Professional Documents
Culture Documents
Work Break-down structure is one of tools used in designing projects. It is a graphical presentation of the
various activities to be undertaken in the project together with the corresponding time duration required to
complete each task. In many cases the expenditure needed to accomplish each activity is also included.
Gannt Charts are graphical tools used to display the logical sequence of the various tasks/activities to be
undertaken in a project with their corresponding time durations.
Critical Path is the path with the longest duration. It determines the project duration. Thus, it is the path you
cannot alter or tamper with.
Preceding table is the table showing the preceding activity which is the last activity that must be completed
before the activity at hand can be done or accomplished.
STEPS
1. Identify the various tasks of the system or project i.e. sub-systems of the project
2. Do task sequencing i.e. determining logical relationships between tasks or the order in which the tasks
must be undertaken to achieve the goal of the project
3. Estimate the time duration of each and every task
4. Identify milestones or indicators for measuring progress/achievements. Milestones act as checklists
for assessing progress of the project.
5. Estimate the time for completing the entire project (allocating time for each activity)
6. Construct activity/task graph e.g. the Ganntt Chart
7. Prepare the work break-down structure
8.
There are two common techniques applied in planning the time duration of projects:
Forward Planning Method: Involves setting the start-date of the project and then determining
the end -date based on the time each activity will take.
Backward Planning Method: Involves setting the end-date of the project and working backwards
to fit activities within the limits of the available time.
Simple Project: Organize a birthday party for your sister. Come up with the following:
SOLUTION
Activity
Preceding Activity
Duration (hrs)
Invitation of guests
12
Confirmation of attendance
12
Budget Preparation
Purchase of Goods
Preparation of Food
0.5
E, F
0.25
Celebration (partying)
B,G
C (1)
D (4)
4
E (5)
START
1
5
F (0.5)
A
(12)
G(0.25
)
3
6
B(12)
END
H(3)
(ii)
(iii)
DESCRIPTION
Ultimate Effects
(Manifestation of PROBLEMS)
Immediate Effects
Underlying Problems
Root Causes
Outcomes
Outputs
Means/Resources/Strategies/
Objectives/Activities
3. SELECTION OF OBJECTIVES/PROJECTS
4. ACTIVITY DEVELOPMENT
1. Grouping of objectives
into
themes/classes
2. Give an all encompassing title to
each class.
3. Eliminate unachievable objectives
4. Fine tune the objectives i.e. align
the objectives to the aspirations of
beneficiaries: Needs Assessment;
Feasibility study etc
5. Develop final list of selected
objectives: These become the
PROJECTS
From
the
list of selected
objectives/projects;
identify
5. PROJECT DESIGN
(i)
(ii)
Do
task
sequencing
i.e.
(iv)
(v)
Determine
total
duration
or
project
completion
(vii)
(viii)
6. IMPLEMENTATION/EXECUTION
monitoring
Processes
Outputs
Outcomes
Impacts
and