Range of recurrence” section, Project set the


starting and ending dates for the working time exception
using the dates you supplied in steps 2 and 3. You can
change these dates if you want.

9. Click OK. When Project redisplays the “Change


Working Time” dialog box, every “Wednesday”
between the beginning and ending dates you specified
appears as an exception on the calendar.

14
15

 To Create a New Calendar Example:


 Create a new calendar called “Egypt Calendar” with the
following specification:

o It will be a Global Calendar.

o Weekly working days will be from SUN to THU.

o It has the following Holidays:

 7 January --- (repeated)


 1 May --- (repeated)
 23 July --- (repeated)
 6 October --- (repeated)

(Use “Details” tab after assigning in the “Exceptions”)

Now,

1. Create a new Project.

2. Click “Tools/ Change Working Time…/Create New Calendar…”,


the “Create New Base Calendar” window appears.

3. Enter the Calendar Name: Egypt Calendar

4. Choose the option: Create New Base Calendar.

5. Press OK, the “Change Working Time” window appears.

6. Click “Options…” tab.

7. Choose “Week starts on: Sunday & Press OK

8. Choose “Work Weeks” tab & Press “Details…” button, the “Details
for [Default]” window appears.

a. Adjust the working & nonworking days in this window.

15
16

9. Choose “Exceptions” tab.

a. Highlight 7 of January

b. Write in the Exception Name: “7 January” and click in the


“Start” column, the highlighted day becomes a nonworking-
day with nonworking-color.

c. Press “Details…” button, the [Details for “7 January”]


window appears.

d. To make this day repeated holiday for 10 years as an example;


in the “Recurrence pattern” section, choose “Yearly”.

e. Choose “End after” radio-button and write 10 occurrences.

10.Repeat for “1 May”, “23 July”, & “6 October”.

11.The “Egypt Calendar” looks like this:

16
17

12.To make this Calendar a “Global” Calendar:

a. Choose “Tools/ Organizer…”, the “Organizer” window


appears.

b. Click the “Calendar” tab, the window will looks like this:

17
18

c. Highlight “Egypt Calendar” and press “<<Copy”, the window


will looks like the following window which means that the
“Egypt Calendar” become Global and will be available for
any project the same way as the “Standard Calendar”.

Hint: This is the place where you can delete any Calendar except the “Standard”
one . . .

18
19

 Applying (Assigning) the new calendar called


“Egypt Calendar” to the Project:
o Click “Project/Project Information…”

o Click on the “Calendar” down arrow.

o Click on “Egypt Calendar” to select it.

o Click OK.

Dates Format:

Date format comes from Windows Setting as follows:

 Start / Setting / Control Panel


o “Regional Option” tab / Customize
 “Date” tab
• Short date format: dd-Mon-yy for example…
• OK
• Apply
• OK

19
20

 To Create Milestones Tasks:


o Milestones Tasks are tasks that usually have zero duration.

o The symbol for a milestone on the “Gantt Chart” view is a


diamond shape.

o A Task does not have to have zero duration to be a milestone;


you can mark any task as a milestone. On the “Advanced” tab
of the “Task Information” dialog box, place a check mark in
the “Mark Task As Milestone” check box. In this case, the
task duration does not change to zero. However, the element
that represents the task in the “Gantt Chart” changes from a
bar, reflecting the task’s duration, to a milestone diamond
symbol, representing the task as a moment in time.

Hint:

Check with 3 Sequential Activities: A (10 days & milestone),


B (8 days), and C (2days) and see the result….

 To Change the Date Format:

o Click “Tools/Options/View/Date Format”

 Setting Schedule Options:

o “Tools/Options/Schedule”

 Show assignment units as a : Decimal (for example),

 Duration is entered in: days (for example),

 Work is entered in: days (for example),

 Default Task Type: Fixed Duration.

20
21

 Saving Project Files:

o “File/Save”

o Note:

By default, Project saves files in Project 2007 format with the


extension .mpp. To save a file in a different format, such as a
Microsoft Access database (.mdb) or a Project 2000 - 2003 file
(also .mpp), you can select that format in the “Save As” type
drop-down list. After you enter a name for your file and
designate its location and type, click Save to save the file.

 Saving Files as Templates:


o One format in the “Save As type” drop-down list is Template
as shown:

21
22

 Protecting Files:
o “File/Save As” & “Tools” button as shown:

22
23

 Entering Tasks:
o Create a new Project called “New Product Brochure_1”

o Enter Tasks as shown:


24
25

 Creating Summary Tasks:

o Highlight row 1 and press “Ins” on the Keyboard; then type


“Write Brochure”.

o Highlight rows 2, 3, 4, and 5 and press “Indent” button as


shown on the next page.

o Repeat for the rest of activities as shown:


26
26

 Displaying and Hiding Tasks


(expanding or collapsing the Summary Tasks):
o The outline structure enables you to view your project at
different levels of detail by expanding or collapsing the
summary tasks.

 Project Summary Task:


o “Tools/Options/View tab”

o Check “Show Project Summary Task”


27

 Using Recurring Tasks:


 Projects often have tasks that occur on a regular basis.

 For example, the following tasks:

o Weekly Staff Meetings.


o Quarterly Reports,
o Monthly Budget Reviews

may occur 20 or so weekly over the life of a 5-month project.

 Use the Project’s Feature that enables you to create the meeting
task, for example. Just once and assign a frequency and timing to
it

 Follow these steps to Create a Recurring Task:

1. Because Project inserts tasks above the selected task, select the
task that you want to appear below the recurring task and choose
“Insert/Recurring Task” to open the “Recurring Task
Information” dialog box, as shown:

4.8

27
28

2. Type the recurring task name in the “Task Name” field.

3. Set the task duration in the “Duration” field. For example, does
the meeting run for two hours, or does a report take a day to write?

4. Set the occurrence of the task by selecting one of the “Recurrence


Pattern” option buttons:

 Daily, Weekly, Monthly, or Yearly.

5. Select the appropriate settings for the recurrence frequency.

 For a Weekly setting, place a check mark next to the day(s)


of the week on which you want the task to occur. For
example, the task may occur every Tuesday.

 For the Monthly or Yearly setting, select the day of the


month on which you want the task to occur. For example,
the task occurs on Day 12 of every month.

 For a daily task, you have only one choice: whether you
want it to occur every day or only on scheduled workdays.
For example, to schedule a computer backup for every day
of the week—regardless of whether anyone is at work—you
can have the task occur every day. (Ask your IT department
how to automate the process so that it occurs even when
nobody is at work.)

6. Set the “Range of recurrence”, the period during which the task
should recur by entering “Start” and “End after” or “End by”
dates. If you need to repeat a test weekly for only one month of
your ten-month project, you can set “Start” and “End after” or
“End by” dates that designate a month of time.

If you set the “End after” number of “occurrences”, Project


calculates the date range that is required to complete that many
occurrences of the recurring task and automatically displays the
ending date in the “End by” box. This method can be useful if one
of these events falls on a holiday:

28
29

 If one of the occurrences falls on a holiday, Project displays


a box that allows you to skip the occurrence or to schedule it
on the next working day.

 For a weekly staff meeting, you can skip that meeting or


schedule it on a different day.

 On the other hand, if you must repeat a test 16 times during


the project cycle, you can schedule the test to occur on the
next working day to compensate for the holiday.

 Therefore, set the number of occurrences rather than the


time range.

7. Click OK to create the task. Project creates the appropriate number


of tasks and displays them as subtasks under a summary task with
the name that you supplied in Step 2. FIGURE 4.10

Task bars appear for each occurrence of the recurring task in the
“Gantt Chart”.

Returning back to our example called “New Product


Brochure_1”:

29
30
31

 Select row 10 and click “Insert/Recurring Task”, the “Recurring


Task Information” dialog box appears:

 Enter “Team Meeting” in the “Task Name” box.

 Enter 1h in the “Duration” box.

 Select the “Daily” button in the “Recurrence pattern” area.

 Select the “Workdays” button.


32

 In the “Range of recurrence” section, select the “End after” button


and write 3.

 Click OK button to return back to the “Gantt Chart” view. Your


screen will now look like this:

32
33
34

 Click on the “Outdent” button on the “Formatting” toolbar.


35

 Expand the “Team Meeting” task by clicking on the “+” symbol.


36

Recurring Tasks: Application…..

 Suppose we would like to construct a Training Programs Plan for


the Year 2010.

 We have limited Training Classes & many Training Programs.

 We used to use a Class for two courses. Each course used to be held
for 3 days a week. For example, a class can be used for Windows
Training Program to be held on SUN, TUE, and THU for two
weeks & Word Training Program will be held at the same Class for
SAT, MON, and WED for two weeks also.

 After finishing of any of these Training Programs, another Training


Programs like Excel & Access will be held.

 In summary:

Class 1:

Course Days Working Days


Title

1 Windows 6 SUN TUETHU . . . . . .


2 Word 6 SAT MON WED . . . . . .
3 Excel 9 SUN TUE THU After
Windows.
4 Access 12 SAT MON WED After Word
37

 We have to do the following:

 Create a new Calendar “Training Programs Calendar”:


6 Days/Week & Week Start on: SAT

 Project Name: Class 1 Schedule

 Assign Calendar to Project

 Create the following Recurrence Tasks according to the above


information:

1. “Windows Program” Task

2. “Word Program” Task

3. "Excel Program” Task (Starts after “Windows Program”)

4. “Access Program” Task (Starts after “Word Program”)

37
38

Hint: Instead of writing the start date above, you can set the “Predecessor|
for the “Excel Program 1” task (which is the “Windows Program 6”
task. Repeat for the rest of Tasks…
Anyhow, this is not practical procedure….

38
39

Hint: Instead of writing the start date above, you can set the “Predecessor|
for the “Access Program 1” task (which is the “Windows Program
6” task. Repeat for the rest of Tasks…
Anyhow, this is not practical procedure….

39
40

40
41

Task Notes:

Notes can be attached to a Task to quickly display information relating to


that Task.

 Double-click on the “Print Brochure” Task; the “Task


Information” window appears.

 Select the “Notes” tab.

 Type “Remember to ask Kate for recommended Printers”

 Click OK.

 Notice the symbol in the “Indicator” column.


42

Manipulating Tasks & Constraints:

 A Constraint is a restriction placed upon a task which limits the


Start or Finish Dates of that task.

 By default, the “As Soon as Possible” constraint is applied to every


task.

 The following represents a list of all of the Constraint Types:

o “As Soon As Possible”: Schedules the task to start as soon as


the beginning of the Project.

o “As Late As Possible”: Schedules the task to end no later than


the end of the Project.

o “Finish No Earlier Than” or “Finish No Later Than”:


Schedules the task to end no later or sooner than a specific
date.

o “Must Finish On” or “Must Start On”: Schedules the task to


finish on or start on a specific date.

o “Start No Earlier Than” or “Start No Later Than”:


Schedules the task to start no earlier than or later than a specific
date.

Hint:

Constraints come from “Task Information/Advanced tab”

42
43

 Using Deadline Dates:


o You also can establish a deadline date for a task. The deadline date
differs from a constraint in that Project doesn’t use the deadline
date when calculating a project’s schedule. Instead, the deadline
date behaves as a visual cue (sign) to notify you with a deadline
dates. If you place your mouse over the deadline indicator, Project
displays the deadline information. If the task finishes after the
deadline date, you also see a symbol in the Indicators column. Be
aware that you won’t see an indicator if you complete the task prior to
the deadline date.

 Deadline Field:

Description: The Deadline field shows the date you enter as a


deadline for the task. A deadline is a target date indicating
when you want a task to be completed. If the deadline date
passes and the task is not completed, Microsoft Office Project
displays an indicator. A deadline is also shown as an arrow in
the “Gantt Chart” view.

Best Uses: Apply a deadline to a task when you want to track a


deadline for a specific task but don't want to lock your schedule
by setting an inflexible constraint such as Must Finish On or
Finish No Later Than. Such constraints affect scheduling while
the Deadline field simply causes an indicator to show if a task
has not been completed by its deadline. Add the Deadline field
to a task sheet when you want to enter, view, or change the
deadlines of tasks in your project. You can also use the
Deadline field for sorting, filtering, and grouping by deadline
date.

Hint:

A Deadline Date comes from “Task Information/Advanced tab”

43
44

Example:
Certain tasks in your project should finish by specific target
dates. However, you don't want these dates to actually affect
how Project schedules the tasks; you just want to be alerted if
the tasks are not completed by these dates. Add the Deadline
field to the Entry Table of the “Gantt Chart” view, and set the
deadline dates for these tasks.

Remarks:

You can also enter a task deadline in the “Task Information”


dialog box. Click “Task Information” and then click the
“Advanced” tab. Click the date in the “Deadline” box.

If you do want Project to schedule tasks according to a specific


finish date, apply either a Finish No Later Than, Finish No
Earlier Than, or Must Finish On constraint. You can set task
constraints on the “Advanced” tab of the “Task Information”
dialog box.

44
45

Adding Constraints:

 Double-click the “Print Brochure” Task; the “Task Information”


dialog box appears.

 Click “Advanced” tab.

 Select “Start No Earlier Than” from the “Constraint type” drop-


down menu.

 Type 7/1/2004 in the “Constraint date” field

 Click OK. Notice how the “Print Brochure” tasks have been moved
in the “Gantt Chart” view.

45
46
47

Editing Tasks:
 Tasks can be edited through their “Task Information” dialog box

 Double-click the “Teem Meeting 1” task to open its “Task


Information” dialog box.

 Change the “Duration” to 2h.

 Click OK.

Deleting Tasks:
 Highlight the Task(s) in the “Gantt Chart” view and Press the “Del”
key.

 Undo the deletion by clicking on the “Undo” button in the “Toolbar”.

Moving Tasks:
 Move the mouse-pointer over the “ID” number of the Task until the
mouse-pointer changes to the shape of a “Move Cursor”.

 Click and hold the mouse button. Drag the mouse-pointer until the
“horizontal grey stripe” is above the row where the moved Task will
be.
48
49

Tasks Relationships (Dependences):

 There are two types of Tasks in a Relationship.

o A Predecessor Task must occur before another Task.

o A Successor Task must occur after another Task.

Finish-to-Start (FS) Relationships:

 It is the most common type of relationship. The start of one Task


begins as soon as its Predecessor Task finishes. The Successor Task
can not start until the Predecessor Task finishes.

Start-to-Start (SS) Relationships:

 In the SS relationship, the Successor Task can not start until the
Predecessor Task starts. The Tasks can happen simultaneously, but
the Predecessor Task needs to have started in order for the Successor
Task to start.

Start-to-Finish (SF) Relationships:

 In a SF relationship, the Successor Task is completed after its


Predecessor Task starts. In other words, the Successor Task can not
finish until the Predecessor Task starts. The SF relationship is rarely
used.

Finish-to-Finish (FF) Relationships:

 In the FF relationship, the Successor Task can not finish until the
Predecessor Task finishes. For example; you finish installing
computers at the same time that you finish moving employees into the
building so that the employees can begin using the computers right
away.
50

Hint:

You can create Tasks Relationships from:

o “Task Information/Predecessor tab”,

o “Window/Split”, or

o Adding Predecessor/Successor column in the “Gant Chart”

Now, it is the time to create the Tasks Relationship in our example “New
Product Brochure” using the following information:

Task Predecessor Type

Research New Product ---


Create an Outline Research New Product
Write a Rough Draft Create an Outline
Edit Rough Draft Write a Rough Draft
Prepare through Desktop Edit Rough Draft
Get Quotes from Printer Prepare through Desktop
Get Printed Get Quotes from Printer
Create Mailing List Get Printed SS
Do Mass Mail Out Create Mailing List

50
51

51
52

Resources

What are Resources:

 Resources are People, Equipments, and Materials (Supplies) used


to accomplish tasks and goals of the project.

Creating Resource List (Example):

 Click “View/Resource Sheet”.

 Click in the 1st row of the “Resource Name” column. Type “Jane
Doe” and press “Return”.

 Repeat for “Katie Aiko” & “Postage”.

 For the resource “Postage”, select “Material” from the drop-down-


list in the “Type” column.

 Enter “Stamps” as a “unit of measurement” in the “Material Label”


column.

 Click “Save” in the “Toolbar” to save your work.

52
53

Working Time for Resources:


 The “Base Calendar” which you choose for a resource determines its
availability.

 You can customize a resource’s calendar if necessary (i.e., blocking


off vacation time for specific resource).

 Double-click on “Jane Doe” in the “Resource Name” column. This


will open the “Resource Information” dialog box. If necessary, click
on the “General” tab.

 Click on the “Change Working Time…” button, the “Change


Working Time” window appears:

53
54

 In the above screen, you can change the “Base calendar” and you can
customize the Calendar from the “Exception” & Work Weeks” tabs.

54
55

Rates for Resources:


 It is important to enter rates for a resource, as this allows MS-Project
to calculate the overall cost of a project.

 The resource’s cost may increase or decrease during the life of the
project, and you need to be able to reflect these changes.

 MS-Project allows entering up to 125 different cost rates for a


resource and specifying the date at which the new rates takes effect.

 In the “Resource Sheet” view, enter the following rates information


for the different resources as shown:

55
56

Resource Notes:
 You use Resource Notes in much the same way as Task Notes.

 For example, double-click the “Jane Doe” resource which will


display the “Resource Information” dialog box. Select the “Notes”
tab.

 Type “Send reminder regarding Team Meeting” in the “Notes”


area:

 Click OK button to save and attach the note to the resource.

 Notice the “note symbol” in the “Indicator” column of the


“Resource Sheet” view. Move your mouse cursor over it to display
the note.

56
57

Assigning Resources (Example):


 Open the “Gantt Chart” view.

 Double-click on the “Team Meeting 1” Task; the “Task


Information” dialog box appears. Click on the “Resources” tab:

 In “Resource Name” column, select “Jane Doe” & “Kati Aiko”


resources for this Task as shown:

57
58

 Click OK button to close the dialog box.

 Now, assign the following Tasks to “Jane Doe” using the “Resource
Names” column in the “Gantt Chart”.

o Research New Product


o Create an Outline
o Write a Rough Draft

 Assign the resource “Katie Aiko” to the following Tasks:

o Edit Rough Draft


o Prepare through Desktop Publishing
o Create Mailing List

 Double-click on the “Do Mass Mail Out” Task to open its “Task
Information” dialog box. Assign resources & units as shown:

Hint: “Assignment Owner” is a new feature in MS Project 2007. In this


field, assign the Individual who is responsible for entering actual work or
reporting progress against an assignment (MS Project 2007 Bible, page
510)

58
59

 Save your Project.

 The Gantt Chart view will look like this”

59
60

60
61

View Information:

 You can use most views to enter and edit information, although
some views can only display information.

 All views are made up of 3 basic components:

o Chart or Graph: Information is represented by pictures.

o Sheet: Information is represented in a table format, similar to a


worksheet.

o Form: Information about a single item is represented as it


might be on a paper form.

61
62

Gantt Chart View: “View/Gantt Chart”


 It is useful for entering task information and viewing the timing and
relationship between tasks.

 The “Gantt Chart” view is the default view within MS-Project. It


consists of the Gantt Table & Gantt Chart.

 The Timescale at the top of the “Gantt Chart” is set to show weeks
(in the middle tier) and days (in the bottom tier) as the default.

However, you can adjust it to show any Timescale you wish:

o Double-click on the Timescale. This will display the


“Timescale” dialog box:

o You can format any tier on the Timescale.

62
63

o Select Days (for example) instead of Weeks for the middle


tier. A preview of changes is shown in the bottom portion of
the dialog box:

63
64

o The “Gantt Chart” will now look like this:

o You can zoom in or out to view larger or smaller time


increments in the Gantt Chart using the “Zoom In” and
“Zoom Out” buttons in the “Toolbar”.

o You can also use “View/Zoom”. Experiment with using


different levels of Zoom.

Calendar View:

 The Calendar View is useful for a general overview of what needs to


be done on a specific day. It uses a monthly format to show
scheduled tasks.

 To display the “Calendar View”, just click “Calendar” icon on the


“View Bar” or “View/Calendar”.

64
65

Task Usage View: “View/Task Usage”


 This View is useful for showing and organizing assigned Resources for each Task:

65
66

 By default, the “Task Usage” table is shown in the left pane. To


choose a different table, click on the “Select All” button (at the top-
left-corner of the table).

 Right-click and select the view you wish to see.

 Work is shown in the “Details” section in the right pane. To select


different options for the “Details” section, click on the “Select All”
button and right-click. This gives you access to the “Timescale”,
“Zoon”, and “Change Working Time” dialog boxes.

 Right-click on “Work” in the “Details” column of the “Task Usage”


chart, and select “Cost”.

66
67

 Notice that now both “Work” & “Cost” are listed in the “Task Usage
Chart”. The cost is displayed in the table.

67
68

Resource Graph View: “View/Resource Graph”

 Click on the “Resource Graph” icon within the “View Bar”; or click
“View/Resource Graph”:

 Note: If the Resources are not visible, use the scroll bar at the bottom
of the Graph Pane to navigate to the dates in which the project fall.

 Notice how a red color represents Over-Allocations

Hint:

If there is no red color appears in the “Resource Graph”


above, make the relationship between “Research New
Product” & “Create an Outline” Tasks as of “SS” Type.

68
69

Resource Sheet View:”View/Resource Sheet”

 This view is very useful for viewing, entering, and editing resource
information. It contains detailed resource information in a worksheet
format.

 If an over-allocation exists, a warning flag is displayed in the


“Indicator” column. In addition, the resource appears in red color.

69
70

Resource Usage View: “View/Resource Usage”

 This view is useful for seeing each resource and the tasks assigned
to that resource.

 This view can be used for entering and editing resource information,
or assigning tasks. To assign or reassign a task, drag and drop
between resources.

70
71

Quick Viewing & Printing Reports:

 Not all information is relevant to everyone, so it is important to


be able to present the appropriate data to the right people.

Using “Print Preview”:

 Returning back to our example “New Product Brochure.mpp”.

 Display the “Print Preview” window, the screen will now look
like this:

 Note that “Print Preview” has its own toolbar; so Use this
toolbar & “File/Page Setup” to arrange for the desired obtained
report.

71
72

Reports:

 Click on the “Report/Reports…”, the “Reports” dialog box


displays:

72
73

Overview Reports:

 Click “Overview…” report and then click “Select” button. You will
see the following “Overview Reports” window:

 There are 5 types of “Overview Reports”:

o Project Summary
o Top-Level Tasks
o Critical Tasks
o Milestones
o Working Days

 Experiment the different types of reports, by choosing


each of the options and clicking on the “Select” button.

 Close the “Reports” dialog box.

73
74

Current Activity Reports:

 There are 6 types of “Current Activity Reports”:

o Unstarted Tasks
o Tasks Starting Soon
o Tasks In Progress
o Completed Tasks
o Should Have Started Tasks
o Slipping Tasks

 Experiment the different types of reports, by choosing


each of the options and clicking on the “Select” button.

 Close the “Reports” dialog box.

74
75

Cost Reports: “Reports/Reports…/Costs”

 Click “Reports/Reports…/Costs/Select”, the following “Cost


Reports” window appears:

 Experiment the different types of reports, by choosing each of


the options and clicking on the “Select” button.

 Close the “Reports” dialog box.

75
76

Workload Reports: “Reports/Reports…/Workload…”

Assignment Reports: “Reports/Reports…/Assignments…”

76
77

Visual Reports: “Reports/Visual Reports”

 This allows taking the data from within a MS-Project, formatting that
data, and then exporting that data to a different application as MS
Excel or MS Visio.

 Click “Report/Visual Reports…”, the “Visual Reports” dialog box


appears:

77
78

 Notice that at the top of the dialog box, by default, templates are
shown that involve both “MS Excel” & “MS Visio”.

 If you do not have “MS Visio” installed on computer, then you


can remove the tick next to this option, so that only “MS Excel”
templates are used.

 Spend a little time experimenting with the Visual Reports feature.

78
79

Case Studies

79
80

Case Study No 1:

Project Name: Case_1


Starting Date: 1/1/2010
Project Calendar: 5 days/Week [SUN]

The Resource “Trainer” is working one Overtime hour every day

Basic Data:
No Task Predecessor Rel. OD Resources Max Material
Type (Day) (Work/ Units Cost
Equipment) (Expenses)
1 Introduction --- --- 1 Trainer 1 $200
Project Manager 1
CAD Operator 1
Facilitator 1
Computers 10
Data Show 1
2 MS Project Introduction FS 1 Trainer 1 $20
CAD Operator 1
Computers 10
Data Show 1
3 Data Entry MS Project FS 1 Trainer 1 $20
CAD Operator 1
Computers 10
Data Show 1
4 Logical MS Project FS 2 Trainer 1
Relations Data Entry SS CAD Operator 10
Computers 1
Data Show 1
5 Constraints Logical FF 1 Trainer 1 $20
Relations
CAD Operator 1
Computers 10
Data Show 1
6 Improvements Constraints FS 1 Trainer 1 $300
Project Manager 1
CAD Operator 1
Facilitator 1
Computers 10
Data Show 1

80
81

Resources: Standard Rate & Overtime Rate:

No Resource Name Resource Std Rate Overtime


Type Rate
1 Trainer Work $20/hr $30/hr

2 CAD Operator Work $7/hr $10/hr

3 Project Manager Work $30/hr $45/hr

4 Facilitator Work $4/hr $6/hr

5 Computer Equipment $2/hr ---

6 Data Show Equipment $4/hr ---

7 Expenses Cost --- ---

81
82

Working Steps:

1. Create a New Project called “Case_1”

2. Change the Start Date & Current Date of the Project to “1/1/2010”.

a. “Project/Project Information”

b. Start date: 1/1/2010

c. Current date: 1/1/2010

3. Create a New Calendar: “Case_1 Cal”.

a. “Tools/Change Working Time”

b. “Create New Calendar…”

82
83

c. Name: Case_1 Cal

83
84

d. Press “Options”

e. Week Starts on: Sunday

f. Press OK

g. Press “Work Weeks” tab on the “Change Working Time”


window, the “Details…” button becomes active.

h. Press “Details…” button.

84
85

i. Change the “Sunday” to Working day

j. Change “Friday” to Non-working day

k. Press OK.

4. Assign “Case_1 Cal” to “Case_1” Project.

a. “Project/Project Information”

b. Calendar: Case_1 Cal.

85
86

86
87

5. Enter Tasks, Durations & Relationships.

a. Sometimes, the Calendar in the “Bar-Chart” area does not


coincide with the Project Calendar especially for the non-
working days.

b. To resolve this problem, click in the “Bar-Chart” area and


right-click to choose “Nonworking Time…”

c. Choose “Case_1 Cal” for “Calendar:” field, then the Gantt-


Chart will look like the one above.

87
88

6. Record the Resources in the “Resource Sheet”.

a. “View/Resource Sheet”

88
89

7. Resource Assignment --- Assign different Resources to


different Tasks:

a. Before Assigning Resources, It will be useful to change the


Task Types to “Fixed Duration” Tasks & Change the “Effort
Driven” to “No”.

b. To facilitate this process, insert two columns as shown above


the make the necessary changes.

c. Now, assign the Resources.

i. Highlight the 1st activity and click the “Assign


Resources” icon on the “Tool Bar” shown in the
window above, the “Assign Resources” window
appears:

89
90

ii. Choose the different resources to the specified task as


shown:

Hint: “R/D” above means Request/Demand…

iii. Repeat with the other Tasks.

90
91

8. To check Resource Allocation, Click “Resource Sheet”:

9. Notice the Resource with red color. This means that there is an over-
allocation for this Resource.

10. Resolve Resource Over-Allocation:

a. “Tools/ Level Resources”, the “Resource Leveling” window


appears:

91
92

b. Press “Level Now”. the result will be shown as follows:

c. Return back to the “Resource Sheet” and notice that there is a


problem with the “Trainer” Resource. To resolve this problem,
assign a “Max. Units” of 10 Trainers; otherwise, the problem
will exist.

92
93

93
94

11. Using Overtime:

 Overtime work does not represent additional work on a Task;


instead, it represents the amount of time that is spent on a
Task outside regular hours.

 To Enter Overtime:

1. Display the “Gantt Chart” View (“View/Gantt Chart”)

2. Choose “Window/Split” to reveal the “Task Form” in the bottom


pane.

3. Click the “Task Form” to make it the active pane.

4. Choose “Format/Details/Resource Work”. Project adds the “Ovt.


Work” column to the “Task Form”:

5. Move to the top pane, and select the task to which you want to
assign overtime.

94
95

6. Move to the bottom pane and fill in the “Overtime Work” for the
appropriate Resource.

7. Click OK, Project adjusts the schedule.

8. You can adjust the “top pane” of the “Gant Chart” so that you
can display the “Overtime Work” & “Overtime Cost” columns
as shown:

95
96

12. Design and Display the different Reports

96
97

Case Study No 2 (Arabic):

Background:

1. You have been assigned the responsibility for scheduling and


monitoring the progress of Building the 2nd Floor of a Villa.

2. Major Engineering Design tasks have been completed.

3. The Project consists of 28 major Activities (Tasks). The


following list of Project Activities includes the basic
information which you need to schedule and track the principle
Activities in the Project.

4. While you are in charge of the scheduling and implementation


of the overall Project, you will receive monthly reports of
Project Implementation Progress from the Construction Site
Supervisors.

5. On the basis of monthly reports from the Project Site, you will
monitor the progress of Project Execution.

6. In carrying out your assignment, you are aware that the


OWNER is anxious to open the Project as early as possible.

97
98

This Case Study will cover the following points:

1. Project Calendar(s),

2. Work Breakdown Structure (WBS) with Responsible


Managers Assignment.

3. Entering Project Activities with their Duration and


Relationships.

4. Scheduling & Assigning Constraints.

5. Establishing Project & Activity Codes which may determine


Responsibilities and Type of Work.

6. Establishing Roles & Resources Dictionaries and Assign


them to Activities as needed to execute the Project which may
be Labor, nonlabor (Equipment) [Work], Material, and
Money (Expenses - Cost/Use).

7. Analyze Project Resources, Optimize the Project Plan,


Baselining the Project Plan, Execute, and Control (Update).

8. Producing different set of Reports, for example:

 Tabular Schedules,

 Bar Charts,

 Time-Scaled Logic Diagrams,

 Project Network Diagrams,

 Resource and Cost Reports:

o Project Labor, Nonlabor (Equipment), Material,


and Expenses Costs,

o Project Cash-Flow, etc….

98
99

Now,

Project Name: Case_2

Project Start Date: 1 Jan 2010

Project Current Date: 1 Jan 2010

Project Calendar: Case_2 Cal

 Holidays:

o 7 January (Christmas --- repeated)

o 1 May (Workers Day --- repeated)

o 23 July (July Revolution --- repeated)

o 6 October (Vector Day --- repeated)

Working Steps:

1. Create New Project called “Case_2.1”

2. Change the Start Date & Current Date of the Project to


“1/1/2010”.

b. “Project/Project Information”

c. Start date: 1/1/2010

d. Current date: 1/1/2010

99
100

3. Create a New Calendar: “Cae_2 Cal”.

a. “Tools/Change Working Time”

b. “Create New Calendar…”

i. Name: Case_2 Cal

ii. Press “Options”

iii. Week Starts on: Sunday

iv. Press OK

v. Press “Workweek” tab on the “Change Working Time”


window.

vi. Change the “Sunday” to working day

vii. Change Friday to Non-working Day

viii. Press OK.

ix. Create the Calendar Holidays as mentioned above.

100
101

4. Assign “Case_2 Cal” to “Case_2.1” Project.

a. “Project/Project Information”

b. Calendar: Case_2 Cal.

c. Press OK.

5. Make “Case_2 Cal” as a “Global Calendar”.

6. Enter Tasks, Durations & Relationships.

a. Look at the Gantt-Chart Area and notice the non-working days


which contradicts the Project Calendar named “Case_2 Cal”.
b. To resolve this problem, click in the Bar-Chart Area and right-
click to choose “Nonworking Time…”
c. Choose “Case_2 Cal” for “Calendar:” field.

d. Enter the Project Tasks & Relationships:

101
102

102
103

103
104

104
105

105
106

7. Coding & Organization:

a. Create two Fields from “Custom Fields” named


“Responsibility” & “Type of Work” to represent just Codes
for the Project Activities.

b. This can be done by creating “Custom Fields” as follows:

c. Click “Tools/Customize/Fields…”, the “Custom Fields”


window appears:

d. Write the field name “Responsibility” as Text1

106
107

e. Press “Lookup…” button to enter the different values for the


custom field as shown:

f. In the “Gantt Chart” view, insert a new column and choose


“Responsibility” Custom Field.

g. Fill in and assign the Responsible for each Task in the Project.

107
108

h. Now, you can organize by “Responsibility” as follows:

i. Click “Project / Group by / Customize Group By…”,


the following “Customize Group By” Window appears:

ii. Choose the Custom Field “Responsibility” as shown


above.

iii. Press OK, the following Layout appears:

108
109

109
110

110
111

iv. Repeat with the Custom Field “Type of Work”

111
112

112
113

8. Record the Resources in the “Resource Sheet”:

a. “View/Resource Sheet”

b. Fill in the Resources as shown:

113
114

Units of Measurements

114
115

115
116

9. Assign different Resources to different Tasks.

a. Before Assigning Resources, It will be useful to change the


Task Types to “Fixed Duration” Tasks & Change the “Effort
Driven to “No”.

b. To facilitate this process, insert two columns as shown:

116
117

117
118

c. You can also do the following at the beginning of Creating the


Project:

“Tools/Options/Schedule”
• Duration is entered in: Days
• Work is entered in: Days
• Default Task Type: Fixed Duration

118
119

d. Now, assign the Resources:

i. Display the “Gantt Chart” and Split the Window.

ii. Display “Resource Work” in the bottom window

1. Right-click & choose “Resource Work”

2. Highlight the 1st activity and click on the bottom


pane to Assign Resources.

3. Use the following “Table of Project’s Resources”

119
120

PROJECT’s RESOURCES
(Activities are sorted by ES and TF)

ID Act. ID
OD Label
Task Resource Units BQ
UOM (Work)
01 STA2 Start 2nd floor activities 01 0.00 0.00
‫ﺍﻟﺘﺠﻬﻴﺰ ﻟﺒﺪء ﺍﻟﻌﻤﻞ‬
02 CO22C100 2nd floor form work columns 07 CARPENTR 6.00 42.00
‫ﺃﻋﻤﺎﻝ ﺷﺪ ﺍﻟﻨﺠﺎﺭﺓ ﻟﻸﻋﻤﺪﺓ‬ ‫ﻧﺠﺎﺭ ﻣﺴﻠﺢ‬
03-1 CO22C200 2nd floor R.F.T columns 04 R.F.T TON 3.00 12.00
‫ﺭﺹ ﺍﻟﺤﺪﻳﺪ ﻟﻸﻋﻤﺪﺓ‬ ‫ﺣﺪﻳﺪ ﺗﺴﻠﻴﺢ‬
03-2 CO22C200 2nd floor R.F.T columns 04 STEELMEN 3.00 12.00
‫ﺭﺹ ﺍﻟﺤﺪﻳﺪ ﻟﻸﻋﻤﺪﺓ‬ ‫ﺣﺪﺍﺩ ﻣﺴﻠﺢ‬
04-1 CO22C300 2nd floor cast in place concrete columns 03 CONC.MIX DAY 1.00 3.00
‫ﺻﺐ ﺍﻟﺨﺮﺳﺎﻧﺔ ﺍﻟﻤﺴﻠﺤﺔ ﻟﻸﻋﻤﺪﺓ‬ ‫ﺍﻟﺨﻼﻃﺔ ﺍﻟﺨﺮﺳﺎﻧﻴﺔ‬
04-2 CO22C300 2nd floor cast in place concrete columns 03 CON.LABR 1.00 3.00
‫ﺻﺐ ﺍﻟﺨﺮﺳﺎﻧﺔ ﺍﻟﻤﺴﻠﺤﺔ ﻟﻸﻋﻤﺪﺓ‬ ‫ﻃﻘﻢ ﺍﻟﻄﺒﻠﻴﺔ‬
04-3 CO22C300 2nd floor cast in place concrete columns 03 CEMENT TON 10.00 30.00
‫ﺻﺐ ﺍﻟﺨﺮﺳﺎﻧﺔ ﺍﻟﻤﺴﻠﺤﺔ ﻟﻸﻋﻤﺪﺓ‬ ‫ﺍﻷﺳﻤﻨﺖ‬
04-4 CO22C300 2nd floor cast in place concrete columns 03 SAND CM 11.67 35.00
‫ﺻﺐ ﺍﻟﺨﺮﺳﺎﻧﺔ ﺍﻟﻤﺴﻠﺤﺔ ﻟﻸﻋﻤﺪﺓ‬ ‫ﺍﻟﺮﻣﻞ‬
04-5 CO22C300 2nd floor cast in place concrete columns 03 GRAVEL CM 23.33 70.00
‫ﺻﺐ ﺍﻟﺨﺮﺳﺎﻧﺔ ﺍﻟﻤﺴﻠﺤﺔ ﻟﻸﻋﻤﺪﺓ‬ ‫ﺍﻟﺰﻟﻂ‬
05-1 CO22C400 2nd floor curing time for columns 05 WATERPRI CM 1.60 8.00
‫ ﻓﻚ ﺍﻟﺸﺪﺓ ﺍﻟﺨﺸﺒﻴﺔ‬+ ‫ﺃﻋﻤﺎﻝ ﺍﻟﻤﻌﺎﻟﺠﺔ‬ ‫ﺛﻤﻦ ﺍﻟﻤﻴﺎﻩ‬

120
121

05-2 CO22C400 2nd floor curing time for columns 05 LABOUR 1.00 5.00
‫ ﻓﻚ ﺍﻟﺸﺪﺓ ﺍﻟﺨﺸﺒﻴﺔ‬+ ‫ﺃﻋﻤﺎﻝ ﺍﻟﻤﻌﺎﻟﺠﺔ‬
06 CO22S100 2nd floor (slabs+stairs) form work 11 CARPENTR 10.00 110.00
‫ﺷﺪ ﺍﻟﻨﺠﺎﺭﺓ ﺍﻟﻤﺴﻠﺤﺔ ﻟﻸﺳﻘﻒ ﻭﺍﻟﺴﻼﻟﻢ‬ ‫ﻧﺠﺎﺭ ﻣﺴﻠﺢ‬
07-1 CO22S200 2nd floor (slabs+stairs) R.F.T 07 STEELMEN 2.29 16.00
‫ﺭﺹ ﺍﻟﺤﺪﻳﺪ ﻟﻸﺳﻘﻒ ﻭﺍﻟﺴﻼﻟﻢ‬ ‫ﺣﺪﺍﺩ ﻣﺴﻠﺢ‬
07-2 CO22S200 2nd floor (slabs+stairs) R.F.T 07 R.F.T TON 3.71 26.00
‫ﺭﺹ ﺍﻟﺤﺪﻳﺪ ﻟﻸﺳﻘﻒ ﻭﺍﻟﺴﻼﻟﻢ‬ ‫ﺣﺪﻳﺪ ﺗﺴﻠﻴﺢ‬
08-1 CO22S300 2nd floor (slabs+stairs) cast in place 03 CON.LABR 2.00 6.00
‫ﺻﺐ ﺍﻟﺨﺮﺳﺎﻧﺔ ﺍﻟﻤﺴﻠﺤﺔ ﻟﻸﺳﻘﻒ ﻭﺍﻟﺴﻼﻟﻢ‬ ‫ﻃﻘﻢ ﺍﻟﻄﺒﻠﻴﺔ‬
08-2 CO22S300 2nd floor (slabs+stairs) cast in place 03 CONC.MIX DAY 2.00 6.00
‫ﺻﺐ ﺍﻟﺨﺮﺳﺎﻧﺔ ﺍﻟﻤﺴﻠﺤﺔ ﻟﻸﺳﻘﻒ ﻭﺍﻟﺴﻼﻟﻢ‬ ‫ﺍﻟﺨﻼﻃﺔ ﺍﻟﺨﺮﺳﺎﻧﻴﺔ‬
08-3 CO22S300 2nd floor (slabs+stairs) cast in place 03 CEMENT TON 25.00 76.00
‫ﺻﺐ ﺍﻟﺨﺮﺳﺎﻧﺔ ﺍﻟﻤﺴﻠﺤﺔ ﻟﻸﺳﻘﻒ ﻭﺍﻟﺴﻼﻟﻢ‬ ‫ﺍﻷﺳﻤﻨﺖ‬
08-4 CO22S300 2nd floor (slabs+stairs) cast in place 03 SAND CM 29.00 87.00
‫ﺻﺐ ﺍﻟﺨﺮﺳﺎﻧﺔ ﺍﻟﻤﺴﻠﺤﺔ ﻟﻸﺳﻘﻒ ﻭﺍﻟﺴﻼﻟﻢ‬ ‫ﺍﻟﺮﻣﻞ‬
08-5 CO22S300 2nd floor (slabs+stairs) cast in place 03 GRAVEL CM 58.00 174.00
‫ﺍﻟﺰﻟﻂ‬
09-1 CO22S400 2nd floor (curing time+removal of form 10 LABOUR 1.00 10.00
work) slab ‫ﻋﻤﺎﻟﺔ ﻋﺎﺩﻳﺔ‬
‫ ﻓﻚ ﺍﻟﺸﺪﺓ ﺍﻟﺨﺸﺒﻴﺔ ﻟﻸﺳﻘﻒ ﻭﺍﻟﺴﻼﻟﻢ‬+ ‫ﺃﻋﻤﺎﻝ ﺍﻟﻤﻌﺎﻟﺠﺔ‬
09-2 CO22S400 2nd floor (curing time+removal of form 10 WATERPRI CM 2.00 20.00
work) slab ‫ﺛﻤﻦ ﺍﻟﻤﻴﺎﻩ‬
‫ ﻓﻚ ﺍﻟﺸﺪﺓ ﺍﻟﺨﺸﺒﻴﺔ ﻟﻸﺳﻘﻒ ﻭﺍﻟﺴﻼﻟﻢ‬+ ‫ﺃﻋﻤﺎﻝ ﺍﻟﻤﻌﺎﻟﺠﺔ‬
10-1 BLO2 100 2nd floor block work thick 25 cm 12 BRIC.LAY 3.00 36.00
‫ ﺳﻢ‬25 ‫ﺃﻋﻤﺎﻝ ﻣﺒﺎﻧﻲ‬ ‫ﺑﻨﺎ‬
10-2 BLO2 100 2nd floor block work thick 25 cm 12 CEMENT TON 1.75 21.00
‫ ﺳﻢ‬25 ‫ﺃﻋﻤﺎﻝ ﻣﺒﺎﻧﻲ‬ ‫ﺍﻷﺳﻤﻨﺖ‬

121
122

10-3 BLO2 100 2nd floor block work thick 25 cm 12 BRICKMAT SM 180.00 2160.00
‫ ﺳﻢ‬25 ‫ﺃﻋﻤﺎﻝ ﻣﺒﺎﻧﻲ‬ ‫ ﺳﻢ‬25 ‫ﻃﻮﺏ‬
11-1 BLO2 200 2nd floor block work thick 12 cm 04 BRIC.LAY 2.00 8.00
‫ ﺳﻢ‬12 ‫ﺃﻋﻤﺎﻝ ﻣﺒﺎﻧﻲ‬ ‫ﺑﻨﺎ‬
11-2 BLO2 200 2nd floor block work thick 12 cm 04 BRICKMAT SM 79.50 318.00
‫ ﺳﻢ‬12 ‫ﺃﻋﻤﺎﻝ ﻣﺒﺎﻧﻲ‬ ‫ ﺳﻢ‬12 ‫ﻃﻮﺏ‬
11-3 BLO2 200 2nd floor block work thick 12 cm 04 CEMENT TON 0.75 3.00
‫ ﺳﻢ‬12 ‫ﺃﻋﻤﺎﻝ ﻣﺒﺎﻧﻲ‬ ‫ﺍﻷﺳﻤﻨﺖ‬
12 WOD2 100 2nd floor (windows+doors) sub frames 07 DOORCARP 4.00 28.00
‫ﺗﺮﻛﻴﺐ ﺣﻠﻮﻕ ﺍﻷﺑﻮﺍﺏ ﻭﺍﻟﺸﺒﺎﺑﻴﻚ‬ ‫ﻧﺠﺎﺭ ﺑﺎﺏ ﻭﺷﺒﺎﻙ‬
13-1 ELE2 100 2nd floor electrical conduits 07 0.00 0.00
‫ﺗﺮﻛﻴﺐ ﻣﻮﺍﺳﻴﺮ ﺍﻟﻜﻬﺮﺑﺎء ﻓﻲ ﺍﻟﺤﻮﺍﺋﻂ‬
13-2 ELE2 100 2nd floor electrical conduits 07 0.00 0.00
‫ﺗﺮﻛﻴﺐ ﻣﻮﺍﺳﻴﺮ ﺍﻟﻜﻬﺮﺑﺎء ﻓﻲ ﺍﻟﺤﻮﺍﺋﻂ‬
14-1 INP2 100 2nd floor internal plastering for (walls+slabs) 20 PLAS.MEN 5.00 100.00
‫ﺍﻟﺒﻴﺎﺽ ﺍﻟﺪﺍﺧﻠﻲ ﻟﻸﺳﻘﻒ ﻭﺍﻟﺤﻮﺍﺋﻂ‬ ‫ﻣﺘﺦﺻﺺ ﺑﻴﺎﺽ‬
14-2 INP2 100 2nd floor internal plastering for (walls+slabs) 20 CEMENT TON 1.15 23.00
‫ﺍﻟﺒﻴﺎﺽ ﺍﻟﺪﺍﺧﻠﻲ ﻟﻸﺳﻘﻒ ﻭﺍﻟﺤﻮﺍﺋﻂ‬ ‫ﺍﻷﺳﻤﻨﺖ‬
14-3 INP2 100 2nd floor internal plastering for (walls+slabs) 20 SAND CM 5.55 111.00
‫ﺍﻟﺒﻴﺎﺽ ﺍﻟﺪﺍﺧﻠﻲ ﻟﻸﺳﻘﻒ ﻭﺍﻟﺤﻮﺍﺋﻂ‬ ‫ﺍﻟﺮﻣﻞ‬
14-4 INP2 100 2nd floor internal plastering for (walls+slabs) 20 GUYPSUM TON 0.10 2.00
‫ﺍﻟﺒﻴﺎﺽ ﺍﻟﺪﺍﺧﻠﻲ ﻟﻸﺳﻘﻒ ﻭﺍﻟﺤﻮﺍﺋﻂ‬ ‫ﺟﻴﺒﺲ‬
15-1 SAN2 100 2nd floor sanitary pipes 20 PLUMBER 3.00 60.00
‫ﺗﺮﻛﻴﺐ ﻣﻮﺍﺳﻴﺮ ﺍﻟﺬﻫﺮ‬ ‫ﺳﺒﺎﻙ‬
15-2 SAN2 100 2nd floor sanitary pipes 20 SAN.PIPE LM 7.50 150.00
‫ﺗﺮﻛﻴﺐ ﻣﻮﺍﺳﻴﺮ ﺍﻟﺬﻫﺮ‬ ‫ﻣﻮﺍﺳﻴﺮ ﺍﻟﺼﺮﻑ‬
‫ﺍﻟﺼﺤﻲ‬

122
123

16-1 INP2 200 2nd floor TRATZO plastering 08 PLAS.MEN 3.00 24.00
‫ ﻡ ﻋﺎﺩﺓ ﻣﺎ ﻳﻜﻮﻥ ﻓﻲ ﺍﻟﻤﻤﺮﺍﺕ‬2 ‫ﺳﻔﻞ ﺑﺄﺭﺗﻔﺎﻉ‬ ‫ﻣﺘﺨﺼﺺ ﺑﻴﺎﺽ‬
16-2 INP2 200 2nd floor TRATZO plastering 08 CEMENT TON 1.25 10.00
‫ ﻡ ﻋﺎﺩﺓ ﻣﺎ ﻳﻜﻮﻥ ﻓﻲ ﺍﻟﻤﻤﺮﺍﺕ‬2 ‫ﺳﻔﻞ ﺑﺄﺭﺗﻔﺎﻉ‬ ‫ﺍﻷﺳﻤﻨﺖ‬
16-3 INP2 200 2nd floor TRATZO plastering 08 SAND CM 29.38 235.00
‫ ﻡ ﻋﺎﺩﺓ ﻣﺎ ﻳﻜﻮﻥ ﻓﻲ ﺍﻟﻤﻤﺮﺍﺕ‬2 ‫ﺳﻔﻞ ﺑﺄﺭﺗﻔﺎﻉ‬ ‫ﺍﻟﺮﻣﻞ‬
16-4 INP2 200 2nd floor TRATZO plastering 08 GUYPSUM TON 0.13 1.00
‫ ﻡ ﻋﺎﺩﺓ ﻣﺎ ﻳﻜﻮﻥ ﻓﻲ ﺍﻟﻤﻤﺮﺍﺕ‬2 ‫ﺳﻔﻞ ﺑﺄﺭﺗﻔﺎﻉ‬ ‫ﺟﻴﺒﺲ‬
16-5 INP2 200 2nd floor TRATZO plastering 08 WHITECEN TON 0.38 3.00
‫ ﻡ ﻋﺎﺩﺓ ﻣﺎ ﻳﻜﻮﻥ ﻓﻲ ﺍﻟﻤﻤﺮﺍﺕ‬2 ‫ﺳﻔﻞ ﺑﺄﺭﺗﻔﺎﻉ‬ ‫ﺃﺳﻨﺖ ﺃﺑﻴﺾ‬
17-1 SAN2 200 2nd floor potable water piping circuits 09 PLUMBER 3.00 27.00
‫ ﺳﺒﺎﻛﺔ‬- ‫ﺗﺮﻛﻴﺐ ﻣﻮﺍﺳﻴﺮ ﺍﻟﺸﺮﺏ‬ ‫ﺳﺒﺎﻙ‬
17-2 SAN2 200 2nd floor potable water piping circuits 09 IRON.PIP LM 21.11 190.00
‫ ﺳﺒﺎﻛﺔ‬- ‫ﺗﺮﻛﻴﺐ ﻣﻮﺍﺳﻴﺮ ﺍﻟﺸﺮﺏ‬ ‫ﻣﻮﺍﺳﻴﺮ ﺣﺪﻳﺪ‬
18-1 ELE2 200 2nd floor electrical wires 14 0.00 0.00
‫ﺃﺩﺧﺎﻝ ﺍﻷﺳﻼﻙ ﻓﻲ ﺍﻟﻤﻮﺍﺳﻴﺮ ﺍﻟﻜﻬﺮﺑﻴﺔ‬
18-2 ELE2 200 2nd floor electrical wires 14 0.00 0.00
‫ﺃﺩﺧﺎﻝ ﺍﻷﺳﻼﻙ ﻓﻲ ﺍﻟﻤﻮﺍﺳﻴﺮ ﺍﻟﻜﻬﺮﺑﻴﺔ‬
19-1 FLO2 100 2nd floor mosaic tiles dim 40*40 cm 10 MOSAIC SM 125.00 1250.00
‫ ﺳﻢ‬40*40 ‫ﺗﺮﻛﻴﺐ ﺑﻼﻁ‬ ‫ﺳﻴﺮﺍﻣﻴﻚ‬
19-2 FLO2 100 2nd floor mosaic tiles dim 40*40 cm 10 TILE.MEN 2.00 20.00
‫ ﺳﻢ‬40*40 ‫ﺗﺮﻛﻴﺐ ﺑﻼﻁ‬ ‫ﻣﺒﻠﻂ‬
19-3 FLO2 100 2nd floor mosaic tiles dim 40*40 cm 10 SAND CM 5.00 50.00
‫ ﺳﻢ‬40*40 ‫ﺗﺮﻛﻴﺐ ﺑﻼﻁ‬ ‫ﺍﻟﺮﻣﻞ‬
19-4 FLO2 100 2nd floor mosaic tiles dim 40*40 cm 10 CEMENT TON 0.80 8.00
‫ ﺳﻢ‬40*40 ‫ﺗﺮﻛﻴﺐ ﺑﻼﻁ‬ ‫ﺍﻷﺳﻤﻨﺖ‬
20-1 ISO2 100 2nd floor bathrooms proofing 02 ISO.MEN 1.00 2.00
‫ﺃﻉﻣﺎﻝ ﺍﻟﻌﺰﻝ ﻟﻠﺤﻤﺎﻣﺎﺕ‬ ‫ﻣﺘﺨﺼﺺ ﻋﺰﻝ‬

123
124

20-2 ISO2 100 2nd floor bathrooms proofing 02 INSULATI SM 100.00 200.00
‫ﺃﻋﻤﺎﻝ ﺍﻟﻌﺰﻝ ﻟﻠﺤﻤﺎﻣﺎﺕ‬ ‫ﻣﺎﺩﺓ ﻋﺎﺯﻟﺔ‬
21-1 CER2 100 2nd floor ceramic (walls+slabs) 04 CERAMIC SM 50.00 200.00
‫ﺗﺮﻛﻴﺐ ﺍﻟﺴﻴﺮﺍﻣﻴﻚ ﻟﻠﺤﻤﺎﻣﺎﺕ‬ ‫ﺳﻴﺮﺍﻣﻴﻚ‬
21-2 CER2 100 2nd floor ceramic (walls+slabs) 04 CER.MEN 2.00 8.00
‫ﺗﺮﻛﻴﺐ ﺍﻟﺴﻴﺮﺍﻣﻴﻚ ﻟﻠﺤﻤﺎﻣﺎﺕ‬ ‫ﻣﺘﺨﺼﺺ ﺗﺮﻛﻴﺐ‬
‫ﺳﻴﺮﺍﻣﻴﻚ‬
21-3 CER2 100 2nd floor ceramic (walls+slabs) 04 SAND CM 2.25 9.00
‫ﺗﺮﻛﻴﺐ ﺍﻟﺴﻴﺮﺍﻣﻴﻚ ﻟﻠﺤﻤﺎﻣﺎﺕ‬ ‫ﺍﻟﺮﻣﻞ‬
22-1 PAI2 100 2nd floor painting preparation layers 06 PAINTMEN 2.00 12.00
‫ﺃﻋﻤﺎﻝ ﺍﻟﺒﻄﺎﻧﺔ ﻟﻠﺪﻫﺎﻧﺎﺕ‬ ‫ﻣﺘﺨﺼﺺ ﺑﻴﺎﺽ‬
22-2 PAI2 100 2nd floor painting preparation layers 06 PAINTMAT SM 308.33 1850.00
‫ﺃﻋﻤﺎﻝ ﺍﻟﺒﻄﺎﻧﺔ ﻟﻠﺪﻫﺎﻧﺎﺕ‬ ‫ﻣﻮﺍﺩ ﺍﻟﺪﻫﺎﻧﺎﺕ‬
23-1 FRP2 100 2nd floor frontal plastering 21 FRON.PLA 4.00 84.00
‫ﺑﻴﺎﺽ ﺍﻟﻮﺍﺟﻬﺎﺕ‬ - ‫ﻣﺒﻴﺾ ﻣﺤﺎﺭﺓ‬
‫ﻭﺍﺟﻬﺎﺕ‬
23-2 FRP2 100 2nd floor frontal plastering 21 CEMENT TON 1.48 31.00
‫ﺑﻴﺎﺽ ﺍﻟﻮﺍﺟﻬﺎﺕ‬ ‫ﺍﻷﺳﻤﻨﺖ‬
23-3 FRP2 100 2nd floor frontal plastering 21 SAND CM 4.05 85.00
‫ﺑﻴﺎﺽ ﺍﻟﻮﺍﺟﻬﺎﺕ‬ ‫ﺍﻟﺮﻣﻞ‬
23-4 FRP2 100 2nd floor frontal plastering 21 GUYPSUM TON 0.05 1.00
‫ﺑﻴﺎﺽ ﺍﻟﻮﺍﺟﻬﺎﺕ‬ ‫ﻣﺘﺨﺼﺺ ﺑﻴﺎﺽ‬
23-5 FRP2 100 2nd floor frontal plastering 21 WHITECEN TON 0.14 3.00
‫ﺑﻴﺎﺽ ﺍﻟﻮﺍﺟﻬﺎﺕ‬
24-1 SAN2 300 2nd floor install of sanitary fixtures 06 PLUMBER 2.00 12.00
‫ ﺳﺒﺎﻛﺔ‬- ‫ﺗﺮﻛﻴﺐ ﺍﻷﺣﻮﺍﺽ ﻭﺍﻟﺤﻨﻔﻴﺎﺕ‬ ‫ﺳﺒﺎﻙ‬
24-2 SAN2 300 2nd floor install of sanitary fixtures 06 SAN.FIXT PART 2.00 12.00
‫ ﺳﺒﺎﻛﺔ‬- ‫ﺗﺮﻛﻴﺐ ﺍﻷﺣﻮﺍﺽ ﻭﺍﻟﺤﻨﻔﻴﺎﺕ‬ ‫ﺻﻴﻨﻲ‬

124
125

25-1 WOD 2200 2nd floor install (doors+windows) 10 DOORCARP 7.20 72.00
‫ﺗﺮﻛﻴﺐ ﺍﻷﺑﻮﺍﺏ ﻭﺍﻟﺸﺒﺎﺑﻴﻚ‬ ‫ﻧﺠﺎﺭ ﺑﺎﺏ ﻭﺷﺒﺎﻙ‬
25-2 WOD 2200 2nd floor install (doors+windows) 10 MOS.DOOR PART 7.20 72.00
‫ﺗﺮﻛﻴﺐ ﺍﻷﺑﻮﺍﺏ ﻭﺍﻟﺸﺒﺎﺑﻴﻚ‬ ‫ﺃﺑﻮﺍﺏ ﻭﺷﺒﺎﺑﻴﻚ‬
‫ﻣﻮﺳﻜﻲ‬
26-1 PAI2 200 2nd floor final painting layers 12 PAINTMAT SM 308.33 3700.00
‫ﺃﻋﻤﺎﻝ ﺍﻟﺪﻫﺎﻧﺎﺕ ﺍﻟﻨﻬﺎﺋﻴﺔ‬ ‫ﻣﻮﺍﺩ ﺍﻟﺪﻫﺎﻧﺎﺕ‬
26-2 PAI2 200 2nd floor final painting layers 12 PAINTMEN 2.00 24.00
‫ﺃﻋﻤﺎﻝ ﺍﻟﺪﻫﺎﻧﺎﺕ ﺍﻟﻨﻬﺎﺋﻴﺔ‬ ‫ﻧﻘﺎﺵ‬
27-1 ELE2 300 2nd floor electrical switches lighting fix 14 LIG.FIXT PART 17.86 250.00
‫ﺗﺮﻛﻴﺒﺎﺕ ﻛﻬﺮﺑﺎﺋﻴﺔ ﻧﻬﺎﺋﻴﺔ‬ ‫ﺗﺮﻛﻴﺒﺎﺕ ﻛﻬﺮﺑﻴﺔ‬
27-2 ELE2 300 2nd floor electrical switches lighting fix 14 0.00 0.00
‫ﺗﺮﻛﻴﺒﺎﺕ ﻙﻫﺮﺑﺎﺋﻴﺔ ﻧﻬﺎﺋﻴﺔ‬
28 END2 2nd floor hand over activities 01 0.00 0.00
‫ﺗﺴﻠﻴﻢ ﺍﻟﻤﺸﺮﻭﻉ‬

125
126

Work = Budget Quantity

126
127

10. Design and Display the different Reports

127
128

Case Study No 2 (English):


Project Name: Case_2

Project Start date: 1 Jan 2010

Calendar: Case_2 Cal


 Holidays:
o 7 January (repeated)
o 1 May (repeated)
o 23 July (repeated)
o 6 October (repeated)

Working Steps:

1. Create New Project called “Case_2.1 Basic Data”.

2. Change the Start Date of the Project to “1/1/2010”.

a. “Project/Project Information”

b. Start date: 1/1/2010

3. Create a New Calendar: “Case_2 Cal”.

a. Click “Tools/Change Working Time…”

b. Click “Create New Calendar…”


i. Name: Case_2 Cal
ii. Press “Options”
iii. Week Starts on: Sunday
iv. Press OK
v. Press “Work Weeks” tab on the “Change Working
Time” window.
vi. Change the “Sunday” to working day
vii. Change Friday to Non-working day
viii. Press OK.
ix. Create the Calendar Holidays as mentioned above.

128
129

4. Assign “Case_2 Cal” to “Case_2.1 Basic Data”.

a. Click “Project/Project Information”

b. Calendar: Case_2 Cal.

c. Press OK.

5. Make “Case_2 C al” as a “Global Calendar”.

6. Enter Tasks, Durations & Relationships.

a. Do the following before Entering Tasks, Duration, &


Relationship:

“Tools/Options/Schedule”
• Duration is entered in: Days
• Work is entered in: Days
• Default Task Type: Fixed Duration

129
130

130
131

b. Look at the Gantt-Chart area and notice the non-working days


which contradicts the Project Calendar named “Case_2 al”.

c. To resolve this problem, click in the Bar-Chart area and right-


click to choose “Nonworking Time…”

d. Choose “Case_2 Cal” for “Calendar:” field.

e. Enter the Project Tasks & Relationships:

131
132

132
133

133
134

134
135

135
136

7. Coding & Organization:

a. Create two Custom Fields from “Tools / Custom Fields…”


named “Responsibility” & “Type of Work” to represent just
Codes for the Tasks of Project.

b. This can be done by creating “Custom Field” as follows:

136
137

c. Press “Lookup…” button to enter the different values for the


custom field as shown:

d. In the “Gantt Chart” view, insert a new column and choose


“Responsibility.

e. Fill in and assign the responsibility value for each task in the
Project.

f. Now, you can organize by “Responsibility” as follows:

137
138

i. “Project / Group by: No Group / Customize Group


By…”, the following window appears:

ii. Choose “Responsibility” in the “Field Name” of


“Group By” as shown above.

iii. Press OK, the following Layout appears:

138
139

139
140

140
141

Coding & Organization:

 In the previous Project “Case_2 Arabic”, we exercised the Project


Organization using the Task Code called “Responsibility”.

 Now, let us create a Custom Field named “Type of Work” to


represent just another Task Code in the Project.

 This can be done by clicking “Tools / Customize / Fields…”, the


Custom Fields window appears:

141
142

 Write the name “Type of Work” as Text3:

 Press “Lookup…” button to enter the different values for the Custom
Field as shown:

142
143

 In the “Gantt Chart” View, insert a new column and choose “Type
of Work”.

 Assign the specific Value corresponding to each Task as shown:

143
144

144
145

 Now, Let us ask a Question Like this: Display All Tasks of


Concrete for Columns.

 To answer this Question, make a Filter using:

o “Project / Filtered for / More Filters… / New…”, the


following window appears:

 Press “New…”, the following window appears:

145
146

 Fill in as shown:

 Press OK, the following Layout including only the requested Tasks
appears:

146
147

147
148

 In the same manner, you can display what you want.

 Exercise you self and try to answer any question concerning this
Project.

148
149

8. Record the Resources in the “Resource Sheet”:


a. “View/Resource Sheet”

b. Fill in the Resources as shown:

Units of Measurements

149
150

150
151

9. Assign different Resources to different Tasks.

a. Before Assigning Resources, It will be useful to change the


Task Types to “Fixed Duration” Tasks & Change the “Effort
Driven to “No”.
[Default: Task Type—Fixed Units & Effort Driven=Yes]

b. To facilitate this process, insert two columns as shown:

c. You can also do the following:

i. “Tools/Options/Schedule”
• Duration is entered in: Days
• Work is entered in: Days
• Default Task Type: Fixed Duration

151
152

Task Types (Fixed Duration, Fixed Units, Fixed Work):


The way MS Project uses Work, Duration, and Resources to schedule
Tasks is called effort-driven scheduling, which is the default scheduling
method. With effort-driven scheduling, the more Resources you assign to a
Task, the shorter the Duration becomes.
To have MS Project schedule a Task exactly the way you want it, you need
to know how these factors do that.

Changing the Task Type:

 The Duration of each Task is determined by Resource Availability


and (most important) by the formula:

Duration = Work ÷ Resource Units


or
Work = Duration * Resource Units

 If you assign Resources, MS Project uses this formula as the basis for
all its scheduling.

 A Task Type (Fixed Duration, Fixed Units, or Fixed Work) is a


method MS Project uses to calculate the Work, Duration, and
Resource Units for a Task. You can choose the method you want MS
Project to use on a Task-by-Task Basis.

152
153

Fixed-Units Tasks:

 Example, say you assign 2 full-time Painters to paint the walls


in 4 days. If you assign 2 more full-time Painters, MS Project
reduces the duration to 2 days.

153
154

 If you assign 2 more Painters, MS Project reduces the Duration to 2


days:

154
155

Fixed-Work Tasks:

 When you set a Task to Fixed-Work, MS Project does not calculate


the Work for the Tasks or Resources. Instead, as you change
Resource Assignments, MS Project calculates Duration.

For example, if you assign 2 Painters full-time to paint the walls in 4


days, and then you assign 2 more full-time Painters to the Task, MS
Project reduces the Duration to 2 days.

155
156

Fixed-Duration Tasks:

 When Duration is fixed, it remains at whatever value you enter and


MS Project calculates Resource Units as you change Assignments.

For example, say you assign 2 Painter full-time to paint the walls in 4
days:

156
157

Later, you assign 2 more full-time Painters. MS Project set the units
for each Painter to %50 because 4 Painters need to work only half-
time to complete the walls in 4 days: How ! ! !

157
158

Effort-Driven Tasks:

 Fixed-Work Tasks are always Effort-Driven Task.

 For Fixed-Duration and Fixed-Units Tasks, you can tell MS Project


to modify the % of Total Work that is allocated to each Resource
based on the number of Assigned Resources if the number of
Resources changes.

158
159

In summary:

Task Type: Fixed Units


Effort Driven: Checked
Task Duration Resource New Work
(Units) Duration
A 10 1 10 10d
2 5 10d
5 2 10d

Task Type: Fixed Duration


Effort Driven: Checked/Unchecked
Task Duration Resource New Work
(Units) Duration
A 10 1 10 10d
2 10 10d
5 10 50d

Task Type: Fixed Work


Effort Driven: Checked by Default
Task Duration Resource New Work
(Units) Duration
A 10 1 10 10d
2 5 10d
5 2 10d

Recommendation:
It is better to set Fixed-Duration & No Effort-Driven in the normal and
most common cases.

159
160

160
161

161
162

d. Now, Assign the Resources:

i. Display the “Gantt Chart” and Split the Window.

ii. Display “Resource Work” in the bottom window


o right-click & choose “Resource Work”

iii. Highlight the 1st activity and click down to Assign


Resources.

iv. Use the following sheet to assign Resources to


different Activities.

162
163

Recourse Assignment ‫ﺗﺨﺼﻴﺺ ﺍﻟﻤﻮﺍﺭﺩ ﻟﻸﻧﺸﻄﺔ‬

Budget
Task name D Resource Quantity
ID (Work)
1 Start 0
2 FormWork for Columns 7
Carpenter 42 days
3 RFT for Columns 4
R.F.T 12 Ton
Steel.Men 20 days
Cast-in-Place Concrete for
4 Columns 3
Cement 30 Ton
Conc.Labor 3 days
Conc.Mix 3 days
Gravel 70 CM
Sand 35 CM
5 Curing Time for Columns 5
Ord.Labor 5 days
Water 8 CM
6 FormWork for Slab & Stairs 11
Carpenter 110 days
7 RFT for Slab & Stairs 7
R.F.T 26 Ton
Steel.Men 14 days
8 Cast-in-Place for Slab & Stairs 3
Cement 25 Ton
Conc.Labor 6 days
Conc.Mix 6 days
Gravel 58 CM
Sand 29 CM
Curing Time& Removal for
9 FormWork 10
Ord.Labor 10 days
Water 2 CM
10 Block Working thick 25 cm 12
Bric.Lay 36 days
BrickMat 180 SM
Cement 2 Ton
11 Block Working thick 12 cm 4
Bric.Lay 8 days
BrickMat 80 SM
Cement 1 Ton

163
164

12 Windows & Doors SubFrames 7


Door.Carp 28 days
13 Electrical Conduits 7
Internal Plastering for Walls &
14 Slab 20
Cement 1 Ton
Gypsum 0.1 Ton
Plast.Men 100 days
Sand 6 CM
15 Sanitary Pipes Fixation 20
Plumber 60 days
Iron.Pipes 7.5 LM
16 TRATZO Plastering height 2 m 8
Cement 1.25 Ton
Guypsum 0.13 Ton
Sand 29 CM
TRATZO.Plasters 24 days
White_Cement 0.38 Ton
17 Potable Water Piping Circuits 9
Plumber 27 days
Iron.Pipes 21 LM
18 Electrical Wires Fixation 14
Mosaic Tiles dim 40*40 cm
19 Fixation 10
Cement 0.8 Ton
Mosaic 125 SM
Sand 5 CM
Tiles.Men 20 days
20 Bathrooms Proofing 2
IsolationMaterial 100 SM
Iso.Men 2 days

21 Ceramic Fixation for Walls & Slab 4


Cer.Men 8 days
Ceramic 50 SM
Sand 2 CM
22 Painting Preparation Layers 6
Paint.Materials 308 SM
Paint.Men 12 days
23 Frontal Plastering 21
Cement 1.48 Ton
Front.Plaster 84 days
Gypsum 0.05 Ton
Sand 4 CM

164
165

White_Cement 0.14 Ton


24 Sanitary Installation 6
Plumber 12 days
San.Fixation 2 Part
25 Doors & Windows Installation 10
Door.Carp 70 days
Moskey.Doors 7 Part
26 Final Painting Layers 12
Paint.Materials 308 SM
Paint.Men 24 days
27 Final Electrical Switches Fixation 14
Electrical.Fixation 18 Part
28 Hand Over 0

165
166

166
167

Task Usage View:


 This View is useful for showing and organizing Assigned Resources
under each Task:

Hint:

o By default, the Task Usage Table is shown in the Left-Pane.


To choose a different Table, click on the “Select All” button (at
the top-left-corner of the Table

o Right-click and select the View you wish to see…..

o Right-click on “Work” in the “Details” column of the “Task


Usage Chart”, and select “Cost”. Notice that both the “Work”
& “Cost” are listed in the “Task Usage Chart”.

167
168

Resource Graph (Histogram) View:


 Click on the “Resource Graph” icon within the “View Bar”.

Hint:

o If the Resources are not visible, use the “Scroll Bar” at the bottom
of the “Graph Pane” to navigate to the Dates in which the Project
fall.

o Notice how a red column represents “Over-Allocations”.

168
169

Resource Sheet View:


 This View is useful for viewing, entering, and editing information. It
contains detailed Resource Information in a Worksheet Format.

 This View is very helpful in determining which Group, a Resource


belongs to.

 If an “Over-Allocation” exists, a warning flag is displayed in the


“Indicator” column. In addition, the Resource appears in red color.

169
170

170
171

Resource Usage View:

 This View is useful for seeing each Resource and the Tasks assigned
to that Resource..

 The View can be used for entering and editing Resource


Information, or Assigning Tasks.

 To Assign or Re-Assign a Task, drag-and-drop between Resources.

 A warning flag appears in the “Indicator” column if an “Over-


Allocation” exists.

171
172

172
173

Hint:

 Sometime, the Gant-Chart Pane did not coincide with the Project
Calendar.

 If this is the case, do the following:

o Double-click on the “Timescale”, the “Timescale” window


appears:

o Click on the “Non-working time” tab as shown:

173
174

Choose the “Project Calendar” from the “Calendar” field as


shown above.

174
175

Tracking (Follow Up)

Understanding Tracking:

 Up to this point, you have been in the Planning Phase (Building a


Project Schedule, Entering Tasks, Adding Resources, and
Resolving Resource Conflicts).

 A good Plan is only half way. How you execute that Plan is the Key.

 You now have a Workable, Good-Looking Project in hand --- and


now, you are ready to start the Project.

Updating Form:

 If your organization has forms and processes to capture actual and


status information, use those forms and processes as much as
possible.

 You may want to create a form for participants to use for their
regular reports. These reports should provide the information that you
need to update your project plan in MS-Project. You may be able to
use one of the reports in MS-Project (or customize one of the Project’s
Reports) to provide the necessary information.

 Create New Table as follows:

o Click “View/Table/More Tables/New…”

o Choose:

 ID
 Name
 Duration

175
176

o Insert Blank columns (Text3) with the following Titles:


 AS --- Actual Start
 AF --- Actual Finish
 AD --- Actual Duration
 RD --- Remaining Duration
 % --- Percent Complete
 AC --- Actual Cost
 AW --- Actual Work
 Notes --- Notes

176
177

o Click OK & Apply, the following Table appears.

o You can distribute it on the Engineers at the Site to fill in and


make feedback.

177
178

178
179

Tracking Process:

 First of all, Record the Start & Finish Date before tracking.

 In our case, these Dates are shown as follows:

Now,

179
180

1. Setting BaseLine:
o Click “Tools/Tracking/Set Baseline”

o Press OK. This saves Baseline and displays it in the Gantt-


Chart area

o The following shows the Gantt-Chart before and after the


Baseline:

180
181

181
182

182
183

2. Tracking Progress:

o Click “View/Table/Tracking”, the Tracking Table displays:

183
184

184
185

 Updating Tasks to Reflect Actual Information:

o Record Actual Information for the Project by filling in the


following fields for each Task that tracks the Progress of the
Project (Actual Data from the Site):

ID Task Name Dur AS AF PCT

1 Start 0 1/1/2010 1/1/2010

2 FormWork for 7 4/1/2010 11/1/2010


Columns

3 RFT for Columns 4 8/1/2010 12/1/2010

4 Cast-in-Place 3 13/1/2010 16/1/2010


Concrete for
Columns

5 Curing Time for 5 19/1/2010 25/1/2010


Columns

6 FormWork for Slab 11 24/1/2010 10/2/2010


& Stairs

7 RFT for Slab & 7 30/1/2010 … 80.0


Stairs

o Notice the AF of Task of ID=6; the Act Dur becomes 14


days instead of 11 days…..

185
186

186
187

3. Status Date:
 You can find the Project’s Status Date (Data Date) in the “Project
Information” dialog box.

 If the Status Date is not set, Project uses the Current Date.

187
188

4. Reviewing Progress & Progress Line

a. Progress Line:
Click “Tools/Tracking/Progress Lines…”

188
189

189
190

5. Reschedule Uncompleted Work (F9 in P3e):


a. Click “Tools/Tracking/Update Project…”

b. Fill in the above window as shown above. That is, choose the
option shown. Note that “11 feb” was the Status Date (Data
Date --- Date of calculation for remaining tasks…)
c. Press OK.
d. Now, notice the new Finish Date from the “Project
Information” as shown:

e. Notice that the Project delays 6 days. Before Updating, it was 2


September.

190
191

6. Reviewing Progress:

This phase needs to create the following:

1. Group,

2. Filter,

3. View including Screen, Table, Group, and Filter

7. Group:
 Click “Project/Group by/More Groups…/New…”, the following
window appears:

 Fill in as shown above. Then, Click OK & Apply to check if it works.

191
192

192
193

8. Filter:

 Create a Dynamic Filter as follows:

o Click “Project/Filtered for/More Filters…/New…”

o Name: Case_2 Dynamic Filter

o Low Value <= Early Start <= High Value

o Check “Show in menu”

o Click OK & Apply:

 Press OK & Apply, the following window appears

193
194

 Fill in ,for example, as follows:

 Press OK, another window appears for “High Value”. Fill it as


follows:

 The following window appears. Notice the “Indicator”. The symbol


“√” appears for Completed Tasks:

194
195

195
196

9. Views:

 Beside the Predefined Views discussed earlier, you can customize


your Views by clicking “View/More View…/New”.

196
197

10. Reporting on Project’s Progress:

Refer to Chapter 13, Microsoft Office Project 2007, Elaine


Marmel, Reference No 2.

197
198

Coordinating Multiple Projects


&
Sharing Resources Among Projects

Example:

 Create a Project “S1”:

ID Task D Pred.
1 A1 5
2 A2 3 A1
3 A3 7 A2

 Create a Project “S2”:

ID Task D Pred.
1 B1 5
2 B2 3 B1
3 B3 7 B2

 Create a Project “S3”:

ID Task D Pred.
1 C1 5
2 C2 3 C1
3 C3 7 C2

198
199

 Linking Tasks Across Projects:

To create a link between Tasks in different Projects, type the


Project Name, a backslash, and then the Predecessor ID
Number. For example: c:\MyProject.mmp\10. If the Predecessor
Information is too long, use the “Task Information” dialog box.

o Now, open the 3 Projects at the same time to see the Task IDs
with their updating WBS Codes

o Press “Window/Arrange All”

o Double-click B1. Its predecessor will be: S1\1 [or S1.mmp\1]


(1 means ID of Task A1 or A1’s WBS Code).

o Double-click C1. Its predecessor will be: S2\1 (1 means ID of


Task B1 or B1’s new WBS Code).

o Notice the dummy Activities due to relationships between


subprojects:

199
200

200
201

 Create Resource Pool Project named RP.mmp


o “View/Resource Sheet”

o Enter the following Resources:

Resource Max. Units Rate


Plumber 3 200/day
Carpenter 5 150/day

 Resource Sharing :

o Open S1.mmp & RP.mmp

o With S1 Active:
 “Tools/Resource Sharing/Share Resources…”, the
“Share Resources” window appears.

 Choose “Use resources From: RP” as shown.


 Press OK

o Close S1 and Open S2 and repeat Resource Sharing.

o Close S2 and Open S3 and repeat Resource Sharing.

Hint: in the same manner, you can share resources between all Projects.

201
202

 Create a Main Project called “Main.mmp”:


o Insert the 3 Projects.

o Assign Resources to different Tasks . . .

o Notice the “Over-Allocation” of Resources . . .

202
203

References

1. CHELTENHAM Courseware
Microsoft Project 2007 Manual – Foundation Level
USA / Canada
Email: info@cheltenhamcourseware.com
Web: www.cheltenhamcourseware.com

2. Elaine Marmel,
Microsoft Office Project 2007 Bible_Hendoone

3. Abdalla ElDaoushy,
Projects Time Management & Controlling using
Project Management Software, Memo No (971),
Institute of National Planning, Cairo, Egypt

4. Abdalla ElDaoushy,
Projects Cost Management (Computer Software
Oriented), Memo No (973),
Institute of National Planning, Cairo, Egypt

203

You might also like