Professional Documents
Culture Documents
Tutorial 1
dm / Tutorial_01
1/4
c:/PscadTraining.
Save
the
case
as
T1.2 Open the main page of your new case. Build a case representing a
simplified two area power system as shown in the figure below. A 145 km
transmission system connects a small wind farm to the 345 kV transmission
system. All connections to Bus 1 are represented by an equivalent 345 kV
source. The equivalent source impedance is derived from a steady state fault
study at 60 Hz.
The wind farm has 10 generators, each 0.75 MW at 0.69 kV. The voltage is
stepped up to 13.8 kV at each machine before connecting to the 13.8/115 kV
transformer. The 10 wind generator installations are modeled as an equivalent
machine of 7.5 MW and a 5 MVA transformer.
All required network data are provided in Appendix 1.
Bus 1
Bus 2
#1
#2
P = 5.485
Q = -3.064
V = 115.9
RRL
A
V
T
TLine_02
T
TLine_01
Ia
P = 3.639
Q = -2.344
V = 13.48
#1
#2
A
V
Wind
Generators
45 km line
100 km line
RL
Ea
345 kv
'Weak system
P+jQ
dm / Tutorial_01
2/4
Timed
Breaker
Logic
Closed@t0
BRK1
1.00499
IM
TIME
Tin
P = 3.648
Q = -1.908
V = 0.6438
Transformer 2
A
V
#1
#2
BRK1
TL
*
-1
T1.3 Discuss different components of the system model and the input data with
the instructor.
T1.4 Run the case with a constant -0.5 pu torque input to the machine. Observe
power and reactive power in different line sections.
1
T1.5 The power in the wind (Pw) is Pw = . A. .C p .V 3 . Implement this equation
2
using the control blocks available in the PSCAD Master Library. Assume a
constant Cp value of 0.35 for the exercise.
23.5
Rotor Radius
X2
Constant Cp assumed
Cp = 0.35
0.35
3.14159
PI
0.5
Constant
Pw
1.22
Air Density
*
N
Pw
N/D
750000.0 D
Wind Source
Mean
Gust
N/D
Tin
D
W
0.75 MW = 750000 W
Vw
x
10
3.0
Wind Speed
log X
T1.6 Run the simulation with a mean wind speed of 10 m/s. This will result in a
torque of approximately 0.5 pu.
dm / Tutorial_01
3/4
T1.7 Use the wind model to study the response of the system to a sudden wind
gust. The gust should be applied when the system is in a steady state.
Gust duration 2 s
Peak gust 2 m/s
Change the gust magnitude and duration to different values and observe results.
Note the voltage fluctuations at the 115 kV load bus.
Note the possible overloading of lines and transformers.
T1.8 Use the wind model to study the response of the system to noise
(turbulence) in the wind.
Note the voltage fluctuations at the 115 kV load bus.
Can the voltage fluctuations be controlled using FACTS solutions?
T1.9 Discuss how field data of wind can be used in a simulation. The data in
windvariation.txt is from a field recording. Use this data in the simulation study.
2
w indvariation.txt
windvariation.txt
D + +
4.0
Ws
dm / Tutorial_01
4/4
dm / Tutorial_02
1/3
dm / Tutorial_02
2/3
Wind Source
Mean
Vw
Tin
P
Ctrl = 1
Beta
1.0
Tm
Vw
Noise
Wind Turbine
MOD 2 Type
Vw
N/D
Ctrl
D
3.0
Pole pairs
CNT
*
60.0
2 Pi
BETA
A 6 Pole Machine
Mechanical speed =
W(pu)*2*pi*f/(pole paris)
Beta
P1
*
0.133
Ctrl = 1
0.5
Pg
Ctrl
TIME
Wind Turbine
Governor
MOD 2 Type
CNT
BRK1
1.00499
W
S
TIME
Tin
*
-1
IM
P = 3.648
Q = -1.908
V = 0.6438
A
V
Timed
Breaker
Logic
Closed@t0
Transformer 2
#1
BRK1
#2
A
TL
dm / Tutorial_02
3/3
dm / Tutorial_03
1/3
2.5 [ohm]
0.5968 [H]
2.5 [ohm]
Idc
R=0
26000
gt5
gt3
gt1
dcVltg
P = 147.8
Q = -0.8703
V = 173.3
Eab
26
Einv
R=0
Ebc
26000
6
gt2
0.5968 [H]
2.5 [ohm]
0.5968 [H]
4
gt6
A
V
R=0
#1
#2
4
gt4
Ec Eb Ea
2.5 [ohm]
T1.2 Use this case to understand the basic operation of voltage sourced
converters.
T1.3 In a sinusoidal PWM scheme, a high frequency (triangular) carrier signal is
compared with a low frequency modulating sinusoidal signal to generate the
firing pulses. The resulting voltage at the converter terminals will have a strong
voltage component of the same low frequency. The phase and the magnitude
(modulation) of the modulating signal will shape the phase and the magnitude of
the dominant low frequency voltage component at the converter.
Main : Graphs
1.25
Trig
sine1
1.00
0.75
0.50
0.25
0.00
-0.25
-0.50
-0.75
-1.00
7.7950
7.8000
7.8050
7.8100
7.8150
7.8200
7.8250
7.8300
7.8350
dm / Tutorial_03
2/3
T1.6 Change the control settings (Kp and Ki) and observe the response. At high
gains, will the system become unstable?
T1.7 A more detailed VSC based system is given in the PSCASD case
VSCTrans_wind_01.psc. The synchronous machine on the sending end may
represent wind generation.
C
Cable2
SE
RE
Sending End
T1.9 The control of the converters can be used to optimize the performance of
the wind system.
Can you think of a simple method to limit the power flow into the network during a
wind gust?(hint: angle of the PWM modulating signal influences power flow)
T1.10 Limit the angle order of the sending end PWM signal. This will limit the
power flow in some way (provided the angle limits are reached).
Observe the machine speed. Does the machine speed settle down after
transients?
dm / Tutorial_03
3/3
DFIGAssignment:
LoadtheincompletePSCADcasenameddfig_case_01_inc.psc.Usethiscaseasthestartingpointto
buildtheDFIGcontrolsoftherotorside.
1) Usecurrentsourcestorepresenttherotorsideconverter.
Irc_ref
Irb_ref
Ira_ref
Irot
W
S
IM
V
TL
2) Usingcontrolblocks,implementaschemetodeterminethepositionofthestatorfluxvector.
D
+
Va
C
Isa
*
0.037
A
alfa
D
+
Vb
C
Isb
*
0.037
Isc
*
0.037
D
+
Vc
C
Valfa
B 3 to 2
Transform
beta Vbeta
C
1
sT
G
1
sT
sT
1 + sT
sT
G
1 + sT
phisx
X
M
M
Vsmag
phsmag
X
Y
phis
phisy
phis
3) Determine the slip angle. This is the angle between the rotor Aaxis and the position of the
statorfluxvector.
phis
C
ang +
D
slpang
Angle
Resolver
4) ThefollowingblockcanbeusedtoconverttheDandQaxisrotorcurrentstorespectivephase
currents.
slpang
Ird
Irq
5)
6)
7)
8)
alfa
Rotor
to Stator
Q
beta
D
alfa
2 to 3 B
Transform
beta
C
Irb_ref Irbb
Irc_ref Ircc
UsesliderstoassignvaluesforIrdandIrq.(Note:StartwithIrd=0.05andIrq=0.2)
NotetheresponseofthemachinepowerandthereactivepowerwhenIrdandIrqarechanged.
Themachineissettorunat1.1puspeed.Inarealsetup,thesignalIrqwillcontrolthemachine
speed.Canwechangethemachinespeedsetpointandmaintainunchangedsteadystatepower
andreactivepower?
ConstructasimplecontrolcircuitthatwillmaintainPandQatdesiredlevels.
25.0
A
B
P1
Ctrl = 1
Ctrl
D + -
30.0
A
B
Q1
*
0.25
Irq
F
P1
CNT
1.0
Ctrl = 1
Ctrl
CNT
Ira_ref Iraa
F
Q1
*
0.25
Ird
I
1.0
9) DiscussthedetailsofamoredetailedDFIGmodelDFIG_Model_Feb_07_*.psc
dm / Tutorial_05
1/3
A
V
Stot
-0.5
Station A
#1
55 km line
230 kV
#2
0.037 [H]
0.037 [H]
TL
100 MVA/ 33 kV
RL
Timed
Breaker
Logic
Open@t0
BRK
BRK
RRL
1.004
Add fault
impedance here
T1.4 Load the case frt_case_SM.psc that is included in with the course material.
In this case, the induction machine is replaced by a synchronous machine (fig 2)
dm / Tutorial_05
2/3
S/H
in out
hold
S2M
Vref0 Vref
Exciter_(AC1A)
VT
Ef0
IT 3
Ef
If
3
Ef0
Ef If
A
V
Te
Tm
w Tm
Tm0
W
S/H
out in
hold
L2N
dm / Tutorial_05
3/3
dm / Tutorial_06
1/3
N
Wm
N/D
60.0
1
sT
Clear
3.0
Gear Ratio
No. of Blades
Cos
*
0.05
'shadowing index'
Vw
Wind
F
Vw
A
Compar- B
ator
2 Pi
dm / Tutorial_06
2/3
T1.6 The high starting current will cause prolonged voltage dips in other parts of
the network. Discuss the soft starting technique that can be used to limit the
starting current and hence the voltage dips.
0.0
Twind A
Ctrl = 1
B
Ctrl
0
-1.0
*
W
S
T
IM
Motor
A
V
Breaker
TIME
dm / Tutorial_06
3/3
NetworkData:
Bus 1
Bus 2
Transformer 1
#1
#2
P = 5.485
Q = -3.064
V = 115.9
RRL
A
V
Transformer 2
T
TLine_02
T
TLine_01
Ia
#1
#2
P = 3.639
Q = -2.344
V = 13.48
A
V
Wind
Generators
45 km line
100 km line
'Weak system'
RL
345 kV
Ea
3 MW / 1 MVAR
66.4 kV/phase
Equivalentsource:
345kV
Z+=35Ohms@85degrees
Z0=32Ohms@80deg
Transformer1:
50MVA,345/115kV
Impedance14%(0.14pu)
Losses(noload/cupper):0.001pu/0.002pu
Noload(ormagnetizing)current1%
Transformer2:
10MVA,115/13.8kV
Impedance1%(0.1pu)
Losses(noload/cupper):0.001pu/0.002pu
Noload(ormagnetizing)current1%
Transmissionlines:
3conductorflattower
Mid-Span Sag:
5.486 [m] for Conductors
3.81 [m] for Ground Wires
G1
G2
2.438 [m]
5.0292 [m]
C1
C2
C3
4.724 [m]
.378 [m]
15.316 [m]
Tower: TH-10
Conductors: Penguin
Ground_Wires: 3/8" EHSS
0 [m]
115kVLoad:
3 MW / 1 MVAR
66.4 kV/phase
WindSystemdata:
BRK1
1.00499
W
S
TIME
Tin
*
-1
IM
P = 3.648
Q = -1.908
V = 0.6438
A
V
Timed
Breaker
Logic
Closed@t0
Transformer 2
#1
#2
BRK1
TL
Thissystemrepresents10inductionmachines(woundrotor)operatinginparallel.Themachinesandthestepuptransformers
arerepresentedbyasingleequivalentmachine/transformer.
Machinedata:
MVA0.75MW*10=7.5
Voltage0.69kV
Turnsratio0.2805
Inertia3.694
Mechanicaldamping1%(0.01pu)
Resistance:(stator/rotor):0.0053[p.u.]/0.007[p.u.]
Magnetizinginductance4.0209
Leakageinductance:(stator/rotor):0.1060[p.u.]/0.1216[p.u.]
Transformer3:
5MVA,13.8/0.69kV
Impedance1%(0.1pu)
Losses(noload/cupper):0.001pu/0.002pu
Noload(ormagnetizing)current1%
Data:
External rotor
resistance
1.004
IM
A
V
Stot
-0.5
#1
Station A
55 km line
230 kV
230 kV Eq. source
#2
0.037 [H]
0.037 [H]
TL
100 MVA/ 33 kV
RL
BRK
BRK
Timed
Breaker
Logic
Open@t0
Z+ = 10 Ohms @ 88 deg
Z0 = 7 Ohms @ 82 deg
RRL
Rrotor
+
Rrotor
+
Rrotor
Wind Farm
W
Add fault
impedance here
Machinedata:
Turnsratio2
Inertia1.7
Mechanicaldamping00.0001pu
Resistance:(stator/rotor):0.0034[p.u.]/0.00607[p.u.]
Magnetizinginductance3
Leakageinductance:(stator/rotor):0.0202[p.u.]/0.021[p.u.]
Tutorial
Basic operation of a Thyristor Controlled
Reactor
Prepared by:
Dr. Ani Gole
Dr. Dharshana Muthumuni
Date: May 2007
Revision:
Date:
1/7
Objective(s):
T1.1 Create a new case by using either the Menu or Toolbar. A new case should appear in the
Workspace settings entitled noname [psc]. Right-click on this Workspace settings entry and
select Save As and give the case a name.
NOTE: Do not use any spaces in the name!
Create a folder called c:/PscadTraining/Tutorial_01. Save the case as T_01.psc
T1.2 Open the main page of your new case. Build a case to study the operation of a thyristor
controlled reactor as shown in fig.1.
The applied voltage is 7.03 kV rms line-neutral at 60 Hz.
The reactor is rated at 33 MVAR (per phase or 100 MVAR 3 phase). What is the required
inductance?
Ia
Vas
FP
T
0.00393 [H]
0.001 [ohm]
FP
33 MVAR (Max)
2/7
T1.3 Plot the currents (Ia) and voltages (Vas) on the source side of the circuit.
cos(th)
A
FP
Vc
120.0
VCO
th
*
.5
B Comparator
sin(th)
Main : Controls
Alfa
Ia1
180
Alpa_Order
90
120
2.61419
Alpa_Order
Alfa
3/7
Understand the functions of different control blocks in Fig.3. This simple circuit forms the building
block of more complex thyristor controlled FACTS devices.
Main : Controls
Alfa
Ia1
180
90
120
2.61419
Alpa_Order
Alfa
T1.5 The results in Fig.5 are for a firing order of 120 degrees. Discuss the results and understand
the basic operation of the device.
Main : Graphs
Voltage (kV)
10.0
Vas
5.0
0.0
-5.0
-10.0
Load cur
Current (kA)
4.0
2.0
0.0
-2.0
-4.0
Firing pulse
FP1
0.80
0.40
0.00
180
Alfa_order
thetA
120
60
0
0.310
0.320
0.330
0.340
0.350
4/7
T1.6 The variation of the fundamental component of the reactor current with the firing angle is
given by the following equation.
I( ) :=
1 2 ( ) 1 sin ( 2 ( ) )
w L
Where,
( ) := ( 90) deg
Verify the PSCAD results with the calculations outlined in the accompanying MATHCAD
worksheet (TCR.mcd). You may use the FFT (Fast Fourier Transform) model in the Master library
to extract different frequency components.
Mag
(7) 1
FFT
Ph
(7)
Ia
F = 60.0 [Hz]
dc
Discuss the Phase angle error due to the time step delay inherent to the
simulation.
Your instructor will explain the calculation program structure of EMTDC and the definition of
electric and control type models.
T1.8 Observe the harmonic spectrum of the source current. Note the absence of higher order
harmonics. The results shown in Fig.7 are for a firing angle of 120 deg.
Ia_
4.0
0.0
[1] 2.62733
5/7
In( , n ) :=
4 V
L w
n n 1
where n := 3 , 5 .. 15
The example discussed so far uses a simplified control setup to generate the firing pulse.
T1.9 Load the case TCR_2.psc.
The firing pulses are generated based on a Phase Locked loop (PLL) based control system. The
phase locked loop generates a sinusoidal signal that is locked in phase to the system voltage
Vs. Understand the various blocks of the PLL.
T1.10 Observe the internal signals of the PLL.
T1.11 Verify the correct operation of the TCR under the following situations.
Sudden change in the system voltage phase angle (possible due to load changes
in the system etc.)
6/7
Appendix:
Peak current (theoretical) at different firing angles (results from Mathcad)
7/7
Tutorial
Simple Thyristor Switched Capacitor (TSC)
This tutorial highlights the operation of a TSC and show the detrimental effect of
misfiring.
LC tuned to
157.55E-6 [H]
Fp
7.0 kV (l-g)
Source
VQ
Fp
1786.43 [uF]
Vs
100000.0 [ohm]
0.001 [ohm]
Ph
300 Hz
33 MVAR
Vc
Max
Misfire Sw.
On Switch
2:
Reset
Forced Firing
0Xing Forced
Retard
1
-1
b) Set R = 100000 Ohms (infinite). Note that the voltage crossing based switching
will not work as the capacitor voltage is higher than the system voltage (due to
voltage amplification in the L-C circuit).
Set the switch to the forced firing position. The logic is set to fire the thyristor at a
voltage peak. In a real system, they should fire at the peak where the difference
between the capacitor and the system voltage is minimum. However the logic
does not ensure this. This gives you the opportunity to investigate what happens
when you accidentally fire at the wrong peak.
Investigate the waveforms with forced firing at the correct as well as the
incorrect instant. Also, observe the magnitude of the voltage amplification. Does
it agree with theory?
c) A pushbutton is provided to initiate a single thyristor misfire. Investigate the overvoltages seen by the thyristors following misfires at different instances.
A metal oxide arrestor (MOV) is usually placed across the thyristor to prevent
over-voltage damage. As its protection level is set rather low, the arrestor is often
triggered following an over-voltage. It does not conduct during normal operation.
d) Place a surge arrestor across the thyristors and observe the reduced over-voltage
following the misfire.
PSCAD TUTORIALS
Power Quality Examples
Tutorial 5
Simulation of flicker due to an Arc Furnace load.
dm / Tutorial_05
1/4
Objective(s):
Modelinganarcfurnace
Modelingflickerduetotheoperationofarcfurnace
MitigationofflickerusingaSTATCOM.
Loadthecaseeaf_statcom.psc.
Thiscaseillustratesthestartingoperationofanarcfurnace.Arcfurnaceloadsarehighly
nonlinearandrandominnature.Thisgivesrisetofluctuatingcurrentsandresultsin
voltagefluctuations.
This case illustrates the basic features of a STATCOM. Discuss with the instructor and
understanddifferentcomponentsofaSTATCOManditscontrols.
RunthearcfurnacecasewiththeSTATCOMinoperationandverifythattheflickerlevel
isreduced.
Change the STATCOM transformer rating and determine the minimumrating required
toreducetheflickerlevels.
dm / Tutorial_05
2/4
k
r
3
m +2
The parameters ki, r and n characterize the arc under a given operating
condition. In reality, this V-I characteristic shows much more noise due to the
unpredictable and chaotic nature of the load. Fig. 1b shows a more realistic EAF
V-I characteristic.
Main : XY Plot
X Axis
Y Axis
I2
V2
100
+y
75
50
25
-x
+x
-25
-50
-75
-100
-1.50
-1.00
-0.50
-y
0.00
0.50
Aperture
(a) Ideal
1.00
1.50
Width 2.5550660793
0.000s
20.000s
Position 11.661
(b) Actual
3/4
dm / Tutorial_05
4/4