2014 Construction Meeting #18
Distribution/Attendance:
City of Ithaca
Downtown Ithaca Alliance
Sasaki Associates
Labella Associates
Vacri Construction / ACP /
Next Time
10:00 AM
Prepared By
Nicole Mason
Location
Commons Project Office 215 East State St Ithaca, NY
(Present at meeting unless noted: A absent)
Michael Kuo, Jessica Buckley, Nicole Mason
Tammy Baker
Susannah Ross, Eamonn Hutton (A), Kimberly Michaels TWM
Dan Walker, James Matzat (A)
Ralph Avery (A), Andy Breznay, Matt Thomas (A), Roberto DeVincentis,
Bob Bellavigna ACP
Mike Lamonica Syrstone
Lou Zupan, Bill Planert, Brian Planert (A)
James Edwards (A), Dave Comer (A)
Doug Stafford (A), Jack Barker (A), Dawn Stillwell, John Mattiace
Jeff Bubb (A), Flint Brann (A), Andy Gana
Jack Czapranski (A), Dennis Kuhn (A)
Item / Description
1. RFIs, SUBMITTALS
1.1. Vacri (Contract #3A):
1.1.1.Granite Coordination
1.1.2.Roadway Curb sample photos to
be sent to Sasaki
Notes
1.1.1. PCG has location of stub ups for EX6
lights from Sasaki. PCG asked for the
elevation of the lights in the granite;
Sasaki responded they have supplied that
information in previous Bulletin and RFI
responses. A sample light box has been
rushed to PCG for additional
dimensioning. ACP not sure a three inch
core can be done. PCG- Only inch
conduit needs to go in, so it doesnt need
to be 3-inch but wants it as large as
possible to account for error. PCG will
coordinate with ACP on exact
dimensioning.
PCG planning to run conduit in the slab,
hanging the conduit on the rebar. Will
coordinate with ACP in field.
Submittal 87 - Vacri has proposal from
APC regarding a cast addition due to the
Page 1 of 4
Due
Page 2 of 4
Page 3 of 4
tomorrow (7/23).
DS concerned about grading on Tioga
the one inch line off of the drip is sticking
out of the ground where they have
regraded.
171 E State St (Center Ithaca) decision
needs to be made about connecting low
or medium pressure service. DDS may
need to give them low pressure now and
then come back in a few years to retire it.
Medium pressure decision may take up to
two years so they cant wait on that
decision.
NYSEG will discuss with DDS if working on
Saturdays is an option.
Already reinstalled
ADDITIONAL NOTES
Concern about paint finish color possible discrepancy between snakehead boxes and utility
panels. Sasaki will send color sample of what they approved.