Professional Documents
Culture Documents
FCE 525
Prof. Patts M.A. Odira
Key Textbooks:
1. Water Resources Engineering by David A. Chin 2nd
Edition, Pearson Prentice Hall; 2006.
2. Water Resources Engineering by Ray K. Linsley; Joseph B.
Franzini; David L. Freyberg; George Tchobanoglous, 4th
Edition, McGraw-Hill, Inc, 1992.
Other Reading Books:
1. Hydrology and Water Resources Engineering by S.K.
Carg; 11th Edition, Khana Publishers; 2000.
2. Elements of Water Resources Engineering by K.N. Duggal
and J.P. Soni; New Age International Publishers; 2007.
3. Hydrology for Engineers by Ray K. Linsley JR.; Max A.
Kohler; Joseph L.H. Paulhus; 3rd Edition; McGraw-Hill
International Book Co; 1984.
Course Content
Water Law:- Introduction to common law; Water Codes;
Ground Water and National Law and Water policy. Planning
for Water Resources development:- National, regional,
catchment planning; objective of planning; planning process;
introduction to multiple purpose projects; introduction to
systems analysis. Economics in Water Resources planning:Importance; costing and cost allocation; interest rates; taxed;
economy studies e.g. cost-benefit, annual cost comparison.
Water resources for arid and semi arid areas:- Surface and
subsurface Dams; Rainwater Harvesting.
Course Content
Dams; spillways; gates and outlet works:- Focus on types of
spillways, gates and outlets; scour protection and energy
dissipation. Reservoir: physical characteristics; capacity and
yield of reservoirs determination methods. Sedimentation in
reservoirs. Hydroelectric power:- types of plants and layouts;
systems and loads in power plants, arrangement and
operation of elements. Power duration curves.
law)?
Elevation
Elevation
area- elevation
curve(capacity curve)
Elevation
w.r.t
(m.s.e)
area elevation
curve
900
area
storage volume
SURCHARGE
STORAGE
POOL LEVEL AT DESIGN FLOOD
NORMAL POOL LEVEL
DAM
USEFUL STORAGE
STREAM
BED
MINIMUM POOL
LEVEL
Sluice
way
Oct.
Nov.
Dec.
Jan.
Feb.
March
Inflow vol. m3
2*106
30,000
10,000
5,000
1,000
3,000
Pane evaporation
(cm)
15
17
14
6.5
Precipitation (cm)
12
14
Water demand m3
40,000
80,000
130,000
140,000
130,000
30,000
Month
Flow
(m3)
Oct
Nov
Dec
Jan
Feb
March
20x105
30x103
10x103
5x103
1x103
3x103
TOTAL
9
15
17
14
8
6.5
12
3
5
2
0
14
Demand
(m3)
D/s
priority
Req. (m3)
40x103
80x103
130x103
140x103
130x103
30x103
100x103
30x103
10x103
5x103
1x103
3x103
10
Evap.
Precip.
3
Vol. (m ) Vol. (m3)
Adjusted
flow vol.
(m3)
Req.
Capacity
(m3)
252x103
420x103
466x103
392x103
224x103
182x103
2032x103
-324x103
-306x103
-328x103
-224x103
266x103
0
404x103
436x103
468x103
354x103
0
384x103
96x103
160x103
64x103
0
448x103
1662X103
= 0 if result is ve.
(+ve)
(Flow-Demand)
Peak 1
Storage
(-ve)
Maximu
m
Storage
Time
Cumulative
rates flow
400
300
200
Capacity to
satisfy
demand
B
Demand
/Year
A
Capacity
Spill over
1 Year
100
1
Capacity to
satisfy
demand
2
Year
3.6.Reservoir Sedimentation
The ultimate destiny of all reservoirs is to be filled with sediment.
If sediment inflow is large compared to the total capacity of a
reservoir, the useful life of the reservoir will be very short.
Reservoir planning must include consideration of the probable rate of
sedimentation in order to determine the useful life of a reservoir
before it is constructed.
Sedimentation occurs as a result of 2 processes;
1. Erosion of soil
2. Transport of the eroded soil (sediment) by water.
1. Erosion of soil may be due to several causes but the major ones are
o Rain
o Flowing water
J
S
ConcentrationDistribution Curve
Finite depth
y
Ca
=
Where C = concentration of sediment of sediment in the water at
a depth y
Ca = concentration at any finite depth a
D = depth of channel
And
1
4
2
3
Log Qs
Amount of sed
sediment flow
sample kept at
a fixed depth
; , ; , ; , ; , ; , ; , ; ;, ,; ;, ,; ;, ,; ;, ,; ;, ,; ;, , ; , ; , ; , ; , ; , ; ,
..
..
. .. .
..
..
..
..
. . . . . .....
.
.
.. ... .
.. ..
. .. .
. . . . .... . .
. .. .
. .. .
..
..
...
... ..
..
... ..
.. ..
..
.. ..
of a delta
density currents
,.
,.
., ,.
.,
,.
,.
.,,. ,.
,.
,.
.,
,.
,.
., ,.
.,
,.
,.
,.
,. ,.
,.
,.
,.
,. .,
,.
,. ,.
,.
.,
,.,. ,.
,.
,. ,. .,., ,.,.
., ,.
., ,. ,. ,.
.,
,.
,.
,. ,.
,.
.,
,. ., .,
., ,. .,.,
,. ,. .,.,.,,.,.
,.
,. ,.
,.
,.
., ., ., ., ,. ,.
., .,,.,.
.,
., ., ,. ., .,,.., ,.
., ,.
.,
., ., ., .,
,.
,.., ., ,. ,. ., .,.,,. .,
.,
.,
.,
,.
,.
,.
,.
., .,
.,
,.
., .,
., ,. ,. ., ,. .,,..,,. .,
,. ., ,. .,
.,
.,
., ,. ., .,,.
., ,. ., ,.., ,.
,.
,.
.,
.,
,.
,. .,
., ., ., ,. ,.
., ,. .,,.., ., .,
.,
,.
,.
., ,. .,
,.
.,
.,
.,
., ,. .,
.,., ,.
.,
.,
.,., ,.., ., ,.
., ,. .,
.,
.,
.,.,
.,
,.
., ,.
,.
Trap eff.
,.
,.
,.
Capacity/inflow ratio
Trap eff
% sediment
trapped
80
60
40
20
0
0.001
0.01
0.1
1.0
10
100
CHAPTER FOUR
FLOOD ROUTING
4.1. Reservoir Routing
A process that shows how a flood ware can be reduced in
magnitude and lengthened in time (attenuated) by the
use of storage in the reach between two points of a
stream.
Routing techniques are used to compute the hydrograph
which will result from a specified pattern of rainfall
excess.
Discharge Q
out flow
(routed flow)
i.e
(1)
(2)
elev
or
Storage capacity
elev
Storage capacity
elev
Q
2
Inflow
hydrograph
= routing
internal
Storage (S)
storage in m3 = x 24 x 60 x 60
If t = 24 hrs the storage scale is plotted in 1
cumec-day
F
C
A
(I +
I
1 2)
2
(I +I
1 2)
Storage
WS
x=0.2
WS
x=0.3
WS
x=0.4
WS
a
K=b
a
Co =
Co =
(i)
(ii)
(iii)
Outflow
hydro graph
when x=1
Outflow
hydro graph
when x=0
Q
Small k value
Large k value
I
(m3/5
Time
(h)
I
(m3/5)
0
5
10
15
20
25
30
35
28.3
26.9
24.1
62.3
133.1
172.7
152.9
121.8
40
45
50
55
60
65
70
90.6
70.8
53.8
42.5
34.0
28.3
24.1
Now C1 =
Now Co =
= 0.2
= 0.2
= 0.6
C1 =
C2 =
= 0.13
= 0.30
= 0.57
I
m3/s
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
5.38
4.82
12.46
26.62
34.4
30.58
24.36
18.12
14.16
10.76
8.50
6.80
5.66
4.82
28.3
26.9
24.1
62.3
133.1
172.7
152.9
121.8
90.6
70.8
53.8
42.5
34.0
28.3
24.1
5.66
5.38
4.82
12.46
26.62
34.4
30.58
24.36
18.12
14.16
10.76
8.50
6.80
5.66
16.98
16.81
16.21
20.09
35.5
57.91
73.73
77.20
71.81
62.45
52.42
43.01
34.99
28.47
28.3
28.02
27.01
33.49
59.17
96.52
122.89
128.67
119.68
104.09
87.37
71.68
58.31
47.45
38.95
The effect of
increasing the
value of X to x=0.1
is to reduce the
peak of the
outflow
hydrograph and
delay the outflow
time slightly.
Spillway
discharge
m3/s
Reservoir
Storage
(1/4 cumec
days)
0
100
200
300
400
500
600
700
800
900
1000
10,000
10,200
10,400
10,600
10,800
11,000
11,240
11,500
11,800
12,080
12,400
Time
(Hrs)
0
6
12
18
24
30
36
42
48
54
60
Flood inflow
m3/s
0
80
200
500
900
800
600
400
200
100
0
Time
O2
0-6
6-12
12-18
18-24
24-30
30-36
36-42
42-48
48-54
54-60
18
65
180
395
565
910
575
475
350
215
1990
1991
1992
1993
January
February
March
April
May
June
July
August
September
October
November
December
40x1010
80x1010
120x1010
200x1010
240x1010
400x1010
720x1010
880x1010
960x1010
1040x1010
1090x1010
1120x1010
1140x1010
1150x1010
1560x1010
1760x1010
2140x1010
2200x1010
2240x1010
2260x1010
2270x1010
2275x1010
2278x1010
2280x1010
2320x1010
2400x1010
2440x1010
2445x1010
2480x1010
2520x1010
2560x1010
2570x1010
2580x1010
2590x1010
2610x1010
2610x1010
2650x1010
2760x1010
3160x1010
3280x1010
3320x1010
3760x1010
4080x1010
4240x1010
4320x1010
4360x1010
4480x1010
4560x1010
CHAPTER FIVE
SPILLWAYS, GATES AND OUTLET WORKS
Spillways: discharge floods downstream and protects
the dam from being damaged by overtopping.
Gates & sluiceways: Provided on the spillway crest
to permit outlet works the operator to control the
release of water downstream fro various purposes
5.1 Spillways
regarded as the safety valve for the dam
Designed to have the capacity to discharge major foods at the
same time as keeping the reservoir level below same predetermined maximum level.
Of 2 types:
o Controlled provided with crest gates or other facility so
that the outflow rate can be adjusted.
o Uncontrolled free discharging once the water level rises
above crest level.
Selection of capacity is related to the degree of protection
required to be provided to the dam
This in turn depends on:
o Type of dam
o Location of dam
5.1.5
or
(4)
Gate loss for a fully open gate and butterfly value is taken as 0.2v2
2g
Headloss through trash racks are found to follow the table below. v2
(5)
Velocity thro
Head loss
Trash rack (m/s) (m)
0.15
0.20
0.30
0.40
0.45
0.50
0.60
0.62
0.006
0.01
0.03
0.05
0.09
0.09
0.13
0.15
(7)
Typical scour
protection works
Appurtenances in
a stilling basin
CHAPTER SIX
WATER LAW
6.1
Introduction
6.4.3.Climate variability
Catchment degradation is causing increased runoff, flash
flooding, reduced infiltration, erosion and siltation and this is
undermining the limited sustainable water resources base in
the county.
6.4.8. HIV/AIDS
HIV/AIDS is also causing untold suffering, particularly
for those living in the rural areas. The challenge for
the GoK is to ensure access to water, among many
other needs, by these vulnerable members of the
society so as reduce water related ailments and
improve their standard of living.
6.5.Policy Direction
In recognition of these issues and challenges, the Government
initiated a process of reform for the entire water sector. The
sector is being transformed in line with national policy as
outlined in the Water Policy Sessional Paper No. 1 of 1999,
which gave birth to the Water Act of 2002, and subsequent
strategies especially the National Poverty Reduction Strategy
Paper, and the Economic Strategy for Wealth and Employment
Creation.
INSTITUTION
3.
4.
5.
7.
8.
9.
10.
11.
12.
National Irrigation
Board (NIB)
CHAPTER SEVEN
POWER SYSTEMS
7.1. Introduction
Most modern power systems are either thermal or hydro
plants. Selection of either depends on an economic analysis of
costs versus energy produced over a given life time. The least
cost solution is then selected.
Initial cost of hydropower plants are usually much higher than
for thermal plants.
Cost of hydropower plant includes,
Dam
Diversion work
Conduits
Land
80
KW
70
X10 3
60
50
40
30
Typical curve
for residential area
load factor =0.6
20
10
12 2
8 10 12 2
Time of day
4 6
10 12
.
thermal power
power
water power
Time of day
Power
Water
Power
Thermal power
Time of day
CHAPTER EIGHT
ENGINEERING ECONOMY IN WATER
RESOURCES PLANNING
8.1 Social Importance
Once the project is completed major water control structures
cannot be altered with ease; it may not be possible to alter
them at all.
There are only a few suitable dam sites, once they are
appropriated; the possibilities for the economic multipurpose
development are very limited.
Once an irrigation project is developed it cannot be moved
because unfavourable soil or climate factors are discovered.
Annual
O&M
Av.
annual
flood
damages
400,000
Annual
damages
and project
costs
400,000
Channel imp.
alone
500,000
250,000
28,715
100,000
378,720
Dev. At site A
alone
3,000,000
190,000
94,950
60,000
344,950
Project
Investment
No flood
mitigation
Annual
investment
charges
126,600
Annual
O&M
80,000
Annual
damages and
project costs
331,600
Site A with
3,500,000
channel
improvement
100,000
123,670
160,000
383,670
Site B with
4,500,000
channel
improvement
60,000
155,320
180,000
395,320
Project
Project
No.
Annual Annual
benefits costs
1
2
3
4
5
6
0
150,000
210,00
275,000
300,000
340,000
400,000
128,720
154,950
206,600
283,670
335,320
Benefitcost
ratio
0
1.17
1.36
1.33
1.06
1.01
Benefits
minus
costs
-400,000
21,280
55,050
68,400
16,330
4,680
1
2
3
4
5
6
0
150,000
210,000
275,000
300,000
340,000
400,000
128,720
154,950
208,600
283,670
335,320
0
60,000
65,000
25,000
40,000
0
26,230
51,650
77,070
51,650
Extra
benefits
to extra
costs
0
2.29
1.26
0.32
0.77
(7.1)
and
F
n= F
,
i,
n
=
(1
+
i)
P
P
(7.2)
1
P
P
=
i,n , =
n
F
(1 + i) F
(7.3)
i
A
A
=
i,n =
F
(1 + i)n - 1 F
(7.4)
i,
n
=
=
i
A
A
(7.5)
i(1+i)
A
A
=
i,n =
n
P
P 1+ i - 1
n
(7.6)
P
1+ i - 1 P
=
,i,n =
n
A
A i(1+i)
n
(7.7)
P
P
1+ i - in - 1
=
,i,n =
2
n
i (1+i)
G
G
(7.8)
A
1
i,n = G
i
n
A
=
n
(1 + i) - 1
G
(7.9)
- n ]=
i,n = - [
i
G
G
i
(7.10)
In cases where the initial return at the end of the first year is Ao
and the annual return increases by an increment G in
subsequent years, the present worth of these is calculated by
adding the present worth of the annual series Ao over n years
to the present worth of the uniform-gradient series with
annual increments of G.
n
1
1 i
g , i,n =
ig
A0
A0
1 i'
(7.10)
CHAPTER NINE
RAINWATER HARVESTING
The areas are called catchments areas and may be divided into
3 types depending on the surface of the catchments area.
Type 1 areas: Total run off occurs in areas with hard surfaces
such as roofs and rocks.
Type 2 areas: Half run-off comes from semi-hard surfaces eg
roads, compounds around a house and rocky slopes.
PAVED AREA
STORAGE
TANK
gravel
run-off pipe
plastic
sand sheeting
SAND BED
slotted
PVC
--------GRAVEL
STORAGE
TANK
CLA
YB
AR
RIE
R
fac
Wa
e re
ter
h
ser
eld
the
voir
i
n sa
imp
erv
nd
iou
by
sb
arri
ers