Professional Documents
Culture Documents
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 1 di 59
GENERAL SPECIFICATIONS
05221.VAR.ELE.SPC
Rev. 4 December 2004
Eni S.p.A.
Exploration & Production Division
FORWARD
Rev. 1
Sheet 28
June 1988
Rev. 2
Sheet 20
August 1997
Computerized issue
Rev. 3
Rev. 4
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 2 di 59
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 3 di 59
1.
SCOPE OF PROGRAM............................................................................................................................................4
2.
3.
4.
5.
6.
7.
8.
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 4 di 59
1. SCOPE OF PROGRAM
The program defines checks and tests to be carried out on individual materials and
electrical system during installation or on completion.
Checks and tests aim at determining any abnormalities that may have occurred during
transport, installation and assembly and at establishing the efficiency of systems and
circuits and feasibility of components.
These checks and tests do not aim at repeating inspections carried out at the supplier's
premises and, therefore, at verifying the performance and correct construction of
materials.
2. DEFINITION OF TERMS
The following words and expressions shall have the meanings hereby assigned to
them:
- "COMPANY" (or Employer) shall mean the name of Company who has
called for Tenders to provide and execute the works and who will employ the
CONTRACTOR and the legal successors in title to the Employer but not (except
with the consent of the CONTRACTOR) any assignee of the Employer;
- CONTRACTOR" means the person or persons, firm or company whose tender
has been accepted by the Employer and includes the CONTRACTOR's personnel
representatives, successor and permitted assignees subject to Employer consent;
- INSPECTION AUTHORITY, i.e. the organization nominated by COMPANY
to supervise checks and tests.
Eni S.p.A.
Exploration & Production Division
3.1
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 5 di 59
3.2
Mechanical Completion
Mechanical Completion is defined as that point in the project when work to install, erect
and fit out the facilities has been completed, and that fitting out work has been tested.
Eg. Electric cables will have been installed, terminated, continuity and insulation
resistance tested but not energised. Motors will similarly have been checked out but not
run.
Checks and tests must be carried out during construction or when systems or a constituent
part of them are mechanically completed to ensure that the equipment and individual
components are installed in accordance with design requirements, suppliers' instructions,
technical codes and accident prevention codes and that there is no obvious damage or
breakage.
Mechanical equipment will be installed, aligned and fitted with any temporary devices
(strainers, etc.) required for commissioning. Initial fill of lubricants, etc., will be made.
Mechanical completion will be done on a methodical system by system basis, and checks
will be documented and compiled in a similar manner.
In the case of areas with potentially explosive atmospheres, checks must be carried out to
ensure that the whole system and individual components are installed in compliance with
appropriate codes.
More particularly, checks and tests listed below must be carried out.
In the case of parts of systems or materials which are not indicated below, checks and
tests must be carried out by analogy with those of materials indicated and in accordance
with the supplier's instructions.
3.3
Pre-commissioning
Pre-commissioning is defined as the activities following Mechanical Completion carried
out to facilitate safe and efficient commissioning of a system.
Eg. Electrical switchgear relays will be tested and settings verified. Motors will be run for
30 minutes without load (uncoupled). Cables will be energised as required.
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 6 di 59
Mechanical equipment will be prepared for operation by testing and running auxiliaries,
by checking trips and other functions. Seal oil and lube oil systems will be flushed.
These checks and tests must be carried out during construction or on completion and, in
any case, before commissioning in order to:
a) determine any abnormalities that may have arisen during installation;
b) ensure the efficiency of systems and circuits;
c) ensure that components operate under safe conditions.
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 7 di 59
4.1
Inspector
Tests and/or checks outlined with code (P) on Data Sheet for duties and responsibilities
entrusted to qualified engineer who will be responsible for the organization of checks and
tests and whose instructions must be complied with by all persons for whatever reasons
they may be present.
The above engineer is the "Inspector" and must therefore sign all documents associated
with checks and tests.
4.2
4.3
Contractor's duties
All duties connected with the Contractor's responsibilities shall be at his own expenses
(e.g. labour equipment, instruments, documentation, etc.).
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 8 di 59
Documentation
Results of tests mentioned in paragraph 3.1 need not be recorded.
Results of checks and tests mentioned in paragraphs 3.2 and 3.3 must be recorded on
appropriate documents which must be attached to this PROGRAM so as to have complete
and exhaustive file on the subject.
For further information see the following chapter 8.
General
The main scope of Mechanical Completion inspections and tests is to ensure conformity
with the project specifications and drawings and to prove that all equipment and materials
are suited to the duties they are intended to perform.
This procedure covers the general responsibilities of the electrical contractor during
checkout of electrical equipment. Specific requirements are given for the following types
of testing:
- General checks
- Grounding system tests
- Insulation resistance tests
- Protective relay system tests
- Load tests
- Noise tests
- Temperature tests
- Vibration tests (where appropriate)
- Illumination level tests
- DC system tests
- Navigation Aids Tests
All work shall be executed in strict accordance with project specifications and the
approved drawings. The written approval of the COMPANY is required for any
deviations.
6.2
Conduct of Tests
a) The Mechanical Completion program shall demonstrate the proper installation of the
complete electrical system.
b) Checkout tests shall be witnessed by the COMPANY as required.
c) Checkout tests may be conducted concurrently with Pre-commissioning tests.
d) Complete dossier shall be submitted to the COMPANY at completion of Mechanical
Completion.
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 9 di 59
e) After the Mechanical Completion program has been completed and accepted by the
Company, the Contractor shall be responsible for maintaining the equipment in a safe
and protected conditions. All covers, doors and access plates shall be properly
fastened. All wiring shall be completed..
f) It should be noted that Mechanical Completion work may be carried out on adjacent
equipment to live installations. The safety precautions listed must be observed.
6.3
Safety
a) General Safety Precautions
The consequences of shock or burn from electrical systems are serious. Work on
electrical equipment shall, therefore, be carried out only when the equipment is deenergised, and by qualified personnel, and who fully understand the electrical system
of the project.
One-line diagrams shall be available at all times. All feeding equipment and circuits
shall be tagged-out and locked-out. The test/check operatives own key or lock shall
form part of the lock-out procedure.
All equipment such as bus bars, circuit breakers, and motor shall be properly grounded
as appropriate before any testing or other work is initiated.
b) Equipment Isolation
All equipment shall be physically disconnected from its power source to prevent
accidental injury to personnel resulting from inadvertent re-energisation. Equipment
isolation is necessary to ensure that voltages applied to the equipment under test are
not allowed to feed-back into power transformers, generators and associated upstream
synchronising and control circuits. The consequences of back-feeding voltages include
danger to personnel and damage to equipment.
c) Medium-Voltage Testing
While any medium-voltage testing is being conducted shall be ensured that the test
area is properly guarded to prevent unauthorised entry and that DANGER notices are
posted adjacent to, and at all access ways to the test area during the period of the test.
All cables must be discharged both before and after applying any test voltage. Any
associated cables not being tested shall be grounded during the test, e.g., other phase
conductors of a three-phase circuit.
Temporary conductors used for test purposes shall not be sized less than the rating of
the circuit under test.
Caution notices shall be posted adjacent to, and at all access ways to the test area.
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 10 di 59
6.4 Generators
6.4.1
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 11 di 59
q) Ensure that gaskets and seals are correctly installed and are in good condition.
r) Ensure that the conductors are correctly connected to terminals (also in order to the
direction of rotation) and that the insulation distance to earth is appropriate.
s) Ensure that drains are correctly installed and effective;
t) Ensure that there are not obvious damages to mounted instruments.
u) Ensure that the air filters are correctly installed and clean.
v) Ensure that the brushes, when existing, are transversally staggered on the surface of the
rings without, however, being in contact with ring corners so that they do not splinter.
The distance between brushes and ring surface is that anticipated by the manufacturer
and the inclination, if any, is correct, i.e. opposite to the direction of rotation.
Brushes move freely, there is even contact with rings and the brush spring pressure is
that specified by the manufacturer. Braided brush leads do not touch the brush gear
w) Check that all mounting and holding down bolts are secure.
6.4.2
Test Certificates
a) Installation and Mechanical Completion shall be recorded on Check List CL-E001
(MOD.ELE.FTC.002).
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 12 di 59
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 13 di 59
q) Inspect the earthing stud and the connection to the general earthing system, including
those in the terminal box.
r) Check that cables or bus-bars are properly terminated, connected and supported;
s) Ensure that all terminal boxes are clean, dry and in good condition. Check that all
spare entries are plugged.
t) Ensure that internal are free from dust, debris, etc.
u) Ensure that bus-bar or cable terminal protection boxes are well closed.
v) Ensure that there are not loose or missing screws or nuts. Accessories are well fixed.
w) Ensure that rollers on rails are chocked.
y) Ensure that gaskets and seals are correctly installed and are in good condition.
x) Ensure that neutral connections are secure.
z) Ensure that the padlocking facilities are satisfactory.
a1) Ensure that enclosures suitable for protection against adverse weather conditions and
sun are securely installed.
a2) Ensure that warning labels (high voltage, high temperature, etc) are properly installed.
a3) Inspect the transformer and auxiliary equipment for alignment and tightness of
foundation bolts and fixings in general.
6.5.2
Test Certificates
a) Installation and Mechanical Completion shall be recorded on Check List CL-E002
(MOD.ELE.FTC.003).
Eni S.p.A.
Exploration & Production Division
6.6
6.6.1
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 14 di 59
Test Certificates
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 15 di 59
Eni S.p.A.
Exploration & Production Division
6.7.2
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 16 di 59
Test Certificates
a) Installation and Mechanical Completion shall be recorded on Check List CL-E003
(MOD.ELE.FTC.004).
Installation Completion
a) Ensure that the equipment meets the area classification and specification requirements.
b) Note the nameplate ratings of the equipment and compare with those given on the
approved drawings.
c) Ensure that the enclosure IP rating meets specification requirements.
d) Inspect the switchboard assembly for alignment, level, tightness of foundation bolts
and fixing in general. Ensure that circuit breaker trucks can be easily manoeuvred in
and out of their cubicles - applicable to all withdrawable equipment.
e) Compare the switchgear equipment with the Equipment Schedule, paying particular
attention to the rating and any circuit changes.
f) Inspect the switchboard earth bar and earth cable for electrical and mechanical
continuity.
g) Ensure that all panel doors and gland plates are bonded to the switchboard structure
and that non-magnetic gland plates are fitted to single core cables.
h) Ensure that all equipment installed in the switchboard is in good condition,
particularly bus-bar insulation and bracing and joint insulation.
i) Inspect bus duct connections.
j) Inspect the inside of the switchgear for cleanliness, paying particular attention to the
insulators.
k) Ensure that all equipment (i.e. circuit breakers, contactors, fuse, switches, voltmeter,
ammeter, protection relay, overload relay, current transformer, etc.) are in good
condition and in particularly meet the drawings, data sheet and specification
requirements.
l) Ensure that there are not obvious damages to equipment and instruments.
m) Ensure that the mechanical operation of equipment, in particular circuit-breakers and
operating devices, is correct. In order to verify this, the circuit-breaker mechanisms
and springs, if any, must be operated, mechanical locks must be checked and, if the
breaker is withdrawable, this operation should also be checked.
Eni S.p.A.
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 17 di 59
6.8.2
TEST
VOLTAGE
(V)
MIN INSULATION
RESISTANCE
(M)
- Up to 1 kV
1000 Vdc
10
- Up to 4.6 kV
2500 Vdc
150
- Above 4.6 kV
5000 Vdc
200
d) A DC high voltage test (pressure test) on both the main and auxiliary circuits shall be
carried out between phases and phase-to-earth. The following conditions must be
adhered to for the tests:
(i) All current transformers secondaries will be short-circuited for the test.
(ii) All voltage transformers shall be disconnected by removal of primary and
secondary fuses for the duration of the test.
Eni S.p.A.
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 18 di 59
(iii) One pole of the testing supply shall be connected to earth and to frame of the
assembly for the phase to earth test.
DC TEST VOLTAGE
(FOR 1 MINUTE)
(kV)
1,5
- 3.6
10 (*)
- 7.2
20 (*)
- 12
28 (*)
- 17.5
38 (*)
- 24
50 (*)
- 36
70 (*)
(*): or as recommended
by Manufacturer
e) Upon completion of testing, reconnect all cables and function test the circuit to ensure
all links and fuses are replaced.
6.8.3
Test Certificates
a) Installation Completion and Mechanical Completion shall be recorded on form
CL-E004 (MOD.ELE.FTC.005).
b) All originals of test certificates generated by supplier must be attached to form
CL-E004 (MOD.ELE.FTC.005) for inclusion in the system test dossier.
Eni S.p.A.
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 19 di 59
Installation Completion
a) Check that the cable installation is as per project specification and drawings.
b) Ensure that the gland certificates meet the Area Classification and Specification
requirements.
c) Inspect the cable glands for tightness and good workmanship. Ensure that the correct
type of gland has been used for the size and type of cable installed.
d) Where conductors have been terminated using crimped connections, ensure that the
correct size and type of crimping lug bas been used.
e) Inspection the earth connections.
6.9.2
6.9.3
TEST VOLTAGE
Eni S.p.A.
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 20 di 59
CABLE OPERATING
VOLTAGE
(V)
U0 /U
5000
6.9.4
INSULATION
RESISTANCE
(M)
(MINIMUM)
(V)
200 (*)
200
Cable lenght (Km)
CABLE OPERATING
VOLTAGE
(V)
U0 /U
BETWEEN
BETWEEN
CONDUCTORS
CONDUCTORS
AND EARTH
(V)
(V)
4 U0
4 U0
TIME
(min)
15
6.9.5
Test Certificates
- MV cable check sheets and test certificates are for individual cables.
- Mechanical completion certification testing of the M.V. cables shall be recorded on
forms CL-E005 and CL-E006 (MOD.ELE.FTC.006 and 007).
Eni S.p.A.
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 21 di 59
Installation Completion
a) Check that cable installation is as per project specifications and drawings.
b) Ensure that the gland certificates meet the Area Classification and Specification
requirements.
c) Inspect the cable glands for tightness and good workmanship. Ensure that the correct
type of gland has been used for the size and type of cable installed and that, where
specified, insulating gland adapters have been installed. Particular attentions should be
paid to barrier glands.
d) Where conductors have been terminated using crimped connections, ensure that the
correct size and type of crimping lug has been used.
6.10.2
CABLE OPERATING
VOLTAGE
(V)
500
600 / 1000
6.10.3
TEST VOLTAGE
(V)
500
1000
INSULATION
RESISTANCE
(M)
(MINIMUM)
1
10
Test Certificates
Installation Completion and Mechanical Completion certification testing of cables shall
be recorded on Forms CL-E006 (MOD.ELE.FTC.007).
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 22 di 59
Installation Completion
a) Note the nameplate rating of the equipment and number, type and rating of batteries
supplied. Compare with the ratings stated on the approved drawings for the
equipment.
b) Ensure that the equipment certificates meet the Area Classification and Specification
Requirements.
c) Inspect the chargers and battery stands for alignment, level and tightness of foundation
bolts and fixing.
d) Inspect the earthing bolts and connections to the earth system, where applicable.
e) Check cleanliness. Where necessary clean the interiors of all control panel, chargers,
etc. Remove any temporary silica-gel drying agents from the panels.
f) Note the type, size and rating of all fuses and protective devices and compare with the
values stated on the approved drawings.
g) Inspect all batteries for cracks, damage, tightness and cleanliness of terminals and
connections.
h) Remove any transit bungs and store for possible future use.
i) Inspect all bolted connections between individual cells in a bank of batteries. Ensure
that all battery terminals have been coated with vaseline or equivalent.
j) Inspect battery circuit breakers.
k) Where batteries and battery chargers are housed in the same cubicle or suite of
cubicles, check the integrity of the gas tight seal between the compartments.
l) Ensure that there is not leakage of the electrolyte.
m) Ensure that connections between cells and blocks are such as to prevent any short
circuit.
n) Ensure that connections from batteries to switchboards are well installed and suitably
marked.
o) Ensure that warning labels, fitted by the manufacturer for special indications, are
intact.
Eni S.p.A.
Exploration & Production Division
6.11.2
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 23 di 59
6.11.3
Test Certificates
a) Installation Completion and Mechanical Completion shall be recorded on forms CLE007 and CL-E008 (MOD.ELE.FTC.008 and 009).
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 24 di 59
Installation Completion
a) Ensure that the equipment meets the Area Classification and Specification
requirements as laid down in the Design Specification and drawings.
b) Note the distribution board circuit numbering and the fuse rating of the circuits and
compare with the approved drawings. Verify the operation of any safety features, such
as interlocks, padlocks and door switches.
c) Note the location of the lighting fittings, sockets, etc. and compare with the approved
drawings. Lighting equipment is correctly located and is no obstructed by pipes or
other plant component thereby preventing the illumination of the areas
d) Inspect the earthing bus-bar and cable earthing connections inside the distribution
boards and the earthing connections from individual items of equipment to the
earthing grid where detailed on drawing refer to the earthing/bonding procedure.
e) Inspect lighting fittings, sockets and switches for neatness, weatherproofing, glanding,
internal connections, general good workmanship and labelling.
f) All equipment in hazardous areas should be inspected in accordance with the
requirements of the procedure for the apparatus for use in hazardous areas.
g) Carry out inspection of junction boxes in accordance with the junction box inspection
procedure.
h) Ensure that the circuits are correctly marked.
i) Ensure that the safety lighting system is installed as per the design project.
j) Ensure that glass and guards of lighting equipment are no broken.
k) Ensure that local lighting panels are suitably welded to the support structure. The
mechanical operation of circuit-breakers is satisfactory.
l) Ensure that protection against corrosion has been provided and is complete or made
good where necessary.
m) Ensure that poles and floodlights are complete with accessories and are earthed.
n) Ensure that road lighting equipment and floodlights are correctly orientated.
6.12.2
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 25 di 59
Test Certificates
a) Installation Completion and Mechanical Completion shall be recorded on form
CL-E009 (MOD.ELE.FTC.010).
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 26 di 59
6.13.2
Test Certificates
a) Installation Completion and Mechanical Completion shall be recorded on form
CL-E010 (MOD.ELE.FTC.011).
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 27 di 59
6.14 Earthing
6.14.1
Installation Completion
a) Compare the earth connection type and size with the Schedule.
b) Where conductors have been terminated using crimped connections, ensure that the
correct size and type of crimping lug has been used.
c) Ensure all connections are tight and greased.
d) In the case of instrument earths, refer to installation specification.
e) Ensure that buried conductors and earth rods are located in accordance with the design.
f) Ensure that conductors installed without protection are sheathed (yellow/green).
g) Ensure that the continuity of the protective conductors (PE), equipotential conductors
and other conductors which form part of the earthing system has been verified.
h) Ensure that conductors rising from the floor or ground are protected by means of a
conduit section.
i) Ensure that buried joints of conductors are protected against damp with a bitumen or
similar mixture.
j) Ensure that earthing and equipotential connections are provided for machines, panels,
equipment, components and structures, including those outside the electrical
installation, as anticipated in the design and in accordance with reference codes.
k) Ensure that down conductors and other apparatus relevant to lightning protection
system comply with the design.
l) Ensure that transformer neutrals are correctly earthed.
m) Ensure that earthing of concrete reinforcing bars has been carried out, if required by
the design.
n) Ensure that terminals and earth bus-bars are correctly installed.
o) Ensure that protective conductors (PE) and earthing conductors are sized in relation to
the design and are correctly fixed and protected.
p) Ensure that metal sheaths and cable armouring are earthed.
q) Ensure that protection against corrosion has been provided and is complete or made
good where necessary.
Eni S.p.A.
Exploration & Production Division
6.14.2
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 28 di 59
ZS U0/Ia
Where:
-
U0: rated voltage between the system phase and earth (V);
Ia: current causing the tripping of the protection device within the times indicated
in the applicable standards (A);
ZS: impedance of fault loop ();
Eni S.p.A.
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 29 di 59
Installation Completion
a) Ensure that the equipment meets the Area Classification and Specification
requirements.
b) Ensure that the equipment identification is correctly shown.
c) Ensure that the heater is free from damage and the paintwork is correct.
d) Ensure that the cables are supported correctly, glands are made off correctly and spare
entries are plugged.
e) Ensure that flanges are undamaged and that seals and gaskets are correctly fitted.
f) Inspect the earthing for
earthing/bonding procedure.
mechanical
and
electrical
continuity.
Refer
to
g) Inspect the terminal box of the heater for neatness of connections and general good
workmanship.
h) All equipment in hazardous areas should be inspected in accordance with the
requirements of the procedure for the apparatus for use in hazardous areas.
6.15.2
6.15.3
Test Certificates
a) Installation Completion and Mechanical Completion shall be recorded on form
CL-E012 (MOD.ELE.FTC.013).
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 30 di 59
6.16 Electrical Equipment & Device (Local Panel - Push Button - Power Socket)
6.16.1
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 31 di 59
w) Ensure that boxes are complete with all bolts and are securely closed.
x) Ensure that plugs fit properly and mechanical interlocks operate correctly
6.16.2
Test Certificates
a) Installation Completion and Mechanical Completion shall be recorded on Forms
CL-E013 (MOD.ELE.FTC.014).
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 32 di 59
6.17.2
Test Certificates
a) There are no specific standard forms for recording that the requirements of this
procedure have been implemented, however, form CL-E013 (MOD.ELE.FTC.014)
may require endorsement to show that the requirements of these procedures have been
complied with.
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 33 di 59
Installation Completion
a) Ensure that doors and hatches close properly, are provided with keys and, from the
inside, can be opened using the handle or crash-bar only as anticipated in the design.
b) Ensure that fencing and boundary limits for keeping persons away from equipment
installed outdoors (e.g. transformers) are correctly installed.
c) Ensure that glass panels are not broken.
d) Ensure that ventilation openings are not blocked off and are fitted with gratings and
insect nets.
e) Ensure that the artificial ventilation system in the panel room and/or battery room
operates correctly.
f) Ensure that the layout of panels and equipment meets requirements as regards working
and safety space, as anticipated in the design.
g) Ensure that all parts of civil works are complete and comply with the design. The floor
slope is correct and the drain pit is clean.
h) Ensure that the floor and walls of the battery room are coated and/or painted with
acid-resistant paint (where necessary). The floor slope is correct and the drain pit is
clean. The floor is fitted with insulating footboards.
i) Ensure that the lighting system and socket outlets are correctly executed.
j) Ensure that the earthing system is complete.
k) Ensure that the floor is fitted with insulating footboards, where necessary.
l) Ensure that canopies are installed on transformers if anticipated in the design.
m) Ensure that fencing and boundary limits for keeping unauthorized persons away are
correctly installed and connected to the earthing system (where necessary).
n) Ensure that protection against corrosion is provided and is complete or made good
where necessary.
o) Ensure that rooms are clean.
p) Ensure that warning labels are fixed to access doors, fencing of transformer bays,
battery room door, etc.
q) Ensure that a set of electrical diagrams is available for whoever must operate the
electrical plant. The one line diagram is correctly displayed and updated.
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 34 di 59
r) Ensure that first-aid equipment and fire-extinguishers are suitably positioned and
available for whoever must operate and maintain the plant. Selectors with automatic
extinction prearrangement and relevant signalling are correctly installed and operative.
s) Ensure that energy tripping pushbutton, if any, is operative and clearly identified.
6.18.2
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 35 di 59
Installation Completion
a) Ensure that control panels are clean and there are no foreign bodies or dust in them.
b) Ensure that there is no obvious damage to mounted instruments and equipment.
c) Ensure that protection devices are set in accordance with the design value.
d) Ensure that doors close properly and are supplied with keys.
e) Ensure that cables and conductors are correctly installed. Conductors of the protection
circuit are correctly connected.
f) Ensure that holes which are not used but which are anticipated for future equipment
and cable inlets are plugged.
g) Ensure that measuring points are correctly positioned in accordance with design and
properly installed.
h) Ensure that measuring points are correctly numbered.
i) Ensure that characteristics of the anodes and reference electrodes for the measurements
are as anticipated in the design.
j) Ensure that the number and location, both plan and depth-wise, of the anodes and
reference electrode are as indicated in the design.
k) Ensure that characteristics of the anodic bed (material surrounding the anodes) are as
laid down in the design.
l) Ensure that the ground of the anode has been compacted and is not subject to future
settlement.
m) Ensure that passive protections against corrosion are provided; these are in complete
execution and do not present faults when restored, if required (painting, thermoplastic
sheaths).
n) Ensure that dielectric joints are correctly positioned and are adequate for the utilization
(operating temperature, isolating and conducting fluids etc.)
o) Ensure that the field connections are properly executed, the connections through bolts
and brazing are protected against corrosion (stainless steel bolts, bituminous or
thermoplastic insulations for buried joints).
p) Ensure that the current absorbed by the protection system is compatible with that of
project design in relation to the adopted protection system: CV constant potential
supply constant current CC CV constant potential with base current Ib.
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 36 di 59
q) Ensure that protective overloads dischargers of insulation joints and those towards
earth are correctly positioned and adequate to the installation site.
r) Ensure that cathodic protection system does not present interferences with other
protected structures and earthing system.
6.19.2
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 37 di 59
Installation Completion
a) Ensure that the equipment meets the area classification and specification requirements,
where applicable.
b) Ensure the mechanical integrity of all components.
c) Inspect the paint finish for damage. Any damaged areas shall be repainted.
d) Inspect the equipment assembly for alignment, level, etc.
e) Inspect the earthing for mechanical and electrical continuity.
6.20.2
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 38 di 59
Installation Completion
The following is a general inspection guide for all types of equipment used in hazardous
areas or specified accordingly and installed in non-hazardous areas.
The particular requirements for special equipment used in these locations will be listed
individually and should be read in conjunction with hazardous area classification data
sheet.
a) Ensure that the apparatus is appropriate to the area classification, the surface
temperature class is correct, the apparatus group is correct and that any special
conditions on the certificate have been followed.
b) Ensure that there are no unauthorised modifications and that it carries correct circuit
identification.
c) Ensure that all bolts, glands and stoppers are tight and that the condition of the
enclosure gaskets is satisfactory.
d) Inspect the interior of the equipment for dust or dirt accumulation and ensure that all
electrical connections are tight. A check should also be made that the electrical
protection is adequate for the drive rating where applicable.
e) Inspect the equipment earthing for security and tightness.
f) Ensure that there is not damage to any cables and that the equipment is adequately
protected against corrosion, weather, vibration and other adverse factors.
g) Ensure that the lamp rating and type are correct.
h) Where guards are used, ensure that they are correctly located and that motor fans and
couplings are not rubbing.
i) The following additional checks are required on special equipment as listed (where
applicable):
(i) Ex'd', Flameproof Enclosure
Ensure that:
- Obstructions in the vicinity of the equipment do not impair the efficient operation
of the flame-path.
- All gaps are correct and free from damage, corrosion, dirt and paint.
- The machined surface may be protected with one of the approved greases.
- All conduit runs are tight and free from corrosion.
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 39 di 59
Eni S.p.A.
Exploration & Production Division
6.21.2
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 40 di 59
6.21.3
Test Certificates
There is no specific standard for recording that the requirements of the Procedure have
been implemented; forms should be used to record the results of any checking and testing
required by the Standard and Code certificate to demonstrate suitability for use in a
hazardous area.
The forms, however, make reference to this Procedure and require endorsement to signify
that the equipment and the standard of installation is suitable for use in hazardous areas.
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 41 di 59
7. PRE-COMMISSIONING REQUIREMENTS
7.1 General
This section covers the general responsibilities of the electrical contractor during Precommissioning of electrical equipment.
a) All work shall be executed in strict accordance with project specifications and the
approved drawings. The written approval of the COMPANY is required for any
deviations by the CONTRACTOR from specifications.
b) The CONTRACTOR shall bring to the attention of the COMPANY any areas of this
specification which conflicts with or does not meet safe and acceptable electrical
practices.
c) The CONTRACTOR shall be responsible for the protection and security of all
equipment during all stages of checkout and commissioning.
d) The CONTRACTOR shall not perform any electrical equipment or system tests that
would either void warranties or damage equipment.
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 42 di 59
7.3 Safety
a) General Safety Precautions
The consequences of shock or burn from electrical systems are serious. Work on
electrical equipment shall, therefore, be performed only when the equipment is deenergised, and by qualified personnel, and who fully understand the electrical system
of the project.
One-line diagrams shall be available at all times. All feeding equipment and circuits
shall be tagged-out and locked-out. The test/check operatives own key or lock shall
form part of the lock-out procedure.
The CONTRACTOR shall be completely responsible for the safety of his own
operatives, and other personnel, at all times.
All equipment such as bus bars, circuit breakers, and motor shall be properly grounded
before any testing or other work is initiated.
b) Equipment Isolation
All equipment shall be physically disconnected from its power source to prevent
accidental injury to personnel resulting from inadvertent re-energisation. Equipment
isolation is necessary to ensure that voltages applied to the equipment under test are
not allowed to back-feed into power transformers, generators, and associated upstream
synchronizing and control circuits. The consequences of back-feeding voltages include
danger to personnel and damage to equipment. A lock-out procedure will be
developed.
c) Medium Voltage Testing
While any high or medium voltage testing is being conducted, the CONTRACTOR
shall ensure that the test area is properly guarded to prevent unauthorized entry and
that DANGER notices are posted adjacent to, and at all access ways to the test area
during the period of the test.
All cables must be discharged both before and after applying any test voltage. Any
associated cables not being tested shall be grounded during the test, e.g., other phase
conductors of a three-phase circuit.
Temporary conductors used for test purposes shall not be sized less than the rating of
the circuit under test.
d) Portable Electrical Equipment
Unless portable electrical equipment is double insulated or connected to ground fault
interrupters, the equipment shall be grounded using flexible supply cable that
incorporates a ground continuity conductor.
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 43 di 59
7.4 Generators
7.4.1
Eni S.p.A.
Exploration & Production Division
7.4.2
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 44 di 59
Test Certificates
a) Pre-commissioning certification testing shall be recorded on Form RS-E001
(MOD.ELE.FTC.020).
b) Any certificates generated by the requirements of electrical procedures (i.e. protection
relay etc.) shall be attached to Form RS-E001 (MOD.ELE.FTC.020) for inclusion in
the system test dossier.
c) Supplier test sheets shall be attached to Form RS-E001 (MOD.ELE.FTC.020) for
inclusion in the system test dossier.
Eni S.p.A.
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 45 di 59
TEST
VOLTAGE
(V)
MIN INSULATION
RESISTANCE
(M)
- Up to 1 kV
1000 Vdc
10
- Up to 4.6 kV
2500 Vdc
150
- Above 4.6 kV
5000 Vdc
200
h) Carry out a power frequency voltage (pressure test) between the MV and LV
windings. The test should be carried out for one minute between each winding with
the core and tank earthed.
Alternatively, a dc pressure test may be applied. Duration of this test shall be fifteen
(15) minutes.
The test voltages to be applied are given in the table below.
TRANSFORMER
WINDING
VOLTAGE
(V)
TEST
VOLTAGE
AC
(V)
MIN INSULATION
RESISTANCE
(M)
5000
10000
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 46 di 59
NOTE: Hi-pot test shall be carried out by supplier (only if original certification
records are not available from the manufacturer).
i) Carry out the required testing of any protection and/or meter circuitry with cables and
bus ducts disconnected and in accordance with Supplier's commissioning instructions.
j) Check phase rotation of transformer secondary windings.
k) Check the operation of cooling fans (if fitted).
7.5.2
to
Forms
RS-E002
Eni S.p.A.
Exploration & Production Division
7.6
7.6.1
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 47 di 59
7.6.2
Test Certificates
a) Pre-commissioning certification testing shall be recorded on Forms RS-E011
(MOD.ELE.FTC.031).
Eni S.p.A.
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 48 di 59
TEST
VOLTAGE
(V)
MIN INSULATION
RESISTANCE
(M)
- Up to 1 kV
1000 Vdc
10
- Up to 4.6 kV
2500 Vdc
150
- Above 4.6 kV
5000 Vdc
200
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 49 di 59
l) Have the coupling broken to separate the motor from the driven unit or the belts
removed from the belt-driven equipment. Ensure that the motor rotates freely and the
rotor end play is within tolerance.
m) Start the motor to determine the direction of rotation and compare this with the
required rotation of the driven unit.
n) Run the motor for about 30 minutes and check the bearings for undue temperature
rise. Check for vibration. Tabulate results after 30 minutes to confirm temperature
stabilizes. On DC motors check for armature sparking (if fitted).
o) Measure and record the line current of the free running motor (at no load).
7.7.2
Test Certificates
a) Pre-commissioning certification testing shall be recorded on Forms RS-E003
(MOD.ELE.FTC.022).
b) Supplier test sheets shall be attached to Form RS-E003 (MOD.ELE.FTC.022) for
inclusion in the system test dossier.
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 50 di 59
7.8.2
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 51 di 59
7.8.4
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 52 di 59
b) Check that all original of suppliers checks list and test records are available.
c) Measure the insulation resistance through the closed isolator (phase to phase and all
phases to earth).
d) Carry out required testing of any protection and/or meter circuitry in accordance with
the requirements of specifications and relevant procedures.
7.8.5
handling.
4) The correct items have been connected together, e.g. the correct set of Current
Transformers have been connected to a given set of relay. This is provided by Primary
Injection Tests.
5) All connections, panel wiring and intertrips are correct. This is provided by Function
Tests.
6) The correct settings and/or adjustments have been applied according to the
requirements of the specification, data sheet and Protection Co-ordination Study.
Eni S.p.A.
Exploration & Production Division
7.8.6
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 53 di 59
7.8.7
Test Certificates
a) Pre-commissioning certification testing shall be recorded on Form RS-E004
(MOD.ELE.FTC.023).
b) Any certificates generated by the requirements of electrical procedures (i.e. protection
relay etc.) shall be attached to Form RS-E004 (MOD.ELE.FTC.023) for inclusion in
the system test dossier.
c) Supplier test sheets shall be attached to Form RS-E004 (MOD.ELE.FTC.023) for
inclusion in the system test dossier.
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 54 di 59
7.9.2
Test Certificates
a) Pre-commissioning certification testing shall be recorded on Forms RS-E005,
RS-E006 and RS-E012 (MOD.ELE.FTC.024, 25 and 32).
b) Any certificates generated by the requirements of electrical procedures (i.e. protection
relay etc.) shall be attached to Forms RS-E005, RS-E006 and RS-E012
(MOD.ELE.FTC.024, 25 and 32) for inclusion in the system test dossier.
c) Supplier test sheets shall be attached to Forms RS-E005, RS-E006 and RS-E012
(MOD.ELE.FTC.024, 25 and 32) for inclusion in the system test dossier.
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 55 di 59
7.10.2
Test Certificates
a) Pre-commissioning certification testing shall be recorded on Form RS-E007
(MOD.ELE.FTC.026).
b) Results of illumination level checks shall be recorded on Form RS-E007
(MOD.ELE.FTC.026).
c) Form RS-E007 (MOD.ELE.FTC.026) shall be endorsed to signify that the
requirements of electrical procedure for apparatus for use in hazardous areas and
procedure for junction box, if appropriate have been carried out satisfactorily.
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 56 di 59
7.11.2
Test Certificates
a) Pre-commissioning certification testing shall be recorded on Form RS-E008
(MOD.ELE.FTC.027).
Form RS-E008 (MOD.ELE.FTC.027) requires endorsement to confirm that the
requirements of electrical procedure for apparatus for use in hazardous areas, battery
and battery charger have been carried out.
b) Supplier test sheets shall be attached to Form RS-E008 (MOD.ELE.FTC.027) for
inclusion in the system test dossier.
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 57 di 59
7.12
Electrical Equipment & Device (Heater, Panel, Junction Box, PushButton Station, Socket)
7.12.1
7.12.2
Test Certificates
a) Pre-commissioning
certification
testing
shall
RS-E009 and RS-E010 (MOD.ELE.FTC.028 and 029).
be recorded on form
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 58 di 59
8. REFERENCE DOCUMENTS
8.1 Specification, Standards and Codes
Electrical installation check and test shall be carried out in accordance with the
requirements of this procedure, the vendors documentation, the project electrical
drawings and with the latest edition of the project specifications and codes:
8.1.1 Standards and Codes
- International Electrical Commission (IEC)
- Others, if required in project specifications.
Eni S.p.A.
Exploration & Production Division
05221 VAR.ELE.SPC
Rev. 4 Dec. 2004
Sheet 59 di 59