Professional Documents
Culture Documents
By
Outline
Introduction
NAPTIN
10 x Generating Stations
27 x new grid connected transformer substations (330/132KV & 132/33KV): extension of
27 others
297 x Injection Sub-stations
23,000 x Distribution Sub-stations (33/0.415KV, 11/0.415KV)
5,000km of 330KV lines
1,600km of 132KV lines
1,700km of 33KV lines
2,700km of 11KV lines
In addition to this, several IPP licenses have been issued by NERC to would-be
GenCos (alone).
These will triple the existing manpower whose skills have to match its OM&A
(Operation, Maintenance and Admin)
NAPTIN
NAPTINs Challenges
Specialised skilled system operators for generation, distribution, and transmission are
urgently required.
Technical manpower required during the project design and construction phase of
various power projects as well as the Operation and Maintenance (O&M) phase.
Urgent need to augment the skills at PHCN and Successor Companies level to orient
them to suit the growing Power Sector needs.
Limited infrastructure/space and training equipment for capacity building compared
to the huge manpower to be trained
Overall, huge funding is required to meet up with scheduled training and re-training.
Presently, paucity of funds causing inability to undertake planned training activities
NAPTIN is still constrained by space as its current rented accommodation has greatly
restricted its training capacity
Major funding is also required for development of its permanent site
NAPTIN
NIPP
0.5%
REA
1%
Ministry of
Power
2%
NAPTIN
1%
PHCN
93%
NERC
1.5%
Private
Owners
NAPTIN
DISCO
3,337
4,597
3,196
7,949
1,424
18
1,483
1,291
1,587
3,581
28,463
GENCO
128
82
1,122
58
391
97
173
39
149
1,163
3,402
LIASION UNIT
140
58
71
40
100
20
175
13
97
702
1,416
TRANSYSCO
258
185
310
18
775
7
216
438
329
869
3,405
TOTAL
3,863
4,922
4,699
8,065
2,690
142
2,047
1,781
2,162
6,315
36,686
TOTAL %
10.5%
13.4%
12.8%
22.0%
7.3%
0.4%
5.6%
4.9%
6%
17.2%
100%
25,0%
22,0%
20,0%
17,2%
15,0%
13,4%
12,8%
10,5%
10,0%
7,3%
5,6%
5,0%
0,4%
0,0%
4,9%
6%
49,5%
50,0%
PROFESSION
Accountants
Craftmen/Artisans
Operators
Education
Engineers
HR
Legal
Technicians
Marketing
Medical
PR
Secretary
Drivers
Others
Total
45,0%
40,0%
35,0%
30,0%
25,0%
20,0%
20,7% 21,4%
18,5% 17,7%
15,0%
12,3%
10,4%
10,0%
5,8%
5,0%
6,8%
5,3%
1,5%
0,3%
1,1% 0,7%
0,0%
51-60
1,334
1,278
417
109
382
885
20
1,496
1,543
78
51
490
754
3,574
12,412
51-60
18.5%
17.7%
5.8%
1.5%
5.3%
12.3%
0.3%
20.7%
21.4%
1.1%
0.7%
6.8%
10.4%
49.5%
19,4%
20,0%
18,5%
19,0%
16,0%
15,5%
15,0%
10,0%
6,6%
4,4%
5,0%
0,5%
0,0%
Below 25
26 - 30
21 - 35
36 - 40
41 - 45
Age Group
Source: PHCN HR statistics March 2012
10
46 - 50
51 - 55
56 - 60
ENGINEERS WITH
STRUCTURED PUPILAGE
TRAINING
GENERATION
TRANSMISSION
DISTRIBUTION
PHCN HQ
TOTAL
ENGINEERS WITHOUT
STRUCTURED TRAINING
147
157
373
37
714
TOTAL NUMBER OF
ENGIGEERS
217
473
1,262
25
1,976
364
629
1,634
63
2,690
2.500
1.976
2.000
ENGINEERS WITH
STRUCTURED
PUPILAGE
1.500
1.262
1.000
714
473
500
147
217
373
157
37
25
GENERATION
TRANSMISSION
DISTRIBUTION
PHCN HQ
TOTAL
11
ENGINEERS
WITHOUT
STRUCTURED
TRAINING
34% of the total employees will be exiting between now and next 7 years of
which 27% are employees classified under technical profession. This include
Engineers, Technologist, Technicians, Craftsmen and Artisans
73% of the 2,690 engineers and technologists have not received structured
training which impacts on their ability to perform and deliver optimally
14.000
12.311
12.000
10.000
8.000
6.000
4.000
4.922
4.699
29%
2.690
41%
2.000
26%
14%
STAFF HOLDING
51-60 YEARS OLD
ENGINEERS/TEC
HNOLOGIST
2.690
382
12
TECHNICIANS
4.699
1.913
ARTISANS/CRAF
TMEN
4.922
1.278
TOTAL
12.311
3.573
extension of 27 others
297no. Injection Sub-stations
23,000 Distribution Sub-stations (33/0.415KV, 11/0.415KV)
5,000km of 330KV lines
1,600km of 132KV lines
1,700km of 33KV lines
2,700km of 11KV lines
In addition to this, several IPP licenses have been issued by NERC to would-be
GenCos.
These will triple the existing manpower whose skills have to march its OM&A
13
25%
75%
ADDITIONAL TECHNICAL
MANPOWER PLANNING
REQUIRED TO MATCH THE
EXPECTED EXPANSION
THROUGH NIPP PROJECTS IN
GENERATION, TRANSMISSION
& DISTRIBUTION
15
COMPANY NAME
EXPECTED ADDITIONAL
GENERATION EXPANSION
IN 5 YEARS (MW)
MECH.
INSTRUMT CHEMIST
MTNCE
1 AFAM
543
10
2 EGBIN
20
36
90
32
59
17
4 KAINJI
15
25
5 SHIRORO
6 OLORUNSOGO
12
7 OMOTOSHO
150
10
8 UGEHLLI
220
9 SAPELE
370
21
69
15
1,388
104
3 JEBBA
10 GEREGU
COMPANY NAME
EXPECTED ADDITIONAL
GENERATION EXPANSION
FROM NIPP (MW)
NIPP 10Nos.
P/Stations
4,802
6,190
Note:
THERMAL
OPT
PC&M
HYROLOGIST
TOTAL ADDITIONAL
COMMUNICATION MANPOWER REQUIRED
24
10
129
50
10
12
183
22
87
12
12
25
14
12
53
10
10
16
225
65
65
348
55
6
-
65
205
24
2
40
34
48
183
40
22
25
909
ADDITIONAL MANPOWER REQUIRED FOR THE NEW 10Nos. NIPP POWER STAIONS
Operations Crew
Maintenance Crew
Instrumentation &
Control
Workshop
80
180
70
70
TOTAL ADDITIONAL
MANPOWER REQUIRED
400
1,309
19
COMPANY NAME
FITTERS
DSO
LINESMEN
TOTAL FOR
ARTISAN/CRAFT.
ENGINEERS / TECHNOLOGISTS
O&M
P&C
PC&M
1 ABUJA
32
67
108
23
27
21
29
2 BENIN
33
24
557
614
144
119
674
33
3 EKO
71
64
334
468
130
50
50
36
4 ENUGU
18
22
120
159
119
14
19
5 IBADAN
73
84
576
733
121
114
6 IKEJA
45
35
41
121
184
7 JOS
15
13
24
51
188
9 KANO
10
13
10 P/H
13
11 YOLA
8 KADUNA
METERING
ENG./TECH
TOTAL
ENGR./TECH.
TOTAL
ADDITIONAL
MANPOWER
REQUIRED
77
208
826
1,584
135
733
42
321
361
52
527
1,381
80
14
85
187
492
122
11
28
11
50
224
207
47
21
21
21
63
317
35
58
44
11
23
11
45
147
15
150
178
173
13
34
53
404
29
31
60
26
38
47
133
325
342
2,758
1,133
393
1,349
227
2,054
5,944
2,091
COMPANY NAME
ADDITIONAL MANPOWER REQUIRED FOR EXPANSION IN NEXT 5 YEARS INCLUDING NIPP PROJECTS
ARTISAN & CRAFTSMEN
CABLE
JOINTING
FITTERS
LINESMEN
DSO
ENGINEERS / TECHNOLOGISTS
TOTAL FOR
ARTISAN/CRAFT.
P&C
O&M
PC&M
METERING
ENGINEERS/
TECHNICAINS
TOTAL
ENGR./TECH.
TOTAL
ADDITIONAL
MANPOWER
REQUIRED
1 ABUJA
10
36
76
122
25
31
24
32
60
147
294
2 BENIN
10
172
189
44
37
208
10
100
355
588
3 EKO
80
72
376
528
146
56
56
40
120
273
947
4 ENUGU
20
24
135
180
135
16
21
11
100
148
462
5 IBADAN
83
94
650
827
136
129
407
58
130
724
1,687
6 IKEJA
60
53
131
244
33
13
103
18
100
234
511
7 JOS
17
14
27
58
138
12
32
13
80
137
332
8 KADUNA
11
11
212
233
53
24
24
24
90
162
448
9 KANO
18
29
105
152
84
18
40
16
140
214
450
10 P/H
20
23
548
591
259
20
50
10
80
160
1,010
11 YOLA
32
36
120
188
29
43
30
84
301
360
399
2,552
3,311
1,083
361
1,008
237
1,030
2,636
7,030
TOTAL MANPOWER REQUIRED FOR EXPANSION IN AT PRESENT AND IN NEXT 5 YEARS INCLUDING NIPP PROJECTS
ARTISAN & CRAFTSMEN
CABLE
JOINTING
FITTERS
LINESMEN
ENGINEERS / TECHNOLOGISTS
TOTAL FOR
ARTISAN/CRAFT.
DSO
P&C
O&M
PC&M
METERING
ENGINEERS/
TECHNICAINS
TOTAL
TOTAL
ADDITIONAL
ENGR./TECH.
MANPOWER
REQUIRED
1 ABUJA
19
68
143
230
48
58
45
61
60
224
502
2 BENIN
43
31
729
803
188
156
882
43
100
1,181
2,172
150
136
710
996
276
106
106
76
120
408
1,680
4 ENUGU
38
46
255
339
254
30
40
20
100
190
783
5 IBADAN
156
178
1,226
1,560
257
243
768
110
130
1,251
3,068
6 IKEJA
105
88
172
365
217
21
183
32
185
421
1,003
7 JOS
32
27
50
109
260
23
60
24
80
187
556
8 KADUNA
20
20
400
440
100
45
45
45
90
225
765
9 KANO
28
42
140
210
128
29
63
27
140
259
597
10 P/H
33
38
698
769
432
33
84
16
80
213
1,414
11 YOLA
61
67
120
248
55
10
81
10
30
131
434
685
741
4,643
6,069
2,215
754
2,357
464
1,115
4,690
12,974
3 EKO
COMPANY NAME
ADDITIONAL
MANPOWER
REQUIRED TO
SUSTAIN PRESENT
CAPABILITY
909
1,486
5,944
TOTAL
8,339
ADDITIONAL
MANPOWER
REQUIRED DUE TO
INCREASE IN NEXT 5
YEARS (NIPP
PROJECTS)
-
400
1,672
7,030
9,102
TOTAL ADDITIONAL
MANPOWER
REQUIRED
909
400
3,158
12,974
17,441
ABOUT NAPTIN
27
ESTABLISHMENT OF NAPTIN
The Power Sector in Nigeria is currently undergoing a reformation by the
Government of Nigeria due to its inefficiencies and inability to provide the
power need for the country. This problems are largely caused by:
Aging power assets
Huge supply deficit (long period of generation capacity stagnation)
Lack of adequately trained professionals and technically skilled
manpower in generation, transmission and distribution and also in the
areas of management, regulatory and policy framework
With the understanding of training deficiencies and its huge impact on the
power sector and recognizing the need for the massive and urgent training
requirement to put the Sector back on track, THE NATIONAL POWER
TRAINING INSTITUTE OF NIGERIA (NAPTIN) was established on
March 23, 2009, as an institute to required to provide and meet the training
needs of the Nigerian Power Sector and beyond.
NAPTIN commenced operations from a room on the 5th Floor of the PHCN
Plc.
NAPTIN was established as a legal entity on the 1st September, 2009 with
its incorporation as a public company limited by guarantee.
It currently has an ambitious plan of training a minimum of 25,000
personnel within 5 years of its establishment and operations
NAPTIN presently has Eight (8) Regional Training Centers (RTC) across
the country with its HQ office in Abuja
28
Vision
"To be a Lead Centre of Excellence in Providing Training,
Sharing Knowledge, Conducting Research, and Providing
Policy Advisory in Power Utilities Reform in Nigeria through
Developing and Implementing State-of-the-Art Training and
Capacity Building Programs in Partnership with National and
International Stakeholders
Mission
29
OUR VALUES
VALUES
Our core values at NAPTIN are summarized as follows:
Creativity and Innovation
Ethical Behaviour
Accountability
Effective Communication
Education, Research and Knowledge
Recognition of Achievement
Integrity
Commitment
Teamwork
Respect
Professional Behaviour
Environmental Sustainability
Social and Cultural Responsibility
Safety in the Workplace
30
RTC,
KADUNA
RTC,
AKANGBA
RTC,
IJORA
NAPTIN
Main campus
Headquarters Abuja
RTC,
OJI
RTC,
AFAM
RTC,
JOS
RTC,
KANO
31
32
NO. OF CLASS
ROOMS
NO.
TRAINEE
CLASS
OF
TOTAL NO. OF
PER TRAINEE FOR ALL
CLASSES
1.
RTC, Ijora
30
150
2.
RTC, Kainji
30
210
3.
RTC, Akangba
30
90
4.
RTC, Kaduna
25
50
5.
RTC, Jos
25
50
6.
RTC, Afam
25
50
7.
RTC, Oji
25
50
8.
RTC Kano
25
50
9.
Abuja CHQ
25
75
TOTAL
28
775
An additional 6 classrooms and 6 syndicate rooms that can accommodate a total of 240
trainees is expected to be commissioned by the end of the year at our permanent site.
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
A TYPICAL ROOM AT
NAPTIN GUEST HOUSE, KAINJI
49
50
51
52
53
54
55
56
57
58
61
62
NAPTIN COURSES
NAPTINs courses are categorized into:
1. Technical courses
2. Non-technical courses
63
TECHNICAL COURSES
The following are NAPTINs technical courses and training programmes designed for Engineers, Technologist
and Technicians in the Power sector. These courses addresses various training needs in generation Transmission &
Distribution
Basic Power System Protection (P1).
Distance Protection Course (P2)
Generator Protection (P3)
Basic Instrument and Control Course for Engineers & Technicians
SCADA System - SCS
Energy Management System (EMS)
Communication Equipments (SCE)
Cable Jointing Course
Distribution Substation Operation Course
System Operations Course
Senior Electrical Operator Course
Electrical Maintenance Course on Transformer
Electrical Maintenance Course on Switchgear
System Lines Distribution Course
Turbine Maintenance Course
Mechanical Auxiliary Plant Mgt. Course
Steam Turbine Training Course (Pupil Engineers)
Gas Turbine Training Course (Pupil Engineers)
Hydro Turbine Training Course
Thermal Operators Course
Maximum Demand Meter Course
64
Electrical Fitters Course
NON-TECHNICAL COURSES
The following are some of NAPTINs courses for non-technical professionals in the power
sector:
65
66
67
68
RTC, Ijora
2.
RTC, Kainji
3.
RTC, Akangba
4.
RTC, Kaduna
5.
RTC, Jos
6.
RTC, Afam
7.
RTC, Oji
8.
Corporate HQ
9.
Foreign
TOTAL
Total No of Beneficiary
2009
2010
2011
2012
TOTAL
124
549
305
52
1,030
56
320
177
327
880
73
252
339
36
700
63
271
190
60
186
178
53
215
160
53
379
624
54
70
2,226
2,043
490
524
31
246
438
30
30
105
1161
132
581
5,340
69
2009
2010
2011
2012
TOTAL
CABLE JOINTERS
ELECTRICAL FITTERS
LINESMEN
ELECTRICAL OPERATORS
ENGINEERS AND
TECHNOLOGIST
MARKETERS
NON-TECHNICAL
48
NIL
145
107
117
265
88
472
263
625
118
NILL
159
370
794
51
NIL
58
26
446
482
88
834
766
1,982
NIL
73
133
380
389
213
NIL
NIL
522
666
TOTAL
490
581
5,340
2,226 2,043
70
NGSDP PROGRAMME
71
NGSDP PROGRAMME
243 trainees but individual and State Government sponsored were admitted
for the programme in 2012, when it commenced.
175 of these trainees are Electrical Engineers who are have been given
practical hands-on training in various aspects of Distribution and
Transmission for the past one year.
46 of these Electrical Engineers have been engaged by Transmission
Company of Nigeria (TCN) in their recent recruitment and are being
deployed to start work immediately due to the technical know-how already
acquired during the NGSDP one year programme. This has saved TCN a
huge cost both in time and money that would have been spent on training
these engineers to get them ready.
TCN through the FGN has requested others who are also recruited but have
not undergone the one year NGSDP programme to be trained first by
NAPTIN before being deployed
It is envisage that the next batch of the NGSDP programme which will
commence in October 2013 will have over 800 in-take of trainees across
the country
THE FUTURE
NAPTINs ONGOING
IMPLEMENTATION PLANS
75
76
4)
5)
6)
5)
Conclusion
NAPTIN is rebranding training in the power
sector to meet international standards.
NAPTIN requires cooperation from all sector
institutions
and
stakeholders
to
ensure
institutionalization and sustainability.
As joint stakeholders in the development of the
Power Sector, NAPTIN should be first stop for any
person seeking power sector training in Nigeria.
NAPTIN awaits suggestion from stakeholders on
areas of training needs desired
79
Contact details
Website:
Portal:
info@naptin.org.ng
www.naptin.org.ng
www.naptinportal.com
80