Professional Documents
Culture Documents
These learning questions (Q1 through Q8) are cross-referenced in the textbook to individual
exercises and problems.
COMPLEXITY SYMBOLS
The textbook uses a coding system to identify the complexity of individual requirements in the
exercises and problems.
Questions Having a Single Correct Answer:
No Symbol
This question requires students to recall or apply knowledge as shown in the
textbook.
This question requires students to extend knowledge beyond the applications
e
shown in the textbook.
Open-ended questions are coded according to the skills described in Steps for Better Thinking
(Exhibit 1.10):
QUESTIONS
11.1
Managers need information about the costs of direct materials and direct labor as well as
whether direct materials and labor have been used efficiently. If the price and efficiency
variances are combined, it is impossible to separate the causes of the variance into
potential changes in prices of direct materials (or the labor hourly wage) and changes in
the amount of materials (or labor hours) used to manufacture the product. Managers need
specific information to better monitor operations and investigate changes.
11.2
Utilities are considered fixed costs. These include phone service, natural gas, and
electricity. The use of natural gas and electricity is affected by weather patterns. Because
weather patterns change, these costs cannot be perfectly predicted. There may be
unanticipated price changes in the cost of utilities. In addition, employees could be
careless in their use of electricity or telephones. Therefore, variances occur regularly.
11.3
GAAP requires that revenues and expenses be matched. Revenues from the sales of units
must be matched to the costs of producing those same units. When a standard cost
system is used, production costs are recorded at standard rather than at actual costs. At
the end of the accounting period adjusting entries are made to close the variance accounts
and to distribute the amounts to inventory and cost of goods sold. These entries
simultaneously close the variance accounts and adjust inventory and cost of goods sold to
reflect actual costs for the period.
11.4
For a simple but meaningful variance report for costs, the following variances should be
calculated.
Price and efficiency variances for direct materials and direct labor provide
information about price changes, purchasing efficiencies and the use of materials.
Managers can correct some of these problems to insure cost-effective production.
The variable overhead spending variance and the fixed overhead budget
variance provide information about whether costs are being kept under control.
11.5
At the end of the accounting period, the following variances need to be recorded: direct
materials and direct labor price and efficiency variances, variable overhead spending
variance, fixed overhead budget variance, variable overhead efficiency variance, and
production volume variance. If the sum of these is immaterial, it is closed to cost of
goods sold. If the sum is material, it is prorated across inventory and COGS.
11.6
Managers monitor variances that are large and unexpected. Sometimes a minimum dollar
amount is set as a criteria so that only variances greater than that amount are investigated.
Managers make trade-offs between the costs of investigating and the benefit from
improving the process or standard. Trends in variances also may affect whether a
The cost categories that are measured and monitored in a given organization depend on
several factors, including the following:
Cost accounting system used: The cost categories will be more precise with
more complex cost accounting systems. An organization with an ABC system
that separates costs into flexible and committed categories could develop
standards and measure variances for every activity performed. Alternatively, only
broad categories may be tracked, such as the traditional direct materials and direct
labor categories.
Costs that managers consider important: Overhead costs are often aggregated
together and include indirect costs such as oil for machine maintenance. While
these costs may not be individually important, they are often monitored as part of
the larger category of overhead costs.
Cost/benefit trade-off for monitoring individual costs: For those costs already
reported by the accounting system, such as direct labor in a job costing system,
the cost to develop standards and monitor variances is probably low, and the
benefit could be relatively high if such monitoring encourages labor to be more
efficient. However, other costs, indirect materials used during set-ups, may be
expensive to track. The benefit from tracking these costs may be low if only very
small amounts of materials are used per set-up. These costs are likely to be
aggregated into overhead.
11.8
Standard costs are often set using the most recent years data. Historical trends may be
analyzed and used. Sometimes industrial engineers develop standards by analyzing the
manufacturing or service delivery process.
11.9
Recurring favorable variances may indicate that some process has improved. These
should be investigated so that standard production practices reflect the process
improvements. Variances may also reflect opportunities to examine the manufacturing
process and quality of materials to determine improvements. Sometimes the standard is
wrong, and the monitoring process is improved by changing the standard to reflect
current operations.
11.10 The contribution margin variance calculates the effects of changes in contribution
margins, given the actual level of sales. The contribution margin sales volume variance
EXERCISES
11.14 Kitchen Tile Company
A. This question requires a missing piece of information: the actual number of hours
worked. However, because the labor efficiency variance is given, the variance formula
can be used to solve for actual labor hours as follows:
Labor efficiency variance = (Standard hours Actual hours)* Standard price
The variance amount is given as $6,720 Favorable, and the standard labor price is given
as $24.00 per hour. The number of standard labor hours is calculated as follows:
Actual production = 18,000 tiles
Standard efficiency is 6 tiles per labor hour
Standard number of labor hours for 18,000 tiles:
= 18,000 tiles/6 tiles per hour
= 3,000 hours
Now solve for actual labor hours using the variance formula:
$6,720 = $24.00 * (3,000 hours Actual hours)
$6,720/$24 = 3,000 Actual hours
280 = 3,000 Actual hours
Actual hours = 3,000 280 = 2,720
Quicker approach: The efficiency variance represents the amount by which actual hours
exceed standard hours, times the standard price. This means that the efficiency variance
represents 280 hours ($6,720/$24). Because the variance was favorable, 280 fewer hours
were used than the standard required. For 18,000 tiles, standard labor hours are 3,000
(18,000/6). Therefore, actual hours are 3,000 280 = 2,720 hours.
B. The direct labor price variance is calculated using the following formula:
Actual labor hours * (Standard price Actual price)
= 2,720 hours * ($24.00 - $24.50)
= $(1,360) Unfavorable
C. The fixed overhead budget (i.e., spending) variance is calculated by simply taking the
difference between standard and actual fixed costs:
Standard fixed costs Actual fixed costs
= $60,000 - $58,720
= $1,280 Favorable
$24,547.20
52,162.80
$76,710.00
$22,000
21,730
$ 270 F
$46,410
47,000
$ (590) U
3,068.4
2,730.0
338.4 hours
$17
$5,752.80 F
F. If managers use 10% of total direct costs as the criteria for investigation, none of these
variances would be investigated. However, the direct labor efficiency variance is
relatively large compared to total direct labor cost at 11% ($5,752.80/$52,162.80). Some
managers may want to investigate this variance, especially if this company is concerned
about quality as a strategy. If quality has decreased as a result of this favorable variance,
defective or low quality units could affect Nakatanis reputation and future revenues if
customers are disgruntled. If production processes have improved, and there is no
adverse change in quality, so managers might want to change the labor quantity standard.
$3,000 F
2,000 U
780 U
700 F
$20,000
$3,000
$17,000
$10,000
$2,000
$28,000
$780
$12,000
$700
$28,080
$108,500
$108,500
102,000
102,000
$5,300
$1,200
$6,500
$28,000
$25,500
$28,000
$25,500
$1,000
$1,500
$9,000
$2,500
$5,300
$1,200
$1,000
$1,500
The total variance of $9,000 would be prorated based on the ending balances in
work-in-process inventory, finished goods inventory, and cost of goods sold.
$60,000
16,000
8,000
$36,000
Because contribution margin represents 4,000 units, the contribution margin per unit must
be $36,000/4,000 = $9. Then, the contribution margin sales volume variance is
$9 x (4,000 - 3,800) = $1,800 U
11.19 Metropolitan Motors
A. The contribution margin budget variance is the difference between the standard
contribution margin and the actual contribution margin.
First, calculate the contribution margin at budget:
Economy
Family
Luxury
(10*$400)
(20*$800)
(5*$1,300)
$ 4,000
16,000
6,500
$26,500
25
10
3
38
$ 5,625
7,500
4,200
$17,325
25 x $400
10 x $800
3 x $1,300
38
$10,000
8,000
3,900
$21,900
The average contribution margin at actual sales mix, standard contribution margin
is $21,900/38 = $576.32
Then take the difference between this and the actual contribution margin.
Contribution margin variance = $21,900 - $17,325 = $4,575 U
The contribution margin sales volume variance is the difference between the standard
volume, mix, and contribution margin and the actual mix and volume at standard
contribution margin or
$21,900 - $26,500 = $4,600 U
Check: The two variances should equal the contribution margin budget variance.
$9,175U = $4,575 U + $4,600 U
C. The contribution margin sales quantity variance is the difference in actual quantity sold
and the standard quantity, given the standard sales mix and standard contribution margin.
The average contribution margin at standard sales mix and standard contribution margin
was calculated above in part A.
(35 - 38) * $757.14 = $2,271.42 F
The contribution margin sales mix variance is the difference between the standard sales
mix and the actual sales mix given actual sales at standard contribution margin. This can
be calculated two different ways. The actual units and actual sales mix at standard
contribution margin total is $21,900. The actual units at standard sales mix and standard
contribution margin is $757.14 * 38 = $28,771.32. So the total variance = $21,900 $28,771 = $6,871.32 U. Alternatively, the averages from above can be used as follows
Contribution margin sales mix variance = ($757.14 - $576.32)*38 = $6,871.16 U
These two variances should sum to the contribution margin sales volume variance of
$4,600, and they do ($6,871 - $2,271 = $4,600).
2.
Cost savings per month = (1,000 lots * $5.00 per lot) = $5,000
Cost savings over 5 years = ($5,000 per month * 60 months) = $300,000
The maximum price the company would be willing to pay for the new equipment is
$300,000. This is equal to the expected labor cost savings over 5 years (ignoring the
time value of money).
11.21 Fine Products Manufacturing Company
A. Total variances = $7,900 unfavorable. Because anything greater than $5,000 is
considered material, the total variance amount is material.
B. Total WIP, FG, and COGS = $32,000.
Each inventory and COGS account gets a portion of the variance:
Work in Process ($2,000/$32,000 x $7,900)
Finished goods ($6,000/$32,000 x $7,900)
Cost of goods sold ($24,000/$32,000 x $7,900)
Total
$ 494
1,481
5,925
$7,900
494
1,481
5,925
1,500
1,000
2,000
5,000
2,000
200
1,200
Standard
Contribution Margin
95,000 x $1.25
$118,750
40,000 x $2.00
80,000
$198,750
PROBLEMS
11.23 Raging Sage Coffee
A. For a coffee cart business, workers are scheduled with more help available when the shop
is busy, such as in the morning. Although each workers hours vary, the schedule remains
fairly fixed, so the cost structure includes a high proportion of fixed cost.
B. In this business, workers need to be at the cart regardless of the number of customers.
Therefore, the direct labor efficiency variance is meaningless and should not be
calculated because it would be measuring whether the clerks sold as many cups of coffee
per labor hour as was expected. Labor costs are fixed, so the computation would reflect a
revenue variance, rather than a labor efficiency variance.
C. Price variance for coffee beans:
Standard cost of actual coffee beans purchased (240 lbs. x $6.00 per lb)
$1,440
Actual cost of coffee beans purchased
1,800
Price variance
$ (360) U
Efficiency variance for coffee beans:
Coffee beans at standard lbs. (0.04 lbs per cup x 8,260 cups)
Actual beans
Variance in pounds
Standard cost per pound
Efficiency variance
330.4 lbs
224.0 lbs.
106.4 lbs.
$6.00
$638.40 F
D. The quantity standard for direct labor implies that 20 cups should be sold per hour of
clerk/brewer time:
0.05 hours per cup x 60 minutes per hour = 3 minutes per cup
In 60 minutes, 20 cups are expected to be made and sold
Expected sales volume (600 clerk/brewer hours x 20 cups per hour)
Actual sales volume
Difference between expected volume and actual volume
12,000 cups
8,260 cups
(3,740) cups
E. There is an unfavorable coffee bean price variance, a favorable coffee bean efficiency
variance, and sales were off by about 32% (3,740 cups/12,000 cups). These variances
might be related. One possibility is that the higher cost of coffee beans caused the
clerks/brewers to reduce the quantity of coffee beans used per cup. This would have
resulted in weaker coffee, which might have caused customers to go elsewhere.
The following are other possible explanations for the unfavorable sales volume variance:
* A competing coffee business opened nearby.
* A nearby employer went out of business or launched a major lay-off of
employees.
F. Instead of basing a bonus based on cost variance measures, give employees a bonus
based on profitability. This provides them motivation to encourage customers to return,
increasing revenue, and also to contain costs.
11.24 Sunglass Guys
A. Standard overhead rate per direct labor hour:
Calculate total estimated overhead at normal production volume:
Estimated overhead = (4,300 x $8.15) + (1,400 x $12.32) + $235,707 = $288,000
Calculate estimated labor hours at normal production volume:
Estimated hours = 0.2 x 4,300 + 0.3 x 1,400 = 1,280 hours
Calculate standard rate by dividing estimated cost by estimated hours:
Rate = $288,000/1,280 = $225 per direct labor hour
B. This method would be useless for monitoring and control because the fixed and variable
overhead costs are not separated. When the production volume variance is commingled
with the fixed overhead budget variance and variable overhead spending variances,
spending variances cannot be calculated, so no information is available about cost
control.
C. The recommendation is to separate fixed and variable overhead costs into separate
standards. Only the spending variances will be useful for monitoring and controlling
overhead costs.
Using normal monthly volume, the fixed overhead budget variance is:
Estimated fixed overhead cost (i.e., static budget)Actual fixed overhead cost
= $235,707 - $237,859 = $2,152 U
The variable overhead spending variance (using units of production as the allocation
base):
Standard variable overhead for actual productionActual variable overhead cost
= ($8.15 * 4,500 Regular units) + ($12.32 * 1,300 Deluxe units) - $54,238
= $36,675 + $16,016 - $54,238
= $1,547 U
1,290 hours
1,280 hours
10 hours
$184.14
$1,841 F
$ 165,735
71,819
237,554
237,859
$
(305) U
$ 30 F
315 U
$285 U
D. If there were no waste, the company would incur costs for only one DVD and one
documentation book per game produced. Thus, the cost of waste is equal to the number
of DVDs and documentation books used in excess of one per unit, valued at standard
cost:
Waste for DVDs:
[Actual DVDs used (1,000 + 800)] x $0.35
= (2,025 1,800) x $0.35
$ 78.75
Waste for documentation books:
(Actual Power Puffs books used 1,000) x $3
+ (Actual MMM books used 800) x $5
= [(1,005 1,000) x $3] + [(825 800) x $5]
140.00
Total waste
$218.75
E. Pros:
Cons:
It may be less costly to allow waste in the standard than to inspect incoming
materials or to pay for higher quality materials.
The company has done it this way a long time, and change might be difficult
for employees.
Several waste-related opportunity costs arise from defective units. As waste
increases, it is likely that the number of defective units sold increases. Greater
defect rates reduce customer satisfaction and reduce sales. By eliminating waste
altogether, this cost is avoided.
The company would have saved $218.75, although no information is given
about the amount of investment required to save this amount.
20,000 cc
(.005) per cc
$(100) U
$(270) U
(100) U
$(170) U
B. The unfavorable efficiency variance represents the cost of wasted serum. To see this,
consider the formula for the efficiency variance:
Efficiency Variance = Standard cost * (Standard quantity Actual quantity)
The difference between the standard quantity and the actual quantity is the amount of
serum wasted. At a standard cost of $.10 per cc, the volume of wasted serum is estimated
to be 1,700 cc ($170 unfavorable efficiency variance/$.10 per cc).
Is this a significant amount of waste? This is a matter of judgment. Below are several
ways to quantity the significance.
Waste, relative to standard quantity of serum:
Standard quantity of serum = 2,000 injections * 10 cc
Percent serum waste (1,700 cc/20,000 cc)
20,000
8.5%
Note: The waste could also have been calculated using percent of standard cost:
$170 efficiency variance/$2,000 standard cost = 8.5%
Number of additional injections that could have been given:
Waste of 1,700 cc / 10 cc per injection
170 injections
The percent waste (8.5%) might or might not be considered a significant cost.
Given the nature of operations at the Baker Street Animal Clinic, it would be
reasonable for waste to be very close to zero.
Had there been zero waste, 8.5% or 170 more injections could have been given.
Perhaps the waste is a sign that the technicians are wasteful in other areas, too.
There could be a significant larger problem.
C. The manager would probably be concerned about the unfavorable efficiency variance.
The manager could ask the technicians to review their procedures and to identify how and
where waste is occurring. Once the reasons for waste are identified, the manager could
help the technicians establish new procedures to minimize or eliminate the waste.
If the technicians are unable to provide reasonable explanations for the waste, the
manager might become concerned that someone is stealing serum and then selling or
using it elsewhere. If the manager considered the cost to be sufficiently large, he/she
might institute new procedures for monitoring the physical use of serum. However, this
type of approach might cost more than the benefit.
Perhaps the easiest and most cost-effective solution would be to provide the technicians
with incentives based on the efficiency variance. The efficiency variance could be used
as part of the technicians performance evaluation. This would encourage them to seek
efficiency improvements on their own.
11.27 Damson Products
[Note: This problem requires students to know about normal versus abnormal waste (see
Chapters 5 and 6).]
A. Most of the variances are immaterial and can be closed to cost of goods sold. However,
three of them need attention. The $13,000 for materials lost should be accounted for as a
flood loss; similarly, the $9,000 in labor should be accounted for as flood loss. This
leaves $12,600 - $13,000 = $400 F and $9,700 - $9,000 = $700 U, respectively, in the
material efficiency and labor efficiency variances to be closed to cost of goods sold.
Note, that variable overhead must not have been allocated on the basis of labor;
otherwise, there would be a large unfavorable variable overhead quantity variance.
The production volume variance should also be split into two amounts. The $10,200 due
to down time during the flood should be part of the flood loss. The remaining $200
should be debited to cost of good sold.
B.
$ 658
Flood Loss
Cost of Goods Sold
Material Efficiency Variance
$13,000
$ 400
12,600
$ 376
Flood Loss
Cost of Goods Sold
Labor Efficiency Variance
$ 9,000
700
$ 376
$ 9,700
$ 507
$ 507
$ 412
$ 782
$ 412
$ 782
200
10,200
$10,400
Estimated Cost
$2,000,000
1,000,000
500,000
90,000
Estimated Activity
5,000,000
250,000
100,000
3,000
ABC Rate
$0.40
$4.00
$5.00
$30.00
Static
Budget
$2,000,000
1,000,000
500,000
90,000
$3,590,000
Actual
Activity
5,800,000
270,000
110,000
3,500
Flexible
Budget
$2,320,000
1,080,000
550,000
105,000
$4,055,000
Actual
Cost
$2,200,000
1,300,000
400,000
100,000
$4,000,000
Variance
$120,000 F
-220,000 U
150,000 F
5,000 F
$ 55,000 F
$300,000 U
$1,160,000
900,000
260,000 F
$ 40,000 U
E. Fixed costs might have increased if new equipment or software was purchased that has
not been reflected in the standard. Costs could be out of control. Variable costs might
have been reduced if new equipment resulted in more efficient operations. The processes
might have been improved somehow. The variance could also reflect normal fluctuations
of processing activities.
F. There is no one answer to this part. Sample solutions and a discussion of typical student
responses will be included in assessment guidance on the Instructors web site for the
textbook (available at www.wiley.com/college/eldenburg).
$640,000
110,000
200,000
950,000
(104,000)
(535,000)
$311,000
= $16.269231
= $18.00
$311,000.00
(32,538.46)
86,538.46
365,000.00
56,000.00
(22,000.00)
(5,075.00)
(1,500.00)
1,500.00
$393,925.00
B.
1. The sales manager should be held responsible for only those variances related to
activities under his or her control. Therefore, the production-related variances
(material price and material quantity) should be excluded. The fixed cost budget
variance should be considered only to the extent that the fixed costs are under the
sales managers control. The sales manager is mostly likely responsible for some
fixed costs, so a budget variance for those costs should be separated from the budget
variance for other costs. The group of sales-related variances, considered together,
provides information to evaluate whether the sales managers changes to prices and
sales effort are benefiting the company. Although individual variances such as sales
quantity and sales price may be negative, the important question is whether the sales
managers new strategies are increasing the companys profits.
2. The manager should be praised. The net effect of the manager's changes can be seen
in the sales mix, quantity, and price variances. These variances total to an $88,000
favorable variance ($32,538.46 U + $86,538.46 F + $56,000.00 F + $22,000.00 U).
C. Sales
Games
(55,000*35,000/50,000) @ $17.60
Business
(55,000*4,000/50,000) @ $49.50
Educational
(55,000*11,000/50,000) @ $20.00
Total sales
Variable costs
55,000 @ $1.80
Fixed costs
Pretax income
$ 677,600
217,800
242,000
1,137,400
99,000
535,000
$ 503,400
D. The managers cannot know for certain whether there will be changes in customer
preferences that affect the demand estimates. They also cannot know for certain when
prices of inputs will increase. Although they can build known price changes into the
budget, even vendors may not anticipate their own price increases up to a year in the
future. The managers cannot know their costs for services such as electricity and
transportation because these prices are affected by weather and gas and oil costs. There
are many uncertainties that cannot be perfectly predicted; these are just a few examples.
11.30 Professor Grader
A. It is not possible to develop a perfect system for measuring student performance in a
course. To know for certain the amount of effort put forth, and the understanding that
each student acquires, a professor would have to monitor all of their actions related to the
course, no matter where the student was. This is impossible. Even if it were possible to
perfectly observe all student actions, uncertainty would still exist about how best to
measure individual course performance. Should students be graded based on the
improvement in their knowledge and other competencies during the course? Should they
be graded based on an absolute standard for the course? Should grades be measured
relative to other students in the same section or several sections taught by the professor?
B. There is probably wider variation in exam results than any of the other measures, but
because some students have access to the exam, variation is reduced. There is probably
very little variation in attendance because it is rarely monitored. There is probably little
variation in the term paper because it is graded on quantity, not quality, and the quantity
standards are known by all students. There is probably little variation on the take-home
exam because students have two weeks to work on it, and judging from other aspects of
this professors performance evaluation systems, it is likely that all of the questions have
single correct answers because they are easy to grade.
The performance measurement for the term paper does not seem to be
consistent with the goals of the course. Measuring length instead of content
would normally not measure whether students understood the subject matter of
the course.
The performance measure is unfair to the extent that some students have
access to the midterm exam and others do not.
The defects in the performance measure are so severe that one should not attempt to use
grades earned in this course as a measure of students' comprehension of the subject
matter.
D. Professor Grader has a responsibility to students and to others who directly finance
students (such as parents and spouses) to grade in a manner that is consistent with
university and program policies and also with the grading system set forth in the course
syllabus. The professor is also responsible for establishing a grading system that is fair to
students in the course and that measures student learning (although how to do this is
uncertain, as described in Part A). This group of stakeholders often considers grades as
signals about student effort and/or ability. If the grades do not measure student effort or
ability, even with error, these stakeholders do not have adequate information about the
students progress.
Professor Grader has responsibilities toward the recruiters who hire the universitys
graduates. Recruiters want to identify students who work hard and learn new things
quickly. Grades measure these skills and abilities, although with error. Without
appropriate measurement, recruiters cannot identify students that might best suit their
needs, and they may no longer use the university for recruiting.
Professor Grader is responsible to the university, which expects professors to ensure that
graduating students have met outcomes specified by the university, such as the ability to
think critically, communicate effectively, be an effective team member, and are
knowledgeable within their respective majors. Universities rely on professors and their
evaluation systems to maintain standards.
It concentrates on the wrong goals--quantity and cost. The firm has achieved
its success through quality.
The performance standard for cost is incorrect. The firm is producing a higher
quality product than other firms in the industry. Consequently, the firm should
expect higher costs than other firms.
Workers are likely to resent the new system and could then leave the
company, requiring increased costs in training and reduced productivity.
E. There is no single answer to this question. However, the answer should contain a
synthesis of the issues discussed in the preceding sections, and it should also address
concerns about responding in a productive way to the new accountant. The following
major areas should be addressed:
A summary of what the proposed system would measure (Part B) and the
weaknesses in the proposal (Part D), followed by a conclusion about whether the
CFO would support the proposal. Most likely, the CFO would not be in favor of
the proposal because it focuses on inappropriate measures.
Identify ways to respond to the new accountant. The response should be positive
so that it encourages the accountant to continue to think creatively and to share
new ideas. The response is also a learning opportunity for the new accountant.
The CFO could discuss the proposal with the cost accountant and ensure that the
accountant understands the proposals flaws. They could then discuss ways to
improve upon the ideas in the proposal.
The problem does not give the total standard amount of fixed direct labor cost or fixed
factory overhead, but they can be calculated from the standard cost information:
Fixed direct labor (1,000 pistons x $6 per piston)
Fixed factory overhead (1,000 pistons x $20 per piston)
$ 6,000
20,000
B. The direct costs consist of: piston shafts, shaft housings, and direct labor. Because the
information in the problem indicates that actual costs were identical to standard costs for
shaft housings, there are no variances for shaft housings. Therefore, direct cost variances
are calculated only for piston shafts and direct labor. Also note that direct labor in this
problem is treated as a fixed cost. Accordingly, budget and volume variances are
calculated for direct labor using the same method that is used for fixed factory overhead.
(90) U
$ 5,700
(6,120)
$ (420) U
$ (420) U
$ 3,800
(3,677)
$ 123 F
123 F
$ 19,000
(18,325)
$
675 F
675 F
D. Below is an excerpt from a sample spreadsheet showing the total selling and
administrative variance for this problem.
The second step is to compare the total net amount of production cost variances ($288 F)
with total actual production costs ($80,462). In this case, the variances amount to only
50
293
1,675
140
120
300
170
1,000
288
G. As manager of the piston division, I would like to know if the quality of the pistons was
the same as usual. Four more pistons were used than expected, so it is possible that
quality has been compromised with a lower price. This could be a problem if defective
shafts are not removed from production and customers receive more defective pistons
than usual. Sales volumes could drop. I would also like to know why labor costs and
hours were up. If workers had to work overtime because of a quality problem, cost and
hours would be up. It appears that fixed and variable overhead costs were under control,
and were even less than expected during the period. Because the fixed overhead budget
variance is fairly large, I would want to know if something has changed and whether the
use of overhead has improved. If so, the standard could be changed, although the efforts
of workers to reduce fixed costs needs to be recognized and praised.
11.33 Bramlett Company
A. The problem states that management wants to maintain the selling price for several years,
so the assumption is made that long-run standard costs will be used for pricing, rather
than the expected costs during start up.
Standard cost per unit
Direct materials
Direct labor
Variable overhead
Fixed overhead (a)
Total
Markup
Selling price
4 pieces @ $20
10 hours @ $25
50% x $250
42.666% x $250
60% x $562
$ 80
250
125
107
562
337
$899
(a) After start up, the firm will produce 1,500 units per month, or 18,000 per year.
The budgeted labor costs for 18,000 units is 18,000 x $250 = $4,500,000.
Using the same basis to allocate fixed overhead as is used to allocate variable
overhead yields a fixed overhead rate of $1,920,000/$4,500,000 = 42.666% of
labor cost.
B. The variances for product costing purposes using the long-term standards would be
Labor price variance
(Standard price actual price) x actual hours
= ($25 - $26) x 12,000 = $12,000 U
Labor efficiency variance
(Standard quantity for actual output actual quantity) x standard price
=[(10 x 950) - 12,000] x $25 = $62,500 U
For product costing purposes, the overhead variances would be as follows (note that
overhead is based on labor cost, not hours):
Variable overhead spending variance
= Actual allocation base (labor cost) at standard rate actual variable
overhead
= [(50% x $312,000) - $160,250 = $ 4,250 U
Fixed overhead budget variance
Static budget for fixed costs (budgeted fixed overhead per month) actual
fixed overhead
= [($1,920,000/12 - $172,220] = $160,000 - $172,220 = $ 12,220 U
Variable overhead efficiency variance
= Standard allocation base at standard rate actual allocation base at
standard rate
= (Standard labor cost actual labor cost) x standard variable rate
= [($25 x 10 hours x 950 units) - $312,000] x 50% = $37,250 U
Production volume variance
= Standard allocation base at standard rate (allocated cost) estimated
allocation base at standard rate (static budget)
= (Standard labor cost for actual output standard labor cost for estimated
output) x standard rate
= [($25 x 10 hours) x (950 units - 1,500)] x 0.42666
= ($237,500 - $375,000) x 0.42666 = $58,666 U
C. Here are some pros and cons for using the long-term standard for the first months
operations.
Pros:
The accounting department performs the calculations they will use for the next
year, and personnel will gain experience with the new system
The variances will reflect the results of the long-term standard and give workers a
more accurate picture of the gaps in their performance
Using the long-term standard may highlight areas with very large variances that
are likely to have larger variances over the next few months
Cons:
Workers may be discouraged when their performance is compared to such high
standards
The standard will not be viewed as realistic, and so may be ignored causing
poorer performance in the first few months than otherwise
Information about variances from these standards is of poor quality and cannot be
used reliably for planning or monitoring
D. The short term standards do not affect the labor price variance. It remains the same as
above:
Labor price variance
=(Standard price actual price) x actual hours
= ($25 - $26) x 12,000 = $12,000 U
However, a substantial portion of the labor efficiency variance was anticipated. That is,
management expected it to take 10 x 1.2 = 12 hours per unit during the first month of
operations. The following variance better reflects performance.
Labor efficiency variance = [(12 x 950) - 12,000] x $25 = $15,000 U
The overhead spending and budget variances are probably unaffected by the learning
curve experienced by labor. Therefore, they are the same as in part B, as follows.
Variable spending variance
= Actual allocation base (labor cost) at standard rate actual variable
overhead
= [(0.5 x $312,000) - $160,250 = $ 4,250 U
Fixed overhead budget variance
= Static budget fixed costs (budgeted fixed overhead per month) actual
fixed overhead
= [($1,920,000/12 - $172,220] = $160,000 - $172,220 = $ 12,220 U
The following variances are used as adjusting entries in the accounting records. It may
be more appropriate for these variances to reflect the expected short-term performance as
well. Therefore they could be calculated as follows.
Variable overhead efficiency variance
= [($25 x 12 x 950) - $312,000] x 0.5 = $13,500 U
Production volume variance
= [($25 x 12 x 950) - ($25 x 12 x 1,000)] x 0.5333
= ($285,000 - $300,000) x 0.5333 = 8,000 U
Fixed overhead budget: An accounting clerk might have accidentally coded a fixed
overhead cost as a variable overhead cost. This error would cause fixed overhead costs to
be overstated and variable overhead costs to be understated.
Production volume: An error in the computation of units produced would cause an error
in this variance. Suppose personnel forget to record the number of units spoiled during a
particular production run. This error would cause the number of good units produced to
be too high, overstating the production volume.
B. The theft of inventory is accounted for with any other errors in inventory quantities at the
time physical inventory is counted. Because it is not possible to distinguish between theft
and errors, the adjustment for missing raw materials inventory is usually recorded as
either direct materials or indirect materials (most likely in variable overhead). If the
adjustment is recorded to direct materials, then the theft would be reflected in the direct
materials efficiency variance (the usage of raw materials would appear to be higher). If
the adjustment is recorded to indirect materials, then the theft would overstate variable
overhead costs, which would be reflected in the variable overhead spending variance.
C. There are several reasons for failing to uncover theft through analysis of the affected
variances. Variances include offsetting positive and negative items, and the theft might
be offset by positive variances such as more efficient use of materials. In addition, cost
standards are often set based on past experience. If the company has always experienced
significant theft, then the cost would already be anticipated in the cost standards.
D. Assuming that the fictitious employee time is charged to direct labor, this fraud would be
reflected in the direct labor efficiency variance. If the pay rate for the fictitious employee
is not equal to the standard direct labor pay rate, then the fraud would also be reflected in
the direct labor price variance. If time for the fictitious employee is charged to an
overhead account, then this fraud would be reflected in the variable overhead spending
variance or fixed overhead budget variance.
E. This error will cause variable overhead costs to be overstated this year by the difference
between the total cost and the amount that should have been depreciated this year.
Variable overhead costs will be understated in future years by the amount of depreciation
that should have been recorded. This error would be reflected in the variable overhead
spending variance. During the current year the variance would be less favorable (or more
unfavorable), and in future years it would be more favorable (or less unfavorable).
F. The most obvious way to increase earnings by misapplying accounting principles for
variances is to close material variance accounts incorrectly. For example, favorable
variances could be closed to cost of goods sold instead of prorated to cost of goods sold
and work in process.