Professional Documents
Culture Documents
I , February 1992
222
C.J. Bridenbaugh
D.A. DiMascio
Ohio Edison Company
Advanced Engineering & Planning Department
Akron, Ohio 44308-1890
transformers, most of which are fixed tap, and over 100 sites for new
or additional capacitor bank installations. The intent of this work was
to determine the transformer tap settings and reactive allocation to
provide the best possible voltage profile for all foreseeable system
conditions while minimizing losses and reactive iniports. Due to the
large number of voltage control devices being studied, an optimal
power flow (OPF) was used for most of the analysis. The use of an
OPF eliminated a significant amount of the trial and error work
normally associated with this type of study. This study demonstrates
the benefit of an OPF for transmission planning studies in addition to
previously demonstrated system operation benefits.
ANALYTICAL APPROACH
INTRODUCTION
Ohio Edison (OE) is completing a program which eliminates all
PCB substation capacitors on the transmission and subtransmission
system. One approach to implementing such a program would be to
replace existing PCB capacitor banks on a one-for-one basis with new
non-PCB banks.[l] A potentid disadvantage in this approach is that it
presupposes that all the existing banks are still required in the
locations and at the MVAr ratings that were determined under different
system conditions than exist today. The early planning for the
replacement program recognized an opportunity to review and more
optimally locate and size the reactive compensation needs of the
system. This planning also recognized that capacitive correction
should be coordinated with other voltage control elements, such as
transformer tap settings,in order to improve the overall operation of
the transmission system.
The primary objectives of this study were to improve the voltage
regulation between light load and on-peak load periods and minimize
losses while determining an appropriate level of reactive
compensation. The voltage regulation problem generally consists of
limiting high voltages during light load periods and low voltages
during on-peak periods. Voltage variation between light load and onpeak periods should be minimized. On-peak and light load system
models were established as the basis for the studies. Considerable
attention was placed on verifying that these base models were realistic
representationsof system performance.
A voltage control evaluation can be accomplished using a
conventional power flow program. However, for a major system
evaluation this method requires the running of numerous trial and
error cases and engineering judgment to find the "optimal" solution.
This type of evaluation can be performed more efficiently and
effectively with the use of an Optimal Power Flow (OPF) program.
An OPF will help determine the minimum amount of control
movement and capital cost necessary to optimize power system
quantitiesby optimizing specified control variables.
The work described in this paper involved the study of all existing
and currently planned voltage control devices on the OE transmission
and subtransmission system. These devices included 104
9 1 SM 4 3 6 - 6 PWRS
A paper recommended and approved
by the IEEE Power System Engineering
Committee
of the IEEE Power Engineering Society for presentation at the IEEE/PES 1991 Summer Meeting, San Diego,
California, July 28 - August 1, 1991. Manuscript
submitted January 3 0 , 1991; made available for
printing May 29, 1991.
A.
0885-8950/92$03.0001992 IEEE
223
B. Constraints
Two key constraints were utilized in defining the optimization
function for this study. These constraints were the upper and lower
bus voltage limits and the relative capacitor installation cost ratios.
The original specified voltage constraints were a maximum of
1.05p.u. for 345 kV, 138 kV, 69 kV and 34.5 kV networks and
1.07P.U. for 23 kV networks. The minimum voltage level specified
was 0.95 p.u. for all voltage classes. The upper voltage level
corresponds to the maximum steady-state design voltage currently
considered for each voltage class. The lower voltage was chosen to
limit the variation in voltage on the transmiSsion and subtransmission
systems between light load and peak loading periods. Some specific
bus voltage limits were specified during the study to avoid extensive
voltage control adjustments for an isolated area.
Voltage limits had the single largest impact on the results of both
the transformer tap and capacitoroptimization. An increase of as little
as 0.01 p.u. in the low voltage limit would cause a substantial increase
in the required capacitor additions. Correspondingly, a decrease of
0.01 p.u. for the upper voltage limit on the 23 kV system required
transformer tap setting adjustments which caused a substantial
increase in the requiredcapacitive additions.
When bus voltages could not be held within the specified
constraints for the given system conditions and available voltage
control elements, the magnitude of all voltage violations was
minimized
General comparative inslallation and replacement costs were
specified for capacitoradditions. The relative costs used reflect higher
installation costs at higher voltage classes. The cost for replacement
installations representsinstallingnew capacitors at sites where existing
banks will be removed. This cost was set to 75% of the cost for new
installations to account for utilization of existing controls, structural
steel, and switching devices. Capacitor bank increment additions for
the various voltage classes were also defined. The size of the
increment additions were larger for the higher voltage classes. These
relative cost ratios and increment addition sizes are indicated in
Table 1.
Table 1
General Installation Sizes and Costs
size WVArS)
BusIkylM&&uLnBlpEkmIiszhma
138
69
34.5
23
84
80
45
12.6
8.4
8.0
4.5
2.0
1.0
1.0
1.0
1S O
.75
.75
.75
C. Study Procedure
All existing and planned substation capacitors are switched either
by automatic voltage control or by operator control voltage ovemde
via SCADA. They are switched on and off as system requirements
change. However, most of the transformers on the system are fmed
tap. Although some fned taps are changed seasonally, the desired
operation is to set the taps at a position which would be acceptable
year round while using capacitors for daily and seasonal voltage
control. To achieve this desired mode of voltage control the
transformertaps were frst optimized to satisfy voltage constraints for
the light load system conditions. The new tap settings were then
incorporated in the peak load case, where the capacitor optimization
was performed.
The light load system case represents the maximum expected
voltage levels on the system while the peak load case represents the
minimum expected voltage levels. For light load conditions it is
assumed that the generators will be at their current light load operating
level and that all shunt capacitors will be switched off. Therefore,
transformer tap setting changes are the most economic and effective
means for reducing the light load voltage levels. For peak load
conditions the generators are assumed to be at their current peak load
operating level and all shunt capacitor banks are available for voltage
control. The transformer tap settings are also assumed available for
voltage control for the peak load case, but are limited by the maximum
setting permitted to ensure voltage constraints are met for the light load
system case.
The transformer and capacitor optimizationswere performed in an
iterative process, requiring passes between the peak and light load
cases. An iterative process was required to ensure a practical
implementation of the transformer tap and capacitor optimization
results. If extensive transformer tap setting changes or capacitive
additions were required to correct isolated voltage violations, the
voltage constraints at these buses were modified. Figure 1 shows a
flow chart of the study process.
The first step is to prepare the on-peak and light load data sets.
T h i s involves specifying the initial load and generation schedules and
initial voltage constraintsfor both load levels. Major system additions
currently planned are also included in the study data sets.
Transformer tap settings are optimized for light load conditions.
The objective of each optimization is to determine tap settings for all
fned tap transformers which keep bus voltages within their limits and
minimize system losses. Bus voltages are reviewed after each
optimization. If the results are not acceptable or practical, voltage
limits can be changed and the process repeated. For each transformer
tap optimization run a preliminary capacitoroptimization is p e r f o d
for the on-peak load case. This ensures the feasibility of the
transformer tap recommendationsfor on-peak capacitor optimization.
This process continues until all tap settings are determined and
acceptable voltages are achieved. These tap settings are then set in the
on-peak case.
When a tentative transforiner tap schedule has been established,
the optimum substation capacitor bank allocation is determined using
the on-peak load model. All existing PCB capacitor banks are
removed from the data base and the associated buses are identified as
possible replacement locations. All non-PCB capacitor banks
normally used for voltage control under peak load conditions are left
on. Existing non-PCB capacitors used for contingency voltage
suppor~are assumed available at a zero installation cost. All Company
substations are initially designated as candidate buses for either new or
additional capacitors. At each candidate bus the maximum bank size,
switching block size and relative cost per installed MVAr are specified
as input to the OPF.
224
Initial Data
Set Preparation
1
Set Voltage Limits
Light Load
Optimize Taps
peak load. The actual generator operating levels for light load
conditions were used and all shunt reactive compensation was
assumed off. The reactive load was varied to model the actual
maximum voltage levels which had been experienced for light load
system conditions.
During these projected light load conditions some bus voltages
exceeded 1.05 P.U. on the subtransmission system. Voltages on the
345 kV and 138 kV transmission system were within the specified
acceptable range. The main objective of the fixed tap transformer
optimization was to bring the subtransmission voltages below the
maximum acceptable voltage level of 1.05 p.u. (1.07 p.u. for the
23 kV system) while minimizing the voltage reduction on the 138 kV
transmission system.
A total of 104 transmission and subtransmission transformers
were included in the optimization. The number, voltage rating and
type of tap changing were:
18 345-138 kV transformers
48 138-69 kV transformers
11 138-34.5 kV transformers
2 138-23kVtransformers
104 Total
Optimize Caps
RESULTS
A. Transformer Tap Optimization
The transformer tap optimization was performed for a light load
system case. The active system load was 1,740 MW, or 42% of the
no LTC's
no LTC's
all LTC's
lLTC
225
1.15,
0 ORlG TAPS
a 1.
...................
=(%)YT 1
40
20
60
80
100
NUMBER OF BUSES
YT w i l l h a v e t h e f o r m - j B T ,
w h e r e BT>O
1 .1 - ...........................................................................................
3
1 -05 -
L
-------A-;.
2
-I
5?
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .........................
1 - ..............
0.95
B. Capacitor Optimization
1
40
20
60
100
80
120
NUMBER OF BUSES
1.06
0 O R l G TAPS
1.04
1.02
,.
..
4
!-
-1
0
=-
0.98
0.96
0.94
..
.
..
..
.
.
F
G
BUS NAME
226
1.1
2
3 BASE
9 NEWTAPS
4000~
1.05
3000.-
n
v
cl
5
>
0
A--
2000-
-.._
---+--
----*
---+- , -----A
0.95 - ............................................ .,..........................................
,
1000--
0.9
1
0
10
20
30
40
NUMBER OF BUSES
0-
RECOMMENDED
l.lT-------
C. Summary
,g
______~.
A23
B23
C23
A69
869
C69
D69
E69
F69
G69
H69
169
J69
+-Original Range +-
x New Range
Figure 8. Area voltage ranges.
ON-PEAK SYSTEM CASE SUMMARY
% D E V I A T I O N FROM ORIGINAL
,
I
I
-8J
0
ORIGINAL
TAPS
-1
-57
NEW TAPS -
-50
227
REFER EN CES
S.A. Miske, Jr., W. Neugebauer, D.J. Ward, A Systems
Approach to the Replacement of Older Substation Capacitors,
mesented
at the 1988 American Power Conference, Chicago
r
- - - ~
Illinois, April 1
R.C. Degeneff, W. Neugebauer, C.H. Saylor, S.L. Corey,
Security-ConstrainedOptimization: An Added Dimension in
Utility Systems Optimal Power Flow, IEEE Computer
Applicationsin Power, October 1988.
R.C. Burchett, H.H. Happ, R.E. Palmer, D.R. Vierath,
Quadratically Convergent Optimal Power Flow, IEEE
Transactions
Power Amaratus and Systems, Volume 103, NO.
~.~~
11, 1984, pp. 3267-3f3.
W.C. Merritt, C.H. Saylor, R.C. Burchett, H.H. Happ,
Security Constrained Optimization - A Case Study, IEEE
Transactions on Power Systems, Volume 3, No. 3, 1988, pp.
970-977.
P.E: Gil!, W. Murray, and M.H. Wright, h W . i d
,Academic Press, 1981.
P.M. Anderson,
ted Power S y w n s , The Iowa
State University-73,
pp. 262-264.
W.D. Stevenson, Jr., Elements of Power S u e m s hdYdS,
McGraw-Hill, Inc., 1982, pp. 216-218.
~
CONCLUSIONS