You are on page 1of 23

DESIGN OF HYDRAULIC STRUCTURES

PEDRO RUIZ GALLO NATIONAL UNIVERSITY


FACULTY OF CIVIL, SYSTEMS ENGINEERING AND
ARCHITECTURE
COLLEGE OF CIVIL ENGINEERING

DESIGN OF HYDRAULIC STRUCTURES

RESERVOIR OUTLET WORKS


INSTRUCTOR: Msc. Ing. Jos Arbul Ramos
STUDENTS:
Santa Mara Carlos, Mariano
Pea Chaquila, Danner

December 2nd, 2014


FICSA - UNPRG
1

DESIGN OF HYDRAULIC STRUCTURES

RESERVOIR OUTLET WORKS


I. INTRODUCTION
Water from the reservoir of a dam is released through two principal types of structures:
1. Spillways, which are provided for storage and detention dams to release surplus water or
floodwater that cannot be contained in the allotted storage space.

Spillways
2. Outlet works, which regulate or release water impounded by a dam. It can release incoming
flows at a retarded rate, as does a detention dam; it can divert incoming flows into canals or
pipelines; or it can release stored waters at rates dictated by downstream needs, by
evacuation considerations, or by a combination of multiple-purpose requirements.

Outlet works

FICSA - UNPRG
2

DESIGN OF HYDRAULIC STRUCTURES


II. STORAGE DAM INTAKE WORKS
Outlet works are so named because they release out water from the reservoir. Some of these
are equipped with an Intake Structure if the water is fed into a canal or a conduit for serving
some specific purpose like meeting irrigation water requirement or hydropower generation,
etc.
Occasionally, the outlet works may be placed at a level high enough to deliver water to a
canal, while a bypass is extended to the river to furnish necessary flows below the dam. Such
bypass flows may be required to satisfy prior-right uses downstream or to maintain a live
stream for preservation of aquatic life, or other purposes. Dams constructed to provide
reservoirs principally and also for recreation or for raising fish and wildlife conservation
require a fairly constant reservoir level. For such dams an outlet works may be needed only to
release the minimum flows necessary to maintain a live stream below the dam. In certain
cases, the outlet works of a dam may be used in lieu of a service spillway combined with an
auxiliary or secondary spillway. In such a case, the usual outlet works installation might be
modified to include a bypass overflow so that the structure can serve as both an outlet works
and a spillway.
An outlet work may act as a flood control regulator to release waters temporarily stored in
flood control storage space or to deplete the storage of a reservoir in anticipation of flood
inflows. Furthermore, the outlets may be used to empty the reservoir to permit inspection, to
allow needed repairs, or to maintain the upstream face of the dam or other structures
normally inundated. The outlets may also aid in lowering the reservoir storage when
controlling objectionable aquatic life in the reservoir is desired.

FICSA - UNPRG
3

DESIGN OF HYDRAULIC STRUCTURES


Outlet works under embankment dam

III. GOALS
The outlet works their main goal is to making controlled release of reservoir water impounded
behind the dam. The outlet works consists of an intake structure that has valves openings at
various heights that allows reservoir water to flow into the structure at a selected flow rate.
Water then flows down the intake tower down to an outlet conduit and through the bottom
of the dam back into a river or channel.

Intake Works

FICSA - UNPRG
4

DESIGN OF HYDRAULIC STRUCTURES


Outlet works

IV. FUNCTIONS OF OUTLET WORKS


The type and design of the outlet works facility will be greatly influenced by the project, its
purposes, and structure-specific functions. An evaluation of each function is absolutely
necessary in any design of the structure selected.
a. Flood control. Outlet works for flood-control projects generally require designs having large
flow capacities and less regulation capabilities. Typically, the outlets are gated for flow
regulation. However, the conduits may be uncontrolled (no gates) for reservoirs that are low
or empty during non-flood periods.
b. Irrigation. Gates and valves for irrigation require close regulation and lower discharge
ranges than flood-control outlet controls. Releases may be discharged into a channel or
conduit rather than into the original riverbed.
c. Water supply. Municipal water supply intakes are generally a secondary project function.
Reliability and water quality are of prime importance in the design. Water intakes are located
and controlled to ensure that the water is free of silt and algae, to obtain desired
temperatures, and to allow intake cleaning.
d. Power. Power penstocks within intake structures should be located so as not to cause any
undesirable entrance flow conditions such as eddies that might jeopardize turbine operation.
Power intakes may require smaller trashrack openings to limit the size of debris that enters
the penstock.
e. Sediment. Projects designed for sediment retention should be designed to pass flows as
the sediment level rises in the reservoir and to prevent sediment from passing through and
damaging or blocking both the entrance and the outlet works itself. Smaller releases are
controlled by multilevel intakes that are closed by gating or stoplogs as the sediment level
rises in the reservoir. For projects with flood flows that are released through the outlet works,
a high-level intake that provides protection against large sediment buildup may be necessary.

V. COMPONENTS OF OUTLET WORKS


For an open-channel outlet works or for a conduit-type outlet where partial full flow prevails, the
control gates or valves should determine the outlet works capacity. Where an outlet works
operates as a pressure pipe, the size of the waterway and that of the control device should
determine the capacity. The overall size of an outlet works is determined by its hydraulic head and
the required discharge. The selection of the size of some of the component parts of the structure,
such as the tunnel, is dictated by practical considerations or by interrelated requirements such as
diversion, reservoir evacuation, and initial filling.
When the type of waterway has been chosen and the method of control established, the
associated structures to complete the layout can be selected. The type of intake structure depends

FICSA - UNPRG
5

DESIGN OF HYDRAULIC STRUCTURES


on its location and function and on the various appurtenances, such as fish-screens, trash racks,
stop log arrangements, or operating platforms that must be furnished. A means for dissipating the
energy of flow before returning the discharge to the river should normally be provided. This can
be accomplished by a flip bucket, a stilling basin, a baffled apron drop, a stilling well, or a similar
dissipation device. Gate chambers, control platforms, or enclosures may be required to provide
operating space and protective housing for the control devices. An outlet works may also require
an outlet channel to return releases to the river and an entrance channel to lead diversion flows or
low-reservoir flows to the intake structure.
Tunnels
Because of its inherent advantages, a tunnel outlet works is preferred where abutment and
foundation conditions permit its use and it is more economical than the other types of outlet
works. A tunnel is not in direct contact with the dam embankment and, therefore, provides a
much safer and more durable layout than can be achieved with a cut-and-cover conduit. Little
foundation settlement, differential movement, and structural displacement is experienced with a
tunnel that has been bored through competent abutment material, and seepage along the outer
surfaces of the tunnel lining or leakage into the material surrounding the tunnel is less serious.
Furthermore, it is less likely that failure of some portion of a tunnel would cause failure of the dam
than the failure of a cut-and-cover conduit that passes under or through the dam.
Cut-and-Cover Conduits
If a closed conduit is to be provided and foundation conditions are not suitable for a tunnel, or if
the required size of the waterway is too small to justify the minimum sized tunnel, a cut-and-cover
conduit should be used. Because this type of conduit passes through or under the dam,
conservative and safe designs must be used. Numerous failures of earthfill dams caused by
improperly designed or constructed cut-and-cover outlet conduits have demonstrated the need
for conservative procedures.
Control Devices
Selection of the outlet works arrangement should be based on the use of commercially available
gates and valves or relatively simple gate designs where possible. The use of special devices that
involve expensive design and fabrication costs should be avoided. Cast iron slide gates, which may
be used for control and guard gates, are available for both rectangular and circular openings and
for design heads up to about 15 metre. However, higher head installations require special gate
designs. Simple radial gates are available for ordinary surface installations, and top-seal radial
gates can be secured from manufacturers on the basis of simple designs and specifications. For
low heads up to about 15 metre, commercial gate and butterfly valves are suitable for control at
the downstream end of pressure pipes if they are designed to operate under free discharge
conditions with the jet well aerated all around. Gate and butterfly valves are also suitable for use
as inline guard valves and can be adapted for inline control valves if air venting and adequate
aeration of the discharge jet are provided immediately downstream from the valve.
The control gate for an outlet works may be placed at the upstream end of the conduit, at an
intermediate point along its length, or at the lower end of the structure. Where flow from a
control gate is released directly into the open as free discharge, only that portion of the conduit

FICSA - UNPRG
6

DESIGN OF HYDRAULIC STRUCTURES


upstream from the gate is under pressure. Where a control gate or valve is placed at the lower end
of the structure, full internal pressure should be considered in the design of the conduit tunnel or
pipe. However, when a control discharges into a free-flow conduit, the location of the control gate
becomes important in the design of the outlet. Upstream gate controls for conduits are generally
placed in a tower structure with the gate hoists mounted on the operating deck (Figure 2). With
this arrangement, the tower must extend above the maximum water surface. If controls are to be
located at some intermediate point along the conduit, high-pressure gates, slide gates, and topseal radial gates may be used. These controls may be located in a wet-well shaft that extends
vertically from the conduit level to the crest of the dam. Typical arrangements of these
installations are shown in Figures 1 to 4.

FICSA - UNPRG
7

DESIGN OF HYDRAULIC STRUCTURES

FICSA - UNPRG
8

DESIGN OF HYDRAULIC STRUCTURES

Intake Structures
In addition to forming the entrance to the outlet works, an intake structure may accommodate
control devices. It also supports necessary auxiliary appurtenances (such as trashracks,
fishscreens, and bypass devices), and it may include temporary diversion openings and provisions
for installation of bulkhead or stoplog closure devices. Intake structures may appear in many
forms. The type of intake structure selected should be based on several factors: the functions it
must serve, the range in reservoir head under which it must operate, the discharge it must handle,
the frequency of reservoir drawdown, the trash conditions in the reservoir (which will determine
the need for or the frequency of cleaning of the trashracks), reservoir wave action that could
affect the stability, and other similar considerations. Depending on its function, an intake structure
may be either submerged or extended in the form of a tower above the maximum reservoir water
surface. A tower must be provided if the controls are placed at the intake, or if an operating
platform is needed for trash removal, maintaining and cleaning fish-screens. Where the structure
serves only as an entrance to the outlet conduit and where trash cleaning is ordinarily not
required, a submerged structure may be adopted.
The necessity for trashracks on an outlet works depends on the size of the sluice or conduit, the
type of control device used, the nature of the trash burden in the reservoir, the use of the water,
the need for excluding small trash from the outflow, and other factors. These factors determine
the type of trashracks and the size of the openings. Where an outlet consists of a small conduit
with valve controls, closely spaced trash bars are needed to exclude small trash. Where an outlet
involves a large conduit with large slide-gate controls, the racks can be more widely spaced. If
there is no danger of clogging or damage from small trash, a trashrack may consist simply of struts
and beams placed to exclude only larger trees and similarly sized floating debris. The rack
arrangement should also be based on the accessibility for removing accumulated trash. Thus, a
submerged rack that seldom will be dewatered must be more substantial than one at or near the
surface. Similarly, an outlet with controls at the entrance, where the gates can be jammed by trash
protruding through the rack bars, must have a more substantial rack arrangement than one whose
controls are not at the entrance.

FICSA - UNPRG
9

DESIGN OF HYDRAULIC STRUCTURES


Energy Dissipating Arrangements
The discharge from an outlet, whether of a gate valve, or free flow conduit, will emerge at a high
velocity, usually in a nearly horizontal direction. If erosion-resistant bedrock exists at shallow
depths, the flow may be discharged directly into the river. Otherwise, it should be directed away
from the toe of the dam by a deflector. Where erosion is to be minimized, a plunge basin may be
excavated and lined with riprap or concrete. When more energy dissipation is required for free
flow conduits, the terminal structures described for spillways may be used. The hydraulic-jump
basin is most often used for energy dissipation of outlet works discharges. However, flow that
emerges from the outlet in the form of a free jet, as is the case for valve-controlled outlets of
pressure conduits, must be directed onto the transition floor approaching the basin so it will
become uniformly distributed before entering the basin. Otherwise, proper energy dissipation will
not be obtained.
Entrance and Outlet Channels
An entrance channel and an outlet channel are often required for a tunnel or cut-and-cover
conduit layout. An entrance channel may be required to convey diversion flows to a conduit in an
abutment or to deliver water to the outlet works intake during low reservoir stage. And an outlet
channel may be required to convey discharges from the end of the outlet works to the river
downstream or to a canal.

FICSA - UNPRG
10

DESIGN OF HYDRAULIC STRUCTURES


VI. INLET STRUCTURES
The inlet structures intake works to consist mainly of trashracks a combination of trashracks
and control gates.
Depending on the particular design at each dam, the intake works must correspond to the
foundation conditions, required discharge operating loads, variations in reservoir water levels
and amount of floating solids that can catch the outlet.

VII. INTAKE IN CONCRETE OR MASONRY DAMS


In the case of concrete dams, irrigation intake structure can be located either at the toe when
operating head is low or in the body of the dam itself when operating head is medium or high.
Typical section of such an intake is shown in Figure 11.

VIII. INTAKE IN EARTHEN DAMS


When the reservoir is formed by an earthen dam, the irrigation tunnel is laid below it or in the
abutment. The intake structure for such situations will be a sloping intake or tower type of
intake. Typical layouts for sloping and tower type intakes are shown in Figure 12 and 13
respectively. As far as possible, reinforced cement concrete pressurized system should be
avoided in the body of the earth dam. Measures like provision of steel liners and suitable

FICSA - UNPRG
11

DESIGN OF HYDRAULIC STRUCTURES


drainage downstream of core, provisions of joints for differential settlements when not
founded on rock should be considered in case pressure conduits are provided under earth
dams.

FICSA - UNPRG
12

DESIGN OF HYDRAULIC STRUCTURES

Intake In Earthen Dams


IX. TRASH RACKS FOR INTAKES
Trashracks are needed to prevent clogging and debris damage to outlet control gates and turbines.
The trashrack type and size of openings depend on the pool elevation, intake elevation, the size of
the outlet conduit, the reservoir trash conditions, type of control device used, use of the water,
and the need to exclude the trash.
a. Intakes for flow regulation. A simple trash structure, usually of reinforced concrete, with clear
horizontal and vertical openings not more than two-thirds the gate width should be provided at
the upstream end of the outlet works to catch trees and other large trash which may reach the
entrance and be capable of blocking the gated passages. Large trash at the tunnel entrance occurs
more often when the permanent pool is only slightly above the entrance than when the
permanent pool is high above the entrance. Only in special cases in which trees and floating
debris are absent from the reservoir and watershed should the trash structure be omitted.
(1) Metal trashracks fabricated of closely spaced bars are generally used for small conduits with
control valves and water supply intakes that require screening of small debris.
(2) To facilitate trash removal immediately after a flood, the working platform at the top for
raking and removal of trash usually should not be lower than the top elevation of the conservation
or maximum power pool. The usual trash structure consists of upright beams, inclined slightly
downstream from the vertical to facilitate raking, and horizontal beams.
(3) If the gate structure is located at the upstream end of the outlet tunnel, the trash structure is
combined with it for economy.
(4) The area of the openings in the trash structure should limit the local net-area velocity to less
than 10 to 15 ft/sec.
b. Floating trash and debris control facilities. Floating trash and debris control can be provided by
a basic trash boom constructed of logs or floating pontoons. Trashracks would still be necessary

FICSA - UNPRG
13

DESIGN OF HYDRAULIC STRUCTURES


to protect intakes from occasional water-logged trees or large logs that pass under the trash
boom.

FICSA - UNPRG
14

DESIGN OF HYDRAULIC STRUCTURES

X. GATES
1. Vertical gate
Similar to that used for crest type gates (Figure 1), but usually for deep-seated purposes like
controlling flow to hydropower intake either the ones with roller wheels (Figure 13), or the sliding
- type without any wheels (Figure 14), are used.

2. Sliding gates
Slide gates, as the name implies, are the gates in which the operating member (that is, gate leaf)
slides on the sealing surfaces provided on the frame. In most cases, the sealing surfaces are also
the load-bearing surface. Slide gates may be with or without top seal depending whether these
are used in a close conduit or as crest gate. A typical installation of a slide gate is shown in Figure

FICSA - UNPRG
15

DESIGN OF HYDRAULIC STRUCTURES


14. These consist of a gate leaf and embedded parts. These embedded parts serve the following
purposes:
a) Transmit water load on the gate leaf to the supporting concrete (structure),
b) Guide the gate leaf during operation, and
c) Provide sealing surface.
According to the Bureau of Indian Standards code IS: 5620 Recommendations for structural
design criteria for low head slide gates, slide gates may be classified into the following three
types depending upon their service conditions.

(i). Bulk head or stop-logs


These are usually located at the upstream end of river outlet conduits or penstocks where in
addition some other equipment is used to cut off flow and are subjected to relatively high heads.

(ii). Emergency or guard gates


These are designed to be operated under unbalanced head, that is, with water flowing through
the conduit or sluice but are not meant for regulation. These are kept either fully opened or fully
closed and are not operated at part gate opening.

(iii). Regulating gates


These are used for regulating flow of water. These are also operated under unbalanced head
condition and are designed to be operated at any gate opening.

FICSA - UNPRG
16

DESIGN OF HYDRAULIC STRUCTURES

3. Deep-seated radial gates


These are low level radial outlet gates. These gates have sealing on top apart from on all sides.
They are located at sluices in the bottom portion of dam (Figure 15). The hoisting arrangement is
usually at the top but could also be provided near the elevation of top seal to reduce hoist stroke.

FICSA - UNPRG
17

DESIGN OF HYDRAULIC STRUCTURES

XI. HEAD LOSSES


Pressure Flow in Outlet Conduits
If a control gate is placed downstream from the conduit entrance, that portion above the control
gate will flow under pressure. An ungated conduit can also flow full depending on the inlet
geometry. The phenomena and the hydraulic equations for flow through an ungated conduit
under pressure. The hydraulic design of a gated pressure conduit should be similar to that for an
ungated pressure conduit.
For flow in a closed pipe system, as shown on figure 10-11, Bernoullis equation can be written as
follows:

Where:
= Total head needed to overcome the various head losses to produce discharge,
= Cumulative losses of the system, and
= Velocity head at the valve.
Equation (3) can be expanded to list each loss as follows:

FICSA - UNPRG
18

DESIGN OF HYDRAULIC STRUCTURES

Where:
= Trashrack losses,
= Entrance losses,
= Bend losses,
= Friction losses,
= Expansion losses,
= Contraction losses,
= Gate or valve losses, and
= Velocity head exit loss at the outlet.
In equation (4), the number subscripts refer to the various components, transitions, and reaches
to which head losses apply.
For a free-discharging outlet,
is measured from the reservoir water surface to the center of the
outlet gate or the outlet opening. If the outflowing jet is supported on a downstream floor, the
head is measured to the top of the emerging jet at the point of greatest contraction; if the outlet
portal is submerged, the head is measured to the tailwater level.
Where the various losses are related to the individual components, equation (4) may be written:
(

(
(
(

(
)

)
(

(
(

)
)

Where:
= trashrack loss coefficient,
= entrance loss coefficient,
= bend loss coefficient,
= friction factor in the Darcy-Weisbach equation for pipe flow.
= expansion loss coefficient,
= contraction loss coefficient,
= gate loss coefficient, and
= exit velocity head coefficient at the outlet.
Equation (5) can be simplified by expressing the individual losses in terms of an arbitrarily chosen
velocity head. The velocity head chosen is usually that in a significant section of the system. If the
various velocity heads for the system shown on figure 10-11 are related to that in the downstream
conduit, area (1), the conversion for x area is found as follows:
Since:

FICSA - UNPRG
19

DESIGN OF HYDRAULIC STRUCTURES

Then:
(

Equation (5) can then be written:


*(

(
(

) (

) (

)
)

If the bracketed part of the expression is represented by

) (

)
)

) (

)+

, the equation can be written:

Then:

FICSA - UNPRG
20

DESIGN OF HYDRAULIC STRUCTURES

XII. POSITION (ELEVATION) OF OUTLET WORKS IN RELATION TO RESERVOIR STORAGE


LEVELS.
The establishment of the intake level and the elevations of the outlet controls and the conveyance
passageway, as they relate to the reservoir storage levels, are influenced by many factors.
Primarily, to attain the required discharge capacity, the outlet must be placed sufficiently below
the minimum reservoir operating level to provide the head required for outlet works flows.
Outlet works for small detention dams are generally constructed near riverbed level because
permanent storage space, except for silt retention, is ordinarily not provided. (These outlet works
may be ungated to retard the outflow while the reservoir temporarily stores the bulk of the flood
runoff, or they may be gated to regulate the releases of the temporarily stored waters.) If the
purpose of the dam is only to raise the reservoir and divert incoming flows at low heads, the main
outlet works generally should be a headworks or regulating structure at a high level. A sluiceway
or small bypass outlet should also be provided to furnish water to the river downstream or to
drain the water from behind the dam during off-season periods. Dams that impound water for
irrigation, for domestic use, or for other conservation purposes, must have outlet works low
enough to draw the reservoir down to the bottom of the allocated storage space; however, the
outlet works may be placed above the riverbed, depending on the established minimum reservoir

FICSA - UNPRG
21

DESIGN OF HYDRAULIC STRUCTURES


storage level. It is common practice to make an allowance in a storage reservoir for inactive
storage to accommodate sediment deposition, for fish and wildlife conservation, and for
recreation. The positioning of the intake sill then becomes an important consideration; it must be
high enough to prevent interference from the sediment deposits, but at the same time, low
enough to permit either a partial or a complete drawdown below the top of the inactive storage.
The size of an outlet conduit for a required discharge varies according to an inverse relationship
with the available head for producing the discharge. This relationship may be expressed by the
following equation:

Where:

The above relationship for a particular design is shown on figure 10-8(A). This example shows that
if the head available for the required outlet Works discharge is increased from 1.6 to 4.6 feet, the
corresponding conduit diameter can be decreased from 6 to 4.75 feet. This shows that the conduit
size can be reduced significantly if the inactive storage level can be increased. The reduction in
active storage capacity resulting from a 3-foot increase in the inactive storage level must be
compensated for by the addition of an equivalent capacity to the top of the pool.

The reservoir capacity curve on figure 10-8(B) shows that for equivalent storages (represented by
de and gh), the 3 feet of head (represented by cd) added to obtain a reduced outlet works size
would require a much smaller increase (represented by fg) in the height of the dam. Thus,

FICSA - UNPRG
22

DESIGN OF HYDRAULIC STRUCTURES


economic studies can be used to determine the proper outlet size in relation to the minimum
reservoir storage level.

Where an outlet is placed at riverbed level to accommodate the construction diversion plan or to
drain the reservoir, the operating sill may be placed at a higher level to provide a sediment and
debris basin and other desired inactive storage space, or the intake may be designed to permit
raising the sill as sediment accumulates. During construction, a temporary diversion opening may
be formed in the base of the intake to handle diversin flows. Later, this opening may be plugged.
For emptying the reservoir, a bypass around the intake may be installed at riverbed level. This
bypass may either empty into the lower portion of the conduit or pass under it. Water can be
delivered to a canal at a higher level by a pressure riser pipe connecting the conduit to the canal.

FICSA - UNPRG
23

You might also like