The following provides examples of the components in a 30%, 50%, 90%, and 100% Design

Documents.

30% Basis of Design Components


Introduction

Purpose/intent of document
Report organization
Provide project organization structure /roles and responsibilities
General site history
Need to outline other components of overall remediation that will be submitted separately
If submitting more than one design process in same document, provide explanation and
ensure adequate separation
Discuss design process
o 30% Design Components
o 50% Design Components
o 90% Design Components
o 100% Design Components

Summary of ROD

Describe remedies outlined in the Record of Decision (ROD)

Basis of Design

Outline work to be undertaken


Identify permitting and regulatory requirements
Summary of previous investigations and results. Examples include but not limited to:
o Soil contamination and soil vapor data
o Groundwater data
o Vapor intrusion data and sub-slab vapor monitoring results
o Previous history of SVE system operations
o Previous pilot testing monitoring results
Design Considerations
o Provide detailed existing conditions mapping (structures, utilities, systems, etc.)
o Property ownership
o Outline subsurface conditions
o Outline surface conditions
o Analyses of data and identification of data gaps
o Discuss future pilot testing and/or other treatments and their impacts to design
considerations
o Discussion of design assumptions

Discuss media/areas to be remediated


Outline COCs for each media
Outline cleanup standards/objectives/performance criteria
Estimate extent of system/describe target
Outline design approach
Describe evaluation of treatment methods

Additional Investigation

Additional data collection to fill data gaps, if needed

50% Basis of Design Components

Investigation results results and analyses of data


Pilot test work plan describe the pilot test methods and procedure for data collection
Pilot test well construction details (e.g. well locations, pilot test equipment details)
Describe all required treatment during pilot testing (e.g. off gasses, waste water)
Discuss all required permitting requirements.
Describe how data from pilot test will be used to finalize system design
Preliminary system layout
Preliminary system construction details
Describe calculations to be used for system design
List construction specification to be provided in the 90% design
Preliminary O&M and performance monitoring plan
Preliminary cost estimates
Preliminary schedule

90% Basis of Design Components

Present pilot test results and analyses of data


Describe how data from pilot test will be used to finalize system design
Present final system calculations for system design
Final system construction drawings
Final system plans and specifications
Provide permits or permit applications
Final O&M and performance monitoring plan
Final cost estimates
Final schedule

100% Basis of Design Components


(will be submitted in Construction Completion Report with As-Builts, if minor comments)

Incorporate comments from 90% Design submittal