Professional Documents
Culture Documents
INTRODUCTION
1.1 Introduction
2
It is still in the early stage where the acceptance level from other suppliers,
developers, contractors and end users are still ambiguous. The objective of this
research is to identify the pros and cons of using steel formwork panel and its
suitability to Malaysias construction industries; as well as to identify the acceptance
level of different parties against this technology.
1.2
Problem Statement
The beneficial of this method need to be identified. However, little has been
done to explore the real situation, concern and awareness between suppliers,
developers, contractors and end user in the local construction industry through the
work they had completed construct.
The common goal of a project is to get profit in the shorten period of time,
getting the easier way to implement the project and doing the works within the
3
budgets or less budget. However, developer and contractors often do not pay
attention on what are the end user needs. The reason on using this new technology
normally is more emphasize in gaining profit instead of obtain the opinion from end
user.
1.3
The aim of the study is to investigate the current state of EFCO E-Form RC
shear wall implementation. The aim is supported by the following objectives.
To study the construction process of the EFCO E-form RC shear wall design.
To identify the strategy used by supplier to introduce EFCO hand e-form to the
contractor.
1.4
Study in research
Select construction
method to be use.
and questionnaire.
Collect data
Prepare presentation.
Analyze data
5
of the method. The final part is identified the awareness of the end user about the
method.
The samples in this study basically included the resident from Melaka and
Johor state for those were intent to buy or had bought the house property. Using
SPSS 12 software system is used to presenting the final result in statistical analysis.
(Neil Frude, 1987)
CHAPTER II
RESEARCH METHODOLOGY
2.1
The objectives of this project report were realized using sequence of method
indicated in figure 2.1. Initially, the problem statement of the project is identified.
Secondly, aims and the objectives of the project are defined for future
accomplishment. Next, the literature review in gathered information about research
topic and challenges faced by the construction industry. The subsided sequence is
defined the data collection method. Interview and questionnaire survey was
conducted to obtain feedback from the construction industry and end user. The next
step is analysis the collected data by using software. It follows by some discussions
and suggestions and eventually conclusion being drawn to conclude this study.
The below are six essential steps in conducting this study as briefly list:
2.1.1
7
2.1.2
2.1.3
Literature Review
o To study from Library, Wed Site, Journal and the needs of the research
topic.
o Empirical study such as Interview, getting feedback from end user.
2.1.4
2.1.5
Data Analysis
o To identify the facts, compare the results with objective.
2.1.6
Figure 2.1 shown in next chapters illustrate the six essential steps in a proper and
simple sequential order.
Begin
Literature Review
Data Analysis
End
9
2.2
Interview
2.2.1
Structured interview
10
2.2.2
Semistructured interview
2.2.3
The unstructured or nondirective interview is even less structured than the life
storey interview and the focused interview. The chief feature of the nondirective
interview is its almost total reliance upon neutral probes that are designed to be as
neutral as possible. They are generally very short, such as why? or uh, huh or
thats interesting. The nondirective interview originated in psychotherapy. It is
intended to probe the respondents deepest and more subjective feeling.
2.2.4
11
2.3
Questionnaire
Once the concepts and hypotheses have been carefully formulated and a good
sample drawn, the next line in the research chain is the data collection instrument.
The questionnaire is generally mailed or handed to the respondent and filled by him
or her with no help from the interviewer. An instrument that is not given directly to
the respondent but is filled in by an interviewer who reads the questions to the
respondent is generally called an interview schedule. We shall use the term
questionnaire as the generic name for both types.
A questionnaire survey was carried out to gather information from end users
who are involved in the purchase house property. The target population consisted of
those residents in Melaka and Johor area where the EFCO E-Form RC shear wall
constructed.
2.3.1
Questionnaire Structure
12
2. Section B (Information about the respondents preference)
The sample of questionnaire used for the survey in this project is shown in
Appendix A. The data collected from the questionnaire survey was analyzed
using frequency analysis and interactive analysis by SPSS 12 analysis software.
2.4
Limitation of Study
13
CHAPTER III
LITERATURE REVIEW
14
The construction industry is very labour intensive although it is very
competitive. It results in a very low productivity as compared with other sectors. The
ineffectiveness and low productivity are caused by failure of the industry to utilise
the new as well as other relevant labour reducing technologies. It is due to the
following factors:
High prices of the systems caused by high set-up costs, low demand
and designs originally meant for in situ constructions.
15
oriented, faster as well as quality controlled. It generally involves prefabricated
products factory manufactured elements that are transported to the construction
sites and erected. While this are various definitions of IBS based on the structural
aspects of the systems, it can be divided into five common types. (See table 3.1)
Type 2
Steel Formwork Systems
Considered as one of the low-level or the least prefabricated IBS as the systems
generally involve site casting, thus, the question of structural quality control arises.
Nevertheless, these systems tunnel forms, till-up systems, beams and columns
moulding forms and permanent steel formworks (metal decks) do offer high quality
finishes, and fast construction with less site labour and material requirement.
Type 3
Steel Framing Systems
Commonly used with Precast concrete slabs, steel columns and beams have always
been the popular choice and used extensively in the fast-track construction of
skyscrapers. Recent development in this type of IBS includes the increased usage of
light steel trusses, which consist of cost-effectively profiled cold-formed channels,
and steel portal frame systems as an alternative for the heavier traditional hot-rolled
16
sections.
Type 4
Timber Frame Systems
Among the products listed in this category are the timber building frames and timber
roof trusses. While timber roof truss systems are popular, timber building frame
systems also have its own niche market, offering interesting designs from simple
dwelling units to buildings requiring high aesthetical values such as chalets for
resorts.
Type 5
Block work Systems
The construction method of using the conventional bricks has been revolutionised by
the development and usage of interlocking concrete masonry units (CMU) and
lightweight concrete blocks. The tedious and time-consuming traditional brick-laying
task is greatly simplified by the usage of these effective alternatives.
High quality finished products and minimal wastage due to factorycontrolled prefabrication environment.
17
Faster completion due to the introduction of components replacing in
situ construction.
18
Faster completion of construction projects due to the usage of
standardised pre-fabricated components and simplified installation
processes.
According to the table 1, the EFCO hand e-form panel is categorised as a new
technology method in Industrialised Building System (IBS). Where this system is
grouped as steel formwork systems includes tunnel forms, tilt up systems, beams and
columns moulding forms or permanent steel formworks.
Normally people will ask why using hand e form besides there still have
others type of steel formwork can be used to accomplish the work. The answer is the
hand e-form is a small panel that can be carrying by worker without using crane
handling. It is easy to handle and the work type is similar with the conventional type
but only the RC wall is took over the brick wall system.
19
The introduction of hand e-form in the construction industry have encouraged
the contractor used panel RC wall as a grid wall for the residential housing project
such as single storey terrace house, double storey terrace house and also in shop
houses. Its emerge have changed the conventional work which previously using
timber and plywood as a form work and brick wall type to the new steel formwork to
form RC panel by eliminate the beam and column framework.
By used hand e- form, the structure of the building is reduced from brick wall
to the RC wall design. It is not a fully RC wall design method where the developers
liked to use 80 % of RC design and remain 20 % brick wall design in order to
satisfied customer renovation habits.
3.2.1
3.2.1.1 Introduction
New construction method not only helps to save our forests, but also save
labour, material, time, interest, capital for construction. It also helps improve the
quality of the house and most important, improve company profit.
The formwork need to be design in order to get full used and fabricated
effectively not only for the company profit but also to convenient workers when they
are carry out the job. There are some criteria need to be considered before design the
EFCO E-form. (Vivian Ho, 2004)
How? First, designers must know about formwork characteristics, and should
think about the formwork first, then, follow the design of the structure. Architects
20
and engineers may reduce formwork cost by designing repeated structures, so that
standard formwork materials and shapes can be reused to the maximum extend.
Architects and engineers need to know the type and shape of formwork available
from manufacturers as well as the type of formwork that can usually be built at the
job site by most of the contractors. Designing the repeated structure so that the
formwork can be reused repetitively, thus minimizing the amount of formwork needfabricated or pre-engineered.
For example a double story house with built up areas 2400 meter square.
0.6 TONNAGE
RM 5120
RM 960
RM 6720
RM 1260
In current condition, the rebar materials have been increased due to the
market shortage situation. Rebar material market price keeps going up from RM 900
per tones increasing to RM 1200 up to currently RM 2100 per tones, but concrete
price has been stably for so many years. The developers will take another step that
21
they will use bigger concrete frame (more concrete content) with minimum steel
content in their future structural framework design.
22
Pre-engineered form aids the contractor in figuring more accurate cost data,
and profit estimation is possible. Further, EFCO shop drawing tends to produce
formwork that is neither over designed nor under designed. Over designed forms are
expensive and under designed forms may be dangerous. In addition, it is also
provides good environmental for the construction workers. This new technology is
provided a convenient and safety workplace to construction workers.
Finally, EFCO shop drawings cut down on job site errors, and reduce the
amount of direct supervision needed to build the forms. EFCO shop drawings allow
the workers to work with minimal supervision and confusion. Efficiencies can save
time, money and the most important is to be adhering to the progress flow time.
Efficiencies give the company the competitive edge.
The changing of wood form to EFCO alloy steel panels will provide the
contractor the ability to speed up the project. In order to do this, the workers must
keep EFCO Hand-E-Form panels in use. It is avoidance from allow EFCO Hand-EForm panels remain on any longer than necessary. It is excellent to use the minimum
number of EFCO Hand-E-Form panels necessary to keep the job moving
continuously.
In addition, props supporting the structure are removed after the particular
section has attended well over its required strength. During construction, the
verticality settlement of the building is continually monitored to ensure and confirm
to the requirements.
23
3.2.1.3 The Necessity in Consider the Cost Effective Forming System
The cost of formwork equipment alone will seldom determine the best
equipment supplier, because Hand-E-Form panels cost may only be about 30% of
cost of which can determine the other 70%, the labour cost.
In order to find the true cost, the calculation formula of true forming cost are
Formwork material cost + Cost of using equipment. Material cost includes all
forming materials, accessories, tools and equipment whether rental or purchase costs.
This will be affected by the project schedule, which determines the number of reuses
that can be expected from a given set of forms. To compare the initial costs for
forming equipment, it cannot simply compare the proposed material cost per square
foot. When project conditions call for or allow forms to be cycled rapidly, basic
square foot costs can be deceiving.
24
affect the trial costing. It is need to make full consideration in selecting a system
supply for certain concrete forming solutions.
In order to complete the project in the same time period, a low initial material
cost forming, low-productivity, labour intensive system may require to use five to ten
times as many square feet of forming materials comparison with a high initial
material cost forming, high-productivity and labour efficient system.
It is not the initial cost of equipment, but the initial cost plus the cost of
using equipment that counts. In order words, given enough time and labour, almost
anything can be done. Nevertheless, productivity of workers can also vary due to jobsite conditions, weather, skill level, experience, and many other conditions.
25
3.2.1.5 The Second Variable is Time Lose
The job size and construction schedule will be two important factors to
consider. Time is very important in construction, as labour is a major cost. If the job
is large enough, the time saved by using manufactured forms with convenient
accessories may be worth the initial cost of the forms.
The EFCO e-form panel considered two type of direction wall in design and
also fabricated method. There are one direction wall and two direction walls. The
two direction wall is an update method from one direction wall to achieved better use
of formwork. Initially, the one direction was creating to facilitate the installation of
the e-form panel. It has upgrade to two directions in taking to the consideration of
design criteria. The two directions wall has good criteria as a support the transfer
loading from slab to the foundation. (Lam. 2004)
3.2.1.6.1
26
forming (wall and slab cast together), or wall and slab cast separately (EFCO,
Unispan, Noe, Megasteel, Grace, L&M, Peri-hori, Thysen, Westform and so on)
3.2.1.6.2
Once the one direction wall had been choosing, there are many restrictions
which will burden the selector whose use on it. The architect needs to design simple
architectural layout which structural design is either straight wall or one direction
wall concept. The structural walls are not free standing by itself and need temporary
prop system to support the formwork and wall before the opposite wall act as support
system to be install. The structure designer will need to design or add more steel and
tie beam design concept for the freestanding wall. In the material cost calculation,
one direction reinforced concrete wall concept, its structural cost is higher than twodirection reinforced concrete wall concept. That is ineffective in structural cost
saving when using one direction reinforced concrete wall concept to build landed
properties such as single, double or three story houses. Due to the design limitation,
the one direction wall is restricting the distant of two architectural walls within 3 to
3.5 meter. One direction wall design is only satisfactory for simple high rise
building.
27
3.2.1.6.3
The two direction wall concept is an upgrade method from the first method. It
have been invented when the contractor demanding 2 wall combine together and
casting constantly. This is the method that fulfils the design criteria as a part of
increase the stability of transfer the loading from slab to foundation. The
architectural layout is special, unique and different. This condition also enables
material saving after the reducing size of the BRC. In addition, it has a very good
process in accelerate the time frame of the progress. Nevertheless, the fabrication of
the E-form panel joints are more complicated when compare with one direction
reinforced wall. It has not become a barrier to the workers where they had have
intent to fabricate and dismantle it successfully without any problem. In this
extremely competitive market, the invention of two direction reinforced fabricated
wall act as trade mark for suppler in order to fulfil the contractors demand.
3.2.2
The Construction Process for the EFCO E-Form RC Shear Wall Design
Housing Project
EFCO E-form RC Shear wall design require a clean flat platform for easy the
fabrication of the panel following sequences of work. The foundation for the work
can be selected from either strip footing or raft foundation which will enable the
loading transfer from the RC wall to the foundation evenly.
28
Before delivery of EFCO Hand-E-Form panels to the site, the project site
must completed with at least four to six blocks of sub structural work up to the
ground slab level. This is the effective way in fulfilled the maintenance of the
formwork circulation system in order to get the cost effective in the cost saving for
the project. Sub structural work is the conventional wood forming. Before concreted
the slab, plumbing cable or necessary fitting had embedded into the slab and wall
starter bar had embedded into the slab.
There are three basic steps to building an EFCO concrete home building, the
base\slab or foundation, the wall, and the roof or deck system.
3.2.2.1.1
Foundation Condition
The first step is constructed the foundation or base slab. Soil resistance
characteristic must be analyzed prior to laying foundation. The outline of the
foundation is first staked and the parameter edge forms are set.
29
Strip footing is concrete feet placed in the ground, and it is reinforced with
steel bars on which the foundation and the subsequent building load are placed. Soil
conditions, together with the weight of the building, determine the size, design, and
the possibility in selection the piling foundation for weak soil condition. Usually, the
workers will carried out setting out work to determine the boundary area for each
block of the building. The compaction of earth work is the most important sequence
to provide the strengthen ground foundation for the loading transfer.
EFCO Hand-E-Form panels must be erected on poured slab. It could not erect
on dirt without poured slab. So, all cable, wire, plumbing, electrical service, sanitary
fitting, conduit need to embed inside the slab of which we must pre-determine it.
30
Preparation for each difference level such as drop at bath room and bedroom
need to be done by infill hardcore such as crusher run accordingly. Before pouring
the concrete to the slab foundation, it is need to applied one layer of plastic sheet to
the surface of the crusher run in order to prevented moisture permeate up to the slab.
31
After all internal embedded utilities (electrical, water and sewer pipes)
completed laid, the slab foundation ready for finishing concrete casting.
32
The wall alignment was marked as preparation for EFCO E-Form fabricate
indicator; the supervisor had to properly check the wall location on the floor by used
survey instrument. Preparation of correct wall setting up must thoroughly follow the
architectural, structural and EFCO Erection Drawings.
Materials for wall setting up are black inn and linear. Wall setting is very
important where must engage a very skillful, experience and knowledgeable
personnel to performed this job.
After the wall setting up has been established for a few units of houses, site
manager needs to inform EFCO Territory manager to arrange EFCO field supervisor
(one to two days trips) to survey and finalized reinforced concrete wall measurement
at site. (The ideally time frame is two weeks from the date of shipment.).This
measurement is extremely important for first time users as well as when project site
is extremely far from EFCO warehouse.
33
3.2.2.3 Electrical Issue
BRC wall are erected at least one block. M & E work that goes to the wall are
set. All electrical boxes are filled either with papers, polystyrene. Wireman tied these
electrical boxes to BRC wall. All electrical fitting must follow the government and
safety regulation.
34
Self-fabricated some concrete spacer/ block, or purchase some bar chairs are
some material used to fix the concrete cover space for the RC shear wall which was
invented by EFCO for friendly use and effective way in work erection. Bar chairs
are cheaper than own fabricated concrete blocks, Project director of Aceside said.
Bar chairs is lightweight material, and it is good when intention to build houses
above single story. (Steven Lew, 2004)
35
3.2.2.5 Conventional Beam box-sub
The probability of locations for conventional beam is at car porch area, at the
back of the house, at end lot and at corner lot. Beam formwork is conventional
wooden formwork and the carpenter is in the process of fabrication this wooden
formwork before delivery of EFCO panels to site.
The contractors had come across with various type of box-sub method and
the effective way need to be found for convenient the installation work. Below are
some methods that have been tried to achieve the best way of construction.
36
Method 1:
Timber box-sub is the cheaper method, but the shape of its box-sub is unable to
achieve 100% perfect. The square timber corner must be cut to the round shape for
plumbing box-sub.
If the square timber did not cut into round shape, it would result in spend a lot of
time to knock down the timber plank. When timber plank sticks concrete, it is
extremely hard to dismantle. It is extremely time consuming if there is an intention to
recycle this piece of timber plank.
Before well hang the timber plank to BRC wall, application of a layer of engine oil
on the surface of timber should be done. Mould oil doesnt apply on the timber
plank. Mould oil only applied on the surface of EFCO Hand-E-Form panels.
Method 2:
Steel tube box-sub, its shape is perfect, but it was very difficult to knock down this
steel tube from reinforced concrete wall. (Plumber of NKS said). The first attempt of
this method at Taman Merbok site shows that it is not a good alternative to use the
steel tube as plumbing box-sub.
Method 3:
Polystyrene box-sub is beautiful and its shape is perfect, but polystyrene material
is expensive than timber plank. All the plumbing box-sub at our Taman Merbok
site was applied this method of construction. It was being proof that effectively and
efficiency.
37
All plumbing & sanitary fitting location, its wall still remains as brick wall.
Therefore, architect and structural design engineer play extremely important role on
this issue.
Wall kickers preparation work need to be done after the wall setting
alignment complete. The wall kickers act as a stable alignment material to provide
prefect fix form for the EFCO E-form panel. Carpenter must complete at least one
block of wall kickers before delivery of EFCO E-Form panels to the site. The
material for kicker formwork is wood product. The casting height of kicker is various
heights.
38
Figure 3.16:
Concrete Work for
Wall Kickers
All the concrete kickers are properly vibrated. Concrete kicker is part of the
structural element. The quality of concrete kicker must same as the structure of
reinforced concrete wall. The concrete for single story house is grade 20. The
concrete for double story house is grade 25.
After prepared the kickers with the starter for BRC jointing work, the next
sequences of work is fix the BRC material as a main part of RC shear wall.
Normally, the site BRC materials are Standard sheet of BRC for Wall. It is
insufficient to order the width of BRC cut to size, because the reinforced concrete
walls are in the orientation of two-direction wall concept. Meanwhile, BRC cut to
size is expensive. The height of wall BRC may cut to size. BRC installer at site is
required to cut its width.
39
After all BRC, box-up beam, electrical box and pipe line have been installed,
the follow work is fabricated of EFCO formwork to form the main wall of the RC
wall. The first operation is erection of EFCO Hand-E-Form panels must started at the
inside face of a wall.
40
The second operation is to erect succeeding panels. It is started to set the next
panel (this second panel), into alignment with HEF clamps to the form panel of
which being set to the previous form panel. Special care should be taken to properly
place the HEF clamp. All Hand-E-Form panels have holes in the flanges at 25mm
center to center around the perimeters. The purpose of this function is to form any
shape of concrete wall by using the various clamps.
41
3.2.2.9 Pin and Plate Clamp Tool
One end of the pin and plate clamp tool is used to assist in the placing of HEF
clamps when necessary. The other end of this tool is used for placing and removing
spreader tie pins.
It is designed for use in aligning the holes in adjacent with form flanges. This
will ease the placing of HEF clamps when misalignment of flange holes occurs. The
third operation is to greased the spreader tie and secure the spreader tie with spreader
tiepins. When one side of the wall is set, grease the spreader tie and secure the
spreader tie with spreader tiepins. Spreader ties are required on one side of the form
joint only. Upon completing the erection of the first side of the wall, spreader tie
must in place. Inserting the spreader tie through the tie slots and pinned it with
spreader tie pins to the first side of the wall, now, the spreader tie are placed into the
wall. This procedure is extremely important. It increases your labor productivity and
minimizes the formwork checking.
42
The forming operation continues with setting one side of the wall. The EFCO
plate clamp is easily placed and perfectly aligns the adjacent form. After all 2 layers
of panel have been erected. It was preceded with placing and props work.
Figure 3.23:
Bracing Work for
Installation
43
3.2.2.11 EFCO E-Form Open Space for Steel Doorframe
There are two types of door frame fix method into the RC wall which are
steel doorframe and EFCO equipment cast separately and door frame cast together
with EFCO formwork.
It is need to infill cement into the steel doorframe. This process will only
make the steel doorframe solid after steel doorframe was being infill with cement.
The worker needed to insert one piece of brick wall on top of the steel door frame.
This experience was original from NKS site. This method of construction was
invented by Mr.Bong of NKS. He had set an extremely good example for steel
doorframe of which did not cast together with EFCO Hand-E-Form panels at the
Taman Merbok site in Malacca.
Figure 3.24:
Formwork
Opening for
Installation of Door
When steel doorframe does not cast together with EFCO Hand-E-Form panel,
it is need to create a concrete door opening in order to fix the door frame later.
The door opening need to be cast extra large which in order for workers to infill
cement into the steel doorframe.
44
For example, the specification of architects Bedroom door opening is
2100mm height X 900mm width. EFCO Hand-E-Form panels are provided a door
opening of 950mm width X 2180mm height in order to convenient in fabricate the
door frame. (NKS, 2004)
Method 1:
On the opening, the additional steel brackets to support steel doorframe need to be
added. Material for steel brackets is locally searching. It is needs to consult from
steel doorframe suppliers. Foremost is the expert in this method of construction
because they invented this method. (30/06/03). Today, Malpakat (Taman Austin
Height site in Johor Bahru) and Foremost (Taman Sri Bayan site at Malacca) applied
steel door cast in together with EFCO Hand-E-Form panels.
45
3.2.2.13 The Disadvantage of Casting Steel Door Together with EFCO Hand-EForm Panels
When the alternative cast steel doorframe together with EFCO Hand-E-Form
panels have been choose, the carpenter productivity will slightly reduce, because it
have created additional workload for formwork installer (carpenter). So, it needs to
compensate the carpenters.
The supervisor must always make sure that carpenters workers have the
skills and knowledge of fixing steel doorframe. If carpenters did not possess this type
of skills and knowledge, it is not encouraged to cast steel doorframe together with
Hand-E-Form panels.
Ground floor height (3200mm) - slab thickness (various) + extra 25mm height
concrete kicker height is our RC wall casting height.
46
Reinforced concrete wall is cast 25mm slightly higher in order to produce a
good concrete joint between the wall and the slab. When formwork height is 3-meter
height, two pieces of EFCO 1500mm height Hand-E-Form panels will be join
together.
28.12
23.43
14.52
11.79
7.71
7.26
After the hand E-Form is fixed, it proceeded with concrete casting work.
Figure 3.25:
Concrete Casting
after Completion
of Formwork
Installation
47
When two reinforced concrete walls distance is very close during concreting,
concreters use some 2 X 6 timber planks, and these timber planks sit on steel
formwork or cast concrete wall. Think safety, work safety. When two reinforced
concrete walls distance is very far, contractors fabricate their own concrete platform.
Instead of erecting traditional scaffolding tower , or fixing EFCO scaffolding bracket
and post on Hand-E-Form panels during concreting, concreters install self fabricated
lightweight steel walking brackets of which hooked on Hand-E-Form panels. This
method was invented at Acesides Mersing site. Later, this method was being
enhanced at Foremost site. Currently, all projects is fully adopted this method of
construction. It helps the concreter to save time, labor to erect scaffolding tower
during concreting and this method also save labor and time to dismantle scaffolding
after concreting.
When the concrete plant is unable to supply the concrete on time, it is need to
have more set of formwork material in order for carpenters to have a continually
daily formwork activity. When formwork material has extra set, result in formwork
double handling time increases. When formwork material has extra set, formwork
material wear and tear increases.
48
3.2.2.16 Concrete Slump Issue
First pour height is 600mm (2 feet height), second pour height is 1000mm (3
feet height), third pour height is also 1000mm height, and finally fourth pour height.
Each truck of wall concrete is five cubic meters. The interval of each truck of
concrete is approximately 40 minutes. The maximum concrete volume per pour for
wall is approximately daily 20 cubic meters for one unit of crane for wall forming
daily productivity. When wall finish has honeycomb, it may be due to your concrete
mixture/ concrete slump or vibrating problems. The pour speed of concrete into
125mm thick reinforced concrete wall
49
Table 3.4: Concrete Casting Quantity Per Day
Formwork Concrete
area
volumn
perpour
m2
b=a/2x0.125c
d=b/c
f=d x e
Concreting
g=f/60
200
13
40
100
250
16
40
125
300
19
40
150
350
22
40
175
400
25
40
200
500
31
40
250
600
38
40
300
5 10am to 7pm
700
44
40
350
800
50
10
40
400
After concreting work, it is need to house keeping all concrete tools, concrete
walking platform with water jet. It is recommended formwork installer and
concreters must be in the same team. If formwork installer is also the concreter, they
can coordinate extremely well. This concept is extremely important when
development is very small and you still want to use system design.
Figure 3.26:
House Keeping
Formwork after
Concrete Casting
50
Figure 3.27:
Formworks
Dismantle Work
Putting some wooden base plate to secure the panel at corner location.
Vertical check.
51
After checking the completed Hand-E-Form panels setup, the walls are
poured, and used water jet to clean the back panel immediately during the concreting.
The carpenter is required to perform vertically check before and after the concreting.
When the minimum curing time for a wall is achieved nine (9) hours, the
forms allowed stripping. After forms are stripped, cleaned and oiled from the
previous days poured, the next setting operation begins.
EFCO hammer tie puller + reusable spreader ties. Choose the strongest
worker to dismantle the spreader tie from reinforced concrete wall. The spreader tie
cannot embed inside the concrete more than 24 hours. The workers must grease
spreader ties by using engine grease. After dismantling all the Hand-E-Form panels,
worker need to be assigned to check any spreader tie was left over the wall. The
holes in spreader ties are covered with skim coat to remain soft and smooth surface.
Type of framework
Minimum curing
12 hours
beams
Soffit formwork to slabs
4 days
Props to Beams
14 days
52
Figure 3.28: RC
Shear Wall after
Completed
Figure 3.29: RC
Shear wall
After the ground level RC wall had completed, the first floor slab work is
preceded. This sequence of work are implemented by remain the conventional
method. 4 X 8 ply woods are used as form to the slab. Scaffolding need to be used
support the loading when casting are put into operation. As usual, all pipeline and
electrical conduits need to be installed before fix the BRC.
In this stage, the BRC starter bars need to be set up early as setting operation
to lay out the exact location of the upper wall. The supervisors are counter checked
the pipeline and electrical line as well as the BRC line before the continue job to be
proceeded.
53
Figure 3.30:
Installation in
Conventional
Method for 1st
Floor Slab
Formwork
Figure 3.31:
Installation of
Rebar for 1st
Floor Structure
54
The forming operation continued with setting one side of the wall. The first
floor panels set up are same as procedure implemented in ground floor wall panel.
Before the workers install the EFCO E-Form panel, the extra 2 high of BRC need to
be set for additional work. This is the purpose for brick laying work for additional at
upper roof area.
Figure 3.34:
Installation of
RC Shear Wall
for 1st Floor of
Building
55
Figure 3.37:
Workers Fix
Column and
Beam on the Top
of the Wall
Figure 3.38:
The Completion
of Formwork
Installation
56
Figure 3.39:
Dismantle of
the Formwork
Figure 3.40:
The Upper
Support Area
for Bricks
Laying
Figure 3.41:
The upper
Support Area
for Bricks
Laying
57
The upper support areas for brick laying patty walls are set up by
conventional method. The upper roof patty walls are still remained brick wall due to
the problem in setting the accurate pitch in roof truss and roofing work.
Figure 3.42:
The Completion
of Upper
Support Area
for Bricks
Laying
The RC gutter work is the conventional method where timber woods and
props are the materials to form the concrete beam and rebar. Normally the RC gutter
is located around the blocks of building. The EFCO E-Form covered with box-up is
the opening space to locate RC gutter to fully fix and joint between the gutter and RC
wall.
58
Figure 3.44:
The
Conventional
RC Gutter
Formwork
Installation
Figure 3.45:
Front View of
the Building
after RC Work
Completed
Each architectural finishing works are furnished with conventional timber fix
formwork. Joint between the RC wall and beam structure are perfectly matched. The
following work is appointed the roof truss workers to commence the truss work. The
rigidity and accurate level of the structure provided a good space for roof truss fixed.
59
Figure 3.46:
Brick Lay Work
and Installation
of Roof Truss
60
Skim coat only applies for reinforce concrete wall at internal areas.
Finally the external walls are plastered with normal cement plaster. It
proceeded with painting works and infrastructure works. (Tai, 2004)
61
CHAPTER IV
4.1 Introduction
Growth stage
Maturity stage
Decline stage
-Seller selects
certain products for
selected market
segment.
-Various product
choices, needs,
expectations exist in
the market.
-Buyers emphasized
problem solving.
-Buyers feel
technical
uncertainty.
Period: Before 2004
-Increasing
competitive
activities
-Customers have
better informed.
Period: From
2004
Until
-Huge tension of
market competition,
price war exists.
-Aggressive
customers,
customers are
knowledgeable.
2008
-Small companies
merge with bigger
companies or some
companies diversify
to other type of
business.
-The number of
suppliers reduced.
Period: From 2020
62
from substitute products such as wood form and a lot of me too products like
Unispan, Simple Form, Fast Form, PDG, and so on. The third type of competition is
competing for the contractors limited buying power.
During the early of 1980 in Malaysia when steel formwork equipment is sale
items, it will always draw heavily on contractors financial resources. Therefore
small contractor is unable to use steel formwork due to lack of finance. Until the
middle of 1990, steel formwork suppliers start to offer the rental terms, and this
option makes steel formwork more available to many contractors.
Generally, the contractors are resistant to change, even the changes are for the
better. People in all organization generally dont like change. Their resistance to
change is caused by their work habits, personal predisposition, educational and
professional training perspective, and fear of the unknown and mistrust of their
superiors and colleagues motives.
From the information obtained from suppliers, it is not easy to promote the
new products to the construction industry. The responsibilities of formwork suppliers
are to move the market from perfect competition toward oligopoly or monopoly.
Only through monopolistic conditions together with outstanding reputation, they
consistently get higher prices than others competitors during market booming.
Besides that, the supplier also apply partnering concept as a tactic to promote the
63
material effectively. This concept emphasised the win-win situation to those involves
in the business to achieved goal interactively. Table 4.2 shows projects implement
EFCO E-Form RC shear wall method in southern area in Malaysia. (Vivian Ho,
2004)
64
Table 4.2: Projects Implement EFCO E-Form RC Shear Wall Method in
Southern Area in Malaysia
Nos
1
2
3
4
Company
Main Contractor/Developer
Name Of Project
Location
Aceside(Malaysia) Sdn Bhd
Medan Alfa Sdn. Bhd
80 units(TypeA)(16'X55')DSTH Mersing,Johor
Aceside(Malaysia) Sdn Bhd
Medan Alfa Sdn. Bhd
80 units(TypeA)(18'X55')DSTH Mersing,Johor
Aceside(Malaysia) Sdn Bhd
Medan Alfa Sdn. Bhd
81 units(LS)(14'X55')
Mersing,Johor
Aceside(Malaysia) Sdn Bhd
Zecon Engineering Bhd
200 units DSTH
BP,Johor
5
6
BCB Berhad
BCB Berhad
7
8
9
10
11
12
13
BCB
BCB
BCB
BCB
BCB
BCB
BCB
BCB
BCB
BCB
BCB
BCB
BCB
BCB
Foremost
Foremost
Foremost
Foremost
Foremost
Foremost
Foremost
Foremost
Foremost
Foremost
Foremost
Foremost
Malpakat
Malpakat
Malpakat
Malpakat
Ngoh Kim
Ngoh Kim
Ngoh Kim
Ngoh Kim
Ngoh Kim
Frontier
Frontier
Frontier
Frontier
Frontier
Frontier
Frontier
Frontier
Frontier
Frontier
Frontier
Frontier
Construction
Construction
Construction
Construction
Siah Construction
Siah Construction
Siah Construction
Siah Construction
Siah Construction
Berhad
Berhad
Berhad
Berhad
Berhad
Berhad
Berhad
BCB Berhad
Laksama Reality Sdn Bhd
Laksama Reality Sdn Bhd
Laksama Reality Sdn Bhd
Laksama Reality Sdn Bhd
Laksama Reality Sdn Bhd
Polywell Enterprise Sdn Bhd
Polywell Enterprise Sdn Bhd
Laksama Reality Sdn Bhd
Laksama Reality Sdn Bhd
Laksama Reality Sdn Bhd
Polywell Enterprise Sdn Bhd
Laksama Reality Sdn Bhd
Mount
Mount
Mount
Mount
NKS
NKS
NKS
NKS
NKS
Austin Sdn.
Austin Sdn.
Austin Sdn.
Austin Sdn.
Development
Development
Development
Development
Development
Bhd
Bhd
Bhd
Bhd
Sdn.
Sdn.
Sdn.
Sdn.
Sdn.
J.Bahru, Johor
J.Bahru, Johor
Kluang,Johor
Kluang,Johor
Kluang,Johor
Kluang,Johor
Kluang,Johor
Kluang,Johor
Kluang,Johor
52 units (SSTH)(22'X70')TM
Pontian,Johor
J.Bahru,
J.Bahru,
J.Bahru,
J.Bahru,
AK,
AK,
AK,
AK,
AK,
Johor
Johor
Johor
Johor
Melaka
Melaka
Melaka
Melaka
Melaka
36
37
Total clients: 6
Total developers: 8
65
INDICATOR:
Type Of Project
DSTH
LS
SF
SSTH
CH
Semi-D
Name Of Project
TPU
TSK
TKB
TS
TM
TRU
TBKI
TRJ
TBC
TSB
TSH
Taman
Taman
Taman
Taman
Taman
Taman
Taman
Taman
Taman
Taman
Taman
Location
BP
J.Bahru
AG
AK
TM
G,DT
AL
Pulai Utama
Sri Kluang
Kluang Baru
Saujana
Megah
Rembia Utama
Bukit Katil Indah
Rembai Jaya
Bukit Cheng
Seri Bayan
Serindit Harmoni
Batu Pahat
Johot Bahru
Alor Gajah
Air Keroh
Tanjong Minyak
Gangsa, Durian Tunggal
Air Leleh
66
4.2 Why Partnering is Important?
Partnering does not happen in isolation. Nor do buyers and sellers suddenly
decide to change the nature of their relationship. Partnering occurs because there are
initiatives from either supplier or buyer driven by a need to improve a companys
competitive performance. These driving forces include:
Pressure on costs
True partnering with customers did not occur naturally. They are cultivated
over a long period by demonstrating respect for the customers personnel and by
recognizing the customers need to generate a reasonable profit.
67
Quality increases
High
Client satisfaction
increases
Low
Time
(OCT)
2000(Oct) 2001(OCT)
Time
Joint action is taken to reduce costs, and this benefits both parties, who can
then be more competitive. The buyer knows that the supplier is being fair in their
pricing and this encourages the development of further business.
68
4.3 Partnering in Action
Building relationship:
69
and suppliers are like a car manufacturer. The car dealer ties up with the car
manufacturer, and sells the brand name exclusively.
This allows the dealer and car manufacturer to form a partnering to sell and
work together. Suppliers brand name and the contractors company name become a
partnering. The partnering makes all the assets of the manufacturer available to the
dealer, so these assets can be put to good use to make money for partnering.
The supplier improves the customers profit by helping them apply their products
and services in ways that will maximize his revenues. In return, the customer helps
the supplier improve their own profit on sales by paying them a premium price. The
relationship with customers as partners is built around mutual profit improvement.
By working closely together with customers as a team, they can create a cooperative
we orientation for the relationship instead of a rivalries, often aggressive-defensive
me-you orientation. As we, the supplier can supplement and complement each
other in achieving objectives of a higher order, reinforce each others capabilities,
invite third and fourth parties onto the team when they can make a necessary
contribution.
Add value
70
If the buyer does a good job of communicating needs to the supplier, and the
supplier does a good job of communicating needs to the buyer, they can mutually
work out all the opportunities before they become problems. By working together on
quality issues and through joint identification of areas of concern, a better quality
performance can be achieved. Long-term agreements allow for the planning of a
number of issues by both parties.
Close co-operation between three partners ensures that the ultimate customer
obtains the right solutions and that the partners develop a reputation that enhances
their professional credibility.
Reducing costs
71
and cost effectiveness of its manufacturing processes. The supplier and design
engineer ensures long-term customer loyalty, while the contractor and developer
reduce their overall costs.
Risk is reduced for buyers since they get to know people in the supplier
organization, and know who to contact when problem arise. Communication is thus
improved. Good communication is critical. Good means open, honest and continual.
If either party has alternative plans to those being openly discussed then eventually
they will be found out and whole relationship will be in jeopardy. Communication
will be through numerous means such as telephone, faxes, short message send
(SMS), e-mail, questionnaires, quotations and drawings. This communication results
in the supplier being treated and feeling as a part of the buyer company. When a
friendly relationship builds up between the buyers and suppliers over the years, the
supplier almost becomes a part of the buyers organization.
EFCO co-operates with design engineers to develop the new market for a
new system design. By providing high levels of technical and manufacturing support,
EFCO ensures that contractor understands how to make the best use of the new
concepts. By developing joint product marketing initiatives, the partners are able to
educate large-scale users.
As a result, the developers increase their market share and builds stronger
relationship with the ultimate customer, while EFCO expand the market for their
products.
72
Partnering is built by experiencing good works together. Being partners is the
result of multiple accomplishments over considerable time. Most partnering is the
result of passing many tests under a wide range of circumstances. Persistent
performance is the keynote. Being a partner is one half of a sales relationship.
Converting a customer into a partner is the necessary other half.
Differentiating services
The supplier gets access to larger markets and higher levels of business, while
the developer is able to improve its cost position by offering purchasers added value
and differentiate their services from price competitors. Partnering occurred because
both partners recognized the business benefits that would result.
Partners have common objectives. Each partner wants to improve his pride
and profit. Partners have agreed on common strategies for achieving their objectives.
Partners are at common risk. Partners have a common defense against all others who
are not included in the partnering.
The basic business of partnering is two parties doing valuable things for each
other. If one partner stops contributing to the enterprise, the partnering stops. A
partnering can therefore be summed up at any time as an energy system whose net
worth is the total value of the things currently being done in it.
73
The partners are sharing in improved profit, and shared experience of
learning together just how their profits can be improved. The act of learning together
is one of the strongest bonding agents in a customer-salesman partnering. It is the
growth element in the relationship because it ensures that both partners will grow. A
successful partnering is mutual support.
How close the customer allows them to involve in their business that depends
on supplier relationships with the customer, and how much value the customer
believes supplier that they can add value to their business process. Therefore sellers
need to maintain contact, and build loyalty over a much longer period of time.
Therefore, selling industrial products requires a long-term selling plan. A plan based
on years of association between the buyer and seller.
74
The supplier regularly monitored levels of customer satisfaction in order to
increase customer retention. They seek to build loyalty and consistently offer
superior value.
ongoing and long-term relationships. Alliances are formed and last for very lengthy
period of time.
Networks can occur naturally, but building the network the supplier want and
need is not simple. They managed it by forging the right connections between people
and by arranged the right contacts and interaction at all levels. Once the network is
established, and they managed the flow of information between the two
organizations.
Partners have common objectives. Each partner wants to improve his pride
and profit. Partners have agreed on common strategies for achieving their objectives.
Partners are at common risk. Partners have a common defense against all others who
are not included in the partnering. The basic business of partnering is two parties
doing valuable things for each other. If one partner stops contributing to the
enterprise, the partnering stops. A partnering can therefore be summed up at any time
as an energy system whose net worth is the total value of the things currently being
done in it.
First of all, the partners are sharing in improved profit and shared experience
of learning together just how their profits can be improved. The act of learning
together is one of the strongest bonding agents in a customer-salesman partnering. It
75
is the growth element in the relationship because it ensured that both partners will
grow.
The partners can help their relationship by motivating each other when the
going gets tough, keeping each other honest and playing the outfield for each other
so that outsider will find it hard to score points against the partners. From a sellers
point of view, he can sell more, sell more often or justify a premium price for what
he sell of which help him improve his own profit in sales. To make a partnering
work, the salesman must be positioned as a consultant and the customer must be
positioned as his client.
76
CHAPTER V
4.1 Introduction
Why New Construction method (EFCO E-Form RC Shear Wall Concept) Can Beat
Old Conventional Method (Beam and Column concept)?
77
EFCO form work method for shear wall design is the pioneer leading provide
new structure framework in residential landed housing project. RC shear wall design
have provide several advantages in rectify the old conventional method. These
advantages are the main expectation for the developers and contractors in achieving
effectives of process in this new technology.
5.2
5.2.1
New design which is used EFCO E-form RC shear wall are more emphasised
in BRC building structure. When BRC quantity increases, it result BRC material cost
for overall project increases. On the contrary manner, the rebar tonnage is reduced.
Finally, the rebar material cost reduced and Rebar labor fixing cost reduced. ( Tan,
2004)
In construction market, rebar labor fixing rate is higher than BRC labor fixing
rate. Rebar labor fixing productivity is lower than BRC labor fixing. When Bar
bender fixing cost reduces, overall steel material and labor rate also be reduced.
Figure 5.1 shows the comparison of quantity steel and BRC between the
conventional method and the EFCO E-form RC shear wall method which is used in
sunflower double storey terrace house in Taman Pulai Utama, Johor. From the result,
it is indicated that the conventional method is used more rebar and A7 BRC which is
3.2 tonnages and 0.602 tonnages separately. The total amount of steel bar in
sunflower double storey terrace house which is used conventional method is 3.8
tonnages per unit house. While the EFCO E-form RC shear wall designs required
0.646 tonnages rebar, 0.973 tonnages A9 BRC, 1.057 tonnages A7 and 0.373
78
tonnages of B6 BRC per unit house. The sum of rebar, A9 BRC, A7 BRC and B6
BRC are 3.049 tonnages. The steel reinforcements cost in conventional method is
RM 9394.40 per unit which is compared to the EFCO E-form RC shear wall designs
is RM 6620.00. It is shows that the construction price for the new method has been
reduced for RM 2774.40 per unit house compare to the conventional old method.
CONVENTIONAL
METHOD
ST EEL
REINFORCEMENT
Kg
A. REBAR
QTY
RATE
Kg 3200.00 2.50
B. BRC
BRC A9
WEIGHT 4.99kg MS
0.00
Kg
EFCO-EFORM RC
SHEAR WALL METHOD
AMOUNT
0.00
BRC A7
WEIGHT 3.02kg MS 199.20
7.00
602
1394.40
BRC B6
WEIGHT 3.73kg MS
8.00
0.00
TOTAL
RATE Kg
9.00
0.00
QTY
195.00
9.00
AMOUNT
646
1615.00
973
1755.00
100.00 8.00
3802 9394.40
373
800.00
3049 6620.00
5.2.2
Building is Lighter
The new design which is EFCO E-form RC shear wall design provides lesser
steel content. It is also less weight from brick wall of which provide loading to the
foundation. So its advantages in reduce the total weight for the building. There will
be less loading to be transfer to the foundation and directly reduce the burden of the
ground to support the weight of the building. Finally, there will be less loading for
the RC pile foundation system. Directly, the number of piles reduces. It has some
cost saving for foundation work, so the costs of rebar, concrete, formwork, labor,
time, and machinery cost, interest, finance are also reduce.
79
5.2.3
In the new structure design, the structure engineer designs for repeat
structure. It is because all RC shear walls are similar in transfer the same loading to
the ground. There are 70% to 90% of the building brick wall volume are converts to
reinforce concrete wall in the new design. When the structure is designed without
beams or fewer beams, the formwork casting time can be reduced. The time frame
for RC shear wall structural curing are less where compare to the conventional beam
and column method. So the number of formwork cycle will be increased.
The EFCO hand E-form panel applies alloy steel material in fabricate the
framework. It has provided strong frame work of which can prevent the formwork
from wear and tear. This strong formwork panel is designed for longer lifespan can
be handling for the repeatedly cycle up to 800 times.
5.2.4
In EFCO E-Form RC shear wall method, 70% to 90% of brick wall quantity
reduced. Brick work will covered approximately 30% of the progress work. Through
new technology, it reduced cost for bricks laying and material wastage. Material
wastage like sand, cement and lime also can be reduced. The hoisting time of
material also reduced. It also leads to effectively in site maintaining and
coordination.
80
From labor point of view, skim coating work is easily work comparison with
plastering work. Cost of plastering is expensive than skim coating, because the skill
level of plastering is higher than skim coating due to uneven surface of brick laying
or due to the quality of wooden formwork for beams and columns. Skim finish
provided beautiful surface than plastering in additional that cost reduce for final
finishing.
CONSTRUCTION
ACTIVITY
CONVENTIONAL
METHOD
QTY
RATE
AMOUNT
EFCO-EFORM RC
SHEAR WALL METHOD
QTY
RATE AMOUNT
A. BRICK WALL
LABOR + MATERIAL
MS
346.48
22.00
7622.56
65.50
22.00
1441.00
B. PLASTERING
LABOR + MATERIAL
MS
692.96
11.00
7622.56
131.00
11.00
1441.00
C. SKIM COATING
LABOR + MATERIAL
MS
199.59
4.00
798.55
761.55
4.00
3046.2
TOTAL
16043.48
5928.20
Figure 5.2 shows the comparison of construction activity and the price
between the conventional method and the EFCO E-form RC shear wall method
81
which is used in sunflower double storey terrace house in Taman Pulai Utama, Johor.
It is indicated that both conventional method and EFCO E-Form RC shear wall
consisted construction activities of brick work, plastering work and skim coating
work. But the EFCO E-Form RC shear wall showed to have fewer amounts than the
conventional method where the differences is RM 10115.28. From the result, we can
conclude that the RC shear wall is a very productivity method compare to the
conventional method.
5.2.5
Labor productivity increases for all type of trades due to clean and neat site.
The EFCO E-form panels generally involve few workers in accomplish the
construction work. Only a group of workers will responsible in fix BRC, set up the
formwork, concreting and formwork stripping. When compare with conventional
type, it need many types of skill workers such as bar bender, carpenter and masonry
workers. System formwork is durable and safe to use which is provided neat and
safety site. Workers work in a safety site without a big amount of worker result in
site congested. Finally the site insurance charge reduced.
5.2.6
The EFCO Hand E-Form RC wall approach to diverted the labour intensive
construction method to the new fabricated method on site where effectively reduce
the construction dependency on foreign labour in the local construction industry. It is
only need a small gang of workers to performed the fabrication and dismantle work.
82
The same group of workers also worked in BRC fix and casting work. It had reduced
60% of labours in conventional method.
5.2.7
5.2.8
83
5.2.9
44. (1) The height of rooms in residential buildings other than shop houses
shall be for living rooms, not less than 2.5 meter.
(2) The average height of rooms with sloping ceilings in residential buildings
other than shop houses shall be for living rooms, not less than 2.5 meters. (Ngoh Kim
Siah, 2004)
Table 5.1: Different Height between Conventional Method and RC Shear Wall
Method
DESCRIPTION
CONVENTIONAL METHOD
EFCO E-FORM RC
SHEAR WALL METHOD
MINIMUM HEAD
ROOM REQUIRED
2500 mm
ASSUMPTION BEAM
"+ SLAB DEPTH
2500mm
SLAB THINKNESS AVERAGE
450 mm - 700 mm
110 mm TO 175 mm
2950 - 3200 mm
2610 - 2675 mm
MINIMUM FLOOR
HEIGHT
The difference in building height between conventional method and EFCO E-Form
RC shear wall method is 340 to 525 mm.
When the developers reduce the floor height, they have additional cost saving
in materials such as tiling (when developer provide full floor height tiling), painting,
formwork, rebar, concrete, crane, brick, plastering, skim coat and other type of
machinery, building weight, numbers of piling, labors, overhead, site maintenance,
capital investment, time, interest and finance cost.
84
5.2.10 Step Progress Claim is Different
DESCRIPTION
DURATION
DAYS
15
6 WEEKS
42 DAYS
25
12 WEEKS
84 DAYS
15
4 WEEKS
28 DAYS
10
8 WEEKS
56 DAYS
15
8 WEEKS
56 DAYS
TOTAL
80
DESCRIPTION
DURATION
DAYS
20
6 WEEKS
42 DAYS
HOUSE (4 BLOCKS)
15
8 WEEKS
56 DAYS
BRICK WALL
10
ROOFING
10
10
SEWERAGE
6 WEEKS
42 DAYS
DRAINAGE
6 WEEKS
42 DAYS
2 WEEKS
14 DAYS
TOTAL
80
42 DAYS
85
From the above table (Richard Ong, 2004), it is indicated that the progress
claim for the 2 method are difference. For the RC shear wall method, the foundation
works covered 15% of overall, reinforced concrete framework is 25%, walls with
door frame, electrical wiring, plumbing and internal skim coat covered 15%, roofing
and external plastering is 10% and finally 15% for the road, drain and sewerage
works. In conventional method, normally, foundation is 20 %, reinforced concrete
frame is 15%, brick works covered 10%, roofing is 10%, internal and external
plastering is 10%, sewerage works is 5%, 5% for drainage works and finally 5% for
the roads works.
From the result, the RC shear wall design combined together brick work and
RC wall which is in conventional method. In other words, when the contractor claims
the reinforced frame work in RC shear method, it is already covered RC plus brick
works. It is revealed that the RC shear walls have the advantages in fast claim when
the contractor claim RC works.
The second advantage is the comparison between the duration for the 4
blocks of double storey terrace houses in both methods. For the RC shear wall
design, it is only needed 38 weeks (266 days) to complete the construction works.
While the conventional method needed 72 weeks (504 days) to complete for the
same unit of houses. The difference is 238 days which is about 3/4 year. The EFCO
hand E-Form RC shear wall design promotes fast track system to accelerate the
duration of the project completed in a short term of period.
With the durable, all steel Hand-E-Form panels, each successive home built
are as high quality as the first. When contractor build a house using pre-engineering
86
and pre-fabricated alloy steel Hand-E-Form panels, it offers greater control of
accuracy and workmanship during construction. This result in a higher quality
structure compared to the conventional method using a lot of timber formwork.
Wood is getting scarcely. Wood will decay when there is too much moisture.
That presents particularly when it is in contact with the ground. Meanwhile a
carpenter used a lot of nails to make the structural parts of wood built forms.
Fasteners, including nails, are the weakest part of any construction joint.
5.3
The Advantages of EFCO Alloy Steel Panels Instead of Wood Built Form
The choice between wood and EFCO alloy steel panels depends on how much
the form will be reused.
87
5.3.1
The job site where EFCO alloy steel panels were used was immeasurably
tidier and more workmanlike than the job sites where wood forms used. In a large
jobs, where several areas would be under construction at the same time, for example
(Taman Pulai Utama, Taman Sri Kluang, Taman Kluang Baru II, Taman Saujana,
Taman Bukit Perdana, Taman Megah, Evergreen Height, Taman Seremban Jaya
(BCB Housing Project), it was easy to visualize the mountains of wrecked form
lumber that would have lying about in various stages of abandonment, and felt that it
would be worth money have the advantage of a clean and orderly job site.
5.3.2
5.3.3
Good Appearance
The alloy steel panels in their various symmetrical shapes leave not only a
smooth surface to the finished concrete; it leaves also a pleasing pattern. There was
little touching up, finishing and cement washing of the surface. This in itself means
88
more than meets the eyes. I felt there was some cost saving in having uniformly nice
surfaces that need little touching up.
5.4 The Advantages of EFCO Alloy Steel Panels Instead of Normal Mild Steel
Form
Normal mild steel is heavy than EFCO alloy steel panels. If the contractors
intend to use normal mild steel form to perform handset forming, it is need to
produce many small pieces of panels. Too many small panels have too many joints.
It will cost more in finishing cost. Small panels need a lot of accessories. A lot of
accessories mean wear and tear, and damage as well as missing cost is higher. It will
also slow down formwork labor productivity.
Alloy steel is the top of the line for value and performance in handset forming
due to its lightweight. If the project is well planning in advance, it may be able to use
600mm X 1500mm panels alone at 70% to 80% of the form done. With the other
twelve largest panels, it will make up about 90% of the square meters of Hand-EForm panels. This further helps increase formwork labor productivity.
89
5.4.1
Formwork needs to be very flexible. For contractors who intend to own the
formwork, they must consider their future formwork must have the characteristics of
that allow the contractor to use the formwork from one project to another project.
The versatile and adaptable factors are very important. In order to achieve the
best result, the contractor needs to think of the entire project when selecting the type
of forms and form material(s).
5.4.2
One-man Operation
The EFCO E-Form panel is the most lightweight panel. It is only 29kg per
square meter, it includes a panel with the steel alloy face sheet, steel stiffeners and
side flanges of which all welded together, and so it can be set in one piece. It is
already has built-in Wales, studs and sheeting, stiffeners. It helps contractors save the
current fabrication cost. It required no wedges or nails for alignment. Only single
steel aligners, never double, are required to straighten the form set-up.
90
Form systems, which one man alone with two hands could strip, move,
assemble, align and plumb. One man can do all operations. It eliminates the buddy
system to one-man operation, and no crane is needed during fixing the formwork.
This reduces inefficiencies when a few workers are standing around waiting for
another to return or waiting for a crane.
System formwork breaks the work down into simple tasks similar to factory
process eliminated the buddy system to one-man operation.
5.4.3
Simple Mechanics
The equipment includes only HEF clamps, spreader tiepins, spreader ties,
rubber seated aligner clamps, pipe braces, aligner tubes, and panels. EFCO Forms are
very simple and handy as far as assembly is concerned which results in a high
productivity rate.
As the system is very simple, there is not a lot of equipment to handle, lose
and replace. Accurately inventory counts that make it easily kept track of the stock.
Simple storage that makes it very easily stored in small area, and it is easy to be kept
for future reuse. It is ready to be use as soon as it arrives on the job site. Transports
easily, transports twice as many square meters in the same truckload of which
comparison with other concepts. Size and weight of panels provide for easy
breakdown, packaging and demobilization of large quantities of materials.
91
5.4.4
EFCO have a high quality manufacturing process. EFCO face sheet used
laser cut, and form the panels with steel frame through robot welding. EFCO face
sheet is over steel flange, which is producing a better form joint. This single tight
joint with no offsets which help produce a dimensionally accurate. It provides a
consistently smooth concrete finish.
Finish cost decreased directly associated with patch and rub due to the forms
leave minimal, sharp lines, which are easily knocked down with a stone. No grinding
and excessive rubbing of residual patterns left by lumber forms or steel forms with
lumber inserts. Patching of tie holes is minimal due to the flat configuration of the
tie.
5.4.5
Spreader ties can be removed without disturbing the form set-up. EFCO
spreader tie has a very small tie hole, 2mm width and 25mm length. It means that
there is a lesser patching cost, lesser water leakage problem for external wall.
92
It is no needs embedded items such as PVC tubes and cones. It helps to save
labor, material and coordinating cost. Its spreader tie also has a built-in function of
which help control the wall thickness as well as increasing the labor productivity.
The disadvantages of RC Shear wall design.
5.4.6
93
Table 5.4: Quantity and Total Price of Concrete for One Unit Sunflower Double
Storey Terrace House in Conventional Method.
CONVENTIONAL METHOD
DESCRIPTION
A. CONCRETE
UNIT
QTY
MC
11.60
164
1902.40
MC
4.30
164
705.20
MC
4.80
164
787.20
MC
16.70
164
2738.80
MC
17.76
164
2912.64
MC
1.00
164
164.00
ROOF BEAM
MC
4.40
164
721.60
MC
2.87
164
470.68
STAIRCASE
MC
1.80
164
295.20
RC CUTTER
MC
1.25
164
205.00
MC
0.00
164
TOTAL
66.48
RATE
AMOUNT
10902.72
94
Table 5.5: Quantity and Total Price of Concrete for One Unit Sunflower Double
Storey Terrace House in RC Shear Wall Method
UNIT
QTY
MC
0.00
164
0.00
STRIP FOUNDATION
MC
1.82
164
298.48
MC
2.50
164
410.00
MC
20.00
164
3280.00
MC
18.77
164
3078.28
MC
0.00
164
0.00
ROOF BEAM
MC
1.00
164
164.00
MC
2.87
164
470.68
STAIRCASE
MC
1.80
164
295.20
RC CUTTER
MC
1.25
164
205.00
MC
23.00
164
3772
TOTAL
73.01
RATE
AMOUNT
11973.64
5.5.1
Before the workers are fix the EFCO E-Form panel, the position of wall
alignment need to be setting as accuracy without mistaken. It is a problem for the
workers to perform it well and result incorrectness. Consequently, the error setting
95
wall needs to be dismantled and rectified it to the correct portion. The inaccuracy of
wall setting lead to the delay of the progress and of formworks transfers cycle.
Besides, the EFCO panel also disable for extra dimension fix. There is a case
in Taman Pulai Utama where for the expansion joint, the workers join the empty
space with wood fix between the 2 panels.
5.5.2
In previous chapter had mentioned that one of the advantages of the RC shear
wall design is a fast amount progress claim for the frame works out of overall the
project. Although there is an advantage in progress claim, but it is also result in delay
for the particular claim. For example, below chart show that the comparison for the
first and second description progress claim where after the foundation have been
claimed, the developer need to wait for extra time (1 month) to claim the second
claim for RC frame work.
This is the condition affected the developers financial control for those very
depend on claim for business turnover. The developer or contractor attempt to
acquire more formwork to achieved the claim target on time. It is effected the
increase of material cost for the project overhead.
96
Table 5.6: Progress Claim and Construction Period 4 Blocks of Sunflower
Double Storey Terrace House in RC Shear Wall Method
DESCRIPTION
DURATION
DAYS
15
6 WEEKS
42 DAYS
25
12 WEEKS
84 DAYS
15
4 WEEKS
28 DAYS
10
8 WEEKS
56 DAYS
15
8 WEEKS
56 DAYS
TOTAL
80
DESCRIPTION
DURATION
DAYS
20
6 WEEKS
42 DAYS
HOUSE (4 BLOCKS)
15
8 WEEKS
56 DAYS
BRICK WALL
10
ROOFING
10
10
SEWERAGE
6 WEEKS
42 DAYS
DRAINAGE
6 WEEKS
42 DAYS
2 WEEKS
14 DAYS
TOTAL
80
42 DAYS
97
CHAPTER VI
6.1 Introduction
This chapter discusses the data collection process involved in the study. The
data for this research was collected through the use of questionnaires targeting house
purchaser in Melaka and Johor, Malaysia.
This chapter presents the third part of objectives for this study. The chapter
will discuss on procedures included process of data collection from questionnaires,
identification of respondent, a survey and analysis of data collected using Statistical
Package for the Social Sciences (SPSS) with version 12.
98
6.2 Identification of Respondents
Relevant information has been studied for this report. This literature review
on variety of information resources was done. The information is obtained through
the reading of relevant journals, books, other researches, Internet, articles and papers.
Besides, several interviews are conducted between supplier, developers and
contractors to collect information for current progress condition. The literature
review also provided foundation for designed questionnaires that adopted in this
study.
The questionnaire was designed into three sections. (Please refer Appendix A
for the sample of questionnaire form)
99
c. Section C (The respondents knowledge about the RC wall design)
The questionnaires were handed out to purchasers through the BCB berhad
sales office in Taman Pulai Utama Johor, Malpakat sales office in Taman Dato
Chellam Johor and NSK sales office in Taman Merbok Melaka. However, only 50
had been completed and returned. This gives responding rate of 50%. Time
100
constrained is the critical factor cause the return of the questionnaires. The duration
used for distribution of questionnaires until collection is 5 weeks.
Table 6.1 tabulates the number of the entities in Johor and Melaka that had
responded to survey.
20
40.0
40.0
40.0
14
28.0
28.0
68.0
16
50
32.0
100.0
32.0
100.0
100.0
101
6.6.1
Frequency Analysis
The Frequencies procedure provides statistics and graphical displays that are
useful for describing many types of variables. For a first look at data, the Frequencies
procedure is a good place to start. For a frequency report and bar chart, it can arrange
the distinct values in ascending or descending order or order the categories by their
frequencies. The frequencies report can be suppressed when a variable has many
distinct values. It is accomplish by label charts with frequencies (the default) or
percentages.
6.6.2
102
6.7 Findings
6.7.1
100 set of questionnaire were sent out and 50 set of it have been completed
and returned. Out of the 50 respondents who provided information on their
profession or designation, 7 were the self employed, 16 were the professional, 17
were involve in service sector and finally 10 were from others profession .Figure 6.1
shows the composition of respondent by profession given in percentage.
Respondents' Profession
Others
20%
Service
34%
Self Employed
14%
Self Employed
Professional
Service
Others
Professional
32%
14% (14 nos.) of respondents were from self employed. 32% (16 nos.) of
them were professional. 34% (17 nos.) were those involved in service sector and
20% or 10 person were from others profession. Table 6.2 shows that occupation of
the respondents.
103
Table 6.2: Respondents Occupation
Occupation
Frequency Percent
Self Employed
Cumulative Percent
14.0
14.0
Professional
16
32.0
46.0
Service
17
34.0
80.0
Others
10
20.0
100.0
Total
50
100.0
Based on bar chart 6.2, 44 of the surveyed respondents were male and 6 of
them were female. It is indicated that most of the respondents own property in survey
area were male.
Respondents' Gender
50
45
44
40
35
30
25
20
15
10
5
0
Male
Female
104
Respondents' Race
Others
Indian 4%
16%
Malay
36%
Malay
Chinese
Indian
Others
Chinese
44%
The most surveyed respondents were Chinese which covered 44% overall of
the respondents. The second is the Malay which is 36%. 16% of the respondents
were Indian and 4% included in others.
As conclusion, majority of the respondents were Chinese and Malay.
105
18
16
14
12
10
8
6
4
2
0
16
Single Storey
Terrace House
8
5
Double Storey
Terrace House
Cluster House
Bungalow
Semi Detached
House
Bungalow
Cluster House
Type Of House
Frequency
Percentage
8.0
8.0
17
34.0
42.0
10.0
52.0
16.0
68.0
Cluster House
16
32.0
100.0
Total
31
100.0
Single Storey
Terrace House
Double Storey
Terrace House
Semi Detached
House
Bungalow
Cumulative Percent
106
From the above figure, majority the purchasers purchased Double Story
Terrace House (34%) and Cluster House (32%). There were 16% of respondent
purchased bungalows; however, there were 10% of purchaser purchased semi
detached house and 8% purchased single storey terrace house. In other words, most
of the respondents proper to purchase double storey terrace house and cluster house.
41
45
40
35
30
25
20
15
10
5
0
For residential
For investment
The survey indicates that commonly respondents were bought house for
residential purposes which is 41 of purchasers aim for it. For the rest of 9 were for
the investment purposes.
107
58%
22%
50000-100000
100001-200000
200001-300000
>300001
108
Melaka
Johor
Johor
70%
According to the results, 70% of respondents were purchased house at Johor area
and 30% of respondents were from Melaka.
27
26
25
24
27
23
22
23
21
Yes
No
109
Out of the 50 respondents, 23 were familiar with RC shear wall design and 27
were not familiar with RC shear wall design. Basically it is shows that not many
respondents were knowledge with RC shear wall design. The Figure 6.8 shows the
distribution of respondent according to those familiar and unfamiliar with RC shear
wall design.
32
35
30
25
18
20
15
10
5
0
Yes
No
From the above figure, we can interpret that most of the respondents feel that
they can accept implementation of RC shear wall for their house purchased. There
were 32 of response (64%) agreed with the new technology system but 18 (36%)of
them reluctant to this technology. This is showing that although some of the
respondents were not familiar with this system but they still can accept the system
for their property.
110
14, 28%
Yes
No
36, 72%
20
25
20
15
10
5
0
Yes
No
111
he results from this Figure 6.11 showed that among them, there were only 20
(40%) of 50 respondents plan to renovate their house. 30 of them planning to
renovate their house. This figure pointed that there is an others condition affect this
figure because Malaysians normally will do renovation for their house.
Area To Renovate
11
12
10
8
6
4
2
0
Infront The Car Porch,
Infront The Car Porch,
Behind The Kitchen Behind The Kitchen, Inside
of House
Analysis shows that there is nearly equal numbers of respondents were either
renovates 2 path of area, in front the Car porch area and behind the kitchen area or
both 3 part of area, in front the car porch area, behind the kitchen and inside the
house. Majority of respondent (11, 55%) plan renovate both 3 area. However, there is
9 of 20 respondents plan to renovate 2 path of area.
112
No
18, 90%
From the 20 respondents plan to renovate house, the figure shows that 90% of
respondents were disagree for the house that is not allowed for interior renovation.
Only 2 of them (10%) agreed for renovation is not allowed. According to analysis in
figure 6.13, most of the respondents plan to renovate their house cannot accept the
house that not allow to renovate for interior design. The others 30 respondents could
accept the house cannot be renovate.
113
Area To Renovate
0%
10%
60%
30%
Wall between dining room and living
Toilet Wall
Figure 6.14 shown that most of the respondents (60%) were commonly
dismantle wall between dining room and living room for renovation. 30% of them
preferred to dismantle wall between family hall and dining for enlarge the space.
10% of the respondents dismantle wall between bedrooms for renovation. Finally
there is no respondents dismantle toilet wall for renovation.
RC shear wall
design
Conventional
method
15, 75%
114
Figure 6.15 shows 15 (75%) out of 20 respondents were accepted RC shear
wall design if this method allow in renovation. Only 5 (25%) respondents were not
preferred in RC shear wall design although it provides convenient in renovation.
6.7.2
Interactive Analysis
6.7.3
Acceptance where interior hacking renovation is
not allow
YES
15
NO
10
SSTH DSTH
SD
CH
- BUNGALOW
SD
CD
- CLUSTER HOUSE
115
out that through a well-developed housing project which reduced purchaser
renovation work could increase respondents preferences in RC Shear wall design.
30
Yes
No
Acceptance
BarsRC
show c
Shear Wall
Design in well
Market Area
Count
20
Respondents
10
0
50000-100000
50000-100000
100001- 200000
100001-200000
200001300000
200001-300000
>300001
>300001
Howmuch
much
isamount
the am
of purchase ?
How
is the
ofount
purchase?
Figure 6.17: Interactive Analysis between the Amounts of the House Purchased
and Acceptance RC Shear Wall Design in Well Market Area
From the analysis, it is shown that for every amount of purchase from 5000 to
exceed 300000, the respondents can accept RC shear wall design in the well market
116
area. This can be an important information to the developer when select the
construction method for project development.
30
Count
20
10
0
Melaka
Johor
Analysis showed that there are two main situations in two difference location
in Melaka and Johor. In Melaka, most of the respondents were planning to renovate
their property but only a few were not for it. In Johor state, it is shown that most of
them were bought luxury property were not planning to renovate their property.
117
25
No
Bars show counts
Count
20
15
10
Yes
No
Do u familiar
with RC shear wall
design
method?
Do
you familiar
with
RC
shear wall design method?
15
Yes
Count
15
10
No
SSTH Bars
SINGLE
STOREY
show counts
TERRACE
HOUSE
10
- BUNGALOW
SD
- SEMI DETACHED
HOUSE
0
Bung alow
Sing le Stor ey Ter rac e House
Cluster House
Doubl e Storey Terr ac e House
Semi D etached House
SSTH
DSTH
SD
CH
Which
category
of of
house
do do
youu purcha se?
w hich
cate gory
house
purchase?
118
15
Yes
No
15
10
10
0
Sing le Stor ey Ter race House
Bung alow
Doubl e Storey Terr ace H ouse
Semi D etached House
SSTH
DSTH
SD
CH
Cluster House
Which
category
ofry
house
do you purchase?
w hich
cate go
of house
do u purcha se?
SSTH SINGLE STOREY
TERRACE HOUSE
DSTH DOUBLE STOREY
TERRACE HOUSE
B
- BUNGALOW
SD
- SEMI DETACHED
HOUSE
CD
- CLUSTER HOUSE
From the analysis figure 6.19, 6.20 and 6.21, the data revealed that even
thought most of the respondents were not familiar with the RC shear wall method,
but there were quite a number of this category of respondents could agree with the
implementation of RC shear wall design. This percentages of respondents are for
those agreed with the method and from the category thats purchased category house
119
from bungalow, semi detached house and cluster house. This is another facts showed
that most of these respondents agreed with RC shear wall design. The reason reflect
that respondents whose purchase luxury property were also not plan to have
renovation, could accept very much in RC shear wall design.
120
CHAPTER VII
7.1 Introduction
7.2 Findings
This section presents the research findings of the study. Basically all the
objectives of this study have been successfully achieved. This study can be
summarized as followings:
121
From the First Objective which is study the Construction Process of the
EFCO E-form RC Shear Wall Design, it is found that the process of the construction
is begin from site preparation, setting out, foundation, process to fabricate the EFCO
panel form, concrete issue until to the whole building completed. Besides, from the
research, there are some modification were found to improve the effectiveness of the
method.
wall. This two directions wall has good criteria as a support the transfer loading from
slab to the foundation. Rectification of the method to not fully implement RC shear
wall design where the developers use 80 % of RC shear wall design and remain 20 %
brick wall design in order to satisfied customers renovation habits.
From the in second objective, it is shown that is not easy to promote the new
products to the construction industry. The responsibilities of formwork suppliers are
to move the market from perfect competition toward oligopoly or monopoly. Only
through monopolistic conditions together with outstanding reputation, they
consistently get higher prices than others competitors during market booming.
Besides that, the supplier also apply partnering concept as a tactic to promote the
material effectively. This concept emphasised the win-win situation to those involves
in the business to achieved goal interactively.
122
luxury house such as bungalow, semi detached house and cluster house could accept
the RC shear wall design. It is because this category of respondents can accept where
the interior renovation is not allowed and they are also not plan to renovate the
house.
To conclude the data analysis, the marketing strategy plays an important role
in promoting the sales of the houses. Most of the luxury houses is constructed by
Malpakat development received a very good sales because of the good marketing
package promote by them which effectively attract buyers to purchased the house.
7.3
Recommendation
123
REFERENCES
Elaine C. Nocks and Gilles O. Einstein (1986). Learning To Use The SPSS Batch
System. New Jersey: Prentice-Hill.
Zaidatun Tasir dan Mohd Salleh Abu (2003). Analisis Data Berkomputer SPSS 11.5
for Windows Kuala Lumpur: Venton Publishing
124
Formwork and False work Equipment. Http: SCI Global.com
125
BIBLIOGRAPHY
126
127
1.
2.
3.
Self Employed
Professional
Service
Others: ___________________
Gender
Male
Female
Race
Malay
Chinese
Indian
Others: __________________________
128
5.
6.
7.
Bungalow House
Cluster House
For residential
For investment
RM 50000 - RM 100000
RM 100000 RM 200000
RM 200000 RM 300000
> RM 300000
Melaka
Johor
129
9.
Yes
No
10.
If your house/property is located at the most well property market area, can
you accept it to be build in RC shear wall method?
Yes
No
11.
Do you prefer your house/property to be built with nice flat ceiling and
wall?
Yes
No
130
12.
Yes
No
If no, proceed to question 20.
13.
14.
Yes
No
15.
Which parts of your house do you plan to dismantle to enlarge the space
inside in the house?
Toilet wall.
131
16.
If both methods, RC shear wall design and conventional beam and column
method enable renovation work, which method would you prefer?
RC Shear Wall Design
Conventional Beam and Column Design
17.
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
132
xii