Professional Documents
Culture Documents
This Electrical Maintenance Manual is compiled based on the equipment instructions provided
by electrical equipment manufacturer of PACITAN 2315MW coal-fired power plant and relevant
materials. It is only suitable for electrical system in this power plant.
The manuals will be revised and improved with the project progress development.
Page 2 of 326
CONTENTS
1
TECHNICAL SPECIFICATIONS
1.2
MAINTENANCE PERIOD
1.3
FUNDAMENTAL REQUIREMENTS
1.4
THE ACCEPTANCE
1.5
RELEVANT TESTS............................................................................................................ 27
1.6
1.7
1.8
LISTS
OF
AND
CONSTRUCTIONS.............................................................6
AND ITEMS....................................................................................8
AFTER
OF
GENERATOR OVERHAUL...............................................15
2.1
EQUIPMENT
2.2
MAINTENANCE
OVERVIEW.................................................................................................... 44
PERIOD AND ITEMS OF MAIN TRANSFORMER AND HIGH VOLTAGE AUXILIARY
TRANSFORMER......................................................................................................................... 51
2.3
MAINTENANCE
2.4
HANDOVER
OF
AND
ACCEPTANCE
AFTER
TRANSFORMER OVERHAUL.......................................64
OF
MOTOR............................................................76
3.1
THE
3.2
MAINTENANCE PERIOD
3.3
3.4
MAINTENANCE TECHNIQUES
3.5
MAINTENANCE
3.6
ATTACHED-TABLES........................................................................................................ 100
3.7
SPARE
TECHNICAL SPECIFICATION OF
OF
DC
AND
MAINTENANCE ITEMS............................................................81
OF
FOR
MOTOR.........................................................................................96
PARTS............................................................................................................... 103
4.2
4.3
4.4
TRANSFORMER............................................................................................................. 130
4.5
SPARE LIST
AND
ATTACHMENT
FOR
FOR INTERIM)............135
GENERALS.................................................................................................................... 135
5.2
TECHNICAL PARAMETERS
5.3
MAINTENANCE PERIOD
5.4
MAINTENANCE CONTENT
5.5
AND
OF
CHARACTERISTICS
OF
CABLE............................................136
CABLE..................................................................................136
OF
CABLE...............................................................................137
ARRANGEMENT,
6.2
MAINTENANCE
OF THE
EQUIPMENTS
IN
DC
SYSTEM................................143
DC SYSTEM.......................................................148
Page 3 of 326
6.3
SEARCHING
6.4
SPARE PARTS
OF
OF
DC SYSTEM EQUIPMENT.....................................................................152
APPENDIX:.......................................................................................................... 155
I.
SUMMARIZATION.................................................................................................................. 1
TECHNICAL INDEX................................................................................................................ 1
USING CONDITIONS............................................................................................................. 2
5.
CHARGE MANAGEMENT........................................................................................................ 9
6.
COMPUTER COMMUNICATION..............................................................................................10
MAINTENANCE
Page 4 of 326
1.1.1
Item
Model
parameter
or Item
Model or parameter
1. Generator
Model
QFSN-315-2-20B
Rated power
315MW
Rated voltage
20KV
Rated current
10726.7A
3000r/min
Rated capacity
370MVA
0.85 (lag)
Rated frequency
50HZ
2152A
Rated
voltage
Number of Phase
Connection method
2-Y
Cooling mode
Water-hydrogen-hydrogen
Direct-axis
reactance
excitation 472V
0.35 MPa
(guarantee 98.8
0.654
Bearing
vibration 0.025mm
(guarantee value)
Rotor
winding 115
temperature
Stator
winding
and 90
outgoing line outlet water
temperature
Temperature
90
between the stator
winding layers
Stator
iron
temperature
Temperature
of 120
stator end structure
element
core 120
120
70
Bracket
temperature
90
3. Hydrogen
Purity
98
Humidity
Page 5 of 326
(rated 4g/m3
hydrogen pressure)
Cooling
temperature
hydrogen 30-46
Hot
hydrogen 65
temperature
453
3t/h
45t/h
0.10.2 MPa
6.58
pH
0.51.5s/cm
Conductivity
0.51.5s/cm
hardness2g/l
of
hydrogen 4
90
0.10.2MPa
Inlet
temperature
water 455
Water capacity
4100t/h
35--45
Outlet
temperature
oil 70
217.5L/min
0.35 MPa
275L/min
5100mm
Gas gap
side)
(single 75mm
54
Parallel
number
branch 2
Hollow
16
Solid
32
56
Retaining
diameter Dk
Shaft diameter
External
diameter
690mm
of 410mm
ring 1200mm
450mm
Page 6 of 326
collector ring
Xh
Rotor weight
51.5t
72m
Manufacturer
KKS
#110MKA01
1.1.2
#220MKA02
Constructions
In this power plant, the QFSN-315-2-20B generators are used, which is provided by
Dongfang Electrical Machinery Co., Ltd.The generator adopts static excitation of selfshunt excitation and water-hydrogen-hydrogen cooling mode.It uses welded base
structure and the bearing is support by welded end cover.The generator casing has
two vertical hydrogen cooler to its ends.There is isolation vibration device between the
stator base and iron core.The rotor is of forged alloy steel assembly and provides
with aresymmetrical axial flow fans on both ends.The generator uses water-hydrogenhydrogen cooling mode,that is, using water cooling for stator inner winding and
hydrogen cooling for rotor inner winding. in addition, iron core of stator and its
stuctural components use hydrogen surface cooling while the collecting ring is of air
cooled mode.
1.2
1.2.1.1
The generator should be overhauled every 4 years, and the overhaul time limit is 50
to 55 days.
1.2.1.2
The generator should be repaired every 4 to 8 months, and the repair time limit is 18
days.
1.2.2.1
Major overhaul
items
Page 7 of 326
Item
Standard Item
Special Item
Content
name
Stator
Page 8 of 326
Page 9 of 326
1. Measure the air gap and pull the 1. Car spinning slip ring.
generator rotor out.
2.
Pull retaining ring to
2. Check the clear-up retaining ring, fan check the end windings and
leaves, ventilation holes, body, center the insulation pad.
ring and balance block, etc.
3. Deal with grounding and
3. Check and clear up air guiding blade, inter turn faults.
and replace it according to the actual
4.
Replace
the
rotor
situations.
structural components (heart
4. The flaw detection and coordination of ring, retaining ring, wedge,
rotor blade, retaining ring and center ring key, flexible devices,
hole.
etc.).
Rotor
temperature
Page 10 of 326
Outgoing
line cover
2. Replace
transformer.
the
current
3.
Replace
the
soft
connection or silver-plated
4. Inspection of water incoming &
layer on re-plated contact
outgoing bus duct and insulating water
surface.
guiding pipe. Check the sewage
discharging pipe and carry out the water
pressure test on outgoing waterway.
4. Replace the sealing
devices and components.
1.2.2.2
1.2.2.2.1
1.2.2.2.2
Check and clear-up the generator outgoing line and the pad of the coil end. (Check
the generator across the manhole. Check and clear-up twice a year.)
1.2.2.2.3
1.2.2.2.4
1.2.2.2.5
Check and clean every part of the main exciter and slip ring, brush holder, brush grip
and leads of the main exciter, and replace the brush.
1.2.2.2.6
1.2.2.2.7
Carry out predictive test according to pretest regulation and equipment situations.
1.2.3
1.2.3.1
Long-time outage
During the long-time of outage, the hydrogen is vented outside, both the seal oil
system and other auxiliary system has stopped. The maitainance items are as follows:
1.2.3.1.1
1.2.3.1.2
Discharge the water remaining in the water pipeline of the stator winding
Page 11 of 326
1)
Open the blowdown port beneath collecting pipe of the turbine end and excitation end,
discharging the water in the collecting pipe.
2)
Dismount the water inlet and outlet pipelines. Cover the water outlet flange with a
cover plate. Connect the hose with the water inlet flange at the excitation end. The
compressed air should be clean without oil and dust.
3)
Switch on the air compressor. Blow out the water in the water loop of the stator from
time to time until there is no moisture contained in the exhaust air. Then, seal the port
of the collecting pipeline.
4)
Extract the water remaining in the water loop of the stator winding which is difficult to
be discharged only with compressed air.
1.2.3.1.3
1.2.3.1.4
1.2.3.1.5
1.2.3.1.6
1.2.3.1.7
Safety measures
The hydrogen alarming system is in service. It is recommended to dismount the
hydrogen supply pipeline during the outage to prevent hydrogen refilling due to
accident.
1.2.3.2
Short-time outage
1.2.3.2.1
General
Page 12 of 326
Dring the short-time outage, the generator is filled with hydrogen, the oil sealing
system is in normal service . Operate the water cooling system of the stator winding
normally.
The common preventive measures include preventing condensation and ensuring
adequate sealing oil. Maintain the low conductivity of the cooling water of the stator
winding for generator restart up as soon as possible. Therefore, the following
parameters should be supervised and recorded regularly:
Temperaturer and pressure of the sealing oil
Purity, humidity and pressure of the hydrogen
The hydrogen that probably leaks into the enclosed bus.
Temperature and conductivity of the stator cooling water
1.2.3.2.2
Hydrogen sealing
Maintain the normal running of the oil sealing system. Keep the pressure of the seal
oil at 0.056MPa, the temperature at 30. Ensure the seal of hydrogen.
1.2.3.2.3
Hydrogen purity
Inspect the hydrogen prity regularly and keep the hydrogen over 95% through refilling
fresh hydrogen.
1.2.3.2.4
Condensation preventing
Keep the relative humidity inside the generator at 50% to prevent dewing. During the
outage, the relative humidity has something to do with the ambient temperature of the
generator. Inspect the generator regularly. Inspect the relative humidity when the
temperature dcecreases by over 8. If it is found that the relative humidity is
excessively high, discharge some hydrogen from the generator. Refill the dry
hydrogen into generator from hydrogen supply system so as to decrease the relative
humidity.
1.2.3.2.5
1.2.3.2.6
Page 13 of 326
1.2.3.2.7
Safety measures
Hydrogen alarming system is in sevice state.
The hydrogen exhaustor in the bearing lubrication oil system is in service for
extracting the hydrogen leakage from the generator or hydrogen blended into the
returning oil system.
When the generator is shut down in winter, if the ambient temperature is prossibly
lower than the freezing temperature (the room temperature is less than ). The
water remaining in the cooler should be discharged thoroughly to prevent icing. Keep
the temperature of the circulating water of the stator winding higher than at least 5
to prevent icing.
1.3
1.3.1
1.3.1.1
Implement the standard items for the overhaul and the necessary spare parts,
materials, special equipment and maintenance working hours budget.
1.3.1.2
Put forward the non-standard projects and changed projects according to equipment
operation and problems left over by the last maintenance, and draw up corresponding
technical organizational measures and security measures so as to implement these
projects required materials, spare parts and maintenance working hours.
1.3.1.3
Draw up overhaul plans and determine the progress of each project according to the
overhaul items.
1.3.1.4
Get ready the drawings, maintenance records and account for an overhaul.
1.3.1.5
The maintenance personnel (including external assistance staff) should learn the
knowledge of technical organizational measures and safety precautions.
They had learned the related safety codes and have passed the exams.
1.3.2
1.3.2.1
The generator should have a definite plan of inspection and maintenance to prevent
the failure. The plan can be divided into A-level and C-level maintenance. Each
generator should be established with record card to log the test results and
maintenance records in order to facilitate future reference.
1.3.2.2
1.3.2.3
Cautions on generator disassembly for maintenances and danger point & risk analysis
1.3.2.3.1
Page 14 of 326
1)
Make sure the replacement of generator has been completed; the hydrogen supplying
system has been installed with blocking plate and disassemble the generator
entrance door when the pressure in the generator is zero. Fill in compressed air
through generator sampling valve to blow away the residual hydrogen in the dead
angle of the generator.
2)
Before entering the generator, carefully and strictly detects should be carried out to
the gas inside the generator by the chemical professionals. Conform there is no
flammable before working. Wear special work clothes when coming into the engine.
3) Use 12V voltage lights and explosion-proof lamp holder in the generator. Joint is
prohibited there. The light line must be of static electricity-proof, no-breakage, good
insulation, and there should be no short circuit or virtual access phenomenon. At the
same time, explosion-proof flashlight must be provided and used in generators.
4) The disassembly of generator components should be based on the requirement of
Installation Guide. Safely keep of the disassembled parts to avoid being lost or
damaged.
5) The components may not be damaged in the disassembly. Make the necessary
markers; measure and keep a good record of the location and data components
before being disassembled.
6) The placement of hydrogen cooler should be safe and reliable; keep a good record of
the hanging out hydrogen cooler water pipe; and do not touch, hit, squeeze or press
the hydrogen cooler pipes.
7)
The transport of the generator end shield and air-gap bulkhead should be safe and
reliable. Move them to generator external part according to the order and place them
properly.
8)
Hoisting tools must undergo a rigorous inspection to ensure adequate safety factor
and it should be unified commanded by an experienced lifting workers.
9)
A pad should be used between the stator and rotor to avoid the friction. The hoisting
rope must be padded with a protective layer such as rubber, so as not to scratch the
rotor core; arrange staff to watch at both ends of stator and rotor clearance and
sufficient staff to maintain the rotor balance.
10) Check carefully the process and measures of plugging the generator stator in
operation position and pulling out the rotor and the use of specific tools to predict
possible incidents.
11) It is forbidden to go into the stator bore wearing shoes with nails. When coming into
the stator, do not step directly on the end of the coil. Especially the cooling water
pipes should not be moved or pushed to avoid the insulation tubes and water pipes
being damaged. The lower part of the core should be paved with rubber.
12) The one who goes into the generator stator bore must not take any metal objects and
Page 15 of 326
other objects in his pocket. It is necessary to focus on the end of the ventilation trench
for protection, in order that no foreign body falls into it.
13) Use qualified cleaning agent to clean the generator end coil in order to avoid
corrosion which may reduce the coil insulation level.
14) Take special care of the tools. Register the tools taking in and out of the stator bore in
order not to be lost. Count the number of the removed parts, nuts, bolts, pins, locking
plates and so on. Get the lost ones back and put them in special wooden box, and
label all of them.
15) Take fire fighting measures in advance for the special case of the need to flare up
when working in the stator bore.
16) It is a must to wear the seatbelt and helmet when working on the scaffolding.
1.3.2.3.2
1)
There are residual pressure in the generator; therefore, it may cause some wounding
due to the bounce of the manhole door when disassembling it.
2)
Combustible gas comes into the generator, personal and equipment damage
incidents occur in the work.
3)
The generator disintegration may cause the damage of hydrogen cooler and the
stator coil.
4)
When plugging the generator stator in operation position and pulling the rotor out, it
may cause the damage of stator and rotor.
5)
6)
When the generator stator bore works, it may result in the damage of stator core, coil
and water pipes.
7)
8)
Damage the coil at the end of the rotor when unplugging the generator rotor or
installing the retaining ring.
9)
Fire may occur when using the organic solvents to clean spare parts.
10) It is a must to wear the seatbelt and helmet when working on the scaffolding.
11) Pay attention to the under-footing during the work to prevent injuries or damage the
work-piece.
12) Use copper wrench, copper pry bars and copper hammer to disassemble the
important components, and protect them well.
1.3.3
1.3.3.1
Page 16 of 326
1)
Back wash the stator coil bar and outcomer before and after generator overhaul, and
before generator minor overhaul.
2)
Back wash the stator coil bar and the outcomer immediately when the generator is
under no load and the water system is not activated. If not, effluent in the water circuit
of the coil bar and outcomer may become dry and affect back wash. Make the record
on flow before and after back wash.Conduct the back wash alternatively every two
hours. The total back wash duration should not be less than 48 hours. The back
washing should proceed without interruption. The flow after back wash should be
higher than that before back wash. Otherwise, increase the pressure for re-back
washing until backwash result can meet the requirement.
3)
If the generator requires long-time outage, conduct the bach wash before internal
cooling pump shuts down. Dry the coil and lead with compressed air of 3kg/cm3 .
Recover the valve to state of running after the above mentioned is finished.
4)
Open the discharging valve of the water inlet pipe and water outlet pipe while washing
to discharge the water in the coil and lead. Make the compressd air of 0.3-0.5kg/cm 3
without oil stain go through coils and leads to remove and the remaining water. Then,
make internal cooling water in service.
After washing, supply the compressed air to remove the water remaining. The
compressed air goes into water inlet pipe and water outlet pipe alternately until the
whole course of back wash is finished.
After washing, discharge the dirt in the blowdown pipe, close the blowdown valve
tightly, inform the inspector to dismount and clean up the filter.
Anylyze and compare the flow before and after the back wash.
1.3.3.2
2)
Dismantle the soft connecting part of the generator main lead. Fasten
the soft
braided behind the screw with white cloth belt so as not to fall down to damage the
porcelain.
3)
Dismantle the slip ring, lead of the brush holder and the leads of AC main exciter and
permanent magnet assistant exciter. Mark both ends of the each lead end.
4)
Remove all the brush spring and put them into special bags after counting the
number.
5)
Place the brush in the position which may not affect the hoisting.
6)
Remove the generator cooler and the cooler flange screws of AC main exciter.
7)
Unlock the generator coupling, and dismantle the oil inlet and outlet pipes of bearing
Page 17 of 326
bush.
8)
Dismantle the slip ring, brush holder and the flange of generator hydrogen system,
and add blocking plate so that the generator is separated from the hydrogen system.
1.3.4
The disassembly of generator internal and external cover and points for attention
1.3.4.1
Remove the cover bolts of the generator at both steam and excitation ends and hoist
the cover away.
2)
Remove the bearing bush at both ends of cover and the upper bush pillow in the
sealing bush by the steam turbine maintenance professionals.
3)
Remove the twineshield at internal end of both steam and excitation sides, measure
and keep records of the gap between the twineshield and the blade and the gap
between the fan ring and the twineshield ring before hand. Put the twineshields on
both internal sides separately and mark them clearly. Measure rotor clearance at four
points respectively on the upper, lower, right and left sides of turbine end and
excitation end of the generator. The differential value is below 10%.
4)
Hang the rotor hoisting tools on the cover of steam and excitation sides respectively.
Find out center and fix it to the cover with cover fastening screws. Then, use M24
55 bolt to locate and fasten, and pad an iron plate between the suspender and cover.
5)
Measure the gap between the internal cover and blade (four points: top,
bottom,
left and right) and keep a good record. Remove the internal cover
on
upper
half side.
6)
Remove the blades on steam and excitation sides and keep a good record. Place in
different boxes in order.
7)
8)
Remove the bearing bush on lower half cover of the steam side and the lower bush
pillow of sealing bush (it is completed by machine).
9)
Remove the bolt on lower half cover of the steam side, and descend the cover 0.5m.
1.3.4.2
Disassembly work can be carried out after making sure that there is no hydrogen in
the generator. Naked flam and smoking is prohibited in the field.
2 Feed the compressed air through the generator sampling valve two days before the
disassembly. Blow off the residual hydrogen in the dead angle of the generator, and
open the manhole.
3)
During the removal of each component, damage is not allowed and marks should be
taken. Keep good records of the location and data of the components before the
disassembly.
Page 18 of 326
4)
Count the number of the removed parts, nuts, bolts, pins, locking plates and so on.
Get the lost ones back and put them in special wooden box, and label all of them.
5)
It should be safe and reliable when hanging the cover and removing the blades. Do
not bump and damage the blades. The strike and hit are forbidden.
1.3.5
1.3.5.1
Before removing the rotor, equip the pulley and the guide rail specially used for
removing stator on excitation side. And then sling the macro-axis on excitation side by
using crane; remove the lower end cap bolt on excitation side, descent the lower end
cap 0.5m on excitation side, drop down the macro-axis on excitation side and make
the pulley into its track.
2)
Sling the macro-axis on turbine side by using crane; loosen the tools for slinging rotor
on turbine side.
3)
Find a fixed point and hang a 5T chain block, pull out the rotor from the turbine side to
excitation side, at the same time, the crane should be translated to the excitation side.
4)
When the pendant cord of the crane is going to connect with the turbine end shield,
hang the micro-axis on turbine side to the end shield by using the tools for hanging
rotor. Loosen the crane; connect the dummy spindle on the turbine side rotor. Crane
should sling the rotor macro-axis on turbine side from the first section of the dummy
spindle, (the other two sections of the dummy spindle cannot be drew out), loosen the
end shield tools for slinging rotor.
5)
Pull the chain block on excitation side; translate the crane toward the excitation side
until the crane wire rope connects to the end shield, hang the crane wire rope to the
second section of the dummy spindle by the same way, and removing rotor continues.
6 Make the crane hang to the third section of the dummy spindle and continues
removing rotor to the excitation end by using the same way. At this time, the center of
the rotor should be moved out of the excitation end shield.
7)
At this time, hang the excitation side macro-axis to the end shield by using tools for
hanging rotor. And then loosen the crane wire rope.
8)
Seal the exposed vent hole of the rotor by rubber stopper or plaster.
9)
Hang a balance weight about 4T on the pulley, equip and fix the specialized stay tape
for hanging rotor at the center of the rotor.
10) Sling the central part of the rotor by wire rope, make it balanced and move the crane
slowly, withdraw the generator rotor from excitation side.
Page 19 of 326
Page 20 of 326
1.3.5.2
The wire rope, tools for hanging rotor and other tools should be the special tools for
removing rotor, so check them carefully and make sure its intensity and functions are
in good condition.
2)
All the operators should be operating under the unified command; they cannot
operate or command the crane as their own will.
3)
Do not lay the rotor during removing it, if it is necessary, the radian of the saddle
supporting should be in accordance with that of the large gear teeth of the rotor, felt
and board should also be equipped.
4)
In the whole process of removing rotor, the large rotor gear teeth should be in vertical
position, and when removing and laying rotor, the air scoop should not be broken.
5)
Never distort the iron core, air scoop, air fan and insulation during removing rotor.
6)
Do not take the protection sleeves, fan sleeve, center sleeve, slip ring and air scoop
on motor as.
7)
During drawing out the rotor, when some problems happens, it should be told to the
operators and the operation should be stopped until the problems are resolved.
8)
Anyone except the operators is not allowed to be close to the operation site, anyone
is not allowed to stay under the crane and the hung rotor.
9)
When laying rotor, the large gear teeth should be always in vertical position.
1.3.6
1.3.6.1
Check that the end section of windings and supporting parts is free of oil crust, check
that the insulation near the bar insulation box is out of expansion.
2)
Check and make sure that the insulated water connecting joints is closely tightened
no gap exists.
3)
Check the polarity and phase connection, shunt connecting wire and main lead for
insulation deterioration, wrinkling, expansion and overheating, check polarity and
phase connection, connector of main lead, shunt connection lead wire for water
leakage.
4)
Check the involute section of the rotor end section, each stent, tie line, vibration-proof
ringarticle pad obliquespacing padslot padconformal materials are not loosening,
deform, overheating, loose and fracture. Once some of them appears, timely
treatment is necessary.
5)
Check that the insulation of the windings end section is out of cracking, the paint film
is not fall off, overheating and cracking. The fixed screw of the copper platen and ring
should be out of loosening, overheating and falling off the paint.
Page 21 of 326
Check that the Tetrafluoroethylene insulation water pipe for crack, wear and quality
deterioration ,otherwise replace it with new pipe even if the it passed hydrostatic test.
1.3.6.2
Check that the stator article wedge is free of loosening, the iron core is not
overheating, vent duck goes smooth and out of foreign objects, the insulation of the
bar is not broken, air baffle is not loosening and broken. When cleaning the dust in the
stator chamber, high-power vacuum cleaner should be used, at the same time
compressed air purging is prohibited.
2)
Check the bar grading of corona shielding is out of small black points and faces, or
the black powder should be cleaned by brush, and then brush the low resistance anticorona paint.
3)
After checking, red epoxy enamel can be brushed at the end section.
1.3.7
1.3.7.1
Maintenance on rotor
1)
Check that the blade of the rotor fan is free of cracking, deforming and plaque, nut is
fastened, polished surface of the blade should be smooth, do some mental testing on
the blade.
2)
When changing blade, weight the new and the old blades, the angle, weight of the
new blade should be in accordance with the previous one.
3)
Check the protection sleeve, center sleeve and fan sleeve for cracks, deformation and
also do flaw detection testing
4)
Check that the balance block is not loosen, the connection parts of protection ring and
proper should be out of discoloration, electrical erosion, electrical burn. The surface of
rotor should be no color change and rusts or overheated signs.
5)
The wedge is free of cracking, protruding, and displacement, there is no dust, oil
crust, and skew on twine scoop, the retainer of the protection ring key should be free
of deforming, unsoldering, there is no loosening, cracking on nylon twine guide blade.
6) Purge the rotor vent path by 3-4kg/cm 2 compressed air, connect it to the special twine
guides for purging the twine. At first, do the twine rejection back purge in hot air area,
then purge of the twine into scoop in the cold air area, each twine scoop purges twice
on both back and normal sequence. If there are three twine scoops blocked in one
tank, it should be reported to the relative authorities. They can analysis the reasons
and find out solutions. At the same time, large gear teeth twine rejection tank should
also be purged
7) Check and make sure the surface of slip ring is smooth, free of rust staining and burn
marks, uneven degrees should be in 0.5mm, or it should be experience car spinning,
the roughness should be above 1.6 .
Page 22 of 326
8) Guide ring lead screw should be tightened, edges should be tight and sealed rubber
ring should be free of air leakage, vent hole should and hook groove and screwing
aperture should be clean, guide ring should be dried with dry compressed air with
density of 3kg/cm2.
9 Center hole sealed block plate screw of generator and excitation sides should be
fastened, the block plate is free of leaking air.
1.3.7.2
To measure the gap at the connection part of protection ring and rotor iron core, filler
gauge is used and the gap is divided into eight points.
2)
Divide the external diameter of the protection ring into 2 section 4 points, measure it
by external micrometer.
3)
Measurement on uneven degree of the slip ring surface, and the eccentricity.
4)
5)
1.3.8
1.3.8.1
Check that the generator water inlet is closed, when discharging all of the water,
remove the water inlet and outlet pipe flange and nipple, and mark the relative
position of the sealing ring and gasket by paint.
2)
Remove the screw connection between the two ends of the cooler and the cooler
shield, remove the sealing ring of the two twine chambers, then sling the cooler by
crane, lay it on the square timber, mark the symbol and position of each cooler.
3)
Remove and mark the end cover of the cooler, mark the separated parts, bolts and
nuts, record the number and then put them in bag.
1.3.8.2
Clean the end cover immediately after it is removed to prevent the mud and scale
becoming dry. Wash the copper tube by 25mm round brush till it is clean.
2)
Clear the mud, scale, rust staining of the end cover, tube plate and nipple, and then
brush the antirust paint.
3)
Check if the sealing rubber washer is not cracking and deteriorated, if so, change
them.
4)
1.3.8.3
Seal the water outlet flange by blocking plate and rubber pad, fill the water to inlet
Page 23 of 326
flange by pumper. Do hydraulic test for the whole set when water is full. The
requirement is that no leak and pressure drop under a water pressure of 0.6 MPa for
30 minutes.
2)
If the leakage and pressure decrease happens, the end cover should be removed, to
find the leakage in each one pipe, do the 0.6 MPa hydraulic test in each pipe for 15
minutes, if the copper pipe is leaking, blank it off at two ends by using the suitable
conical copper plug which is annealed. If the bulged ring is still leaking, bulge it again,
and the hydraulic test should be qualified.
3)
The blocked copper tube should not take more than 5 of the whole tube. After the
hydraulic test is qualified, assembly it follows the symbols, and check the sealing pad
at each part.
1.3.9
Maintenance standard of the generator outgoing, slip ring support and its lead
1)
Check the flexible wiring and transfer connection inside the outgoing housing, to
make sure that they are free of loosening and rupture, the porcelain bushing should
be smooth and clean, the silver coating of each contact are in good condition, and
there is no heating, discoloration, discharging. The insulated materials in each part
are free of heating, discoloration and carbonating.
2)
The insulation water pipe and the Jellyfish tube of the incoming and outgoing should
be out of loosening and rupturing.
3 The silver layer on each contact of the outgoing housing, joints and soft braided
connection line are smooth and in good condition. Before connecting them, clean then
by alcohol. When the soft braided connection line is fixed, check the contact by
0.05mm feeler gauge, the insert depth in each point should be less than 5mm.
4)
Clean the oil crust in the outgoing shield, keep the drain outlet goes smoothly. When
all the tests are qualified, equip the outgoing shield man whole valve, and change its
sealing rubber pad.
5 Clean each brush hands on the brush rack, adjust each brush holder to a distance of
2-3mm to slip ring, make it perpendicular to the slip ring.
6 Exchange the position of anode and cathode in each overhaul on slip ring, in order to
make the degree of wear is similar.
7)
Change the wear or short carbon brush, and make the contact connects well; contact
area should be over 75%. There should be a 0.1mm gap in the brush hand of the
electrical brush.
8)
The brand of the electrical brush should be the same, the brush should be free of
rupture, the brush braid should be fixed firmly, the difference between the contact
resistance should not be too large, the spring pressure should be in the range of
25.887%N, the adjacent brush voltage difference should be 10%, if vibrated, the
presses can increase 50%--75%.
Page 24 of 326
9)
1.3.10
Purge the brush rack and the slip ring by using dried compressed air, to measure the
insulation is in good condition.
Fitting Generator Rotor
1)
Put the generator bearing sleeves and bottom bearing bushings in the lower end
cover, and then sling the lower end cover to the turbine pit with a decrease of 0.40.5m.
2)
Methods on wearing rotor is the same to that of removing rotor, but operates in the
reverse sequence.
1.3.11
When rotor wears, the internal and external end cover should be assembled
immediately, it is not allowed to hang the rotor on the hanger for a long period.
2)
Clean the insulation board and the internal end cover of the turbine and excitation
sides. Firstly assembly the lower half internal end cover at the two sides and the fan
cover, insulation board and then the lower half external end cover and bush.
3)
Assembly the upper half internal end cover of the two sides together with fan cover
and insulation board. Measure the insulation of the internal end cover to ground is
above 1M by using megger.
4)
Measure the gap between the fan and the fan cover, gaps between air dampers
should be qualified.
5)
All the screws, dowel, flat washers and cone stopper are fixed firmly, and been
checked by a designated person.
1.4
1.4.1
1.4.1.1
1.4.1.2
The service personnel should prepare overhaul record, measured data record and
resolve defect record. Acceptance items as follows:
1. Overhaul technology completed after iron core stopped by generator, fasten coil end,
lead to line circuit and water channel and stator bar circuit and water channel,
1.4.1.3
2.
Bar and outgoing line circuit/water channel flow and water pressure test finished.
3.
4.
5.
Page 25 of 326
2.
Equipment surface status inspected and repaired, site and equipment cleaned, no
apparent defect, remove if any requirements
3.
Start to test after above items inspected and passed, evaluating entirely after no fault
inspected.
4.
1.4.2
1.4.2.1
Service personnel should record and collect after minor repair and clean site and
equipment, no apparent defect, remove if any requirements
1.4.2.2
The technical personnel of power planting should inspect minor overhaul items and
accept and evaluate entirely for equipment minor overhaul items and quality condition
1.5
Relevant Tests
1.5.1
Electrical test
If there is no special instructions, discharge all hydrogen as well as cooling water in
stator wire rod and out-going before test. Open the metal wire between temperature
detection latchboard and earthing terminal (steam end and excitation end). Restore
the metal wire after the test. Test working condition (cold or hot state) should be
determined based on actual confition of the test items. The test items are as follows:
Items
1) Measure insulation
resistance and
absorptance of stator coil
before and after maijor
and minor overhaul of
generator.
Test content
2) Before
the
generator When there is water in the stator or the residual water is
overhaul, the stator AC blown dry, the time for coil to earth and inter phase current
voltage
resistant
test current withstand test is 1.5UN1 minute.
should be carried out
3) Mwasure the stator DC The voltage will stay at each section for 1 minute when
withstand current and increasing from 0.5UN to 2.5UN, and following
leaked current before and requirements should be met: the leaked current should not
Page 26 of 326
Note
after the overhaul or after increase with the time increasing. Under the required test
widingings replacement.
voltage, the difference between phases should be 100%
higher than minimum value. The maximum leaked value is
below 20A, compare the difference value between
phases, and the value should change obviously. The
earthing plate on steam excitation end collecting pipe and
stator coil out-going assembly pipe flange should be open.
4) Measure
the
DC After the error caused by different lead wire kength is
resistance of stator coil in valibrated, the difference value between maximum and
generator major overhaul
minimum of DC resistance of each phase should not be
2% higher than minimum value. And relative change with
the initial value should not be more than 2%.
5) Measure the insulation The insulation resistance should be 1M when measured
resistance of rotor coil with 500V Megohmmeter, and it should be 0.5M when
before and after the measured with 2500V Megohmmeter.
generator major and minor
overhaul:
6) Measure
the
DC The value can not exceed 2% of initial value.
resistance of totor coil
during motor overhaul
7) After
the
generator Measure with 1000V Megohmmeter, and the value should
overhaul or minor repair, be 30K (regulation of manufacturer with no water
the insulation resistance inside), and it should be 100K when there is no water.
of manifold on steam and
excitation
ends
and
outgoing
manifold
of
stator.
8) After
the
generator The stator out-going bushing can bear 64500V AC
overhaul,
out-going frequency dry-arc electrical strength after the generator
bushing of stator should overhaul. The test should last one minute.
carry out the AC voltage
resistance test.
9) Measure
the
AC The test voltage peak value should not be 463V higher
impedance
of
rotor than rated excitation voltage. The measured value can be
winding after generator much different with initial value.
overhaul
Page 27 of 326
10) Measure the insulation The value should be 1M when measured with 1000V
resistance of generator Megohmmeter.
bearing after overhaul
11) Meaure the shaft voltage When the bearing oil membrane is short circuited, the
after generator overhaul
voltage on two ends of rotor should be equal with voltage
between bearing and the support.
12) Measure
the
no-load
characteristic curve after
generator overhaul oor
winding replacement.
13) Measure the short circuit The data should be within error range compared with
curve
after
winding manufacturer data
replacement
or
when
necessary
14) The stator iron core test there is partial high temperature or short circuit may exist
should be carried out in overhaul.
when the core is damaged
15) Measure that the anti- Measure that the anti-corona coating to ground potential of
corona coating to ground stator is5V when necessary.
potential of stator is when
necessary.
1.5.2
Generator stator bar flow rate test (measured with ultrasonic flow meter)
1.5.2.1
The end covers on both sides of generator are open during overhaul, and then
connect stator cooling water in and clip two sides of output water pipe insulation guide
pipe with ultrasonic flow meter to measure (coat insulation water conduit with
Vaseline). Measure steam side insulation water output pipe during washing, while
measure excitation end insulation water output pipe. The measurement of dlow rate in
out-going bushing is the same.
1.5.2.2
Open the access door to enter the generator to measure when minor overhaul, the
method is the same with above.
1.5.2.3
Compare when the flow rate test of all branches are finished, the difference among all
these value can neither be 20%more than average value nor 20% more than previous
test. Otherwise, find out the cause and eliminate.
Page 28 of 326
1.5.3
1.5.3.1
Test with system means doing the test with cooling water system directly.
1.5.3.2
Test without system means opening the inlet and outlet water pipe flange of generator
stator cooling water, and then install dedicated test flange pipe to do the test.
1.5.3.3
The cooling water of 0.49-0.687MPa will flow into generator winding and out-going
and keep the water in for 4 hours.
1.5.3.4
Check the water conduit on by one to mare there is no crack, abrasion, damaged
caused by disassembly and deterioration , if there is, replace the pipe wuith new pipe
which can meet the requirement of test.
1.5.3.5
Check the all joints of bars, insulation water conduit joints, parallel lead wire to soft
connection upper joint and pole group joints one by one, and there should be no water
leakage.
1.5.3.6
All parts should be restored into operating state after tests above.
1.5.4
1.5.5
1.5.5.1
During the major overhaul of generator if only coolers need to be disassembled, the
air pressure test can be carried out. Activate oil sealing after the generator assembly.
Inject dry compressed air into stator to replace air test.
1.5.5.2
Close the first valve of hydrogen pipe, carbon dioxide pipe and the first valve of their
meters, and then close out-going blowdown valve.
1.5.5.3
Make clean and dry compressed air flow into generator air temperature meter screw
hole and install a master gauge of 0-0.5MPa.
1.5.5.4
Increase the gage pressure to 0.1MPa and sealing oil pressure to 0.15MPa, check the
leakage point with soap water.
1.5.5.5
After all air leakage points are eliminated, increase the pressure to 0.3MPa gage
pressure and sealing oil pressure to 0.35MPa, continue leakage checking until there
is no leakage point.
1.5.5.6
Keep the pressure inside at 0.3MPa gage pressure, close the air source valve. When
the temperature and pressure change outside is not obvious, the influence on the
pressure inside can be ignored. 24hours later, if the pressure decrease does not
exceed 0.0041MPa and corresponding air leakage is 10m3, then it can be consider
to meet the requirement of test.
1.5.5.7
If the pressure decrease of pipes with hydrogen, carbon dioxide and meters does not
exceed 0.15MPa during air filling test, it meets the requirements of test.
Page 29 of 326
1.6
1.6.1
1.6.1.1
Page 30 of 326
1.6.1.2
Model instruction:
Code
GES
Position
Code instruction:
1)
2)
3)
4)
5)
1.6.1.3
Technical Parameters
1.6.1.3.1
The excitation system can operate continuously if the excitation voltage/current does
not exceed 1.1 times of the rated value.
1.6.1.3.2.
The peak voltage multiple of the excitation system, which is the forced excitation
voltage multiple should not be less than 1.8.
1.6.1.3.3
The allowable forced excitation duration should not be less than 10s.
1.6.1.3.4
The nominal response of the excitation system should not be less than 2 times/s.
1.6.1.3.5
1.6.1.3.6
The voltage output of the AVR should change within a scope from 0.3% of the rated
generator voltage to 1% per second.
Page 31 of 326
1.6.1.3.7
1.6.1.3.8
The AVR should maintain the generator voltage static difference at 1%.
1.6.1.3.9
When the generator carries no load, the frequency should not vary for more than 1%
and the output voltage for less than 0.25%.
1.6.1.3.10
When the generator carries no load, the voltage regulating margin should not be more
than 50% of the percentage with fluctuations for less than 3 times and the regulating
duration should be less than 5s.
1.6.1.3.11
If the generator voltage needs to be suddenly raised from zero, the AVR should
maintains the generator voltage output margin below 15% of the rated value with
fluctuations for less than 3 times and the regulating duration should be less than 10s.
1.6.1.3.12
If the rotor current is less than 1.1 times of the rated value, the rectified voltage
supplied to both ends of the rotor coil should have a maximum transient value that is
not more than 30% of the rotor coil voltage amplitude measured in the test in
manufactory.
1.6.1.3.13
If any parallel branch or serial connection is available, the average current coefficient
thyristor bridge should be at least 0.85, and the average voltage coefficient should be
at least 0.9.
1.6.1.3.14
Signal input: the electrical signal input into AVR is obtained from the PT and CT of
generator output:
3100V
50Hz
Voltage 3100V
50Hz
35A
3 phases
50Hz
Current 35A
1.6.1.3.15
50Hz
3 phases
3 phases
+FBC
--QF
+SCR
Excitation CB
AVR
+AVR
G
+PRO
Rotor Protection
TE
Page 32 of 326
1.6.1.4.1
1.6.1.4.2
Silica-controlled Rectifier
This rectifier converts the A.C. power from the transformer for excitation into D.C.
power which is then transmitted to the generator excitation circuit.
Usually, several bridges operate in parallel to burden with the load. As a result, the
rectifier can still supply stable excitation current into the rotor even if some of the
rectification branches are faulty. How many bridges need to be paralleled and how
much current each bridge can bear should depend the specification of the thyristor
element. But generally speaking, the rectifier should still be capable of the excitation
for rated operating condition of the generator if one bridge is out of service. In some
other cases, the rectifier should be capable of the excitation for forced excitation if
one bridge is out of service.
The silica-controlled bridges are under the control of the AVR which regulates the
output power to change the excitation current of the generator so that the output
voltage and reactive power of the generator can be regulated.
1.6.1.4.3
CB for Excitation
This CB has got the alias of de-excitation CB or field CB which is the visible fracture
between the rotor coil and the rectifier. It is one of the vital part for the de-excitation
circuit of the rotor, and is capable of quick tripping and field energy transfer in
emergency so as to ensure safety of the generator.
The D.C. output of the rectifier is transmitted into the generator rotor via this circuit
breaker.
1.6.1.4.4
AVR
The AVR which is installed in the AVR panel is composed of the signal processing part,
the control & calculation part and the signal output part. The AVR acquires all sorts of
analogues and on-off information of the generator that are then calculated and
processed by an industrial computer for the control of the output of the large-powered
rectifier. Thus, the excitation system can be under control.
The AVR is of a fault tolerating structure with dual-channel redundancy. Moreover, it is
equipped with 2 independent sets of hardware circuits respectively composed of signal
processing, control & calculation and signal output. The two circuits operate
independently with some mutual connection.
The two channels operate in parallel in a way that one is the operating channel while
the other as the hot backup for it. Software is utilized to actualize the functions of
mutual diagnosis, real-time on-line self-diagnosis, mutual tracing, communication as
well as mutual switchover.
1.6.1.4.5
Fault Signal
Page 33 of 326
This part serves as the reference for analysis and solution for fault alarm in the
excitation system.
The sub-option of FAULT INFO beneath the menu of SYSTEM INFO, which is provided
by the man-machine interface unit, can be used to display some of the faults detected
by self-diagnosis function. In the meantime, some of the essential fault information is
transmitted through the hard relay connector to the AVR output terminal so that the
information can be used for the remote alarm system.
This situation has occurred if 1 is displayed at the position beside the fault alarm signal.
Info.
Description
Fault Description
Device Execution
Solution
PT
wire
breaking
for
channel A(B) of
AVR
The PT connected
with the regulating
channel
A(B)
comes up with wire
breaking or the
measuring board is
faulty
The
operating
channel
switches
from channel A(B) to
channel B(A). If both
of the PTs have
come up with wire
breaking,
the
regulation mode is
switched
from
Constant Voltage
To
Constant
Current
Switch to constant
current.
Perform
maintenance on the
PT circuit.
Faulty
The
operating Put the faulty channel
synchronization
channel is switched out of service for
between
channel from A(B) to B(A)
prompt maintenance.
A(B) and TR. or
between
channel
A(B) and pulse
board
Fault
of
channel A(B)
HMI
communication
Communication
fault
between
channel A(B) and Alarm
the
superior
computer
AVR excitation No
voltage
initiation failure established
Page 34 of 326
circuit,
the
rotor
circuit as well as the
brush abrasion
Inspect
circuit
the
Protection for
over-voltage
starting up
Alarm
Protection for
over-excitation
limitation
Alarm
Less excitation
More excitation
logic
starting up
Protection
underexcitation
limitation
for
Alarm
starting up
Protection for
V/F limitation
Alarm
Less excitation
starting up
Power
limitation
of
rectification
panel
One
power One of the parallel Alarming,
blocking Inspect the faulty
panel faulty
rectification panels the pulse of the rectification panel.
is faulty.
faulty panel
Two
power Two of the parallel Alarming,
blocking Inspect the faulty
panels faulty
rectification panels the pulse of the rectification panel.
are faulty.
faulty panel, limiting
the forced excitation
Three
power Three
of
the Alarming, activating
panels faulty
parallel rectification all the power panels,
panels are faulty.
limiting the load of
them.
Stator current LCU command can Alarm
limitation
not be executed
Page 35 of 326
Inspect
the
communication circuit
effectively.
and
see
if
the
regulation setting has
gone beyond the
given authority/ been
exceeded.
Power
panel This panel is off.
1(2 or 3)
Rectification
panel is out of
operation
Power
panel Vent gate for power Cut off the pulse of
1(2 or 3)
panel 1(2 or 3) is this panel to put it
not open
out of service.
Fans
for
rectification
panel are out
of operation.
Power
panel Pulse missing in
1(2 or 3)
rectification
of
power panel 1(2 or Alarm
Pulse loss in 3)
rectification
panel 1(2 or 3)
Power
panel Thyristor for power
1(2 or 3)
panel 1(2 or 3)
carries not current
No current in
rectification
panel
Alarming,
automatically
disabling
thyristor bridge
Open
the
A.C.
disconnector and the
this D.C. disconnection to
conduct inspections
on the thyristor.
Power
panel The protective fuse
1(2 or 3)
for
thyristor
of
power panel1(2 or
Fuse blowout 3) blows out.
in rectification
panel
Alarming,
automatically
disabling
thyristor bridge
Power
panel AVR receives no Alarm
1(2 or 3)
info. from this panel
Input
fault
module
Power
panel Command
from
1(2 or 3)
AVR can not be
Alarm
accurately
Output module executed.
fault
Page 36 of 326
this
Inspect
the
communication circuit
and the intelligent
communication
module
Inspect
the
communication circuit
and the intelligent
communication
module
De-excitation
panel
Inspect
the
CB
mechanism and the
control circuit.
Inspect
the
CB
mechanism and the
control circuit.
Inspect
the
communication circuit
and the intelligent
communication
module
Commands
from
AVR can not be
Alarm
accurately
Output module executed.
fault
Inspect
the
communication circuit
and the intelligent
communication
module
De-excitation
panel
Inspect
the
CB
mechanism and the
control circuit.
Field
CB
rejects opening
De-excitation
panel
Field
CB
rejects closing
De-excitation
panel
Input
fault
module
De-excitation
panel
Field
CB
mistakenly
opened
1.6.2
Equipment Maintenance
1.6.2.1
Overview on Maintenance
Fouls may remain in the electronic elements and in the rectification device due to the
ambient. Also, the vibration of equipment during operation may loosen the electrical
contacts. As a result, the excitation circuit which has high voltage and high current
would be shocked. Therefore, regular cleaning and maintenance seems vital for the
excitation system.
No.
Object
Every year
Tr.
for Inspect to find out if any Sweep away the dust and sundries, check
Excitation
abnormal noises exist.
whether there are abnormal noises.
Rectifier
2
Fans
Air Strainer
Page 37 of 326
Radiator
External inspection
External inspection
Rectifier
Disconnecto
r
for
Rectifier
Field CB
7
Field CB
CB for Initial
Excitation
Bus-bar
AVR
10
Hardware
External inspection
External inspections
11
Functional
Inspection
What is listed in the table above will be described in detail hereafter. The instructions
for inspections every 3 months and annual inspections should be executed separately
since the inspections every 3 months only involve external work while the annual
inspects requires some maintenance.
1.6.2.2
1.6.2.2.1
Excitation Transformer
Inspections should be conducted on the external of the transformer to judge by the
noises if the transformer is operating normally.
1.6.2.2.2
Rectifier
1) Inspections are necessary for the contamination on rectifier fans and noises.
Since it is impractical to supply lube oil into the fans, the faulty ones need to be
exchanged.
2) Inspect to see how the air strainer has been contaminated that is embedded in
the vent orifices on the rectifier door. Negative influence would be performed on the
ventilation and heat radiation of the panel if too much dust has deposited on the
strainer so that this strainer should be exchanged.
3) Check the contamination of the radiator.
4) If parallel operating thyristor bridges are adopted, the amperemeter of each
bridge should be read to see if the current has fluctuated.
Page 38 of 326
1.6.2.2.3
AVR
1)
Inspections are needed to see if too much dust has deposited on the circuit
board and if oxidization by overheating has occurred.
b Inspect to see if the relay has started up with abnormal arcing and whether
the lamp is normal.
c
2)
screen
Comparison on the measured values: find out the differential value between
the measured value on the display and those of other positions in order to
make sure the device indication is correct.
Testing on the spare regulative circuit: the spare regulative circuit and the
excitation current regulation channel need to be inspected to verify that
balanced tracing can be performed in channel A and channel B as well as in
the manual and auto channels.
c a AVR Switching between master/slave channel
c b Switch the AVR to constant current(manually operated).
c c Another switchover should be carried out in the constant current mode to
switch the operation of the AVR between the operating channel and the
spare one to return the AVR to the former mode.
c d Return the AVR to the auto mode.
The output of AVR before switchover and the value after switchover
should not exceed 0.5. If the switchovers have been finished smoothly,
all of the spare circuits can be regarded as normal. However, if an
distinct change has been brought by the switchover, the cause should be
found out.
Note that the current regulation channel is not capable of tracing the
voltage regulating current under the extreme working condition. Thus,
the channel should be switched to auto mode when the testing is
completed. Since the limiter can not perform its function in the mode of
constant current, diligent monitor is required for the motor operation.
Annual Maintenance
The maintenance for the excitation equipment should be finished during the
annual minus overhaul of the unit when the whole unit is shut down.
a
Excitation Transformer
External inspection involves the inspections for contaminants and abnormal
noises. Note that the external should be cleaned with a piece of dry cloth or a
vacuum cleaner or compressed air (low pressure) but no solutions should be
Page 39 of 326
used.
b
Rectifier
b.a The rectifier fans should be inspected for the existence of contaminants
and abnormal noises. The abnormal fans should be exchanged because
no lube oil can be supplied into them. In addition, the cooling fans
installed in the fan casing should be exchanged after 24000 hours
operation.
b.b Inspections are needed for the air strainer installed in the vent gate of the
rectifier door. If too much dust has deposited on the strainer, the panel
ventilation and heat radiation would be affected, as a result, the strainer
should be cleaned or exchanged.
b.c Inspections should be conducted on the radiator for fouls which should
be cleaned with a brush, a vacuum cleaner or compressed air (low
pressure) but no solutions should be used.
b.d Inspect the current distribution of the parallel rectifiers. Several groups of
data should be sampled before this inspection for analytical purpose. If
the current distribution severely fluctuates, detailed inspections should
be conducted on the bridges with abnormally decreased or increased
current output.
b.e Inspect the conduction of the thyristor bridge. Each bridge should be
connected with a low resistor for the small current ring breaking test
during which the oscillograph should be used to observe if the D.C.
output waveform is regular and if the waveform can change stably during
the regulation.
b.f Check if the load disconnector on AC and DC side of rectifier bridge is
loosen or disconnected because of vibration or fatigue.
Page 40 of 326
AVR
External Inspection
d.a
d.b
d.c
Inspect to see if the wires have loosened and if the insulator is damaged.
d.d
d.e
1.7
1.8
Number
Equipment
Model
specification
and Unit
Quantity
Manufacturer
Generator
1.1
Generator
brush box
1.2
Generator
electric brush
Shanghai
morgan
or
German Suker
1.3
Generator
bearing bush
Dongfang
electrical
1.4
Stabilization
Remark
Based on
technical
agreement
Page 41 of 326
Dongfang
electrical
Dongfang
bearing bush
electrical
1.5
Out-going
bushing
1.6
Bearing
sealing
insulation
parts
1.7
Hydrogen
cooler
Dongfang
electrical
Deyang
1.8
Sealing parts
(including
rubber sealing
parts)
Dongfang
electrical
Deyang
1.9
Stator
insulation
water conduit
Dongfang
electrical
Deyang
1.10
Stator water
joint thermal
detection
components
1.11
Paddle
type
fan
blade
(each end)
1.12
Water
inner
cooling stator
insulation
detector
1.13
Protection ring
Excitation
system
2.1
Thyristor
components
2.2
Fast fuse
oil
Dongfang
electrical
Deyang
Dongfang
electrical
Deyang
China
18Mn18Cr
Japan/Germa
n
Based on
technical
agreement
Switzerland
ABB
Page 42 of 326
2.3
Dedicated
software
Set
2.4
Excitation
transformer
HV CT
2.5
Excitation
transformer
LV CT
2.6
Instruments,
buttons
and
indication
lamps (10% of
total amount,
at least one
each
specification)
2.7
24V Switch
power
2.8
Rectifier
cooling fan
German RS
2.9
Fast fuse
Xian
2.10
Control circuit
fuse (twice of
total amount
each
specification)
Set
Schneider
2.1
Equipment overview
2.1.1
2.1.1.1
Main Transformer #1
Model
SFPZ10-370000/150TH
Page 43 of 326
Main Transformer #2
SFPZ10-370000/150TH
Rated capacity
370000/370000
Rated voltage
15081.25%/20
Rated frequency
50
Connection type
YNd1
Phase number
No-load current
0.248
0.200
No-load loss
172.49
164.69
698.11
699.52
Impedance voltage
13.93
13.96
Cooling mode
Cooler quantity
Weight
of
transformer
the 181.8
181.8
Oil weight
65
65
Total weight
293.3
293.3
Upper
weight
oil
Factory
number
tank 27
27
serial 200812127
200903016
Production date
No.21st, 2009
Mar.5th, 2009
KKS Code
10BAT01
20BAT01
Manufacturer
Shandong electrical equipment company
2.1.1.2
High voltage
Low voltage
Page 44 of 326
2.1.2
Switch
position
Current
165000
1294.7
163125
1309.5
161250
1324.8
159375
1340.4
157500
1356.3
155625
1372.7
153750
1389.4
151875
1406.5
150000
1424.1
10
148125
1442.2
11
146250
1460.6
12
144375
1479.6
13
142500
1499.1
14
140625
1519.1
15
138750
1539.6
16
136875
1560.7
17
135000
1582.4
Voltage
Voltage
Current
20000
10681
UAT #1
Model
SFF10-40000/20TH
Rated capacity
40000/25000-25000
Rated voltage
2022.5%/6.3-6.3
Rated frequency
50
Phase number
Connection type
Dyn11-yn11
Page 45 of 326
UAT #2
No-load current
0.152
0.099
No-load loss
25.6
22.04
160.67
153.5
KW
Short circuit loss
Impedance
voltage
Highlow1+low2
High
91.6(118.9)
low2(low2)
89.7(115.4)
Low1-low2
164.3
157.3
High1-low2
6.88
6.92
High
16.16(16.05)
low1(low2)
16.11(16.29)
Low1-low2
37.11
38.88
Cooling mode
ONAF
No air capacity
28000
Weight of transformer
38.8
Oil weight
14.2
Total weight
63.1
5.5
200811119
200903017
Production date
KKS Code
10BBT01
20BBT01
Manufacturer
2.1.3
2.1.3.1
Equipment
SST
Model
SFFZ10-40000/154TH
Rated capacity
40000/25000-25000
Rated voltage
15481.25%/6.3-6.3
Rated frequency
50
Page 46 of 326
Phase number
Connection type
Ynyno-yno+d
No-load current
0.135
No-load loss
30.254
KW
Short
loss
circuit
%
Impedance
voltage
Highlow1+low2
153.74
Highlow1(low2)
Low1-low2
Highlow1+low2
8.92
Highlow1(low2)
16.93(17.10)
Low1-low2
35.01
Cooling mode
ONAN/ONAF
Transformer weight
39.0
Oil weight
33.4
Total weight
100
9.4
200811122
Production number
KKS Code
00BCT01
Manufacturer
2.1.3.2
High voltage
Switch
position
Voltage
169400
Page 47 of 326
167475
165550
163625
161700
159775
157850
155925
154000
10
152075
11
150150
12
148225
13
146300
14
144375
15
142450
16
140525
17
138600
Low voltage
Voltage
Current
6300-6300
2291.1-2291.1
2.1.4
Low voltage auxiliary dry type transformer (three phase epoxy molded type)
Equipment
Unit
transform
er
ESP
transform
er
Commo
n
transfor
mer
Water
treatment
and
chemical
transformer
Circulatio
n water
transform
er
Coal
handling
transform
er
Illuminati
on
transform
er
Quantity
KKS Code
10BFT01,
10BFT04,
10BHT03
,
10BFT
03, 20B
10BFT02,
Page 48 of 326
20BFT01,
10BFT05
20BFT02,
20BFT04,
20BHT03
20BFT05
Model
SCB9-2000/6.3
SCB9-2
500/6.3
SCB9-1600/
6.3
SCB9-630/6.3
Rated capacity
2000
2500
1600
630
10%
8%
4.5%
Rated current
Rated voltage
6.32x2.5%/0.4kV
Rated
frequency
50
Commection
type code
Dyn11
Short
circuit 8%
impedance
Load loss
No-load loss
No-load current
Short
time
frequency
withstand
voltage
Surge impact
withstand
voltage
Insulation level
Cooling mode
Natural cooling
Protection level
Neutral
point Direct earthing
operation mode
Temperature
rise limit
Intelligent
temperature
Page 49 of 326
FT03
and
humidity
controller
Manufacturer
2.2
Maintenance Period And Items Of Main Transformer And High Voltage Auxiliary
Transformer
2.2.1
Maintenance period
2.2.1.1
Overhaul period
1 After the transformer was put into operation, within 5 years, we should suspend
the shell (or transformer proper) for check or overhaul. This is because after a period
of operation, the shrink of insulating pieces and loosen of fasteners will forms some
defects that needs check and overhaul in time. Later, the check and overhaul period
like this type can been 10year. Because the transformer will have further insulation
aging, shrink and loosen, especially the transformer will suffer the shock of overvoltage and over-current for many times.
2 If the abnormal phenomenon was found in the transformer during normal
operation or the internal failure was confirmed through test, we should carry out the
overhaul ahead of schedule.
3 When the transformer bears outlet short-circuit, we should consider overhauling it
ahead of schedule.
2.2.1.2
Repair period
1
2.2.2
Maintenance items
2.2.2.1
Overhaul items
1
4 Maintenance of iron core, core bolts, and yoke frame, cross bolt and grounding
blade.
5 Maintenance of oil tank and accessories, including: sleeve, oil tank9including
silicon rubber vesicle and diaphragm) pressure release valve, and absorber etc.
6 Replace the entire sealing silica rubber layer and test the leakage of the
configuration.
7 Check and test of gas relay, protect devices, temperature measuring elements
and operation control panel.
8 Maintenance of cooler, oil pump, motor of fan, oil flow relay, valves, pipes, oil
purifier.
Page 50 of 326
Repair items.
1
3 Discharge the oil mire in the dirt collector of oil tank, check the oil level gauge,
and add oil to sleeve, transformer proper and on-load tap changer if necessary.
4
Check the entire sealing rubber pad, dispose the oil leakage.
6 Check and replace of sleeve sealing and the top connecting cap. Check and
clean of porcelain.
7 Maintenance and test of various protective devices, measuring devices and
operation control panel.
8
2.2.3.1
2.2.3.2
Compile the overhaul engineering technical, organize the measures and plan.
1Organization of personnel and work dividing.
2Verify the maintenance items and establish construction schedule.
3 The construction precept of special items, the technical measures to insure the
safety and quality of construction, fireproofing measures on site.
4List of main construct tools, equipments and main material.
5Draw the necessary construction sketch and blue print.
6 Prepare the technical record forms, ascertain the drawings of spare parts which
should be draw and check.
7Prepare the material for overhaul.
Page 51 of 326
2.2.3.3
2.2.3.4
2.2.4
2.2.4.1
2.2.4.1.1
Page 52 of 326
We should check the oil valve position of cooler, oil purifier and gas relay.
6) Discharge the air from the air vent on the sleeve rising seat, upper hole cover,
cooler and oil purifier top.
7) When we dismantle the operation rod of no-load tap changer, we should
remember the position of tap changer and make a mark, we should put the on-load
tap changer into settled position.
8)
Hoist
1 We should dismantle the components which was connected to the transformer
and will affect the hoist.
2 Choose the suitable hoist tools, steel line harness and the hoist ring according to
the weight of transformer.
3) We should suspend the steel line on the hoist device of transformer, when we
start to strengthen the steel line we should recheck the suspend and colligate
conditions, after confirm we can continue to hoist.
4) When we suspend the transformer proper, the angle between lines should not
bigger than 600, otherwise the special sleeve and adjusting rope should be used to
Page 53 of 326
maintain the balance the transformer proper. The transformer proper can not hit the
box wall during hoist.
5)
we should tie the rope on the four corners and support it to maintain the balance.
6) The rise and fall speed can not be too fast during hoist, and we should master the
barycenter to avoid incline.
7) When we set the transformer, we should choose the location first, put the layers
and then set down the transformer slowly.
8) When we revert the transformer, we should cover the seal rubber layer on the box
edge and fix it with Ushape clip.
9) When we revert the transformer, we should point the transformer proper at the
position, and set down the transformer slowly, pay attentions to the distance between
transformer proper and box wall to avoid damage.
10) When the transformer proper approached the box edge, we should align the bolt
holes, screw the bolts and take out U type clamp, preventing the deformation of
sealing gaskets, when the transformer proper at its proper position we can tighten the
bolts symmetrically and evenly.
11) When we hang and assemble the bushing, its gradient should be equals to the
obliquity of bushing flange and oil tank flange, and tie it up with rope to avoid hit and
overturn.
12) The hoist work should be divided unambiguous, and sent someone to send
command, and have the uniform signal.
13) When the auto car crane was adopted, we should pay attention to the promote
angle of crane arm, the distance between gyre angle and the nearby electrified
equipments during hoist, sent someone to supervise is necessary.
14) During check process, we should not keep the transformer proper in the air for a
long time, and we should put the transformer proper reposefully during check.
15We should not put the transformer core in the air for a long time, otherwise the
vacuum zing damp proofing measures should be taken.
2.2.4.2
2.2.4.2.1
Page 54 of 326
which has no relationship with the work, and should wear the special clothes and soft
bottom shoe, and wears the clean gloves, to touch the winding and insulation layers
with hands is not allowed.
5We should maintain the cleanness of oil tank bottom, and there should not have
impurities.
6 For the forced oil cooling windings, we should check the on the lower clamp,
whether the connection is reliable or not, whether the sealing is good or not, whether
the outlet line position on the insulation panel is sealed or not.
2.2.4.2.2
2.2.4.2.3
2.2.4.2.4
Page 55 of 326
requirements or not.
3 To check whether the insulation frame has loosen, crack and displacement, and
check the fix condition of down lead on the insulation frame.
4 Check the insulation distance between down lead and every parts.
5 Check whether the seal of sleeve cap is good or not, and check whether the
connection between sleeve and down lead is fixed or not.
2.2.4.2.5
2.2.4.3
2.2.4.3.1
of
3Replace the gasket of every part, maintain the butterfly valve. And get ready for
general assemble.
4 Clean the oil dirt and rust on the cooling oil pipe two sides, paint the anti-rust
lacquer and anti-corrosion surface lacquer.
C
Page 56 of 326
2.2.4.3.3
2)
3)
4)
5)
2) Screw off the localizing bolts on the upper part, turn the operation handle, to
check whether the dynamic contactor is flexible or not, whether the indicating position
of upper part is consistent or not.
3) To check whether the dynamic and static contactor are contacted well or not,
whether the condition of contactor surface is good or not.
4) To check whether the contactor tapping line is tighten or not, and whether the line
was loosen or not.
5)
To check whether the condition of tap changer insulating pieces is good or not.
6) Before and after dismantle and assemble the indicating position should be
consistent we can not cross-over the three phase handle and operation mechanism.
7) Check whether the contact of insulation operation rod U shape stick is good or
not.
8) If we found the switch insulation was affected with damp or was uncovered in the
air with a long time, we should dry it.
2.2.4.3.4
Page 57 of 326
3)
Sample the oil for assay, if the oil is unqualified we should change it.
4)
5) Check whether the fasteners of breaker is loosen or not, whether the main spring
and restore spring claw and clip of fast speed mechanism is deformed or ruptured or
not, whether there is some damage on intertexture soft connection of every contactor,
the burnt degree dynamic and static contactor, whether the transition resistance flat
line was broken and its resistance value is consistent with the nameplate or not,
measuring the transformer program of relative contact resistance and dynamic and
static contactor.
6)
2.2.4.3.5
Discharge the oil in the oil tank and clean the inside of oil tank.
2)
3) Rub-up the external wall of rubber chamber with clean cloth, put the rubber
chamber into the oil tank from man hole.
4) Hang the rubber chamber on the hooks by nylon rope, connect the out leading
hole, and then tighten the man hole flange.
2.2.4.3.6
Maintenance of absorber.
1) Pour out the inside moisture absorption substance, and check the separating
cover is complete, and clean it.
2.2.4.3.7
2)
3)
4)
Fill the oil to a proper level, and make the oil form a oil film.
2.2.4.3.8
2.2.4.3.9
2)
2.2.4.3.10
2)
Clean it
3)
Page 58 of 326
1) Check the completion, flexible and sealing of rotary shaft, damper, replace the
seal gasket.
2) The oil valve should be dismantled and be maintained disassembly, skive and
replace the seal gland.
3) Carry out the comprehensive check to the air(oil) discharge valve and replace the
seal gasket.
2.2.4.3.11
1) To check whether the rotation of the fan is agile or not, whether the fan shield is
be scraped or not.
2)
3)
4)
5)
6)
1) Open the stopping gasket, screw off the cover type nuts, drop out the stopping
gasket. Use the special tools(triangle claw) to remove the blade impeller from the
shaft, and remove the key and wimble sheath and keep them at the same time.
2) Check the riveting conditions between blade impeller and wheel hub, If the
riveting was loosen we can use a iron hammer to rivet it.
3) Put the blade impeller on a flat, to check the install angle of blades should be
consistent, otherwise we should regulate it.
4) Dismantle the motor shield, and screw off the fixing bolts on the rear end shield,
take out the rear end shield.
5) To check whether there is some damage on the rear end shield, clean the
lubricating grease in the bearing chamber, to measuring the bearing chamber with
inner diameter caliper micrometer is bigger 0.025mm(diameter), if the corrosion is too
serious we should replace it with a new one.
2.2.4.4
2.2.4.4.1
General assemble
1) Before assemble, we should clean the radiator(cooler), oil storage tank, antiexplosion devices(safety air duct), oil pipe, rising seat without CT, sleeve and all the
parts and components and configurations, use the eligible transformer oil to wash the
parts and components and configurations which directly contacted with transformer.
And we should clean the auxiliary oil and water pipe lines of transformer, and make
the record.
2) Before we assemble the last section oil storage tank , we should clean the water
pipeline should be cleaned, and make record.
3)
For the parts and components with install indicator, we should assemble it
Page 59 of 326
We can not draw, wrest and bend the transformer download root.
5) Before we assemble the sleeve we must check whether the non-excitation tap
changer connection rod is inserted in the shaft of tap charger.
6) When we assemble the configurations, we should do it according to the
installation and use specification of manufacturer.
7) We should localize and seal the upper localization parts of oil tank top according
to the external dimension and technical specification.
8) We should replace all the seal gaskets with new one, the dimension meets the
requirements, and when it bearings the forces the compression is even, the
compression volume should better be 2/3.
9)
The vacuum oil injection technique should be use for filling the transformer.
Vacuumize the cooler with the main body at the same time.
1) Increase the vacuum degree evenly in one hour, when it reaches to 8 104Pa,
maintain it for one hour, if no abnormal conditions was found, and then increase the
vacuum degree to 9.75104Pa gradually, and maintain it for one hour, check whether
the oil tank has deformation and abnormal conditions or not. If no abnormal
conditions were found, we can inject oil to the transformer under vacuum condition,
the oil should be degassed and dehydrated through vacuum oil filter, the oil filter and
the pipelines should be sealed. When we injecting oil to the transformer we should
maintain the vacuum degree at 9.751046.7102Pa, when the oil level reaches to
200mm of top cover, we stop to inject oil to the transformer, if the oil injecting time is
longer than 6hours, maintain this vacuum degree 6 hours, and the vacuum can be
broken.
2) Open the air release valve at the top of the oil storage tank, inject oil from the
oiling pipe of oil storage tank until the oil is overflowed from the air release valve, and
tighten the air release valve, then discharge the oil from oiling pipe, and make the oil
level a little bit higher than requested level, and then install the absorber.
3) From the end of secondary oil injection, we can put the transformer for 24 hours,
during this period, we should release the air a several times(and start up the oil
submerged pump), to check whether there is oil leakage and the oil level decrease
phenomenon.
2.3
2.3.1
2.3.1.1
2.3.1.1.1
Maintenance period of dry type transformer is along with the overhaul and repair
period of unit.
2.3.1.1.2
2.3.1.2
Check items.
Page 60 of 326
1)
2)
3)
4)
5)
6)
7)
8)
9)
Clean the dust, dirt and moisture inside and outside of transformer.
2)
3)
4)
2.3.2
2.3.2.1
2.3.2.2
2)
3) Compile the technical measures which can insure the construction safety and
quality. And the firefighting measures on site.
4)
5)
6) Prepare the technical record forms, ascertain the drawings of spare parts which
should be draw and check.
7)
2.3.2.3
Page 61 of 326
Security works on the site, assign some one to guard the site.
Whether the bolts of transformer was loosen, whether there is abnormal sound.
8Is there any loosen and partial overheat phenomenon on the electric connection
part of sleeve and connection board, is there any broken part on the porcelain, and
then clean the dust and dirt on the ferrule.
9) Whether the cover board of winding is pressed tightly on the winding, is there any
loosen phenomenon on the mat pad.
10) Whether the transformer was grounded reliably.
11) measuring the insulation resistance of winding.
12) There is no holes and gaps that an let the small animals in and do some harm to
the transformer.
2.3.3
2.3.3.1
Carry out the maintenance according to the check contents before maintenance
2.3.3.2
We should clean the dismantled bolts and accessories by clean agent, repair and
replace it if any damages were found, and then keep it properly to avoid get lost and
damage.
2.3.3.3
Dismantle the small instruments and sleeves first and then dismantle the big iron
parts, during dismantle, and the sequence of assemble is contrary.
2.3.3.4
Check the integrality of transformer proper, whether there is any defects(for example
overheat, arc trace, loosen, deformation on winding, the color of tap was changed)
Page 62 of 326
exists. Check the reason and maintain the abnormal conditions, make record at the
same time.
2.3.3.5
Check the interphase isolating board and surround screen, to check whether there is
broken, color change, deformation and arc-discharge phenomenon, if any abnormal
was found, we should take the relevant measures.
2.3.3.6
Whether the winding surface is clean, is there any damage on the insulation.
2.3.3.7
Check whether there is any displacement or loosen phenomenon on the winding pad.
2.3.3.8
To check whether the ventilation duct of winding was blocked by oil dirt or the other
substance, if necessary we can use soft brush(calico or foam) to clean it.
2.3.3.9
To check the surface of iron core is flat or nor, whether there is interslices short-circuit
or color change, and arc-discharge burnt traces, and loosen phenomenon exists,
whether there is accumulated oil dirt on the top of upper iron yoke and the bottom of
lower iron yoke. We can use calico or foam to clean it. If the segments has cocked or
unregulated parts, we can beat it by a wooden or copper hammer.
2.3.3.10
Check the tightness and insulation conditions of iron core, upper and lower clamp,
square iron, winding end finger(including pressed iron)
2.3.3.11
checks the air duct across the iron core and clamp. The pad of air duct should not
have off and blocked phenomenon.
2.3.3.12
Checks the contact and insulating conditions of iron core grounding patch.
2.3.3.13
check the insulation tie condition of down lead and, to check whether there is
deformation, frangibility, broken, phenomenon, and whether the wire of down lead
was broken, the weld on down lead and down lead contactor is good or not, and
whether there is some overheat phenomenon.
2.3.3.14
To check whether the down lead was connected well, is there any overheat
phenomenon. Whether the insulation distance from down to every part and the fix
condition of down lead meets the requirements.
2.3.3.15
To check whether the insulation frame has loosen, crack and displacement, and
check the fix condition of down lead on the insulation frame.
2.3.3.16
Checks the insulation distance between down lead and every parts.
2.3.3.17
Use the electric blower or compressed air to blow the inside and outside or
transformer until there is no dust blow out; the flow speed of air can not be too fast to
avoid to blow the condensate to transformer. We can use clean agent to clean the
naked part of down leads, sleeve, connection board, and shell.
2.3.3.18
2.3.3.19
2.4
Page 63 of 326
calculate and hand over the finish and acceptance report, and invite the relevant
departments to organize relevant unit, maintenance department, HV test, oil assay,
relay protection, operation and measure units to accept the site.
2.4.1
2.4.1.1
Maintenance record.
Check items
Techinic requirements
Hang
the
(1)the time for transformer
shield(core)
proper uncovered in the air:
and check
when the 65, is 16 hours,
when the relative humidity
is lower than 75 ,
is12hours
Disposals
Checke
d by
of
Ambient temperature:
Page 64 of 326
mechanism.
(7) No heating and off weld
phenomenon of conductor
taps.
(8) The surface is clean and
without oil dirt.
Down lead
Page 65 of 326
Insulation
frame
Insulation resistance M
Insulation resistance M
Insulation resistance M
(2)There
is
no
inter- Insulation resistance M
segments
short
circuit,
Insulation resistance M
heat, and no color change
Insulation resistance M
and burnt trace.
(3) The insulation lacquer
does not fall off
(4)Insulation to ground is
perfect, 200M under
normal temperature.
(5) Insulation between iron
core and square iron
(6) Insulation between iron
core and clamp
(7) Insulation between iron
core and drawstring
(8) Insulation between iron
core and core bolt.
(9) The oil duct of iron core
and clamp was unblocked,
the oil duct pad is in good
order.
(10) The insulation of iron
core and the positioning pin
is perfect.
(11) The matted wood of
iron core feet was fixed and
Page 66 of 326
have no loosen.
(12) There is no heating
trace
on
grounding
segments, and was fixed
good.
(13) Grounding of iron core
electric field shield out
going line is perfect
(14) The iron core surface is
clean, without oil dirt and
sundries.
Cover board (1) The cover board does
and cross bolt not
have
serious
eccentricity
(2) The insulation of steel
cover board and cross bolt
is good, and was been well
connected with clamp by
grounding segment.
(3) The cross bolt and
metal seat is tighten and
without suspend.
(4) The lock bolt of cross
bolt is tighten.
Non-excitation
tap changer,
Page 67 of 326
Page 68 of 326
locknuts
are
Page 69 of 326
reliable.
(6) The seal of box is good.
(7) The insulation of control
circuit is good.
Commissionin (1) The action cycle meets
g
after the
specification
of
assemble.
manufacturer.
(2) The measured DC
resistance of transformer
three phase positions meets
the standard.
Oil
tank(including
sleeve
and
rising seat)
Page 70 of 326
Pressure
release
valve(safety
gas duct)
Page 71 of 326
Oil purifier
level
at
Gas relay
good
without
Flow speed
ms
Insulation resistance M
Page 72 of 326
measuring
elements
Valves
piston
Cooling
devices
(5) Painting.
Oil pump
According to maintenance
technique of oil pump.
Fans
According to maintenance
technique of fans
Sleeve
(1)
The
external
of
porcelain should be clean
and without crack, broken
and arc-discharging trace.
(2) Replace the changeable
rubber
gasket
of
oil
discharge hole, it should be
Whether
it
was
sealed well and without
disassembled dry or not.
leakage.
Attach the construction
(3) Oil level of capacitor
record and test report.
sleeve and oil filled sleeve
should
be
normal,
if
necessary add oil or
replace oil.
Page 73 of 326
Oil treatment
(2)
The
oil
type,
predigestion of oil quality,
pressure
withstand,
moisture and chromatogram
analysis of injected oil
should
meets
the
requirements in GB2536
90 <transformer oil>
Overhaul
preventive test
HV insulation test report, predigestion and chromatogram test list of oil, the calibrating
report of thermometer, test report of gas relay and transformers.
2.4.2
2.4.2.1
There are no defects and oil dirt on transformer proper, cooler and all the
accessories.
2.4.2.2
2.4.2.3
2.4.2.4
2.4.2.5
The oil valves on the oil systems such as oil storage tank, cooler and oil purifier was
at open positon.
2.4.2.6
Ground the ground small sleeve of HV sleeve, the seal capacity of the cap on the top
Page 74 of 326
The oil level of oil storage tank and oil filled sleeve of transformer is normal, there is
no gas in the gas collection box of diaphragm type oil storage tank, the oil
conservator level of on-load tap changer is normal.
2.4.2.8
2.4.2.9
The moisture absorber in the absorber is enough, and does not been affected with
damp, the oil seal is good, and can performance the normal absorb function.
2.4.2.10
The position of no-load tap changer should meet the operation requirements, the
action of on-loading operation is correct, the action of interlock device is correct, the
tapping position of control panel, operation mechanism box and top cover are
consistent.
2.4.2.11
2.4.2.12
The commissioning of cooling device is normal, start-up all the submerged oil pump
to circulating the forced oil device for a long time and discharge the air for several
times.
2.4.2.13
Carry out the automatic operation test of standby cooling device, and carry out the
failure shut down test of operating cooler.
2.4.2.14
After the commissioning and calibrating the action of relay protection device is
correct.
2.4.3
2.4.3.1
All he protection device should be put into operation during the operation of
transformer, the gas relay of transformer proper should be put into operation, the
heavy gas should be at outlet trip position.
2.4.3.2
The impact test under rated voltage(3 times for replace the winding, and 2 times for
overhaul), should not have abnormal conditions, the excitation flow can not cause the
action of protection devices.
2.4.3.3
After the first energize the maintained time should not be less than 10 minutes, and
the transformer should not have abnormal conditions.
2.4.3.4
After energize, check all the weld line and contact surface of transformer and cooler,
there should not have oil leakage, and the transformer should not have abnormal
oscillation and arc discharge sound.
2.4.3.5
Analyze and compare the chromatogram datum of oil before and after operation, the
chromatogram datum of oil before and after operation should not have obvious
changes.
2.5
Spare parts
Not available now
3.1
3.1.1
Page 75 of 326
Equipment
Model
(KW)
(KV)
Capacit
y
Voltag
e
2150
990
2+2
FD
motor
fan YKK450-4THW
500
1490
2+2
PA
motor
fan YKK630-4THW
1700
1490
2+2
Medium
YHP560-6
speed coal
pulverizer
motor
520
982
5+5
Condensate YLKK500-4
pump motor
1000
1500
2+2
CWP motor
1900
2+2
Closed
KK4002-4TH
circulation
cooling
water pump
motor
355
2+2
3300
Instrument
air
compressor
motor
200
Fire fighting
pump motor
250
Sea water
booster
pump motor
160
2+2
Coal
crusher
motor
550
Y355-2
Curren
t
Page 76 of 326
Rotar
y
speed
1493
Wirin
g
Insulatio
n level
Quantit
y
1+1
C-01A belt
conveyor
motor
250
C-04A belt
conveyor
motor
200
C-05A belt
conveyor
400
C-03A belt
conveyor
250
C-02A belt
conveyor
motor
160
C-07A belt
conveyor
motor
160
3.1.2
Equipment
Capacity
Voltage
Current
Wiring
Rotary
speed
Quantity
110
0.38
Condenser
water
chamber
vacuum
pump motor
7.5
0.38
1+1
Fiber
ball 1LA7
conveying
pump motor
0.38
2+2
Condensat
Y160M1-2
e
pump
make-up
water pump
11
0.38
1+1
Y132M-4
500
Insulation
level
Page 77 of 326
2+2
Startup
water
feeding
pump motor
Y250M-2
55
0.38
1+1
110
0.38
2+2
0.75
0.38
2+2
18.5
0.38
2+2
18.5
0.38
2+2
19
0.38
Jacking
YB250M-4
device antiexplosion
motor
55
0.38
1+1
Startup
boiler
house FD
fan motor
110
0.38
2920
Page 78 of 326
2+2
Turning
gear motor
22
0.38
730
Electric
YB280S-2centrifugal
TH
oil supply
pump antiexplosion
motor
75
0.38
Electric
YB160L-2centrifugal
TH
oil
unloading
pump antiexplosion
motor
13.6
0.38
Truck
YB160M-4electric oil TH
unloading
pump antiexplosion
motor
15
0.38
ID
fan
cooling fan
motor
1+1
4+4
110
0.38
Electronic
SA77 /TJ
weighing
coal feeder
motor
2.2
0.38
132
0.38
55
0.38
1+1
Main
tank
fume
0.38
2+2
oil YB11ZM-2
oil
960
2+2
5+5
1480
Page 79 of 326
2+2
exhaust fan
motor
AC
oil Y132M2-6
pump
conveying
pump motor
5.5
0.38
2+2
Electronic
SA57 /TJ
weighing
coal feeder
cleaning
chain motor
0.37
0.38
5+5
132
0.38
Intermittent
blowdown
water pump
motor
15
0.38
2+2
3.1.3
Equipment
Main
equipment
DC lube oil
pump
Rated
power
Rated
voltage
17
220
7.5
220
Rated
current
Rated
rotary
speed
Air
side
sealing oil
pump
Feed pump Z2-42
turbine oil
supply
device DC
emergency
oil
pump
Page 80 of 326
Excitation
mode
Rated
excitation
current
Quantity
motor
3.2
3.2.1
Maintenance period
3.2.1.1
High voltage motor should be overhauled at the same time as unit overhaul, generally
the overhaul period is three years, and repair period is 2 times a year
3.2.1.2
For the high voltage motor which installed in the clear areas in the room or the full
closed high voltage motor, its maintenance period can be shorten or prolonged
according to the actual operation hours and preventive insulation test conditions
every.
3.2.1.3
If the overhaul is carries out to the unit, the repair of high voltage is unnecessary to
carries out
3.2.1.4
If the problem is found in operation and preventive test and repair, it should be
changed into overhaul.
3.2.2
Maintenance items
3.2.2.1
Repair items
3.2.2.1.1
The high voltage motor should be blow out and flushed; the general check should be
carries out.
3.2.2.1.2
Check and deal with the partial insulation of the windings, and carries out the
mending
works. Fix and bind up the winding and lead partially.
3.2.2.1.3
Measure the gas gap between the stator and rotor (when the condition is allowable)
3.2.2.1.4
Check the bearings and bearing house, cleaning the bearings, check the bearings, or
change the lubricating oil if necessary.
3.2.2.1.5
3.2.2.1.6
3.2.2.1.7
3.2.2.1.8
for the rolling bearings, the insulation of the bearing block and soleplate.
3.2.2.2
Overhaul items
3.2.2.2.1
3.2.2.2.2
Check the motor disassembly, clearing and clean the motor stator, rotor, frame,
undercarriage and junction box, cleanout the oil dirt and accumulated dust.
3.2.2.2.3
Check and clean the front and rear bearings, change the lubricating oil, replace the
bearings is necessary.
Page 81 of 326
3.2.2.2.4
Rescrape the bearing bush, repair the bearing bush and mend the bearing bush,
replace the insulation bushing of the sliding bearing if necessary.(this item should be
carries out by the boiler ,steam turbine maintenance staff)
3.2.2.2.5
Check the stator winding, replace the winding partially, strengthen and mend winding
insulation. Dispose and replace the loosen slot wedge, strengthen the insulation of
the winding end and leading wires, over lines. Reinforce and replace the colligation
line of winding ends.
3.2.2.2.6
Check or replace rotor squirrel cage failure such as bar broken, loosen, sealing-off
and so on, reinforce and welding it.
3.2.2.2.7
If the squirrel cage bar of the motor rotor has changed or welded, the dynamic
balance test should be carries out.
3.2.2.2.8
If the winding was totally aged, we should contact with the manufacturer to replace
the whole windings.
3.2.2.2.9
3.2.2.2.10
3.2.2.2.11
3.3
3.3.1
3.3.1.1
Prepare the needed equipments and spare parts for motor maintenance
3.3.1.2
Prepare all the power off permit for the equipment exit the standby condition, and
through site check and verified that the start up devices of this equipment is already
exit the standby condition. Breaker and the disconnecting link is already open, and
carries out short-circuit grounding measurements, and hang the alarm plate of
working, forbid to connecting, verified the safety measurements is complete; then the
maintenance group can enter the site.
3.3.1.3
Before work, the measuring work of initial data should carries out, and makes
records.
3.3.1.4
To dismantle the inlet power cable of the motor, the phase should be marked with
color; three phases short-circuit and ground the connection link.
3.3.1.5
3.3.1.6
3.3.1.7
Prepare the tool for dismantle the bearings, and the equipments and material to dry
and heating the motor.
Page 82 of 326
3.3.2
The maintenance items of the high voltage motor and working process and the
requirements
3.3.2.1
3.3.2.1.1
Cleanout the motor surface. Motor surface should not have dust dirt, oil dirt, and other
dunghills.
3.3.2.1.2
To check that the end shields of motor sides are complete and has no damage, no
crack, and the motor fans has no damage and deformation.
3.3.2.1.3
There is no accumulated dust, loosen inside the junction box and high voltage
connection porcelain bottle, there is overheating phenomenon on connection bolt,
and there is no arc-discharging crack phenomenon exists on HV connection
porcelain.
3.3.2.1.4
When dismantle the inlet cable of the motor, we should avoid damaging the HV
porcelain and the other accessories
3.3.2.2
3.3.2.2.1
3.3.2.2.2
Page 83 of 326
crosstie reposefully. The end shield should be put upwards for check and clean.
3.3.2.2.3
1) For the motor which adopts sliding bearings, before pulling out the rotor the
bushes of the bearings should be dismantle first ,before dismantle the bearing bushes
the gaps between the bearings should be measured and the data should be recorded.
Because this work belongs to mechanical work, so the mechanical stuff should be
contacted for cooperate
2) When the bearing is pulled out, it needs be cleaned and take good care
3) The lower insulation layer of the sliding bearings should be complete and has no
damages, when it is installed again the insulation layer should be put in position
4) Before pulling out the rotor of the motor the gas gap between of stator and rotor
should be measured by feeler
5) The gas gap should be measured at the two sides of the iron core respectively,
before measuring we should make four measure datum marks on the upper, lower,
left and right side of the motor. We should turn the rotor for many times and then we
can educe the data.
6) The asymmetry value of any side of iron core gas gap should not be bigger than
510%. The measured gas gap value differences of iron core should not be bigger
then 15% of the average value
B
1) When we take out the rotor, it should be carries out at the area where the crane
can move, when we take out the rotor of large sized motor, the crane should be 5 ton
at least. We can adopt multi-hanging point and prolonged shaft method to take the
rotor out of the chamber. After dismantle, we should put the rotor on frame or crosstie
for check and clean.
2) In the whole process to pulling out the rotor, a person should command the
group, and take good cooperation with the crane group. Especially to take out the
rotor of large sized motor, properly air gap between rotor and stator should be
maintained to avoid scrape the stator iron core and end winding.
3) Before install the prolonged shaft we should protect the bearing journal.
3.3.2.2.4
1) Iron core of rotor should have no trace of attrition and damage, if the traces are
exists, the reason should be check out and the position of attrition and damage
should be disposed.
Page 84 of 326
2) Rotor iron core should not have loosen phenomenon, if the iron core was loosen,
we should fasten it, or fill it with epoxy
B
The weld points on the rotor squirrel cage bar and end rings should not have changed
color, overheated, loosen, weld cracking and bad contact phenomenon. During the
operation before the maintenance, if the start torque decreased, stator temperature
increases sharply, stator current is higher than normal operation, unit oscillation is
bigger than normal operation, yawp increases, the pointer of three phase ampere
meter has periodical vibration when the unit carries load, the squirrel cage bar should
be checked carefully.
The squirrel cage bar can be checked by different methods
Take out the rotor and observe the squirrel cage bar, and beat every with a small
hammer, if the bar is broken, the noise is big and hoarseness.
4) If we can not affirm the squirrel cage bar failure point, we can adopt the big
current test method. Use one set of big current generator of 220/124 voltage and
capacity of 15---20kVA, connect the secondary voltage to the two sides end rings of
squirrel cage bar, adjusting the secondary voltage between 300---1500A, at this time
rotor surface will produce a magnetic field. then splash the iron powder on the rotor,
and the iron powder will distributed in order and clearly along the direction of the bars,
if some part has little iron powder or has no powder, it shows that the broken bar is
exist.
5) If the broken bars are found, the bar should be taking out, and check whether the
broken bar is caused by mechanical damage or big current burnt the bar. And then
check if the unequal burr or iron core protruding pad are exists in the cage bar slot,
and dispose them in time, and at the same time machining the new eligible bars
according to the original bars dimension and type, and bore the eligible holes on two
sides end rings, make the meld point tidy and even. The end rings should be melded
by the engineer with rich experiences.
6) The squirrel cage bar should be well fixed in the rotor slot; we should press its
upper and lower side on the bottom and notch of the slot. When we replace the
squirrel cage bar, the parallel connection of several conductors shall not be used to
instead one bar. If the bar was loosen in the slot, the can be used to fix it.
7) We should make the welding point of replaced bars smooth and even, after the
bar of rotor was changed, we should carry out the balance test of rotor.
3.3.2.2.5
1) The iron core teeth should be pressed and no loosen phenomenon exists; there
is no red powder and yellow powder on the core surface, no broken blades of the
Page 85 of 326
teeth. And no partial overheat and color-change phenomenon on the surface lacquer.
2) There is no contusion, burr concave and protruding points and burnt short-circuit
conditions on the core.
3) There are no oil dirt and metal substances inside the core.
4) The pressing screw and rod of two sides of the iron core is fixed, and no partial
overheat and crack phenomenon the
5) Ventilation slot is unblocked, and there is no accumulated ash, oil dirt, eye winker
and partial blocked phenomenon.
6) When we check the iron core, we can use a hammer to beat the teeth parts and
teeth board of two sides of the core, if the core was loosen, it will gives out hoarse
sound, and the rust pieces and dust will spurt. If the core relaxation was found, tuck
some mica pieces or insulation layers in the relaxation parts, and fix these parts with
epoxy.
7) If some eye winker such as metal powder or were found inside the core, we
should check out the reason. If the burr and short-circuit points were found, we should
eliminate the burr and chisel out the short-circuit points, and paint the epoxy
insulation lacquer.
8) Use the clear and dry air to blow out the ventilation holes and slots one by one,
until the ventilation holes was unblocked.
B
1) winding coil surface should be clear and has no dirt, the winding coil has no
overheat, deformation and damage phenomenon
2) The connection line and leading line between windings has no deformation, the
interphase distance is even, and has enough creepage distance, the arrangement is
in order.
3) There is no aged, loosen, off and broken line phenomenon occurs on insulation
block and tie of the end, the insulation block is fixed and reliable.
4) The slot wedge should be tight and not broken, if the slot wedge was loosen and
damaged, we must tuck it in or replace it again.
5) We can use the carbon tetrachloride or electrified cleaning agent to clean the
winding surface.
6) If the insulation layers have aged, crack, exuviate and bed phenomenon, we
should check out the reason.
7) If the winding become flexible or the insulation part is damaged, it should be
colligated again.
3.3.2.3
Page 86 of 326
3.3.2.3.1
3.3.2.3.2
Because the coordinative surface of bearing journal will be damaged and the
coordinative intensity will be debased during dismantle the rolling bearings, so the
bearing s can not be dismantled voluntarily, if these following conditions were met
during the maintenance, we should think about to dismantle the rolling bearings:
1) Replace the failure bearings.
2) The normal abrasion of bearing reaches to the allowable value of technical
standard, and we should replace it by a new one.
3) Only after dismantled the bearings the other component can be changed, for
example: change the shaft, and lathe the shaft.
4) The assemble quality of bearing is not good, it need to assemble again.
B
1) When we dismantle the bearings, the force bearing points should be even and
correct. When we dismantle the bearings from the motor shaft, the inside track of the
bearing should bear the even forces. And if we dismantle the bearings from the end
shields bearing housing, the outside track should bear the even forces.
2) We should use special tools to dismantle the bearings.
3) When we span the dismantle tolls, we should make the length of every tension
rod equal, and the distance to main screw should be equal, and the claw should not
Page 87 of 326
be deflexed, and should hook the bearings straightly. in order to protect the center
hole of the rotor shaft end, we can not put the puller on the center hole directly, put a
piece metal board or a rolling ball to protect it.
4) When we tighten the main screw and take out the bearings, the force should be
even. The forces on every hook should be equal. And the actions should be uniform,
and we can not hitch it.
5) During dismantle, do not damage the of the rotor shaft bearing journal.
6)
For the shrink-fit bearings, to use cold dismantle methods is not allowed.
Because if we use this method, not only the dismantle is difficult, but also the
coordinative surface precision was damaged, and the bearing noise was increased,
so the hot dismantle method can be used, the process are
Span the dismantle tolls, and clean out the bearing lubricating grease.
Wrap the rotor shaft surface besides the bearing with asbestos cloth or anti-oil rubber
to avoid the hot oil pour on the surface and the shaft and bearing inside track
expanded in the same time, and its every difficult to dismantle.
Heat the hot oil(wasted transformer oil) to about 110 , and then use oil pot or oil
scoop pour the hot oil on the bearing inside track, it will expands, after expands, the
force between bearing journal and bearing inside track decreased, then we can use
dismantle tools to dismantle the bearings easily.
This operation need several peoples cooperation, wearing the gloves to avoid been
burnt.
C
1) It does not matter whether the bearing is newly use or just dismantled from the
bearing journal, first it should be cleaned and then we can assemble and use it.
2) For a eligible bearing, its rotation should be balance, the rotating speed should be
even, and has no cacophony.
3) The inside and out side surface of the bearings should not have rust spot sand
nicks, bearing rolling ball clamp has not deformation, and the rolling ball proper has
no wear marks.
4) We should choose the lubricating grease of rolling bearing according to the type
standard and use site in table 2. The specified lubricating grease should be used but
not the lubricating oil of any type.
Page 88 of 326
5) If the full closed bearing is adopted, we can not use hot oil to heat it, we can
adopt electric heating method to heat the bearing evenly and then put it inside of the
bearing.
6) According to the actual conditions of the site, we can use the following methods
to clean the rolling bearing.
High pressure steam and high pressure air methods blow it clear and use benzine to
wash it for two times.
If the lubricating oil is already concreted, we can use 105 hot oil to wash it, and
clean it, then use benzine to clean it for two times, this method is convenient and
quick. But we should take the fire fighting safety measures and before we clean the
bearings.(we can use wasted transformer oil as the oil for washing, when boiling the
oil we should sent someone to take care of the oil, and this person can not leaves the
site.)
7If the bearing is not use after clean, we can clean it with clear calico and wrap it
carefully to avoid the dust drops on it.
D Before assemble of the bearings, we should use benzine to clean the bearing
housing, front and rear end shields of the bearing and component and accessories of
the bearing journal. And make sure that there is no damage and burr on the bearing
journal, and after the benzine was volatile we can assemble it.
E before we assemble the bearings, first we should put the inner cover in, and then
use hot oil(wasted transformer oil) heat the bearing to 110maintain this condition
about 58 minutes, after the inner track was expanded use a isolated tool and lifting
the bearing,(we must put the side with letter forth and the side without letters entad )
and put the bearing on the bearing journal quickly, and push it the bearing positions,
after the bearing is cooled and the inner track is fastened, we can carry out the next
works.
F chose and paint the proper lubricating grease in side the bearing lodgement and
in front and rear oil cover of the bearing, generally the oil amount of front and rear
bearing is about 2/3 of the bearing capacity. And then rotate the bearing to make the
redundant grease in the bearing lodgement flow out, scrape the redundant grease,
fasten the front and rear end shields , and waiting for the installation after put the rotor
in position.
3.3.2.3.3
Page 89 of 326
2)Use compressed air about 0.10.3Mpa to blow the dust on motor core and
winding.
3)The sequence of install the motor rotor is contrary to dismantle.
4)When we install the rotor, we should pay attention to maintain the gas
gap distance between rotor stator. And do not damage the stator winding
and winding end coil.
5)If necessary, we should carry out this work with the cooperation of the
crane staff.
3.3.2.3.4
3.3.2.3.5
After the gas gap is regulated to even, fasten the end shield screw symmetrically
Page 90 of 326
3.3.2.4 Dry the HV motor (when the motor was affected with damp)
1) We can use the following methods to dry the HV motor according to the actual
situation if necessary.
2) Stator iron loss heating method, this method is used for the motor at dismantle
situation. The method is, reel some insulated conductor on stator iron core, and
connect 380V AC voltage, heat and dry the motor winding by the vortex loss produce
by stator core.
3) Stator copper loss heating method: this method is used for the motor at
assembled situation. The method is to connect the stator winding with working
connection methods, and then connect the stator winding with 10 15% rated
voltage(three phase working frequency AC voltage), stator voltage reaches to 50
70% of its rated value. Use the copper loss heat of motor winding proper to heat and
dry the motor winding.
4) When the insulation resistance value and absorbptance R60/R15 were
increased and reaches to required value, under the same condition, if this value is
maintained in 5 hours, this process can be stopped.
3.3.3
3.3.4
3.3.4.1
3.3.4.2
Page 91 of 326
3.4.1
3.4.1.1
3.4.1.2
3.4.1.2.1
Page 92 of 326
3.4.1.2.3
1) To avoid the fasteners (small screws, gaskets and bushes) remains in the motor
when we assemble the motor after maintenance, before dismantle the end shield, we
should check whether all the fasteners are complete and put the defects conditions in
the record,
2) Before dismantle the end shields we should dismantle the bearing end shields at
two sides first, we should put the dismantled accessories (small screws, gaskets and
bushes etc.)In the box to avoid been lost.
3) Before we dismantle the end shield, we should mark the end shield of frame two
sides and frame cooperate line with different marks, and then screw off the bolts, and
then jack out the end shield by jack bolt hole until the end shield get off the frame, if
there is no jack bolt hole, and the cooperation of stop surface is not so tight, we can
insert a crowbar in the cooperation line of end shield and frame, beat the end shield
use a hammer, or use a screwdriver or a small crowbar crow the protuberance on the
end shield, and let the end shield off the frame stop surface, if the stop surface
cooperation is too tight, we can take the efficient measures to dismantle the end
shield without any damage, to acts recklessly is not allowed.
4) For the motor with roller bearings as its load end, we should dismantle the nonload end first.
Page 93 of 326
5) The end shield of the large sized motor above 50KW is very heavy, when we
dismantle it, for seek of safety we should use electric pulley; we can not use our
shoulder and hands.
3.4.1.2.4
For check and replace the rolling bearings, please consults dismantle and assemble
method of HV motor bearings.
3.4.1.2.5
3.4.1.2.6
Page 94 of 326
again.
5) For the motor affected by damp, first we should clean it by air, an then put it in the
dry room to dry it and furbish the insulation resistance. If the condition is not allowed,
we can use iodine-tungsten light to heat it.
6)When the stator winding slot wedge was loosen, we should check out the resin, and
we must reinforce it again or replace it.
7) Check and repair the motor iron core.
a) To check whether the stator iron core is pressed tightly, if the iron core was
loosen, we should take measures. For the iron core which used screws to tense it, we
need to tense the screws, tighten the screws evenly and symmetrically, tense the iron
core. If it is just Light partial iron core loosen and end two side loosen, first we should
clean the rust and oil dirt, use benzine or clean agent to clean it and dry. Wedge the
blades into loosen core chips, Wedge mica or insulation layers in, and then paint the
insulation lacquer or fix it with epoxy.
b) To check whether there is partial wear, the color changes to blue because of heat
on stator or not, if the wear and heating phenomenon was found, we should check out
the reason and do some dispose work.
3.4.1.3
Page 95 of 326
bearings. For the notes and quantity to add lubricating oil, we can consult the notes
and quantity of HV motor bearing lubricating oil.
9) When assemble the rotor, we should be careful and do not damage the stator
winding and iron core.
10) After assemble, we should check the insulation resistance of motor again, the
value should be equal with the value before assemble.
3.4.2
3.4.2.1
Before trial running, the maintenance group should put the maintenance tools and
test equipments in order, clean the sanitation and the other eye winkers on the site
and check the following items:
1) The insulation resistance should be eligible; it should not be lower than the value
before maintenance obviously.
2) Connection of the leads of the motor and the cable should be reliable and correct.
3) The fasten conditions of all the motor mechanism parts should be good, and
every screws should be tighten.
4) Hold the shaft end by hand and try to run it, to check if the rotor is balance and
light or not, there should be no abnormal sounds in the bearings and motor.
5) The whole protective circuit, measuring circuit, control circuit and signal circuit
should be complete, and to check that it is in normal condition.
3.4.2.2
Prepare the trial running permit, after the operation staff checked it is eligible; we can
energize it and do the trial running.
3.4.2.3
3.5
Maintenance of DC motor.
3.5.1
3.5.1.1
Maintenance period of DC motor Overhaul with the unit,, or overhaul under failure
Page 96 of 326
condition and special conditions, arrange 12 check and repair works every year.
3.5.1.2
3.5.1.3
3.5.2
3.5.2.1
3.5.2.1.1
3.5.2.1.2
Page 97 of 326
2Take out the carbon brush from brush holder, if we need to dismantle the electric
brushes from the frame, we should number the brush, and then dismantle the
connection wire from brush rod.
3 Screw off the bolts on the rear end shield; use the tools to prize the end shield
along with the end shield edge evenly. made the stop surface of out cover leave the
frame and bearing out track, remove the rear end shield. Before we remove the rear
end shield, we should wrap the rotor rectifier, preventing to damage the rectifier when
we dismantle the rear end shield.
4Dismantle the front end shield: after screw off the bolts of front end shield, take out
the rotor which is connected with the stator carefully. During this process, do not
touch the windings and direction exchanger, put the rotor on frame or crosstie at a
certain height after it was been pulled out.
5Screw off the bearing bolts on end shield, remove the bearing external cover and
end shield.
6 We can check the internal fan of the rotor, and carry out the general clean
according to check situation, it is no need to dismantle it. if the failure occurs in end
winding or the check quality can not be guaranteed because the dirt on end winding is
too much, we can dismantle the fan.
3.5.2.2
3.5.2.3
3.5.2.4
Page 98 of 326
1 The armature winding should be clean and without dust dirt, the surface is
smooth, and there is no damage and overheat phenomenon on insulation.
2There is no off, loosen and overheat phenomenon on weld of winding and rectifier.
3The surface of rectifier should be clean without dust dirt, smooth without spots.
4the mica duct should be clean without dust and dirt, and it should be 1 1.5mm
lower than copper segments. The duct shape forms a right angle, and the measured
DC resistance difference between segments no more than 10%
5there should not be concave and protruding phenomenon on rectifier, the highest
and lowest parts should not exceed 0.5mm when it was exceeded we should lathe
it. After lathe, the diameter of rectifier segments can not be 10mm smaller than the
initial value.
6 The fan should be clean without dust dirt, and there is no damage and loosen
phenomenon on the blades
3.5.2.5
3.5.2.6
Page 99 of 326
3Lubrication oil in the bearings should meet the requirements of the manufacturer.
4The leading line should be clean, the insulation is perfect, without broken, no dirt
on contactor, the screws was pressed tightly, the connection is reliable, the indicate of
leading line is evident.
5The insulation of every circuit should not less than 0.5 M
3.5.2.7
3.5.2.8
3.5.2.9
3.5.3
3.5.3.1
Complete the test running procedure, stop all the maintenance work of motor, put the
operate power supply and motor drive power supply.
3.5.3.2
Start up the motor; detect the rotating direction of motor and the indication of ampere
meter.
3.5.3.3
3.5.3.4
3.5.3.5
The abnormal phenomenon should not occur during 1 hours no-load operation.
3.5.3.6
after checked there is no abnormal occurs on the motor, shut down the motor, and
restore the safety measures of maintenance, assemble the coupler, and put it into
standby operation.
3.6
Attached-tables
3.6.1
Table 1
3.6.2
Eligible value
insulation
resistance
of
380V
500V
0.5M
>1.3
6KV
2.5KV
10M
>1.3
absorptance
code
name
drop
point
calcium
base ZG2
lubricating
ZG3
grease GB491 ZG4
65
ZG---5
80
265295
85
220250
90
175205
95
130160
Natrium
base ZN---2
lubricating
ZN3
140
265295
140
220250
150
175205
calcium
& ZGN---2
natrium
base ZGN---3
lubricating
grease SYB14
0362
120
250290
135
200240
Grease
for ZGN69
rolling
2
bearing SY151
465
120
#2aeroZL45---2
lubricating
grease SY150
865
170
285315
compound
ZFU1
aluminium base ZFU2
lub. Grease.
ZFU---3
180
310350
200
270300
220
230250
compound
ZFU---1
calcium
base ZFU---2
lubricating
ZFU---3
grease.
180
310350
200
270300
220
230250
molybdenum
3
bisulphite
lub.
grease
220
240280
ZFG--1E
180
310350
ZFG--2E
200
260300
ZFG--3G 220
210250
ZFG--4G 240
160200
speed, 3000
3.7
to
lubricate
the
high
temperature and high load
mechanism equipments.
1500
1000
Below 750
0085
01
012
Table 4 the permitted largest abrasion value of rolling bearing radial gap.
internal diameter of radial gap
bearing
new ball bearing
permitted
largest
abrasion value
2030
0.010.02
0.030.05
0.10
3550
0.010.02
0.030.07
0.20
5580
0.010.02
0.060.08
0.25
85120
0.020.04
0.080.10
0.30
130--150
0.020.05
0.100.12
0.35
Name
Unit
NO.
bearing
set
2 for each
Piece
10 for each
Spare parts
4.1
150 KV GIS
4.1.1
4.1.2
4.1.2.1
Category
Interval
Patrol
inspect
Every
months
Description
Items
Contents
If the indicator and indicating light are
normal or not.
If there is abnormal sound or odour
If there is overheat or discoloring on the
terminal
If the grounding conductor or bracket is
corroded or damaged.
Check the indication of pressure gauge.
Regular
Specific
Every
year
12 years
Operating test
Indication state.
Check the reading on SF6 pressure
gauge before and after operating. Check
if there is any sound of gas leaking
Operating
Check if there is damp, rust or dirt inside
device
and the control box and control panel
control panel
Add lube oil and clean it up.
Tighten the conductor in the LV circuit.
Others
Category
Interval
Description
Items
damage
or
abnormity. Conduct
the
inspection
based
on
instruction, working
method
and
environment
conditions of the
breaker.
Disconnecting Inspect
closely
and
repair
the
unit
and disconnecting unit & isolating unit.
isolating unit
Change the corresponding components.
Measuring
test
Contents
under
12 years
Operating
1The spring is eroded and deformed.
device
and Repair the damaged components.
control panel
2Adjust the stroke.
3) Check if each pin in the connecting
section is normal.
4) Lubrication
5 Check and repair the auxiliary
switch.
6 Regulate the oil buffer. Change the
oil.
7 Change the components according
to the stipulation.
Disconnecting Inspect
closely
and
repair
the
unit
and disconnecting unit & isolating unit.
isolating unit
Change the corresponding components.
Category
Interval
Description
Items
environment
conditions of
breaker.
Contents
Measuring
the test
under
Body
Position
Items
Remark
Outside
Foundation
tightness.
bolt Conduct
checking
terminal interior
Grounding
tightness.
Inside
while
the
Abnormal sound.
Rust.
Check
disconnecting
components.
the
SF6
System
The system
of
wiring
Working pressure of
SF6
temperature
compensation pressure
switch.
Working
state
operating counter
Tightness
terminal
of
No.
Position
Items
Remark
Measurement
of 2M
insulation resistant of
control circuit
of
If it works normally
or not.
Inspection
connecting
disconnecting coil
of
&
it
if
it
if
Tightness of bolts in
each section
Damage
damper.
to
rubber
G1(=1.40.3)
No.
Position
Items
Remark
Operation
mechanism
If it is normal.
Operation
c. scrutinous inspect
No.
Item
Content
After
installation
before
activation
Corrosion
Wiring state
Keep
the
wirings
of
terminal plate and all the
other components and
tighten the bolts of all the
terminals.
Fastener
Closed
tripped
Patrol
& inspection
Regular
inspection
Manual
operation
opening
closing
Normal activation
of
&
Motor driven
operation of
opening
&
closing
Inspection
Inspect and test based on
and test on the related clauses in the
interlock
specification
Insulation
test
Cleaning
10
Lubrication
4.1.2.4
1) Patrol inspection
2)
No.
Items
Solutions
Regular inspection
3)
No.
Items
Contect
Procedure
Operating test
Clean and
refilling
Insulation
resistant
Otherpatrolling
items
oil Rubbing
connection
section
Meaurement
insulation
resistant
Cycle
Maintaining conditions
Contents
When
problems
are
discovered
furing
patrolling inspeciton
When
abnormal
conditions are discovered
during operating
Other precautions
Remark
4.1.3
4.1.3.1
Cleaning
4.1.3.1.1
Applicable range
This section is applicable to insulator casing and metal components cleaning. The
insulator surface must be clean. In addition, all the metal components must be
cleaned thoroughly without dust and other particles.
4.1.3.1.2
Cleaning solvent
Ethanol and acetone are allowed for cleaning the insulator surface.
Note: Do not breathe in the vaporized solvent while operating.
4.1.3.1.3
Consumable
Use the wiping paper or dacron cloth to clean up the surface of the cast insulator.
Use the white dacron cloth to clean up metal components
When cleaning the pouring insulator and metal components, dip these required
consumables into the cleaning solvent to make sure the surface of the components is
cleaned up.
Use the dry cloth instead of the dirty cloth for the final cleaning of the components.
4.1.3.1.4
4.1.3.2
Air sealing
4.1.3.2.1
Acppication range
This section states the details on the operation procedure of sealing the SF6 with O
ring and air sealing glue for SF6 equipment.
4.1.3.2.2
Sealing surface
Sealign ring
Sealing groove
4.1.3.2.2.3 When fix the flanges, make sure the O ring is in place.
4.1.3.2.3
Air side
Air
glue
Gas side
sealing
4.1.3.2.3.2
Other precautions
(1) Do not mix the grease and air sealing glue.
(2) Remove the residual air sealing glue after assembling
(3) Screw on the cover of the air sealing glue tube immediately after usage.
4.1.3.2.4
No.
Procedure
54
655
Picture
765
766
876
877
4.1.3.3
SF6 filling
4.1.3.3.1
Application range
This section is applicable to SF6 filling into equipment after equipment installation or
maintenance. The process of SF6 filling includes extraction, leakage inspection and
SF6 filling (see Fig.7)
4.1.3.3.2
Process of evacuation
5.3.2.1
Connect the pipeline of vacuum pump with air inlet of equipment. It is required that all
the air pipes and vacuum pump should be be consistent with the capactity of the
equipment needed to be extracted.
4.1.3.3.2.2 Check if the rotating direction of vacuum pump is correct. Start up the pump.
4.1.3.3.2.3 After the vacuum reaches 133P, keep extraction for 30 mins.
4.1.3.2.4
If the vacuum pump stops running, close the valve of the vacuum pump and check if
the oil flows in reverse direction.
4.1.3.3.3
4.1.3.3.3.1 After extraction, close the air inlet valve and measure the pressure of the air chamber.
4.1.3.3.3.2 Conduct the leakage test. It is required that within 4 hours, It is required that the
difference between initial pressure and final pressure does not exceed 133P.
4.1.3.3.3.3 If the pressure increasing is approximately 133P, continue extracting until the vacuum
reaches 133P. Keep it for 30m. Repeat the leakage test to see whether there is
leakage or moisture venting.
4.1.3.3.4
Use SF6 to discharge the air in the pipeline. Fill SF6 to the equipment until it reaches
the rated value.
The rated pressure of the breaker is 0.5MPa. The maximum pressure is: 0.52MPa
The rated pressure of other air chamber is 0.4MPa. The maximum pressure is
0.42MP.
4.1.3.3.4.3 After filling, dismount the pipeline, cover the self-sealing joint.
Notes: (1) At the beginning of filling, open the valve of the SF6 bottle gradually for
filling slowly.
(2) For reserving and transporting the product which do not need to be disassembled,
fill the SF6 until the pressure reaces 0.02-0.05MPa. When install the equipment on
site, if there is no air leaking through checking, extraction and leak inspection are not
required. Fill the SF6 according to the instruction book.
4.1.3.4
Refill SF6
4.1.3.4.1
Application range
This section is applicable to refill of SF6 switchgear which is running (when the
pressure of various gas of decrease).
4.1.3.4.2
4.1.3.4.2.1 Remove the blank cover of the SF6 bottle and the protective cover at the inlet of the
7 SF6
Self-sealing joint
Connector A
O ring
Safety valve
Relief valve
Rubber pipe
Check valve
SF6 container
joint B
4.1.3.5
4.1.3.5.1
Precautions
4.1.3.5.1.1 Do not change the the sorbent during raining or the moisture content is larger than
80%.
4.1.3.5.1.2 The time for taking the sorbent from the sealing device and putting it inside can not
exceed 30 mins.
4.1.3.5.1.3 After assembling the sorbent, extract the equipment as soon as possible.
4.1.3.5.2
Procedure
No
Procedure
Picture
4.1.3.6
4.1.3.6.1
Application range
This section is applicable to installation of the control cable and cable gland disposal
connected with switchgear.
4.1.3.6.2
Installation of controlcable
4.1.3.6.2.1 All the cables in the switchgear are layed on the wire conduit or cable support.
4.1.3.6.2.2 After installing the cable in the control box, regulate it properly.
4.1.3.6.3.1 Open the cable, its coat should be longer than the wiring terminal.
4.1.3.6.3.2 Peel off the metallic layer and the ethene coat.
4.1.3.6.3.3 Connect the grounding wire to the metallic layer by tin weling or clamp.
4.1.3.6.3.4 Use the insulation belt (e.g.FB insulation belt) to twine the end of the cover, metallic
layer and ethene coat forming two films around them. If the cable insulation requires
water proofing, paint silica gel (water repellent) on both ends of the cable before
winding the insulation belt.
4.1.3.6.3.5 Remember that connect the grounding wire to the grounding terminal in the
mechanism box.
4.1.3.7
4.1.3.7.1
4.1.3.7.2.1 Confirm the SF6 is recycled completely. Dismount the galvanized bolts. Check the
covering plate.
4.1.3.7.2.2 Dismount the M12 hexagonal bolts. Take out both fixed contact b7 and fixed arc
contact b12 at this time. If the fixed contact is slightly abraded, reinstall the contact.
4.1.3.7.2.3 Insert the remover e1 for the nozzle and disassemble nozzle b14.
4.1.3.7.2.4 Insert the remover e2 for movable contact. Dismount the movable contact b15.
Hexagon bolt
Support
conductor
of
fixed contact b7
remover e1 for
the nozzle
b14
nozzle
Remover
e2
for
movable
arc
extinguishing contact
Movable
arc
extinguishing contact
b15
4.1.3.7.3
4.1.3.7.4
Inspect the working pressure of the SF6 pressure switch (SF6 density switch) see Fig.
10.
Inspect the working pressure in the following order
4.1.3.7.4.1 Close the SF6 controlling valve (a2) and dismount blind cover A (a5).
4.1.3.7.4.2 Slowly open the vent valve F of SF6 (a3) and use a buzzer or tester to check the
releasing pressure of the switch while observing pressure gauge of SF6.
4.1.3.7.4.2 Slowly open and close the vent valve F (3) of SF6 and open the controlling valve E
(a2) and check the releasing pressure in the same way as that mentioned in
section4.1.3.7.4.2.
4.1.3.7.4.4 When connected, the working pressure that is in the following range is normal.
= 4.50.3kg/cm20.450.03MPa
20
= 4.00.3kg/cm 0.400.03MPa
=63GA63GL+0.1~0.5kg/cm20.01~0.05MPa
Releasing pressure (63GA63GL)
= Working pressure63GA63GL+0.1-0.5kg/cm20.01-0.05MPa
When the blank cover A (a5) recovers, slightly open the vent valve (a3) to vent the air
in the pipe. After tightening the blank cover, use the suds to inspect if there is air
leaking in the disassembled part. Besides, make sure the contro
lling valve E (a2) is open after the test.
a5 blind cover A
O tank
Tank downside
breaker
a2 controlling valve E
a3
vent
valve F
4.1.3.7.5
4.1.3.7.6
4.1.4.1
The work should be carried out under the guidance of the personnel who is in charge
of WORKING UNDER OXYGEN LACKING
4.1.4.2
Confirm the number of the personnel before and after the work.
4.1.4.3
4.1.4.4
4.1.4.5
Ventilate the air CB. Make the record on the oxygen density.
4.1.4.6
Start working under the conditions that the oxygen density is over 18%, the oxygen
density is not lower than 18% when the ventilator is in service.
4.1.4.7
4.1.4.8
Move the SF6 bottle from the CB. Hang the sign plate DO NOT OPEN OR CLOSE.
4.2
4.2.1
4.2.1.1
breaker
Rated voltage
10kV
Working voltage
Rated current
1250A
Rated
current
Phase number
3-phase
Rated frequency
6.3KV
breaking 40kA
Mechanical
service life
Electrical service
life
Mode
of Spring energy type
operation
mechanism
Voltage
operation
supply
50Hz
of DC 110V
power
Manufactory
4.2.1.2
10kV
busbar 3150A
breaking 40kA
Working voltage
6.3 kV
Rated frequency
50 Hz
Rated
thermal
stability time
LZZBJ9-10
Overvoltage
protection
implement
Zero
sequence LXKB-120
transformer
Circuit
breaker
state
intelligent
controller
Manufactory
4.2.1.3
Natural cooling
10kV
Working voltage
6.3 kV
1250A
Rated frequency
50 Hz
Rated
current
breaking 40kA
Rated
thermal
stability time
LZZBJ9-10
Overvoltage
Natural cooling
Zero
sequence LXKB-120
transformer
breaker
protection device
Shendian
state
intelligent
controller
Manufactory
4.2.2
4.2.2.1
Maintenance frequency
4.2.2.1.1
4.2.2.1.2
If has overhaul in that year, it will be taken along with unit overhaul.
4.2.2.2
4.2.2.2.1
4.2.2.2.2
4.2.2.2.3
Check regularly
4.2.3.
4.2.3.1
4.2.3.2
4.2.3.3
4.2.3..4
4.2.3..5
b)Contact travel: moving distance of component after dynamic and static contactor
contacts and produces closing force. This circuit breaker adopts the method of
indirect measuring contactor spring compressing quantity to test the contact travel of
contactor. Test contact travel of three phase separately. Test method is as the above
drawing. Measuring result should accord with the parameter scope when leave the
factory.
c)Contactor bouncing time: interval between contactor close and dynamic and static
contactor flick again when circuit breaker switch on. Test the contactor flick time of
three phases separately. Measuring result should accord with the parameter scope
when leave the factory.
d)Three phase switch off synchronization: time difference between earliest separating
phase contactor and latest separating phase contactor when circuit breaker breaking.
Measuring result should accord with the parameter scope when leave the factory.
e)Switch off time: interval between the moment that circuit breaker receive the
breaking signal and the moment that all phase contactors separate. This value should
be measured separately during circuit breaker rated voltage, lowest operation voltage
and highest operation voltage.
f)Switch on time: interval between the moments that circuit breaker receives closing
signal and all phase contactor contact.
4.2.3..6
4.2.3..7
4.2.4
4.2.4.1
Usually the circuit breaker installs in the manufacture by standard clamping fixture
and all the cooperation relation is ensured by clamping fixture. Do not do much
disassembly and installation during maintenance process. Because circuit breaker
maybe can not reaches the basic performance requirement after disassembly and
installation, even worse than before disassembly.
4.2.4.2
For the components that require to disassemble, method, procedure and position
For those have been disassembled and can not reach the standard requirement after
installation and checking, contact the manufacture for repair. Operation of equipment
with failure is forbidden.
4.3
4.3.1
4.3.1.1
400V
Working voltage
Rated
current
Phase
number
400V
Rated
frequency
50Hz
Manufactory
Manufactory
4.3.1.2
400V
Working voltage
Rated current
See drawing
Rated
current
Phase number
3-phase
Rated frequency
Manufactory
400V
breaking 42KA
50Hz
4.3.2
4.3.2.1
Maintenance frequency
4.3.2.1.1
4.3.2.1.2
If has overhaul in that year, it will be taken along with unit overhaul.
4.3.2.2
4.3.2.2.1
4.3.2.2.2
NS
4.3.2.2.3
Check regularly
4.3.3
4.3.3.1
4.3.3.2
4.3.3.3
4.3.3.4
4)No rust and distortion phenomenon for electromagnet. Agile iron core without
unsmooth blockage and displacement. Active iron core and static iron core contacts
closely.Break time gap meets the requirement.
5)Arc extinction device is good and arc extinction bar should be cleaned with firm
installation and correct location. Contactor should not touch the arc extinction cover
when close the switch manually with certain distance.
6)Agile Operating mechanism. No unsmooth blockage, abrasion and distortion for
every active parts and components; good springiness of spring; adding oil to rotary
shaft part.
7)It should closed reliably after energy saving (under pressure trip must close).
Energy saving spring should in shortest position after switch closed. Pressure
"separate" Button manually and the switch can be open reliably.
8 Good insulation and agile rotation of energy saving motor. Check entirely when
overhaul.
9Energy releasing electromagnet coil is good. DC resistance meets the requirement
of nameplate data and with tightness connection.Suitable adjustment of switch on
mechanism which can switch on reliably and working voltage meets the
requirement85110%Ue.
10 Good insulation of switch off coil. DC resistance meets the requirement of
nameplate data and with tightness connection. Suitable adjustment of switch off
mechanism which can switch off reliably and operation voltage meets the
requirement3570%Ue.
11Operating fuse is good. Fuse rated current is qualified and with good contacting.
12 Firm installation of auxiliary contact with good contacting, no burn, good
insulating condition, and gap meets the requirement and suitable regulation of on-off
time. Check whether its on-off location is suitable Manually and motor driven, switch
off and switch on.
13 Primary overcurrent mechanism is good. Regulation of overcurrent meets the
requirement and can switch off reliably.Dismantle it when nonuse and fixup it to avoid
misoperation
14Good insulation of secondary loop, terminal block is clean and with clearly marks.
15Pedestal is good and firm with vertical installation.
16 Inspection methods for brainpower controller protection characteristic setting
value are as following:
a)For L25X type controller: contact CW2 appropriative tester, press "selection" Button
convert to the setting value that will be checked. If want to change the setting value,
rotated the code board and regulate every setting value.
b)For M25M26L26 type controller: press "setting" Button, protection characteristic
setting value will displayed on LED screen. If want to change the setting value, press
/ to regulate every setting value and press "save" Button to save the chang ing
value.
Usually the circuit breaker installs in the manufacture by standard clamping fixture
and all the cooperation relation is ensured by clamping fixture. Do not do much
disassembly and installation during maintenance process. Because circuit breaker
maybe can not reaches the basic performance requirement after disassembly and
installation, even worse than before disassembly.
4.3.4.2
For the components that require to disassemble, method, procedure and position
method should be designed before disassemble so as to make sure the correctness
for next assembly.
4.3.4.3
For those have been disassembled and can not reach the standard requirement after
installation and checking, contact the manufacture for repair. Operation of equipment
with failure is forbidden.
4.4
Transformer
4.4.1
4.4.2
4.2.2.1
Maintenance interval
4.4.2.1.1
Conduct the minor overhaul every 1-3 years, the preventive test should also be done.
Lessen the minor overhaul interval for the transformer that is running in the poor
environment.
4.4.2.1.2
During the overhaul, whether the transformer needs to be maintained depends on the
transformer preventive test result, on-line monitoring result of transformer in service,
and the all-round analysis.
4.4.2.1.3
Conduct the temporary maintenance timely if the serious defects are found during the
operation.
4.4.2.2
4.4.2.2.1
Overhaul items
poles for
4.4.3.1
No.
Items
Maintenance technology
Quality criteria
1) The expander is
sealed reliably without
leaking and permanent
deformation.
2) There is no residual
gas in the gas releasing
2) Check if there is gas inside the gas valve
releasing valve of the expander, if any, 3)
The
oil
level
ascertain the cause, discharge the residual indication unit or the oil
gas.
temperature pressure
4)
The
pressure
releasing device of the
4) Check if the pressure releasing device of box expander is good
the box expander is good. If the releasing 5) The top cover and
plate has cracks, ascertain the cause and the coat of the rippling
replace it.
expander
are
5) Check if all the connecting bolts of the top
cover of the corrugated expander are
complete and eroded. If any,complete the
bolts and remove the erosion on the top
cover and coat.
increased.
6) The paint coating is
good
2
the
3) The moisture is
good, silica gel is try,
the oil in the oil cup is
pure and the oil content
is normal.
4)
Primary
lead
wiring connection is reliable.
Porcelain
bushing
inspection
3) The hydrophobicity
of the coating and silico
gel creepage skirt is
good.
4) Check the hydrophobicity of the stainrepellent layer, if it falis, clean it and paint
again. Change the creepage if it fails.
4
Inspection 1) Inspect and complete tne name plate and 1) The name plate and
of oil tank indication plates.
the indication plates are
ans
all in place
2) Remove the dirt and corrosion outside
pedestal
5) The membrane of
the pressure releasing
device is good and
sealed reliably
6) The tighness of the
oil releasing valve is
good without leaking
7) Paint coating is good
4.4.3.2
No.
Item
Inspection
solid
insulation
surface
Maintenance technology
of 1) Remove the dust and dirt in the
insulation surface using abluent if
necessary, then clean the surface using
clean water and wipe it.
2) If there is any sign of discharging on the
insulation surface, abrade the carburized
layer using a crocus paper. After seeing the
normal resin insulation surface, clean it
with the acetone solution, paint it again
with the resin of the same type.
3) If there are cracks on the insulation
surface, inspect that if the cracks have
extended along the primary direction. If it is
only a partial fault, abrase the flawed parts
and repaint the resin of the same type. If
the crack is throughout, replace the
transducer.
4) When the silica powder of resin casting
Quality criteria
1) The surface of the
solid insulator is clean
without dirt and dust.
2) There is no sign of
discharging or crack
on the surface of the
porcelain insulator
3) There is no crack
on the surface of the
resin insulator
4) The paint coating
on the surface of the
resin is good
5)
The
semiconductive coat
on the resin surface is
in good condition.
1)
There
is
no
oxidation in contacting
surface of primary
wiring terminal and
the fastener are all in
2) Check if the primary wiring fastener is place and connected
tightened based on the requirements and reliably
complete the bolts washer.
2) Primary wiring is
connected reliably.
Check if the Remove the oxidized layer of the The lugs of the end
equipotential
contacting part. Tighten the bolts on the wiring
of
the
line of busbar lugs of the tightening wiring.
equipotential line and
CT is reliably
primary current bas
connected
are
tightened,
contacting reliably
Check
the 1) Make sure all the marking on the wiring 1) All the markings on
name plate in terminals are complete and clear. Make a the wiring terminals
the checker
new marking if there is lacking or damage. are complete and
2) The name plate is good and contact the clear.
manufacturer if there is lacking or damage.
4.4.4
4.4.4.1
For Primary and secondary circuit operatioin of the transformer, issue the
working permit and operating permit according to the related regulations and
stipulations. take safety measures.
4.4.4.2
4.4.4.3
4.4.4.4
4.5
Spare List and Attachment for Oil Standard (Unavailable for Interim)
Generals
The cable of our plant electrical specialty can be classified as power cable and control
cable. The control cable can not be damaged easily for its section area and its
passage current both are smaller, so only household inspection is enough in the daily
maintenance; the passage current is larger in the operation of power cable and easily
causes faults of heat and so on, so this manual focus on the maintenance and
inspection of power cable
5.2
5.2.1
5.2.1.1
5.2.1.2
Model
Rated voltage
Mode of insulation
Insulation
resistance
ZRC-YJV-10-1240
10 KV
1000
ZRC-YJV-7.2/12-3185
12 KV
1000
ZRC-YJV-7.2/12-3150
12 KV
1000
ZRC-YJV-7.2/12-3120
12 KV
1000
ZRC-YJV-0.6/1
0.6 KV
1000
Model
Rated voltage
ZRC-KVVP
0.6 KV
Mode of insulation
Insulation
resistance
1000
PVC
ZRC-DJYVPV
0.6 KV
PVC
1000
ZRC-KVV
0.6 KV
PVC
1000
5.2.2
5.2.2.1
The full name of ZRC-YJV type cable is cross linked polythene insulation polyvinyl
chloride conduit fire retardant power cable, and it is used for places in need of
relevant fire retardance such as indoors, tunnels, and cable trenches and so on.
5.2.2.2
It has a fire retardant performance and can control the fire spread in certain bound
when the cable burns, so serious accidents caused by the firing cable can be avoided,
and then the fire protection level of cable line can be improved
5.2.2.3
5.3
5.3.1
Most of power cable is laid in the cable tunnel frame, and the patrol and inspection of
cable in cable tunnels and risers should be carried out once a month
5.3.2
5.3.3
When the newly-installed cable line has been put into operation for 3 12 months, a
DC withstand voltage test should usually be done and the electrical preventive test
should be done once a year after that
5.4
5.4.1
After the cable line was power off and before it was been put into operation again, we
should check that the insulation of cable is good. For the cable that power off time is
longer than one week but not enough for 1month, we should measuring the insulation
resistance of the cable conductor to ground with megger, if we have any doubt we
must test it with DC voltage which is lower than the voltage used for conventional DC
voltage withstand test, test it for 1minFor the cable that power off time is longer than
one month but not enough for one year, we must carry out the DC withstand voltage
test 50% specified test voltage value, test it for 1min for the cable that power off
time is longer than one year we should carry out the conventional DC withstand
voltage test.
5.4.2
The cable patrol and inspection is done monthly, it is mainly to check whether there is
phenomenon of overheating with cable and connectors and whether there is
phenomenon of chap or distortion with polyvinyl chloride conduit. Whether there is
detrimental accumulation of dust and ash, whether the fire fighting and blocking
facility is complete, whether the fir alarm device equipment can be started up
normally, where the cable tunnel lighting is perfect; and there should also be complete
records of the cable patrol and inspection.
5.4.3
5.4.3.1
5.4.3.2
5.4.3.3
5.4.3.4
5.4.3.4.1
The test voltage value should be tested according to 2.5 times of rated voltage value,
5.4.3.4.2
The leakage current of 5 minutes voltage withstand time should be no more than the
leakage current of 1 minute voltage withstand time
5.4.4
5.4.4.1
Before and after telemetering the insulation resistance, the testing cable must be
discharged fully, and only then test personnel can touch it with hand
5.4.4.2
When the DC withstand voltage test is done to the main insulation of cable or the
insulation resistance is
5.4.4.3
continue operating cable line under the monitoring condition, the test cycle should be
shorten, if within no less than 6 months, after more than 3 times continuous tests, the
test result does not go bad, then it can be tested according to its normal cycle
5.4.4.4
After the withstand voltage test, only when the current limiting resistor of about
80k/KV repeats discharging several times until there is no spark in discharging of
conductor, then the direct earthing discharge can be started.
5.4.4.5
During the DC withstand voltage test, we should measure the leakage current when 1
minute later after the test voltage is reaches to specified value and when the add
voltage time reaches to the specified time. The leakage current value and imbalance
coefficient (ratio of maximum and minimum value) can be used as reference to judge
the insulation conditions but not to judge whether we can put it into operation or not. If
we found the leakage current compared with the last tested value has big change, or
the leakage current is unstable, it means it increased sharply along the increase of
test voltage or add voltage time, we should find out the reason. If it caused by the
leakage current of terminal tap surface or to-ground stray current, we should eliminate
it, if we doubt that the insulation of cable line is not good, we can increase the test
voltage(or prolong the test time,(dont exceed the leave manufacturer test voltage in
standard )to confirm whether it can operating continuously or not.
5.4.4.6
Before and after time of the cable DC withstand voltage test, it is necessary to
measure the insulation resistance of cable with megohm meter, and the twice
measuring values of insulation resistance should not differentiate largely. Or else,
check out the problem and solve it
5.5
5.5.1
5.5.1.1
The size of cross linked cable connector ends should refer to the basic size
requirement, and if the section are of cable is very large in fabricating, the size can
aptly be broadened according to the practical conditions of cable pyrocondensation
accessories
5.5.1.2
5.5.1.3
Set two cable wires to be connected right against and 200---300mm in superposition,
and make sure the joint center of the two cable wires
5.5.1.4
Measure the size according to the requirement and shuck off the external sheath,
colligate the armor 50mm apart from the fracture with line, and shuck off all others
5.5.1.5
Keep the 20mm internal sheath, shuck off all other insulation and the stuffing
5.5.1.6
Strip off the external shield insulation of two cable that ready for connection, align the
centre wire of cable, and saw it off from the centre point.
5.5.1.7
the distance from centre point to two sides is300mm for every cable Strip off the
external shield layer, keep down 20mm of semi-conductive layer, clean the semiconductive substance on insulation layer.
5.5.1.8
Cover the stress pipe on the phases of the two side cables, cover it for 20mm, heat
and fix it.
5.5.1.9
Cover the longer side of stripped cable with end socket, sealing socket and protection
sheath, cover every phase wire with 2insulation sleeves, 2semi-conductive
tubes and copper wire, and Cover the cable short side with end socket and sealing
sleeve.
5.5.1.10
crimp connect the connection tube of centre taps, measure 1/2 of cable wire and
connect the tube of 5mm length, cut off the insulation layer, measure the insulation
layer for 35mm from the breaking, and cut it to a cone of 30mm length, keep 5mm
semi-conductive layer, clean the oxide film of crimp connect tube, clean it with alcohol
and paint the conductive grease, choose the compression mold according to section
of cable wires, and crimp connect every phase, we can crimp the crimp connect cycle
for 4---5 rings, when we crimp connect every cycle, after it was finished we should
waiting for half a minute and then take off the compression mold, we should pay
attention that the taps after crimp connection should without obvious edges and
corners, of necessary we can mend it by file.
5.5.1.11
After crimp connection, tie the semi-conductor layers on the phases of centre crimp
connected tube, and join it with the semi-conductor of two sides.
5.5.1.12
Wrap stuffing glue between the cones of two ends, and the thickness should be no
less than 3mm
5.5.1.13
Fixing the internal insulation conduit: set the internal insulation conduit between the
bushing of ends and fix it by heating from the midst
5.5.1.14
Fixing the external insulation conduit: set the external insulation conduit at the central
position of the internal insulation conduit, heat and fix it, while heating it follows the
sequence from the midst to the two ends
5.5.1.15
Fixing the semi-conductor conduit: cover two semi-conductive pipes on the insulation
pipe, cover 50mm copper shield on two sides, heat and fix it from the centre to two
sides.
5.5.1.16
Install the shield and ground line, connect the two side copper screen layers tie up the
ends and weld it, cycle and tie up the cable wire, weld the two sides on the shield
layers, and weld it on the screen layers at two sides.
5.5.1.17
Fixing the metal sheath: set the external insulation conduit at the central position of
the internal insulation conduit, heat and fix it, while heating it follows the sequence
from the midst to the two ends
5.5.1.18
Cover the seal sleeve on the end of protection shield, cover the two ends with 100mm
tube and cable external shield, then heat and fix it from the centre to two ends, during
the heating process of sealing sleeve, the temperature can not be too high, heat
along the cable cycle in sequence, and can not heat the cable at will, make the
sealing sleeve close to the cable tightly, check whether there is overheat crack
phenomenon exists after heating, thereby the whole technique of pyrocondensation
for the cable was completed.
5.5.2
5.5.2.1
Sheath disassembly
horizontally place the cable (see Fig. 1).the sheath to be stripped is classified two
sections:one is 750mm in length measured out door;the other one is 550mm in length
measured indoor.
5.5.2.2
Armor stripping
Coat the outside protective bushing of 30mm in length from fracture end with metal.
Then bind it. Remove the left protective bushing.
5.5.2.3
5.5.2.4
5.5.2.5
Welding grounding
Polish the jointing part of the armor grounding. Use the grounding wire to connect
(divided into three parts) each-phase copper shield layer and the armor. Weld them
firmly.
5.5.2.6
5.5.2.7
Glove fixing
Sleeve the Y-shaped root with the glove. Heat both ends for better fixing with fingers.
5.5.2.8
5.5.2.9
Sleeve the stress pipe according to Fig. 2. Connect it with copper shield of 20mm in
thickness. Heat it for fixing.
5.5.2.10
Terminal connection
Deepen the hole of wiring terminal by 5mm. Strip off the insulation on wire core,
sharpten the end. Connect the terminal through pressing. Bind the filling gel on the
sharp end. Overlap the terminal by 10mm.
5.5.2.11
5.5.2.12
5.5.2.13
5.5.2.14
5.5.2.15
5.5.2.16
5.5.3
5.5.3.1
Transparent PVC strip: its specification is 0.23mm in thickness and 25mm in width, it
is used for the protection of usually-temporary casing or cable external package
5.5.3.2
Standard for the irradiated high pressure polyethylene layer: thickness 0.1mmwidth:
25mmuse for the insulation of centre tap of cross linking polyethylene cable below
35KV and indoor terminal. irradiated high pressure polyethylene layer was been
reheat and stretched during manufacturing (stretched 30% under 100 )and then it
was been cooled and cut and packed, after it was been packed, if we heat it it will
rebound, (heat is not crosslinking process) and in-turn compress the gas between
layers and increase the discharge voltage.
5.5.3.3
PVC stickiness strip: its specification is 0.12mm in thickness and 10 to 25mm in width,
it is used for commonly airproofing cable connectors of 10KV voltage grade below but
not used for the long-term sealing
5.5.3.4
Black PVC strip: its specification is 0.25mm in thickness and 30mm in width, and it is
used for the furthest outer layer protection for cable connectors and connection ends
of the plastic. This kind of plastic strip has a superior withstand ageing performance to
common PVC strip
5.5.3.5
Polyvinyl tetrachloride strip: its specification is 0.1mm in thickness and 25mm in width,
it withstands a high temperature (about 300 ) and has a excellent insulation
strength. It produces extremely-toxic gas in burning, so do not burn it at will. While in
fabricating XLPE cable connectors, it is only used for de-module usage not for
insulation materials
5.5.3.6
5.5.3.6.1
5.5.3.6.2
1 each model
5.5.3.6.3
1 pair
5.5.3.6.4
5.5.3.6.5
Clamp
5.5.3.6.6
5.5.3.6.7
Electrician tools
5.6
Spare parts
1
1 set
1 set
Description
Specification
model
Specification
power cable
and Unit
of
all
Quantity
Each 10
10KV
cross
linked
cable 240mm2
accessories (end connection)
Set
10KV
cross
linked
cable 185mm2
accessories (end connection)
Set
10KV
cross
linked
cable 150mm2
accessories (end connection)
Set
cable 120mm2
Set
10KV
cross
linked
6.1
6.1.1
The DC system includes unit DC system (control and dynamic), switchyard DC system
and coal handling DC system.
6.1.1.1
Unit DC system
The unit DC system consists of following parts:
6.1.1.1.1
6.1.1.1.2
a)
b)
c)
d)
Other two units are equipped with one set of common charging device which is
respectively connected to DC busbar and dynamic batteries of two units via two
mutual interlock switches.
b)
c)
d)
All DC equipment above used for two units are arranged in 0m level and UPS room
of CCR.
6.1.1.2
Switchyard DC system
This DC system is used to supply power to loads like control, relay protection and
emergency illumination in 150KV relay room. It used single busbar sectional
connection mode and main consists of following equipment:
6.1.1.3
a)
b)
c)
d)
e)
6.1.2
6.1.3
6.1.3.1
Technical specification
Type
Rated
voltage
Weight
Length
Width
Tall
Total
height
GFM-100
100
64
170
325
350
GFM-400
400
157
175
330
340
22.0
GFM-500
500
244
175
330
341
34.0
1800
490
350
340
350
140.0
GFM-1800 2
6.1.3.2
10H
ratio Exterior dimension
capacity
Electric performance
Charging performance: charging method: current limiting----voltage stable
Initial charging current: 0.1C
8.5
5 hours ratio
3 hours ratio
1hour ratio
Final
1.8V
A
voltage Final
1.8V
AH
A
voltage Final
1.8V
AH
A
voltage Final
1.75V
AH
A
voltage
GFM-100
10
100
18
90
25
81
55
60
GFM-400
40
400
72
360
100
324
220
240
GFM-500
50
500
90
450
125
360
275
300
1800
324
1620
450
1458
990
1080
GFM-1800 180
6.1.4
6.1.4.1
Technique specifications
Working ambient temperature 1045
Working ambient humidity: 90PH
Working ambient height 2000m from sea level
AC in-put voltage 380V20
AC in-put frequency502HZ
Setted out-put voltage 243VDC
Out-put voltage range180V300VDC
Setted out-put current20ADC
Out-put current range 220ADC
Voltage stabilize precision0.2%
Current stabilize precision0.2%
Texture and wave coefficient : 0.2%
AH
6.1.5.1
Using condition
The altitude can not higher than 2000m;
Ambient temperature :-10 T40 ;
The maximum ambient relative humidity is no more than 90%,, no dewing(relative to
the ambient temperature is 205 )
Used in the area where there is no conductive or explode dust, and there is no gas
can corrupt and damage the insulation
There is no serious shake and shock on the used location.
6.1.5.2
Technique specification
Voltage of power supply:220V10%(AC/DC)
Frequency of power grid :5010%HZ
Control out-put voltage :-6.56.5V
DC in-put :0V5V,025MA,050MA, 0100MA,8 way
Grounding in-put:
Alarm range of grounding resistance:099K
Define rate of grounding resistance:1 K
Voltage error of bus : 1.5%
Error of bus grounding resistance: 15%
Error of branch grounding resistance: 20%
Test way number:0 96
Operation mode: continuous operation and automatic walking down
The biggest power cost: 50VA
Test bus section number: two section bus
Current in-put
Voltage measuring range: voltage of single battery is 0 18V; of battery bank is 0
300V
6.1.6.1
Used conditions
Ambient temperature :-1050
Relative humidity: highest 90%
Atmospheric pressure:86106Kpa
In-put power supply:220V10%
Exterior dimension :630350138
6.1.6.2
Technique parameters.
Frequency of power grid:501HZ
Alarm range of grounding resistance: 099K
Define rate of grounding resistance:1 K
Voltage error of bus: less than 1%
Error of bus grounding resistance: 15%
Error of branch grounding resistance: less than 20%
Test ways nnumber:0 128 way(the summation of two sections)
Operation mode: continuous operation, automatic walks down.
Biggest power cost: 50VA
Test bus section number: two section of bus
6.2.1
Maintenance of SUPER FM GFM valve control type sealed lead acid battery
6.2.1.1
For the GFM-150, GFM-300, GFM-1500 valve control type sealed lead acid battery,
its charging mode is continuous floating charge, and its charging method is limit
current-stable voltage, during stable voltage charging, the current of battery
decreases step by step, and finally, it will be stable, if the current decreases under
0.01C, and this condition maintains 3-5 and does not changed, it shows the charging
of battery was finished, and the battery can be put into floating operation.
6.2.1.2
6.2.1.3
If the transport, storage and installation of battery costs a lot of time, some of the
capacity of the battery will loss, if no need to check the capacity of battery, when
voltage of the open circuit end of battery is higher than 2.13V, we can put it into
floating operation directly, if the voltage of the open circuit end of battery is lower than
2.13V, we should stable charging the battery first, and then put it into floating
operation, if needed we can check the capacity.
6.2.1.4
We should discharging the batteries according to the actual load every year, we
should maintain the stability of current, discharge out 30 of the rated
capacity(0.IC/hour for three hours),during discharging we should measuring the
voltage, discharging current and temperature every one hour(for individual battery and
battery bank), after discharge we should equal charge the battery and put it into
floating operation.
6.2.1.5
We should measuring the individual voltage and the terminal voltage every month,
cheek whether there is exterior deformation and heating, and keep the completed
operation record, the total floating voltage should reaches to 2.24V, and maintain it
within l
6.2.1.6
We should check whether the connected conductor is fixed or not, and whether there
is corrosion, if the loosen phenomenon was found we should tight it to prescribed
torque, and replace the corrosion one in time.
6.2.1.7
Do not increase or decrease the load of the individual battery in same battery bank, it
will cause the imbalance of individual battery capacity and the inhomogeneity of
charging, and shorten the using time of the battery, if we take out some batteries for
the other usage, or they are not in the same group when we charging the batteries,
we should put them together during discharging.
6.2.1.8
Equal charging is no need during normal floating operation, we should equal charge
the battery if the following conditions were found:
Best storage temperature of battery are 5-20 Storage place should clean,
ventilation and not wet. Battery more than three months should balanced charge.
6.2.1.10
Charge and discharge with big current usually will shorten the service life.
6.2.1.11
Floating charge when capacity of 12V are 50100A. Service lives are three years. 2V
is for floating charge and the service life are ten years.
6.2.2
6.3
6.3.1
No
Failure
Failure result
Floating
charge Large
water
operation voltage over consumption,
high(more than 2.30v/)
temperature increases,
battery
leakage,
shorten service life
countermeasure
Regulate
voltage
control value, or
change the failure
voltage
control
component
low Regulate
voltage
control
value,
balanced charge
water Decrease
charge
charging(more
0.2CA)
than consumption,
current, shut down
temperature increase, and
repair
the
battery distortion
equipment
Average
environment Too mach water loss by Strengthen
temperature over high
evaporation,
floating ventilation or use air
charge
current condition
increases,
corrosion
quickens,
shorten
service life
Deep discharge
10
Deep
discharge Shorten the service life
frequency(such as once
for every month)
Avoid this,
battery with
capacity
11
Charge immediately,
balanced
charge
carefully.
12
For
charge,
charge
work
down
and
necessary
balanced
by manual
Balanced charge, or
charge with large
electricity
than
normal
install
larger
Short circuit of whole Terminal is melt down Avoid this, check the
battery group or single that damage battery connect lead with
battery
group or battery
insulating equipment
14
15
16
17
18
Acid
leakage
terminals
battery
6.3.2
Trouble shooting of JZ-22020B type high frequency switch power supply module
6.3.2.1
Incorrect of module output voltage: regulate the voltage through the potentiometer on
the board in front of the module panel to correct output voltage value.
Over-voltage protection after module electrify: regulate output voltage exceeds the
overpressure protection value manually or module control output voltage regulation
terminal input voltage over high.
6.3.2.2
Unstable of output voltage: check whether fluctuation of output voltage over the
permissive scope or load fluctuate continuously and seriously.
6.3.2.3
No output current of module: check whether DC output line is turnoff or not, output
Name
Type
Technical
character
Number
FU3
Fuse
RT18-32X/3P
6A
Q1
Plastic
shell DZ20J 225/3300
circuit breaker
180A
2FL
General splitter
M1-M8
High
frequency Jz5.99.001
second type 20A
EP1
Current module
Kt-500A
B2
DC voltage
FPD-1-A9-PD2030-75mV/4
20mA
QA1
Isolating switch
QAS-400/2
2H4
Indicator light
AD11-22/RAC380V
1T
Temperature
sensor
FU4
Minitype
breaker
HAU
buzzer
FL29-300A/75Mv
circuit GMN20R 6A
24V(DISCONTINU
OUS TYPE)24V
BS
DC
voltage T-UD-D-201
transmitter
Brainpower
JZ5.997.705
monitoring total
conversion
and
connection board
M9-M13
High
frequency JZ5.99.001
second type 20A
WJ
Monitoring
module-
horizontal
220V
type
1S
Button
LA38-11S/209B
1H
Indicator light
AD11-22/21-8GZ
B3
DC
voltage FPD-1-V13-PD2-03
transmitter
B1
DC
voltage FPD-1-A9-PD2-03
transmitter
QF1-3
Minitype
breaker
PA1
Ammeter
AC/DC220V
circuit GMN20R 6A
PA19511000A/75
mV
350V/4
20mA
PV1-2
Voltmeter
PZ195U-300V
0-75Mv/4 2
20mA
EP2-3
Current module
KT-500A
S1-S2
Striker
RX-1000A
F1-F2
Fuse
NT4-1000A
1FL
General splitter
FL-29/1000A-75mV
Q2
Plastic
shell GM225H-2320R
circuit breaker
QA2
Isolating switch
QPS-1000/2P
3H
Isolating switch
AD11-22/21-8GZ
1-7Z
Minitype
breaker
8-16Z
29,31Z
19,29Z
26Z
200A
AC/DC220V
circuit GM225M-23228R
25A
Minitype
breaker
circuit GM225M-23228R
32A
18
23- Minitype
breaker
circuit GM225M-23228R
10A
32Z
Minitype
breaker
circuit GM225M-23228R
10A
21,22Z
27,28,30Z
Minitype
breaker
circuit GM225M-23228R
16A
17-18Z
33Z
Minitype
breaker
circuit GM225M-23228R
63A
34Z
Minitype
breaker
circuit GM225M-23228R
100A
18
35Z
Minitype
breaker
circuit GM225M-23228R
315A
36Z
Minitype
breaker
circuit GM225M-23228R
180A
Appendix:
JZ-MC- Intelligence Monitor Equipments (V4.01)
INSTRUCTION
Table of contents
1Summarization
2Technique Indexes
3Usage Conditions
4Basic Methods For Operating Intelligence Monitor Equipment
5Charge Management
6Computer Communication
7Definition And specification Of Interface
157
Summarization
HJZ-MC- intelligence monitor equipment belongs to industry intelligence inspection
instruments whose main part is a singlechip. With the artificial intelligence technique and
the intangibly-control method, it monitors the running state and parameters of powersupply system, and shows them on the LCD screen. At the same time, it sends these data
information to the remote control end and accepts data/work parameters and statements
sent by operators or previous computer through the communication interface RS-232 and
RS422/485 so that it keeps the power-supply system running under the given state and
perform its tasks of measuring, communicating, controlling and modulating remotely.
Gather Charge Management of being automaticallyItinerant Ground-InspectionItinerant
battery-inspection with Various function togetherachieve so gather
perform its tasks of alarming overlimit or belowlimit voltage, as well as AC cutting and
restarting automatically, etc.
This equipment is mainly used to monitor GZDW PEDW DC power-supply series
produced by Jiuzhou Co. Moreover it also can monitor this companys rectifier modules
and power-supply and Battery products of other companies through changing the control
program according to the consumers need.
Technical Index
Voltage of Power-supply: 220V10% (AC or DC)
Frequency of Electric network: 50Hz10%
Output voltage of Control Uo: -6.5V+6.5V0V5V
DC Input: 0V5V or 025mA or 050mA or 0100mA, 8 loops (2 loop for spare)
Ground input
1.Ground alarm range:
0~99K
1K
1.5%
50VA
Battery input
1.Range of measuring voltage:
45S
6.Inspection amount:
1~108
7. Running way:
Using Conditions
a. Altitude less than 2000m;
b. Surrounding temperature: -10 T40
c. Surrounding humidity less than 90 , no dew (Namely surrounding temperature is
205)
d. No conductive or explosive dust, no erosive or insulation-damaging air in the
surrounding;
e. No strong quiver or impact in the surrounding.
159
1)
a.
b.
c.
d.
e. Warning list: it lists what failures and the time they have occurred at. The items
include warning type, setting value, real value and time.
f. Parameter setting: it is managed by operating men. The following text describes the
detail.
g.
Menu select: Press or to selects item that you want Then Press confirm
160
2)
In this screen display all Parameter of monitor system collection and monitors the
systemWhen happen alarmLight of back of screen has Lighted and pop-up new alarm
information Press 0 to close alarm bell At normal Light of back has closed when
screen savingPress any key to exits screen saving and Lights the light of back.Press
ESC to exits the screen
3) Page Of Battery Voltage
In this screendisplay Battery Voltage of monitor system collection
161
001:
002:
003:
004:
005:
006:
007:
008:
009:
010:
011:
012:
02.35
02.35
02.35
02.35
02.35
02.35
02.35
02.35
02.35
02.35
02.35
02.35
013:
014:
015:
016:
017:
018:
019:
020:
021:
022:
023:
024:
02.35
02.35
02.35
02.35
02.35
02.35
02.35
02.35
02.35
02.35
02.35
02.35
025:
026:
027:
028:
029:
030:
031:
032:
033:
034:
035:
036:
02.35
02.35
02.35
02.35
02.35
02.35
02.35
02.35
02.35
02.35
02.35
02.35
162
5)
163
6)
7) When Parameter Setting is selected and confirm is pressed, the following page will
display.
164
Twineows default of password is 0000. After keying in password and pressing conform,
the following twineow appears.
8)
The parameters can be set both when the charger is charging and when it is not charging.
After Parameter Setting in the main menu being chosen and the equipment showing that
it has enter setting state, you can start to set parameters. Parameters are divided into four
parts respectively in the four frames with broken lines in the figure. Press to choose
parts and press or to move cursor.
Charge state0-- main charge1-- equalizing charge2-- Float charge
System switch: 0-- Stop; 1-- Work;
Module mode: 0--10A1--20A
Warning list: 0Clear; 1RecordRecord means recording a new log after the previous
ones each time the system is started; Clear means recording a new log after deleting the
previous ones each time the system is started. And on choosing Delete state, the current
log is deleted;
Screen saving0Have no Screen saving1Have Screen saving
Device address0255
The rest parameters can be set directly by pressing number keys. After being pressed,
the numbers inputted are valid. They are saved to system after Conform key is pressed,
and system exits from parameter setting screen and return main menu screen. The
parameter setting has function of checking given parameters validity. Namely, the system
cannot exit from parameter setting screen after pressing Conform key if the inputted
voltage of balancing, float or main charge is incorrect. So you should correct the numbers
and try again. The inputted numbers are not valid and the system backs to main menu
screen if you press Exit key.
In the main menu, consumer can choose other menus, or the system automatically enters
running monitor screen and displays work state.
Parameters can be set:
See Fig.
Alarm limits setting:
Here, failure alarms up and low limits can be set.
When setting Battery upper limit and lower limit, need to be noticed:
The fact value is that input value multiplied by 0.01. For example, inputs 1255, So fact
value is 12.55. The rest are integer input.
Time and date setting:
20YYMMDD ( 2 )
Here, time and date can be set.
Format HHMMSS
20YYMMDD
Indicator Lights:
166
1. Power
2.
Main Charge
3 Equalizing Charge
4. Float Charge
5. Work
6. Stop
7. Alarm 1
8. Alarm 2
9. Alarm 3
Charger normal work state: the indicator lights of Power, Work, Main Charge/Equalizing
Charge/Float Charge are lightened, while Failure lights are off.
Charger abnormal work state: Failure lights are lightened. Charger Were stopped by
Monitor system when module failure, Charger work state Were not affected when other
failure.
5.
Charge Management
According to the charge sampling information of storage battery and complying with set
management procedure, the intelligence monitor equipment can automatically choose and
switch charge modes, and dynamically manage storage batterys to keep them running in
full capacitance state..
5.1.
5.2
5.3
6.
Computer Communication
6.1
Signal Collection
6.1.1
6.1.2
6.2
6.3
168
Appendix
Intelligence Monitor Equipment Interface specification
Sketch Map Of Back Panel Of Intelligence Monitor Equipment Its includes from left to right
AVR-CPU card The AC date collection card The DC date collection card switch input
cardswitch output cardItinerant battery-inspection card123Itinerant GroundInspection card 12 and Itinerant Ground-Inspection card
1
The AVR-CPU card includes from up to down respectively 9-pin D-type head interface and
phoenix 5-pin
Terminals.( output passive contact, capacity is 0.3A 125VAC, or 0.3 A 110VDC or 1A 30 VDC.)
It is composed of 9-pin D-type head
2--- 232 output TXD
3--- 232 input RXD
5--- 232 GND
6--- 485 Data+
7--- 485 Dataphoenix 5-pin terminals
12--- module Start/stop signal terminal
34--- N.C
45 N.O Alarm bell control terminals
169
The fourth, fifth and ninth pin are for common (AC date collection card is optional element)
3
The DC date collection card includes from up to down respectively indicator light for
communication to main CPU, 25-pin D-type head interface.
25--- charge voltage
24--- charger current
23--- KM voltage
22--- KM current
21---battery group voltage
20---battery group current
19--- spare 1
18--- spare 2
the fourth to the thirteenth are for 12 V grounding
the first and second are for +12V
the third and the fifteenth are for -12V
the sixteenth is for output 0V~5V
the seventeenth is for control high frequency output 6.5V~ +6.5V
The upper of switch and pulsed input card is indicator light for communication to main CPU;
the low part is DB 15-pin terminal. Its input signal is passive contact or photoelectric switch
1- charger alarm
9- battery fuse break
2- feed line switch alarm
10- arrester alarm
3 - spare 1
170
11 - spare 2
4 - spare 3
12 - spare 4
5 - spare 5
13- temperature pulse input
6- ammeter pulse1
14- ammeter pulse2
7+12V
8 and 15- 12V grounded (for common)
5
Switch output card has DB 15-pin terminal. Its output signal is passive contact, capacity is
0.3A 125VAC, or 0.3 A 110VDC or 1A 30 VDC.
1- charger failure
9- battery fuse breaker
2- feed wire switch alarm
10- arrester alarm
3- HM voltage alarm
11- KM voltage alarm
4- output current alarm
12- AC alarm
5- Mother line grounded
13- Mother line voltage to ground alarm
6- battery voltage alarm
14- spare 1
7,8 and 15- for common
171
Itinerant Ground-Inspection card is composed of 37 needles with D-type heads (Male) and
phoenix 3-needle terminals
Through the first to the thirty-twelfth needles the sensors sampling voltages (0-5V) of the first
to the thirty-twelfth branches are inputted respectively, and the other five needles are not used.
When the branches are more than 32, the cardis needed. The 3 needles of the phoenix
terminal supply work voltage to the sensors respectively with +12V, 12VGND and 12V.
1:
3:
5:
7:
8:
GND
9:
10:
+12V
11: 12VGND
12: -12V
172
7
7.1
173
174
175
176
177
178
179
180
181
7.1.2
182
183
184
185
186
187
188
189
190
7.1.3
191
192
193
194
195
196
197
198
199
7.1.4
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
7.1.5
7.1.5.1
7.1.5.1.1
Manufactory:
7.1.5.1.2
Model: RCS-924A
7.1.5.1.3
Rated value
Rated AC secondary current(A):
Rated AC primary voltage(kV)
1
150
7.1.5.1.4.1
7.1.5.1.4.2
7.1.5.2
7.1.5.2.1
DC voltage: 110V
7.1.5.2.2
7.1.5.2.3
AC current
7.1.5.2.4
50HZ
1A
7.1.5.2.5
7.1.5.2.6
7.1.5.2.7
7.1.5.2.8
7.1.5.2.9
(o.4 O.6)Ie
0.8
Line-break delay:
10~9990ms adjustable
Pole difference 10 ms
217
7.1.5.2.11
Pole difference 10 ms
lOOV adjustable
Sequence voltage
Pole difference 1v
lOV adjustable
5~65V adjustable
Grade 1v
<30ms
40~90V adjustable
<8ms
7.1.6
7.1.6.1
64In
continue 10000%IH
0.15VA
1s
lower than IH
AC voltage:
Precise measuring range 0
Overvoltage capacity
1.85UH
lower than UH
7.1.6.2.2
0.02VA
<20 ms
18 ms
Return time
<60 ms
30A
3S, 10A
218
1s
Switch on capacity
30A
3S, 10A
Switch on capacity
30A
3S, 10A
Input joint
Switch on capacity
30A
3S, 10A
Distance protection
Impedance set range
Time set range:
0.1/ IH
250/ IH (
0 10S
pole difference
0.01S
Impedance characteristics:
Mho, Quadrilateral
7.1.6.2.7
circle characteristics
0.08
quadrangle characteristics
-95
0.01%IH
+95
30 S
600 S
132 V
pole difference 1 S
pole difference 0.5V
90o
600ms
pole difference 1o
pole difference 0.01ms
7.1.8.1
Range
Operation/retreat
of
sequence protection
positive
0.599.99A
Positive
delay
0-10s
sequence
breaking current
definite
time
mode
sequence
protection
Negative
Instructions
0.599.99A
220
limit
Negative
sequence
inverse
time
limit
0-10s
0.2-5A
1-9999
0-10s
0.2-60s
PT line-break
retreat
operation
and
PT line-break block
Operation:PT
line-break
block
undervoltage;retreat:PT line-break non-block
undervoltage(set as retreat upon leaving factory)
0-60s
221
Return time
104000s
0.5-1
0-1
0-10
Other
Rated current
0.5-5A
set
values
(motor)Start
1-99s
time
Process
Three-phase
fuse
operation
and retreat
Display primary
operation
and
retreat
Operation:
display
primary
side
current,voltage,power;retreat:display secondary
side current,voltage,power (set as retreat upon
leaving factory)
PT
no-load
voltage ratio
1-5000
CT
no-load
voltage ratio
1-5000
Process interlock
1 operation and
Operation:
222
act
to
trip;retreat:the
function
interlock
retreat
trip
Process interlock
1 delay
0-60s
Process interlock
2 operation and
retreat
Process interlock
2 delay
Process interlock
3 operation and
retreat
Process interlock
3 delay
Process interlock
4 operation and
retreat
Process interlock
4 delay
Communication address
1-99
Communication
mode)
baud
rate(485
0-4
0-9600;1-4800;2-2400;3-1200;4-600(
0)
0-9600;1-4800;2-2400;3-1200;4-600
(set as 0 upon leaving factory)
1-99
7.1.9
0-1
223
Front panel
Panel
The panel of this device consists of display, operational keys, shortcut keys, indication
lamps and 232 communication commissioning interface as shown in following drawing:
1.Operation
2.Interlock switching
3.Switching
4.Operation power
5.Standby power
6.Remote
7.Protection
8.Reserve
9.Receive
10.Send
Reset
Cancel
Confirm
320240 big LCD. It can accomplish measured value display, function activation and
deactivation, value setting, local manual switching, sequence of event, fault recoding
checking and pringting in coordination with operational keys.
Operational keys
There are totally 7 operational keys, they are:
Directional keys (,,,): four direction keys can be used to move the menu focus)
Reset: Reset the master and slave CPU simultaneously and clean the signal.
Shortcut keys
There are 5 shortcut keys
Shortcut keys 1~4: Have different functions in different interface. The specific function
will be displayed in right shortcut column on LCD. The function of these keys can also be
defined based on the need of users.
Shortcut key 5: it is also called help hotkey. Press this button in all interfaces (not default
interface), relevant help will appear. In default interface, the current operation state will
be shown in fast display for users to check.
Indication lamp
There are totally 10 indication lamps in the panel:
Operation : It will flicker slowly in normal operation and quickly in interlock state. When
the device is in commissioning or operation without CPU, this lamp should be off.
Interlock switching: When it is on, the device is in interlock state so the switching logic
can not be implemented.
Switching: When it is on, the switching is just finished, it will be off after reset.
Operation power: When it is on, the working auxiliary contact is closed, and when it is off,
the working auxiliary contact is open.
Standby power: When it is on, the standby auxiliary contact is closed, and when it is off,
the standby auxiliary contact is open.
Remote: When it is of, the device is in remote operation mode, and when it is off, it is
local operation mode.
Send: Communication sending lamp. It is used for comminucation between device and
portable computer.
225
226
227
AC modules (MAI400)
Change the signal of isolation transformer of site PT secondary output voltage and CT
secondary output current into small signal to main CPU plug-in modules. Both PT and
CT are high accuracy current output type.
magnified by photoelectricity and intermediate relay and then sent to relay plug-in. the
outlet command of this plug-in can usually be kept for 0.5s.
Note: There is polarity difference among outlet CLOSE OPERATION, TRIP
OPERATION, RESERVE OUTLET 1, RESERVE OUTLET 2, CLOSE STANDBY LOW,
TRIP STANDBY, CLOSE STANDBY HIGH and PROTECTION OUTLET. If it is
connected reversely, the switch can not trip or close correctly.
Terminal wiring
Power module (MPW
400)
DC+ and DC-; it is used for operation power (can be powered by 220/110V and AC/DC
power supply).
AC module (MAI
400)
Ua, Ub, Uc and Un. Auxiliary busbar voltage (three phase). If line voltage is needed,
connect with Ua, Ub and Uc. If phase voltage is needed, connect with Ua, Ub, Uc and Un
Ugz and Ugz*. Operating power voltage (auxiliary branch or generator PT voltage). It can
measure line voltage or phase voltage.
Uby and Uby*. Standby power voltage. It can meaure line voltage or phase voltage.
Igz and Igz*: operating branch current input. It can get line current or phase current.
Iba, Iba*, Ibb, Ibb*, Ibc and Ibc*: standby branch three phase current input.
400)
Protection startup (XC-1): connected with generator, transformer or G-T unit protection
contact. It can connect all outlet contacts need plant power transferring in parallel. The
connective mode is closed short impulse.
229
Protection interlock (XC-2): connected with outlet contacts of 6KV busbar protection (if
there is), operation power branch protection and HV auxiliary standby protection. The
plant power transfer station should be blocked when there proections are activated. The
connective mode is closed short impulse.
Standby auxiliary contact (XC-4)): auxiliary constant open contact of standby branch
power switch (standby power switch).
Manual switching (XC-6): switch the startup contact manually, and the connective mode
is closed short impulse no less than 50ms. This signal is only useful when the control
mode of the device is REMOTE.
Manual switching mode (XC-7): manual switching mode selective contact. The
connective mode is sustaining. It is serial connection when it is disconnected. The
switching mode when it is connected is determined by setting value REMOTE
CONTROL ASSEMBLY. If the setting value is SERIAL /PARALLEL CONNECTION, then
the connective mode is parallel connection. Ifit is PARAKKEK SIMULTANEITY, then the
connective mode is simultaneous mode. This signal is only effective when the control
mode is REMOTE.
Reset (XC-10): The connective mode is closed short impulse no less than 50ms. If the
device is blocked because the switching function is activated or there is fault ot
abnormality, eliminate the fault or abmormality firt, and then reset the signal and clean
the signal.
Close operation only (XC-12): the connective mode is closed short impulse. The ON/OFF
input value is used to send CLOSE OPERATION SWITCH command. This signal is only
effective when the control mode of the device is REMOTE.
Close standby only (XC-13): the connective mode is closed short impulse no less than
50ms. The ON/OFF input value is used to send CLOSE STANDBY SWITCH command.
This signal is only effective when the control mode of the device is REMOTE.
+24V(XC-15) : 24V DC power output is used to connect debugger and power the
debugger.
401)
These dodules are signal output. All signals are put out in air contact mode.
Switching finished (XG1-1and XG1-2): constant open contact. When the switch needs to
be opened has been tripped and the switch needs to be closed has been closed, the
device will send out this signal. The air contact output will be maintained until the device
is reset.
Switching abnormal (XG1-3 and XG1-4) : constant open contact. If the switch should trip
does not trip, the switch should be closed is not closed or the switching conditions can
not be satisfied within the set time after switching is started (for example, in 5s), the
device will send out signal. The signal will be sent out is air contact mode and be
maintained until the device is reset.
Switching interlock (XG1-5 and XG1-6) : constant open contact. When any of following
conditions appears, the device will carry out interlock switching automatically. The signal
will be sent out in air contact output and maintained until the interlock is unlocked.
If there is PT wire break, switch position abnormal, device internal fault, eternal
protection interlock, standby de-energization interlock or one of the switching
functions is out of operation.
Switching exit (XG1-7 and XG1-8) constant open contact. When any of following
conditions happens, the device will send out this signal and the switching operation can
not be carried out. The signal is sent out in air contact mode. When the SWITCHING
EXIT signal is sent out, the SWITCHING INTERLOCK signal will be sent out
simultaneously, when none of following conditions happens, the SWITCHING EXIT
signal will be relieved automatically and the switching can be carried out, which means
the device can be activated and deactivated reciprocately without resetting.
The switching functions of fast switching, leading phase angle, leading switching
time, residual voltage switching and long delay switching are all set on
DEACTIVATION.
Remote/local (XF1-1 and XF1-2) : Output air contact shows that the current control mode
is remote or local. It is remote when it is open and local when it is closed.
Parallel/serial (parallel/ simultaneous) (XF1-3 and XF1-4) : the remote switching mode is
parallel when the contact is open. The meaning of connection is determined by setting
value REMOTE SWITCHING SET. If the setting value is PARELLEL/SERIAL, then the
connective mode is serial mode, but if it is PARALLEL SIMULTANEOUS, it is
simultaneous mode.
Protection activation (XF1-5 and XF1-6) and protection deactivation (XF1-7 and XF1-8) :
not in use now.
231
Switch position abnormal (XG2-1 and XG2-2) : constant open contact. Switch position
abmormal signal. When any of following conditions happens, the device will be blocked
automatically and sends out this signal. The signal will be sent out in air contact mode
and maintained until the condition is eliminateda and the device is reset.
Switch position abnomal includes : full open or full closed during energization, close the
operating brach during operation to result in full closed or close the standby branch
during operation to result in full closed, open standby during the operation to result in
full open, the switch is full open or closed in single operation, faulse opening of
operation branch and PT disconnector open.
Standby de-ergization interlock (XG2-3 and XG2-4) : constant open contact. When the
auxiliary busbar is powered by operation power, the standby power is backup power.
When the auxiliary busbar is powered by standby power, the operation power is backup
power. When the voltage of backup power is lower than set value and the backup power
loss interlock is activated, this contact is closed. The signal is sent out in air contact
output and maintained until the power loss is relieved.
Note : when the standby PT is in maintenance, the backup power loss interlock function
can be exited via value setting menu, the device can still be switched, but the switching
mode is different with normal switching mode. The device can still carry out switching
when no power loss. But it can only accomplish residual voltage switching and long
delay switching when there is power loss.
PT wire break (XG2-5 and XG2-6) : constant open contact. The device will be blocked
and send out signal automativally when it is detected to have wire break on busbar. The
signal will be sent out in air contact output and maintained until the fault is eliminate and
the device is reset.
Device abnormal (XG2-7 and XG2-8 ) : constant open contant. If the device detects that
there is abnormality, it will be blocked and send out signal automatically. The fault
condition can be checked in the fault report. The signal is sent out in air contact output
and maintained until the fault is eliminated and the device is reset.
Reat acceleration activation (XG2-9 and XG2-10) : constant open contact. Thid contact
will be closed simultaneously to start the rear acceleration function of branch protection
when the deviceswitching is started. The time of duration of contact closing is the
switching time plus 500ms.
Single close allowed (XF2-1 and XF2-2) : constant open cantact. If the current operation
allows single close operation, this signal will be sent out.
Reserve 1, 2, 3 and 4 (XF2-3, XF2-4, XF2-5, XF2-6, XF2-7, XF2-8, XF2-9 and XF2-10) :
constant open contact. It is reserved for the expansion of the device.
401)
Close operation (XE1-1 and XE1-2) : close the operation power switch outlet contact.
This contact is current self-holding type. When it is connected, it will be relieved
sutomatically after the auxiliary contact of operation power switch on closing circuit. This
outlet has polarity difference. XE1-1 is connected to positive end while XE1-2 is
connected with negative end.
Trip operation (XE1-3 and XE1-4) : trip operation power switch outlet contact. This
contact is current self-holding type. It will be relieved after the auxiliary contact of
operation power switch on trip circuit is open when it is connected. This outlet has
polarity difference. XE1-3 is connected with positive end and XE1-4 is connected with
negative end.
232
Reserved outlet 1 (XE1-5 and XE1-6) and reserved outlet 2 (XE1-7 and XE1-8) :the
reserved outlet contact of the device. The connective mode is similar with above. The
outlet has polarity difference. XE1-5 is connected with positive end and XE1-6 is
connected with negative end. XE1-7 is connected with positive end and XE1-8 is
connected with negative end.
Auxilaries switching 1(XE1-9 and XE1-10) and auxiliaies switching 2 (XE1-11 and XE112) : they will respectively be the outlets for section one and section two when the LV
auxiliaries switching function is needed.
400)
Close standby low (XE2-1 and XE2-2) : close standby power switch outlet contact. This
contact is current self-holding type. It will be automatically relieved after the auxiliary
contact of close circuit switch is open when it is connected. This outlet had polarity
difference. XE2-1 is connected with positive end and XE2-2 is connected with negative
end.
Trip standby (XE2-3 and XE2-4) : trip standby power switch outlet contact. The
connective mode is the same with above. This outlet has polarity difference. XE2-3 is
connected with positive end and XE2-4 is connected with negative end.
Close standby high (XE2-5 and XE2-6) : close the HV CB of standby transformer or
another outlet contact of LV side. The connective mode is the same with above. This
outlet has polarity difference. XE2-5 is connected with positive end and XE2-6 is
connected with negative end.
Protection outlet (XE2-7 and XE2-8) : not in use now. this outlet has polarity difference.
XE2-7 is connected with positive end and XE2-8 is connected with negative end.
Reserved output 1 (XE2-9 and XE2-10) and reserve output 2 (XE2-11 and XE2-12) :
reserved for device expansion.
400)
Commissioning port: used for communication port 232 connected with the computer. It is
just used for program upgrading currently, not open to users.
401)
Commissioning port: the function of this port is totally the same with 232 communication
port on the panel and used for communication with system management software.
NET1A and NET1B: on site bus 485 interface. The communication protocal can be
selected as MFC1.0 or Modbus protocol.
NET2A and NET2B: on site bus 485 interface. The communication protocal can be
selected as MFC1.0 or Modbus protocol.
GPS+ and GPS-: used for GPS timing. It requires 24V impulse signal connected from the
external.
400)
The device is equipped with a commissioning test module for the convenience of on site
commissioning. Remember to turn the module K1~K6 to open position and K7 to working
position or draw out the commissioning test module.
233
Set
type
value
Operation mode
Unit
Scope
Default
value
No
Mode1,2 and 3
Mode 1
234
Remark
Normal parallel
switching
voltage
difference
Normal parallel
switching
frequency
difference
Hz
0.02
Normal parallel
switching phase
difference
Degree
0.5
Normal parallel
trip delay
0.01
Simultaneous
switching close
standby delay
Ms
500
50
Standby HV/LV
close delay
Ms
120
Fast switching
frequency
difference
Hz
0.1
2.0
1.5
Fast switching
phase difference
Degree
0.5
60.0
30.0
10
Synchronous
switching
frequency
difference
Hz
0.1
5.0
5.0
11
Synchronous
constant leading
phase angle
-30
-120
-90
12
Synchronous
constant leading
time
Ms
13
Residual
switching
voltage
magnitude
20
235
20
20
0.50
20.0
5.00
150
60
0.50
15.0
0.50
70
25
Close circuit
total time
14
Voltage
loss
startup
switching
voltage
magnitude
20
90
15
Voltage
loss
startup delay
0.10
16
Backup power
loss
voltage
magnitude
50
17
Backup power
loss delay
ms
18
LV switch over
to
auxiliaries
section
one
voltage
magnitude
20
80
60
19
LV switch over
to
auxiliaries
section
two
voltage
magnitude
20
80
60
20
Auxiliaries
swiching section
one delay
0.0
20.0
0.5
21
Auxiliaries
swiching section
two delay
0.0
20.0
9.0
22
Initial
angle 1
phase
Degree
0/30.0/60.0/9
0.0/120.0
Related to
actual wiring
of voltage
23
Initial
angle 2
phase
0/30.0/60.0/9
0.0/120.0
Related to
actual wiring
of voltage
24
No
current
criterion
set
value
0.10-2.00
0.50
5.00
90
200-500
236
40
1.00
80
200
25
0.5-10.0
26
Single operation
no voltage set
value
27
Single operation
synchronous
phase difference
Degree
28
Single operation
synchronous
phase difference
29
Single operation
synchronous
frequency
difference
9.0
0-60
60
0.5-60.0
Hz
30.0
0-20
20
0.1-2.0
1.5
Scope
Default
value
Remote/local
Remote
Control mode
Protection
mode
switching
Serial/simultaneous
Serial
Serial/simultaneous
Serial
Parallel
auto
Remote
parallel
switching mode
Semi-auto/auto
Auto
Parallel /serial,
simultaneous
parallel
Activation/deactivation
237
Parallel /
serial
Activatio
n
Remark
Fast switching
Activation/deactivation
Activatio
n/deactiv
ation
Synchronous
phase angle
leading
Activation/deactivation
Deactivat
ion
10
Synchronous
time
leading
Activation/deactivation
Activatio
n/deactiv
ation
11
Residual
switching
voltage
Activation/deactivation
Activatio
n/deactiv
ation
12
LV switch over to
auxiliaries section 1
Activation/deactivation
Deactivat
ion
13
LV switch over to
auxiliaries section 2
Activation/deactivation
Deactivat
ion
14
Backup power
interlock
Activation/deactivation
Activatio
n/deactiv
ation
15
Switching
activation/deactivation
Activation/deactivation
Activatio
n/deactiv
ation
16
Single
operation
activation/deactivation
Activation/deactivation
Deactivat
ion
17
No current criterion
activation/deactivation
Activation/deactivation
Deactivat
ion
18
Long
delay
activation/deactivation
Activation/deactivation
Deactivat
ion
19
Activation/deactivation
Deactivat
ion
20
Single
operation
synchronous
close
activation/deactivation
Activation/deactivation
Deactivat
ion
loss
123
Operation mode: there are three sets of set value for the device, they are respectively
called operation mode1, 2 and 3.
238
Simultaneous switching close standby delay: if the switching mode is simultaneous, then
TRIP WORKING (standby ) command will be sent, the command to close standby
(working) LV switch will be sent after a time delay set according to the set value.
Standby HV/LV close delay: when the CLOSE STANDBY HIGH command is sent, the
device will send CLOSE STANDBY LOW command after this time delay.
If the switching mode of fast switching frequency difference and fast switching phase
difference is fast switching, then the device will send CLOSE command when the
frequency and phase difference on two sides of switches to be closed are lower than the
fast switching frequency and phase difference.
Synchronous constant leading phase angle: when the frequency difference on two sides
of switch to be closed is lower than synchronous switching frequency difference, the
device will send CLOSE command if the angle difference of switch on both sides is within
the set value scope.
Synchronous constant leading time: this value is usually set based on the ingerent total
delay of standby switch close circuit.
Residual voltage switching voltage magnitude: if the switching mode is residual voltage
switching, then the busbar voltage is less than this set value and the device will send out
CLOSE command. The default value is 25.
Voltage loss startup voltage magnitude and delay: when the busbar voltage is less than
voltage loss startup voltage magnitude, in-coming current is less than no current set
value and the duration exceeds voltage loss startup delay, the conditions of voltage loss
startup are satisfied. Because the voltage during voltage loss startup is very low, the
device usually uses residual switching and long delay switching. The fast switching and
synchronous swiching usually fail because the working condition fail to meet
requirements.
Backup power loss voltage magnitude and backup power loss delay: when the standby
side voltage is lower than backup power loss voltage magnitude and the time exceeds
backup power loss delay, the condition of backup power loss is satidfied. If the backup
power loss interlock control word is activated, then the device will carry out switching
interlock. The default value is 80% and 200ms.
startup. If the condition does not allow all loads to startup up automatically, disconnect
some unnecessary loads to be directly useful for auto startup of other important motors..
this device is equipped with two LV load decreasing outlet which can set voltage and
time delay respectively. The LV load decreasing function is only effective during device
switching. The default value are 60%, 60 , 0.5s and 9.0s.
Initial phase angle difference 1: it is used to compensate phase angle difference between
standby transformer power voltage and busbar voltage caused by wiring and so on. the
default value is 0. For instance, assume that the busbar voltage and standby power
voltage is the same phase, and they are connected via Y/Y-12 transformer, then if the
standby power takes UAN and busbar takes UAN, the set initial phase angle1 difference
is 0 degree. If the standby power takes UAN and busbar takes UAB, the initial pgase
angle difference 1 is -30 degree. If the standby power takes UAC and busbar takes UAB,
the initial phase angle difference 2 is -60 degree.
Initial phase angle difference 2: it is used to compensate phase angle difference between
working power voltage and busbar voltage caused by wiring and so on. The default value
is 0. For instance, assume that the busbar voltage and standby power voltage is the
same phase, and they are connected via Y/Y-12 transformer, then if the standby power
takes UAN and busbar takes UAN, the set initial phase angle2 difference is 0 degree. If
the standby power takes UAN and busbar takes UAB, the initial pgase angle difference 2
is -30 degree. If the standby power takes UAC and busbar takes UAB, the initial phase
angle difference 2 is -60 degree.
No current criterion set value: in faulty trip startup logic, if the CB is tripped and the
current is lower than this set value, the device will enter faulty trip logic. The no-current
criterion in faulty trip can be activated and deactivated with control word no-current
criterion. The default value is 0.5A.
Long delay set value: when the long delay switching is in operation, after the switching is
started, the device will send out CLOSE command after time delay set by this set value.
Single operation no voltage set value: In switch single close, when the voltage on any
one side of the working switch is lower than this set value, the no voltage close condition
is satisfied. The default value is 60.
Control mode: only when the control word is REMOTE, can manual switching and single
operation be carried out on remote control console or DCS system. Then the local (on
the device) manual switching and single operation can not be operated. When the
control word is set LOCAL, the manual switching and single operation can be carried out
on the device and then the remote operation can not be carried out. The default value is
REMOTE.
Protection switching mode: this condtro word is used to determine the switching mode
under protection startup mode. The default value is serial.
Voltage loss switching mode: this control mode is used to determine switching mod
under voltage loss mode. The default value is serial.
240
Local manual switching mode: this control word is used to determine the switching mode
under local manual switching mode. The default value is parallel auto.
Remote parallel switching mode: this control mode is used to determine parallel auto ot
parallel semi-auto mode during remote manual serial switching.
Remote switching assembly: this control word determines the selection scope of control
mode during remote manual switching. When this control modes selects parallel/serial
mode, the remote control can only select serial or parallel. When this control word
selects parallel/simultaneous mode, the remote manual switching can only select parallel
or simultaneous.
Voltage loss startup: this control word demines if the voltage loss startup mode will be
activated. The default value is activated.
Fast switching: this control word is used to determine if the fast switching mode is
activated in serial or simultaneous switching. The default value is activated. Note: the
parallel switching mode also uses fast switching, but it is not affected by this set value.
Synchronous leading phase angle: this control word is used to determine whether the
synchronous leading phase angle switching mode is activated. The default value is
deactivated.
Synchronous leading teme: this control word is used to determine if the synchronous
leading switching mode is activated. The default value is activated.
Residual vaoltage switching: this control word is used to determine if the residual
switching mode is activated. The default value is activated.
LV switching auxiliaries section 1 and section 2: these two set value are used to
determine if the function of LV switching auxiliaries section 1and section 2 is activated.
The default value for both sections is deactivated.
Backup power loss block: when this control word is activated, if the backup power loss
block conditions are satisfied, then the switching function of the device will be blocked,
none of switching mode can be carried out. When some conditions like PT maintenance
happen, the backup power loss block needs to be deactivated temporarily. When this
control word is deactivatedm even backup power loss conditions are satisfied, the device
will not be blocked and can still carry out switching. But the switching mode is different
with normal switching mode. Only residual switching and long delay switching can be
carried out when there is backup power loss but no block.
Switching activation and deactivation: in this control word setting, the device is blocked
so none switching can be carried out when this control word is deactivated. The default
value is activated.
Single operation activation and deactivation: in this control word setting, the single
operation is blocked when the control word is deactivated. The default value is
deactivated.
No current criterion activation and deactivation: this control word is used to determine if
the no current criterion needs to cooperate with faulty trip startup logic. If this control
word is activated, then we need to figure out if it is faulty trip after the switch is trip based
on no current criterion set value. If this control word is deactivated, then no current
criterion when faulty trip startup. The default value is deactivated.
Long delay switching activation and deactivation: this control word is used to determine if
the long delay switching needs to be activated. The default value is deactivated.
241
Single operation closing activation and deactivation: this set value is used to determine if
no voltage closing mode is allowed when single switch closing. The default value is
deactivated.
Single operation closing activation and deactivation: this set valur is used to determine if
the synchronous closing mode is allowed when single switch closing. The default value is
deactivated.
7.1.10
Range
Instruction
Main
incoming
selection
lead
Auto-operation
action
operation and retreat
Operation:the
function
retreat: the function exits
operates,
Auto-restore
action
operation and retreat
Operation:the
function
retreat: the function exits
operates,
External
joint
block
operation and retreat
Operation:the
function
retreat: the function exits
operates,
Overcurrent
block
operation and retreat
Operation:the
function
retreat: the function exits
operates,
PT
Operation:the
operates,
line-break
block
242
function
10-400V
10-400V
Incoming
lead
voltage value
10-400V
0.5-5A
0.5-5A
0-10s
0-10s
0-10s
0-10s
with
Exit
1-5000
1-5000
line
overcurrent
operation and retreat
line
value
overcurrent
set
Operation:the
function
retreat: the function exits
0.5
99.99 A
0-60s
operates,
line
accelerating
operation and retreat
line
current
accelerating
Operation:the
function
retreat: the function exits
0 .5 99.99 A
0-3s
line
overcurrent
0.5
99.99 A
243
operates,
operates,
0-60s
line
accelerating
operation and retreat
7.1.11
operates,
0.5
99.99 A
0-3s
Communication address
1-99
Telecommunication baud
rate (485 mode)
0-4
0- 9600 1-4800
3-1200 4-600
0-1
2-2400
7.1.11.1
Technical index
7.1.11.1.1
7.1.11.1.2
All of the input binary(parallel connection points selection, remote reset, start
synchronization work, single-side no voltage close confirm,no-voltage no-load
close confirm, circuit breaker auxiliary joints,etc.) are normal open spare joints.
7.1.11.1.3
7.1.11.1.4
7.1.11.1.5
Working power supply 220V DC power supply, power consumption is less than
20volt-ampere.
Insulation intensity: weak electricity circuit against ground
Strong electricity circuit against ground
50V 50Hz/min
2000V 50Hz/min
1000V 50Hz/min
50(C
storage temperature:
automatic equipment
7.2.1
7.2.1.1
7.2.1.2
7.2.1.3
7.2.1.4
7.2.1.5
7.2.2
7.2.2.1
7.2.2.1.1
7.2.2.1.2
Complementary check:
1) Check after equipment alteration
2) Check after maintenance or replacement of primary equipemnt.
3) Check after the abnormal is found during operation
4) Check after accident
7.2.2.1.3
Check and acceptance of newly installed equipment should be carried out under
the following situation:
7.2.2.1.3.1
7.2.2.1.3.2
When newly installed device is put into the existing primary equipment.
7.2.2.1.3.3
When make big changes to the operating equipment or add new circuit.
7.2.2.1.3.4
The newly installed and reconstructed equipment which is not checked according
to the regulation requirement should be prohibited to be put into operation.
7.2.2.1.3.5
Periodic check must be carried out according to the time limit specified in the
regulation.
7.2.2.1.4
Checking cycle
Refer to Table 7.2.2.1.4
Table 7.2.2.1.4
equipment
245
No.
Description of equipment
Microcomputer
protection
device
including generatortransformer set protection device,
150KV busbar protection, 150KV
line protection,
LV auxiliary
transformer
protection,
motor
protection,etc.
Current
types
various
High
frequency
protection
channel(including channels used
together with communication while
maintained by commonication
department)device:1.high
frequency cable; connecting wave
filter 2.high frequency wave
transformer
of
Checking cycle
246
5
6
7.2.2.2
hindering device
7.2.2.3
Generally, periodic check during the period below on protection devices should be
made along with the primary equipment maintenance.
7.2.2.3.1
7.2.2.3.2
Line high frequency protectionbefore the protected line transfering high peak
load.
7.2.2.3.3
7.2.2.3.4
Auto reclose function of linecarry out along with circuit breaker power off period.
7.2.2.3.5
7.2.2.3.6
7.2.2.3.7
Multi-protection of the same element. If the whole check can not be arranged in
the period of protected equipment power off, it may be arranged in the season
with low probability of fault occurrence to make each set of protection device
retreat from operation in turn.
7.2.2.4
7.2.2.4.1
7.2.2.4.1.1
7.2.2.4.1.2
The rated voltage of DC test power supply shall be same as DC rated voltage of
equipment. The test branch is furnished with special safety CB. The fuse must
satisfy the safety requirement. It is not allowed to use DC branch power supply of
running equipment to test.
7.2.2.4.2
Before check at local, we need know the primary equipment and neighboring
equipment of test devices, and prepare the technical measures for system safety
operation during the check. The work principal fills out Relay Protection Safety
247
As for the setting test of equipment, it shall be carried out based on the setting
values inform provided by relevant relay protection authorities. The test principal
shall be familiar with the setting values, check the setting values complete or not
and check the ratio of current and PT in accordance with site practice or not.
7.2.2.5
7.2.2.5.1
The test shall apply suitable instruments. The measuring of insulated resistance is
generally of 1000V megger.
7.2.2.5.2
The wiring principle of test loop is to make sure electric quantity energizing device
in accordance with practical work condition. The test loop of simulation fault shall
have the conditions testing the whole set of devices. The whole set of test of
device refers to the voltage of auto device and incoming terminal of current
secondary loop energize all devices of the same protected equipment by
simulated voltage and current so as to test the actions of all devices during fault
and reclose.
7.2.2.5.3
For the test of complicated device, the simulation test loop shall be with following
conditions.
7.2.2.5.3.1
The relative phase of test current and voltage can vary within 0 0 360 0 . Test
power supply is generally 3-phase 4-wire system and test current can be single
phase but with conditions energizing three phases. The current of single phase
can be adjusted within 0-50A equally, while, the current of simulated 3-phase
short circuit shall be not less than 20A.
7.2.2.5.3.2
There shall be logic control loop simulating fault occurring and eliminating.
Generally it can simulate following cases:
7.2.2.5.3.2.1
Varied 2-phase short circuit, 2-phase short circuit grounding and single phase
grounding fault;
7.2.2.5.3.2.2
7.2.2.5.3.2.3
7.2.2.5.3.2.4
Conversion from single phase short circuit into 2-phase grounding or 3-phase
short circuit fault after specified delay (test to complex reclose and test after
accident);
When checking complex reclose or single phase relcose device, in order to reduce the
trip and close of CB, we need prepare special 3-phase CB separate operation
simulating loop which shall meet following basic requirements:
Simulating separate phase trip and close loop basically same as practical current
Logic loop similar with convert performance and time of CB trip and close auxiliary
contacts
Light indication loop similar with functions of control panel CB position monitor light
248
The wiring type of act time test loop of device shall meet following requirements:
Try not to dismantle the wiring on loop for test of some relay act time in device loop.
As for the required relay, we shall measure the practical difference of relay act time limit
according to mutual act relationship of loops so as to know the allowance.
Act time of device measuring shall be all the time limit from tested devices fault voltage
and current until trip pulse to CB. We use the chronograph to read the time
difference between the simulated fault occurring and startup. Generally it is less
than 5ms unless special requirement. The measurement of protected device act
time shall apply electronic millisecond meter which will not be impacted power
supply frequency.
The check of HF dispatcher shall apply electronic meter with suitable frequency
range. The grounding of meter measuring terminal or connecting type of ground
potential terminal shall obey the specifications of meter application so as to avoid
error measurement.
The measurement of high frequency shall apply digital frequency meter.
Before connecting AC work frequency test power supply, we must disconnect the
grounding point in the device AC loop first. It is not allowed that there is one more
grounding point except the test power supply. When the terminal of measuring
instrument has grounding point, these grounding points must connect to the same
grounding point.
For the measuring instrument specifying grounding terminal, it is not allowed to
connect DC power supply circuit directly so as to avoid DC power grounding
when checking on site.
For the protect device applying transistor or IC element, we need pay more attention to
following items so as to avoid element from damage when checking.
The display screen shall be connected with grounding grid of substation solidly.
The measuring instruments specifying grounding terminal are not allowed to connect to
element loop directly.
There shall be the measures to prevent electrostatic induction power from introducing to
element.
7.2.2.6
7.2.2.6.1
7.2.2.6.1.1
7.2.2.6.1.1.1
Checking conditions:
Disconnect all added power supply (DC and AC power supply)
7.2.2.6.1.1.2
7.2.2.6.1.1.2.1
The quality of device, device case and auxiliary equipments, lead, terminal and
material etc:
Observe the protection cabinet (screen) and all cases have no deformation or
scratch. The color is suitable. No damage to buttons or indicator; nameplate
and vendor name are clear;
249
7.2.2.6.1.1.2.2
7.2.2.6.1.1.2.3
7.2.2.6.1.1.2.4
7.2.2.6.1.1.2.5
All standard plugs shall be sound; the plug has no damage and contact solid.
All grounding wires and copper sockets are solid;
The soleplate on cabinets and small switches are solid. The wiring of wiring
terminal is solid and reliable.
Checking of terminals wiring behind cabinet
The marks on terminals are clear; the specifications and numbers of wiring
terminals shall be completely consistent with design drawing. Use
corresponding screw driver to tighten the screws of wiring terminals. There
shall be spring sheets and other vibration-proof sheets on fixed screws to
ensure the wiring solid. The link between inner and outer terminals of TA
secondary wiring on terminal strip is sound. The fixed screws shall be
tightened. All metal conductors of terminal strip wiring shall contact terminals
reliably and the gap has no insulation objects. The wiring terminals shall have
plastic tubes with tabs and the tabs shall be clear.
7.2.2.6.1.1.2.6
7.2.2.6.1.1.3
7.2.2.6.1.1.4
7.2.2.6.1.1.5
The outer checking of all relays shall be carried out according to related test
regulations.
7.2.2.6.1.1.6
7.2.2.6.1.2
7.2.2.6.1.2.1
7.2.2.6.1.2.2
7.2.2.6.1.2.3
7.2.2.6.1.2.4
Check if signal relay is sound and check the correctness of output loop
wiring;
7.2.2.6.1.2.5
Check if trip relay is sound and check the correctness of output loop wiring;
7.2.2.6.1.2.6
7.2.2.6.1.2.7
7.2.2.6.2
7.2.2.6.2.1
7.2.2.6.2.2
7.2.2.6.2.3
7.2.2.6.2.4.1
7.2.2.6.2.4.2
Check the grounding points and grounding status of current secondary loop.
Only one grounding point is allowed in one current loop.
7.2.2.6.2.5
7.2.2.6.2.5.1
7.2.2.6.2.5.2
7.2.2.6.2.5.3
7.2.2.6.2.5.4
Check the erection sites of all fuses of PT secondary loop and check if the
fusing current is proper (the fusing current of fuse need be decided by test);
check the quality and selectivity. Check if the fuse coil impedance is proper.
7.2.2.6.2.5.5
7.2.2.6.2.6
7.2.2.6.2.6.1
7.2.2.6.2.6.2
All secondary loop grounding and cells in one cable; the regular check is only
to measure all secondary loop grounding insulation.
7.2.2.6.2.6.3
7.2.2.6.2.6.4
For the current and voltage loop newly run or varied, we shall check voltage
loop by work voltage directly. Check the correctness of current secondary
loop wiring by load current;
7.2.2.6.3
7.2.2.6.3.1
Check the open and close of auxiliary contacts related with protection loop or
the switchover time of these contacts;
7.2.2.6.3.2
7.2.2.6.3.3
7.2.2.6.4
7.2.2.6.4.1
Clean all elements of microcomputer and auto devices and carry out
necessary maintenance. The elements including: power supply related with
device, operate handle, button, plug, protection soleplate, socket, location
indicator, central signal device, terminal strip, cable and fuse in these
elements loop etc.
251
7.2.2.6.4.2
Insulation measurement
7.2.2.6.4.2.1
7.2.2.6.4.2.2
Test method: under normal test atmosphere, connect all terminals of current,
voltage, DC control signal loop respectively together; measure all loops
grounding by 1000V megger; the insulation resistance of all electric contact
loops shall be more than 100 M.
7.2.2.6.4.3
7.2.2.6.4.3.1
Medium intensity
Technical requirement:
Among all conduct loops grounding and the loops, the loops of rated
insulation voltage more than 60V shall be able to bear 2.0kV work frequency
voltage or 2.8kv DC voltage; the loops of rated insulation voltage not more
than 60V shall be able to bear 500V work frequency voltage or 710V DC
voltage for 1 minute without breakdown, flashover or element damage;
7.2.2.6.4.3.2
Test method:
In the place of cabinet grounding with copper strip, remove all grounding
wires (except cabinet shield wires) to insulation locations; keep all except the
plate of upper weak circuit drawing out and keep together if there is operate
cabinet in one cabinet (short-circuit wire is generally connected). Connect the
grounding wire of voltage proof device to cabinet grounding wire and connect
HV output terminal to voltage proof wire on terminal; the select time on
voltage proof device is 60s; input 2KV work frequency voltage; if the voltage
proof device has no alarm, it is qualified; if it has alarm, check related plugs.
Test result: details see Insulation Performance Test Table
Insulation performance test table
Test location
Insulation
resistanc
e
Medium intensity
Voltag
e
Test result
K
V
AC input to ground
100 M
2.0
DC input to ground
100 M
2.0
100 M
2.0
100 M
2.0
AC input to DC input
100 M
2.0
100 M
2.0
100 M
2.0
100 M
2.0
7.2.2.6.5.1
7.2.2.6.5.3
7.2.2.6.5.4
7.2.2.6.5.4.1
Added faults equal to 0.95 and 1.05 of protection set values respectively,
observe the act of various sections of protections. When inputing 0.95 of set
value, the protection shall be reliable without act; when 1.05, the protection
shall act reliably.
7.2.2.6.5.4.2
For the logic loop with and condition, we need confirm by test. As long as
one conditions lost, the protection shall not act or no act in outlet.
7.2.2.6.5.4.3
Static stability test: adjust the static test according to commissioning guidline;
increase or reduce the electric quantity inputing to protection slowly until the
protection act. Record the added electric quantity when protection acts.
7.2.2.6.5.4.4
7.2.2.6.5.5
7.2.2.6.5.6
7.2.2.6.5.7
7.2.2.6.5.8
7.2.2.6.5.9
7.2.2.6.5.10
7.2.2.6.5.11
7.2.2.6.5.11.1
7.2.2.6.5.11.2
7.2.2.6.5.11.3
7.2.2.6.5.12
MMI display is clear and stable; the operate course, corresponding functions
and display sequence are in accordance with instructions.
7.2.2.6.6
7.2.2.6.6.1
7.2.2.6.6.2
7.2.2.6.6.3
After one equipment unit power off, we shall check if the indications of all
signal loops are correct when checking the protection. The signal loop
equipmet may not be checked separately.
7.2.2.6.7
7.2.2.6.7.1
Disconnect all loops induced from outside and cables at terminal strip of
protection screen. Connect all terminals of current, voltage and DC control
signal loop together. Measure the following insulation resistance by 1000v
megger. The values shall be more than 10M.
7.2.2.6.7.1.1
7.2.2.6.7.1.2
7.2.2.6.7.2
7.2.2.6.7.3
Carry out voltage proof test once every 5 years to running equipment and its
loops; when insulation resistance more than 1M, it is allowed to replace in
the way of measuring insulation resistance by 2500V megger temporarily.
7.2.2.6.8
7.2.2.6.8.1
7.2.2.6.8.2
For basic check items of all common relay and auxiliary equipment and
standards to intermediate relay, the check items are as following:
7.2.2.6.8.2.1
7.2.2.6.8.2.2
7.2.2.6.8.2.3
For the relay with two or more coils, we shall check the correctness of polarity
indication among coils and measure the insulation resistance between two
coils.
7.2.2.6.8.2.4
7.2.2.6.8.2.5
Act (reset) time measurement is to protect the relay and output intermediate
relay having requirement to act (reset) time in protection loop design and to
prevent from tripping relay.
For the grid protection used to super HV and intermediate relay directly used
to CB trip, the act time shall be less than 10ms.
The act current preventing from tripping relay shall be suitable to intermediate
relay directly acting to CB trip. Under the same actual CB trip current, the act
254
time of relay shall be less than the convert time of trip CB auxiliary contact.
In regular check, the act time check and the whole set test of device shall be
carried out together.
7.2.2.6.8.3
7.2.2.6.8.3.1
7.2.2.6.8.3.2
7.2.2.6.8.3.3
7.2.2.6.8.4
7.2.2.6.8.4.1
Act voltage (current) check: for the serial signal relay reflecting current act,
the voltage drop shall not exceed 10% of work DC voltage.
7.2.2.6.8.4.2
When several signal relays are parallel and possible least intermediate relays
are serial connected, check the reliability of act.
The display voltage (act current) of signal relay shall be lower than act
voltage of connected relay. And check the protect screen will have to error
display when possible outside vibration occurs.
7.2.2.6.8.4.3
7.2.2.6.8.5
7.2.2.6.8.5.1
The act and reset value when act graduations are at max, min and
intermediate positions;
7.2.2.6.8.5.2
7.2.2.6.8.5.3
For LV relay, input running voltage respectively and check it has no shake.
7.2.2.6.8.5.4
For induction relay of reverse time limit, we shall record the current in min
graduation and set valuetime characteristics curve.
7.2.2.6.8.6
7.2.2.6.8.6.1
Check the latent act of relay current and voltage. It is not allowed to have
latent act with act direction, but allowed to have small non act direction
(reverse) latent act.
7.2.2.6.8.6.2
Check the act zone of relay and check the correctness and sense angle of
current and voltage coil polarity indication in accordance with technical
instructions.
7.2.2.6.8.6.3
Under the condition of max sense angle or within 200 difference, measure the
min act volt-ampere and lowest act voltage;
7.2.2.6.8.6.4
7.2.2.6.8.6.5
Check the act of contacts in the case of possible max short-circuits capacity
to obverse and reverse phases;
7.2.2.6.8.7
7.2.2.6.8.7.1
7.2.2.6.8.7.2
Adjust, measure and record max sense angle, act impedance and reset
impedance.
7.2.2.6.8.7.3
In regular check, calibrate the static min act current and min accurate work
current in setting position.
7.2.2.6.8.7.4
determine the max and min act impedance; and calculate the excursion.
7.2.2.6.8.8
7.2.2.6.8.8.1
The test items of process equipments such as damper, connect filter and HF
cable etc. in relay protection special HF channel shall be in accordance with
electric power carrier wave communication regulations.
7.2.2.6.8.8.2
Open HV side of connect filter in channel (close GDS) and after remove the
grounding point, measure the insulation resistance to ground of connect filter
secondary side (including HF cable) and primary side and insulation
resistance in primary and secondary bays.
7.2.2.6.8.8.3
7.2.2.6.8.8.4
For the special HF channel, the result of transmission attenuation test shall
satisfy the channel allowance of dispatcher receiving signal not less than
8.6dB when it is new and some device is replaced or added, otherwise the
protection is not allowed to run.
7.2.7.7
7.2.2.8
7.2.2.9
from Nanjing
7.2.2.10
from Nanjing
from Nanjing
7.2.2.11
7.2.2.12
7.2.2.15
7.2.2.16
7.2.2.17
The maintenance items and standards uses the MFC 2000-3A type
mirco-auxiliary Quick Shut Device Instructions from Jiangsu Jingzhi Co.,
Ltd.
7.2.2.18
7.2.3
7.2.3.1
7.2.3.2
7.2.3.3
Measure the phase of all current differential protection CT and the differential
current (differential voltage) in differential loop so as to distinguish the
correctness of loop wiring and current ratio compensate loop.
7.2.3.4
7.2.3.5
For the transformer differential protection, we need check if the protection can
be impacted by excitation surge in the way of running transformer under full
voltage.
257
7.2.3.6
7.2.3.7
7.2.3.8
7.2.4
7.2.4.1
Cover all protection devices, relays and auxiliary equipments well. Take antidust measures to necessary elements.
7.2.4.2
Dismantle the test equipment, instrument and wires used in check and clean
the site. All dismantled or temporary wires shall be resumed and all signal
devices reset.
7.2.4.3
Relay protection personnel explain the check results to operators and clarify if
the protection device can run.
7.2.4.4
The operators must check and prove the protection device has no trip or
close impulse in the way of one end to ground measuring voltage according
to signal light indication or high internal resistance voltmeter before running
protection device. And then the operators can connect the linkage sheet of
protection device to operation positions.
7.2.4.5
The relay protection check personnel shall complete the check report in
specified time. The technician in this group shall check carefully. Take
necessary measures as the case may be if the problems impacting protection
running are found.
7.3
7.3.1
7.3.2
8.1
General description
8.1.1
8.1.2
8.1.3
8.1.3.1
Preventative test
Preventative test is checking, test and monitoring (including oil sampling and
air sampling) to the equipment to find out the potential problem and prevent
accidents or equipment damage.
8.1.3.2
Insulation resistance
The ratio of DC current and voltage value applied between two electrodes of
insulation structure and discharge current value flowing through these
electrodes. The insulation resistance value is usually measured directly with a
megameter.
8.1.3.3
Absoor[tance
The insulation resistance value ratio of insulation resistance when 1min and
insulation resistance when 15s in the same test.
8.1.3.4
Polarization index
The insulation resistance value ratio of insulation resistance when 10min and
insulation resistance when 1min.
8.1.3.8
8.1.4
This test results should be campared with all precious resuts and test results
of equipment of the same type. Make a estimation after a thorough analysis
based on relevant results and changing law and trend.
8.1.5
8.1.6
The withstand voltage test should be carried out on 20KV and below
electrical equipment following this manual (except for some equipment with
special regulations). The withstand voltage test should also be carried out on
150KV electrical equipment if necessary.
8.1.7
When the voltage during 50Hz AC voltage withstand test reaches test
voltage, the duration time should always be 1min if there is no special
instruction. The voltage application time for other voltage withstand test is
regulated in test requirements of relevant equipment.
8.1.8
The voltage withstand test for oil filling equipment can only be carried out
after sufficient delay duration when it is filled with oil. The delay duration
should meet following requirements according to the rated voltage of the
259
48h
24h
8.1.9
When carrying out voltage withstand test, all equipment connected together
should be separated to do test (not including complete set equipment
assembled by manufactuere), but the equipment of same test voltage can be
tested together. The electrical equipment with different test voltage in single
test can be tested together with other equipment if it is difficult to carry out
single test. Then the test voltage should uses the minimum test voltage in all
connected equipment.
8.1.10
When the rated voltage of electrical equipment is different with rated voltage
used in actual operation, the test voltage should be confirmed based on
following rules:
8.1.10.1
When equipment with high rated voltage is used to strengthen the insulation,
the test voltage should be ascertained by the rated voltage of the equipment.
8.1.10.2
8.1.11
When carrying out all tests relevant with temperature and humidity (like
measuring DC resistance, insulation resistance, tg and leaked current),
measure the temperature of the test subjects and temperature and humidity
of ambient air.
The temperature of test subject in insulation test should not be lower than
+5. The outdoor test should be carried out in good weather and relative air
humidity should not be higher than 80%.
8.1.12
8.1.14
8.2
8.2.1
8.2.1.1
All test personnel should be familiar with relevant part in Safety Code of
Electrical Industry and relevant HV test codes and pass the exam.
8.2.1.2
8.2.1.3
equipment.
8.2.1.4
The responsible person must fill test report when all high voltage work is
finished. The test report should be checked by foreman or technician and
handed in to technical department in three days. If the report is for
preventative test of unit major overhaul, it should be handed in 10 days after
the work is finished.
8.2.1.5
8.2.1.6
Each test should be carried after with the permission of respondible person.
The operator should report timely when the voltage gets to standard value.
Cut off the power supply and report to the responsible person timely when the
voltage is decreased.
8.2.1.7
8.2.1.8
Assembly and disassembly of test power must be carried out by two persons.
Work permission procedures must be implemented when assembling and
disassembling power supply on LV distribution panel.
8.2.1.9
8.2.1.9.1
8.2.1.9.2
8.2.1.9.3
8.2.1.9.4
8.2.1.9.5
8.2.1.9.6
8.2.1.9.7
8.2.1.9.8
8.2.1.10
8.2.1.10.1
Comply with Safety Code carefully and in obedience with the command of
responsible person.
8.2.1.10.2
8.2.1.10.3
8.2.1.10.4
8.2.2
8.2.2.1
8.2.2.2
The power switch of test equipment should use disconnector with obvious
break point. The power board should be right beside the switchyard operator
so that the operator can cut off the power supply quickly.
8.2.2.3
The test equipment should be laid steady and firmly and be close to the test
subject as much as possible. The HV lead wire should be short and
supported with insulation objects if necessary.
261
8.2.2.4
The test equipment should be packaged and banded when loading in a truck
for transporting to avoid vibration or hitting damage on the equipment.
8.2.2.5
All test equipment should be thoroughly checked before and after unit major
overhaul.
8.2.2.6
The test instruments and meters should be regularly calibrated once every
year to guarantee accuracy of the test.
8.2.2.7
The test equipment should be placed in dry and clean place and avoid
extrusion, piling and dust.
8.2.2.8
8.2.2.9
The insulation tools used in the test should be carried out with AC voltage
withstand test once a year. Check the voltage withstand before the test if
necessary.
8.2.2.10
The other department should get the approval from the test department if
they need to borrow the test equipment and carry out relevant procedures.
The returned equipment should pass the acceptance. If there is damage, the
test department should claim for compensation to the borrower.
8.2.3
8.2.3.1
The power supply should be cut off; external connection wire should be
completely dismounted and there should be obvious break point, then the test
can be carried out.
8.2.3.2
8.2.3.3
The external surface of the test subjects should be clean and dry. Do
shielding treatment if necessary.
8.2.3.4
The test subject must be earthed in short circuit and discharged sufficiently.
8.2.3.5
The safe distance between test subject and energized equipment and
personnel should meet the requirement in the Safety Code of Electric
Industry.
8.2.3.6
After the voltage and the time of test subject are both in required scope,
evenly decrease the voltage to 25% below test voltage in 5s and then cut off
the power supply.
8.2.3.7
In HV DC test, when the test voltage is decreased to zero position, cut off the
power supply and discharge the test subject to ground with a discharging rod.
The test subject of large capacity need to be charged via discharging resistor
first and then directly charged. Wear insulation gloves during discharging.
8.2.3.8
The induction HV test can only be carried out when the insulation property
(insulation resistance, oil voltage withstand, medium loss and DC resistance)
of the test sunject meet requirements. The no-load characteristic should have
no obvious change before and after the test, otherwise, find out the cause.
8.2.3.9
8.2.4
8.2.4.1
The fluctuation of test power voltage in the laboratory should not be too
violent. The allowable distortion rate of sinewave should not exceed 5%. It is
better to take line voltage as test power when there is strict requirement on
waveform.
8.2.4.2
8.2.4.3
The responsible person should thoroughly check the wiring condition and test
site before the test.
8.2.4.4
Ring the alarm or inform orally before voltage increasing. Report the
increasing value during each stage of voltage increasing.
8.2.4.5
If the wiring needs to be changed after the test, cut off the power supply first.
Earth the test subject in short circuit on the voltage increasing part after the
discharging.
8.2.5
8.2.5.1
A temporary rail should be set in test site and hanging a warning board reads
STOP, HIGH VOLTAGE! Outside.
8.2.5.2
If two ends of the test subject are not in the same place, another end should
be guarded by an appointed person.
8.2.5.3
8.2.5.4
Pay attention to the superposition of test voltage and system voltage among
electrical break points.
8.2.5.5
8.2.5.6
8.2.5.7
If rain or thunder occurs during outdoor test, stop the test timely and leave the
site.
8.2.5.8
8.2.5.9
Pay attention to safe distance with energized equipment when moving long
tools like bamboo (aluminum) ladder.
8.2.5.10
8.2.5.11
Other conditions that may affect the test should be recorded on test site.
8.2.6
Others
8.2.6.1
Meters and instruments no less than 0.5 levels should be used in the test to
reduce test error.
8.2.6.2
During the test, input low voltage into the test subject first to observe if the
263
The short circuit switch for measurement should trip when rated value is
reached and will be closed immediately after reading the value. It should not
be open for too long.
8.2.6.4
Decrease the voltage, disconnect the power supply and find out the cause if
any of following condition happens:
The swaying of the measurement meter is too violent;
Flashover occurs on test subject;
Abnormal discharging sound is found on test subject.
8.2.6.5
The voltage increasing speed can never be too fast, too slow or increase to
full voltage duddennly. The voltage is usually increased from 1/2 of the test
voltage to full volume and this process should last no less than 15min. Do not
disconnect the test power when full voltage.
8.2.6.6
During the test, if discharging occurs on the surface of the test subject, as
long as the test voltage is kept and no indication change in the meter, the test
does not need to be interrupted.
8.2.6.7
The test should be carried out in good weather and the temperature of test
subject and ambient air temperature should be not lower than +5; the
relative air humidity is not higher than 80%, otherwise, the result can only be
reference.
8.2.6.8
8.2.6.9
The instrument and meter in the test site should be placed steady. The
instruments need level calibration should meet the requirement.
8.2.7
Test log
8.2.7.1
Upper layer oil temperature and tap position of the transformer must be
recorded when measuring DC resistance of transformer coils (except for dry
type transformer).
8.2.7.2
Record motor model number, site number, capacity, factory numer and
manufacturer of motor in motor test.
8.2.7.3
8.2.7.4
In order to analyze test data better after the test, record the multiplying power
grades and indication scale as well as test data if the meter used have
multiplying power.
8.2.7.5
If the phase difference of the motor lead wire can not be distinguished by
other permanent mark, it can be marked with spatial location (like up, down,
left and right), and record the phase combining with the color belt banding on
the lead wire.
264
8.2.7.6
8.2.7.7
When carrying out test on more than one cables in parallel, mark the test site
and cable, for example, front, behind, left or right. Explain this is the position
taking XX as reference object.
8.2.7.8
When carrying out voltage withstand test on some equipment, the insulation
resistance of its associated equipment should also be measured and
reflected in original record before and after the test.
8.2.7.9
The power frequency voltage withstand test can be carried out on several
equipment or two equipment simultaneously, but note which equipment is
tested together.
8.2.8
Test termination
8.2.8.1
The high voltage should be decreased to zero position. Cut off the power
supply. The test power circuit should be obviously open. Earth the test
subject in short circuit and charge sufficiently, and then restore the orihinal
wiring of the test subject.
8.2.8.2
Dismount the temporary earthing short cirxuit wire after the test. Thoroughly
check the test subject to prevent anything left on the test equipment.
8.2.8.3
Compare the test result with previous test or factory test data, and convert
the value into the value when the temperature is 75 (or 75) based on
relevant formula.
8.2.8.4
If the value exceeds the regulation compared with precious data, find out the
cause; solve it and measure again.
8.2.8.5
If the test result does not meet the requirement and the test subject has sever
defect, report to superior department immediately.
8.2.8.6
All test personnel and equipment need to be withdrawed from the site after
the site is cleaned.
8.3
8.3.1
8.3.1.1
compare the value with the initial measurement under the same temperature.
If the value is 1/3~1/5 lower than initial value, find out the cause and eliminate
it. The unblanced coefficient should not be more than 2, and the absorptance
R60/R15 should be 1.6.
8.3.1.2
The coil to ground and inter-phase AC voltage withstand test 1.5UN should
be one minute when there is water or the residual water is blown dry in the
stator.
Carry out stator DC voltage withstand test and measure the leaked current
before and after the generator major overhaul or after winding replacement.
The voltage will stay in each stage for 1min when increasing from 1.5UN to
2.5UN, and following criterions need to be met:
Leaked current should not increase with the time;
The phase difference among phases should not be 100% higher than
minimum value;
The maximum leaked current is below 20A;
The inter phase difference should have obvious change compared with initial
test result;
The earthing plates on the flange of steam excitation collecting pipe and
stator coil out-going assembly water pipe should be disconnected.
8.3.1.4
8.3.1.5
8.3.1.6
8.3.1.6
8.3.1.7
Measure the insulation resistance of steam and excitation collecting pipe and
stator out-going collecting pipe.
The insulation resistance measured with 1000V megger should be 30K
(manufacturer regulation when with water); and it should be 100K when
there is no residual water.
8.3.1.8
The stator out-going bushing should bear 64500V AC power frequency dry
arc electrical strength after major overhaul, and the test takes 1min.
8.3.1.9
266
initial value.
8.3.1.10
8.3.1.11
8.3.1.12
8.3.1.13
8.3.1.14
8.3.1.15
Carry out stator iron core test when there is partial damage, partial high
temperature and suspect that there is short circuit duting major overhaul. The
highest temperature of iron tooth should not exceed 15 and temperature
among tooth should not exceed 15.
8.3.2
DC motor
8.3.2.1
8.3.2.2
Test items:
The periodic test items can refer to number 1 in table 2.
Major overhaul test items can refer to number 1,2,3,4,5,7 and 9 in table 2.
8.3.2.3
Numbe
r
1
Item
Insulation
resistance
winding
Period
of
Requirements
Instruction
With
1000V
megogmmeter
1.
Minor
overhaul
2.
Major
overhaul
DC resistance
of winding
Major
overhaul
DC resistance
among
armature
Major
overhaul
Compare and
judge
among
corresponding
winding
blades
blades
AC voltage
withstand test
of winding
Major
overhaul
The armature to
shaft AC voltage
withstand test
can be replaced
by
2500V
Megohmmeter
test.
Adjust central
position
of
carbon brush
Major
overhaul
Do no spark
reversing test if
necessary.
Check
the
polarity
of
winding and
the
correctness of
its connection
During
connection
change
Polarity
and
connection
should be correct.
Measure the
air clearance
between
armature and
magnetic pole
Major
overhaul
The
deviation
of
air
clearance of each point and
average value:
No-load run
check of DC
motor
1.
After
major
overhaul;
2.
After
winding
replacemen
t
8.3.3
AC motor
8.3.3.1
Numbe
r
Items
Insulation
resistance
and
absorptance
of winding
Period
1.
Minor
overhaul;
2.
Major
overhaul.
Requirements
Instruction
1) Insulation resistance:
1)
The
absorptance
should
be
measured if the
motor
is
of
500kW or above.
DC
resistance
of winding
1) One year
(6KV and
above or
100KW and
above
motor)
2)
Major
overhaul
3)
Minor
overhaul
Stator
winding
leaked
current and
DC voltage
withstand
test
1)
Major
overhaul;
2) winding
replacemen
t
AC voltage
withstand
test of stator
winding
1)
After
major
overhaul
2)
After
269
2) Use 1000V
Megohmmeter
on motor below
6.3KV;
use
2500V
Megohmmeter
on motor of or
above 6.3KV.
winding
replacemen
t
5
Check the
polarity of
the stator
winding
When
connection
changes
1) Check if the
connection
of
two branches is
correct
for
double windings
motor.
2) Do not check
the polarity if the
neutral point is
not led out.
Stator iron
core test
1) When all
windings
replacemen
t or after
iron core
repair
1) This test is
carried out on
motor of 6KV or
above 500kw;
2) If there is no
partial defect on
stator iron core,
just need to
check
overall
condition, then
we can only
measure the noload loss value.
2)
When
necessary
When
necessary
1) The no-load
run checking is
no less than 1h;
2)
No-load
current is only
measured when
we suspect there
is
something
wrong with the
motor;
3) Only the noload
current
needs to be
measured
for
motor of below
6KV. Do not
270
measure no-load
loss.
8.3.3.2
Test items:
Periodic test items refer to number 1 and 2 in table 3.
Test items in major overhaul refer to number 1, 2, 3 and 4 in table 3.
8.3.4
Power transformer
8.3.4.1
Items
Period
Requirements
Chromatograp
hic study of
gas dissolved
in the oil
1) 6 months
for
main
transformer
and
HV
auxiliary
transformer
is regulated
based on
their own
requirement
s
winding
DC
resistance
1)
1~3
years
or
regulated
by
themselves;
2) After the
tap position
of
no
excitation
regulation
transformer
is changed.
Instruction
1) All hydrocarbons
include
CH4, C2H6,
C2H4 and C2H2.
2) If the dissolved gas
content
has
the
increasing
trend,
judge
with
the
combination of gas
production
rate,
shorten the period to
for tracking analysis if
necessary;
3) Do not judge with
the combination of
gas production rate
for the equipment with
low
hydrocarbon
content.
1) If the resistance
difference
among
phases
when
production exceeds
thw required value
and the manufacturer
has explained the
cause
of
the
difference, implement
based on item 3).
2) Resistance value
during
different
3) After the
tap of tap
changer
transformer
is repaired (
on all taps);
temperature
is
calculated according
to following formula:
R2 R1
4)
After
major
overhaul;
T t2
T t1
R1 and R2 are
respectively
resistance value when
the temperature is
t1and t2. T is constant
value for calculation
which is set as 235.
5)
When
necessary
3) The transformer
without
excitation
voltage
regulation
should be measured
after the tap is locked.
3
winding
insulation
resistance,
absorptance
and
polarization
index
1)
1~3
years
or
regulated
by
themselves;
2)
After
major
overhaul;
3)
When
necessary.
Tg of winding
1) 1-3
years
or
stipulate by
itself
1
Comvert the insulation
resistance to value under the
same temperature, the value
should have no obvious
change
compared
with
previous test result.
2) The acsorpance should not
be lower than 1.3 (within 10
30 ) or the porlarity index
should not be lower than 1.5.
1) When the temperature is
20,the tg is not greater than
the following values:
66
220kV 0.8%
66
220kV 0.8%
35kV
1.5%
2 After
overhaul
3 Whe
n
necessary
272
3) Refer to the
temperature of the oil
in the top layer
tg 2 tg 1 1.3( t2 t1 ) / 10
4) Try to measure
when
the
oil
temperature is below
50 . The tg value in
different temperatures
can be calculated
through the following
formula:
tg 2 tg 1 1.3( t2 t1 ) / 10
5
The tg and
capacitance of
the capacitivetype bushing
1) 1-3 years
2 After
overhaul
1) Measure in positive
connection way
2) While measuring,
record the ambient
temperature and the
oil temperature in the
top layer of the
transformer
3 Whe
n
necessary
6
Insulation
test
oil
1) 1-3 years
2 After
overhaul
3 Whe
n
necessary
7
1) 1-5 years
(6kV and
below)
2)
2 After
overhaul
3)
After
changing of
winding
1)
1)
Conduct
in
frequency
doubling
induction or operation
wave induction
2) If no transformer of
66kV and below is
equipped, conduct the
external
power
4 Whe
n
necessary
1) 1-3 years
or stipulate
by itself
1) There is no obvious
difference comparing with the
history value
2 After
overhaul
3 Whe
n
necessary
9
Moisture
content in the
oil
Seen
in
Chapter
Insulation
oil
1
0
Air content in
the oil
Seen
in
Chapter
Insulation
oil
11
The
winding
leaking current
1) 1-3 years
or stipulate
by itself
2 After
overhaul
2) In the case of
grounding
through
clamp, measure the
clamp independently
The
windin
g rated
voltage
6
kV
20k
V
150K
V
10k
V
20k
V
40kV
1) After the
disconnecti
ng
and
connecting
of
the
tapping
DC test
voltage
1
2
frequency
voltage
withstand test
274
switch
2)After
changing
the winding
3)
When
necessary
1
3
1
4
Check
connection
type
of
transformer
After
the
winding is
changed
No-load
current and noload loss
1) After the
winding is
changed
The
3-phase
or
single-phase
test
power source can be
used.
The
rated
voltage or the lower
voltage value can be
used as the test
voltage
The
3-phase
or
single-phase
test
power source can be
used.
The
rated
voltage or the lower
current value can be
used as the test
voltage
2)
When
necessary
1
5
Short-circuit
impedance and
load loss
1) After the
winding is
changed
2)
When
necessary
1
6
Test
and
inspection of
AVR with load
1) One year
or
as
required by
the
manufactur
er
275
2)
After
overhaul
3)
When
necessary
Check
activation
sequence and
tangle
Conduct
the
manual control,
electric control
and
remote
control for 2
circulation
Measure
the
resistance
value of the
transitional
resistance
Measure
switching time
Check
the
contacting
state
of
insertion
contact,
movable
&
fixed contact
and connecting
state of electric
circuit
1
7
Check
clearance
among the odd
contacts and
even contacts
No burns or variation
Check
operation box
Insulation
oil
test of selector
switch
chamber
Accord with
requirements
manufacturer
Secondary
circuit
insulation
The
temperature
measuring
device and its
second circuit
1) 1-3 years
2)
After
overhaul
3)
When
necessary
1
8
1) 1-3 years
(secondary
circuit)
2)
After
overhaul
the
technical
of
the
2500V megger is
used while measuring
insulation resistance
3)
When
necessary
1
277
2500V megger is
used for measuring
insulation resistance
2
0
Inspection
pressure
releaser
of
Whole sealing
inspection
When
necessary
The
difference
between
activation value and the value
on the nameplate should be in
sphere of 10% and accords
with
the
stipulation
of
manufacturer
After
overhaul
Inception
of
cooling
devicendary
circuit
1)
Stipulated
by itself
2) After how
overhaul
3)
When
necessary
2500V megger is
used while measuring
the
insulation
resistance
The insulation
1)
After
278
2500V
megger
is
test of the
current
transformer in
the bushing
overhaul
used
2)
When
necessary
8.3.4.2
8.3.4.2.1
8.3.4.2.2
is
seen
in
No.
8.3.4.3
Dry transformer
8.3.4.3.1
8.3.4.3.2
The overhaul where the winding is changed is seen in No. 2,3, 7, 12,13,14,15, 17
in chart 4.
8.3.4.4
Grounding transformer
8.3.4.4.1
8.3.4.4.2
Test items during overhaul are number 2, 3, 6, 7, 9, 15, 16 and 22, of which
number 15 and 16 are for winding replacement.
8.3.4.5
8.3.4.5.1
The following tests are available when abnormal results of analysis for gases in
oil are available.
wineing D.C resistance
Iron core insulation resistance and grounding current
No-load loss, no-load current measurement, long time no-load operation or light
load operation monitored by analysis of gas content in oil and partial discharge
detector
Long time load test performed by short circuit method and monitored by
chromatographic analysis of gas content in oil
Check tests for oil pumps, coolers
Check test for oil tank leakage of on-load voltage regulation switch
Insulation characteristic (insulation resistance, absorptance, polarization index,
tg and leakage current)
Insulation oil breakdown voltage, tg
Water content in insulation oil
Gas content in insulation oil (500kV)
Voltage withstand test
279
8.3.4.5.2
After relay alarm, analyze dissolved gas content in transformer oil and gas
content in relay.
8.3.4.5.3
The following tests are available for transformer outlet short circuit.
Analysis of dissolved gas content in oil
winding D.C resistance
Short circuit impedance
winding frequency response
No-load current and loss
8.3.4.5.4
8.3.4.5.5
8.3.4.5.6
The following tests are available for abnormal vibration and noise.
Vibration measurement
Noise measurement
Analysis of dissolved gas content in oil
Impedance measurement
8.3.5
8.3.5.1
Current transformer
8.3.5.1.1
Items, cycles and requirements for current transformer are available in list 6.
List 6
Item
Cycle
Requirement
Insulation
resistance
winding
tapping
1)before
activation
of
and
2) every 1-3
years
3)after
overhaul
4)when
necessary
2)
Insulation
resistance between
earth and capacitor
current transformer
tapping should not
be
less
than
1000M.
280
Description
2500V insulation resistance
meter is applied.
tg and electric
capacity
1)before
activation
2) every 1-3
years
3)after
overhaul
4)when
necessary
2
0
k
V
15
0
kV
After
overhaul
3
.
0
2.0
during
operatio
n
3
.
5
2.5
2) Ascertain the
causes when the
differential
value
between
electric
capacity
of
capacitor CT main
insulation and initial
value or factory
value is 5%.
3) When insulation
resistance between
earth and capacitor
CT tapping is less
than 1000M, tg
between earth and
transformer tapping,
and it s should not
exceed 2%.
3
chromatographic
analysis
for
dissolved
gas
content in oil
1)before
activation
2) every 1-3
years
3)after
Attention should be
paid
when
gas
components
of
dissolved
gas
components
281
overhaul
4)when
necessary
(volume fraction) in
oil exceeds any of
the following values.
be based on manufacturer
requirements.
Overall hydrocarbon
(10010-6)
H2(15010-6)
C2H2(210-6)
The above values
are for
110kV and below.
4
A.C
voltage
withstand test
1)every 1-3
years
2)
after
overhaul
3)when
necessary
Polarization check
1)after
overhaul
2)when
necessary
1)after
overhaul
2)when
necessary
Check
and
calibration
for
excitation
characteristic
curve
Leakage check
When
necessary
1)after
overhaul
be available.
2)when
necessary
1)after
overhaul
2)when
necessary
1
0
Insulation
breakdown
voltage
oil
1)after
overhaul
2)when
necessary
Notes
Before activation means the condition that equipment is ready to be activated
after handing over, getting ready to activate, and also before putting the storage
fresh equipment into operation.
8.3.5.1.2
8.3.5.2
Potential transformer
Items, cycles and requirements for electromagnetic voltage, capacitor voltage
transformer
List 7 Items, cycles and requirements for electromagnetic voltage, capacitor
voltage transformer
1
Item
Cycle
requirement
description
Insulati
on
resista
nce
1)every 13 years
2500V
insulation
resistance
meter
is
applied
for
primary
winding.
2)after
overhaul
3)when
necessary
1000V
insulation
resistance
meter
is
applied
for
secondary
winding.
10
283
20
3
0
4
0
tg test
cascade
for
PT
150
kV
tg
1.5
2.
0
3.
5
5
.
0
2.0
2.
5
4.
0
5
.
5
1)winding
insulation
a)
Temperatur
e
1
0
2
0
3
0
40
150
kV
Ov
er
ha
ul
1.
5
2.
0
3
.
5
5.0
Op
er
ati
on
2.
0
2.
5
4
.
0
5.5
should apply
end shielding
method. Other
teats methods
are up to
power plant.
chroma
tograph
ic
analysi
s for
dissolv
ed gas
content
in oil
1)before
activation
A.C
voltage
withsta
nd test
1)every 3
years(for
20kV and
below)
2) every 13 years
3)after
overhaul
4)when
necessary
2)
after
overhaul
3)
when
necessary
C2H2 should
not
be
available in oil
of
newly
activated
transformer.
C2H2 (210-6)
15
Test voltage KV
21
38
284
1) Frequency
multiplication
induction
voltage
withstand test
is applied for
cascade or
multi-staged
insulation
transformer.
2)
Transformer
allowable
voltage rise
should
be
taken
into
consideration
when
the
above
test
method
is
applied.
3) Check for
insulation
damage
should
be
performed
before and
after the test.
Noload
current
measur
ement
1)after
overhaul
2)when
necessary
ineffectively
grounded
1.9U n / 3
neutral grounded system
1.5U n / 3
6
Leakag
e
check
Insulati
on
resista
1)after
overhaul
Check
method
should
be
based
on
regulations
from
manufacturer.
2500V
insulation
resistance
2)when
necessary
During
overhaul
285
nce of
iron
core
tighten
ed bolt
8
meter
applied.
1)winding
replaceme
nt
is
2)after
wiring
change
9
Voltage
ratio
1)winding
replaceme
nt
2)wiring
change
10
Insulati
on oil
breakd
own
voltage
1)after
overhaul
2)when
necessary
Value
difference and
phase
difference
should
be
measured
after winding
replacement.
Notes
Test items, cycle, and requirement of capacitor voltage transformer (CVT) in sheet
8
No.
Items
Cycle
Voltage ratio
1)After
overhaul
Requirement
major
2)When necessary
2
Insulation
resistance of
middle
transformer
tg of middle
transformer
1)After
overhaul
Same
nameplate
Remark
as
mark
major
Set by user
2)When necessary
1)After
overhaul
major
2)When necessary
There should be
no
significant
change compared
286
Adopt tramegger of
2500V
Switch gear
8.3.6.1
SF6 breaker
8.3.6.1.1
Period
Requirements
Test items of
SF6 gas
Leak test of
SF6 gas
1)After major
overhaul
2)When
necessary
Secondary
circuit and
control
circuit
insulation
resistance
1)1~3 years
Withstand
voltage test
1)After major
overhaul
2)After major
overhaul
2)When
necessary
Description
no
or
to
of
Conduct
according
GB11023
to
Insulation resistance
no less than 2M
Adopt
tramegger
of
500V or 1000V
Test voltage of AC
withstand voltage or
operation
impact
withstand voltage test
is 80% of leave
factory test voltage
Test
is
conducted with
rated voltage of
SF6 gas
Secondary
circuit and
control
circuit AC
voltage
withstand
test
After major
overhaul
Insulation
resistance after
withstand
voltage
test
should not be
dropped
Speed
character of
breaker
After major
overhaul
Measuring method
and measuring result
should
meet
manufacturer
provision
No test if no
requirement
from
manufacturer
Time
parameter
of breaker
1)After major
overhaul
2)After
If
there
provision
287
is
no
from
mechanism
major
overhaul
manufacturer,
synchronism
of
breaker
opening,
closing should meet
following
requirement:
5ms
Non-synchronous
closing in phase-tophase no more than
5ms
Non-synchronous
opening in phase-tophase no more than
3ms
Non-synchronous
same phase closing
between each open
contacts no more
than 3ms
Non-synchronous
same phase opening
between each open
contacts no more
than 2ms
Action
voltage of
opening,
closing
electromagn
et
1)1~3 years
2)After major
overhaul
3)After
mechanism
major
overhaul
1)Lowest
action
voltage of control
mechanism opening,
closing
electromagnet should
be within 30%
65% of rated value of
control voltage
2)Imported
equipments
follow
manufacturer
provision
Conducting
circuit
resistance
1)1~3years
Measure by DC
pressure drop
method, current
2)After major
288
overhaul
10
11
Opening,
closing coil
DC
resistance
SF6
gas
density
monitor test
1)After major
overhaul
2)After
mechanism
major
overhaul
1)1~3years
2)After major
overhaul
flow should be
no less than
100A
Should
manufacturer
provision
meet
By
manufacturer
provision
3)When
necessary
12
13
8.3.6.1.2
Pressure
meter
calibration,
mechanism
operation
pressure(air
pressure,
hydraulic
pressure)
setting value
calibration
Performanc
e of locking,
anti-jump
etc auxiliary
control
device
1)1~3years
2)After major
overhaul
By
manufacturer
provision
1)After major
overhaul
By
manufacturer
provision
Should calibrate
setting value of
air pressure of
each grade for
pneumatic
mechanism
2)When
necessary
See
4
9
items
10
11
12 in
in number
11 12
8.3.6.2
8.3.6.2.1
See test items, cycle, and requirement of low voltage breaker and automatic
289
For automatic erasing switch, should check opening and closing switching order
of normally opened and closed contact, and main contact, arcing contact surface
condition and action cooperation condition etc.
8.3.6.3
Vacuum breaker
8.3.6.3.1
See test items, cycle, and requirement of vacuum breaker in sheet 11.
Sheet 11 Test items, cycle, and requirement of vacuum breaker
Items
Period
Requirements
Insulation
resistance
1)1~3
years
1)Integral
insulation
resistance consult to
manufacturer provision
2)After
major
overhaul
major
In operation
2
AC voltage
withstand
test(main
circuit over
ground,
phase
to
phase
and
open
contact)
Secondary
circuit
and
control circuit
AC voltage
withstand
test
1)1~3
years
2)After
major
overhaul
Descriptions
100
0
300
290
1)Loft
rod
changed or been
dried must have
voltage withstand
test
2)Voltage
withstand value
of
phase
to
phase, phase to
ground and open
contact are same
Conducting
circuit
resistance
Mechanical
character of
breaker
1)1~3
years
2)After
major
overhaul
After
major
overhaul
1)Should
meet
manufacturer provision
after major overhaul
2)Set
by
user,
recommend no more than
1.2 times of factory
setting
Should
meet
manufacturer provision
Measure DC drop
voltage method,
current flow no
less than 100A
Conduct
under
rated operation
voltage
6
Lowest
action
voltage
of
control
mechanism
opening,
closing
electromagn
et
After
major
overhaul
Insulation
resistance
and
DC
resistance of
opening,
closing
electromagn
et coil
1)1~3
years
Measuring of
vacuum
degree
of
vacuum
extinction
chamber
When
major
and
minor
overhaul
2)Imported
equipment
bases on manufacturer
provision
2)After
major
overhaul
1)Insulation resistance no
less than 2 M
2)DC resistance should
meet
manufacturer
provision
Set by user
Check if soft
Should be tight
291
Adopt tramegger
of 1000V
connection
clipping
piece
on
moving
contact loose
8.3.6.3.2
After
major
overhaul
7 in sheet 11.
Disconnector
8.3.6.4.1
8.3.6.4.2
Requirement
Remark
1)1~3 years
Insulation
resistance
of insulator
and lift rod
2)After major
overhaul
Adopt tramegger
of 2500V
Insulation
resistance
of
secondary
circuit
1)1~3 years
Adopt tramegger
of 1000V
Should measure
insulation
resistance before
and
after AC
voltage withstand
test; resistance
after
voltage
withstand should
not drop
3
AC voltage
withstand
test
Cycle
Secondary
circuit AC
voltage
2)After major
overhaul
3)When
necessary
After
major
overhaul
292
withstand
test
5
Lowest
action
voltage of
control
mechanism
coil
After
major
overhaul
Conducting
circuit
resistance
value
After
major
overhaul
Action
condition of
control
mechanism
After
major
overhaul
Measure with DC
drop
voltage
method, current
value is no less
than 100A
8.3.4.5
8.3.4.5.1
The following tests are available when abnormal results of analysis for gases in
oil are available.
winding D.C resistance
Iron core insulation resistance and grounding current
No-load loss, no-load current measurement, long time no-load operation or light
load operation monitored by analysis of gas content in oil and partial discharge
detector
Long time load test performed by short circuit method and monitored by
chromatographic analysis of gas content in oil
Check tests for oil pumps, coolers
Check test for oil tank leakage of on-load voltage regulation switch
Insulation characteristic (insulation resistance, absorptance, polarization index,
tg and leakage current)
293
After relay alarm, analyze dissolved gas content in transformer oil and gas
content in relay.
8.3.4.5.3
The following tests are available for transformer outlet short circuit.
Analysis of dissolved gas content in oil
winding D.C resistance
Short circuit impedance
winding frequency response
No-load current and loss
8.3.4.5.4
8.3.4.5.5
8.3.4.5.6
The following tests are available for abnormal vibration and noise.
Vibration measurement
Noise measurement
Analysis of dissolved gas content in oil
Impedance measurement
8.3.5
8.3.5.1
Current transformer
8.3.5.1.1
Items, cycles and requirements for current transformer are available in list 6.
List 6 Items, cycles and requirements for current transformer
Item
Insulation
resistance
winding
tapping
Cycle
of
and
1)before
activation
2) every 1-3
years
3)after
overhaul
4)when
Requirement
Description
2)
Insulation
resistance between
earth and capacitor
294
tg and electric
capacity
necessary
current transformer
tapping should not
be
less
than
1000M.
1)before
activation
2) every 1-3
years
3)after
overhaul
4)when
necessary
Voltage
class
2
0
k
V
15
0
kV
After
overhaul
3
.
0
2.0
during
operatio
n
3
.
5
2.5
2) Ascertain the
causes when the
differential
value
between
electric
capacity
of
capacitor CT main
insulation and initial
value or factory
value is 5%.
3) When insulation
resistance between
earth and capacitor
CT tapping is less
than 1000M, tg
between earth and
transformer tapping,
and it s should not
exceed 2%.
3
chromatographic
1)before
Attention should be
295
analysis
dissolved
content in oil
for
gas
activation
2) every 1-3
years
3)after
overhaul
4)when
necessary
paid
when
gas
components
of
dissolved
gas
components
(volume fraction) in
oil exceeds any of
the following values.
Overall hydrocarbon
(10010-6)
H2(15010-6)
C2H2(210-6)
The above values
are for
110kV and below.
A.C
voltage
withstand test
1)every 1-3
years
2)
after
overhaul
3)when
necessary
Polarization check
1)after
overhaul
2)when
necessary
1)after
overhaul
2)when
necessary
Check
and
calibration
for
excitation
characteristic
When
necessary
296
curve
same
type
or
characteristic curve
from manufacturer.
Leakage check
1)after
overhaul
No leakage should
be available.
2)when
necessary
1)after
overhaul
2)when
necessary
1
0
Insulation
breakdown
voltage
oil
1)after
overhaul
2)when
necessary
Notes
Before activation means the condition that equipment is ready to be activated
after handing over, getting ready to activate, and also before putting the storage
fresh equipment into operation.
8.3.5.1.2
8.3.5.2
Potential transformer
Items, cycles and requirements for electromagnetic voltage, capacitor voltage
transformer
List 7 Items, cycles and requirements for electromagnetic voltage, capacitor
voltage transformer
Item
1
Insulati
on
resista
nce
Cycle
1)every 13 years
Requirement
Description
2500V
insulation
resistance
meter
is
applied
for
primary
winding.
2)after
overhaul
3)when
necessary
1000V
insulation
resistance
meter
is
applied
for
297
secondary
winding.
2
tg
1)winding
insulation
a)
Temperatur
e
1
0
2
0
3
0
40
150
kV
Ov
er
ha
ul
1.
5
2.
0
3
.
5
5.0
Op
er
ati
on
2.
0
2.
5
4
.
0
5.5
Chrom
atograp
hic
analysi
s for
dissolv
ed gas
content
in oil
1)before
activation
A.C
voltage
withsta
nd test
1)every 3
years(for
20kV and
below)
2) every 13 years
3)after
overhaul
4)when
necessary
2)
after
overhaul
3)
when
necessary
C2H2 should
not
be
available in oil
of
newly
activated
transformer.
C2H2 (210-6)
15
Test voltage KV
21
38
298
1) Frequency
multiplication
induction
voltage
withstand test
is applied for
cascade or
multi-staged
insulation
transformer.
2)
Transformer
allowable
voltage rise
should
be
taken
into
consideration
when
above
method
applied.
the
test
is
3) Check for
insulation
damage
should
be
performed
before and
after the test.
5
Noload
current
measur
ement
1)after
overhaul
2)when
necessary
ineffectively
grounded
1.9U n / 3
neutral grounded system
1.5U n / 3
6
Leakag
e
check
Insulati
on
resista
nce of
iron
core
tighten
ed bolt
1)after
overhaul
Check
method
should
be
based
on
regulations
from
manufacturer.
2500V
insulation
resistance
meter
applied.
2)when
necessary
During
overhaul
1)winding
replaceme
is
nt
2)after
wiring
change
9
Voltage
ratio
1)winding
replaceme
nt
2)wiring
change
10
Insulati
on oil
breakd
own
voltage
1)after
overhaul
2)when
necessary
Value
difference and
phase
difference
should
be
measured
after winding
replacement.
Notes
Before activation means the condition that equipment is ready to be activated
after handing over, getting ready to activate, and also before putting the storage
fresh equipment into operation.
8.3.5.2.2
No.
Test items, cycle, and requirement of capacitor voltage transformer (CVT) in sheet
8
Items
Cycle
Requirement
1
Voltage ratio
1)After
overhaul
major
Same
nameplate
Remark
as
mark
2)When necessary
2
Insulation
resistance of
middle
transformer
3
tg
tg of middle
transformer
1)After
overhaul
major
Set by user
Adopt tramegger of
2500V
2)When necessary
1)After
overhaul
major
2)When necessary
There should be
no
significant
change compared
with initial value
8.3.6
Switch gear
8.3.6.1
SF6 breaker
8.3.6.1.1
Cycle
Requirements
Descriptions
Leak test of
SF6 gas
1)After major
overhaul
2)When
necessary
Secondary
circuit and
control
circuit
insulation
resistance
Withstand
voltage test
1)1~3 years
2)After major
overhaul
1)After major
overhaul
2)When
necessary
no
or
to
of
Insulation resistance
no less than 2M
Test voltage of AC
withstand voltage or
operation
impact
withstand voltage test
is 80% of leave
factory test voltage
Secondary
circuit and
control
circuit AC
voltage
withstand
test
After major
overhaul
Speed
character of
breaker
After major
overhaul
Measuring method
and measuring result
should
meet
manufacturer
provision
Time
parameter
of breaker
1)After major
overhaul
2)After
mechanism
major
overhaul
Conduct
according
GB11023
to
Adopt
tramegger
of
500V or 1000V
Test
is
conducted with
rated voltage of
SF6 gas
Insulation
resistance after
withstand
voltage
test
should not be
dropped
If
there
is
no
provision
from
manufacturer,
synchronism
of
breaker
opening,
301
No test if no
requirement
from
manufacturer
Action
voltage of
opening,
closing
electromagn
et
1)1~3 years
2)After major
overhaul
3)After
mechanism
major
overhaul
1)Lowest
action
voltage of control
mechanism opening,
closing
electromagnet should
be within 30%
65% of rated value of
control voltage
2)Imported
equipments
follow
manufacturer
provision
10
Conducting
circuit
resistance
1)1~3years
2)After major
overhaul
Opening,
1)After major
Measure by DC
pressure drop
method, current
flow should be
no less than
100A
Should
302
meet
closing coil
DC
resistance
11
SF6
gas
density
monitor test
overhaul
2)After
mechanism
major
overhaul
1)1~3years
2)After major
overhaul
manufacturer
provision
By
manufacturer
provision
3)When
necessary
12
13
8.3.6.1.2
Pressure
meter
calibration,
mechanism
operation
pressure(air
pressure,
hydraulic
pressure)
setting value
calibration
Performanc
e of locking,
anti-jump
etc auxiliary
control
device
1)1~3years
2)After major
overhaul
1)After major
overhaul
By
manufacturer
provision
Should calibrate
setting value of
air pressure of
each grade for
pneumatic
mechanism
By
manufacturer
provision
2)When
necessary
See
4
9
items
10
11
12 in
in number
11 12
8.3.6.
8.3.6.2.1
See test items, cycle, and requirement of low voltage breaker and automatic
erasing switch in number 9 and 10 in sheet 9.
8.3.6.2.2
For automatic erasing switch, should check opening and closing switching order
303
of normally opened and closed contact, and main contact, arcing contact surface
condition and action cooperation condition etc.
8.3.6.3
Vacuum breaker
8.3.6.3.1
See test items, cycle, and requirement of vacuum breaker in sheet 11.
Sheet 11 Test items, cycle, and requirement of vacuum breaker
Items
Insulation
resistance
Cycle
Requirements
1)1~3
years
1)Integral
insulation
resistance consult to
manufacturer provision
2)After
major
overhaul
Descriptions
major
100
0
300
In operation
2
AC voltage
withstand
test(main
circuit over
ground,
phase
to
phase
and
open
contact)
1)1~3
years
2)After
major
overhaul
2)Voltage
withstand value
of
phase
to
phase, phase to
ground and open
contact are same
3
Secondary
circuit
and
control circuit
AC voltage
withstand
test
1)Loft
rod
changed or been
dried must have
voltage withstand
test
1)1~3
years
2)After
major
overhaul
304
4
Conducting
circuit
resistance
1)1~3
years
2)After
major
overhaul
Mechanical
character of
breaker
After
major
overhaul
Lowest
action
voltage
of
control
mechanism
opening,
closing
electromagn
et
After
major
overhaul
Insulation
resistance
and
DC
resistance of
opening,
closing
electromagn
et coil
1)1~3
years
Measuring of
vacuum
degree
of
vacuum
extinction
When
major
and
minor
overhaul
1)Should
meet
manufacturer provision
after major overhaul
Measure DC drop
voltage method,
current flow no
less than 100A
2)Set
by
user,
recommend no more than
1.2 times of factory
setting
Should
meet
manufacturer provision
Conduct
under
rated operation
voltage
6
1) Lowest action voltage
of control mechanism
opening,
closing
electromagnet should be
30%~65% of within rated
operation voltage
2)Imported
equipment
bases on manufacturer
provision
2)After
major
overhaul
1)Insulation resistance no
less than 2 M
2)DC resistance should
meet
manufacturer
provision
8
Set by user
305
Adopt tramegger
of 1000V
chamber
9
8.3.6.3.2
Check if soft
connection
clipping
piece
on
moving
contact loose
After
major
overhaul
Should be tight
7 in sheet 11.
Disconnector
8.3.6.4.1
8.3.6.4.2
Cycle
Requirement
Insulation
resistance
of insulator
and lift rod
1)1~3 years
Adopt tramegger
of 2500V
Insulation
resistance
of
secondary
circuit
1)1~3 years
Adopt tramegger
of 1000V
AC voltage
withstand
test
Remark
2)After major
overhaul
2)After major
overhaul
3)When
necessary
After
major
overhaul
306
Should measure
insulation
resistance before
and
after AC
voltage withstand
test; resistance
after
voltage
withstand should
not drop
4
Secondary
circuit AC
voltage
withstand
test
After
major
overhaul
5
Lowest
action
voltage of
control
mechanism
coil
After
major
overhaul
Conducting
circuit
resistance
value
After
major
overhaul
Action
condition of
control
mechanism
After
major
overhaul
6
Measure with DC
drop
voltage
method, current
value is no less
than 100A
HV on-off module
8.3.6.5.1
Item
Cycle
Requirement
Description
Isolation resistance of
1)1 3 year
Isolation
307
auxiliary circuit
control circuit
and
2)After overhaul
resistance should
not lower than
2M
AC HV withstand testing
of auxiliary circuit and
control circuit
After overhaul
2KV
voltage
CB
characteristics
speed
After overhaul
Meet
manufacturer
requirement
CB
mechanical
characteristic
After overhaul
Meet
manufacturer
requirement
Conduction
circuit
resistance
of
CB,
isolation switch and
isolation plug
1)1 3 year
1) Meet the
requirement after
overhaul
minimum
activation
voltage for opening or
closing electromagnet of
actuator
1)1 3 year
2)After overhaul
2) Not exceed
1.5
times of
manufacturer
set
value
during operation
2)After overhaul of
After overhaul
Isolation
testing
1)1 3 year
AC withstand testing
Could be omitted if
no specification from
manufacturer
Measurement
of
isolation switch and
isolation
plug
conduct
under
suitable condition
1) Whole isolation
resistance
not
specified.
2) Isolation
resistance
of
breaking port and
organic lifting rod
must not lower
than
following
valve
resistance
testing
Isolation
resistance more
than 2M
DC
resistance
should
meet
manufacturer
requirement
2)After overhaul
Meet
manufacturer
requirement
1)1 3 year
Testing
308
voltage
10
2)After overhaul
according
with
manufacturer
requirement
1)1 year
Meet
manufacturer
requirement
1)1 3 year
2)After overhaul
Meet
manufacturer
requirement
After overhaul
13
14
15
CT, PT of HV on-off
module
8.3.6.5.2
2)After overhaul
method: phase to
earthing
during
closing; phase to
break port during trip
Five
safe
are:
prevent to faulty
open or close CB;
prevent to open or
close isolation switch
with load; prevent
to operate earthing
(wire)
with
load;
operate
prevent
CB with earthing wire
(switch); prevent
from enter wrong live
compartment.
When necessary
After overhaul
When necessary
8.3.7
8.3.7.1
The testing item, cycle and requirement of accumulate battery DC panel (cabinet)
refer to form 14.
Form 14. The testing item, cycle and requirement of accumulate battery DC
panel (cabinet)
No.
1
Item
Cycle
Requirement
Description
Testing
of
accumulate battery
capacity
1 year
Voltage testing of
accumulate battery
after
discharging
complete
1 year
When necessary
According with manufacturer requirement
When necessary
309
Various
inspect
protection
Isolation resistance
of bus in feeder
panel
8.3.7.2
1 year
Various
function
normal
When necessary
Isolation
resistance
should
not
lower
than
10M
Inspection item:
isolation monitor system
Voltage monitor system
Use 1000V megger
8.3.8
Bushing
8.3.8.1
The testing item, cycle and requirement of bushing refer to form 15.
Form 15 The testing item, cycle and requirement of bushing
No.
1
Item
Main isolation and
capacity
bushing
terminal
earthing
isolation resistance
Cycle
Requirement
1~3 year
After overhaul
When
necessary
Isolation resistance
of main isolation
should not lower than
10000M
Description
Use 2500V megger
Isolation resistance
of terminal earthing
must not lower than
1000M
2
Capacitance
and
tg of main isolation
and
capacity
bushing
terminal
earthing
1~3 year
After overhaul
When
necessary
310
Tg (%) value at
20
should
according
with
manufacturer
requirement
Color
spectrum
analyze
of
oil
dissolved gas
Before
activation
After overhaul
When
necessary
AC withstand testing
After overhaul
Testing voltage is
85% of set value
When
necessary
partial
test
discharge
After overhaul
According
manufacturer
requirement
When
necessary
20KV
or
below
porcelain wall through
bushing
could
withstand high voltage
together with bus
isolator
with
Attention: 1. Oil filled busing means the main isolation bushing use oil as medium.
8.3.8.2
8.3.9
8.3.9.1
The testing item, cycle and requirement of support isolator and suspension
isolator refer to form 16
Form 16 The testing item, cycle and requirement of support isolator and suspension isolator
No
.
1
Item
Inspection
of
zero
value
isolator (66KV
and above)
Cycle
1~5 year
Requirement
Inspect
voltage
under
Description
operation
regulation
and
inspection cycle of
isolator
could
according
with
degression ratio
Inspect
each
component
for
multicomponent
needle type isolator
Isolation
resistance
Suspending
isolator 1~5 year
Needle
type
support isolator
Use
2500V
above megger
or
1~5 year
AC
withstand
testing
Single
component
support isolator
1~5 year
Suspending
isolator 1~5 year
Needle
type
support isolator
1~5 year
Refer to main
equipment
When replace
isolator
support isolator
Attention: Testing item of needle type support isolator and suspending isolator
during operation could select any one from zero value inspection, isolation
resistance and AC withstanding testing. The testing of 1,2,3 item not conduct for
glass suspending isolator, broken isolator in operation must be promptly replace.
8.3.10
Power cables
8.3.10.1
General regulations
8.3.10.1.1
Conduct the DC voltage withstanding test and measure the insulated resistance
for cable main insulator on each phase. The other two-phase conductor, metallic
shield or metallic sheath and armour should be grounded together while testing or
measuring one-phase.
8.3.10.1.2
Conduct a DC voltage withstand test after newly buried cables are put into
operation for 3 to 12 months. Next time they will be tested by the normal cycle.
8.3.10.1.3
8.3.10.1.4
The sheath over-voltage protector must be temporarily grounded when one end of
metallic shield or metallic sheath is grounded and the other end main insulator of
single chip cable with protector is conducted a DC voltage withstand test.
8.3.10.1.5
After the voltage withstand test, it is not allowed for the conductor to directed
discharge with the ground until it is no spark when repeated discharging is
finished across the 80kcurrent-limiting resistance per kilovolt
312
8.3.10.1.6
Use the megohm meter to measure the grounding insulated resistance of cable
conductor when the offpower time is more than one week and less than a month.
If there is a question, use DC voltage below common DC voltage withstanding
voltage to test and the voltage-increasing time is 1 minute. When the offpower
time is more than one month and less than a year, conduct the DC voltage
withstand test with 50% testing voltage value and the voltage-increasing time is 1
minute. When the offpower time is more than one year, conduct the common DC
voltage withstand test for the cables.
8.3.10.1.7
8.3.10.1.8
Measure the leakage current when the testing voltage rises to the specified value
after one minute and voltage-increasing time reaches the specified time while
conducting a DC voltage withstand test. The leakage current and unbalanced coexistence (the ratio of Max and Mini) are only a reference instead of the operation
evidence to check the insulated. If there is a big difference between the leakage
current and last testing value or the leakage current is instable (its current will
sharply rise as the testing voltage increases or voltage-increasing time extends,.),
find out the cause. If the cause is related to the leakage current on the surface of
terminal end or grounding stray current, eliminate it. If the cable insulated route is
not good, improve the testing voltage (the DC voltage of outgoing testing is
available) or extend the testing time to make sure the normal operating.
8.3.10.1.9
The operation division can extend the testing cycle according to operation
conditions of cables and past experience and testing achievements.
8.3.10.2
8.3.10.2.1
The testing item, cycle and requirement about rubber and plastic insulated power
cables can be seen in the following table 17.
Table 17 Testing item, Cycle and Requirement about Rubber and Plastic insulated Power cables
SN.
Item
Cycle
insul
ated
resist
ance
of
cable
main
insul
ated
1)Important
cables: every
year
Requirement
Not specified
a)3.6/6kV 3
b) 0.6/1kV 5
General
cables:
a)3.6/6kV
every 3 years
313
Explanation
1000V megameter
for
0.6/1kV
cable;2500V
megameter
for
above 0.6/1kV cable
b)0.6/1kV
every 5 years
insul
ated
resist
ance
of
cable
outer
sheat
h
Important
cables:
every year
a)3.6/6kV 3
0.5M
Each kilometer insulated
resistance should be
below 0.5M.
b) 0.6/1kV 5
General cable:
a)3.6/6kV
3years
Use
megameter.
500V
b)0.6/1kV
5years
3
Insul
ated
resist
ance
of
cable
insid
e
liner
4
Ratio
of
copp
er
shiel
d
resist
ance
and
cond
uctor
resist
ance
cable
DC
volta
1)Important
cables:
every year
2)General
cables :
every year
1)Preactivation
2)Redesigned
terminal
or
postconnecting
3)post-Inlet
water
when
inside liner is
damaged.
Redesigned
terminal
or
post-
314
ge
withs
tand
test
of
main
insul
ated
8.3.10.2.2
connecting
increasing
minutes
puncture.
time
is 5
without
DC
testing
Voltage
Cable
voltage
rated
DC
voltage
1.8/3
11
21/35
63
3.6/6
18
26/35
78
6/6
25
48/66
144
6/10
25
64/110
192
8.7/10
37
127/220
305
testing
8.3.10.2.3
Testing method about the ratio of copper shield resistor and conductor
resistance
8.3.10.2.3.1
8.3.10.2.3.2
It indicates the DC resistance increases and the corrosion probably exists on the
copper shield when the ratio of the first and the latter is bigger than that of preactivation. When the ratio decreases compared with that of pre-activation, it
indicates that the contact resistance in the accessory components probably
increases.
8.3.11
8.3.11.1
Transformer oil
8.3.11.1.1
The testing items and requirements about transformer oil during the operation can
be seen in table 19 and the testing cycle is as following 5 8 9
8.3.11.1.1.1
The 150kV transformer oil, the project SN for one year testing cycle is 1,2,3,6 and
the SN is 5,8 and 9 when necessary.
8.3.11.1.1.2
8.3.11.1.1.3
The project SN of oil testing for the new transformer after overhaul and before the
activation is 1, 2,3,4,5,6,7,8 and 9.
8.3.11.1.1.4
The test for CT&PT, and enclosed tube oil can be conducted by the analysis test
of the dissolved gas color spectrum in oil. The item follows the regulations of
CT&PT and enclosed tube sections.
8.3.11.1.1.5
315
8.3.11.1.2
The speed for oiliness aging is different due to the different conditions of
equipment and operation. When the oil PH value of major equipment is
approaching 4.4 or the color turns deep and other parameters are near the
specified value or failed, shorten the testing cycle and increase the testing items.
Handle it when necessary.
8.3.11.1.3
Table19
Numbe
r
Item
Demands
Description
Appearance
Water Soluble
Acid Ph Value
5.4
4.2
Carry Out
According
GB7598
Test
To
Acid
Value
mgKOH/g
0.03
0.1
Carry Out
According
GB264
GB7599
Test
To
or
Flashing Point
(Closed Hole)
140
(#10
Oil)
Carry Out
According
GB261
Test
To
Oil
Before
Activation
Operation Oil
Transparent, No
Foreign Matters
or Suspender
Matters
Inject
Oil
Sample
into
Test Tube. Cool
the Sample to
5. Observe
with Sufficient
Light.
#25
1) Not Less
Than
5
Compare with
Lift Column.
2) Not Less
Than
5
Compare with
Last Test Value.
Water Content
mg/L
66
20
110kV
66
35
110kV
220kV 15
220kV 25
330
10
330
15
500kV
316
500kV
Attention to the
Temperature
Effect during the
Operation. Take
Sample When the
Top
Oil
Temperature
Is
Higher
Than
50. Carry Out
Test According to
GB7600
or
GB7601.
Breakdown
Voltage
Less
Than
15kV, 30
Less
Than
15kV, 25
Carry Out
According
GB/T507
DL/T429.9
Test
To
or
kV
66
40
66
35
Interfacial
Tension (25)
mN/m
35
19
Carry Out
According
GB/T6541.
Test
To
tg(90)%
Less Than or
Equal to 330kV,
1
Less Than or
Equal to 300kV,
4
Carry Out
According
GB5654.
Test
To
Volume
Resistivity
61010
330kV
3109
Carry Out
According
DL/T421
GB5654.
Test
To
or
Test
To
or
220kV
220kV
(90)m
10
Air Content in
Oil
(Volume
Fraction)%
Normally, 3
Carry Out
According
DL/T423
DL/T450.
11
Sludge
and
Deposit (Mass
Fraction)%
Normally, 0.02
12
Chromatographi
c Analysis of
Dissolved Gas
in Oil
317
and GB7252.
Notes:
1 Sealing equipment such as transformer, difficult to take sample or make up oil,
takes sample or not should according to specific conditions.
2 The test item, period and requirements of the transformer oil in on-load tap
changer of transformer should according to manufacturer regulations.
8.3.11.1.4
The regulations about makeup oil or different type of oil mixed use.
8.3.11.1.4.1
All property of makeup oil should meet the requirements of equipments oil. If not,
sludge will be rapidly separated out from oil at times. Therefore, mixed oil sample
separating out and tg test should be performed in advance. Mixed can be
performed only there is no deposits and tg value lower than primary equipment
oil.
8.3.11.1.4.2
Different type of fresh oil or the same quality operation oil should not be mixed in
principle. If it is a must, should according to mixed oil actual measurement
condensation point to decide if it can be used.
8.3.11.1.4.3
For imported oil, unknown oil and contained different additive oil carry out the
aging test for participating oil and the oil sample that has been mixed in advance
if it is necessary to mix with different type of oil.
8.3.11.1.4.4
The mixing ratio of oil sample should be in accordance with actually used oil. Take
the 11 to mix if the actually used ratio is unknown.
8.3.11.2
SF6 gas
8.3.11.2.1
8.3.11.2.2
Carry out the test after SF6 gas is supplied into electrical equipment with 24h.
8.3.11.2.3
8.3.11.2.3.1
Makeup gas must be met the new quality standard. Attention to the contact and
piping dry during making up.
8.3.11.2.3.2
The gas that meets the new quality standard can be mixed used.
Table 20
Numbe
r
Item
Period
Humidity(20
1)1
Demands
3
1) After Major
318
Description
1)Perform
According
To
Volume
Fraction)10-6
Years(150k
V)
2)After
Major
Overhaul
3)When
Necessary
Overhaul of
CB
Arc
Extinguish
Chamber Air
Chamber
is
During
150.
Operation
is300.
2) After Major
Overhaul of
Other
Chambers are
250.
During
Operation
is500.
Density
(Under
Standard
Conditions)
When
Necessary
6.16 kg/m3
According
to
SD308
Density Test Method in SF6
New Gas to Carry Out
Test.
Toxicity
When
Necessary
Non-toxic
According
to
SD312
Biological Test Method of
SF6 Gas Toxicity to Carry
Out Test.
Acidity
1)After
Major
Overhaul
0.3
1)After
Major
Overhaul
1) After Major
Overhaul
0.05
2)When
Necessary
2)
Operation
According to SD311 GC
Test Method of Air CF4
in SF6 New Gas to Carry
Out Test.
2)When
Necessary
5
CF4
(Mass
Fraction)%
319
In
0.1
6
Air
(Mass
Fraction)%
Hydrolyzable
Fluoride
g/g
1)After
Major
Overhaul
1) After Major
Overhaul
0.05
2)When
Necessary
2)
Operation
0.2
1)After
Major
Overhaul
1.0
2)When
Necessary
8
Mineral Oil
1)After
Major
Overhaul
g/g
10
2)When
Necessary
Refers to Number 5.
In
According
to
SD309
Hydrolyzable
Fluoride
Content Test Method in
SF6 Gas to Carry Out Test.
According
to
SD310
Mineral Oil Content Test
Method in SF6
Gas
(Infrared Spectrometry) to
Carry Out Test.
Thunder arrester
For testing items, period and requirements for metallic oxide thunder arrester, see
figure 21.
Figure 21 Testing items, period and requirements for metallic oxide thunder arrester
Item
No.
Items
Period
Requirements
Illustration
Insulation
resistance
1)Before
every
thunderstor
m season
2)When
necessary
2
Leakage
current
under DC
1mA voltage
(U1mA) and
0.75 U1mA
1)Before
every
thunderstor
m season
2)When
necessary
320
1)
Recording
the
testing
environment
temperature
and
relative humidity
2) Applying screening
line
to
current
measurement
conductor wire
3) Initial value is
measuring value of test
shift.
3
AC leakage
current
under
operational
voltage
1)Measuring
the current
under fresh
operation
voltage
of
110kV and
above once
after
the
fresh
operation,
and once a
year
afterwards
before every
thunderstor
m season
Recording
measurement value of
environment
temperature, relative
humidity
and
operational voltage
Measuring when the
porcelain
bushing
surface is dry.
Noting phase-to-phase
interference.
Corresponding to GB11032 or
the
manufactured
specifications
1)Measured
temperature should be
2015 .
2)When
necessary
4
Reference
voltage
under
reference
current for
power
frequency
When
necessary
Base
insulation
resistor
1)Before
every
thunderstor
m season
2)Proceeding
the
measurement
separately for each
section, and if one
section of the whole
phase thunder arrester
is off-test, replacing the
sectional
thunder
arrester (or the entire
phase) and ensuring
the arrester with good
quality.
Once a quarter
2)When
necessary
6
Checking
action status
1)Before
every
321
of discharge
counter
thunderstor
m season
2)When
necessary
8.3.13
Busbar
A Enclosed busbar
1) For testing items, period and requirements for enclosed busbar, see figure 21.
Figure 21
Item
No.
Items
Period
Requirements
Illustration
Insulation
resistor
Major
overh
aul
Using ohm
gauge of
2500 V
AC
voltage
withstand
test
Durin
g
major
overh
aul
Rated
voltage
(kV)
Field
4.2
3.2
42
32
15
57
43
20
68
51
Common busbar
1) For testing items, period and requirements for common busbar, see figure 23.
Figure 23 Testing items, period and requirements for common busbar
Item No.
Items
Period
Requirements
Insulation resistor
1)1-3 years
No less
1M/kV
AC voltage
test
withstand
1)1-3 years
2)During major overhaul
322
than
Illustratio
n
Secondary circuit
8.3.14.1
For testing items, period and requirements for secondary circuit, see items No.1
and 2 in figure 23.
Figure 24 Testing items, period and requirements for secondary circuit
Item
No.
Items
Period
Requirements
Illustration
Insulation
resistor
1)During
major
overhaul
2)When
replacing
secondary
wire
AC voltage
withstand
test
1)During
major
overhaul
2)When
replacing
secondary
wire
1) For
nonimportant circuit,
use ohm gauge of
2500 V instead.
2) No AC voltage
withstand test for
circuit of 48V or
below
3) For circuit with
electro elements,
take
out
the
elements or get a
short circuit on
both ends
8.3.14.2
See No.1 and No.2 in table 24for the test items during overhaul.
8.3.15
Table 25
test items, cycle and requirements of distribution device and power wiring under
323
1kv
No.
Items
Cycle
Requirements
Description
1) The
insulation
resistance
for
each
section in distribution
device should not be
smaller than 0.5M;
1
Insulation
Resistanc
e
Overhaul
2) The
insulation
resistance of power wiring
is usually not smaller than
0.5M.
2
AC
Withstand
Test
of
Distributio
n Device
Overhaul
Check
Phase
Change
Equipment
or Wiring
Notes:
1. Distribution equipment refers to switchboard, distribution transformer bank,
distribution box, operating panel and conductive part;
2. AC voltage withstand test is not carried to power wiring.
8.3.16
ESP
8.3.16.1
See the test item, cycle and requirements of high-pressure silicon rectifier
transformer in table 26.
Table 26 Test item, cycle and requirements of high-pressure silicon rectifier transformer
No.
Items
Cycle
Requirements
Insulation
Resistance of HP
winding against LP
winding and Earth
1)after
overhaul
500M
Use 2500V
megohmmeter
.
300M
Use 1000V
megohmmeter
.
Insulation
Resistance of LP
winding
2)When
necessary
1)After
overhaul
324
Description
2)When
necessary
3
Insulation
Resistance
for
Silicon
Rectifier
element and HP
bushing
against
earth
1)After
overhaul
2)When
necessary
Core-through
Screw Insulation
Resistance against
Earth
1)After
overhaul
2)When
necessary
DC Resistance of
HP and LP winding
1)After
overhaul
2)When
necessary
10
Sampling
Resistance
Current
Voltage
of
and
Forward
and
Reverse
Resistance of All
Bridge Arms
Transformer
Test
Oil
1)After
overhaul
2)When
necessary
1)After
overhaul
2)When
necessary
No requirements
The
deviation
between this and
setting range is
from -2% to +2%.
With
the
conversion of
75
The
deviation
varies from -5%
to +5% of setting
range
Resistance
deviation
between bridge
arms is smaller
than 10%.
1) 1 year
2)
after
overhaul
Chromatography
Analysis
of
Dissolved gas in oil
1) 1 year
2)
after
overhaul
No-load Step-up
1) Overhaul
2)After
replacing
winding
3)When
necessary
8.3.16.2
2000M
Electric field
without ESP
See the test items, cycle and requirements of insulation supporter and connecting
element in table 27.
Table 27 Test items, cycle and requirements of insulation supporter and connecting element
325
No.
Items
Cycle
Requirements
Insulation
Resistance
Before
replacing
Withstand Test
After
DC100kV or AC 72kV
for
1min
without
flashing
326
500M
Description
Use
2500V
megohmmeter.