You are on page 1of 350

Technical Consideration and Impact of

Converting Overhead Power Lines to


Underground Power Cables
A Thesis
Submitted to the Faculty of
Health, Engineering and Science
By

Hassan Al-Khalidi
for

Doctor of Philosophy
Principal Supervisor

Professor Akhtar Kalam

Abstract

ABSTRACT
In the modern era, overhead transmission lines become irrelevant in the
development of new cities as underground cables become mandatory.
Nonetheless, it is crucial to understand overhead line technology in order to
model the next generation of power networks, as most of the power networks
still comprise overhead lines.

This field of study was exposed to methodical and thorough research; there is a
common perspective which is shared amongst multinational power engineers
and researchers, that underground transmission cabling bestows mammoth
improvements & benefits when compared to its predecessor technology of
overhead lines. However, the overhead technology is still dominating and is in
use all over the world.

A comprehensive overview of the overhead power network along with its


structure was dedicatedly elaborated on. For decades, power has been
transmitted via a relatively low cost medium, commonly known as overhead
lines. Since then, substantial transformations have been occurring to improve
the reliability of overhead networks. A load flow technique is often employed to
analyse and design an improved overhead power network. An overview of
overhead power networks has also been extensively further explored in this
research. Various conductors used in overhead lines have also been discussed.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

Abstract

As power loss is a major concern for transmission systems, an elaborative


study on power losses in overhead lines has also been included.

This research investigates the technical trends of moving overhead lines to


underground cables. It will discuss local & overseas experience and practices in
this area, hence develop a proposal solution in accordance with the local
conditions and regulation. New ideas are contributing in the development of
underground system significantly, which enhance reliability, efficiency and
lowering the cost of installation and maintenance. These ideas cover various
phases of an underground system.

The objective of this research is to investigate the effect of new technology and
practices on moving overhead lines to underground cables to improve
occupational health and safety of personal, worker wellbeing (e.g. reduce risks
of fatal accidents caused by cars hitting power poles) and reliability of electricity
supply, as well as improve in the landscape.

Load flow analysis and other industrial based specialised software applications
were utilised to investigate and develop various sub-transmission network
models. The results obtained from the load flow analysis provided crucial
information about the network.

The Victorian overhead power network has been examined in an attempt to


efficiently design an underground network for Victoria. It has become mandatory

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

II

Abstract

for most modern cities worldwide to use underground power cables. This
demonstrates

that

undergrounding

has

become

economically

and

technologically feasible. Various advantages have been presented about


underground cables in this chapter. However, there are significant challenges in
the underground network as much as it has benefits. It is essential to carefully
design and implement an underground power network.

This research contributed directly to the body of knowledge of power


transmission and distribution systems. More specifically, it contributes to the
overhead

transmission

lines undergrounding framework.

The

research

produced reference guidelines for Victorian underground sub-transmission and


distribution networks. The research made a unique technical contribution to the
processes and procedures of undergrounding overhead power lines in Victoria
as well as laid emphasis on portability aspects for potential adoption by other
Australian states.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

III

Declaration

Declaration
I, Hassan Al-Khalidi, declare that the PhD thesis entitled Technical
Consideration and Impact of Converting Overhead Power Lines to
Underground Power Cables is no more than 100,000 words in length
including quotes and exclusive of tables, figures, appendices, bibliography,
references and footnotes. This thesis contains no material that has been
submitted previously, in whole or in part, for the award of any other academic
degree or diploma. Except where otherwise indicated, this thesis is my own
work.

Signature

Date 14 / 08 / 2009

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

IV

Acknowledgements

ACKNOWLEDGEMENTS
The author wishes to express his heartfelt gratitude and sincere thanks to his
principal supervisor, Dr Akhtar Kalam, Professor of Electrical Engineering,
Victoria University, Australia, for his kind guidance, invaluable support, constant
encouragement and supervision throughout the course of this research.

The author is profoundly grateful to Energy Safe Victoria for providing all the
sponsorship and the support required by this research; in particular he would
like to thank Alan Kelly, General Manager - Corporate Services, Mike Ebdon Executive Manager Infrastructure Safety and special thanks to Bill Greenland,
former General Manager Supply Safety, Office of the Chief Electrical
Inspector. Furthermore, the author would also like to thank Neil Watt - Manager
Asset Strategy & Performance, Electricity Networks and John Papamichael Network Control Manager, CitiPower Pty & Powercor Australia Ltd. for providing
the necessary assistance and facilities in order to successfully complete this
research. A Conclusive appreciation by the author to George Zarev- Manager
T&D and Doug McKinnon from Hatch energy for their kind support. Special
thanks will be extended by the author to Bob Coulter Manager, Engineering &
Strategic Development, Adapt Australia.

The author also wishes to express his sincere gratitude to Dag Willn
Assistant Director, Ultera - A Southwire / nkt cables Joint Venture, for his
constant support throughout the project.
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

Acknowledgements

It is a distinct pleasure for the author to acknowledge his heartfelt gratitude to


his wife Hediye Hassan for her moral support, inspiration, patience and
perseverance with him especially in time of frustration. The author is also
grateful to the understanding of his son Mohamed and daughter Marwa for the
time they had to miss their father. The author extends his thanks to his brother
Hussein, his sister Ikbal and his brother-in-law Tarik Al taee and other family
members for their support and encouragement.

Finally, the author wishes to express his thanks to Abdulrahman Hadbah, Dr.
Amanullah M Than Oo, Associate Professor Aladin Zayegh and all staff
members in the School of Engineering and Science for their help and
assistance.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

VI

List of Abbreviations

List of Abbreviations
3D

three-Dimensional

AAAC

All Aluminium Alloy Conductor

AACSR

All Aluminium Alloy Conductor Steel Reinforced

ac

Alternating Current

ACAR

Aluminium Conductor Alloy Reinforced

ACSR

Aluminium-Conductor Steel-Reinforced

CBDs

Central Business Districts

CIE

Centre for International Economics

CMOS

Customer Minutes Off-Supply

dc

Direct Current

DNSP

Distribution Network Service Providers

DTS

Distributed Temperature Sensor

EDSA

Electrical power system Design Simulation and power Analytics

EHV

Extra High Voltage

EMF

Electric and Magnetic Fields

FODT

Fibre Optic Distributed Temperature

FPSC

Florida Public Service Commission

GDP

Gross Domestic Product

GIL

Gas Insulated Lines

GPIR

Ground-Penetrating Image Radar

HTS

High Temperature Superconductive

HV

High Voltage

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

VII

List of Abbreviations

IPART

Independent Pricing and Regulatory Tribunal

IPRT NSW

Independent Pricing and Regulatory Tribunal of New South


Wales

JLARC

Joint Legislative Audit and Review Commission

LV

Low Voltage

MV

Medium Voltage

NGOs

Non-Government Organisations

NSW

New South Wales

ORNL

Oak Ridge National Lab

PSEG

Public Service Electric and Gas Company

PSS/E

Power System Simulator for Engineering

ROI

Return On Investment

SAIDI

System Average Interruption Duration Index

SAIDI

System Average Interruption Duration Index

SCC

State Corporation Commission

UAE

United Arab Emirates

WMTS

West Melbourne Terminal Station

XLPE

cross Linked Polyethylene

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

VIII

Table of Contents

TABLE OF CONTENTS
ABSTRACT......................................................................................................... I
Declaration ....................................................................................................... IV
ACKNOWLEDGEMENTS .................................................................................. V
List of Abbreviations ...................................................................................... VII
TABLE OF CONTENTS .................................................................................... IX
List of Figures................................................................................................ XIII
List of Tables ................................................................................................XVII
List of Publications ........................................................................................XX
CHAPTER 1 ....................................................................................................... 1
THESIS OVERVIEW .......................................................................................... 1
1.0 Introduction .................................................................................................. 1
1.1 Motivation..................................................................................................... 4
1.2 Research methodologies and techniques .................................................... 6
1.3 Originality of the Thesis.............................................................................. 11
1.4 Objectives .................................................................................................. 12
1.5 Organisation of the Thesis ......................................................................... 13
CHAPTER 2 ..................................................................................................... 15
LITERATURE REVIEW.................................................................................... 15
2.0 Introduction ................................................................................................ 15
2.1 Issues with Power Networks ...................................................................... 17
2.2 Conclusion ................................................................................................. 47
CHAPTER 3 ..................................................................................................... 48
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

IX

Table of Contents

OVERHEAD POWER NETWORKS ................................................................. 48


3.0 Introduction ................................................................................................ 48
3.1 Overhead Power Network Overview .......................................................... 49
3.2 Reliability Issues in Power Network ........................................................... 51
3.3 Types of Overhead Power Line Conductors .............................................. 53
3.4 Load Flow Analysis .................................................................................... 55
3.5 Conclusion ................................................................................................. 57
CHAPTER 4 ..................................................................................................... 58
DEVELOPMENT AND ANALYSIS OF VICTORIAN OVERHEAD POWER
NETWORK MODEL ......................................................................................... 58
4.0 Introduction ................................................................................................ 58
4.1 Power Loss in Overhead Lines .................................................................. 59
4.2 General Overview of Victorian Overhead Power Network.......................... 60
4.3 WMTS 2007 Overhead Base Model .......................................................... 65
4.4 WMTS 2011 Overhead Forecast Model ..................................................... 79
4.5 Citipower 2007 Overhead Overall Power Losses ....................................... 94
4.6 Citipower 2011 Forecast Overhead Overall Power Losses ...................... 100
4.7 Conclusion ............................................................................................... 108
CHAPTER 5 ................................................................................................... 110
UNDERGROUND POWER NETWORKS ...................................................... 110
5.0 Introduction .............................................................................................. 110
5.1 General Overview .................................................................................... 111
5.2 Voltage Regulation ................................................................................... 113
5.3 Overhead vs. Underground ...................................................................... 113

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

Table of Contents

5.4 Reliability Issues ...................................................................................... 117


5.5 Power Network Fundamentals ................................................................. 120
5.6 Underground Construction ....................................................................... 130
5.7 Conclusion ............................................................................................... 133
CHAPTER 6 ................................................................................................... 135
DEVELOPMENT AND ANALYSIS OF VICTORIAN UNDERGROUND POWER
NETWORK MODEL ....................................................................................... 135
6.0 Introduction .............................................................................................. 135
6.1 WMTS 2007 Underground Model ............................................................ 136
6.2 WMTS Underground 2011 Forecast Model.............................................. 154
6.3 Citipower 2007 Underground Overall Power Losses ............................... 165
6.4 Citipower 2011 Forecast Underground Overall Power Losses................. 172
6.5 Conclusion ............................................................................................... 181
CHAPTER 7 ................................................................................................... 183
DEVELOPMENT AND ANALYSIS OF VICTORIAN HYBRID POWER
NETWORK MODEL ....................................................................................... 183
7.0 Introduction .............................................................................................. 183
7.1 General Overview of HTS Cable Technology .......................................... 185
7.2 Feasibility Studies .................................................................................... 197
7.3 The 66kV - 300 MVA HTS Triaxial Cable for Melbourne .......................... 206
7.4 Hybrid Power Network Sub-Model ........................................................... 208
7.5 HTS Cable and Fault Current................................................................... 219
7.6 HTS Cable and Short Circuit Analysis Sub-Model ................................... 222
7.7 Conclusion ............................................................................................... 225

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

XI

Table of Contents

CHAPTER 8 ................................................................................................... 226


CONCLUSION AND RECOMMENDATIONS ................................................ 226
8.0 Introduction .............................................................................................. 226
8.1 Appraise ................................................................................................... 226
8.2 Recommendations ................................................................................... 232
REFERENCES ............................................................................................... 236
Appendix A ................................................................................................... 244
Appendix B ................................................................................................... 250
Appendix C ................................................................................................... 279
Appendix D ................................................................................................... 284
Appendix E.................................................................................................... 286
Appendix F .................................................................................................... 294
Appendix G ................................................................................................... 297
Appendix H ................................................................................................... 299
Appendix I ..................................................................................................... 309
Appendix J .................................................................................................... 319

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

XII

List of Figures

List of Figures
FIGURE 1.1: POWER NETWORK WITH OVERHEAD TRANSMISSION AND DISTRIBUTION
SYSTEMS....................................................................................................... 2

FIGURE 1.2: CITIPOWER ZONE SUBSTATION 2007 AND FORECAST 2011 LOADINGS ..... 9
FIGURE 2.1: THE DEVASTATING EFFECTS OF WILD WEATHER HURRICANE KATRINA
2005 .......................................................................................................... 43
FIGURE 3.1: AVERAGE CMOS OVER THREE YEARS ............................................... 53
FIGURE 4.1: CITIPOWER ZONE SUBSTATION AND SUB-TRANSMISSION SYSTEM ....... 64
FIGURE 4.2: WMTS 66KV OVERHEAD BASE SUB-MODEL ........................................ 66
FIGURE 4.3: WMTS 66KV OVERHEAD LINES POWER LOSSES ................................. 70
FIGURE 4.4: WMTS 66KV POWER LOSSES COMPARISON OF BOTH EDSA AND PSS/E
.................................................................................................................. 72
FIGURE 4.5: WMTS 22KV OVERHEAD SUB-MODEL ................................................ 74
FIGURE 4.6: WMTS 22KV OVERHEAD LINES POWER LOSSES ................................. 77
FIGURE 4.7: WMTS 22KV POWER LOSSES COMPARISON OF BOTH EDSA AND PSS/E
.................................................................................................................. 78
FIGURE 4.8: WMTS 66KV OVERHEAD 2011 FORECAST SUB-MODEL I ..................... 80
FIGURE 4.9: WMTS 66KV OVERHEAD 2011 UPDATED FORECAST SUB-MODEL II ...... 82
FIGURE 4.10: WMTS 66KV OVERHEAD 2011 FORECAST LINES POWER LOSSES....... 86
FIGURE 4.11: WMTS 22KV OVERHEAD 2011 FORECAST SUB-MODEL ..................... 88
FIGURE 4.12: WMTS 22KV OVERHEAD 2011 FORECAST LINES POWER LOSSES....... 92
FIGURE 4.13: WMTS 22KV AND 66KV OVERHEAD POWER LOSS COMPARISON ........ 93
FIGURE 4.14: CITIPOWER 66KV OVERHEAD OVERALL POWER LOSS ......................... 97
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

XIII

List of Figures

FIGURE 4.15: CITIPOWER 22KV OVERHEAD OVERALL POWER LOSS ......................... 99


FIGURE 4.16: CITIPOWER 66KV OVERHEAD 2011 FORECAST OVERALL POWER LOSSES
................................................................................................................ 103
FIGURE 4.17: CITIPOWER 22KV OVERHEAD 2011 FORECAST OVERALL POWER LOSS
................................................................................................................ 106
FIGURE 4.18: CITIPOWER OVERALL OVERHEAD POWER LOSS COMPARISON............ 107
FIGURE 5.1: POWER NETWORK WITH UNDERGROUND SUB-TRANSMISSION AND
DISTRIBUTION SYSTEMS .............................................................................. 111

FIGURE 5.2: UNPLANNED SAIDI BY CAUSE FOR 2004 ......................................... 118


FIGURE 5.3: TYPICAL XLPE UNDERGROUND CABLE ............................................. 123
FIGURE 5.4: GIL CABLE DESIGN ......................................................................... 124
FIGURE 5.5: TYPICAL HTS CABLE ...................................................................... 127
FIGURE 6.1: WMTS 66KV UNDERGROUND SUB-MODEL ....................................... 138
FIGURE 6.2: WMTS 66KV UNDERGROUND CABLES POWER LOSSES ...................... 141
FIGURE 6.3: WMTS 22KV UNDERGROUND SUB-MODEL I...................................... 142
FIGURE 6.4: WMTS 22KV UNDERGROUND SUB-MODEL II..................................... 145
FIGURE 6.5: WMTS 22KV UNDERGROUND SUB-MODEL II POWER LOSSES ............. 148
FIGURE 6.6: WMTS 22KV UNDERGROUND SUB-MODEL III.................................... 150
FIGURE 6.7: WMTS 22KV UNDERGROUND SUB-MODEL III POWER LOSSES ............ 152
FIGURE 6.8: WMTS 22KV UNDERGROUND SUB-MODEL III BRANCH LOADING ......... 154
FIGURE 6.9: WMTS 66KV UNDERGROUND 2011 FORECAST SUB-MODEL .............. 156
FIGURE 6.10: WMTS 66KV UNDERGROUND 2011 FORECAST POWER LOSSES ....... 159
FIGURE 6.11: WMTS 22KV UNDERGROUND 2011 FORECAST SUB-MODEL ............ 160
FIGURE 6.12: WMTS 22KV UNDERGROUND 2011 FORECAST POWER LOSSES ....... 163

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

XIV

List of Figures

FIGURE 6.13: WMTS 22KV AND 66KV UNDERGROUND POWER LOSS COMPARISON 164
FIGURE 6.14: CITIPOWER 66KV UNDERGROUND OVERALL POWER LOSSES ............ 168
FIGURE 6.15: CITIPOWER 22KV UNDERGROUND OVERALL POWER LOSSES ............ 171
FIGURE 6.16: CITIPOWER 66KV UNDERGROUND 2011 FORECAST OVERALL POWER
LOSSES ..................................................................................................... 175

FIGURE 6.17: CITIPOWER 22KV UNDERGROUND 2011 FORECAST OVERALL POWER


LOSSES ..................................................................................................... 178

FIGURE 6.18: CITIPOWER OVERALL UNDERGROUND POWER LOSS COMPARISON ..... 179
FIGURE 6.19: CITIPOWER OVERALL UNDERGROUND POWER LOSS COMPARISON ..... 180
FIGURE 6.20: CITIPOWER TOTAL NUMBER OF LINES COMPARED TO CABLES............ 181
FIGURE 7.1: TRIAXIAL SUPERCONDUCTING CABLE DESIGN .................................... 187
FIGURE 7.2: FULL SCALE TRIAX TERMINATION ..................................................... 188
FIGURE 7.3: TRIAXIAL SUPERCONDUCTING CABLE TERMINATION............................ 193
FIGURE 7.4: GROWTH IN U.S.-MANUFACTURED SUPERCONDUCTING WIRES ........... 195
FIGURE 7.5: PRICE-VOLUME CURVE DEVELOPED BY THE GERMAN INDUSTRY
ASSOCIATION IV SUPRA.............................................................................. 196

FIGURE 7.6: THE NETHERLANDS HV CIRCUITS LENGTH ........................................ 198


FIGURE 7.7: HV-NETWORK BEFORE AND AFTER INSTALLATION HTS CABLE ............ 199
FIGURE 7.8: CRYOCOOLER PULSE WITH TUBE DESIGN .......................................... 200
FIGURE 7.9: COOLING SYSTEM FOR LONG LENGTH SUPERCONDUCTING CABLES - AN
ARRAY OF PULSE TUBE CRYOCOOLERS AND RESERVE LIQUID NITROGEN TANK . 201

FIGURE 7.10: EXPECTED ROUTE LENGTH PER UNIT DEMAND ................................. 202
FIGURE 7.11: ROUTE LENGTH VERSES 154KV UNDERGROUND CABLE PROCESSION
RATE CIRCUIT TO KM ............................................................................. 204

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

XV

List of Figures

FIGURE 7.12: DEPLOYMENT OF 22KV HTS CABLE IN CITY CENTRE........................ 205


FIGURE 7.13: 66KV, 300 MVA HTS TRIAXIAL CABLE ........................................... 207
FIGURE 7.14: CITIPOWER 66KV HYBRID SUB-MODEL I .......................................... 210
FIGURE 7.15: CITIPOWER 66KV HYBRID SUB-MODEL I LOSSES .............................. 212
FIGURE 7.16: CITIPOWER WMTS ZONE SUBSTATIONS AND SUB-TRANSMISSION
UNDERGROUND CABLES

............................................................................. 213

FIGURE 7.17: CITIPOWER 66KV HYBRID SUB-MODEL II ......................................... 215


FIGURE 7.18: HYBRID SUB-MODEL II CABLE LOADING ........................................... 216
FIGURE 7.19: CITIPOWER 66KV HYBRID SUB-MODEL II LOSSES ............................. 218
FIGURE 7.20: HTS CABLE ABILITY TO LIMIT A FAULT CURRENT .............................. 222
FIGURE 7.21: CITIPOWER 66KV HYBRID SHORT CIRCUIT ANALYSIS SUB-MODEL ...... 224
FIGURE 8.1: CITIPOWER 66KV LQ-JA PILOT SUB-MODEL ..................................... 234

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

XVI

List of Tables

List of Tables
TABLE 2.1: PERCENTAGE OF CABLES UNDERGROUND IN NSW ............................... 18
TABLE 2.2: STATUS OF EUROPEAN LOW VOLTAGE NETWORKS ................................ 21
TABLE 2.3: STATUS OF EUROPEAN MEDIUM VOLTAGE NETWORKS ........................... 22
TABLE 2.4: STATUS OF EUROPEAN HIGH VOLTAGE NETWORK.................................. 23
TABLE 2.5: STATUS OF EUROPEAN EXTRA HIGH VOLTAGE NETWORK ....................... 23
TABLE 2.6: GLOBAL POWER TRANSMISSION AND DISTRIBUTION PRACTICES .............. 26
TABLE 2.7: POTENTIAL BENEFITS FROM UNDERGROUNDING CABLES ACROSS NSW .. 31
TABLE 2.8: ANNUAL UNDERGROUNDING BENEFITS INDICATIVE ASSORTMENT ............ 33
TABLE 3.1: OVERHEAD LINE CONDUCTORS - TYPES AND FEATURES - ....................... 55
TABLE 4.1: WMTS 66KV OVERHEAD EDSA LOAD FLOW BUS RESULTS ................... 68
TABLE 4.2: WMTS 66KV OVERHEAD LINES LOSSES............................................... 69
TABLE 4.3: PSS/E WMTS 66KV OVERHEAD LINES LOSSES ................................... 71
TABLE 4.4: WMTS 22KV OVERHEAD EDSA LOAD FLOW BUS RESULTS ................... 75
TABLE 4.5: WMTS 22KV OVERHEAD LINES POWER LOSSES ................................... 76
TABLE 4.6: PSS/E WMTS 22KV OVERHEAD LINES POWER LOSSES ........................ 78
TABLE 4.7: WMTS 66KV OVERHEAD 2011 UPDATED FORECAST LOAD FLOW RESULTS
.................................................................................................................. 83
TABLE 4.8: WMTS 66KV OVERHEAD 2011 UPDATED FORECAST LINES LOSSES ....... 85
TABLE 4.9: WMTS 22KV OVERHEAD 2011 FORECAST LOAD FLOW RESULTS............ 89
TABLE 4.10: WMTS 22KV OVERHEAD 2011 FORECAST LINES LOSSES .................... 90
TABLE 4.11: CITIPOWER 66KV OVERHEAD OVERALL LINES LOSSES ......................... 94
TABLE 4.12: CITIPOWER 22KV OVERHEAD OVERALL LINES LOSSES ......................... 98
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

XVII

List of Tables

TABLE 4.13: CITIPOWER 66KV OVERHEAD 2011 FORECAST OVERALL LINES LOSSES
................................................................................................................ 101
TABLE 4.14: CITIPOWER 22KV OVERHEAD 2011 FORECAST OVERALL POWER LOSSES
................................................................................................................ 104
TABLE 5.1: AVERAGE MAINTENANCE COSTS OF AUSTRALIAN
ELECTRICITY NETWORK ...................................................................... 119
TABLE 6.1: WMTS 66KV UNDERGROUND EDSA LOAD FLOW BUS RESULTS........... 139
TABLE 6.2: WMTS 66KV UNDERGROUND LOSSES ............................................... 140
TABLE 6.3: WMTS 22KV UNDERGROUND SUB-MODEL II EDSA LOAD FLOW BUS
RESULTS ................................................................................................... 146

TABLE 6.4: WMTS 22KV UNDERGROUND SUB-MODEL II POWER LOSSES ............... 147
TABLE 6.5: WMTS 22KV UNDERGROUND SUB-MODEL III EDSA LOAD FLOW BUS
RESULTS ................................................................................................... 151

TABLE 6.6: WMTS 22KV UNDERGROUND SUB-MODEL III POWER LOSSES .............. 152
TABLE 6.7: WMTS 22KV UNDERGROUND SUB-MODEL III CABLE LOADING .............. 153
TABLE 6.8: WMTS 66KV UNDERGROUND 2011 UPDATED FORECAST LOAD FLOW
RESULTS ................................................................................................... 157

TABLE 6.9: WMTS 66KV UNDERGROUND 2011 UPDATED FORECAST LINES LOSSES158
TABLE 6.10: WMTS 22KV UNDERGROUND 2011 UPDATED FORECAST LOAD FLOW
RESULTS ................................................................................................... 161

TABLE 6.11: WMTS 22KV UNDERGROUND 2011 UPDATED FORECAST LINES LOSSES
................................................................................................................ 162
TABLE 6.12: CITIPOWER 66KV UNDERGROUND OVERALL LINES LOSSES ................ 165
TABLE 6.13: CITIPOWER 22KV UNDERGROUND OVERALL LINES LOSSES ................ 169

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

XVIII

List of Tables

TABLE 6.14: CITIPOWER 66KV UNDERGROUND 2011 FORECAST OVERALL LINES


LOSSES ..................................................................................................... 173

TABLE 6.15: CITIPOWER 22KV UNDERGROUND 2011 FORECAST OVERALL POWER


LOSSES ..................................................................................................... 176

TABLE 7.1: 66KV 300 MVA HTS CABLE FOR MELBOURNE DATA .......................... 208
TABLE 7.2: CITIPOWER 66KV HYBRID SUB-MODEL I POWER LOSSES ...................... 211
TABLE 7.3: CITIPOWER 66KV HYBRID SUB-MODEL II CABLE LOADING ..................... 214
TABLE 7.4: HYBRID SUB-MODEL II POWER LOSSES ............................................... 217
TABLE 7.5: CITIPOWER 66KV HYBRID V SHORT CIRCUIT ANALYSIS RESULTS ........... 223

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

XIX

List of Publications

List of Publications
1. H. Al-Khalidi & A. Kalam, Enhancing Security of Power Transmission and
Distribution Networks with underground cables AUPEC 05, September 2528, Hobart, Tasmania, Australia.

2. A. Kalam & H. Al-Khalidi, Victoria University, Australia, D Willn, Ultera, NKT


Research, Denmark, HTS Cable and its Anticipated Effects on Power
Transmission Networks IEE ACDC 2006, March 28th-31st, London, UK.

3. H. Al-Khalidi & A. Kalam, Victoria University, Australia, The Impact of


Underground Cables on Power Transmission and Distribution Networks
PECon 2006, November 28 and 29, Putra Jaya, Malaysia.

4. H. Al-Khalidi, A. Kalam, A. Maungthan Oo, Victoria University, Australia,


Investigation of aging devices in power network, AUPEC 2006, December
10-19, Melbourne, Australia.

5. H. Al-Khalidi & A. Kalam, Victoria University, Australia, Reduction in subtransmission loss using underground power cables, AUPEC 2008,
December 14-17, Sydney, Australia.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

XX

List of Publications

6. A. Hadbah, A. Kalam, H. Al-Khalidi, Victoria University, Australia, The


subsequent security problems attributable to increasing interconnectivity of
SCADA systems, AUPEC 2008, December 14-17, Sydney, Australia.

7. H. Al-Khalidi & A. Kalam, Victoria University, Australia, Savings in


Transmission losses using Underground Cables Compared to Overhead
Lines, Transactions IEEE Pakistan, 2008, Pakistan.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

XXI

Chapter 1: Thesis Overview

CHAPTER 1
THESIS OVERVIEW
1.0 Introduction
In most countries around the world, the electricity sector has been liberalised
forcing the electricity utilities to operate increasingly on commercial terms.
Therefore, utilities must develop greater flexibility and security in terms of the
supply and distribution of electricity, in the best and in the most effective
environmentally-friendly way possible.

Replacing overhead lines with underground cables has been an increasing


trend in Europe over the last decade. New cable technology combined with
improved production processes and specifications of international testing has
led to increased usage of underground cables [1]. Australia has fallen well
behind other countries in such moves, mainly due to:

Low density and demographics of Australian cities,

High cost of underground systems, and

Limited restrictions on using overhead lines.

Currently, due to greater public environmental awareness, restrictions on land


usage, and higher demand for reliable and efficient electricity supply, a marked
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

Chapter 1: Thesis Overview

increase in the use of underground cable network is expected [2]. Frequent and
major power outages cause many concerns. Some of these concerns relate to
the security and reliability of the power systems. Ageing assets also play a big
role in more frequent outages (most of the outages and disruptions usually
occur on the distribution part of the power network) [3].

A typical overhead power network consists of power generation, transmission


and distribution systems. Figure 1.1 shows the different stages of a typical
overhead power network [4]. Distribution parts of the network contribute to most
of the outages mainly due to their physical location close to natural vegetation
e.g. trees, bushes etc. In Australia, trees are well known to cause the highest
number of overhead outages [3].

Figure 1.1: Power network with overhead transmission and distribution


systems [4]

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

Chapter 1: Thesis Overview

Various projects on the conversion of overhead lines to underground cables


have been successfully carried out in many countries including Australia; most
of these projects are designed to meet the local conditions of the cable route,
yet many technical issues have been raised before and during project
implementation. These issues will not only affect the delivery but the ongoing
performance of the network. This research discusses the implications of this
process and recommends scenarios for installing and maintaining underground
cables to provide an efficient, reliable and economical electricity supply [3].

Although there are few researches and reports delivered on moving overhead
lines to underground cables but not to the extent of investigating the
implementation of new technology and its effect on electricity supply from
efficiency, reliability and economic points of view. Research efforts discussed in
references [1, 2, 5-9], have been continuing on the reliable movement of
overhead power lines to underground cables. Most of these studies are
independently prepared by individuals or research organisations for local
government and councils. The foci of these studies have been mainly
concentrated on specific local routes. Perhaps Putting Cables Underground
Working Group report [9] was the only comprehensive report that covers putting
overhead power lines underground in Australia, the report was relinquished in
1998 and it covers various aspect of the moving process but it did not discuss
or presented the possibility of using new type of underground cables or using
new techniques in placing power cables underground over the whole of
Australia.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

Chapter 1: Thesis Overview

This thesis will investigates the various technical aspects of moving overhead
lines to underground, which may include new way of placing underground
cables in Victoria and adopting new cable technologies such as the new type of
cross

Linked

Polyethylene

(XLPE)

cables

and

High

Temperature

Superconductive (HTS) cables. Most of these discussions are based on local


and overseas experiences and in accordance with their local conditions and
regulations.

The research in the thesis moves further with a pioneering project which
investigates the technical aspects of converting overhead power lines to
underground cables and their effects on the Victorian power network, in
particular. The research also looks into the state of the art technology of HTS
cables. It further explores ways of utilising this technology in combination with
the existing ones by using XLPE cables so as to effectively and efficiently model
the Victorian power network.

1.1 Motivation
The technical considerations for moving overhead networks to underground will
have a great impact on the network in terms of safety and reliability. Analysing
these considerations and employing new technologies will enhance the delivery
of power in terms of safety and reliability. Improving the overall process of
moving overhead lines to underground cables has always been the aim of
utilities that plan or consider such a move. Earlier researches and contemporary
studies [5, 7, 9, 10] show that underground cables can improve the efficiency
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

Chapter 1: Thesis Overview

and reliability of the electricity supply and reduce the risks of fatal accidents
caused by cars hitting power poles as well as improve the landscape.

The main causes of overhead power transmission and distribution networks


interruption are in fact unplanned external causes such as storms, bushfires,
lightning, trees, animals, vehicle accidents and vandalism. Interruptions can
also be caused by equipment and line or cable failure due to overload and
ageing. However, overhead networks are much more vulnerable to external
causes. In general, the maintenance works required for overhead networks are
about twice the number as compared to those for underground power networks
[3].

From the research on Victorian local distribution company, Citipower 2004


performance report [11], it was found that 70% of outages are attributed to the
overhead network and 30% to the underground network. The average duration
for an overhead fault is 50-55 minutes with an average duration of
approximately 65 minutes for an underground fault. These figures are based on
the System Average Interruption Duration Index (SAIDI). The higher duration for
the underground network is a reflection of the time it takes to effect repairs.

For many decades, overhead lines had proven to be a reliable solution, both
technically and economically. Back then, no other alternative and competitive
system was available and there was little concern for the environmental aspect
when planning and constructing a new electrical network. However, modern

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

Chapter 1: Thesis Overview

technology, with its continuous development of manufacturing and installation,


makes it possible for underground systems to be competitive with overhead
lines - technically, environmentally and economically. Whilst most overhead
interruptions occur for a short period of time, mainly less than a second due to
surge strikes, other permanent interruptions are usually caused by external
factors [12].

As reliability and efficiency have become a major factor, moving overhead lines
underground has become a vital concern to Victorian utilities. As part of a long
term investigation into the improvement of infrastructure and safety of the
Victorian electricity supply, a comprehensive study on moving overhead lines
underground focusing on local environments is a necessity. It is therefore
essential to have a technically reliable guide for the future implementation of
underground power cables for the state, one with the potential to be utilised by
other states as well.

1.2 Research methodologies and techniques


This research aims to study the existing overhead power network in Victoria and
proposes a technical model for converting overhead power lines to
underground.

The

modelling,

design,

implementation,

simulation

and

development were carried out using Electrical power system Design Simulation
and power Analytics (EDSA) - Paladin and Power System Simulator for
Engineering (PSS/E). The subsequent sections will provide detailed

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

Chapter 1: Thesis Overview

elaborations

of

the

proposed

methodologies

and

techniques.

The

methodologies, techniques and analysis details are as follows:

1.2.1 Analysis of the current power networks


Primary research was carried out to study the existing overhead power network
along with the underground cables. Thorough research was further carried out
to investigate local and overseas models of underground cables. This provides
vital

information

on

the

various

methods

and

techniques

used

in

undergrounding cables. The literature survey further suggests that up until now,
little or no research has been undertaken to analyse power networks
incorporating new technologies, like HTS cables in order to convert overhead
power lines to underground. Thus detailed research was carried out, in this
study, on the load flow analysis of the power network so as to examine the
current behavioural patterns of the network and to provide insight into how the
network will appear in the future?

1.2.2 Investigation of the Victorian overhead power networks


Network

parameters

and

performance

results

were

obtained

after

comprehensive study of the Victorian overhead power networks. A section of


the large power network was selected to effectively study the behaviour of the
overall network as it was impossible to conduct the investigation over the whole
Victorian power network. Network behaviour was investigated and an efficient
underground cables model was developed.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

Chapter 1: Thesis Overview

1.2.3 Development and analysis of the Victorian overhead power


networks
After obtaining overhead power network real data for the year 2007 on the
selected section, an overhead network model was developed in order to
perform further simulation. The results obtained from the simulation are based
on normal operations or steady state conditions, and abnormal or at fault
conditions. The results are used as a reference to compare the other setup and
configuration results of the network.

1.2.4 Development and analysis of the Victorian overhead power


networks with 2011 forecast
This model is similar to the overhead model as described in Section 1.2.3 with
the exception of loading demand, moreover, a 2011 forecast load demand was
used to determine the new overall load flow and identify the elements under
stress in the network. Figure 1.2 shows Citipower zone substations loadings for
2007 and the forecast loadings of 2011 based on reference [11].

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

Chapter 1: Thesis Overview

Figure 1.2: Citipower zone substation 2007 and forecast 2011 loadings
[11]

1.2.5 Development and analysis of the Victorian underground power


networks
An underground model was developed based on the overhead model with the
exception of line parameters. In this scenario, XLPE cable parameters were
used instead of traditional overhead line parameters.

In cases where the cable rating was less than the overhead line, cable selection
was made based on either using a higher cable rating or using double circuits.
All other network parameters were kept, where possible, to provide a smooth
transition from an overhead to an underground model.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

Chapter 1: Thesis Overview

1.2.6 Development and analysis of the Victorian overhead power


networks with 2011 forecast
This model is similar to the underground model as described in Section 1.2.5
with the exception of using 2011 loading demand. Furthermore, the 2011 load
forecast which is used in this model was same as the loading forecast used in
the 2011 forecast overhead model. This enables a comparison to be drawn
between the two models, to determine the new overall load flow and to identify
the elements under stress in the network in this model.

1.2.7 Development and analysis of the Victorian hybrid power networks


Two types of contemporary cable technologies were used in the development of
the hybrid cables underground model. In this model, selected lengths of HTS
cable were used in conjunction with XLPE cables that have approximately the
same or higher rating as the underground model. The forecasted load demand
for the year 2011 was deployed only in the development of the network with
various configurations. One voltage level has been used to highlight the
potential benefits of HTS cables in handling massive capacity and providing a
great load flow venue in the network. The result of this model was then
compared with the results obtained from a similar configuration for overhead
and underground models.

1.2.8 Model optimisation of the Victorian underground power network


Based on the earlier developed models and their results, a final optimised
underground network model was acquired for the Victorian power network. The

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

10

Chapter 1: Thesis Overview

highest priorities were given to the overall safety, efficiency and reliability which
was incorporated in this model, as this is vital for any power network. The
results obtained from this model demonstrate that a promising overall
performance can be achieved for more reliable and flexible power flow in the
network.

1.3 Originality of the Thesis


This research contributes directly to the knowledge of power system
transmission and distribution. More specifically, it contributes to the knowledge
of overhead lines and underground cables systems. The research produces
reference

guidelines

for

Victorian

underground

sub-transmission

and

distribution networks. The research makes a unique technical contribution to the


process of moving overhead power lines to underground cables in Victoria and
its potentialities for other Australian states.

This research contributes to knowledge in the following specific areas:

(1) in identifying the requirements of the technical aspect of moving


overhead power lines to underground in Victoria, the proposed research
is of immense benefit to the Victorian overhead sub-transmission and
distribution network as it provides a technical proposal for migrating to
the underground network;

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

11

Chapter 1: Thesis Overview

(2) it investigates the implementation of a new cable technology and its


effect on the electricity supply from the points of view of efficiency,
reliability and economics;

(3) it presents a unique simulated model that produces a new voltage level
of the new underground cable technology, HTS, to be used in small
section of the Victorian power network;

(4) it reveals the intermingled implementation of the new cable technology,


HTS, with the traditional underground cable technology, XLPE, and their
simulated performance;

(5) it demonstrates a substantial reduction in the impact of the power


network on the environment, which includes Electric and Magnetic Fields
(EMF) and pollution in addition to the exponential improvement of public
safety.

1.4 Objectives
This study develops a load flow model to pinpoint problems in existing overhead
network and determine the effects of the underground cables on Victorian
power network overall. After developing the flow model, load flow analysis is
performed. The purpose of this flow analysis is to compute accurate steadystate voltages of all transmission and distribution sections in the network. Also it

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

12

Chapter 1: Thesis Overview

gives the necessary data needed to confidently plan improvements to existing


network and justify the recommendation of this study.

1.5 Organisation of the Thesis


This thesis contains eight chapters and is organized as follows:

Chapter 1 provides a basic introduction to the research as well as the


motivation behind this research. This chapter also includes the research
methodologies and techniques and the contribution of this research to the
knowledge of science and engineering.

Chapter 2 presents a literature review of recent developments in both overhead


and underground transmission and distribution power networks. Furthermore,
an investigation of the current overhead power network is presented in Chapter
3. Meanwhile, an elaboration on the development and analysis of the Victorian
overhead power network model is covered in Chapter 4.

Underground cable technology and underground power networks are explored


in Chapter 5, whereas Chapter 6 further emphasises the details of the
development and analysis of the underground power network model.

An in-depth view of the development and analysis of an optimised model for


Victorias power network that consists of hybrid underground cable technologies

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

13

Chapter 1: Thesis Overview

is further portrayed in Chapter 7. Finally, conclusions and recommendations for


future work are discussed in Chapter 8.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

14

Chapter 2: Literature Review

CHAPTER 2
LITERATURE REVIEW
2.0 Introduction
The purpose of this chapter is to provide the necessary background required for
understanding the moving of overhead power lines to underground. It also
highlights the concepts that relate to power network transmission and
distribution media conversion as well as recent developments and research in
this field. It further discusses the advantages and limitations of each concept, as
well as their anticipated effects on the surroundings and the reliability of the
power network overall.

To facilitate the understanding of present undergrounding research and


practices, it is essential to investigate the early introduction of underground
cables to the power network. While undergrounding overhead lines is not a new
topic and has been going on for many decades, especially for low to medium
voltage, in the past, the limited adoption of the conversion was mainly due to
the high cost associated with underground cables and their installation, and
limited environmental concerns related to the overhead lines [13].

Historically underground cables have been associated with high cost


(approximately twice the cost of overhead lines), attributed to:
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

15

Chapter 2: Literature Review

cost of insulation and protection that underground cables require as they


are normally laid about a meter or so below ground;

the extra space required for cable connection;

the limited utilisation of the easement due to the necessity to access the
cable for repair and maintenance work;

the requirement for reactive power compensation at 400kV at every 15


20 km due to ac current.

As a result of impedance difference, it is difficult to connect underground cables


to an existing overhead network, and to resolve this issue, meshed networks
have to be reconfigured and partially operated, which necessitates the
requirement for power transformation increase, hence this incurs more
investment costs [7].

However, since the early 70s, the undergrounding of power cables started
getting more attention, hence limited installation of high and extra high voltage
began. Another factor that contributed to the acceleration of this process is the
increased awareness, in public, about benefits gained on environmental and
aesthetic grounds. In any case the high cost has always been the main reason
for reluctance among utilities to remove overhead lines [13].

To highlight these, this chapter is arranged to provide deeper understanding of


overhead and underground lines. Section 2.1 elaborates issues related to
overhead power networks. Overhead transmission lines and their environmental
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

16

Chapter 2: Literature Review

effects are discussed in Section 2.2. As understanding the fundamentals is so


critical in developing future power networks, a detailed elaboration is given in
Section 2.3. The chapter is concluding remarks are in Section 2.4.

2.1 Issues with Power Networks


In recent years, there has been increasing interest in and attention to
underground power networks, due to the belief, which is adapted by many
public groups and research bodies around the world, that undergrounding will
help tackle many of the issues surrounding power networks, such as reliability,
environmental and health issues, just to name a few. Various research studies
[5-7, 9, 10, 14, 15] were carried out by many public groups and research
organizations around the world looking at a mixture of underground power
network issues. Many of these researchers have identified various issues
concerning power networks but due to the nature of this work which is only
concerned about subtransmission and distribution networks, this thesis will thus,
only target and examine a series of case studies that are relevant to the scope
of the aforementioned issues in both underground and overhead networks.

2.1.1 Research literature on overhead and underground power networks


There have been various research studies and innovations carried out around
the world in overhead line and underground cable. Europe leads the world in
underground technologies. The following sub-sections discuss a range of
research and findings conducted in Australia, Europe and United States.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

17

Chapter 2: Literature Review

a) Australian Scenario
Most of the Australian states are looking towards moving their overhead
networks to underground. The local government of NSW is looking at various
ways to increase underground lines both in urban and regional areas. The
Minister for Energy asked the Independent Pricing and Regulatory Tribunal
(IPART) to assess long term costs and benefits. Though there is a concern for
the extremely high cost for undergrounding, nonetheless, due to the pressure
from the public, the ministry is looking at ways to implement it in an economical
way. Table 2.1 shows the percentage for both low and high voltage of
underground cables in NSW [10].

Table 2.1: Percentage of cables underground in NSW [10]


Whole of NSW
underground

EnergyAustralia
Integral Energy
Country Energy
Australian
Inland Energy

Urban centres
underground

LV mains

HV mains

LV mains

HV mains

23
39
8

36
17
1

25
39
14

63
24
17

<1

An initiative from the NSW government, together with electricity companies and
various community groups are currently investigating the likelihood of
implementing a much wider undergrounding program. Specifically, it is
considering undergrounding electricity lines carrying voltages of up to 22kV in
urban and regional areas [10].

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

18

Chapter 2: Literature Review

Local councils often need Distribution Network Service Providers (DNSP) to


underground both low and high voltage distribution lines in newly developed
areas. In these cases, developers of the area install the underground cabling
and when completed, the ownership of these assets are transferred to the
DNSP [10].

However, in already established suburban areas where overhead construction


already exists, the DNSP or other parties such as local councils may initiate an
undergrounding project. Whenever considering any undergrounding project,
EnergyAustralia states: undergrounding schemes are initiated in areas where
supply reliability is below an acceptable standard, for example the Northern
Beaches programs over the last 10 years. Undergrounding low voltage cables
only provides supply reliability improvements for customers in the immediate
vicinity [10].

The Australian government initiated a study to address the community concerns


to

investigate

the

possibility

of

moving

overhead

power

lines

and

telecommunication cables underground [9]. The common concerns about the


overhead lines are:

unsightly appearance;

vulnerable to weather damages;

risk of motor vehicle collision with the power poles, and

risk of direct conductor contacts.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

19

Chapter 2: Literature Review

Undergrounding has been carried out in most central business districts and
mandatory planning policies have been adopted by all federal states and
territories that all new estate must have their power and telecommunication
services underground. While there is no current enforcement encouraging the
initiation of undergrounding, yet there are some obligatory measurements to
underground communication cables within six months of undergrounding power
lines [9].

The literature survey has revealed many reports on undergrounding [1, 5, 6, 810, 15-18] covering the technical, costing and regulatory aspects of
undergrounding. Focusing on available practices and technologies, it estimates
the total cost of undergrounding both power lines and telecommunication cables
for urban and suburban Australia to be around $23.37 billion. This will cost a
house hold an average of $5,516 for such a move, with a potential of reducing
the cost by up to 35% over five years if a number of innovative ideas identified
by reference [9] were implemented.

b) European Scenario
Reference [13] provides a report on undergrounding of electricity lines in
Europe which summarises the current position of overhead lines and
underground cables in Europe as per network voltage and presents its findings
in three categories:

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

20

Chapter 2: Literature Review

Low to Medium: a distribution network which consists of low voltages


(200 to 400V) and medium voltages (10 to 50kV)
High: considered as distribution in some countries and transmission in
others. This network consists of high voltages (60 to 150kV)
Extra High: a main transmission network which consists of extra high
voltages (220 to 400kV).

Table 2.2 highlights the lengths of the Low Voltage (LV) networks and the
associated percentage of underground cables installed in a number of
European countries in the period 1999 to 2000. This table shows that most of
the countries covered by the report have achieved a high rate of underground
cables compared to overhead lines in their low voltage networks.

Table 2.2: Status of European low voltage networks [13]

Netherlands
UK
Germany
Denmark
Belgium
Norway
Italy
France
Portugal
Spain
Austria

km of
network

Length of
network
(m/habitant)

Percentage
underground

145,000
377,000
926,000
92,000
108,000
185,000
709,000
632,000
112,000
241,000
65,000

8.9
6.4
11.3
17.6
10.6
41.3
12.1
10.5
11.9
6.0
8.0

100 %
81 %
75 %
65 %
44 %
38 %
30 %
27 %
19 %
17 %
15 %

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

21

Chapter 2: Literature Review

Table 2.3 demonstrates the Medium Voltage (MV) networks lengths and the
percentage of underground cables installed in a number of European countries.

Table 2.3: Status of European medium voltage networks [13]


km of
network
Netherlands
Belgium
UK
Germany
Denmark
Sweden
Italy
France
Norway
Spain
Portugal
Austria

101,900
65,000
372,000
475,000
55,000
98,700
331,000
574,000
92,000
96,448
58,000
57,000

Length of
network
(m/habitant)
8.9
6.4
6.3
5.8
10.5
12.3
5.7
9.5
20.5
2.4
6.1
7.0

Percentage
underground
100 %
85 %
81 %
60 %
59 %
53 %
35 %
32 %
31 %
30 %
16 %
15 %

Table 2.3 confirms what has already been mentioned in Table 2.2 that most of
the countries are well advanced in adopting underground cable lines in their
medium voltage networks.

Correspondingly Tables 2.4 and 2.5 disclose the High Voltage (HV) and Extra
High Voltage (EHV) networks respectively, the lengths and the percentage of
underground cables installed in a number of European countries. Although at
high voltage, the undergrounding percentage rate varies somehow between low
to medium, however countries like Netherlands, UK, Denmark and Switzerland

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

22

Chapter 2: Literature Review

scored a higher percentage especially in the extra high voltage networks


compared to other countries listed in the Tables 2.4 2.5.

Table 2.4: Status of European high voltage network [13]


High Voltage
60-90-110-150 kV

Denmark
UK
Netherlands
Switzerland
Germany
Belgium
France
Portugal
Norway
Italy

km of
network

km of
Underground

8,005
25,825
6,457
6,080
76,349
5,172
50,513
9,311
19,825
36,677

1,673
3,789
905
680
4,740
396
1,984
258
624
449

20.9
14.8
14.0
11.2
8.2
7.6
3.9
3.8
3.2
1.2

Table 2.5: Status of European extra high voltage network [13]


Extra High Voltage
220-275 kV

380-400 kV

km of
km of
network Underground
Denmark
UK
France
Italy
Norway
Netherlands
Germany
Switzerland
Portugal
Belgium

5,578
3,029
27,890
13,641
6,049
648
21,545
5,822
4,409
267

375
71
813
387
64
6
35
22
-

%
6.5
2.3
2.9
2.8
1.1
0.9
0.2
0.4
0
0

km of
km of
network Underground
788
20,794
9,751
2,316
1,979
18,314
1,800
1,234
883

11
2.5
9
36
0.4
62
-

1.4
0.01
0.1
1.8
0.02
0.3
0
0

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

23

Chapter 2: Literature Review

It is clearly noted that HV and EHV underground sections of the network are
only constructed in urban or semi urban areas and in areas with environment or
historic restrictions. Therefore, the high cost of undergrounding cables in such
areas compared to overhead lines reinforces the conclusion outlined before
which is that the percentage of undergrounding at high voltage levels in the
European countries is still low [13].

Various countries around the globe have always had the aspiration of upgrading
their overhead power lines, telephone lines, cable TV lines, and optical cables
to underground. Jey et al. [19] remarks that many power consumers around the
world find it hard to believe that, with 21st technologies controlling 21st century
economies, electrical engineers are still relying on 19th century wooden poles.
Utilities and cable companies dealing with sewer, gas and water are digging up
streets all year round. This leads to a fair question directed at the public
officials: why are they not implementing a policy of utility corridors for burying all
services together? [19].

Many customers and end users who are longing for infinite bandwidth already
have sanitary sewers, storm drains, waterlines, hot water pipes and natural gas
lines reaching their premises. It makes all the sense in the world to build the
power cables in these existing rights of way on conduits, ducts, sanitary sewers,
storm drains, water mains, hot water pipes, and gas pipes. Building
underground power cables will meet customers basic needs that they have
forever been longing for and they should always remember that paying undue
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

24

Chapter 2: Literature Review

attention to a return on their investment so early in the process is an


unproductive exercise [19].

When was there ever a time when the leaders in charge of sewers, drinking
water lines, hot water pipes, electricity grids, hydropower stations, roads,
bridges, transportation systems, hospitals, museums, parks, and opera halls,
were questioned: as to what the return on the investment has been for the past
century? Would customers have enjoyed the same quality of life without these
services? Civil engineers are in an ideal position to guide these industries with
their unique talents in planning, execution, and serving their commitment [19].

Jey et al. [19] has provided a comprehensive global survey about moving
overhead lines around the world. The result of this study, which is given in
Table 2.6, indicates that most countries around the world would prefer to move
their overhead power lines underground.

Although, they have considerably lower Gross Domestic Product (GDP)


ranking, yet countries such as Denmark, Germany, Holland, Hong Kong,
Iceland, Israel, Singapore, Sweden, Switzerland and United Arab Emirates
(UAE) just to name a few [19], have already converted all or most of their
overhead lines underground.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

25

Chapter 2: Literature Review

Table 2.6: Global power transmission and distribution practices


[19]

Country

Algeria
Argentina
Australia
Austria
Belgium
Brazil
Canada
Chile
China
Croatia
Czech
Denmark
Egypt
Estonia
Finland
France
Germany
Greece
Holland
Hong
Kong
Hungary
Iceland
India
Iran

Dist.
Volt.
(kV)

Dist. Line
Length
(km)

5.5 to
30
6.5 to
66
11 to
44
1 to
36
.23 to
29
.22 to
34.5

172,424

6.6 to
66
.5 to
220
.4 to
35
.4 to
35
10 to
24
3 to
30
6 to
.23 to
110
.22 to
20
.4110
<150
1 to
30
.22 to
33
10 to
120
1 to
24
2.2 to
15
6 to

314,805

%
U/G

176,756

64

4,000,000

7,300,000

20

121,465

24

97,000

24

59,299

59

242,346
61,159
354,243

21

1,206,000

29

1,550,800

72

170,000
249,936

100

17,000

85

65,800

16

8,132

100

5,084,126
433,487

Trans.
Volt.
(kV)
60, to
500
132 to
500
66 to
500
110 to
380
30 to
380
138 to
750
110 to
500
35 to
500
110 to
400
110 to
400
30 to
400
66 to
500
110,330
110 to
400
220 to
400
220to
380
66 to
400
50 to
380
132 to
400
120 to
750
110 to
400
32 to
400
63 to

Trans.
line
length
(km)

%
U/G
for
trans.

Population
(Million)

Size
(sq km)

11,912

28.7

2,381,740

32,447

35

2,766,890

75,195

20.0

7,617,930

9,611

8.2

82,738

8,717

32

10.3

30,230

170,000

182.0

8,456,510

155,328
10,561

32.2
15.7

9,220,970
748,800

163,300

1,287

9,326,410

7,236

4.4

56,414

6,520

4.3

56,600

14,481

21

5.4

42,394

18,495

74.8

995,950

4,980
21,526

1.5
5.2

45,000
305,470

100,000

60.0

545,630

36,800

0.5

82.5

357,026

10.7

130,800

10,000
12,352

31

16.0

33,883

1,600

50

7.4

1,042

3,900

10.2

92,030

1,917

0.3

106,000

35,790

945.0

3,287,590

60,516

62.5

1,648,000

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

26

Chapter 2: Literature Review

Ireland
Israel
Italy
Japan
Jordan
Korea (S)
Mexico
Morocco
New
Zealand
Norway
Oman
Poland
Portugal
Saudi
Singapore
Slovenia
S. Africa
Spain
Sweden
Swiss
Tunisia
Turkey
UAE
UK
USA
Yugoslav
Venezuela

33
5 to
38
13.2
to 33
.22 to
20
.1 to
6.6
.4 to
33
6.6 to
22.9
2.4 to
85
5.5 to
30
11 to
65
1 to
72
.433
to 33
15
to110
1 to
130
13.8
to 33
.4 to
22
.4 to
35
22 to
165
.38 to
132
.4 to
145
1 to
20
10 to
30
6.3 to
34.5
11 to
33
.23 to
132
<69
3.8 to
35
.12 to
69

80,000
21,140

33

1,031,000
1,274,664

35,477

16

366,983

10

622,059

28,769
160,739
200,000
15,616
644,900
187,272
109,000

35
100

57,600

43

256,384
550,000

23
80

250,000

80

66,500

80
615,907

60

4,793,656

147,072

400
110 to
400
161 to
400
132 to
400
22 to
500
132,400

5,800

3.6

70,280

4,800

6.0

20,330

65,863

58.0

294,020

165,667

12

127.0

374,744

5.3

92,300

3,037

66 to
765
115 to
400
60 to
225
110 to
350
60 to
420
33 to
132
220 to
750
150 to
400
66 to
380
66 to
400
110 to
400
220 to
765
220,400

27,937

48.0

98,190

72,000

105.0

1,923,040

31.7

446,300

4.0

268,680

18,246

4.5

307,860

6,580

2.8

212,460

12,610

38.6

304,465

11,918

10.1

91,951

19,000

24.0

1,960,582

100

4.6

683

2.0

20,000

42.8

1,219,912

40.2

504,750

132 to
400
60 to
400
90 to
225
66 to
380
132 to
400
275,400

30,665

9.0

410,934

20,000

7.3

39,770

3,150

9.0

163,610

68.0

770,760

69 to
765
110 to
400
115-765

13,609
17,667

2,600

12

26,443
32,240

1,600

10

4.0

82,880

13,912

60.0

241,590

607,494

0.4

290.0

9,158,960

10,868

10.6

102,173

22,212

24.0

912,050

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

27

Chapter 2: Literature Review

c) North American Scenario


InfraSource Technology, which is a leading provider of infrastructure
construction services for electric power, gas, telecommunications, and energy
intensive industries in the United States, has compiled an inclusive report on
undergrounding studies in Florida US [5]. This report stated that overhead
construction is a common practice in Florida, however, privately owned utilities
have to have a mechanism whereby customers can choose to move their
existing overhead services to underground, which of course comes at an
additional cost.

Brown [5], InfraSource has initiated a case study to investigate the implication of
undergrounding the existing overheard infrastructure in Florida as a response to
the order of the Florida Public Service Commission, which instructed each
privately-owned utility to establish a collaborative research plan to investigate
possible means of enhancing and developing a storm proof power network.
The extent of this project is basically focused on hurricanes and its effects on
the performance of underground power networks as well as the advantages of
underground power networks in normal wind-free circumstances.

Maney [20] shows how the traditional practice, by power utilities, is to go


overhead for all voltages, which is due to the fact that utilities are accustomed to
focus on direct costs such as Return On Investment (ROI), maintenance and
operational costs. However, they seem to deviate from this practice in two
instances: when it is more economically viable to go underground, or when
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

28

Chapter 2: Literature Review

customers - in newly developed housing estates - request underground and will


agree to bear the extra cost associated with undergrounding.

Although, using underground distribution lines is a very common practice in the


U.S., it is a different story when it comes to high-voltage transmission lines. In
the state of Virginia, underground lines make up a very small portion of
transmission lines. On the other hand, Europe is known for its extensive use of
undergrounding, though it is not yet considered as common practice [16].

In general, underground transmission lines are more expensive to install than


overhead lines. The cost of underground lines tends to bloat due to the high
cost of materials such as cables and insulating fluid. Overhead lines insulation
is achieved by using a free to use insulator Air, while underground cables
thickness, which is required to provide appropriate insulation, exponentially
adds to the cost of undergrounding transmission [16].

2.1.2 Benefits and limitation of underground power networks


According to Independent Pricing and Regulatory Tribunal of New South Wales
(IPRT NSW) [10], the benefits of undergrounding, which may accrue to the
wider community, are those comprising the external costs of overhead
networks. These costs (or negative externalities) can be seen as a by-product
of having power supplied by overhead electricity cables. They include:

actual or perceived impacts on the visual amenity of local environments;

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

29

Chapter 2: Literature Review

motor vehicle accidents that involve collisions with electricity poles;

the costs to consumers of power outages that result from storm damage
to overhead lines.

External costs are much less tangible than the avoided costs which accrue to
DNSP, and the value of avoiding many of them by placing overhead
infrastructure underground cannot be quantified in any absolute sense. Based
on a Centre for International Economics (CIE) assessment, the Tribunal
estimates the value of the quantifiable benefits of the proposed program to
range between around $535 and $625 million over 40 years in net present value
terms, or $350-$400 per connection or lead in. This is equivalent to around 40%
of the estimated cost of the proposed undergrounding program, assuming an
optimally planned approach is used [10].

This project had several quantifiable benefits that were reported such as:

decrease in costs associated with motor vehicle accidents that involve


collisions with power poles;

improvement in energy supply reliability;

elimination of overhead network maintenance costs;

increase in DNSP revenues due to substantial decrease in outages


associated with overhead network losses.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

30

Chapter 2: Literature Review

These benefits and estimated value over the project phase along a period of 40
years in net present value terms have been highlighted in Table 2.7 [10].

Table 2.7: Potential benefits from undergrounding cables


across NSW [10]
Item
Reduction in motor vehicle accident costs
Improvements in reliability of supply
Reduction in maintenance costs
Reduction in revenue losses
TOTAL
Benefits per lead in
Benefits as a proportion of optimised
system costs

Present value over project span


$230-$260 million
$55-$115 million
$105 million
$145 million
$535-$625 million
$350-$400
40 per cent

Furthermore, this project has also reported some unquantifiable benefits which
include, but are not restricted to the following [10]:

improvement of public amenity associated with less overhead power


lines outside residence and commercial areas;

improvement of utilities workplaces safety;

better landscaping and vegetation management;

improvement of public safety with the elimination of overhead lines which


reduces accidents associated with contacting overhead lines;

potential of improving health risk of electromagnetic fields.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

31

Chapter 2: Literature Review

The working group estimates that the quantifiable benefits represent around
10% of the total cost.

There are some other indirect advantages such as

beautifying landscapes allowing more trees to be planted and the likelihood of


property value improvement. The eventual direct advantages of undergrounding
include [9]:

decrease in motor vehicle collisions with poles accidents;

saving in transmission losses;

savings in power losses due to overhead outages;

savings in maintenance costs;

savings in tree pruning costs;

potential of increasing property values;

decline in electrocutions;

reduction in greenhouse gas emissions (due to reduced transmission


losses);

lowering of bushfire risks.

The most direct benefit noticed by the study was the decrease in motor vehicle
collisions that were estimated to cost between $105 and $160 million per year.
Table 2.8 summarises the best estimate of the direct benefits found by the
study [9].

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

32

Chapter 2: Literature Review

Table 2.8: Annual undergrounding benefits indicative


assortment [9]
Annual benefits (a)
($ per km of line)
Minimum
Maximum
1 358
2 793
18
1 531
35
1 120
0
292
1 411
5 736

Type of benefit
Reduced motor vehicle accidents
Maintenance costs.
Tree trimming
Reduced transmission losses
Total

Jey et al. [19], provided a comprehensive global survey about moving overhead
lines around the world. The results of this study which is given in Table 2.5
indicate that most countries around the world would prefer to move their
overhead power lines underground due to the following factors:

Increased public environmental awareness;

City planning with increased population;

Power frequent outage cost;

Reduced maintenance cost;

High transmission loss;

Electrocution prevention;

Bushfire risks reduction;

Reduced severity of auto accidents;

Reduction in cost of tree pruning;

Improved amenities;

Improved real estate value.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

33

Chapter 2: Literature Review

Some of the highlighted advantages of undergrounding include but are not


limited to:

Reliability effects, private and public advantages;

Reduction of outages and changes in restoration times;

Maintenance and operation cost reduction;

Reduced vegetation management costs.

In addition, this case study has conducted a survey which explored the
possibility of developing a sound and realistic standard which can be used to
evaluate and measure the advantages, limitations and costs of undergrounding
overheard power networks.

Finally, this study has concluded that the Florida Public Service Commission
(FPSC) along with many other utilities in Florida are keen on converting all of
their overhead

power networks to underground to achieve

optimum

performance and a better fault tolerance and improved amenities as well as a


storm resilient power grid. Furthermore, it finds that failure rates and reliability
modelling of the power network during storms, as functions of storm strength,
have not been attended to by any literature, whether academic or industrial, up
until year 2006. It also has emphasised the non quantifiable benefits of
undergrounding, such as the added value to real estate and the overall
improved landscape which ultimately leads to the increased GDP value of the
city [5].
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

34

Chapter 2: Literature Review

Transmission lines, as many property valuation surveys suggest, have a


negative impact on property values. Joint Legislative Audit and Review
Commission (JLARC) in reference [16] has reported that this can be as much
as 15%. Furthermore, the author founds that the decrease of property values
varied between 3-5% among single family residences near Henricos
transmission lines in Virginia, US. They added that the two main factors that
influence the decrease in these property values are: the perception that
transmission lines are unpleasant to the eye as well as the belief of some
people that EMF can cause health concerns. It is only fair to mention, that
amenities such as freeways, airports or landfills may decrease property values
just as much, if not more, than transmission lines.

However, despite earlier given factors, when most power utilities are asked why
they dont move their overhead lines underground, their response and prime
excuse would be the high cost associated with this technology and the already
highly congested underground corridors: with social utilities such as water
pipes, sewers, gas mains and telephones [19].

Johnson [15] argues that undergrounding overhead lines requires a hefty bill to
be paid, due to the estimated cost of up to 10 times what it costs to install
overhead power lines. When compared to overhead power systems,
underground power systems tend to have fewer outages, but these outages are
usually much longer than those of their overhead counterparts. In addition,
underground power systems are still susceptible to outages during extreme
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

35

Chapter 2: Literature Review

weather conditions.

Furthermore, Johnson

[15] strongly disputes

that

undergrounding adds no substantial benefits to the networks reliability, which


makes paying an enormous price tag totally unacceptable for such an exercise.

On the other hand, Johnson [15] believes some ad-hoc benefits of


undergrounding

do

exist

such

as

improved

aesthetics.

Despite

the

unquantifiable benefits of undergrounding, many communities are still


demanding the removal of their power lines because of the real and substantial
socio-economical benefits that are felt and harvested by improved aesthetics,
which in turn is echoed through the improved tourism figures and many more
cascading advantages. Therefore, the justification of undergrounding projects
can not be evaluated using the traditional economical matrices alone. Thus,
giant obstacles are often placed in front of public decision makers when
assigning budgets towards the aesthetic benefits of undergrounding.

2.1.3 Power outages nationally and internationally


Wild weather conditions have always renewed the demand for retrofitting the
overhead network to underground. After all, underground cables are mostly
immune from the weather elements that cause most of the outages in the
overhead network and they are less susceptive to the damage caused, for
instance, by wind, storm, ice or other wild weather conditions.

There have been many concerns expressed by various community groups in


New South Wales (NSW) - Australia for overhead lines. Power customers are
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

36

Chapter 2: Literature Review

worried about overhead lines during storms and bush fires as they are prone to
major service disruptions. Another concern shown by the general public for
overhead lines is the aesthetic look making them very messy and unsafe [10].

Overhead power lines have become a concern for many members of the
community in NSW. Particularly, the community is concerned about the
potential for overhead lines to be damaged in storms and bushfires, and power
outages resulting from this damage. The estimated ROI benefit is equivalent to
around 40% of the cost for the proposed undergrounding project [10].

In December 1999, severe storms destroyed large parts of the French power
network and as a consequence many power blackouts were encountered. In the
aftermath to this event, French authorities made the decision of undergrounding
many critical parts of the network to improve reliability and secure power supply
during abnormal weather conditions. There are other similar cases in the
European countries where extreme weather conditions have fast-tracked
undergrounding the overhead power network [13].

In the wake of the worst ice storm that occurred in the eastern Canadian region
around 10 years ago, HydroQubec decided to move their overhead lines
underground due to the sheer damage and the severity of the consequences of
this mighty storm which caused a major outage for prolonged periods of time
[19].

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

37

Chapter 2: Literature Review

Mother Nature will always continue to expose the vulnerabilities of overhead


power grids and the aforementioned cases of natural disasters are just some of
many that have taken place around the world. Therefore, one feels compelled to
mention more of these disasters: like the 14th August 2003 blackout due to
transmission line overheating and sagging on a tree, this blackout affected 12
American and Canadian states and provinces with an estimated US$14 billion
of economical loss. A similar scenario occurred in the same year on the 28th of
September in Austria, France, Italy and Slovenia where an outage affected 60
million people attributed to a tree flashover [19].

In the Canadian province of Ontario, power outages on overhead lines happen


on a regular basis due to the harsh windy weather wind faster than 80kph pattern. Surely, this sends a negative message to the general public in Ontario
and illustrates a clear negligence on behalf of the utilities, which are responsible
for providing a reliable power system. In addition, the population of that region
almost believes that these utilities did not have the interest of the customers as
their first priority [19].

In 1994, Maney [20] predicted that by 2000 many utilities are expected to
underground their distribution network. He claimed that the drives for such
moves include:

improved high quality underground cables;

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

38

Chapter 2: Literature Review

advanced techniques used in both detecting underground faults and


installing underground cables, for instance, direct burial or directional
boring.

Overhead lines have always been the preferred short term investment by the
utilities to meet their stockholders profit expectation, as overhead lines have
less complexity and overall easier installation and maintenance than
underground cables. Basically, overhead lines have always used the same
technology: bare wires insulated by ceramic insulators on the poles and air
used as insulation medium between wires. Nevertheless, the costs of
recovering overhead networks after storm damages are conceded to the
customers [20].

Unlike overhead lines, underground cables do not have the advantage of air
ventilation; therefore, they have to be installed prudently to be able to dissipate
the heat generated during operation. Heat dissipation in underground cables
has a great impact on the cable performance and its operating life span. When
overhead lines overheat they can sag and their rating might decline, meanwhile
when a cable overheats repeatedly its insulation might get damaged which in
turn leads to insulation breakage and ultimately a fault may occur. Thus,
planning engineers must exercise extra precision and skill when designing an
underground power network and take into consideration the cable heat transfer
problem for continued loading [20].

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

39

Chapter 2: Literature Review

Further to the aforementioned reasons, power utilities do not seem keen on


undergrounding because of the fact that there are no legal obligations to force
them to consider societal costs and of course there is no competition amongst
the utilities to foster such a move [20].

Furthermore, natural disasters were behind the outage which affected over 10
million people on the American east coast as a result of Hurricane Isabel and its
sheer destructive power. As a result a major power company in that region has
incurred a cost of US$128 million to restore power supply to the affected area.
Eventually, this cost was recovered one way or another and this was felt by the
average American customer [19].

In a survey completed in the late 1990s, it was stated that on average an


American consumer will experience more than 40 power outages a year. It did
not stop there: the matter has been getting worse especially in the past 6 years
[19].

A privately owned power utility has mentioned, in their annual report for 2003,
that on average they had one outage a day somewhere in their power grid; the
majority of these outages were attributed to severe weather, auto accidents and
animals contacting the wires [19].

Power outages have enormous affects on societies and their main


infrastructures. Loss of power means shortage in:
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

40

Chapter 2: Literature Review

drinking water supply;

heating or cooling;

sewage treatment;

interrupted transportation, communications and fire-fighting capability;

ability to evacuate high rise buildings in a timely manner, and many


other service disruptions.

Faults related to auto accidents cost the Australian utilities in excess of $250
million per year while the American counterparts pay in excess of US$5 billion
per year [19].

Maney [20], emphasises the brutal force of natural and weather related losses
such as ice, hail and other storms, e.g. Northwest Florida suffered from the
famous Alberto tropical storm in 1994 which caused a power outage that
affected over 1800 customers for several days. Similarly, in 1994 the Richmond,
VA, Times Dispatch reported five storms that were responsible for leaving
hundreds of thousands of customers out of power for weeks at a time. In
addition to the apparent cost of power outages, end customers such as
retailers, restaurants and food stores suffer from a massive loss due to the
spoiled food supplies in their freezers.

Another devastating effect of hurricanes was experienced in Florida due to


Hurricane Andrew: during the aftermath of this natural catastrophe it was initially
estimated that 1.4 million customers were left in the dark, 2 weeks later a local
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

41

Chapter 2: Literature Review

paper reported that 97,000 were still waiting for their power to be reconnected.
Furthermore, it was estimated that over 60% of overhead powerlines and 3% of
underground cables needed replacement. This clearly indicates the advantage
of underground over overhead in stormy and severe weather conditions [20].

In 2005 after hurricane Katrina, which ripped through New Orleans and
destroyed power systems throughout Louisiana and Mississippi, hurricane Rita
caused yet more destruction and mayhem not only across these regions but
extended to Arkansas and Texas. Entergy, the regional power supplier,
recorded outages to more than 1 million customers following Katrina as well as
more than 766,000 customers suffering black outs because of Rita. Entergy
claimed to have restored power to more than 75% of the affected regions in less
than three weeks when Rita first incapacitated the power supply to these
regions. However, more than 150,000 of those affected by Katrina were still in
the dark due to widespread flooding and landslides.

Entergy claimed to have employed over 10,000 contractors and crewmen to


carry out maintenance work on both hurricanes Katrina and Ritas affected
sites. Rita knocked down more than 6,120kms of transmission lines when it
reached its full destruction strength. Figure 2.1 shows the devastating effects of
hurricane Katrina [21].

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

42

Chapter 2: Literature Review

Figure 2.1: The devastating effects of wild weather hurricane Katrina


2005 [21]

Although, underground transmission lines are less inclined to be affected by the


elements such as lightning, high winds and storms, the advantage of having
them can be sometimes over emphasised.

Virginias State Corporation

Commission (SCC) claimed that almost all the damage that occurs to overhead
lines usually takes place around the distribution level rather than the
transmission level.

According to SCC, overhead lines are preferable for

reliability reasons, as underground lines have proven to require longer repair


times than their overhead counterparts [16].

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

43

Chapter 2: Literature Review

2.1.4 Environmental Issues concerning power networks


The relationship between overhead lines and underground cables has been
widely investigated in reference [16]: a study was carried out by JLARC about
the policies and criteria used by SCC. This study evaluated the feasibility of
moving overhead transmission lines underground in the state, including costs
and the impact of such a move on the property values. The study concluded
that the technologies are readily available but it would be an expensive exercise
in average priced-areas (4 to 10 times more expensive than overhead).
However, it could be considered a cheap exercise, in fact cheaper than
overhead lines when the land value is extremely high because it would then
require smaller rights-of-way.

SCC has demanded that utilities address potential environmental impacts in


their transmission line applications. Residential property owners, environmental
groups, and local governments have often promoted underground construction
as the preferred way to address concerns regarding the environmental impact
of transmission lines. However, the SCC did not find that undergrounding was
necessary in order to diminish these concerns and undergrounding was only
ordered where a viable overhead right-of-way did not exist or where the party
requesting the undergrounding agreed to wear the cost [16].
Another worthwhile shining example of underground power cables would be the
Salt River project in Phoenix, Arizona, where all services moved underground;
they have been determined to move more than 100 km of overhead cables
underground every year [19].
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

44

Chapter 2: Literature Review

Further to the aspects discussed earlier, the negative impact of overhead may
include the use of wood poles which are treated with highly toxic chemicals that
could leak into the grounds and hence affect the surrounding soil and the food
chain which is grown in the area. Thus, the move to underground sees a
significant reduction in the use of these poles. The extent of the environmental
damage which is caused by these toxic poles does not stop at contaminated
soils, it reaches beyond that as it is evident in Florida, where it was reported to
FPSC that 20 public and private wells including the main well region of Miami
city were contaminated due to the high concentration of the toxic chemicals
which were released by the wood pole treatment plants. This massive
accumulation of mutagenic compounds has adverse effects on the populations
health and well being, which are yet to be determined by the experts [20].

The public seems to be more aware of the obvious advantages that


undergrounding can bring with it, but the lack of official support from the
relevant authorities has left the private citizen no choice but to form activists
groups. The public believes that through court actions they will be able to collect
a reasonable amount of data for analysis and to further support their case
against the giant utilities, which are to date still reluctant to engage directly with
the community to solve this problem. Of course, having a national policy would
be seen as a victory to these groups and would enable the public to reap the
rewards of such policy by forcing utilities to take action towards more realistic
in-depth cost-benefit analysis of undergrounding urban power lines [20].

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

45

Chapter 2: Literature Review

2.1.5 Health and safety issues concerning power networks


In the United States, the growing demand is clearly exhibited by motivated
activists who constantly rally and lobby giant utilities and government bodies
when they propose new overhead powerlines. In other words, these organised
groups argue that they are rejecting the new overhead powerlines on the basis
of health issues due to the exposure to electromagnetic fields as well as their
effect on property devaluation. Some of these non-government organisations
(NGOs) which are dedicated to achieving a safer power delivery through
undergrounding include:

The Electromagnetic Radiation Alliance (national and international)

Citizens Opposed to Unsafe Power (PA)

Alliance to Limit Electromagnetic Radiation Today (CT)

Coalition for Safe Electric Power (VA)

Parents Against an Unsafe Environment (PA)

Michigan Safe Energy Fund (MI)

Concerned Citizens for Power Line Safety (FL)

Citizens for Power Lines Underground etc.

In reference [20], the authors believe that power utilities are not admitting in
public about the existence of safer methods of power delivery, such as
undergrounding, merely for legal reasons as they do not wish to end up
defending an overwhelming number of potential lawsuits in court rooms across
the country.
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

46

Chapter 2: Literature Review

The rising concern about EMF generated by transmission lines is often reported
as a main cause of childhood leukaemia. However, rigorous scientific research
has been unable to determine if there is a fundamental link between EMF and
cancer, particularly leukaemia, nevertheless, statistically frequent correlation
has been observed[16].

2.2 Conclusion
This chapter provided the necessary background in the transition of overhead
lines to underground for distribution and transmission power networks. Both
benefits and limitations have been explored for underground and overhead
technologies. Various cable technologies have also been extensively discussed.
From the extensive research carried out, it is agreed by the multinational power
engineers and researchers, that underground transmission cabling provides
enormous benefits compared to its predecessor technology of overhead lines.
However, the overhead technology is still dominating and is in use all over the
world. The next chapter dedicatedly elaborates the comprehensive overview of
overhead power networks along with its structure.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

47

Chapter 3: Overhead Power Networks

CHAPTER 3
OVERHEAD POWER
NETWORKS
3.0 Introduction
The literature and research findings of power network technologies were
presented in Chapter 2. The comprehensive overview of the overhead power
network and its structure is presented in Section 3.1. The reliability issues of the
power network were examined by investigating a section of Melbournes
overhead power network which is presented in Section 3.2. As there are various
types of conductors available in the market, Section 3.4 elaborates many types
of overhead power line conductors to compare with the underground cables.
Load flow analysis and power losses in overhead lines are presented in
Sections 3.5 and 3.6 respectively as understanding this analysis is vital to
comprehend various models developed which will be discussed in the
forthcoming chapters. Concluding remarks are provided in the final section of
this chapter.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

48

Chapter 3: Overhead Power Networks

3.1 Overhead Power Network Overview


Overhead lines employ a free and natural insulation medium - Air - to insulate
long exposed conductors. Overhead lines are almost always favoured over their
much

more

expensive

counterpart,

underground

cables,

due

to

the

unavailability of inexpensive alternatives to supply electricity, especially at high


voltage levels [22].

In general, costs of both construction types (overhead and underground) are


greatly affected by many factors, such as, material and labour as well as soil
and topographical factors. However, in certain circumstances underground
cables tend to be favoured over overhead lines due to the route condition. For
instance, constructing an underground cable in a green field area is more
feasible and cost justifiable than constructing overhead lines [22].

Overhead conductors are governed with strict rules and regulations, such as
clearance from ground and nearby buildings, including easement and impact of
EMF as well as swing of conductors to allow wind blowing across the lines at
specific speeds. Usually, the line height is determined by the maximum
conductors sag between towers.

When designing overhead power grids,

engineers should consider these factors as well as extreme weather conditions


with high current loading in hot temperatures or cold weather conditions with
low load and their implication for conductors stress levels [22].

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

49

Chapter 3: Overhead Power Networks

The common type of overhead line is an Aluminium-Conductor Steel-Reinforced


(ACSR) conductor, which is used usually for LV and MV distribution networks
that require small conductor sizes. This type of overhead line is fabricated by
winding Aluminium wires that conduct the current around a core of steel strands
in which they enforce the mechanical strength of the entire conductor.
Overhead lines require some sort of support to keep them off the ground and
have clearance required for their operation. They can be hung on a selection of
types of supports: most obvious for LV and MV are wooden, concrete or steel
poles; meanwhile for higher voltages, steel towers are the typical construction
[22].

In addition to double-sided line clearance, many types of insulated overhead


lines are commonly used in bushy topography to prevent physical contact with
trees or to avoid conductor clashing which leads to a short circuit and can
instigate a fault. Therefore, insulated overhead lines are considered safer than
exposed lines [22].

In the UK and the USA, individually insulated conductors are commonly used
for distribution, while in some parts of Europe, such as France and Italy, selfsupported aerial cables are widely employed for distribution services. There are
other types of constructions which utilise an insulated neutral instead of bare
wires. Naturally, insulation of MV lines is more costly than LV; therefore the
constructions mentioned earlier are only feasible under certain situations. Thus,

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

50

Chapter 3: Overhead Power Networks

covered conductors for MV areas are more price-smart solutions as far as


utilities are concerned [22].
In HV levels there are a couple of conductor types that are commonly used for
transmitting 36 kV and higher, such as the ACSR and All Aluminium Alloy
Conductor (AAAC). However, Aluminium Conductor Alloy Reinforced (ACAR)
and All Aluminium Alloy Conductor Steel Reinforced (AACSR) are less
commonly used than ACSR due to the significant price difference. ACSR has
many benefits which made it popular in the past. Some of these advantages
are: mechanical strength, excellent manufacturing capacity (which effectively
meets the market demand) and its cost effectiveness [23].

3.2 Reliability Issues in Power Network


There is an on-going demand from consumers for a more reliable and
economical power supply. Many factors contribute to determining the reliability
of a power network: design, construction, operation and maintenance which
have their combined input into the overall power network reliability. Moreover,
liberalisation of the electricity sector along with adopting new technology
commercially puts great pressure on electricity utilities to operate not only
economically but reliably and securely too.

The main causes of overhead power transmission and distribution network


interruption are in fact unplanned external causes, like storms, bushfires,
lightning, trees, animals, vehicle accidents and vandalism. Interruptions can

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

51

Chapter 3: Overhead Power Networks

also be caused by equipment and line or cable failure due to overload and
ageing. However, overhead networks are more vulnerable to the external
causes; adding to that, in general, the maintenance works required for overhead
networks are about twice the number compared to the underground power
networks maintenance works.

Frequent and major power interruptions cause many concerns. Some of them
relate to the power systems security and reliability. Ageing assets can play a
big role in more frequent power interruptions (most of the outages and
disruption usually occur on the distribution part of the power network).

According to Mutton et al. report [3], 85% of all Customer Minutes Off-Supply
(CMOS) results from faults on the 22kV distribution system. The low voltage
network to a consumers property accounts for only 4% and, although faults at
zone substations and on sub transmission circuits impact on a large number of
customers, they account for only 11% of customer minutes off-supply. The top
three causes of outages account for 50% of all outages (Trees 23%, No
Identified Cause 14% and Planned Outages 13%). Lightning, animals or birds
and high voltage conductor failures each account for around 7%. In 1999, trees
caused more than 80% of faults on the two worst short rural 22kV feeders
(Belgrave 24 and Kinglake 2). Figure 3.1 shows the percentage of top causes
for outages during 1997 to 1999 by CMOS of a local power distribution network
SP AusNet (formerly known as TXU) [3].

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

52

Chapter 3: Overhead Power Networks

Figure 3.1: Average CMOS over three years [3]

3.3 Types of Overhead Power Line Conductors


Overall, there are a number of different overhead line conductor types which are
usually installed by spacing between the individual conductors in order to
acquire various voltage ratings. The following are the three major types [24]:

AAC - All Aluminium Conductor


AAAC - All Aluminium Alloy Conductor
ACSR - Aluminium Conductor Steel Reinforced

Each of these overhead conductors has its own features, advantages and
disadvantages. Table 3.1 summarises some of these features. Moreover, these
features constitute many of the factors that an engineer would have to take into
account when determining the type of conductors required for designing an

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

53

Chapter 3: Overhead Power Networks

overhead network. A short list, which highlights some of these important factors
is as follows [24]:

Section length
The length of an overhead line can be decided with the following factors
taken into account: terrain of line easement, quantity and quality of
conductors, local climate conditions, nature of load and the required
safety procedures.

Degree of sagging
Degree of sagging is determined by measuring the catenary curve which
takes into account the ratio of line span and weight as well as the
structure required to support the conductor above the ground.

Daily conductor stress


The daily conductor stress is the unit which measures the variation of
conductor stress under the normal operation load at or around the mean
temperature with minimal or no high demand on existing load.

Surrounding environment temperature


Local climate has an explicit impact on the conductor temperature. Thus
evaluating the actual operating temperature of a conductor is considered
as an essential exercise in order to enhance conductor capacity
utilization and mitigate the risk of sagging.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

54

Chapter 3: Overhead Power Networks

Table 3.1: Overhead line conductors - types and features - [24]


Cable

Category

Pros

Cons

AAC
All Aluminium
Conductors;
comprises a single
or multiple strands
made of hard drawn
1350 Aluminium
Alloy.
1. excellent
corrosion
resistance
2. conductor of
choice in coastal
areas
3. heavily used in
urban areas as
spans are short
but high
conductivity is
required
10. low strength-toweight ratio
11. limited use in
transmission lines
and rural
distribution
because of the
long spans

ACSR
AAAC
Aluminium Conductor A high strength
Steel Reinforced;
Aluminiumcomprises a solid or
Magnesium-Silicon
stranded steel core
Alloy cable;
surrounded by one or
more layers of
strands of 1350
aluminium
4. Mainly used for
7. offers excellent
overhead ground
electrical
wires
characteristics
5. extra long spans
8. excellent sag6. makes the best
tension
candidates for river
characteristics
crossing etc
9. superior
corrosion
resistance

12. inner core wires


13. limited use
may require zinc
14. thermal
coating (galvanized)
coefficient of
steel
expansion is
greater ACSR

3.4 Load Flow Analysis


Load flow analysis, by and large referenced as load flow, is the most important
tool used in power system analysis, design and planning. It is an essential tool
power utilities use for planning, operating, efficiency and power exchange.
Power flow is also necessary for other network situations, for instance, transient
stabilities or for contingency scenarios.
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

55

Chapter 3: Overhead Power Networks

acload-flow analysis is essential when determining the capability of a


distribution network under different network configuration and loading
conditions. A typical report of the load flow analysis should accommodate the
losses of various parts of the network such as: infeed power sources whether
generated within the network or transformer substations; infeed obtained from
higher voltage network. Generally speaking, carrying out this type of analysis
on MV and LV networks is a much simpler task due to their radial
configuration than its HV counterparts. However, radial networks tend to have
a very high number of load points thus obtaining readings on individual points is
restricted to the annual unit consumption at a known LV level [22].

In addition to system losses, load flow analysis is highly affected by the


characteristics and loading of each node point at each section of the network.
Microprocessor units are usually used at incoming supply and outgoing feeders
to complement the load data necessary to carry out the system analysis, due to
the fact that only a small amount of load data is collected from maximum
demand indicators at MV networks [22].

Correction factors are commonly used in system analysis when carried out on
MV and LV networks in order to achieve flawless results with unrealistically very
high value for the total current flows. This is merely due to the fact that in some
cases, the maximum possible demand of customers appliances is hard to
estimate as their ratings and quantities are simply unknown. This is where
lowering the estimated rate of all loads becomes vital so that the simultaneous
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

56

Chapter 3: Overhead Power Networks

maximum demand of the group of loads equates to the total of individual loads.
Lowering the rating is usually achieved by applying a coincidence factor which
is defined as the ratio of the simultaneous maximum demand of a group of load
points to the sum of the maximum demands of the individual loads [22].

3.5 Conclusion
For decades, power has been transmitted via a relatively low cost medium,
commonly known as overhead lines. Since then, substantial transformations
have been occurring to improve the reliability of overhead networks. A load flow
technique is often employed to analyse and design an improved overhead
power network. Chapter 3 has provided an overview of overhead power
networks.

This chapter has also extensively explored overhead power networks various
aspects as well as the major factors that form the core requirements of a
reliable power network. Various conductors used in overhead lines have also
been discussed. As power loss is a major concern for transmission systems, an
elaborative study on power losses in overhead lines has also been included.
The next chapter looks at the Victorian overhead power network in an attempt
to efficiently design an underground network for Victoria.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

57

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

CHAPTER 4
DEVELOPMENT AND
ANALYSIS OF VICTORIAN
OVERHEAD POWER NETWORK
MODEL
4.0 Introduction
Further to the general overview of overhead power networks presented in
chapter 3, this chapter discusses and presents the existing Victorian overhead
network model which is based on sub-models developed separately then
combined together to form the overall overhead model. A load flow analysis will
be carried out on this model where the results obtained from this study will be
further verified and used as a bench mark to validate future models that will be
developed in following chapters.

It is of great significance to mention that the overhead model was developed


using two industrial power software applications; this step constitutes an integral

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

58

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

part of this study so that it provides a mechanism for the comparison,


verification and validation of the obtained results.

4.1 Power Loss in Overhead Lines


Power losses in overhead lines are the representation of the amount of lost
power from the generated power that did not deliver to load. These losses are
attributed to the resistance of various components of the power network mainly
transmission lines. Losses depend on the network conditions such as loading,
network topology, type of network, location of generation and load as well as
power demand. The average power loss in transmission lines would be 3% of
the transmitted power, with maximum loss occurring at peak power demand.
Given the nonlinear nature of losses, it will be a tricky task trying to put a figure
of how much the loss can cost. Consequently, measuring losses directly can
not be performed. On the other hand power flow analysis utilised by computer
software can calculate and give very close indication about exact transmission
losses. The results obtained from such software will also give comprehensive
information about the losses associated with particular loads or customer [25].

Overhead transmission lines have traditionally played a major role in delivering


power from remote generation plants, where energy sources are located away
from loads, with distances of over hundreds of kilometres. As technology
advances, various developments have identified the core weakness of
transmission technologies/capabilities. In todays competitive era, energy has
become the prime commodity for developed and developing countries. For
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

59

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

decades, power engineers had overlooked the importance of transmission


capabilities along with its losses. Approximately 70% of the energy is lost in the
process of generation and transmission; underground transmission cabling
technology brings new hope in substantially saving transmission losses.

Despite the simplicity and low cost of overhead transmission lines, they induce
reactive power to the power network. This reactive power is proportional to the
length and load of transmission line. Therefore more reactive power is
generated. Consequently, series compensation can be substantially utilised to
offset the generated reactive power [26].

Please refer to Appendix A for more information about power loss calculation.

4.2 General Overview of Victorian Overhead


Power Network
Overhead lines have been a dominant transmission medium in Australia for
many years, mainly due to their simple structure, lower solution cost, and ease
in locating and repairing faults. Depending on the nature of the fault, overhead
line faults may last from a few milliseconds to days, with the longer duration
caused by extreme weather, bush fires and other abnormal conditions. It is very
likely that overhead line faults can strike 100 times more than underground due
to external causes such as wind loading, lightning surges and tracking on dirty

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

60

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

insulators [27]. Most of the faults last only momentarily, which are intercepted
easily by power system protection techniques.

There are a number of power distribution companies in Victoria. Citipower and


Powercor's combined networks deliver electricity to nearly a million customers
throughout Victoria, from central Melbourne, west to the borders of South
Australia to New South Wales and, according to the companys latest report, it
operates the most reliable electricity network in Australia.

Citipower Subtransmission lines are configured in an efficient manner to supply


its zone substations, in which the lines are connected to the terminal stations
using loop and/or meshed topology. This redundancy based configuration of
lines that supply each zone substation provides extra continuity and security of
electricity supply in the case of individual lines being unavailable due to
maintenance or disruption of service.

Citipower owns a power network that consists of around 61,000 poles and more
than 4,270km of overhead lines, service lines and over 2,220km of underground
cables. Overall, Citipower runs 38 zone substations, 83 subtransmission lines,
around 3200 distribution substations and 600 distribution feeders. Moreover,
Citipower utilises zone substations to transform subtransmission line voltages
in Victoria 66kV or 22kV - down to distribution voltages which are 11kV or 6.6kV
in addition distribution feeders are used to supply the distribution substations
[28].
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

61

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Citipower must plan its distribution network future expansion due to the
Victorian regulation which clearly states that planning the augmentation of
distribution networks is the business owners responsibility. Augmentation
planning is usually carried out to provide efficient, secure and reliable supply to
customers. Thus Citipower takes its augmentation planning very seriously to
match its network capacity which is mostly motivated by geographical swing
due to new urban development as well as customer demand. Figure 4.1 exhibits
the scope of the Citipower network of the areas supplied by each zone
substation. It is worth mentioning that this map is not intended to show
overlapping between adjacent zone substations as it is designed to show zone
supply areas.

Overhead network data were obtained from Citipower and its publications from
the public domain. Some of network data were not available; therefore the
following assumptions were made for the development of the network:

1. Lines to be treated as a single section line although they might consist of


multiple section to simplify the models.

2. Summer circuit rating has been used in load flow analysis which has a lower
line rating than winter to accommodate for worse case scenarios.

3. Where power factor is not given, 85% was used for residential load and 95%
used for industrial load.
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

62

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

4. n-1 (n elements in service) redundancy configuration has been applied to all


models and sub models to maintain Citipower n-1 network configuration; in
other words if an individual subtransmission line was out of service the
supply to its zone substation would not be lost.

5. No corrective measures such as opening or closing circuit breakers or phase


shifters regulating, which normally carried out by power utility for n-1
redundancy configuration have been accommodated for in the simulation.

Appendix B lists Citipower zone substations information, where as Appendices


C and D show West Melbourne Terminal Station (WMTS) sub-transmission
lines information and single line diagram respectively.

Separate sections of the Citipower power network were developed individually


for each terminal station; separate sections for 66kV and 22kV voltage levels
were created using Advanced Power Flow Program EDSA power tool. The
overhead network model was developed in order to perform load flow analysis
to calculate the overall power losses in the entire network feeders. The results
obtained from the simulation are based on normal operations or steady state
conditions as well as abnormal or at fault conditions. The obtained results were
used as a benchmark to compare the other setup and configuration results of
the network.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

63

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Figure 4.1: C-itipower zone substation and sub-transmission system [28]

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

64

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

4.3 WMTS 2007 Overhead Base Model


This model comprises of multiple sub-models; these include the 66kV and 22kV
WMTS terminal station loops which are presented in Figure 4.1. After obtaining
the flow analysis of the two voltage levels, a submission of all power losses,
which basically represents the loading demand of the WMTS for the year 2007,
is identified to undergo further analysis.

4.2.1 EDSA WMTS 66kV overhead base sub-model


The configuration of this base sub-model closely matches the existing Citipower
section of the network with zone substation loading obtained from the
companys 2007 planning report [11]. Additionally, WMTS 66kV overhead
network parameters for 2007 were obtained from Citipower annual report, then
used to develop and analyse this sub-model. Figure 4.2 shows the WMTS
terminal station 66kV section of the network base sub-model.

It can also be noted that a summary of the load flow analysis results is situated
close to the bus, line or transformer in Figure 4.2. The summary includes an
arrow that reveals the direction of power flow. Real and reactive power are also
shown close to each bus, line or transformer in terms of positive values, which
denote whether the power flow direction is out from the bus and vice versa or
whether negative values are applied for power flow direction in the bus.
Accordingly, summing up of the four power flow values for each line or feeder
will provide real and reactive power losses in the specific line.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

65

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Figure 4.2: WMTS 66kV overhead base sub-model


Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

66

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Another observation that can be drawn from the Figure 4.2 is that sections or
elements of the network are colour coded according to their loading in normal
operating conditions;

Bus voltage violation:

Under limit or less than 95% of rating is displayed in blue

Range between 96% - 104% of rating is displayed in black

Over limit or higher than 105% of rating is displayed in Red colour

Current violation:

Under limit or less than 50% of rating is displayed in green colour

Range between 51% - 99% of rating is displayed in black colour.

Over limit or higher than 100% of rating is displayed in orange colour.

Transformer violation:

Under limit or less than 50% of rating is displayed in light blue colour.

Range between 51% - 99% of rating is displayed in black colour.

Over limit or higher than 100% of rating is displayed in yellow colour.

Table 4.1 illustrates the bus results of flow analysis performed on the WMTS
66kV sub-model. The table also lists bus parameters including name, real and
reactive generated powers, real and reactive static loads and load flow results
from which the real and reactive power losses are obtained with bus current
rating and power factor incorporated.
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

67

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Table 4.1: WMTS 66kV overhead EDSA load flow bus results
Bus Info Generation Static Load
Load Flow Results
--------------- ----------------- ------------------------ ----------------------------------------------Name
MW MVAR MW MVAR To Bus Name MW MVAR Amp %pf
-------------- ------- -------- ------- --------- ------------------- --------- ---------- ------- -------Sub JA 66 0.00 0.00 0.00 0.00
Sub LQ 66
28.77 28.60 356 70.9
Sub JA 66 0.00 0.00 0.00 0.00
Sub LQ 66
28.77 28.60 356 70.9
Sub VM 66
3.77
3.66 46 71.7
WMTS 66
-26.23 -24.58 316 73.0
WMTS 66
-26.28 -24.55 316 73.1
Sub LQ 66 0.00 0.00 0.00 0.00
Sub JA 66
-28.76 -28.55 356 71.0
Sub VM 66
-16.65 -13.76 190 77.1
Sub VM 66
-14.45 -12.88 170 74.7
Sub NC 66 0.00 0.00 0.00 0.00
Sub WB 66 -2.32 -2.60 31 66.5
WMTS 66
-8.29 -7.47 98 74.3
Sub VM 66 0.00 0.00 0.00 0.00
Sub JA 66
-3.77 -3.66 46 71.7
Sub LQ 66
16.66 13.78 190 77.1
Sub LQ 66
14.46 12.90 170 74.6
Sub W 66
12.31 11.26 147 73.8
Sub WA 66
13.50 12.36 161 73.7
Sub WA 66
13.45 12.34 160 73.7
WMTS 66
-32.94 -24.38 360 80.4
WMTS 66
-24.76 -22.59 294 73.9
WMTS 66
-41.35 -40.66 509 71.3
Sub W 66 0.00 0.00 0.00 0.00
Sub VM 66
-12.28 -11.25 147 73.7
Sub WA 66
12.28 11.25 147 73.7
Sub WA 66 0.00 0.00 0.00 0.00
Sub VM 66
-13.47 -12.34 161 73.7
Sub VM 66
-13.43 -12.32 160 73.7
Sub W 66
-12.28 -11.25 147 73.7
Sub WB 66 0.00 0.00 0.00 0.00
WMTS 66
-10.67 -10.31 130 71.9
Sub NC 66
2.32
2.60 31 66.5
WMTS 66 0.00 0.00 0.00 0.00
Sub WB 66
10.69 10.39 130 71.7
Sub JA 66
26.26 24.74 316 72.8
Sub JA 66
26.31 24.71 316 72.9
Sub NC 66
8.32
7.55 98 74.1
Sub VM 66
32.99 24.56 360 80.2
Sub VM 66
24.80 22.75 294 73.7
Sub VM 66
41.40 40.93 509 71.1
-------------------------------------------------------Total losses 0.36
1.23

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

68

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

The load flow results obtained in Table 4.1 are summarised in Table 4.2. The
table shows, in two different columns, the power delivered to and from the line
and in the last two columns it lists the power difference or power losses. The
total real power losses were found to be 352.5 kW; in addition total reactive
power was found to be 1,222.3 kVAR.

Table 4.2: WMTS 66kV overhead lines losses


Branch
From -> To Flow To -> From Flow Losses
----------------- ------------------------ ------------------------ -------------------------------------Name
MW
MVAR
MW
MVAR
kW kVAR
---------------------- ------------- ----------------- ------------- ----------------- -------- ----------LQ-JA
-28.759 -28.552
28.770
28.598
10.6 46.4
VM-JA
-3.769
-3.663
3.770
3.665
0.3
1.3
VM-LQ1
16.661
13.776
-16.655 -13.757
6.1
18.8
VM-LQ2
14.458
12.898
-14.454 -12.881
4.8
17.0
VM-W
12.308
11.265
-12.284 -11.250
24.2 14.6
VM-WA1
13.495
12.361
-13.466 -12.343
29.1 17.6
VM-WA2
13.454
12.337
-13.425 -12.320
29.0 17.5
WA-W
-12.282 -11.249
12.284
11.250
2.4
1.4
WB-NC
-2.317
-2.600
2.318
2.604
1.6
4.7
WMTS-JA1
26.261
24.741
-26.232 -24.583
28.9 157.6
WMTS-JA2
26.311
24.708
-26.282 -24.550
29.2 157.6
WMTS-NC
317
7.546
-8.289
-7.470
28.1 75.7
WMTS-VM1
32.993
24.560
-32.936 -24.376
57.4 184.7
WMTS-VM2
24.796
22.746
-24.765 -22.591
31.2 155.1
WMTS-VM3
41.396
40.934
-41.352 -40.664
44.0 270.1
WMTS-WB
10.692
10.390
-10.666 -10.308
25.6 82.2
--------------------------------------------------Total power losses
352.5 1222.3

WMTS 66kV lines real and reactive power losses are shown in Figure 4.3; the
figure demonstrates that the power losses are line impedance dependents, as it
can be observed that although line WMTS VM3 is shorter in length than its
counterpart WMTS VM2, however, its real and reactive power losses are
much higher and the clear reason for that is its higher impedance.
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

69

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

WMTS 66kV Overhead Lines Losses


300

250

200

150

100

50

LQ

-J
A
VM
VM JA
-L
VM Q1
-L
Q
2
VM
VM -W
-W
VM A1
-W
A2
W
A
W W
B
W
M -NC
T
W S -J
M A1
TS
W -JA
M
2
W TS
M -N
TS C
W
M VM
TS 1
W
M VM
TS 2
W -V M
M
TS 3
-W
B

kW
kVAR

Figure 4.3: WMTS 66kV overhead lines power losses

4.2.2 PSS/E WMTS 66kV overhead base sub-model


The configuration and parameters of this base sub-model with the year 2007
loading demand has been obtained directly from Citipower as a file. The file was
then simulated using PSS/E software. Table 4.3 shows the results of this
simulated sub-model.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

70

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Table 4.3: PSS/E WMTS 66kV overhead lines losses


FROM
SHUNT
TO
BUS NAME MW/MVAR BUS NAME
WMTS 66
0.00
JA 66
JA 66
0.00
WMTS 66
WMTS 66
0.00
JA 66
JA 66
0.00
WMTS 66
WMTS 66
0.00
NC 66
NC 66
0.00
WMTS 66
WMTS 66
0.00
VM1 66
VM1 66
0.00
WMTS 66
WMTS 66
0.00
VM2 66
VM2 66
0.00
WMTS 66
WMTS 66
0.00
VM3 66
VM3 66
0.00
WMTS 66
WMTS 66
0.00
WB 66
WB 66
0.00
WMTS 66
JA 66
0.00
LQ2 66
LQ2 66
0.00
JA 66
JA 66
0.00
VM2 66
VM2 66
0.00
JA 66
LQ1 66
0.00
VM1 66
VM1 66
0.00
LQ1 66
LQ3 66
0.00
VM3 66
VM3 66
0.00
LQ3 66
W1 66
0.00
VM3 66
VM3 66
0.00
W1 66
W1 66
0.00
WA3 66
WA3 66
0.00
W1 66
NC 66
0.00
WB 66
WB 66
0.00
NC 66
VM1 66
0.00
WA1 66
WA1 66
0.00
VM1 66
VM2 66
0.00
WA2 66
WA2 66
0.00
VM2 66
Total power losses

LOAD FLOW
RATING
kW
kVAR
AMPS %I SET A
38297.8
17654.7 366
-38260.2
-17488.3 374
38297.8
17654.7 366
-38260.2
-17498.3 374
13755.9
7138.1
135 28 480A
-13725.8
-7044.4
136 28 480A
89382.3
58078.7 926
-89315.5
-57891.7 927
35641.6
18355.5 348
-35599.9
-18135.8 352
90188.2
56242.5 924
-90150
-56045.4 939
17937.3
9644.2
177 37 480A
-17891.5
-9494.4
183 38 480A
29.317
-28.898
366
-29.212
-28.852
366
5036.1
8257.6
84
-5035
-8253.1
84
-49740.8
-32777.1 523
49744
32789.3 517
-50143.1
-32107.2 529
50186.3
32134.9 521
-21787.2
-13855.3 230
21840.2
13877.7 226
21787.2
14595.3 230
-21781.7
-14591.6 230
-3965.1
-2363.9
42 10 430A
3967.8
2369.2
40 9 430A
21511.6
13316.7 222
-21458.4
-13254.1 226
22221.5
14374.3 231
-22193.9
-14320.5 235
487.405

1362.346

The results in results Table 4.3 were compared to the results obtained earlier
from Table 4.2 and it is fair to conclude that there is a close similarity between
real and reactive power losses in simulation results obtained from both power

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

71

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

software applications. Thus, the validity of the WMTS 66kV base sub-model
developed in Section 4.1.1 has proven to be correct. (i.e. EDSA and PSSE)
because it has exhibited many similarities with a degree of discrimination in
minor tolerance. Figure 4.4 shows results obtained from the comparison of
WMTS 66kV power losses, again acquired from both EDSA and PSSE
software.

WMTS 66kV Overhead Lines Losses


300

250

200

150

100

50

LQ
-J
VM A
VM -JA
-L
VM Q 1
-L
Q
VM 2
VM -W
-W
VM A
1
-W
A2
W
A
W -W
W BM N
T C
W S-J
M A
T
1
W S-J
M A2
W TS
M -N
T
W S- C
M VM
T
W S- 1
M VM
TS 2
W -V
M M
TS 3
-W
B

0
EDSA kW
PSS/E kW
EDSA kVAR
PSS/E kVAR

Figure 4.4: WMTS 66kV power losses comparison of both EDSA and
PSS/E

4.2.3 EDSA WMTS 22kV overhead base sub-model


The configuration of this base sub-model has many similarities to the WMTS
66kV sub-model exhibited earlier in Section 4.2.1, which closely matches the
existing Citipower section of the network. Again the 2007 zone substation

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

72

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

loading demand parameters were acquired from the companys 2007 planning
report.

Figure 4.5 shows the WMTS terminal station 22kV section of the

network base sub-model.

The developed sub-model in Figure 4.5 shows the WMTS terminal station 22kV
section of the network base sub-model and a load flow analysis on the model
was carried out to obtain power loss figures. Again Figure 4.5 shows the
summary of the load flow analysis results situated close to the bus, line or
transformer.

The lists of bus parameters in Table 4.4 of the WMTS 22kV sub-model
comprises of name, real and reactive generated power, real and reactive static
load and load flow results where real and reactive power losses can be
obtained with the bus current rating and power factor incorporated as well.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

73

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Figure 4.5: WMTS 22kV overhead sub-model


Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

74

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Table 4.4: WMTS 22kV overhead EDSA load flow bus results
Bus Info
Generation Static Load Load Flow Results
------------------- ----------------- ----------------- -------------------------------------------------Name
MW MVAR MW MVAR To Bus Name MW MVAR Amp %pf
------------------- ------- ---------- ----- -------- -------------------- -------- --------- ------ ------Sub BSBQ 22 0.00 0.00 0.00 0.00 Sub J 22
1.56 1.1 50 81.8
WMTS 22
-8.19 -5.57 261 82.7
WMTS 22
-7.67 -5.22 245 82.7
Sub DA 22
0.00 0.00 0.00 0.00 WMTS 22
-6.88 -4.63 218 83
WMTS 22
-6.79 -4.57 215 83
Sub J
0.00 0.00 0.00 0.00 Sub BSBQ 22 -1.56 -1.1 50 81.8
Sub LS 22
-8.12 -5.58 260 82.4
WMTS 22
-7.84 -5.35 251 82.6
Sub LS 22
0.00 0.00 0.00 0.00 Sub J 22
8.14 5.62 260 82.3
WMTS 22
-12.42 -8.4 394 82.8
WMTS 22
-8.67 -5.87 275 82.8
WMTS 22
0.00 0.00 0.00 0.00 Sub BSBQ 22 8.22 5.63 261 82.5
Sub BSBQ 22 7.71 5.27 245 82.5
Sub DA 22
6.89 4.65 218 82.9
Sub DA 22
6.8
4.59 215 82.9
Sub J 22
7.88 5.42 251 82.4
Sub LS 22
12.44 8.44 394 82.8
Sub LS 22
8.68 5.89 275 82.8
----------------------------------------------------Total losses 0.18 0.32

The load flow results obtained in Table 4.4 are summarised in Table 4.5. The
table shows, in two different columns, the power delivered to and from the line
and in the last two columns it lists the power difference or power losses. The
total real power losses were found to be 207.5 kW; in addition the total reactive
power was found to be 311.7 kVAR.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

75

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Table 4.5: WMTS 22kV overhead lines power losses


Branch
From -> To Flow
To -> From Flow
Losses
------------------------------------------------------ --------------------------------------------------Name
MW
MVAR
MW
MVAR
kW kVAR
---------------------- ------------- ----------------- ------------- ----------------- -------- ----------BSBQ-J
1.561
1.098
-1.56
-1.096
1.3
1.9
J-LS
-8.115
-5.58
8.145
5.624
29.4 44.2
WMTS-BSBQ1 8.223
5.626
-8.186
-5.569
37.5 56.4
WMTS-BSBQ2 7.709
5.274
-7.674
-5.221
35.2 52.9
WMTS-DA1
6.887
4.648
-6.875
-4.629
12.4 18.7
WMTS-DA2
6.803
4.59
-6.791
-4.572
12.3 18.5
WMTS-J1
7.878
5.416
-7.836
-5.352
42.2 63.4
WMTS-LS1
12.439
8.436
-12.417 -8.404
21.9 32.8
WMTS-LS2
8.682
5.888
-8.667
-5.866
15.3 22.9
--------------------------------------------------Total power losses
207.5 311.7

Real and reactive power losses of WMTS 22kV overhead lines are exhibited in
Figure 4.6. The figure demonstrates that the power losses are line impedance
dependent, as can be observed clearly in the fact that although line WMTS
BSBQ1 is shorter in length than its counterpart WMTS BSBQ2, however, its
real and reactive power losses are higher and the reason for that is the higher
current passing through it which in turn causes higher power losses.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

76

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

WMTS 22kV Overhead Lines Losses


70
60
50
40
30
20
10

-B
SB
Q
1
TS
-B
SB
Q
W
2
M
TS
-D
A1
W
M
TS
-D
A2
W
M
TS
-J
W
1
M
TS
-L
S1
W
M
TS
-L
S2

JLS

kW
kVAR

W
M

W
M

TS

BS
BQ
-J

Figure 4.6: WMTS 22kV overhead lines power losses

4.2.4 PSS/E WMTS 22kV overhead base sub-model


The configuration and parameters of this base sub-model with the year 2007
loading demand has been obtained directly from Citipower as a file. The file was
then simulated using PSS/E software, Table 4.6 shows the results of this
simulated sub-model.

The results in Table 4.6 compare the results obtained earlier from Table 4.5.
The comparison demonstrates a close similarity of real and reactive power
losses. In other words, both simulation results obtained from two different power
softwares are agreed. Thus the validity of the WMTS 22kV base sub-model
developed in Section 4.1.3 is confirmed. Figure 4.7 shows a comparison of
WMTS 22kV power losses acquired from both EDSA and PSSE softwares.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

77

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Table 4.6: PSS/E WMTS 22kV overhead lines power losses


FROM
SHUNT
TO
LOAD FLOW
RATING
BUS NAME MW/MVAR BUS NAME kW
kVAR AMPS %I SET A
BSBQ 22
0.0
J 22
9272.8
4614.5
J 22
0.0
BSBQ 22
-9271.2
-4612.3
J 22
0.0
LS 22
-5967.3
-7936.4
LS 22
0.0
J 22
5997.6
7982.2
BSBQ 22
0.0
WMTS 22
-15048.2 -8048.7
WMTS 22
0.0
BSBQ 22
15089.2 8107
BSBQ 22
0.0
WMTS 22
-16806.5 -8975.2
WMTS 22
0.0
BSBQ 22
16845.3 9030.6
DA 22
0.0
WMTS 22
-10678.7 -6631.3
WMTS 22
0.0
DA 22
10692.1 6650.7
DA 22
0.0
WMTS 22
-9868.6
-6351.2
WMTS 22
0.0
DA 22
9882.1
6375.1
J 22
0.0
WMTS 22
-12386.9 -10464.4
WMTS 22
0.0
J 22
12430
10533.2
LS 22
0.0
WMTS 22
-13165.2 -12183.2
WMTS 22
0.0
LS 22
13185
12226.3
LS 22
0.0
WMTS 22
-11895.2 -10121.4
WMTS 22
0.0
LS 22
11910.8 10147.6
------------------------------------------------------------Total power losses
217.1
343.1

WMTS 22kV Overhead Lines Losses


70
60
50
40
30
20
10

J
TS -LS
-B
W
SB
M
Q
TS
1
-B
SB
Q
W
2
M
TS
-D
W
A1
M
TS
-D
A2
W
M
TS
-J
W
1
M
TS
-L
S1
W
M
TS
-L
S2

W
M

BS
BQ

-J

0
EDSA kW
PSS/E kW
EDSA kVAR
PSS/E kVAR

Figure 4.7: WMTS 22kV power losses comparison of both EDSA and
PSS/E
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

78

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

To summarise this section, the summation of power losses found in 22kV and
66kV loops are presented as the total power losses in the WMTS section of
Citipower for existing network configuration with 2007 loading demand.

Total real power losses = 207.50 + 352.50 = 560.00 kW


Total reactive power losses = 311.7 + 1222.3 = 1534.00 kVAR

4.4 WMTS 2011 Overhead Forecast Model


This model consists of a series of sub-models; these include the 66kV and 22kV
WMTS terminal station loops indicated in Figure 4.1. Forecast load demands for
the year 2011 are used in these sub-models. After obtaining the flow analysis of
the two voltage levels, a submission of all power losses which basically
represents the loading demand forecast of WMTS for the year 2011 is identified
for further analysis.

4.3.1 WMTS 66kV overhead 2011 forecast sub-model


In this sub-model, a 2011 forecast load demand is used to determine the new
overall load flow and identify stressed or exceeded rating elements in the
network. After the first attempt to run the load flow analysis, the load flow
analysis failed to converge as several elements were identified as stressed to
well over their 100% rating, Figure 4.8 shows the WMTS 66kV overhead 2011
forecast demand sub-model I; it can be noted that there are few lines or feeders
and transformers that are well stressed, with some exceeding 130% of rating.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

79

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Figure 4.8: WMTS 66kV overhead 2011 forecast sub-model I


Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

80

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

An expected finding from Figure 4.8 reveals that many elements in the submodel will be exceeding their 100% rating. These elements are identified by
their colour coding; the line WMTS VM3 is clearly over 100% loaded and it is
found to be 101.3% meanwhile VM zone substation transformers are found to
be loaded to 132.7% and are loaded to 116.5%. Additionally there were other
elements identified when n-1 redundancy configuration was used. After
identifying all the elements over stressed in this sub-model, single or double
circuits were added to keep in line with Citipower n-1 redundancy configuration.
Also new transformers have been added or existing transformers upgraded to
enable the load flow analysis convergence. Figure 4.9 shows the updated
WMTS 66kV overhead 2011 forecast sub-model where all elements are
operating under their 100% rating and n-1 Citipower redundancy configuration
is maintained.

The bus results of flow analysis performed on the WMTS 66kV overhead 2011
forecast sub-model II are presented in Table 4.7. The table lists bus parameters
including the current rating.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

81

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Figure 4.9: WMTS 66kV overhead 2011 updated forecast sub-model II


Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

82

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Table 4.7: WMTS 66kV overhead 2011 updated forecast load


flow results
Bus Info Generation Static Load
Load Flow Results
--------------- ----------------- ------------------------ ----------------------------------------------Name
MW MVAR MW MVAR To Bus Name MW
MVAR Amp %pf
-------------- ------- -------- ------- --------- ------------------- --------- ---------- ------- -------Sub JA 66 0.00 0.00 0.00 0.00
Sub LQ 66
36.73 34.65 446 72.7
Sub VM 66
-12.03 -14.25 165 64.5
WMTS 66
-66.69 -69.39 851 69.3
WMTS 66
-64.19 -66.79 819 69.3
Sub LQ 66 0.00 0.00 0.00 0.00
Sub JA 66
-36.72 -34.58 446 72.8
Sub VM 66
-42.6 -37.02 500 75.5
Sub VM 66
-33.48 -29.09 393 75.5
Sub NC 66 0.00 0.00 0.00 0.00
Sub WB 66 -7.58 -8.54 101 66.4
WMTS 66
-13.46 -13.13 166 71.6
Sub VM 66 0.00 0.00 0.00 0.00
Sub JA 66
12.03 14.27 165 64.5
Sub LQ 66
42.66 37.15 500 75.4
Sub LQ 66
33.51 29.19 393 75.4
Sub W 66
10.21 9.86 125 71.9
Sub W 66
10.21 9.86 125 71.9
Sub W 66
10.21 9.86 125 71.9
Sub WA 66
11.19 10.82 137 71.9
Sub WA 66
11.19 10.82 137 71.9
Sub WA 66
11.16 10.80 137 71.9
WMTS 66
-74.71 -59.86 846 78.0
WMTS 66
-55.80 -54.97 692 71.2
WMTS 66
-92.91 -98.65 1197 68.6
Sub W 66 0.00 0.00 0.00 0.00
Sub VM 66
-10.19 -9.85 125 71.9
Sub VM 66
-10.19 -9.85 125 71.9
Sub VM 66
-10.19 -9.85 125 71.9
Sub WA 66
10.19 9.85 125 71.9
Sub WA 66
10.19 9.85 125 71.9
Sub WA 66
10.19 9.85 125 71.9
Sub WA 66 0.00 0.00 0.00 0.00
Sub VM 66
-11.17 -10.81 137 71.9
Sub VM 66
-11.17 -10.81 137 71.9
Sub VM 66
-11.14 -10.78 137 71.8
Sub W 66
-10.19 -9.85 125 71.9
Sub W 66
-10.19 -9.85 125 71.9
Sub W 66
-10.19 -9.85 125 71.9
Sub WB 66 0.00 0.00 0.00 0.00
Sub NC 66
7.60
8.59 101 66.2
WMTS 66
-13.35 -13.85 169 69.4
WMTS 66
-13.35 -13.85 169 69.4
WMTS 66 0.00 0.00 0.00 0.00
Sub JA 66
66.90 70.54 851 68.8
Sub JA 66
64.39 67.89 819 68.8
Sub NC 66
13.54 13.35 166 71.2
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

83

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Sub VM 66
75.03 60.88 846 77.7
Sub VM 66
55.97 55.82 692 70.8
Sub VM 66
93.15 100.14 1197 68.1
Sub WB 66
13.39 13.99 169 69.2
Sub WB 66
13.39 13.99 169 69.2
-------------------------------------------------------Total losses 1.54
6.55

The load flow results obtained in Table 4.7 are summarised in Table 4.8. The
table shows in two different columns the power delivered to and from the line
and in the last two columns it lists the power difference or power losses. The
total real power losses were found to be 1545.8 kW; in addition total reactive
power was found to be 6,555.7 kVAR.

The WMTS 66kV lines real and reactive power losses are shown in Figure
4.10. The figure demonstrates that the power losses are line impedance
dependent, as it can be observed that although line WMTS VM3 is shorter in
length than its counterpart WMTS VM2, however its real and reactive power
losses are much higher. The interpretation for this is due to its current rating
which is less than WMTS VM2 yet it carries almost double the amount of
current passing through, as current always tends to pass through shorter paths.
As a result, it will produce higher losses.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

84

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Table 4.8: WMTS 66kV overhead 2011 updated forecast lines


losses
Branch
From -> To Flow To -> From Flow Losses
----------------- ------------------------ ------------------------ -------------------------------------Name
MW
MVAR
MW
MVAR
kW kVAR
---------------------- ------------- ----------------- ------------- ----------------- -------- ----------LQ-JA
-36.718 -34.577
36.734
34.649
16.6 72.9
VM-JA
12.034
14.267
-12.029 -14.250
4.2
17.0
VM-LQ1
42.655
37.150
-42.613 -37.020
42.2 129.9
VM-LQ2
33.515
29.189
-33.482 -29.087
33.1 102.0
VM-W1
10.211
9.860
-10.193 -9.850
17.7 10.7
VM-W2
10.211
9.860
-10.193 -9.850
17.7 10.7
VM-W3
10.211
9.860
-10.193 -9.850
17.7 10.7
VM-WA1
11.195
10.818
-11.173 -10.805
21.3 12.9
VM-WA2
11.195
10.818
-11.173 -10.805
21.3 12.9
VM-WA3
11.160
10.797
-11.139 -10.784
21.2 12.8
WA-W1
-10.191 -9.849
10.193
9.850
1.7
1.0
WA-W2
-10.191 -9.849
10.193
9.850
1.7
1.0
WA-W3
-10.191 -9.849
10.193
9.850
1.7
1.0
WB-NC
-7.582
-8.542
7.600
8.593
17.1 51.3
WMTS-JA1
66.897
70.539
-66.687 -69.394
209.8 1144.9
WMTS-JA2
64.389
67.893
-64.187 -66.791
202.0 1102.0
WMTS-NC
13.541
13.348
-13.461 -13.130
80.5 217.1
WMTS-VM1
75.032
60.884
-74.715 -59.865
316.7 1019.6
WMTS-VM2
55.970
55.822
-55.798 -54.966
172.5 856.3
WMTS-VM3
93.149
100.142
-92.906 -98.650
242.7 1491.6
WMTS-WB1
13.389
13.986
-13.346 -13.847
43.2 138.7
WMTS-WB2
13.389
13.986
-13.346 -13.847
43.2 138.7
-------------------------------------------------Total power losses 1545.8 6555.7

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

85

86
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

Figure 4.10: WMTS 66kV overhead 2011 forecast lines power losses
0

500

1000

1500

2000

2500

3000

3500

4000

Citipower 66kV Overhead 2011 Overall Power Losses

LQ
VM JA
-L
Q
VM 1
-W
VM 1
VM W3
-W
W A2
AW
W 1
W A-W
M
TS 3
W -J
M A1
T
W SM NC
T
W S-V
M
T M2
S
-W
B
AR 1
-B
BC C
FR TK
-M
P1
FR
R -W
TS
R -AR
TS
-C
R W
TS
R -FR
TS
-F
R R
TS 3
-N
R R
TS
-T
K
W
-M
F
B
TS P
-A
FB P1
FB T STS E
FB -F
T S B2
FB -MG
T
S 2
FB -S
O
T
S- 1
W
G
M 1
G
-A
P
LQ Q
-H
B
TS 2
T
SV SL
T
SEB

kVAR

kW

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

4.3.2 WMTS 22kV overhead 2011 forecast sub-model


The configuration of this base sub-model has many similarities to the WMTS
66kV sub-model exhibited earlier in Section 4.3.1, where a load demand of
2011 forecast load demand is used to determine the new overall load flow and
identify the elements under stress in the network. After identifying all the
elements under stress in this sub-model, single or double circuits are added to
keep in line with Citipower n-1 redundancy configuration. Also new transformers
have been added or upgraded to enable the load flow analysis to converge.
Figure 4.11 shows the updated WMTS 22kV overhead 2011 forecast submodel.

After performing load flow analysis on the WMTS 22kV overhead 2011 forecast
sub-model, the bus results were listed in Table 4.9. The table lists bus
parameters including the current rating.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

87

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Figure 4.11: WMTS 22kV overhead 2011 forecast sub-model


Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

88

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Table 4.9: WMTS 22kV overhead 2011 forecast load flow results
Bus Info
Generation Static Load Load Flow Results
----------------- ----------------- ----------------- ----------------------------------------------------Name
MW MVAR MW MVAR To Bus Name MW MVAR Amp %pf
----------------- ------ ---------- ------ --------- --------------------- ------- --------- ------- -----Sub BSBQ 22 0.00 0.00 0.00 0.00 Sub J 22
-0.64 -0.51 22 78.5
Sub J 22
-1.17 -0.48 34 92.4
WMTS 22
-12.07 -9.09 400 79.9
WMTS 22
-11.32 -8.52 375 79.9
WMTS 22
-12.07 -9.09 400 79.9
Sub DA 22
0.00 0.00 0.00 0.00 WMTS 22
-12.13 -8.94 397 80.5
WMTS 22
-12.13 -8.94 397 80.5
WMTS 22
-11.98 -8.83 392 80.5
Sub J 22
0.00 0.00 0.00 0.00 Sub BSBQ 22 0.64
0.51 22 78.4
Sub BSBQ 22 1.17
0.49 34 92.3
Sub LS 22
-4.01 -2.77 128 82.3
Sub LS 22
-4.01 -2.77 128 82.3
WMTS 22
-5.21 -3.76 169 81.1
WMTS 22
-5.21 -3.76 169 81.1
WMTS 22
-5.21 -3.76 169 81.1
Sub LS 22
0.00 0.00 0.00 0.00 Sub J 22
4.01
2.78 128 82.2
Sub J 22
4.01
2.78 128 82.2
WMTS 22
-12.52 -9.45 413 79.8
WMTS 22
-8.74 -6.60 288 79.8
WMTS 22
-12.52 -9.45 413 79.8
WMTS 22
0.00 0.00 0.00 0.00 Sub BSBQ 22 12.16 9.22 400 79.7
Sub BSBQ 22 11.40 8.64 375 79.7
Sub BSBQ 22 12.16 9.22 400 79.7
Sub DA 22
12.17 9.00 397 80.4
Sub DA 22
12.17 9.00 397 80.4
Sub DA 22
12.02 8.89 392 80.4
Sub J 22
5.23
3.79 169 81.0
Sub J 22
5.23
3.79 169 81.0
Sub J 22
5.23
3.79 169 81.0
Sub LS 22
12.54 9.49 413 79.8
Sub LS 22
8.76
6.62 288 79.8
Sub LS 22
12.54 9.49 413 79.8
-------------------------------------------------------Total losses
0.5
0.78

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

89

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

The load flow results obtained in Table 4.9 are summarised in Table 4.10. The
table shows in two different columns the power delivered to and from the line
and in the last two columns it lists the power difference or power losses.
The total real power losses were found to be 526.2 kW; in addition the total
reactive power was found to be 786.5 kVAR.

Table 4.10: WMTS 22kV overhead 2011 forecast lines losses


Branch
From -> To Flow
To -> From Flow
Losses
------------------------------------------------------ --------------------------------------------------Name
MW
MVAR
MW
MVAR
kW kVAR
---------------------- ------------- ----------------- ------------- ----------------- -------- ----------BSBQ-J1
-0.639
-0.505
0.641
0.509
2.3
3.4
BSBQ-J2
-1.168
-0.483
1.173
0.488
4.9
4.2
J-LS1
-4.007
-2.767
4.014
2.778
7.2
10.7
J-LS2
-4.007
-2.767
4.014
2.778
7.2
10.7
WMTS-BSBQ1 12.159
9.217
-12.071 -9.085
88.1 132.2
WMTS-BSBQ2 11.399
8.641
-11.316 -8.517
82.6 124.0
WMTS-BSBQ3 12.159
9.217
-12.071 -9.085
88.1 132.2
WMTS-DA1
12.167
9.003
-12.125 -8.941
41.3 62.0
WMTS-DA2
12.167
9.003
-12.125 -8.941
41.3 62.0
WMTS-DA3
12.017
8.893
-11.977 -8.832
40.8 61.3
WMTS-J1
5.227
3.789
-5.207
-3.760
19.3 28.9
WMTS-J2
5.227
3.789
-5.207
-3.760
19.3 28.9
WMTS-J3
5.227
3.789
-5.207
-3.760
19.3 28.9
WMTS-LS1
12.545
9.487
-12.521 -9.451
23.9 36.0
WMTS-LS2
8.756
6.621
-8.739
-6.596
16.7 25.1
WMTS-LS3
12.545
9.487
-12.521 -9.451
23.9 36.0
--------------------------------------------------Total power losses
526.2 786.5

The WMTS 22kV overhead lines real and reactive power losses are shown in
Figure 4.12. The figure demonstrates that the power losses are line impedance
dependent, as it can be observed that although the line WMTS BSBQ1 is
shorter in length than its counterpart WMTS BSBQ2, however its real and

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

90

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

reactive power losses are much higher and the reason for that is the higher
current passing through it.

To sum up this section, the summation of power losses found in 22kV and 66kV
loops are presented as the total power losses in the WMTS section of Citipower
for network configuration with a forecast 2011 loading demand.

Total real power losses = 526.2 + 1545.8 = 2072.00 kW


Total reactive power losses = 786.5 + 6555.7 = 7342.20 kVAR

A better representation of the power loss comparison for the Citipower WMTS
section of the overhead network with power losses obtained from both 2007 and
2011 loading demand is shown in Figure 4.13.

As can be seen, the losses for the forecast year 2011 are three and a half times
more than the losses for the year 2007; this observation can be interpreted as
due to the high amount of current that flows through the inductor of the lines
which causes greater losses.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

91

50

100

150

200

250

300

350

400

kVAR

BS
B
Q
W
-J
M
J 1
W TS- -LS
M B
TS SB 1
- Q
W B 1
M SBQ
TS 3
W -D
M A2
W TSM J
W TS 1
M
TS -J3
-L
PR S2
PR R1
R R3
R -SM
TS 2
R -P
TS R2
R PR4
TS
R -R2
T
R S-R
TS 4
R -RP
TS 2
BT -SM
S 1
B -B
T
S- K1
B
BT K3
S
BT -C2
S
BT -C4
BT S-F
S 2
BT -FF
S 1
BT -FF
S 3
B -NS
T
S- 1
N
N S3
TT
P1

Citipower 22kV Overhead 2011 Overall Power Losses

kW

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Figure 4.12: WMTS 22kV overhead 2011 forecast lines power losses
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

92

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Figure 4.13: WMTS 22kV and 66kV overhead power loss comparison

Another observation that can be drawn from WMTS both 22kV and 66kV
forecast sub-modules is that some of the lines have been duplicated and some
transformers have been upgraded to keep the n-1 citipower configuration in
position. These additional elements are:

VM W2, VM W3, WA W2, WA W3, WMTS WB2, BSBQ J2, J LS2,


WMTS BSBQ3, WMTS DA3, WMTS J2, WMTS J3, WMTS LS3,
VMTx4 and WATx3.

Meanwhile upgraded elements are:

DA transformers 1-3 has been upgraded from 13.5 MVA to 20 MVA; and BSBQ
transformer 1-3 has been upgraded from 10 MVA to 20 MVA.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

93

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

4.5 Citipower 2007 Overhead Overall Power


Losses
Data for the remaining terminal stations loops of overhead network is found in
Figure 4.1. Most of this data was obtained from Citipower and its publications
from the public domain with the exception of the assumptions mentioned earlier
in Section 4.1. Separate sub-models were developed individually for each
terminal station with separate sections for 66kV and 22kV voltage levels.

Appendix E lists Citipower Terminal stations overhead sub-models.

Following the load flow analysis of the two voltage levels, 66kV and 22kV, a
submission of all power losses is given in Tables 4.11 and 4.12 to undergo
further analysis, which basically represents the loading demand of WMTS for
the year 2007.

Table 4.11: Citipower 66kV overhead overall lines losses


Branch Name
----------------------------------LQ-JA
VM-JA
VM-LQ1
VM-LQ2
VM-W
VM-WA1
VM-WA2
WA-W
WB-NC
WMTS-JA1
WMTS-JA2

kW losses kVAR losses


---------------- --------------------10.6
46.4
0.3
1.3
6.1
18.8
4.8
17.0
24.2
14.6
29.1
17.6
29.0
17.5
2.4
1.4
1.6
4.7
28.9
157.6
29.2
157.6

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

94

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

WMTS-NC
28.1
75.7
WMTS-VM1
57.4
184.7
WMTS-VM2
31.2
155.1
WMTS-VM3
44.0
270.1
WMTS-WB
25.6
82.2
AR-BC
1
2.7
B-CW
1.1
2.9
BC-TK
17.3
45.8
CL-K
0.3
1
FR-MP1
1.4
4.7
FR-MP2
1.7
5.8
FR-W
0.3
1
NR-B
29.3
71.4
RTS-AR
20.5
84.3
RTS-CL
70.5
208
RTS-CW
58.2
212.8
RTS-EW
40.8
117.1
RTS-FR1
29.7
98.4
RTS-FR2
29.7
98.4
RTS-FR3
30
98.8
RTS-K
34.6
173.4
RTS-NR
155.2
486
RTS-SK
105.8
259.1
RTS-TK
37.7
120
SK-EW
2.9
9.4
W-MP
0.4
1.5
E-PM
0.2
0.5
FBTS-AP
22.1
88.7
FBTS-E
3.4
9.3
FBTS-FB
31.4
514.7
FBTS-MG
30.6
131.4
FBTS-PM
1.7
5.4
FBTS-SO1
23.4
91.3
FBTS-SO2
20.9
71.4
FBTS-WG
58.5
794.4
MG-AP
0.5
2.7
WG-FB
2.8
37.9
L-Q
0.4
1.3
Q-HB
44.4
176.3
TSTS-HB
86.3
710
TSTS-L
137.4
779.5
EB-RD
1.5
4.5
SVTS-EB
93.2
340.3
SVTS-RD
71.9
229.4
---------------------------------------------------------------------Total overall power losses: 1,651.5
7,313.8

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

95

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Both the real and reactive power losses of Citipower 66kV overhead lines are
shown in Figure 4.14. The figure demonstrates that the power losses are line
impedance dependent and the higher current passing and longer length of line
will result in higher power losses in that particular line.

The Citipower 22kV overhead lines for both real and reactive power losses are
summarised in Table 4.12.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

96

100

200

300

400

500

600

700

800

kVAR

L
V Q-J
M
-L A
V Q
V M- 1
M
-W W
W WB A2
W MT -N
M S C
W TS -JA
M - 2
TS V M
-V 1
AR M3
B -BC
F C-T
R
-M K
F P1
R RT W
R STS AR
R -CW
R TSTS F
R
R -FR
TS 3
R -N
T R
S
-T
FB W- K
M
T
F S- P
B
A
FB TS P
FB TS FB
T
S- PM
M SO
G 2
-A
TS L P
T -Q
S
-H
S EB B
V
TS-RD
R
D

Citipower 66kV Overhead Overall Lines Losses

kW

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Figure 4.14: Citipower 66kV overhead overall power loss

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

97

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Table 4.12: Citipower 22kV overhead overall lines losses


Branch Name
kW losses kVAR losses
-------------------------------------------------- --------------------BSBQ-J
1.3
1.9
J-LS
29.4
44.2
WMTS-BSBQ1
37.5
56.4
WMTS-BSBQ2
35.2
52.9
WMTS-DA1
12.4
18.7
WMTS-DA2
12.3
18.5
WMTS-J1
42.2
63.4
WMTS-LS1
21.9
32.8
WMTS-LS2
15.3
22.9
PR-R
15.5
8.5
R-SM
4
2.3
RTS-PR2
16.2
14
RTS-PR3
16.2
14
RTS-R1
8.2
6.1
RTS-R2
8.1
5.6
RTS-R3
7.9
5.1
RTS-RP1
9.4
5.4
RTS-RP2
6.6
5
RTS-RP3
10.1
6
RTS-SM1
10.3
5.6
RTS-SM2
10.1
5.7
BTS-BK1
2.5
4.7
BTS-BK2
1.2
2.1
BTS-BK3
2.5
4.7
BTS-C2
12.9
6.6
BTS-C3
13.2
6.7
BTS-C4
13.5
6.9
BTS-F1
5.8
3.6
BTS-F2
5.8
3.6
BTS-F3
10.2
5.2
BTS-FF1
9
15.6
BTS-FF2
18.3
30.5
BTS-FF3
35.8
57.5
BTS-NS1
107.7
177.1
BTS-NS2
104.3
201.7
BTS-NS3
103.7
210.8
NT-TP1
22.1
22.6
NT-TP2
29.1
31.1
---------------------------------------------------------------------Total overall power losses: 827.7
1,186.0

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

98

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Similarly, Citipower 22kV overhead lines with both real and reactive power
losses are represented in Figure 4.15. The figure demonstrates that power
losses are line impedance dependent and the higher current passing and longer
length of line will result in higher power losses in that particular line.

Citipower 22kV Overhead Overall Lines Losses


250

200

150

100

50

BS
W
B
M
TS QJ
-B
SB
W
Q
M
1
TS
-D
A1
W
M
TS
W
-J
M
1
TS
-L
S2
RT
SR
RT P3
SSM
2
BT
SBK
2
BT
SC2
BT
SC4
BT
SF2
BT
SFF
1
BT
SFF
3
BT
SNS
2
NT
-T
P1

KW
KVAR

Figure 4.15: Citipower 22kV overhead overall power loss

A combined summation of power losses is found in Tables 4.11 and 4.12 for
22kV and 66kV loops which illustrate the total power losses in the Citipower for
the overhead network configuration with a 2007 loading demand.

Total real power losses = 827.7 + 1,651.5 = 2,479.2 kW


Total reactive power losses = 1,186.0 + 7,313.8 = 8499.8 kVAR

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

99

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

4.6 Citipower 2011 Forecast Overhead Overall


Power Losses
Overhead network data, for the year 2011, of all terminal stations loops found in
Figure 4.1 were again obtained from Citipower publications. Some of the
network data were not available; therefore assumptions in Section 4.1 were
used for the development of the network. Separate sub-models were developed
individually for each terminal station with separate sections for 22kV and 66kV
voltage levels.

Appendix H lists Citipower Terminal stations overhead Forecast 2011 submodels.

After obtaining the flow analysis of the two voltage levels, a submission of all
power losses, which represents the loading demand of WMTS for the year
2011, is given in Tables 4.13 and 4.14 to undergo further analysis.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

100

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Table 4.13: Citipower 66kV overhead 2011 forecast overall lines


losses
Branch Name
----------------------------------LQ-JA
VM-JA
VM-LQ1
VM-LQ2
VM-W1
VM-W2
VM-W3
VM-WA1
VM-WA2
VM-WA3
WA-W1
WA-W2
WA-W3
WB-NC
WMTS-JA1
WMTS-JA2
WMTS-NC
WMTS-VM1
WMTS-VM2
WMTS-VM3
WMTS-WB1
WMTS-WB2
AR-BC
B-CW
BC-TK
CL-K
FR-MP1
FR-MP2
FR-W
NR-B
RTS-AR
RTS-CL
RTS-CW
RTS-EW
RTS-FR1
RTS-FR2
RTS-FR3
RTS-K
RTS-NR
RTS-SK
RTS-TK

kW losses
--------------16.6
4.2
42.2
33.1
17.7
17.7
17.7
21.3
21.3
21.2
1.7
1.7
1.7
17.1
209.8
202
80.5
316.7
172.5
242.7
43.2
43.2
1.2
0.3
29.7
14.6
13.5
16.6
15.4
44.1
142.2
160.4
156.3
50.7
173
173
173
186.8
150.8
189.7
61

kVAR losses
-----------------72.9
17
129.9
102
10.7
10.7
10.7
12.9
12.9
12.8
1
1
1
51.3
1144.9
1102
217.1
1019.6
856.3
1491.6
138.7
138.7
1.8
0.5
78.5
22
46.4
57.3
23.2
107.5
213.8
241.2
235.1
76.3
260.2
260.2
260.2
280.9
226.7
285.3
91.8

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

101

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

SK-EW
6.3
20.5
W-MP
19.9
29.9
E-PM
0.02
0.05
FBTS-AP1
63
252.6
FBTS-AP2
63
252.6
FBTS-E
16.8
45.7
FBTS-FB1
31.3
512.7
FBTS-FB2
31.3
512.7
FBTS-MG1
76.3
328.3
FBTS-MG2
76.3
328.3
FBTS-PM
14.3
44.5
FBTS-SO1
214.9
837.2
FBTS-SO2
191.3
655.4
FBTS-WG1
44.4
602.9
FBTS-WG2
44.4
602.9
MG-AP
3.4
17.4
WG-FB
6.4
86.5
L-Q
1.4
4.3
Q-HB1
70.1
278.1
Q-HB2
70.1
278.1
TSTS-HB
178.2
1466
TSTS-L
286.9
1627.6
EB-RD
25.1
78
SVTS-EB
1040.3
3797
SVTS-RD
766.1
2444.5
-----------------------------------------------------------------------Total overall power losses: 6639.62
24428.35

The Citipower 66kV overhead overall lines real and reactive power losses are
shown in Figure 4.16. The figure demonstrates that the power losses are line
impedance dependent and the higher current passing and longer length of line
will result in higher power losses in that particular line.

The Citipower 22kV overhead lines both real and reactive power losses are
summarised in Table 4.14.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

102

103
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

Figure 4.16: Citipower 66kV overhead 2011 forecast overall power losses
0

500

1000

1500

2000

2500

3000

3500

4000

Citipower 66kV Overhead 2011 Overall Power Losses

LQ
VM -JA
-L
VM Q1
-W
VM 1
VM -W
3
-W
W A2
AW W1
W AM W
T 3
W S-J
M A
W TS 1
M -N
W TS C
M -V
T M
S
-W 2
B
AR 1
-B
BC C
FR -TK
-M
P
FR 1
R -W
TS
R TS AR
-C
R W
TS
R -F
TS R
-F
R R
TS 3
R NR
T
S
-T
K
FB W-M
T
S- P
A
FB P1
FB TS
T -E
FB S-F
TS B2
FB -M
T G
FB S-S 2
T
S- O1
W
G
M 1
G
-A
P
LQ Q
-H
TS B2
SV TS
-L
T
SEB

kVAR

kW

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Table 4.14: Citipower 22kV overhead 2011 forecast overall


power losses
Branch Name
----------------------------------BSBQ-J1
BSBQ-J2
J-LS1
J-LS2
WMTS-BSBQ1
WMTS-BSBQ2
WMTS-BSBQ3
WMTS-DA1
WMTS-DA2
WMTS-DA3
WMTS-J1
WMTS-J2
WMTS-J3
WMTS-LS1
WMTS-LS2
WMTS-LS3
PR-R1
PR-R2
PR-R3
R-SM1
R-SM2
RTS-PR1
RTS-PR2
RTS-PR3
RTS-PR4
RTS-R1
RTS-R2
RTS-R3
RTS-R4
RTS-RP1
RTS-RP2
RTS-RP3
RTS-SM1
RTS-SM2
BTS-BK1
BTS-BK2
BTS-BK3
BTS-BK4
BTS-C2
BTS-C3
BTS-C4

kW losses
---------------2.3
4.9
7.2
7.2
88.1
82.6
88.1
41.3
41.3
40.8
19.3
19.3
19.3
23.9
16.7
23.9
4.6
4.6
4.6
25.3
25.3
21.1
21.2
21.2
21.2
30.6
30
29.2
30
67.4
47.6
72.1
68.2
67.1
9
4.3
9
9
16.7
17
17.5

kVAR losses
--------------------3.4
4.2
10.7
10.7
132.2
124
132.2
62
62
61.3
28.9
28.9
28.9
36
25.1
36
7
7
7
38.1
38.1
18.2
18.3
18.3
18.3
22.7
20.7
19
20.7
38.7
35.7
43.3
37.1
37.5
17
7.8
17
17
8.5
8.7
8.9

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

104

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

BTS-F1
20.2
12.7
BTS-F2
20.2
12.7
BTS-F3
35.4
18
BTS-FF1
8.3
14.3
BTS-FF2
16.8
27.9
BTS-FF3
52.1
78.4
BTS-FF4
52.1
78.4
BTS-NS1
196.2
322.7
BTS-NS2
190
367.5
BTS-NS3
188.9
384
BTS-NS4
188.9
384
NT-TP1
91.1
92.9
NT-TP2
120
128.2
-----------------------------------------------------------------------Total overall power losses:
2380.2
3238.8
The Citipower 22kV overhead overall lines real and reactive power losses are
graphically represented in Figure 4.17. The figure demonstrates that power
losses are line impedance dependent and the higher current passing and longer
length of line will result in higher power losses in that particular line.

A combined summation of power losses that was found in Tables 4.13 and 4.14
for 22kV and 66kV loops which are presented as the total power losses in the
Citipower for overhead network configuration with a 2011 forecast loading
demand.

Total real power losses = 6639.62 + 2380.20 = 9019.82 kW


Total reactive power losses = 24428.35 + 3238.80 = 27667.15 kVAR

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

105

400
350
300
250
200
150
100
50
0
1 1 1 3 2 1 3 2 1 3 2 2 4 2 4 2 1 1 3 2 4 2 1 3 1 3 1
-J LS BQ BQ DA -J -J LS -R -R SM PR PR -R -R RP SM BK BK -C -C -F -FF -FF NS NS -TP
BQ J- BS BS S- TS TS TS- PR PR R- TS- TS- TS TS TS- S- TS- TS- BTS BTS BTS TS TS TS- TS- NT
S
R R R
T
- - T M M M
B B B B
B
R R
R B B
TS TS WM W W W
M M
W W

Citipower 22kV Overhead 2011 Overall Power Losses

106

kVAR

kW

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

Figure 4.17: Citipower 22kV overhead 2011 forecast overall power loss

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

A clearer representation of the comparison of power losses for the overall


Citipower overhead network with power losses obtained from both 2007 and
2011 loading demand is shown in Figure 4.18.

Citipower Overall Overhead Losses Comparison


30000.00
25000.00
20000.00
15000.00
10000.00
5000.00
0.00
kW

kVAR

2007
2011

Figure 4.18: Citipower overall overhead power loss comparison

As can be seen, the losses for the forecast year 2011 are almost three and a
half times more than the losses for the year 2007, Moreover there are many
lines duplicated to keep the Citipower n-1 configuration; the added lines
reduced the power losses due to the fact that less current will pass through the
same lines and it will produce less power losses.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

107

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

4.7 Conclusion
A Comprehensive analysis and development of Victorian overhead power
network sub-models were presented in detail in this chapter. In addition, an
elaboration on overall overhead network sub-models was discussed in chapter
3. These analyses are of great significance for future growth and for the safe
operation of the Victorian power network. Various forecasted models were
analysed and critical analysis has been provided to determine the need to add
additional lines and transformers to enable the handling of the additional
forecasted load in the network.

Load flow analyses and other industrial based specialised software were used
to investigate and develop various sub-transmission network models. The
results obtained from the load flow analyses provided crucial information about
all buses in the network. Some buses were exceeding their normal operation
values or nominal values so an action was made to rectify the problem
associated with any abnormality in the network; The Citipower n-1 redundancy
configurations were met in all developed sub-models.

Another outcome of the load flow analysis was the determination of the real and
reactive power losses at each line and the effect of forecasted loading on the
losses was identified.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

108

Chapter 4: Development and Analysis of Victorian Overhead Power Network Model

The next chapter looks at the Victorian overhead power network in an attempt
to efficiently design an underground network for Victoria.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

109

Chapter 5: Underground Power Networks

CHAPTER 5
UNDERGROUND POWER
NETWORKS
5.0 Introduction
Undergrounding is no longer perceived as a prohibitively expensive exercise
due to its the advancement of technology in underground cables as discussed
earlier in this thesis. The cost of undergrounding is very encouraging practically
when installed in newly developed estates. However, old established areas will
continue to remain serviced by overhead power lines due to the expensive
conversion exercise at this point in time.

A typical underground power sub-transmission and distribution system with the


other stages of the power network including generation and overhead
transmission is shown in Figure 5.1.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

110

Chapter 5: Underground Power Networks

Figure 5.1: Power Network with underground sub-transmission and


distribution systems [4]

Despite the added reliability that could be gained from undergrounding, it is


important to know that fault detection and elimination is much more time and
money consuming than its overhead counterpart.

Even shorter interruption time in overhead lines, does not hold as a viable
discussion point when arguing against installing underground solutions.
Furthermore, the total loss of revenues is far less when undergrounding than
using overhead and thats primarily due the significantly decreased fault
frequency [29].

5.1 General Overview


The electric energy industry dates from the late 18th (1882) century when
Thomas Edison created the first underground system of commercial electricity
distribution. This system, as humble as it may have been with a capacity to
deliver 100 Volts of direct current, however, was the corner stone of a greater

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

111

Chapter 5: Underground Power Networks

system which witnessed the birth of the transformer four years later (1886). The
transformer made distribution for long distance a dream comes true, thanks to
the Alternating Current (ac) electric pressure which reached 1000 Volts and
then dropped the current to safer levels for domestic use, similar to Direct
Currents (dc). This great invention opened the door wide for commercial
distribution especially when overhead lines were easily utilised due to their
relatively low cost [29].

Needless to say, that these relatively inexpensive overhead lines systems have
contributed to the rapid growth of rural and suburban communities in the out
skirts of major cities. But with the growth of populations and boom of business
around the globe, due to the industrial revolution post World War II, Central
Business Districts (CBDs) around the world started to see a shift from the
traditional overhead lines and they started building underground systems for
aesthetical and

economical reasons. The

continuous development

in

technology and plastic fabrication post World War II has led to the wide
expansion of underground systems in those urban and metropolitan areas with
new creative designs of curvy streets and closes. Consequently, this has made
thinking of using overhead less appealing to infrastructure developers, as it is
more material and man power exhaustive and demanding than its more
aesthetically

appealing

and

environmentally

friendly

and

lower

cost

underground systems. Furthermore, undergrounding has witnessed a huge


reduction in cost in the past 5 decades due to technological advancement in

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

112

Chapter 5: Underground Power Networks

cable fabrication and installation techniques such as direct burial of extra long
spans between splices [29].

5.2 Voltage Regulation


In general, electricity is transmitted in high voltage from the generation plants to
distribution substations. Voltages at distribution stages are much lower than
their levels at the generation stages where they are distributed to different
loads. Finally, they are dropped further to much lower levels where they will be
used by domestic consumers [29].

Normally, generated voltage could reach 20kV or more; this voltage is then
raised to approximately 140kV by transformers to prepare it for high load
transmission over long distance routes to reach transmission substations where
voltage levels are stepped down to approximately 69kV to enter into low load
distribution substations in designated areas and this where the main voltage is
regulated between 120 or 240 Volts by distribution transformers [29].

5.3 Overhead vs. Underground


Electric energy utilises overhead and underground means to deliver power.
Overhead networks comprise relatively low-cost insulators and conductors
mounted on poles made of various materials like wood, steel or concrete. Other
overhead equipments are installed on some of these poles which make it more
cost effective to repair and maintain. On the other hand, this direct exposure
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

113

Chapter 5: Underground Power Networks

has a down side of being highly susceptible to malfunctioning due to


environmental and man made breakdowns [29].

Undergrounding consists of maintenance holes which are commonly referred to


as manholes which are tubes used to connect underground utilities to the
surface. Manholes are widely used in sewer systems, electrical and
communication systems. These manholes are situated at regular intervals along
the utility path, to allow easy access to maintenance workers. Rubber and other
insulated conductors (cables) are installed and sliced inside these underground
cavities. Therefore, fault detection and repairs can be a very costly exercise
[29].

Undergrounding used to be implemented in very few cases where it met strict


regulatory conditions. This was primarily, due to the high cost involved in
undergrounding, for example when utilities and the public dispute over private
property for line easement. Over the years, various factors have played a
significant role in increasing the deployment of undergrounding. Some of these
core factors are: the demand for higher power consumption which has led to
building more generation sites. Unfortunately, it became ultra difficult to obtain
properties for such purposes. Another factor was the need for larger more
economical generation units instead of local units. Finally, a more recent factor
came into inception which is that health and environmental effects have been
pushed quite heavily by industry lobby groups, regulators and more green
governments [29].
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

114

Chapter 5: Underground Power Networks

The aforementioned emphasis on health and environmental effects was the


major driver for increased undergrounding due to the perception that
underground cables will emit less electromagnetic field. Furthermore, cities
began to pay extra attention to the visual appearance of their urban areas and
business districts to attract more tourists and investors, therefore more power
lines started to disappear in well presented paved areas. Underground cables in
general operate under lower voltage levels than their overhead counterparts.
Therefore, it was necessary to implement step-up and step-down transformers
to maintain a long overhead line route [29].

The biggest advantage of underground installation is that it is less exposed and


susceptible to external factors than overhead. However, somehow or other, this
advantage can be offset by the time and effort spent in locating and repairing
faults should they take place. The nature of the installation design and the
complexity will be determined by the obligatory standards used for the
installation [29].

Chang et al. [14], argued that although underground cables have continued, up
until the present, to be more expensive than overhead lines for the same
capacity, a number of European countries like the Netherlands have had
underground cables installed widely since the early 70s. The reasons behind
their ultimate decisions were based on:

environmental nature of power network reliability;


Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

115

Chapter 5: Underground Power Networks

shortage of land and its utilisation;


recent regulation changes and opposition to overhead lines among the
public.

On the other hand development and reduction in the cost of cable technology
enhanced with reliable and efficient cable installation have contributed
considerably in reducing the overall cost of underground cables. Meanwhile the
cost ratio is less prominent at lower voltages and the economic potential of
operating and maintenance costs favour underground cables and make them a
dominant alternative solution to overhead lines in many cases such as:

highly congested or populated urban areas;


areas with historic or environmental values;
crucial sections of the network which have low reliability records; and
areas with a need for extra capacity where constructing a new overhead
transmission line is out of question.

Adopting underground power cables has been slow in Australia in the past
mainly as a consequence of the high cost of the cable technology, the low
density demographic of Australian cities and limited restrictions on the use of
overhead lines. Major catastrophic events have normally acted as the
mechanism which drives the undergrounding of power lines. In 1974, when
Cyclone Tracey hit Darwin it provided the justification for undergrounding
Darwin overhead lines so subsequently by 1980, more than 50% of that city
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

116

Chapter 5: Underground Power Networks

was serviced by underground LV and MV cables. Although there was little effort
to retrofit existing areas throughout Australian cities since 1980, a steady
introduction of underground cables for new residential areas has been
undertaken. The bush fire risks in Australia has turned out to be more apparent
due to climate change, in many cases these bushfires were results of clashing
of bare conductors. Besides, the consumer demand for a more reliable and
safer power supply will highlight the necessity of undergrounding the existing
power network [30]. The relevant aspects of different underground cables have
been elaborated.

5.4 Reliability Issues


As reference [31] reported, the top predominate causes of outages which
account for over 50% of all power outages were external and due to tree and
conductor failure. Figure 5.2 shows the percentage of top causes for outages
for SP AusNet Electricity Distribution, Australia in 2004.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

117

Chapter 5: Underground Power Networks

35%
30%
25%
20%
15%
10%
5%

rd
O
ve
rlo
ad
Co
An
nd
im
uc
al
to
rF
ai
lu
re

Bi

Hu
O
th
m
er
an
Ag
en
cy

Tr
ee

Xa
rm

Po
le

Fi
Un
re
de
rg
ro
un
d
W
ea
th
er
Li
gh
tn
in
g

0%

Figure 5.2: Unplanned SAIDI by Cause for 2004 [31]

This figure shows that there is a correlation between reliability and external
factors. Progress in reliability is achievable by reducing the controllable
unplanned outages such as trees, no cause identified outages and equipment
failure. In other words, implementing underground cables will have the potential
to reduce power outages throughout normal weather and limit the damage of
severe ones, although if a fault occurs a longer time is needed to recover the
power supply.

Another aspect of underground reliability is the potential for reduced network


maintenance and losses caused by electricity outages and reduced
transmission losses. As reference [9] suggested, maintenance costs are equal
to the sum of preventive maintenance, vegetation management and reactive
maintenance; in spite of that, the cost of overhead maintenance would

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

118

Chapter 5: Underground Power Networks

approximately double provided replacement materials cost was included. Table


5.1 shows average maintenance in the Australian electricity network.

TABLE 5.1: AVERAGE MAINTENANCE COSTS OF


AUSTRALIAN ELECTRICITY NETWORK [9]
Type of maintenance

Expenditure on maintenance
(Average of 1997 & 1998)
($ per km of line per year)
Low *
Medium
High

OH Overhead /
UG Underground

OH

UG

OH

UG

OH

UG

Preventative

282

128

380

158

590

941

Vegetation Management

107

nil

194

nil

285

nil

Reactive

79

102

155

178

527

460

Total non capital

468

230

729

336

1 402

1 401

Total capital & non capital

936

460

1 458

672

2 804

2 802

* Represents the lower 25% quartile, medium and upper 25% quartile of maintenance expenditure from a database of
thirteen utilities.
# Costs are for urban residential areas, excluding the central business district and lightly populated rural areas and the
costs include, labour, contractors, vehicles and materials, but exclude capital costs such as transformers, poles and
cable.

The figures indicate that maintenance costs of overhead network are about
twice as much as underground. Nevertheless, the figures are a representation
of the difference between the maintenance costs of existing overhead systems
and new underground cables. However, $786 per kilometre of line per year for
the medium avoided maintenance cost is expected to draw near the difference
between the figures for overhead and underground shown in Table 5.1, as time
progresses and the new underground system ages [9].

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

119

Chapter 5: Underground Power Networks

Based on the System Average Interruption Duration Index (SAIDI) of a local


power distribution company in Melbourne SP AusNet [3], it is predicted that
70% of outages are encountered on the overhead network and 30% on the
underground network, with an average duration for an overhead fault of 50
minutes and an average duration of approximately 65 minutes for an
underground fault. The longer time it takes to repair an underground faulty
cable, reflects a higher duration for the underground network fault. This is a
reflection of the time it takes to effect repairs. On a per unit basis an
underground fault will take about 10 times longer than an overhead lines fault to
repair (with a similar cost ratio), hence the need for the interconnectivity on the
underground system. For 2004 alone, SP AusNet experienced 84 outages on
its overhead HV load power feeders and 54 on its underground feeders. The
causes for outages on the overhead network were animals, vegetation, weather
and third parties.

5.5 Power Network Fundamentals


As stated earlier, underground cables have the potential to reduce outages,
maintenance cost and transmission losses. In general transmission losses are
lower with underground cables compared to overhead lines. Additionally, new
underground cable technology with its unique characteristics of low impedance
and ohmic loss enables a massive increase in power transmission capacity.
Underground cables can also deliver economic benefits where civil works are

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

120

Chapter 5: Underground Power Networks

reduced by avoiding unnecessary digging; besides there is a big savings in tree


pruning for local councils.

To make the decision of moving overhead distribution systems underground


there are many issues, which need to be considered thoroughly. The technical
and non-technical issues and their broad impact can be categorised as follows:

design aspects;

engineering aspects;

innovation aspects.

5.5.1 Design aspects


Replacing of overhead lines networks by underground cables networks has
many advantages and some disadvantages. There are several technical
aspects that need to be considered when planning for such a move, especially
in established residential areas, which can be a nightmare for network
designers. Some of the challenging issues that designers normally face include:

how to design undergrounpower network using existing zone and


terminal substations due to land acquisition troubles;

number and location of the new pad-mounted substations associated


with an underground network need to be identified, as this is a very
significant issue to the resident and electricity distributors;

type of cable and cable technology to be used;

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

121

Chapter 5: Underground Power Networks

the co-ordination time between different services has to be minimised to


maximise overall efficiency of undergrounding cables.

On the other side, this conversion will provide network designers with a good
opportunity to design a modern network to meet not only current load
requirements but also the future anticipated load. Designers will be more
confident in designing underground networks since many of the design
parameters will be known to a certain extent [32].

The continuous development of underground cables and equipment technology


has led to tightening the variation of price tag between overhead and
underground systems. Moreover, traditionally, overhead lines have been
associated with costing less to construct and maintain, and this is still the case,
especially for transmission levels, but this can not be taken as a rule of thumb.
In cases of regulatory demand, coastal view urban and residential areas, and
new real estate, underground will have obvious advantages over overhead lines
[29].

5.5.2 Engineering aspects


Cable selection is the main element in designing underground power systems.
Selecting the best available and reliable underground cable technology has the
potential of overcoming many of the cost, safety and environment related
issues. This study will focus on three different types of cables.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

122

Chapter 5: Underground Power Networks

Cross-linked polyethylene (XLPE) cable

XLPE cable is the major developing technology and has wide industry
acceptance at voltages up to 132-154kV. This type of cable uses vulcanised
polyethylene insulation, which is solid insulation extruded onto the conductor
during cable manufacture. For high quality insulating properties, the raw
materials must be free of even minute contaminants and the extrusion and
vulcanising process must ensure homogeneity and absence of voids and
moisture in the insulation. Compared with oil-filled cable it is considered to be a
simplified technology. According to Karlstrand et al. [12], During the last
decade, no other power cables have had such a high rate of improvement as
XPLE cable technology. Improvements were made possible due to the overall
cost savings, along with environmental focus and de-regulation of electricity
markets which makes XLPE cable systems more attractive solutions where they
were not even an option in the past [9]. Figure 5.3 shows typical XLPE
underground cable as manufactured by Olex in Melbourne.

Figure 5.3: Typical XLPE underground cable [33]


Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

123

Chapter 5: Underground Power Networks

Gas Insulated Lines (GIL) cable

The GIL cable has achieved high system reliability by means of the austerity of
its design. This design consists of an aluminium conductor supported by
insulators and spacers with a pressurised gas compartment which is covered by
an aluminium envelope. The technology has established its reliability in more
than 3,000 km and 30 years of operation exclusive of main failures. Hitherto,
GIL cables advantages have been limited to special application. Nevertheless,
they turn out to be an economical solution for long distance application with the
introduction of site assemblage, standardization of its components and better
design. Yet a major cost reduction could be accomplished through highly
standardized GIL units, developing automated orbital welding machines and
pipeline laying methods [7, 34]. Figure 5.4 shows GIL cable design.

Figure 5.4: GIL cable design [34]

According to Koch et al. [34], the first US Gas Insulated Transmission line
installed in 1972 still operates today at the Public Service Electric and Gas
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

124

Chapter 5: Underground Power Networks

Company (PSEG) Hudson Generating station in New Jersey, while in 1974


Europe installed the First Gas Insulated Transmission Line to connect the
electrical generator of a hydro pump storage plant in Schluchsee, Germany.
The GIL went into commission in 1975 and up to now it has been in service
without interruption. A section of 700 meters of the line was installed in a tunnel
in the mountain, nonetheless, this GIL is the longest application at 420 kV
voltage level in the world, while the worlds longest GIL installation with 20 km
single phase length is the Shinmeika-Tokai Line in Chubu, Japan. Currently
nearly 200 kilometers of GIL are installed worldwide at voltage levels from 135
to 800 kV. The GIL applications include high voltage substations, power
generation plants and areas with severe environmental restrictions. Moreover,
GIL has a flexible design, where circuit length can vary between 10 meters to
kilometers in length, in addition to all different climate conditions from the low
temperatures in Canada to the high ambient temperatures in Saudi Arabia or
Singapore, or rough conditions in Europe or South Africa.

The importance of GIL in configurations is clearly represented by an idea of


installing a double-circuit GIL in the pilot tunnel of the new planned railway
galleries between Italy and Austria through the Brenner Pass. Another aspect of
the GIL system is isolation from surroundings because the entire high voltage
system including insulators is entirely sealed inside the aluminium field. The
magnetic field effect in any GIL arrangement normally is tremendously low due
to the shielding effect of the opposing currents flowing in the field, therefore, this
feature is crucial when extremely low magnetic field levels are demanded, for
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

125

Chapter 5: Underground Power Networks

example in countries with highly restrictive magnetic field regulations.


Meanwhile the limitation of this technology may well include the high cost as
well as the cable flexibility, where cable installation requires a direct route,
therefore, to achieve bending of the cable a small number of straight sections or
elbow sections can be used [34, 35].

High Temperature Superconductive (HTS) cable

HTS cable has an exclusive feature: the ability to conduct electricity without
resistive losses; this feature grants a potential for increasing the reliability of the
cable, hence, the power system. As opposed to conventional power cables,
HTS cable utilises high-tech underground cable technology; it presents not only
advanced power transfer mechanism with minimum losses and more compact
design of power applications, but also a better power flow absorption in the
networks at the same voltage levels. A high current rate and higher capacity
than conventional overhead lines or underground cables at similar voltage, is
another unique characteristic of HTS cable which is an outcome of its low
electric losses which are about < 1% compared with about 8% for conventional
cables of low to medium voltage range. HTS cable technology allows an
enormous growth in power transmission capacity, thus HTS cable has the
potential of becoming a practicable solution to power transmission dilemmas.
Other advantages are the ability to carry current of up to 5 times more than
conventional underground power cables, power evaluation of up to 10 times
more than the same thickness copper wire and the transmission of the power
can be done at lower voltage. The delivery of an extra capability is vitally
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

126

Chapter 5: Underground Power Networks

advantageous especially in highly congested cities. Meanwhile, transmissions


at lower level voltages are more approachable; they have the potential to
reduce supplementary generation by transmitting a larger portion of generated
power and they provide, in commission, cost savings. In the same token, this
technique may well decrease or even eliminate numbers of transformers and
related equipment, savings also in building extra substations, consequently
reduction in power systems costs and declining system vulnerability [36].
Figure 5.5 shows HTS cable as developed by Ultera, Denmark.

Figure 5.5: Typical HTS cable

A HTS cable does show a promising future. Nevertheless, the significant ordeal
of this technology has always been the high cost associated with the cost of
superconductive materials on top of the cable-cooling cost which is essential for
its normal operation temperature (-208C for current HTS cables). In an attempt
to reduce the second most expensive component of HTS cable system, a new

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

127

Chapter 5: Underground Power Networks

cryogenic electrical insulator design has been developed to reduce costs by 4050%, and it cuts the energy losses by 50%; the estimated cost of HTS
conductor required to transmit 1 kA over 1 m length using HTS cables is
approximately 11 EUR/kAm. In the meantime, highly reliable cable cooling
technology has been developed aiming at longer service life for longer service
intervals to reduce maintenance costs. All those incentives will make HTS cable
technology more practically feasible, but industry scale production is necessary
to bring the cost down considerably in the longer run [36]. The first commercial
product in 2006 was presented at the Hannover Messe 24-28 April 2006.
Although HTS cable is still in the research and development phase, the forecast
predicts a rational technical and economic alternative for power systems. The
market expectation for superconductor products is anticipated to intensify to
near US$5 billion by the year 2010 and to US$38 billion by 2020 [36].

5.5.3 Innovation aspects


New ideas which enhance reliability, efficiency and lower the cost of installation
and maintenance are contributing significantly in the development of
underground cable networks. These ideas cover various phases of the
underground systems. A few ideas are identified as follows:

Cable tunnel

Most urban underground cables run in congested streets, which require part of
the traffic being diverted, often for a long time, causing disruption to traffic flow,

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

128

Chapter 5: Underground Power Networks

parking and pedestrians in the area. Using a tunnel has several advantages
over conventional cable burial technique:

impact on traffic flow and other utilities would be minimal;

shorter outages are required to connect;

ease of access for maintenance and testing;

secure cable environment for 100 years;

direct tunnel route will results in reduction in cable length.

As an extra benefit, cable tunnel are naturally ventilated, where cables are laid
in vertical snaking on saddles with spacing of 7.2 m in horizontal and 0.6 m in
vertical direction; tunnel temperatures are permanently monitored using fibre
optic Distributed Temperature Sensor (DTS) [18, 37].

Fibre optic sensing system

Although some methods are already in use to locate a fault, the cable needs to
be removed from service and connected to detection equipment, but locating a
fault in underground system can take extensive time and effort. A new method
is integrating Fibre Optic Distributed Temperature (FODT) sensor into the cable.
This sensor can find the fault immediately by applying fault detection of XLPE
installed underground cable in a resistance grounded system. The maximum
detection distance, distance resolution and processing time for fault location are
10km, 1m and 30s respectively [38, 39].
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

129

Chapter 5: Underground Power Networks

Underground object radar


Underground assets maps, if they exist, are often inaccurate, incomplete or out
of date, and the use of metal detectors to find these assets often proves
disappointing. Researchers have developed a new Ground-Penetrating Image
Radar (GPIR) system that creates sharp, three-dimensional (3-D) images of
underground lines and objects. This system can be utilised to reduce operating
and maintenance costs, by reducing unnecessary excavations and lowering the
risk of damaging other assets [38, 40].

5.6 Underground Construction


To put cables underground, there are a couple of conventional practical options
available, either using trenching technique or boring technique. The decision is
based on the geology of the area that the underground cable will be routed
through. Determining the best scenario for each individual site can minimise
time and efforts and increase efficiency overall.

Trenching: This technique involves an open cut along the edges of the trench to
avoid damaging the surrounding area and then excavation work will be carried
out, in general, using a tracked excavator. In some cases where space is an
issue, a site plan to redirect traffic or limiting time of work needs to be
implemented. Utilising the site for traffic flow will be a big challenge itself, e.g.
excavated materials should be moved to a temporary area. If rocks are present,
a hydraulic breaker will be used. This is the most common tool used to break

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

130

Chapter 5: Underground Power Networks

rock and it can be swapped with the excavators bucked in a short time with
limited vibration impact operation. There are limited cases where explosives are
used as an alternative to hydraulic tools. Precautions should be taken under
engineering supervision to make sure that blasts will not produce overwhelming
vibration [32, 41].

Boring: There are two types of boring technique, straight and directional.
Straight boring uses a kind of rotating drill to make a direct hole through the
ground. The direction of the boring is determined to a certain extent once the
drilling starts. The operator cannot adjust the direction afterwards. The drilling
machine is placed in a pit below the ground level and a similar pit dug some
distance from the first pit, which becomes the ending point of the drilling.
Directional boring involves drilling a straight or curved hole. Boring technique is
commonly used in crossing roads which can be a tough and an expensive
process, which depends on the size of the drilled hole and soil type [9].

Cable Laying: The cables can be delivered to the site on large drums, typically
4m in diameter. Due to height restrictions, these drums are transported by a low
loader. Due to the cables high mass and large transport drum size the amount
of cable that can be handled in a single length is limited. Therefore a joint is
required at each interval along the route. Jointing employs highly skilled
techniques to provide a high quality electrical connection. The insulation is then
reconstructed across the joint. The joint is contained within an insulating and
waterproofing casing for final protection. Joint bay excavations are wider than
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

131

Chapter 5: Underground Power Networks

for a normal trench to provide a suitable working area; this bay should be kept
clean and dry for jointing operations. It is usually lined with concrete. At joint
positions, a link box is located within 10m and contains electrical equipment
associated with earthing of cable sheaths [32].

Backfill and Surface Reinstatement: The trench can be backfilled with materials
such as crushed rock or selected sand, which assist in conducting heat
generated in the cable. Failure to meet such conditions will cause premature
cable faults. Plastic protective slaps and plastic waring tapes are buried within
the backfill to provide protection and permanent identification of buried cables.
The surface can then be reinstated in a manner consistent with land use e.g. in
the form of road pavement or regressed for open areas [32].

Retirement of Overhead Assets: All poles, cross-areas, insulators, switchgear


and associated hardware and conductors, including old public lighting poles
have to be removed safely and disposed of in an appropriate manner. All pole
holes are to be filled with suitable materials to the final finished surface level
[32].

Constructing underground cables can be determined by the nature of the route


and type of cable installation. In general, for highly congested areas like
shopping strips, the recommended method would be installing the cable in
ducts where lengths of cables and equipment are installed in ducts and
manholes to accommodate for future cable maintenance and replacement. In

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

132

Chapter 5: Underground Power Networks

using this method there is less disturbance for the area which makes it relatively
faster than other methods [29].

Other forms of installation can be used where direct burial in a trench is used. It
enables long lengths of cable to be installed and offers saving in terms of
building ducts and manholes; also there will be fewer joints in the route which
increases the overall reliability of the cable. Sharing the ducts or trench with
other utilities can reduce the overall cost of cable installation, but coordination
issues can subdue such savings [29].

There are cases where installation can be done using boring technique
especially in sandy areas; this will eliminate the cost of trenching and backfilling.
This type of installation can be used in road crossing or under river [29].

5.7 Conclusion
It has become mandatory for most modern cities worldwide to use underground
power cables. This demonstrates that undergrounding has become feasible
economically and technologically. Various advantages have been presented
about underground cables. However, there are significant challenges in the
underground network as much as it has benefits, it is essential to carefully
design and implement an underground power network. In line with this, the next
chapter discusses the development and analysis of a Victorian hybrid
underground power network, where although conventional XLPE cables are

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

133

Chapter 5: Underground Power Networks

used, new cable technology in the form of HTS cables was visualised to be
utilised.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

134

Chapter 6: Development and Analysis of Victorian underground power network model

CHAPTER 6
DEVELOPMENT AND
ANALYSIS OF VICTORIAN
UNDERGROUND POWER
NETWORK MODEL
6.0 Introduction
The general overview of underground power networks and cable technologies
was presented in Chapter 5. This chapter discusses about the proposed
Victorian underground network model. Load flow analysis was used in analysing
the Victorian network. Section 6.1 provides details about the Victorian
underground power network model. This model is based on sub-models
developed separately then combined together to form the overall underground
model. A load flow analysis is carried out on the sub-models where the results
obtained from this study are compared with results obtained from other models
developed in pervious sections and to be developing in next chapter.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

135

Chapter 6: Development and Analysis of Victorian underground power network model

6.1 WMTS 2007 Underground Model


This model comprises multiple sub-models: these include the 66kV and 22kV
WMTS terminal station loops which as indicated earlier in Figure 4.1. After
obtaining the load flow analysis of the two voltage levels, a submission of all
power losses, which basically represents the loading demand of WMTS for the
year 2007, is identified to undergo further analysis.

6.1.1 EDSA WMTS 66kV underground sub-model


The configuration of this base sub-model is set to closely match the overhead
sub-model presented in Section 4.2 with the exception that overhead lines are
replaced with underground cables. The 66kV XLPE Olex underground cable
parameters were used in this sub-model; full cable information is given in
Appendix F.

It worth stating that the load demand of the year 2007 which was used in this
sub-model was obtained from Citipower 2007 planning report [28].

The model shown in Figure 6.1 displays a summary of the load flow analysis
results situated close to the bus, line or transformer. The summary includes an
arrow that reveals the direction of power flow. Real and reactive power are also
shown close to each bus, line or transformer in terms of positive values which
denote when power flow direction is out from the bus and vice versa; in other
words, negative values have been applied for power flow direction into the bus.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

136

Chapter 6: Development and Analysis of Victorian underground power network model

Accordingly, summing up of the four power flow values for each line or feeder
will provide real and reactive power losses in the specific line.

The figure shows all feeders consist of a single circuit or single cable, as
compared to the WMTS 66kV overhead sub-model in Section 4.2.1; the
grounds for such a move is that the 66kV XLPE cable has a current rate of
1260A. This rating is considerably high and in some cases as much as twice the
66kV overhead lines rating. Therefore, instead of under utilising the cable to
around 40% of its full capacity, a single cable with utilisation of over 80% is
employed; bearing in mind the n-1 redundancy configuration is maintained.

Table 6.1 illustrates the bus results of load flow analysis performed on the
WMTS 66kV sub-model. The table also lists bus parameters including name,
real and reactive generated powers, real and reactive static loads and load flow
results from which the real and reactive power losses are obtained with bus
current rating and power factor incorporated.

Table 6.2, summarises load flow results obtained in Table 6.1. The table shows,
in two different columns, the power delivered to and from the line, and in the last
two columns it lists the power difference or power losses. The total real power
losses are found to be 159.1 kW; in addition the total reactive power was found
to be -45215 kVAR.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

137

Chapter 6: Development and Analysis of Victorian underground power network model

Figure 6.1: WMTS 66kV underground sub-model


Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

138

Chapter 6: Development and Analysis of Victorian underground power network model

Table 6.1: WMTS 66kV underground EDSA load flow bus results
Bus Info Generation Static Load
Load Flow Results
--------------- ----------------- ------------------------ ----------------------------------------------Name
MW MVAR MW MVAR To Bus Name MW MVAR Amp %pf
-------------- ------- -------- ------- --------- ------------------- --------- ---------- ------- -------Sub JA 66 0.00 0.00 0.00 0.00
Sub LQ
30.74 28.57 369 73.3
Sub JA 66 0.00 0.00 0.00 0.00
Sub LQ
30.74 26.79 362 75.4
Sub VM 66
4.23
2.68 51 84.4
WMTS 66
-27.47 -23.17 298 76.4
WMTS 66
-27.47 -23.17 298 76.4
Sub LQ 66 0.00 0.00 0.00 0.00
Sub JA 66
-30.73 -27.48 362 74.6
Sub VM 66
-14.57 -13.86 170 72.5
Sub VM 66
-14.57 -13.86 170 72.5
Sub NC 66 0.00 0.00 0.00 0.00
Sub WB 66 -2.41 -3.62 38 55.4
WMTS 66
-8.2
-6.44 75 78.6
Sub VM 66 0.00 0.00 0.00 0.00
Sub JA 66
-4.23 -4.06 51 72.1
Sub LQ 66
14.57 12.71 170 75.3
Sub LQ 66
14.57 12.71 170 75.3
Sub W 66
12.6
9.62 139 79.5
Sub WA 66
13.29 10.27 148 79.1
Sub WA 66
13.29 10.27 148 79.1
WMTS 66
-32.18 -26.73 351 76.9
WMTS 66
-32.18 -26.73 351 76.9
WMTS 66
-32.18 -26.73 351 76.9
Sub W
0.00 0.00 0.00 0.00
Sub VM 66
-12.59 -11.4 139 74.1
Sub WA 66
12.59 11.4 151 74.1
Sub WA 66 0.00 0.00 0.00 0.00
Sub VM 66
-13.29 -12.15 148 73.8
Sub VM 66
-13.29 -12.15 148 73.8
Sub W 66
-12.59 -11.61 151 73.5
Sub WB 66 0.00 0.00 0.00 0.00
Sub NC 66
2.41 -2.44 38 70.2
WMTS 66
-10.76 -5.26 94 89.8
WMTS 66 0.00 0.00 0.00 0.00
Sub JA 66
27.49 20.07 298 80.8
Sub JA 66
27.49 20.07 298 80.8
Sub NC 66
8.2
-2.6
75 95.3
Sub VM 66
32.21 23.96 351 80.2
Sub VM 66
32.21 23.96 351 80.2
Sub VM 66
32.21 23.96 351 80.2
Sub WB 66
10.76 -0.26 94 100
-------------------------------------------------------Total losses 0.15 -45.25

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

139

Chapter 6: Development and Analysis of Victorian underground power network model

Table 6.2: WMTS 66kV underground losses


Branch
From -> To Flow To -> From Flow Losses
----------------- ------------------------ ------------------------ -------------------------------------Name
MW
MVAR
MW
MVAR
kW kVAR
---------------------- ------------- ----------------- ------------- ----------------- -------- ----------LQ-JA
-30.734 -27.476
30.741
26.789
7.1
-687.4
VM-JA
-4.226
-4.056
4.226
2.681
0.2
-1375.5
VM-LQ1
14.568
12.712
-14.565 -13.857
2.6
-1144.7
VM-LQ2
14.568
12.712
-14.565 -13.857
2.6
-1144.7
VM-W
12.595
9.623
-12.592 -11.401
2.7
-1778
VM-WA1
13.295
10.266
-13.292 -12.146
3.3
-1879.7
VM-WA2
13.295
10.266
-13.292 -12.146
3.3
-1879.7
WA-W
-12.592 -11.61
12.592
11.401
0.4
-208.8
WB-NC
-2.41
-3.624
2.41
-2.445
0.2
-6068.7
WMTS-JA1
27.493
20.066
-27.471 -23.17
22.5 -3104.4
WMTS-JA2
27.493
20.066
-27.471 -23.17
22.5 -3104.4
WMTS-NC
8.2
-2.596
-8.196
-6.437
3.6
-9033.3
WMTS-VM1
32.206
23.963
-32.178 -26.726
28.1 -2763.4
WMTS-VM2
32.206
23.963
-32.178 -26.726
28.1 -2763.4
WMTS-VM3
32.206
23.963
-32.178 -26.726
28.1 -2763.4
WMTS-WB
10.761 -0.26
-10.757 -5.256
3.8
-5515.5
--------------------------------------------------Total power losses
159.1 -45215

WMTS 66kV lines real and reactive power losses are shown in Figure 6.2. The
figure demonstrates that the power losses are line impedance dependent. As
can be observed, cable WMTS JA1 is longer in length than its counterpart
WMTS VM1, therefore its real and reactive power losses are more; the clear
reason for that is the higher impedance which in turn causes higher power
losses.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

140

Chapter 6: Development and Analysis of Victorian underground power network model

WMTS 66kV Underground Cable Losses

LQ
-J
A
VM
VM JA
-L
Q
VM 1
-L
Q
2
VM
VM -W
-W
VM A1
-W
A2
W
AW
W
W B-N
M
TS C
W -JA
M
TS 1
W -JA
2
M
T
W SN
M
TS C
W
VM
M
TS 1
W -V
M
M
TS 2
W -VM
M
TS 3
-W
B

1000
0
-1000
-2000
-3000
-4000
-5000
-6000
-7000
-8000
-9000
-10000

kW
kVAR

Figure 6.2: WMTS 66kV underground cables power losses

6.1.2 EDSA WMTS 22kV underground sub-model I


The configuration of this base sub-model has many similarities to the WMTS
22kV sub-model exhibited earlier in Section 4.2.3, which closely matched the
existing Citipower section of the network with the exception that overhead lines
are replaced with 22kV XLPE underground cables. Again the 2007 zone
substation loading demand parameters were acquired from the companys 2007
planning report [28]. The 22kV XLPE Olex underground cable parameters were
used in this sub-model. Full cable information is given in Appendix G.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

141

Chapter 6: Development and Analysis of Victorian underground power network model

Figure 6.3: WMTS 22kV underground sub-model I


Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

142

Chapter 6: Development and Analysis of Victorian underground power network model

An expected, finding from Figure 6.3 reveals many cables in the sub-model will
be operating over their 100% rating; these elements are identified by their
colour coding and one particular cable WMTS LS1 will exceed its 140% rating
under normal operation condition. Additionally there are more elements
identified when n-1 redundancy configuration is used. After identifying all the
elements over stressed in this sub-model, single or double circuits are added to
keep in line with the Citipower n-1 redundancy configuration. A 22kV XLPE
cable with a current rate of 325A which is commonly used by power utilities in
Melbourne is employed rather than the 22kV XLPE cable with 280A current
rating to enhance the capacity of the feeders and minimise the number of
parallel circuits required for normal and contingency operations. Figure 6.5
shows the updated WMTS 22kV underground sub-model where all elements
are operating under their 100% rating and n-1 Citipower redundancy
configuration is maintained.

The developed sub-model II in Figure 6.4 shows the WMTS terminal station
22kV section of the network base sub-model and a load flow analysis on the
model was carried out to obtain power loss figures. Again Figure 6.5 shows the
summary of the load flow analysis results situated close to the bus, line or
transformer.

The lists of bus parameters in Table 6.3 of WMTS 22kV sub-model comprises
name, real and reactive generated power, real and reactive static load and load

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

143

Chapter 6: Development and Analysis of Victorian underground power network model

flow results where real and reactive power losses can be obtained with bus
current rating and power factor incorporated as well.

The load flow results obtained in Table 6.3 are summarised in Table 6.4. The
table shows in two different columns the power delivered to and from the line
and in the last two columns it lists the power difference or power losses. The
total real power losses found to be 300.7 kW, in addition total reactive power
was found to be -3334 kVAR.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

144

Chapter 6: Development and Analysis of Victorian underground power network model

Figure 6.4: WMTS 22kV underground sub-model II


Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

145

Chapter 6: Development and Analysis of Victorian underground power network model

Table 6.3: WMTS 22kV underground sub-model II EDSA load


flow bus results
Bus Info
Generation Static Load Load Flow Results
------------------- ----------------- ----------------- -------------------------------------------------Name
MW MVAR MW MVAR To Bus Name MW MVAR Amp %pf
------------------- ------- ---------- ----- -------- -------------------- -------- --------- ------ ------Sub BSBQ 22 0.00 0.00
0.00 0.00 Sub J 22
-1.27 -0.87 41 82.6
Sub J 22
-1.22 -0.78 38 84.2
WMTS 22
-6.09 -4
189 83.6
WMTS 22
-5.71 -4.05 173 81.6
Sub DA 22
0.00 0.00
0.00 0.00 WMTS 22
-4.66 -3.16 147 82.8
WMTS 22
-4.6 -3.24 143 81.8
WMTS 22
-4.4 -2.8 136 84.4
Sub J 22
0.00 0.00
0.00 0.00 Sub BSBQ 22 1.27 0.65 41 89
Sub BSBQ 22 1.22 0.57 38 90.7
Sub LS 22
-3.98 -2.6 126 83.7
Sub LS 22
-3.98 -2.6 126 83.7
WMTS 22
-4.06 -2.77 126 82.6
WMTS 22
-4.06 -2.77 126 82.6
WMTS 22
-3.92 -2.49 119 84.4
Sub LS 22
0.00 0.00
0.00 0.00 Sub J 22
4
2.42 126 85.5
Sub J 22
4
2.42 126 85.5
WMTS 22
-6.9 -4.33 213 84.7
WMTS 22
-6.9 -4.33 213 84.7
WMTS 22
-7.14 -4.83 226 82.8
WMTS 22
0.00 0.00
0.00 0.00 Sub BSBQ 22 6.14 3.79 189 85.1
Sub BSBQ 22 5.76 3.25 173 87.1
Sub DA 22
4.68 3.06 147 83.7
Sub DA 22
4.62 2.91 143 84.6
Sub DA 22
4.42 2.7 136 85.3
Sub J 22
4.09 2.49 126 85.4
Sub J 22
4.09 2.49 126 85.4
Sub J 22
3.94 2.21 119 87.2
Sub LS 22
6.91 4.28 213 85
Sub LS 22
6.91 4.28 213 85
Sub LS 22
7.16 4.78 226 83.2
----------------------------------------------------Total losses 0.32 -3.32

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

146

Chapter 6: Development and Analysis of Victorian underground power network model

Table 6.4: WMTS 22kV underground sub-model II power losses


Branch
From -> To Flow
To -> From Flow
Losses
------------------------------------------------------ --------------------------------------------------Name
MW
MVAR
MW
MVAR
kW kVAR
---------------------- ------------- ----------------- ------------- ----------------- -------- ----------BSBQ-J1
-1.268
-0.866
1.27
0.65
1.7
-215.2
BSBQ-J2
-1.222
-0.782
1.223
0.567
1.7
-215.3
J-LS1
-3.98
-2.604
3.996
2.422
15.6 -181.9
J-LS2
-3.98
-2.604
3.996
2.422
15.6 -181.9
WMTS-BSBQ1 6.141
3.786
-6.095
-4
46.7 -213.8
WMTS-BSBQ2 5.757
3.249
-5.714
-4.046
43.7 -797.2
WMTS-DA1
4.677
3.064
-4.66
-3.16
17.4 -96.3
WMTS-DA2
4.62
2.909
-4.603
-3.238
17.2 -329.6
WMTS-DA3
4.421
2.705
-4.405
-2.803
16.3 -98.8
WMTS-J1
4.087
2.489
-4.062
-2.77
25.5 -281.3
WMTS-J2
4.087
2.489
-4.062
-2.77
25.5 -281.3
WMTS-J3
3.944
2.209
-3.919
-2.492
24.6 -283
WMTS-LS1
6.912
4.277
-6.896
-4.33
16.2 -53.2
WMTS-LS2
6.912
4.277
-6.896
-4.33
16.2 -53.2
WMTS-LS3
7.157
4.777
-7.141
-4.829
16.8 -52
--------------------------------------------------Total power losses
300.7 -3334

Figure 6.5 shows WMTS 22kV underground cables real and reactive power
losses; the figure demonstrates that the power losses are line impedance
dependent, as can be observed in that although line WMTS DA2 is same in
length as its counterpart WMTS DA3 however its real and reactive power
losses are much higher and the reason for that is the higher current passing
through it.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

147

Chapter 6: Development and Analysis of Victorian underground power network model

WMTS 22kV Underground Cable Losses


100
0
-100
-200
-300
-400
-500
-600
-700
-800

1
2
3
1
2
3
1
2
1
2
3
1
2
1
2
-J -J -LS -LS BQ BQ DA DA DA S-J S-J S-J -LS -LS -LS
Q
Q
J
J
T
T
T S S
S
S S S
S
B B
S
-B S-B MT MT MT WM WM WM MT MT MT
BS BS
S
T
T W W W
W W W
M M
W W

kW
kVAR

Figure 6.5: WMTS 22kV underground sub-model II power losses

As a conclusion for this section, the summation of power losses found in 22kV
and 66kV loops are presented as the total power losses in the WMTS section of
Citipower for the existing network configuration with 2007 loading demand.

Total real power losses = 300.7 + 159.1 = 459.8 kW


Total reactive power losses = -3334 + (-45215) = -48549 kVAR

6.1.3 EDSA WMTS 22kV underground sub-model III


The configuration of this base sub-model has many similarities to the WMTS
66kV sub-model exhibited earlier in Section 4.2.3, which closely matches the
existing Citipower section of the network with the exception that overhead lines
are replaced with 22kV XLPE underground cables. However, 66kV cables have
been used in this model as one step forward towards upgrading the zone

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

148

Chapter 6: Development and Analysis of Victorian underground power network model

substations voltage level from 22kV to 66kV which is part of Citipower future
planning. Again the 2007 zone substation loading demand parameters were
acquired from the companys 2007 planning report. The 22kV XLPE Olex
underground cable parameters were used in this sub-model; full cable
information is given in Appendix F.

The developed sub-model III in Figure 6.6 shows the WMTS terminal station
22kV section of the network base sub-model; a load flow analysis on the model
was carried out to obtain power loss figures. Again Figure 6.7 shows the
summary of the load flow analysis results situated close to the bus, line or
transformer.

The lists of bus parameters in Table 6.5 of the WMTS 22kV sub-model
comprise name, real and reactive generated power, real and reactive static load
and load flow results where real and reactive power losses can be obtained with
the bus current rating and power factor incorporated as well.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

149

Chapter 6: Development and Analysis of Victorian underground power network model

Figure 6.6: WMTS 22kV underground sub-model III


Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

150

Chapter 6: Development and Analysis of Victorian underground power network model

Table 6.5: WMTS 22kV underground sub-model III EDSA load


flow bus results
Bus Info
Generation Static Load Load Flow Results
------------------- ----------------- ----------------- -------------------------------------------------Name
MW MVAR MW MVAR To Bus Name MW MVAR Amp %pf
------------------- ------- ---------- ----- -------- -------------------- -------- --------- ------ ------Sub BSBQ 22 0
0
0
0
Sub J 22
-1.08
-0.85 36 78.5
WMTS 22
-13.22 -8.85 418 83.1
Sub DA 22
0
0
0
0
WMTS 22
-6.83
-4.6 215 82.9
WMTS 22
-6.83
-4.6 215 82.9
Sub J 22
0
0
0
0
Sub BSBQ 22 1.08
0.57 36 88.4
Sub LS 22
-8.56
-5.81 274 82.8
WMTS 22
-10.03 -6.8 316 82.8
Sub LS 22
0
0
0
0
Sub J 22
8.57
5.65 274 83.5
WMTS 22
-21.51 -14.3 680 83.3
WMTS 22
0
0
0
0
Sub BSBQ 22 13.26 8.82 418 83.3
Sub DA 22
6.84
4.48 215 83.6
Sub DA 22
6.84
4.48 215 83.6
Sub J 22
10.06 6.61 316 83.6
Sub LS 22
21.54 14.41 680 83.1
----------------------------------------------------Total losses 0.13
-0.79

The load flow results obtained in Table 6.5 are summarised in Table 6.6. The
table shows, in two different columns, the power delivered to and from the line,
and in the last two columns it lists the power difference or power losses. The
total real power losses were found to be 110 kW; in addition the total reactive
power was found to be -786.9 kVAR.

Real and reactive power losses of WMTS 22kV underground cables are
exhibited in Figure 6.7. The figure demonstrates that the power losses are line
impedance dependent, as can be observed clearly in the fact that although line
WMTS BSBQ1 is shorter in length than its counterpart WMTS BSBQ2,

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

151

Chapter 6: Development and Analysis of Victorian underground power network model

however, its real and reactive power losses are higher and the reason for that is
the higher current passing through it, which in turn causes higher power losses.

Table 6.6: WMTS 22kV underground sub-model III power losses


Branch
From -> To Flow
To -> From Flow
Losses
------------------------------------------------------ --------------------------------------------------Name
MW
MVAR
MW
MVAR
kW kVAR
---------------------- ------------- ----------------- ------------- ----------------- -------- ----------BSBQ-J
-1.076
-0.85
1.076
0.571
0.2
-278.9
J-LS
-8.56
-5.807
8.572
5.652
12.3 -155.3
WMTS-BSBQ
13.259
8.818
-13.221 -8.853
37.1 -34.7
WMTS-DA1
6.838
4.483
-6.833
-4.601
4.7
-118.3
WMTS-DA2
6.838
4.483
-6.833
-4.601
4.7
-118.3
WMTS-J
10.056
6.613
-10.03
-6.802
26.1 -189
WMTS-LS
21.537
14.408
-21.512 -14.301
24.9 107.6
--------------------------------------------------Total power losses
110.0 -786.9

WMTS 22kV Underground Cable Losses

-L
S
W
M
TS

-J
W
M
TS

A2
W
M
TS

-D

A1
-D
W
M
TS

BQ
-B
S

W
M
TS

JLS

BS
BQ

-J

150
100
50
0
-50
-100
-150
-200
-250
-300
kW
kVAR

Figure 6.7: WMTS 22kV underground sub-model III power losses

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

152

Chapter 6: Development and Analysis of Victorian underground power network model

In line with the Citipower future projects which are planned for the next 5 year
period, an upgrade of existing 22kV stations to a high capacity 66kV CBD type
station is due with ultimate firm capacity enhancement. This will assimilate the
need for a new transmission network connection and the additional capacity to
reinforce the loading of other Citipower stations. The result of this model
confirms the prediction of low cable loading, where one cable recorded below
3%. Table 6.7 lists the WMTS 22kV underground sub-model III cable loading.

Table 6.7: WMTS 22kV underground sub-model III cable


loading
Branch Name
-----------------------BSBQ-J
J-LS
WMTS-BSBQ
WMTS-DA1
WMTS-DA2
WMTS-J
WMTS-LS

Ampacity Loading Amp


---------------- -------------------1260
36.41
1260
274.44
1260
417.89
1260
214.58
1260
214.58
1260
315.87
1260
680.04

% Loading
--------------2.9
21.8
33.2
17
17
25.1
54

A graphic representation of Table 6.7 is illustrated in Figure 6.8; it can be clearly


noted that the cable loading off all branches of model III are very low. However,
this low load rating is vital for future network expansion or load growth; in the
coming subsections future demand will be examined on this model to identify
the cable current utilisation and expected future capacity potential.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

153

Chapter 6: Development and Analysis of Victorian underground power network model

Branch Loading
800

60

700

50
40

500
400

30

300

Amp

600

20

200
10

100

-L
S
W
M
TS

-J
W
M
TS

A2
W
M
TS

-D

A1
-D
W
M
TS

BQ
-B
S
W
M
TS

BS
BQ

JLS

-J

Loading Amp
Loading %

Figure 6.8: WMTS 22kV underground sub-model III branch loading

6.2 WMTS Underground 2011 Forecast Model


This model consists of a series of sub-models; these include the 66kV and 22kV
WMTS terminal station loops as indicated earlier in Figure 4.1. Forecast load
demands for the year 2011 are used in these sub-models. After obtaining the
flow analysis of the two voltage levels, a submission of all power losses, which
basically represents the loading demand forecast of the WMTS for the year
2011, is identified for further analysis.

6.2.1 WMTS 66kV underground 2011 forecast sub-model


In this sub model, a 2011 forecast load demand is used to determine the new
overall load flow and identify the elements under stress in the network. After the
first attempt to run the load flow analysis, the load flow analysis revealed no
element of the network was over stressed or exceeds their 100% rating; also
the percentage of loading is less compared to the WMTS overhead sub-model
presented in Section 4.3.1. In other words the proposed increased load will not
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

154

Chapter 6: Development and Analysis of Victorian underground power network model

exceed the cable rating; therefore, the overall network capacity will be
enhanced and can meet the expected growth without installing additional
circuits. Nevertheless, compared to overhead sub-model in Section 4.3.1, fewer
circuits have to be installed to meet expected load growth. Figure 6.9 shows the
WMTS 66kV underground 2011 forecast demand sub-model.

Figure 6.9 reveals the expected finding that many elements in the sub-model
will not be stressed or exceeds their 100% loading rating. The Citipower n-1
redundancy configuration has been met in this sub-model with fewer circuits
installed; consequently, the overall cost of undergrounding will be reduced.
Table 6.8 illustrates the bus results of flow analysis performed on the WMTS
66kV underground 2011 forecast sub-model. The table lists bus parameters
including the current rating.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

155

Chapter 6: Development and Analysis of Victorian underground power network model

Figure 6.9: WMTS 66kV underground 2011 forecast sub-model


Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

156

Chapter 6: Development and Analysis of Victorian underground power network model

Table 6.8: WMTS 66kV underground 2011 updated forecast load


flow results
Bus Info Generation Static Load
Load Flow Results
--------------- ----------------- ------------------------ ----------------------------------------------Name
MW MVAR MW MVAR To Bus Name MW
MVAR Amp %pf
-------------- ------- -------- ------- --------- ------------------- --------- ---------- ------- -------Sub JA 66 0.00 0.00 0.00 0.00
Sub LQ 66
44.46 37.99 521 76
Sub LQ 66
44.46 37.99 521 76
Sub VM 66
13.81 10.49 161 79.6
WMTS 66
-69.64 -67.44 838 71.8
WMTS 66
-69.64 -67.44 838 71.8
WMTS 66
-69.64 -67.44 838 71.8
Sub LQ 66 0.00 0.00 0.00 0.00
Sub JA 66
-44.44 -38.61 521 75.5
Sub JA 66
-44.44 -38.61 521 75.5
Sub VM 66
-11.96 -11.75 142 71.3
Sub VM 66
-11.96 -11.75 142 71.3
Sub NC 66 0.00 0.00 0.00 0.00
Sub WB 66 -4.1
-5.64 36 58.8
WMTS 66
-16.94 -15.99 161 72.7
Sub VM 66 0.00 0.00 0.00 0.00
Sub JA 66
-13.81 -11.83 161 75.9
Sub LQ 66
11.96 10.62 142 74.8
Sub LQ 66
11.96 10.62 142 74.8
Sub W 66
31.19 28.44 374 73.9
Sub WA 66
32.92 30.12 395 73.8
WMTS 66
-72.63 -69.46 869 72.3
WMTS 66
-72.63 -69.46 869 72.3
Sub W 66 0.00 0.00 0.00 0.00
Sub VM 66
-31.17 -30.06 374 72
Sub WA 66
31.17 30.06 386 72
Sub WA 66 0.00 0.00 0.00 0.00
Sub VM 66
-32.9 -31.82 395 71.9
Sub W 66
-31.17 -30.25 386 71.8
Sub WB 66 0.00 0.00 0.00 0.00
Sub NC 66
4.1
-0.38 36 99.6
WMTS 66
-23.2 -18.71 235 77.8
WMTS 66 0.00 0.00 0.00 0.00
Sub JA 66
69.81 65.5 838 72.9
Sub JA 66
69.81 65.5 838 72.9
Sub JA 66
69.81 65.5 838 72.9
Sub NC 66
16.96 7.14 161 92.2
Sub VM 66
72.82 67.55 869 73.3
Sub VM 66
72.82 67.55 869 73.3
Sub WB 66
23.22 13.38 235 86.6
-------------------------------------------------------Total losses 1.01 -38.19

Table 6.9, summarises load flow results obtained in Table 6.8. The table shows,
in two different columns, the power delivered to and from the line and in the last
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

157

Chapter 6: Development and Analysis of Victorian underground power network model

two columns it lists the power difference or power losses. The total real power
losses were found to be 1028.7 kW; in addition the total reactive power was
found to be -38208.2 kVAR.

Table 6.9: WMTS 66kV underground 2011 updated forecast


lines losses
Branch
From -> To Flow To -> From Flow Losses
----------------- ------------------------ ------------------------ -------------------------------------Name
MW
MVAR
MW
MVAR
kW kVAR
---------------------- ------------- ----------------- ------------- ----------------- -------- ----------LQ-JA1
-44.444 -38.61
44.459
37.991
14.7 -618.3
LQ-JA2
-44.444 -38.61
44.459
37.991
14.7 -618.3
VM-JA
-13.812 -11.83
13.815
10.493
2.5
-1337.4
VM-LQ1
11.965
10.615
-11.963 -11.748
1.8
-1132.4
VM-LQ2
11.965
10.615
-11.963 -11.748
1.8
-1132.4
VM-W
31.188
28.437
-31.169 -30.06
19
-1623.4
VM-WA
32.92
30.123
-32.898 -31.824
22.5 -1700.3
WA-W
-31.166 -30.25
31.169
30.06
2.3
-189.8
WB-NC
4.103
-0.377
-4.103
-5.637
0.8
-6014.1
WMTS-JA1
69.809
65.498
-69.637 -67.441
172.3 -1943
WMTS-JA2
69.809
65.498
-69.637 -67.441
172.3 -1943
WMTS-JA3
69.809
65.498
-69.637 -67.441
172.3 -1943
WMTS-NC
16.961
7.136
-16.939 -15.991
21.5 -8855.4
WMTS-VM1
72.824
67.552
-72.631 -69.464
192.7 -1912
WMTS-VM2
72.824
67.552
-72.631 -69.464
192.7 -1912
WMTS-WB
23.22
13.378
-23.196 -18.711
24.8 -5333.4
--------------------------------------------------Total power losses 1028.7 -38208.2

Figure 6.10 shows the WMTS 66kV line real and reactive power losses. The
figure demonstrates that the power losses are line impedance dependent, as
can be observed in the fact that although line WMTS VM3 is shorter in length
than its counterpart WMTS VM2, however its real and reactive power losses
are much higher. The interpretation for this is due to its current rating which is
less than WMTS VM2 yet it carries almost double the amount of current
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

158

Chapter 6: Development and Analysis of Victorian underground power network model

passing through as current always tends to pass through shorter paths; as a


result it will produce higher losses.

WMTS 66kV Underground 2011 Forecast Losses

LQ
-J
L Q A1
-J
A
VM 2
VM -JA
-L
V M Q1
-L
Q
VM 2
VM -W
-W
W A
A
W -W
W B
M -N
T C
W S-J
M A
T
1
W S-J
M A
T
2
W S-J
M A
W TS 3
M -N
T
W S-V C
M
T M1
W S-V
M M
TS 2
-W
B

1000
0
-1000
-2000
-3000
-4000
-5000
-6000
-7000
-8000
-9000
kW
kVAR

Figure 6.10: WMTS 66kV underground 2011 forecast power losses

6.2.2 WMTS 22kV underground 2011 forecast sub-model


Again the configuration of this base sub-model has many similarities to the
configuration of the sub-model in Section 4.3.1 where a load demand of 2011
forecast load demand is used to determine the new overall load flow and
identify the elements under stress in the network. After identifying all the
elements under stress in this sub-model, single or double circuits are added to
keep in line with Citipower n-1 redundancy configuration. Also new transformers
have been added or upgraded to enable the load flow analysis to converge.
Figure 6.11 shows the updated WMTS 22kV underground 2011 forecast submodel.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

159

Chapter 6: Development and Analysis of Victorian underground power network model

Figure 6.11: WMTS 22kV underground 2011 forecast sub-model


Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

160

Chapter 6: Development and Analysis of Victorian underground power network model

Table 6.10 shows the bus results of flow analysis performed on the WMTS
22kV underground 2011 forecast sub-model. The table lists bus parameters
including the current rating.

Table 6.10: WMTS 22kV underground 2011 updated forecast


load flow results
Bus Info
Generation Static Load Load Flow Results
----------------- ----------------- ----------------- ----------------------------------------------------Name
MW MVAR MW MVAR To Bus Name MW MVAR Amp %pf
----------------- ------ ---------- ------ --------- --------------------- ------- --------- ------- -----Sub BSBQ 22 0 0 0
0
Sub J 22
-1
-2.16 64 42.1
WMTS 22
-18.72 -13.21 607 81.7
WMTS 22
-17.55 -12.4 569 81.7
Sub DA 22
0 0 0
0
WMTS 22
-18.11 -13.38 594 80.4
WMTS22
-18.11 -13.38 594 80.4
Sub J 22
0 0 0
0
Sub BSBQ 22
1
-0.62 64 85.1
Sub LS 22
-6.97 -4.37 218 84.7
WMTS 22
-7.95 -5.38 248 82.8
WMTS 22
-7.91 -5.46 249 82.3
Sub LS 22
0 0 0
0
Sub J 22
6.97
4.18 218 85.8
WMTS 22
-16.36 -12.07 535 80.5
WMTS 22
-16.36 -12.07 535 80.5
WMTS 22
0 0 0
0
Sub BSBQ 22
18.8
13.48 607 81.3
Sub BSBQ 22
17.62 12.62 569 81.3
Sub DA 22
18.15 13.49 594 80.3
Sub DA 22
18.15 13.49 594 80.3
Sub J1 22
7.97
5.12 248 84.1
Sub J2 22
7.92
5.2
249 83.6
Sub LS1 22
16.38 12.11 535 80.4
Sub LS2 22
16.38 12.11 535 80.4
-------------------------------------------------------Total losses
0.3
-2.7

Table 6.11 summarises load flow results obtained in Table 6.10. The table
shows, in two different columns, the power delivered to and from the line and in
the last two columns it lists the power difference or power losses. The total real

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

161

Chapter 6: Development and Analysis of Victorian underground power network model

power losses were found to be 293.4 kW; in addition the total reactive power
was found to be -2694.4 kVAR.

Table 6.11: WMTS 22kV underground 2011 updated forecast


lines losses
Branch
From -> To Flow
To -> From Flow
Losses
------------------------------------------------------ --------------------------------------------------Name
MW
MVAR
MW
MVAR
kW kVAR
---------------------- ------------- ----------------- ------------- ----------------- -------- ----------BSBQ-J
-1.002
-2.16
1.004
-0.619
2
-2779.1
J-LS
-6.968
-4.374
6.975
4.183
7.2
-190.9
WMTS-BSBQ1 18.799
13.484
-18.721 -13.205
78.1 278.4
WMTS-BSBQ2 17.624
12.62
-17.551 -12.4
73.2 220.4
WMTS-DA1
18.15
13.494
-18.115 -13.376
35.4 117.7
WMTS-DA2
18.15
13.494
-18.115 -13.376
35.4 117.7
WMTS-J1
7.966
5.116
-7.95
-5.381
16.2 -264.9
WMTS-J2
7.924
5.199
-7.909
-5.464
15.1 -264.5
WMTS-LS1
16.38
12.107
-16.365 -12.071
15.4 35.4
WMTS-LS2
16.38
12.107
-16.365 -12.071
15.4 35.4
--------------------------------------------------Total power losses
293.4 -2694.4

Figure 6.12 shows the WMTS 22kV underground cables real and reactive
power losses. The figure demonstrates that the power losses are line
impedance dependent, as it can be observed that although line WMTS
BSBQ1 is shorter in length than its counterpart WMTS BSBQ2, however its
real and reactive power losses are much higher, and the reason for that is the
higher current passing through it causing higher losses.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

162

Chapter 6: Development and Analysis of Victorian underground power network model

Figure 6.12: WMTS 22kV underground 2011 forecast power losses

To sum up this section, the summation of power losses found in 22kV and 66kV
loops are presented as the total power losses in the WMTS section of Citipower
for the network configuration with a forecast 2011 loading demand.

Total forecast 2011 real power losses = 293.4 + 1028.7 = 1322.1 kW


Total forecast 2011 reactive power losses = -2694.4 + (-38208.2)
= -40902.6 kVAR

Figure 6.13 shows the power loss comparison for the Citipower WMTS section
of the underground network with power losses obtained from both 2007 and
2011 loading demand.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

163

Chapter 6: Development and Analysis of Victorian underground power network model

WMTS 22kV & 66kV Real and Reactive Power Losses Comparison

5000
0
-5000
-10000
-15000
-20000
-25000
-30000
-35000
-40000
-45000
2007

-50000
kW

kVAR

2011

Figure 6.13: WMTS 22kV and 66kV underground power loss comparison

As can be seen from the figure, the real losses for the forecast year 2011 are
almost 900 kW more than the losses for the year 2007. However, reactive
losses are almost 8000 kVAR less than the losses for the year 2007. This
observation can be interpreted as due to the high utilisation of cables expected
for the forecasted year, hence the negative reactance will be changed to
positive when cable current loading increased over approximately 50%. Also the
losses are confirming the high demand on power expected for the year 2011; a
matching proportional increase in the power loss is the conscience.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

164

Chapter 6: Development and Analysis of Victorian underground power network model

6.3 Citipower 2007 Underground Overall Power


Losses
Data for the remaining terminal stations loops of overhead network can be seen
in Figure 4.1. Most of this data was obtained from Citipower and its publications
from the public domain with the exception of the assumptions mentioned earlier
in Section 4.1. Separate sub-models were developed individually for each
terminal station with separate sections for 66kV and 22kV voltage levels.
Appendix I lists Citipower Terminal stations underground sub-models.

Following the flow analysis of the two voltage levels, a submission of all power
losses, which basically represents the loading demand of WMTS for the year
2007, is given in Tables 6.12 and 6.13 to undergo further analysis.

Table 6.12: Citipower 66kV underground overall lines losses


Branch Name
----------------------------------LQ-JA
VM-JA
VM-LQ1
VM-LQ2
VM-W
VM-WA1
VM-WA2
WA-W
WB-NC
WMTS-JA1
WMTS-JA2
WMTS-NC
WMTS-VM1
WMTS-VM2
WMTS-VM3

kW losses kVAR losses


---------------- --------------------7.1
-687.4
0.2
-1375.5
2.6
-1144.7
2.6
-1144.7
2.7
-1778
3.3
-1879.7
3.3
-1879.7
0.4
-208.8
0.2
-6068.7
22.5
-3104.4
22.5
-3104.4
3.6
-9033.3
28.1
-2763.4
28.1
-2763.4
28.1
-2763.4

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

165

Chapter 6: Development and Analysis of Victorian underground power network model

WMTS-WB
3.8
-5515.5
AR-BC
0.1
-3298.1
B-CW
0.1
-1479.1
BC-TK
2.4
-2642.8
CL-K
0.5
-2758.5
FR-MP
2.4
-721.2
FR-W
0.4
-736.5
NR-B
4.8
-1762.7
RTS-AR
5
-8381.3
RTS-CL
6.7
-7082.5
RTS-CW
12.8
-12224.5
RTS-EW
9.1
-7711.6
RTS-FR1
30.7
-4440.6
RTS-FR2
30.7
-4440.6
RTS-K
8
-3987.9
RTS-NR
33.2
-2300.1
RTS-SK
17
-5719.8
RTS-TK
7
-1759
SK-EW
1.2
-2217.8
W-MP
0.6
-946
E-PM
0
-1280
FBTS-AP
5.9
-4427.8
FBTS-E
0.7
-866.3
FBTS-FB
6.4
-2569.8
FBTS-MG
9.1
-2163.1
FBTS-PM
0.3
-1384.9
FBTS-SO1
4.7
-4117.7
FBTS-SO2
4
-4869.5
FBTS-WG
10.7
-896.3
MG-AP
0.3
-2126.4
WG-FB
0.7
-1238
L-Q
0.1
-4132
Q-HB
9.3
-8414.8
TSTS-HB
36.2
-10984.4
TSTS-L
39.6
-20098.9
EB-RD
0.4
-6388.5
SVTS-EB
14
-7346.1
SVTS-RD
7.1
-14665.7
---------------------------------------------------------------------Total overall power losses: 481.30
-217795.80

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

166

Chapter 6: Development and Analysis of Victorian underground power network model

Both the real and reactive power losses of Citipower 66kV underground cables
are shown in Figure 6.14. The figure demonstrates that the power losses are
line impedance dependent and the higher current passing and longer length of
line will result in higher power losses in that particular line.

The Citipower 22kV undergrounds real and reactive power losses are
summarised in Table 6.13.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

167

kW
kVAR

Chapter 6: Development and Analysis of Victorian underground power network model

H
B
-25000

-20000

-15000

-10000

-5000

5000

LQ
V -JA
M
-L
Q
VM 1
VM -W
-W
W A2
W BM NC
W TSM JA
T
W S-V 2
M
T M1
S
-V
M
AR 3
-B
BC C
-T
F K
R
-M
P
N
R
R -B
TS
R -CL
TS
R -E
TS W
-F
R R2
TS
R N
TS R
-T
W K
F -M
B
TS P
FB -A
TS P
FB -F
T B
FB S-P
T
M
S
-S
O
M 2
G
-A
P
TS L-Q

WMTS 66kV Overall Underground Cable Losses

TS
-

Figure 6.14: Citipower 66kV underground overall power losses


Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

168

Chapter 6: Development and Analysis of Victorian underground power network model

Table 6.13: Citipower 22kV underground overall lines losses


Branch Name
----------------------------------BSBQ-J1
BSBQ-J2
J-LS1
J-LS2
WMTS-BSBQ1
WMTS-BSBQ2
WMTS-DA1
WMTS-DA2
WMTS-DA3
WMTS-J1
WMTS-J2
WMTS-J3
WMTS-LS1
WMTS-LS2
WMTS-LS3
PR-R1
PR-R2
R-SM
R-SM2
RTS-PR2
RTS-PR3
RTS-R1
RTS-R2
RTS-R3
RTS-RP1
RTS-RP2
RTS-RP3
RTS-SM1
RTS-SM2
BTS-BK1
BTS-BK2
BTS-BK3
BTS-C2
BTS-C3
BTS-C4
BTS-F1
BTS-F2
BTS-F3
BTS-FF1
BTS-FF2
BTS-FF3
BTS-NS1
BTS-NS2

kW losses kVAR losses


---------------- --------------------1.7
-215.2
1.7
-215.3
15.6
-181.9
15.6
-181.9
46.7
-213.8
43.7
-797.2
17.4
-96.3
17.2
-329.6
16.3
-98.8
25.5
-281.3
25.5
-281.3
24.6
-283
16.2
-53.2
16.2
-53.2
16.8
-52
4.2
-467.6
4.4
-467.3
2.7
-387.7
2.5
-387.8
30.5
-236.8
30.5
-236.8
19.6
-80
19.6
-80
19.6
-80
13.1
-513.6
14.9
-447.7
13.5
-497.2
14.4
-375.1
13.7
-375.9
4
-209.4
4
-211.1
4
-211.1
11.7
-157.2
11.7
-157.2
11.7
-157.2
9.5
-191
9.1
-199.3
9.5
-191
25.1
-272
27.5
-246.4
27.5
-246.4
100.4
-432.6
100.4
-432.6

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

169

Chapter 6: Development and Analysis of Victorian underground power network model

BTS-NS3
100.4
-432.6
NT-TP1
29.4
-1465.8
NT-TP2
61.5
-676.9
--------------------------------------------------------------------Total overall power losses: 1051.30
-13857.30
Similarly, Citipower 22kV undergrounds real and reactive power losses are
graphically represented in Figure 6.15. The figure demonstrates that power
losses are line impedance dependent and the higher current passing and longer
length of line will result in higher power losses in that particular line.

A combined summation of power losses is found in Tables 6.11 and 6.12 for
22kV and 66kV loops which illustrate the total power losses in the Citipower for
the underground network configuration with a 2007 loading demand.

Total real power losses = 481.30 + 1051.30 = 1532.6 kW


Total reactive power losses = -217795.8 + (-13857.30) = -231653.10 kVAR

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

170

-1600

-1400

-1200

-1000

-800

-600

-400

-200

200

kVAR

BS
B
Q
W J- J1
L
W MT S1
M S
W T ...
M S-D
T A
W S-D 1
W MT A3
M S
W T -J
M S-L 2
T S
S
-L 1
PR S3
R -R
R - 2
TS SM
- 2
R PR
T
R S- 3
TS R
R -R 2
T P
R S-R 1
TS P
B -S 3
T
S- M2
BT BK
S 2
BT -C
S 2
BT -C
BT S- 4
S F
B -F 2
T
S F
B -F 1
T
S- F3
N NS
T- 2
T
P1

WMTS 22kV Overall Underground Cable Losses

kW

Chapter 6: Development and Analysis of Victorian underground power network model

Figure 6.15: Citipower 22kV underground overall power losses


Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

171

Chapter 6: Development and Analysis of Victorian underground power network model

6.4 Citipower

2011

Forecast

Underground

Overall Power Losses


The sub-models in this section are sought to be aligned with Section 6.3.
However, load demand data, for the year 2011, of all terminal stations loops as
found earlier in Figure 4.1 were again obtained from Citipower publications and
used in developing the sub-models of this section. Some of the network data
were not available; therefore assumptions in Section 4.1 were used for the
development of the network. Separate sub-models were developed individually
for each terminal station with separate sections for 22kV and 66kV voltage
levels.

Appendix J lists Citipower Terminal stations underground Forecast 2011 submodels.

After obtaining the flow analysis of the two voltage levels, a submission of all
power losses, which represents the loading demand of WMTS for the year
2011, is given in Tables 6.14 and 6.15 to undergo further analysis.

The Citipower 66kV undergrounds real and reactive power losses are in Figure
6.16. The figure demonstrates that the power losses are line impedance
dependent and the higher current passing and longer length of line will result in
higher power losses in that particular line.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

172

Chapter 6: Development and Analysis of Victorian underground power network model

Table 6.14: Citipower 66kV underground 2011 forecast overall


lines losses
Branch Name
----------------------------------LQ-JA1
LQ-JA2
VM-JA
VM-LQ1
VM-LQ2
VM-W
VM-WA
WA-W
WB-NC
WMTS-JA1
WMTS-JA2
WMTS-JA3
WMTS-NC
WMTS-VM1
WMTS-VM2
WMTS-WB
AR-BC
B-CW
BC-TK
CL-K
FR-MP
FR-W
NR-B
RTS-AR
RTS-CL
RTS-CW
RTS-EW
RTS-FR1
RTS-FR2
RTS-K
RTS-NR
RTS-SK
RTS-TK
SK-EW
W-MP
E-PM
FBTS-E
FBTS-FB
FBTS-MG1
FBTS-MG2
FBTS-PM

kW losses
---------------14.7
14.7
2.5
1.8
1.8
19
22.5
2.3
0.8
172.3
172.3
172.3
21.5
192.7
192.7
24.8
1.2
0.3
16.8
10.6
20.3
3.8
15.8
44.1
115.3
49.7
57
144.3
144.3
133.9
137.5
100.5
63
4.7
5
0.1
3.4
13
23.6
25.4
2.9

kVAR losses
---------------------618.3
-618.3
-1337.4
-1132.4
-1132.4
-1623.4
-1700.3
-189.8
-6014.1
-1943
-1943
-1943
-8855.4
-1912
-1912
-5333.4
-3254.7
-1460.3
-2511.6
-2626.4
-580.7
-706.2
-1660.3
-8036.2
-6177.9
-11870.1
-7304.7
-3564.1
-3564.1
-2995.5
-1496.2
-5049.6
-1327.7
-2165.4
-906
-1277.9
-843.5
-2512.6
-2040.3
-2040.8
-1362

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

173

Chapter 6: Development and Analysis of Victorian underground power network model

FBTS-SO1
46.6
-3753.2
FBTS-SO2
39.6
-4553.8
FBTS-WG1
11.1
-892.3
FBTS-WG2
12
-892.5
FPTS-AP1
18.8
-4323.2
FPTS-AP2
18.8
-4323.2
MG-AP
1.6
-2107.1
WG-FB
5.3
-1198.4
L-Q
0
-4051.2
Q-HB
55.6
-7919.5
TSTS-HB
58.6
-10756.7
TSTS-L
107.8
-19335.8
EB-RD
0.9
-6234.5
SVTS-EB
180.2
-5893.6
SVTS-RD
82.4
-13877.2
----------------------------------------------------------------------------Total overall power losses: 2804.50
-205655.20

The Citipower 22kV undergrounds both real and reactive power losses are
summarised in Table 6.15.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

174

2000
0
-2000
-4000
-6000
-8000
-10000
-12000
-14000
-16000
-18000
-20000

kVAR

LQ
V JA1
VMM-J
A
VM-LQ
2
W W -WA
M BW TS NC
M -J
W T A
M S-N 2
TS C
AR...
BC-BC
FR -TK
-M
N P
R RT
R S- B
T C
R S-E L
TS W
R -FR
TS 2
R TS NR
W TK
F FB -MP
B
TS TS
FB -M -E
FB TS G1
FB TS -PM
T -S
FP S-W O2
T
S G2
W -A
G P2
-F
Q B
T -H
S ST B
V
TS S-L
EB

Citipower 66kV Underground Overall 2011 Forecast Losses

kW

Chapter 6: Development and Analysis of Victorian underground power network model

Figure 6.16: Citipower 66kV underground 2011 forecast overall power


losses
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

175

Chapter 6: Development and Analysis of Victorian underground power network model

Table 6.15: Citipower 22kV underground 2011 forecast overall


power losses
Branch Name
kW losses kVAR losses
-------------------------------------------------- --------------------BSBQ-J
2
-2779.1
J-LS
7.2
-190.9
WMTS-BSBQ1
78.1
278.4
WMTS-BSBQ2
73.2
220.4
WMTS-DA1
35.4
117.7
WMTS-DA2
35.4
117.7
WMTS-J1
16.2
-264.9
WMTS-J2
15.1
-264.5
WMTS-LS1
15.4
35.4
WMTS-LS2
15.4
35.4
PR-R1
0.4
-672.2
PR-R2
0.4
-672.2
R-SM1
107.1
268.9
R-SM2
107.1
268.9
RTS-PR1
21.6
-199.8
RTS-PR2
21.6
-199.8
RTS-R1
40
174.4
RTS-R2
40
174.4
RTS-R3
40
174.4
RTS-RP1
39.2
-621.9
RTS-RP2
20.6
-499
RTS-SM1
169.5
853.2
RTS-SM2
169.5
853.2
RTS-SM3
169.5
853.2
BTS-BK1
8.5
-241.1
BTS-BK2
8.4
-244
BTS-C2
4.3
-203.9
BTS-C3
4.3
-203.9
BTS-F1
9.7
-209.1
BTS-F2
9.3
-223.8
BTS-FF1
31.5
-135.4
BTS-FF2
31.5
-135.4
BTS-NS1
95.8
36.6
BTS-NS2
95.8
36.6
NT-TP1
14.3
-2027.3
NT-TP2
30
-778.8
----------------------------------------------------------------------Total overall power losses: 1583.30
-6268.20

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

176

Chapter 6: Development and Analysis of Victorian underground power network model

The Citipower 22kV overall undergrounds real and reactive power losses are
graphically represented in Figure 6.17. The figure demonstrates that power
losses are line impedance dependent and the higher current passing and longer
length of line will result in higher power losses in that particular line.

A combined summation of power losses is found in Table 6.13 and 6.14 for
22kV and 66kV loops which are presented as the total power losses in the
Citipower for underground network configuration with a 2011 forecast loading
demand.

Total real power losses = 1583.30 + 2804.50 = 4387.8 kW


Total reactive power losses = -6268.20 + (-205655.20) = -211923.4 kVAR

A clearer representation of the comparison of power losses for the overall


Citipower underground network with power losses obtained from both 2007 and
2011 loading demand is shown in Figure 6.18.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

177

Chapter 6: Development and Analysis of Victorian underground power network model

Figure 6.17: Citipower 22kV underground 2011 forecast overall power


losses
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

178

Chapter 6: Development and Analysis of Victorian underground power network model

Citipower Overall Underground Power Losses Comparison

50000.00
0.00
-50000.00
-100000.00
-150000.00
-200000.00
2007

-250000.00
kW

kVAR

2011

Figure 6.18: Citipower overall underground power loss comparison

As can be seen, the real losses for the forecast year 2011 are almost 3000 kW
greater than the losses for the year 2007; on the other hand, the reactive losses
for 2011 are almost 20000 less than the losses for 2007. Moreover there are
many lines duplicated to keep the Citipower n-1 configuration; the added lines
reduced the power losses due to the fact that less current will pass through the
same lines and it will produce less power losses. Data in Figure 6.19 can be
compared with the data in Figure 4.18 in Section 4.6, to highlight the Citipower
overall power losses for the year 2007 and forecast losses of the year 2011.
Figure 6.19 presents the comparison of Citipower overall power losses for
overhead and the proposed underground models.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

179

Chapter 6: Development and Analysis of Victorian underground power network model

Citipower Overall Power Losses Comparison

50000.00
0.00
-50000.00
-100000.00
-150000.00

Overhead kW
Underground kW

-200000.00

Overhead kVAR

-250000.00

Underground kVAR

2007

2011

Figure 6.19: Citipower overall underground power loss comparison

As predicted, the real power losses comparison in Figure 6.20 shows almost
50% reduction between the losses in the year 2007 and the projected loss for
the year 2011. However, the reactive power losses for the year 2007 were less
than the anticipated reduction in losses. More interestingly, losses in reactive
power for the year 2011 have exhibited a higher figure in underground than
overhead losses. The obvious reasons for both scenarios is that less feeders
have been used in the 2007 underground model than those used in the
overhead model; furthermore, the same number of feeders have been used for
2011.

In Figure 6.20 there is a clear indication of the previously mentioned finding,


that is, the number of circuits or number of cables in the underground forecast
model is 25% less than the overhead forecast model.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

180

Chapter 6: Development and Analysis of Victorian underground power network model

Citipower Total Number of Feeders

120
100
80
60
40
20

Overhead
Underground

0
2007

2011

Figure 6.20: Citipower total number of lines compared to cables

6.5 Conclusion
A thorough analysis and development of Victorian underground power network
sub-models were presented in detail in this chapter. In addition, an elaboration
on overall underground network sub-models was discussed in chapter 5. These
analyses are of great significance for the future growth and safe operation of the
Victorian power network. Various forecasted models were analysed in order to
determine the need for additional lines and transformers to cope with the
additional forecasted load.

Load flow analysis and other industrial based specialised software were used to
investigate and develop various sub-transmission network models. The results
obtained from the load flow analyses provided crucial information about all
buses in the network. Some buses were exceeding their normal operation
values or nominal values so an action was made to rectify the problem
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

181

Chapter 6: Development and Analysis of Victorian underground power network model

associated with any abnormality in the network; again the Citipower n-1
redundancy configurations were met in all sub-models developed in this work.

Another outcome of the load flow analysis was the discovery of real and
reactive power losses at each line and the effect of forecasted loading on the
losses were identified as well.

The next chapter looks at the Victorian hybrid power network in an attempt to
efficiently design an underground network for Victoria.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

182

Chapter 7: Development and Analysis of Victorian Hybrid power network model

CHAPTER 7
DEVELOPMENT AND
ANALYSIS OF VICTORIAN
HYBRID POWER NETWORK
MODEL
7.0 Introduction
HTS cable has a unique characteristic of low impedance to current flow. Unlike
conventional power cables, HTS cable offers higher power transfer with
minimum losses and more compact design of power applications yet better
power flow absorption in the networks at the same voltage levels.

In attempts to closely study the effect of HTS cable on power networks, several
pilot projects were carried out around the world. Promising results were
achieved in terms of cable capacity and reliability. However, the big challenge of
this technology is the high cost of superconductive materials in addition to the
cost associated with cable-cooling, which is required at its normal operation

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

183

Chapter 7: Development and Analysis of Victorian Hybrid power network model

temperature (-208C for present HTS cables). A new cable design which utilises
the cryogenic electrical insulator has been developed, in parallel with
developing highly reliable cable cooling technology with a long service life
aiming for longer service intervals. These are expected to reduce the cost of
HTS cable technology significantly in the short term; and in the midterm industry
scale production will certainly further reduce the cost of HTS cable. This chapter
will present the technology involved in HTS cable and its anticipated effects on
power transmission networks.

For the last few decades power transmission for long distance was only
possible with extra high voltage. However the transmission network required
huge investment in high voltage equipment and switch gears, yet it came with
big electrical transmission losses. Fast growing cities and deregulation of the
electrical sector in many countries around the world resulted in overwhelming
demand for more power [42]. So far, the focus of the electricity market has been
narrowed onto the generation part of the power network, directing much of
power investment into the new way of generation and renewable energy
technology. This leaves the transmission part of the network with the burden of
ageing and overloading to face reliability challenges. HTS cables, with their
unique characteristics of low impedance and high current rate, have the
potential for increasing power transmission capacity. Therefore by transferring a
larger amount of generated power that normally is lost in conventional power
transmission cables, less generation is then required for the existing load [17].

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

184

Chapter 7: Development and Analysis of Victorian Hybrid power network model

Further on in this chapter, Section 7.2 will explain in detail the obtained results
from the load flow analysis performed on the hybrid sub-model, where four
lengths of HTS cable were employed in conjunction with the conventional XLPE
cable. The employment enabled a comparison to be drawn on the performance
and impact of the HTS cable on the Citipower power network. WMTS loop was
identified to be a potential site for future proposed HTS cable due to the
predicted high load demand, current and scheduled zone substations upgrades
from 22kV to 66kV like BSBQ.

7.1 General

Overview

of

HTS

Cable

Technology
Superconductivity occurs in some materials at very low temperatures; it is often
recognised to have exactly Zero electrical resistance with no interior magnetic
field. The hunt for superconductive material has always played a vital role in
continuous research and development which has led to great discoveries
especially in the past couple of decades. Materials, such as ceramics, copper
oxides and barium along with many others, were discovered in the late 1980s.
The key benefits of such materials are the relatively low cost of refrigeration
compared with that of conventional metallic superconductors. Examples, of
potential applications of such superconductors, would be such as, utilising them
in transmission cables to gain a huge reduction in high voltage transmission
losses. In addition, the very low or no EMF leaves the doors widely open for

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

185

Chapter 7: Development and Analysis of Victorian Hybrid power network model

applications such as fast trains and other applications that are within close
proximity to users [43].

7.1.1 Superconducting cables


During the late 1980s many studies explored developing and designing the
most cost effective superconducting cable. The outcome of these studies
resulted in the design of low-loss dielectric insulators. In addition, other forms of
insulators have also been considered in the literature [29, 3335] such as liquid
air impregnated paper as well as glass-epoxy tapes. As noted earlier, the
discovery of ceramics superconductors has significantly contributed towards
eliminating many of the problems associated with superconducting at high
temperatures [42].

7.1.2 HTS triaxial cables design


Ultera - A Southwire Company of Carrollton, GA. and nkt cables of Denmark
Joint Venture, of two leading wire and cable manufacture around the world, has
successfully built and tested a new HTS cable design. It offers a thrilling new
conductor design with the focus of reducing the technology cost and enhancing
its reliability through reducing material cost, cooling areas and requirements,
and thermal and electrical losses. The concept was to reduce the quantity of
HTS wire needed, and reduce cooling requirements by means of using a
common cold surface area. Thereby, the triaxial conductor design which placed
all three phase conductors concentrically around a common central core was
implemented. Electrical field cancellation was also achieved by the three
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

186

Chapter 7: Development and Analysis of Victorian Hybrid power network model

concentric phases being 120 (electrical) apart. Thus one common copper
shield was used to carry neutral currents. The first full-scale prototype of the
Triax design was built and tested at Ulteras development partner Oak Ridge
National Lab (ORNL) in 2002. The triaxial conductor design is shown in Figure
7.1 [44].

Figure 7.1: Triaxial superconducting cable design [44]

This design was a big milestone towards reducing HTS cables system costs
and achieving a commercially viable product. The major breakthrough of the
Triax design was tackling specifically the two major cost components in a
superconducting cable system: HTS wires and refrigeration.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

187

Chapter 7: Development and Analysis of Victorian Hybrid power network model

The Triax cable design termination provides ambient temperature transition to


the three phases and the shield, which is typically at ground potential, as shown
in Figure 7.2. The three concentric phases are connected to copper leads that
continue throughout the length of the termination. The three phase connections
are shown at the right side of the termination while the neutral bushing is hidden
on the back side of the termination body. Another interesting feature of the Triax
termination, is the slim design in which the body of the termination is no larger
in diameter than the cable cryostat [44].

Figure 7.2: Full scale Triax termination [45]

7.1.3 Potential benefits of HTS cables


HTS cable is more expensive than any of the conventional cables (MV and HV).
However, there can be economic benefits in short connections (1-3 km) where

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

188

Chapter 7: Development and Analysis of Victorian Hybrid power network model

one or several HV stations (110-220 kV) can be converted to /replaced by MV


stations (10-72 kV).

The biggest advantage is however that connection into city centres becomes
possible without building new HV substations, as has been demonstrated with
the 1.7 km project in New Orleans, US.

7.1.4

High capacity

HTS cables have the potential to improve the efficiency and stability of the
power networks with their capacity to carry current up to 5 times more than
conventional underground power cables. Therefore, more flexible power
transmission or power flow within the power networks will be possible. Yet due
to their compact design, they provide the best real life solution, for retrofitting
conventional cables to increase capacity in highly congested cities where
existing conduits have been utilised to the maximum. This will enhance the
future expansion of the power network and give power designers more flexibility
in designing the network. Masuda et al. [46], states that the cost of constructing
HTS cables is likely to be much less than the cost of constructing a new conduit
for conventional underground cables; this assumption is calculated based on
current construction techniques and assuming the cooling system interval is
every 5 km apart. In this aspect HTS cables will be more economic to construct
than upgrading the conventional cables rating, which in some cases is not an
option given that conduits have limited diameters. For these reasons, HTS

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

189

Chapter 7: Development and Analysis of Victorian Hybrid power network model

cables become a more competitive and attractive solution where there was not
an option before [17, 46].

7.1.5 Low ohmic resistance


Low ohmic resistance is the nature of superconductivity. In HTS cables, the
ohmic resistance is almost zero at the critical temperature, which reduces
transmission losses to very small amounts. According to Masuda et al. [46], a
superconducting shield is constructed not only to eliminate the electromagnetic
field leakage outside the cable, but also to eliminate eddy current loss from the
electromagnetic field. These losses are normally generated by the alternating
current and are similar to the magnetization loss of the superconductor itself.
Additional losses are the dielectric loss of the insulation and the heat incursion
through the thermal insulation pipe. The resulting heat has to be removed and
HTS cables temperature needs to be maintained at the cable operating
temperature. Coolant from a cooling unit is required to balance this heat gain. In
addition, electric power is required for running the cooling unit. In summary, the
loss of the superconducting cable is approximately half that of a conventional
cable [46].

7.1.6 Low impedance


The low inductance in HTS cables is due to the high performing cryogenic
dielectric, which permits a thin electrical layer and a screened cable design with
zero external magnetic fields. This results in a small volume of magnetic field
surrounding the conductor and therefore a low induction.
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

190

Chapter 7: Development and Analysis of Victorian Hybrid power network model

7.1.7 Limitation of HTS cables


HTS cable has many advantages and some limitations. Like any other new
technology under development it faces some hurdles. As has been pointed out
in some of the early work, these hurdles include:

(1) the high cost of the technology that can make the feasibility of installing HTS
cable uneconomical;
(2) high power ratings requirement, meaning that unless there is an enormous
amount of power that needs to be shifted for a short distance the use of HTS
cables can hardly be justified e.g Detroit project [8];
(3) break-even energy losses due to the high maintenance cost, especially for
the refrigeration part of the system.

7.1.8 Energy losses - a comparison between HTS and XLPE cables It is very well known that HTS cables ohmic losses are much lower than those
with XLPE cables as mentioned in Section 7.1.5. For the purpose of this
comparison, reference [46] has chosen three phase HTS and insulated copper
conductor XLPE cables, the HTS cables capacity rated at 3,000 A at 132 kV
while the XLPEs capacity parameters where 1,080 A at 138kV. The negligible
difference in voltage levels were highlighted merely to distinguish between the
standards used in the US and Europe and will have no affects on the analysis
results.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

191

Chapter 7: Development and Analysis of Victorian Hybrid power network model

The ac losses in a particular conductor are proportional to its length and the
amount of current passing through the conductor. In XLPE cables the heat is
absorbed by the surrounding insulators while in HTS it must be explicitly
eliminated in order to maintain its efficiency within regular operating
temperatures. HTS cables heat load includes thermal losses from heat leakage
in addition to another requirement which dictates that HTS cables must connect
to system elements at ambient temperature.

What's more, the lack of experience in HTS cable technology has added to the
fear, of power utilities, of adopting it. These hurdles can outweigh any benefits
of HTS cable unless it proves commercially reliable. Until then it will not be a
widely accepted technology. So far, the HTS cable has been successfully
demonstrated in laboratory prototypes and to certain extents in the real life grid.
The next phase should be a commercial scale introduction of this technology
with larger HTS cable systems engineered to operate on the utility network [47].

7.1.9 Development of HTS cables


Bearing in mind all the challenges faced during the early development of HTS
cables, Ultera is currently addressing these issues by developing a new cable
design. it uses one thermally insulating envelope Cryostat for all three phases,
and eliminates the need for a return screen for each of the phases. This
reduces cost by 40-50%, and it cuts the energy losses by 50%. In this way
Ultera achieves usefulness at smaller rated power. It has been estimated that

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

192

Chapter 7: Development and Analysis of Victorian Hybrid power network model

the cost of the materials required to transmit 1 kA over 1 m length using HTS
cables is approximately 11 EUR/kAm [47].

Nkt cables had 200 m HTS cable on pilot installation running for 2 years with
American Electric Power. The cable was type tested in 2005 then installed and
commissioned in 2006. The first generation of this cooling system was used at
the time. The availability of cable reached 99.95% with only one scheduled
outage. Overall nkt cables has more than 9 years of operation experience [45].
Figure 7.3 shows the 200 m pilot installation in the utility grid in Columbus, in
the United States.

Figure 7.3: Triaxial superconducting cable termination [45]


Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

193

Chapter 7: Development and Analysis of Victorian Hybrid power network model

The latest results obtained are approved type tests at 13 kV for a cable system
with a power rating of 69 MVA. This is still a lot of power, but not as large as the
1-5 GVA that is mentioned by earlier work [45]. The cable has an inductance in
the order of 16 H/km. This allows it to absorb the load flow from other parts of
the network at the same voltage. In order to reduce the operation costs, Ultera
have partnered with Praxair, one of the three largest gas manufacturers. They
develop cooling technology with long service life; the goal is longer service
intervals than three years. The operation costs are then dominated by the
losses and the electricity cost of running the cooler. This is similar to a
conventional cable. The breakeven is around 3000 h of usage, which is an
ordinary load level in most systems. For higher loading, the HTS cables are
more efficient, for example in industrial systems, with 5000 h load per year [47].

Although developing and manufacturing HTS cable sounds intimidating,


Shahidehpour [47], predicts the outlook for HTS cable to be a realistic technical
and economic alternative for power delivery. Figure 7.4 shows the growth in
U.S.-manufactured superconducting wires. Meanwhile, it is expected that the
market for superconductor products is projected to grow to near US$5 billion by
the year 2010 and to US$38 billion by 2020 [47].

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

194

Chapter 7: Development and Analysis of Victorian Hybrid power network model

Figure 7.4: Growth in U.S.-manufactured superconducting wires [47]

In relation to the price of HTS, there are delays in the reduction in the price due
to the slow adoption and slow growth in volume, and also due to the transit to
second generation conductors. Figure 7.5 is an indicator of second generation
tape price fall. The price-volume curve was developed by the German industry
association IV Supra. This will eventually translate to second generation tapes
being cheaper than copper. The tape industry is fighting to reach approximately
40 k$/kAm. The very long-term (large-volume) forecast is still 10-20 $/kAm. [45]

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

195

Chapter 7: Development and Analysis of Victorian Hybrid power network model

Figure 7.5: Price-volume curve developed by the German industry


association IV Supra [45]

Today, several HTS cable projects are underway in the United States and
around the world. One of these projects was the first to supply electricity to
50,000 customers in Copenhagen, Denmark, and another example was in
Carrollton, Georgia [47], where more than 26,000 hours of fault-free operation
were recorded while powering three manufacturing plants. Studies by major
corporations and organizations, have suggested that principle investments in
the HTS cables technology are needed. They will play a significant role to meet
the necessary need for reliable and affordable electric power in the United
States. Now it is obvious, the technology will progressively play a big role in the
power applications for large markets in terms of cost as well as efficiency and
performance [47].

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

196

Chapter 7: Development and Analysis of Victorian Hybrid power network model

7.2 Feasibility Studies


7.2.1 Power to city centre 6 km in Amsterdam
The technological advancement over the years has brought HTS cables a long
way in terms of length as they have increased from cables a few hundred
meters long to cables kilometres in length. In this case study [48], two Dutch
utilities have come together to replace a 150kV Gas Pressure cable with a 50kV
HTS cable which will be retrofitted into the existing steel pipe that was
accommodating the old Gas Pressure cable. The new HTS cable will be utilising
a new generation of modern and efficient cooling systems which are also known
as Pulse Tube Coolers [48].

Figure 7.6 shows the length of the Netherlands High Voltage circuits in
kilometres. These long distance networks have necessitated the need for the
long HTS cable which was developed for this case study in order to retrofit into
a steel pipe that was occupied by an old gas pressure cable [48].

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

197

Chapter 7: Development and Analysis of Victorian Hybrid power network model

Figure 7.6: The Netherlands HV circuits length [48]

The advantages gained from this case study:

zero electro-magnetic emissions;

eliminating the need for alternating voltage level;

substantially lower energy losses;

eliminating negative thermal influence on other infrastructure;

huge reduction in civil cost.

The case study has applied the newly developed HTS cable in a pilot project.
This extra-long HTS cable was retrofitted into the aforementioned steel pipe.
The location of this pilot project was carefully selected in the Dutch capital
where three GP cables 6km long with 100MVA capacity fed the 150kV
substation with 200 MVA connected load [48].

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

198

Chapter 7: Development and Analysis of Victorian Hybrid power network model

As illustrated in Figure 7.7, the three 100MVA gas pressure

cables were

replaced with two 200MVA XLPE cables connected to 150kV busbar, in addition
to one 250MVA HTS cable connected to a 50kV busbar of the zone substation
[48].

Before

After

Figure 7.7: HV-network before and after installation HTS cable [48]

Since the operating temperature of the HTS cable should be kept below 75K
and in order to obtain low-loss superconductivity, the HTS cable temperature
will be controlled by a liquid nitrogen cooling station installed at each end. As
shown in Figure 7.8, the motor utilises oscillations that are produced by a
magnetic field which makes it free of moving parts and oil to eliminate wear and
tear as well as the need for any ongoing maintenance. In turn this motor is
attached to a cold-head Crycooler. These Crycoolers are very versatile and
reliable for distributed refrigeration applications [48].

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

199

Chapter 7: Development and Analysis of Victorian Hybrid power network model

Figure 7.8: Cryocooler pulse with tube design [48]

A stack of cryocoolers or cryogenic pumps can be located where needed along


the length of the cable as shown in Figure 7.9.

The advantage of installing a stack of these crycoolers would be the


redundancy required for maintenance purposes in case of faults, as well as load
balancing on the cooling system. Perhaps it is worth mentioning that some
assumptions were made in this study, such as, modifying

the grids

impedances to allow a large part of the power flow through the HTS cable
instead of the other two XLPE cables. If the impedances were left without
alterations the HTS cable would not be used to its full potential. Moreover,
coupling between two 50kV substations was another predicament that needed
to be addressed, as coupling should be carried out in a way to ensure that short
circuit currents will hinder the substations busbar and other components [48].
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

200

Chapter 7: Development and Analysis of Victorian Hybrid power network model

Figure 7.9: Cooling system for long length superconducting cables - an


array of pulse tube cryocoolers and reserve liquid nitrogen tank - [48]

Further to the issues above, phase shifting of the three phases in the cable may
prove necessary to regulate the asymmetry effect of the current and the voltage
which may take place due to the very concentric design of the HTS cable. The
asymmetrical effect can result in a large voltage on transformers that will
damage equipment [48].

In summary, this study has explored the possibility of installing a long distance
HTS cable in an existing HV-network. Preliminary studies during the projects
feasibility stage showed that most plausible technical problems can be resolved.
The full potential of the HTS cable will be harnessed thanks to the new and

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

201

Chapter 7: Development and Analysis of Victorian Hybrid power network model

efficient crycoolers. This Dutch case study has certainly paved the way for a
commercial scale application of HTS cables around the world [48].

7.2.2 22.9kV HTS cable in metropolitan city of South Korea


This case study details the planning and deployment aspects of a 22kV HTS
cable in big congested cities like Seoul. The aim of the project described in this
study was to replace existing 154kV or 22.9kV conventional cable. As is the
trend around major cities in the world, Seoul has an ever increasing energy
demand coupled with poor investment in power infrastructure. The route length
per MW demand is likely to diminish from the current 0.6 to 0.53 C-km/MW in
2010 [49]. Figure 7.10 illustrates the anticipated decline of route length per unit
demand in the future.

Figure 7.10: Expected route length per unit demand [49]


Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

202

Chapter 7: Development and Analysis of Victorian Hybrid power network model

The increased demand and shrinking route lengths have instigated a complex
dilemma in transmission and distribution networks. New improvements in the
HTS cable design that provide massive power transfer for short distances may
be the answer for power network system planning and operating predicaments
[49].

Yoon et al. [49] predicted a rise in the order of 4 to 5% annually in power


demand. This demand will be experienced by South Koreans in the year 2010
where the maximum demand is predicted to exceed 67 GW. A large percentage
of this predicted growth will take place in the metropolitan areas. Therefore, a
robust and reliable power network is essential to keep up with such a
demanding environment, where the HTS cable can play a vital role.

Figure 7.11 demonstrates the countrys 154kV underground cable route length
versus procession rate; notably the rate will increase dramatically from 6.8% to
11.6% and Yoon et al. [49] expected the rate to hit 13.4% by 2020.

Other issues that affect the need for deploying HTS cable include: limited
transmission capacity of existing distribution lines; the congested underground
easement with many utilities assets; the burden of constructing new cable in the
jam-packed cities which mean disruption to traffic and public areas, and rapid
increase in general power supplys cost to accommodate for laying new cable
[49].

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

203

Chapter 7: Development and Analysis of Victorian Hybrid power network model

154kV Route Length and Procession Rate


25,000

14
12

20,000
15,000

KMs

8
6

10,000

% Rate

10

4
5,000

Total Route
Underground Cable

0
2000

2005

Procession rate

2010

Years

Figure 7.11: Route length verses 154kV underground cable procession


rate circuit to km [49]

This case study has identified some general benefits of utilising HTS cable in
the city centre for the overall power network [49].

savings in transmission losses;

reduction in civil work with less site disturbance;

saving in overall cost of laying underground cable;

gaining more space by converting large 145kV to smaller 22kV


substations;

eliminating the need for new 154kV substation;

gaining better investment yields;

environmental benefits.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

204

Chapter 7: Development and Analysis of Victorian Hybrid power network model

Figure 7.12 shows the deployment steps of 22kV HTS cable in city centre. The
following steps summarise the phases in which the HTS cable has been
deployed when migrating from 154kV to 22.9kV substation [49].

(1) replace 154kV conventional cable linking suburban to city centre


substations;
(2) convert city centre 154kV to 22.9kV substations;
(3) replace 154kV conventional cable linking city centre substations with
22kV HTS cable;
(4) replace 154kV conventional cable linking substation to city centre loads
with 22kV HTS cable.

Figure 7.12: Deployment of 22kV HTS cable in city centre [49]

In conclusion, this case study highlighted the benefits of retrofitting 154kV


conventional cable with the lower voltage level 22kV HTS cable, with potential
advantages such as:
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

205

Chapter 7: Development and Analysis of Victorian Hybrid power network model

higher transmission capacity with lower voltage level on top of minimum


power losses, can be the answer of congested cities power networks;

retaining spaces in the city substations by converting them from 154kV


to 22.9kV substations where big transformers and other equipment will
be removed, also eliminating the need for new 154kV substation;

savings in the civil works by retrofitting 22kV HTS cable in existing ducts;

gaining the experience of installing, testing and operating the HTS cable,
together with solving any problems that might arise in each stage;

aiming for developing higher rate HTS cable;

comprehensive research on the proposed site should be done first in


order to find the practicality of the HTS cable application is
recommended.

7.3 The 66kV - 300 MVA HTS Triaxial Cable for


Melbourne
A 66kV, 300 MVA HTS cable has been designed by Ultera for the purpose of
this research. The configuration of this Triax design cable is basically sharing
a common centre, where the three electrical phases are concentrically
assembled around a common central core. The three phases are insulated with
thermal and electrical insulators. Although there are two void spaces in addition
to the three electrical phases and insulators, the overall diameter of the cable is
170 mm. However the diameter can be changed by reconfiguring the number of
HTS tapes. Figure 7.13 shows the 66kV, 300 MVA HTS cable.
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

206

Chapter 7: Development and Analysis of Victorian Hybrid power network model

Figure 7.13: 66kV, 300 MVA HTS triaxial cable [50]

Ulteras electrical data for the HTS cables was obtained and used in the design
and verification development stages of the hybrid sub-model. As it can be noted
the cable resistance is almost zero, meanwhile the cables inductance and
capacitance are much lower than its XLPE counterpart or any rival conventional
cable. The lower values of the cable electrical elements give the cable the
competitive advantage of high current rating allowing a great amount of power
to be shifted through the cable, so it would take an enormous amount of current
to overload the HTS cable. Table 7.1 provides comprehensive details on the
66kV HTS cable physical and technical data.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

207

Chapter 7: Development and Analysis of Victorian Hybrid power network model

Table 7.1: 66kV 300 MVA HTS cable for Melbourne data
HTS cable
Technical Data
Type of Cable:66kV Triax three-phase
Construction / Conductor
Conductor Diameter
Insulation
Cable diameter
Weight
Pulling force (max)
Electrical Data
dc resistance
acresistance (eqv.)
Nominal voltage
BIL
Capacitance (transposed)
Inductance
Surge Impedance
SIL/natural load
Critical length (cap.)
30 deg length limit (ind.)
Thermal Data, full load
Heat released to soil
Internal temp. increase
Cooling requirement

kA
mm
mm
kg/m
tons

3x2.6
84
Cryoflex
170
14
2

/km
/km
kV
kV
F/km
H/km

MVA
km
km

< 10
110
66
350
1.8
30
4.1
1070
99
643

W/m
K
kW/km

-2
1
2

7.4 Hybrid Power Network Sub-Model


In this study, a hybrid sub-model is developed to emulate Melbournes CBD
network. This network is currently over loaded due to the vast expansion of the
CBD with many residential towers built in the citys central district. Additional
HTS cables maybe the answer to the necessity concerning the required load
growth. This hybrid model replaces the conventional underground cables with
limited excavation and construction work, as it utilises the existing conduits that
were originally housing the old oil-filled cables. This replacement will allow for
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

208

Chapter 7: Development and Analysis of Victorian Hybrid power network model

enhanced capacity of power transfer as opposed to installing a new 220kV


transmission line going through the city of Melbourne, like the Richmond to
Brunswick cable [51].

7.4.1 Citipower 66kV hybrid sub-model I


To enable the comparison of HTS cable to conventional XLPE, hybrid submodel will initially use WMTS 2011 forecasted model in Section 6.2 with the
addition of BSBQ zone substation. Despite the obtained convergence when
running the load flow analysis, WMTS-JA and WMTS-BSBQ cables were
stretched to 200% of their normal load rating. Figure 7.14 shows the Citipower
66kV hybrid Sub-Model I with 2011 forecasted demand and BSBQ zone
substation added; it can be noted that to meet the n-1 configuration, there are a
few cables have been duplicated up to five times, consequently no element in
the sub-model was stressed or exceeded its 100% rating.

The figure displays a summary of the load flow analysis results situated close to
the bus, line or transformer. The summary includes an arrow that reveals the
direction of power flow.

Table 7.2, illustrates the bus results of flow analysis performed on the WMTS
66kV hybrid sub-model. The table also lists bus parameters including name,
real and reactive generated powers.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

209

Chapter 7: Development and Analysis of Victorian Hybrid power network model

Figure 7.14: Citipower 66kV hybrid sub-model I


Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

210

Chapter 7: Development and Analysis of Victorian Hybrid power network model

Table 7.2: Citipower 66kV hybrid sub-model I power losses


Branch
From -> To Flow To -> From Flow Losses
------------------------------------------------------------------------------------------------------Name
MW
MVAR MW
MVAR
kW kVAR
----------------------------------------------------- ------------- ------------- ---------------------WMTS-BSBQ (XLPE) 260.856 221.801 -260.513 -231.916 343.8 -10115.3
WMTS-JA (XLPE)
225.411 192.562 -225.076 -206.34 334.7 -13778.2
BSBQ-LQ (XLPE)
72.143 63.796 -72.121 -69.947 21.9 -6151.7
LQ-JA (XLPE)
-76.646 -64.836 76.656 61.969 10.5 -2866.8
WMTS-NC
16.961 7.138 -16.939 -15.992 21.5 -8853.8
WMTS-WB
23.22 13.38 -23.196 -18.712 24.8 -5332.4
BSBQ-VM
34.122 32.352 -34.105 -33.585 17.7 -1233.4
BSBQ-W
41.43 38.494 -41.41
-39.398 19.5 -903.9
JA-VM
-23.62 -22.865 23.629 21.561 8.3
-1303.9
JA-VM
13.309 13.006 -13.306 -14.35
2.9
-1344.1
LQ-WA
22.656 21.263 -22.65
-22.268 6
-1005.1
W-WA
41.41 39.398 -41.406 -39.578 4
-179.8
WB-NC
4.103 -0.376 -4.103
-5.637
0.8
-6013.1
--------------------------------------------------Total power losses 816.4 -59081.5

The table exhibits, in two different columns, the power delivered to and from the
line and in the last two columns it lists the power losses. The total real power
losses were found to be 816.4 kW; in addition the total reactive power was
found to be -59081.5 kVAR.

A graphical representation of the load flow analysis of hybrid sub-model I is


presented in Figure 7.15.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

211

Chapter 7: Development and Analysis of Victorian Hybrid power network model

WMTS 66kV Losses using XLPE Cables


2000
0
-2000
-4000
-6000
-8000
-10000
-12000

kW
kVar

TS
-B
SB
W
M Q(
TS
XL
BS -JA PE
BQ (X )
-L LP
E)
Q
LQ (X
-J LPE
A
(X )
LP
W
M E)
T
W S-N
M
C
TS
B S WB
BQ
BS VM
BQ
-W
JA
-V
M
JA
-V
M
LQ
-W
A
W
-W
W A
BN
C

-14000

Figure 7.15: Citipower 66kV hybrid sub-model I losses

7.4.2 Citipower 66kV hybrid sub-model II


The configuration of this sub-model has many similarities to the WMTS 66kV
underground 2011 forecasted sub-model exhibited earlier in Section 6.2.1. The
exception was that four 66kV XLPE cables identified as WMTS-JA, WMTS-VM,
LQ-JA and VM-LQ routes with five or four circuits were replaced with single
cable of 66kV HTS cable. Again the 2011 zone substation loading demand
parameters were acquired from the companys 2007 planning report. The 66kV
HTS cable parameters presented in Section 7.2 were used in this sub-model.

Figure 7.16 illustrates the Citipower WMTS loops, indicating the proposed
location of HTS cables; also the figure shows some of the Citipower zone

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

212

Chapter 7: Development and Analysis of Victorian Hybrid power network model

substations. It is worth mentioning that this map is not intended for the exact
distance between zone substations; rather approximate lengths were used.

Figure 7.16: Citipower WMTS zone substations and sub-transmission


underground cables [28]

The deployment of HTS cable has the potential of eliminating some of the small
zone substations in the area where the cables run, as the load of those small
substations can be transferred to the upgraded bigger once like JA, LQ and
BSBQ, hence small substations can be converted to switching stations or
decommissioned and the revenues generated from properties sale can
significantly contribute towards funding the HTS cable replacement.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

213

Chapter 7: Development and Analysis of Victorian Hybrid power network model

In this sub-model, XLPE cables of WMTS-BSBQ, WMTS-JA, BSBQ-LQ and


LQ-JA were replaced with the Melbourne 66kV HTS cables. Other network
parameters are kept the same as the hybrid sub-model I to lay the ground for
cable comparison. The obvious observation was only one HTS cable per route
was required to meet n-1 Citipower configuration. Figure 7.17 presents the
updated hybrid sub-model with selected lengths of the HTS cable.

The figure shows all feeders consist of a single circuit or single cable, as
compared to the Citipower 66kV hybrid Sub-Model I in Section 7.2.1, bearing in
mind that the n-1 redundancy configuration is maintained. The result of this submodel confirms the prediction of low cable loading, where one HTS cable is
recorded below 12%. Table 7.3 lists the WMTS 66kV hybrid sub-model II cable
loading.

Table 7.3: Citipower 66kV hybrid sub-model II cable loading


Branch Name
Ampacity
------------------------------------- --------------WMTS-BSBQ (HTS cable) 7800
WMTS-JA (HTS cable)
7800
BSBQ-LQ (HTS cable)
7800
LQ-JA (HTS cable)
7800
BSBQ-VM
1260
BSBQ-W
1260
JA-VM
1260
JA-VM
1260
LQ-WA
1260
W-WA
1260
WB-NC
1260
WMTS-NC
1260
WMTS-WB
1260

Loading Amp % Loading


--------------------- ----------------2813.00
36.1
2738.31
35.1
931.94
11.9
1028.31
13.2
289.09
22.9
356.69
28.3
298.36
23.7
273.07
21.7
408.59
32.4
363.07
28.8
36.22
2.9
161.04
12.8
234.53
18.6

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

214

Chapter 7: Development and Analysis of Victorian Hybrid power network model

Figure 7.17: Citipower 66kV hybrid sub-model II


Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

215

Chapter 7: Development and Analysis of Victorian Hybrid power network model

A graphic representation of Table 7.4 is illustrated in Figure 7.18; it can be


clearly noted that the cable loading off all branches of model III is very low. In
particular, the HTS cables have a low load rating which is vital for future
network expansion or load growth, to utilise the high capacity potential of the
cables.

Hybrid Sub-Model II cable loading


3000

40
35

2500

30
25

1500

20

Amp

2000

15

1000

10
500

5
0
Loading Amp
Loading %

M
TS
-

BS
BQ
W
(H
M
TS
TS
Ca
-JA
bl
BS
(
BQ HTS e)
-L
Ca
Q
bl
(H
TS e)
LQ
Ca
-JA
bl
(H
e)
TS
Ca
bl
BS e)
BQ
-V
M
BS
BQ
-W
JA
-V
M
1
JA
-V
M
2
LQ
-W
A
W
-W
A
W
BNC
W
M
TS
W -NC
M
TS
-W
B

Figure 7.18: Hybrid sub-model II cable loading

The maximum loading utilised by WMTS-JA HTS cable was found to be 72%
when WMTS-BSBQ HTS cable disconnected or taken out of service. This
means there is a margin of 28% for extra loading that can be utilised in future
growth or should the need for extra capacity be raised due to unforeseen
circumstances. In addition, the corrective measurements such as opening or
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

216

Chapter 7: Development and Analysis of Victorian Hybrid power network model

closing circuit breakers or regulating phase shifters, which are normally taken
by Citipower for n-1 redundancy configuration, have not been adopted in the
simulation of this sub-model, owing to the lack of information regarding the
Citipower n-1 contingences, as it is considered confidential. However, the
results from the simulation identified the influence that HTS cable can have on
overall power network.

Table 7.4 illustrates the bus results of flow analysis performed on the hybrid
sub-model II. The table also lists bus parameters including name, real and
reactive generated powers, real and reactive static loads and load flow results
from which the real and reactive power losses are obtained with bus current
rating and power factor incorporated.

Table 7.4: Hybrid sub-model II power losses


Branch
From -> To Flow To -> From Flow
Losses
------------------------------------------------------------------------------------------------------Name
MW
MVAR
MW
MVAR
kW kVAR
---------------------------- ------------- ------------- ------------- --------------- -------- --------BSBQ-LQ (HTS)
79.742 77.761 -79.741 -77.749 0.5
-7367.6
LQ-JA (HTS)
-89.782 -78.385 89.782 78.4
0.3
-3430.2
WMTS-BSBQ (HTS) 246.648 227.768 -246.641 -227.655 6.8
-11704.9
WMTS-JA (HTS)
238.85 224.803 -238.841 -224.695 8.3
-15056.1
BSBQ-VM
24.105 23.979 -24.096 -23.911 8.7
-1317.6
BSBQ-W
29.987 28.804 -29.977 -28.725 10.1 -987.9
JA-VM
-24.289 -23.871 24.298 23.939
8.8
-1317.2
JA-VM
22.645 22.791 -22.637 -22.73
7.8
-1324.5
LQ-WA
34.087 33.019 -34.074 -32.917 13.2 -963.8
W-WA
29.977 28.725 -29.975 -28.71
2.1
-196.9
WB-NC
4.105
4.385
-4.104
-4.376
0.8
-6013.2
WMTS-NC
16.969 17.499 -16.939 -17.27
21.5 -8853.9
WMTS-WB
23.232 23.745 -23.198 -23.485 24.8 -5332.5
--------------------------------------------------Total power losses 113.7 -63866.3
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

217

Chapter 7: Development and Analysis of Victorian Hybrid power network model

The total real power losses were found to be 113.7 kW; in addition the total
reactive power was found to be -63866.3 kVAR.

The HTS cable capacitance influence reduction in the compensating reactor of


the cable by its smaller charging current as compared with XLPE or oil filled
cables. Magnetic shield of HTS cable reduces its reactance by utilising an outer
HTS conductor. This results in a more stable power network and voltage levels
[52].

A graphical representation of the load flow analysis of hybrid sub-model I is


presented in Figure 7.19.

Citipower 66kV Hybrid Losses


2000
0
-2000
-4000
-6000
-8000
-10000
-12000
-14000
kW
kVar

BS
BQ

-L
Q
W
M LQ- (HT
TS JA S
)
-B
SB (HT
W
M Q S)
TS (H
-J TS
A
)
(H
BS T S
BQ )
BS -VM
BQ
-W
JA
-V
M
JA
-V
LQ M
-W
A
W
-W
W A
B
W -N
M
C
T
W S-N
M
TS C
-W
B

-16000

Figure 7.19: Citipower 66kV hybrid sub-model II losses

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

218

Chapter 7: Development and Analysis of Victorian Hybrid power network model

Figure 7.19 reveals the potential capacity gain to the citipower network and
WMTS section in particular. The current WMTS 66kV overhead sub-model
presented in Section 4.2.1 had double and triple lines connecting the WMTS to
the zone substation JA and VM. Meanwhile the WMTS hybrid sub-model I,
which includes the upgraded substation BSBQ, had four cables for WMTSBSBQ and five cables for WMTS-JA; the cables were XLPE type rated at
1260A. It has been found that maximum loading of the cables reached up to
48% at normal operation and less than 100% at n-1 configuration. An
interesting finding was uncovered in Figure 7.18, where a single cable of HTS
rated at 7800A was able to meet and exceed the forecasted load demand for
the year 2011, whats more, the maximum cable loading was found to be 36%
at normal operation and about 80% at n-1 configuration. This is a clear
indication of what extra capacity HTS cable can provide for the network adding
to that the big savings in eliminating the need for constructing new cable ducts
in the city, should the HTS cable the one to be chosen rather than XPLE.

7.5 HTS Cable and Fault Current


A fault can occur in a power network due to various reasons. The effects of this
fault can alter the network behaviour, so predicting these effects are of critical
importance to determine the overall network response to the fault. Here is
where fault current calculation plays a big role in ascertaining the consequence
for network voltages and currents. Furthermore, a reliable network can only be

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

219

Chapter 7: Development and Analysis of Victorian Hybrid power network model

designed when a comprehensive analysis of the system behaviour is carried out


during all types of operation conditions [53].

There are two main circumstances that any particular power network operates
under, the first of which is a normal operation, under normal conditions, while
the second operation is spread over the network when abnormalities occur or
when the network is under the effect of a range of faults. By simulating these
faults it is possible then to: configure the network in a way which minimizes the
effects of faults; rate the network elements to accommodate for the fault
currents; estimate the rating break point so that switchgears and fuses within
the network operate safely; validate the suitability of network protection;
determine the reliability and security of the network and investigate any poor
performance in the network [53].

Like any other power cable in a particular power network, HTS cable can be
struck with fault current [54]. Normally fault current can be as high as ten to
thirty times the normal operating current. The period of which the fault current
can last is determined by the protection equipment and the load of the cable, in
any circumstance the fault current will constrain the HTS conductor to operate
as a normal conductor. In other words, it loses its superconductivity properties
for the fault duration; this means heat will build up in the conductor in that period
and the real concern is whether or not the generated heat can damage the HTS
cable. In an attempt to investigate the effects of fault current on HTS cables,
Lue et al. [54] presented an interesting finding from a few tests carried out on a
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

220

Chapter 7: Development and Analysis of Victorian Hybrid power network model

HTS prototype cable. The finding stated that a negligible degrading was
observed. In addition, limitations of both thermal and high current magnitude
were found in these tests.

Fault current testing of HTS cables was performed by Southwire on a 30 meter


cable. According to Lue et al. [55], the aim of the test was to verify that HTS
cables can withstand a high fault current. The results of the testing indicate a
rise in the cable voltage, meaning that the cable conductor temperature had
risen during the fault. In addition, not only was the temperature of the cable
raised but also the resistive properties of the cable conductor have rose
throughout the fault, yet when the fault disappeared, the cable voltage returned
almost to its normal level. However, the resistive properties of the cable
conductor did fall to its normal value at slower rate, in comparison to the voltage
drop rate.

Verily, extra high currents cause high magnetic fields and superconductivity will
be interrupted for a few milliseconds. The resulting high resistance of the
conductor limits the fault current in HTS cables. In light of this cable behaviour
at the fault current, HTS cable inherits a current limitation property, so by
knowing the amount of receptivity rise, the limitation of HTS cables current can
be set. Figure 7.20 which was provided by nkt cables [56], shows cable
resistance as a function of current. It can be clearly observed that the cable
resistance has risen immediately at the fault current then it reached a finite limit
even when the current kept rising.
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

221

Chapter 7: Development and Analysis of Victorian Hybrid power network model

Figure 7.20: HTS cable ability to limit a fault current [56]

7.6 HTS Cable and Short Circuit Analysis SubModel


In this sub-model a short circuit analysis using EDSA software has been
performed on Citipower 66kV hybrid Sub-Model II which was presented in
Section 7.4.2. This analysis brings to light anticipated current levels of HTS
cables during short circuit event. Knowing the magnitude of the short circuit
current can be vital in designing the power network elements, especially
protection equipment. What would be of a great concern to this study is whether
or not current protection schemes and switchgears are to be replaced?
Moreover, the short circuit analysis will highlight areas where protection is
inadequate and if there are any requirements for changes to network elements
settings change to bring down short circuit fault to acceptable levels. Figure

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

222

Chapter 7: Development and Analysis of Victorian Hybrid power network model

7.21 shows the HTS cable and Short Circuit Analysis Sub-Model. The figure
clearly illustrates the analysed sub-model for short circuit event and the results
are noted close to each bus bar in the network.

The results obtained from short circuit analysis of Citipower 66kV hybrid submodel II are presented in Table 7.5 The table lists bus parameters including the
current rating.

Table 7.5: Citipower 66kV hybrid v short circuit analysis results


Bus Name
BSBQ 66kV Bus
JA 66kV Bus
LQ 66kV Bus
NC 66kV Bus
VM 66kV Bus
W 66kV Bus
WA 66kV Bus
WB 66kV Bus

IP
A
2216
2216
2216
2173
2212
2211
2211
2182

3P Fault
A
875
875
875
856
873
873
873
860

LL Fault
A
758
758
758
741
756
756
756
745

LG Fault
A
735
735
735
722
733
733
733
725

LLG Fault
A
846
846
846
836
845
845
845
838

Meanwhile the fault level at HTS cable was found to be matching the bus fault.
A fault occurred 35 Meters away from a bus in LQ-JA HTS cable was: 875A for
three phase, line-ground and double line-ground faults; 758A for line-line fault.

The results presented in Table 7.6 confirm the expected outcome of the
analysis. As mentioned earlier, insignificant increases in the fault currents have
been found on the buses that HTS cables were attached to. This indicates that
normal protection schemes should be sufficient to handle any fault currents that
might occur in the network.
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

223

Chapter 7: Development and Analysis of Victorian Hybrid power network model

Figure 7.21: Citipower 66kV hybrid short circuit analysis sub-model


Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

224

Chapter 7: Development and Analysis of Victorian Hybrid power network model

7.7 Conclusion
HTS cable technology enables a massive increase in power transmission
capacity, with its unique characteristics of low impedance and low ohmic loss.
HTS cable has the potential of becoming a feasible new solution to power
transmission problems. This incorporates environmental benefits of no thermal
or magnetic field emission and no visual impact on the aesthetic surroundings.
Economic benefits can also be achieved in situations where civil works are
reduced by avoiding unnecessary excavation works.

The Triax design facilitates economic benefits through the substitution of HV by


MV attributable to reduced transmission losses. It will be essential to
demonstrate the reliability and efficiency of this technology commercially in
order to gain wide acceptance.

This chapter has established that utilising HTS cables will enhance the reliability
and improve power networks loading capacity. A hybrid sub-model has been
simulated for load flow as well as short circuit analysis. All results revealed that
HTS cables can be employed along with conventional cables like XLPE, and in
some circumstances the HTS cables may prove a more technically and
economically efficient solution than any other counterparts.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

225

Chapter 8: Conclusions and Recommendations

CHAPTER 8
CONCLUSION AND
RECOMMENDATIONS
8.0 Introduction
In most countries around the world, energy and power sectors have been
liberalised, which has forced the electricity utilities to operate under more
competitive retail markets. Hence, utilities were put under pressure to develop
greater flexibility, environmental-friendliness and security for supplying,
transmitting and distributing electricity.

Chapter 1 highlighted the increasing global trend of overhead lines replacement


with underground cables over the last decade. Emerging new cable technology,
combined

with

improved

production

processes

and

specifications

of

international testing, has led to increased usage of underground cables.

8.1 Appraise
Chapter 2 established the necessary background in the transition of overhead
lines to underground for both, distribution and transmission power networks.
Benefits and limitations have been closely examined in underground and
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

226

Chapter 8: Conclusions and Recommendations

overhead technologies. Various cable technologies have also been extensively


questioned and scrutinised.

This field of study was exposed to methodical and thorough research; there is a
common perspective which is shared amongst multinational power engineers
and researchers, that underground transmission cabling bestows mammoth
improvements & benefits when compared to its predecessor technology of
overhead lines. Nonetheless, the overhead technology is still dominating and is
in use all over the world.

A comprehensive overview of the overhead power network along with its


structure was dedicatedly elaborated in Chapter 3. For decades, power has
been transmitted via a relatively low cost medium, commonly known as
overhead lines. Since then, substantial transformations have been occurring to
improve the reliability of overhead networks. A load flow technique is often
employed to analyse and design an improved overhead power network.
Chapter 4 has provided an overview of overhead power networks. This chapter
has also extensively explored overhead power networks various aspects as
well as the major factors that form the core requirements of a reliable power
network. Various conductors used in overhead lines have also been discussed.
As power loss is a major concern for transmission systems, an elaborative
study on power losses in overhead lines has also been included.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

227

Chapter 8: Conclusions and Recommendations

The Victorian overhead power network was researched in an attempt to


efficiently design an underground network for Victoria, which is covered in
Chapter 5. Comprehensive analyses and the development of Victorian
overhead power network sub-models were presented in detail in this chapter. In
addition, a great deal of emphasis was placed on overall overhead network submodels, which were discussed in Chapter 4. These analytical studies are of a
great significance for the future growth and the safe operation of the Victorian
power network. Various forecast models were analysed and critically analysed
in order to determine future network needs of additional lines and transformers
to cope and cater for the extra load which was predicted in forecast studies.

Load flow analysis and other industrial based specialised software applications
were utilised to investigate and develop various sub-transmission network
models. The results obtained from the load flow analysis provided crucial
information about all buses in the network. Some buses were exceeding their
normal operation values or nominal values so an action was made to rectify the
problem associated with any abnormality in the network. It is worth mentioning
that Citipower n-1 redundancy configurations were met in all of the developed
sub-models. Another outcome of the load flow analysis was the uncovering of
the real and reactive power losses at each line and the effect of forecasted
loading on the losses was also identified.

Chapter 6 examined the Victorian overhead power network in an attempt to


efficiently design an underground network for Victoria. It has become mandatory
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

228

Chapter 8: Conclusions and Recommendations

for most modern cities worldwide to use underground power cables. This
demonstrates

that

undergrounding

has

become

economically

and

technologically feasible. Various advantages have been presented about


underground cables in this chapter. However, there are significant challenges in
the underground network as much as it has benefits. It is essential to carefully
design and implement an underground power network.

A thorough analysis and development of Victorian underground power network


sub-models were presented in detail in this chapter. In addition, an elaboration
of overall underground network sub-models was discussed in chapter 6. This
analytical study was again of great significance for the future growth and safe
operation of the Victorian power network. Various forecasted models were
analysed to determine the future need for additional lines and transformers in
order to enable the handling of the forecasted extra load.

Load flow analysis and other industrial based specialised software applications
were used to investigate and develop various sub-transmission network models.
The results obtained from the load flow analysis provided crucial information
about all buses in the network. Some buses were exceeding their normal
operation values or nominal values so an action was made to rectify the
problem associated with any abnormality in the network, Citipower n-1
redundancy configurations were met in all sub-models developed in this
chapter.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

229

Chapter 8: Conclusions and Recommendations

Another outcome of the load flow analysis was the determination of real and
reactive power losses at each line, also the effect of the forecasted loading on
the losses were identified.

Chapter 7 discussed the development and analysis of a Victorian hybrid


underground power network, where, in addition to conventional XLPE cables a
new generation of cable technology was used in the form of HTS cables. HTS
cable technology enables a massive increase in power transmission capacity
with its unique characteristics of low impedance and ohmic loss. HTS cable has
the potential of becoming a feasibly new solution to power transmission
problems. This incorporates environmental benefits of no thermal or magnetic
field emission and no visual impact on the surroundings. Economic benefits
can also be achieved in situations where civil works are reduced by avoiding
unnecessary excavation.

The Triax design facilitates economic benefit through the substitution of HV with
MV, attributable to reduced transmission losses. It will be essential to
demonstrate the reliability and efficiency of this technology commercially in
order to gain wide acceptance.
Chapter 7 has also established that utilising HTS cables will enhance reliability
and improve the loading capacity of power networks. A hybrid sub-model has
been simulated for load flow analysis purposes as well as for short circuit
analysis; all results revealed that HTS cables can be employed alongside

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

230

Chapter 8: Conclusions and Recommendations

conventional cables like XLPE, and in some circumstances the HTS cables may
prove to be a more economical solution than any other counterpart cables.

This research contributed directly to the body of knowledge of power


transmission and distribution systems. More specifically, it contributes to the
overhead

transmission

lines undergrounding framework.

The

research

produced reference guidelines for Victorian underground sub-transmission and


distribution networks. The research made a unique technical contribution to the
processes and procedures of undergrounding overhead power lines in Victoria
as well as laid emphasis on portability aspects for potential adoption by other
Australian states.

This research contributes to the knowledge framework in the following areas:

(1) identifies the requirements of the technical aspects of undergrounding


overhead power lines in Victoria, this work is of immense benefit to the
Victorian overhead sub-transmission and distribution networks as it
provides a technical solution with appropriate processes and measures
for migrating to underground network;
(2) investigates the implementation of a new cable technology and its effects
on the electricity supply from efficiency point of view as well as reliability
and economics;

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

231

Chapter 8: Conclusions and Recommendations

(3) presents a unique simulated models that produce a new voltage level of
the new underground cable technology, HTS, to be used in a small
section of the Victorian power network;
(4) demonstrates the hybrid implementation of the new cable technology,
HTS, combined with the traditional underground cable technology, XLPE,
and their simulated performance;
(5) it signifies a remarkable reduction in the environmental impact of power
networks, which includes EMF and pollution in addition to the improved
public safety.

8.2 Recommendations
Large scale applications of HTS cables are crucial when making a strategic
decision for the viability of HTS in comparison to its conventional XLPE
counterparts. [57]. Market acceptance of HTS cable technology needs an
extensive and a proven field illustration, which covers both, the systems
capabilities and appropriateness for installation within commercial utilities [58].

The following works are recommended in extension to this research; a pilot


project with HTS cable runs approximately 700 m between two 66kV zone
substations LQ and JA of WMTS loop in Citipower network. The location for this
pilot project was selected because it mingles performance specifications
suitable for the application of HTS cables in addition to other advantages. The

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

232

Chapter 8: Conclusions and Recommendations

chosen route offers many of the challenges that will be faced in other field
installations

Figure 8.1 presents the Citipower 66kV LQ-JA pilot sub-model with the selected
length of the HTS cable. A load flow analysis on the model was carried out to
obtain power loss figures. The figure shows the summary of the load flow
analysis results situated close to the bus, line or transformer.

Power capacity can be increased up to three folds when existing ducts are
retrofitted with HTS cables. Given the ever increasing cost of rights-of-way with
highly congested pathways with other utility assets such as gas and telephony,
all of these factors make the cost of construction new ducts for underground
power cables unrealistic.

The objective of the proposed pilot is to demonstrate HTS cables in an


operational grid. The cable design and its accessories were presented in
Section 7.3. However, this cable will need to be tested for a period of time to
verify the installation in order to establish a benchmark for the cables attributes
and behaviour in the Australian environment. Altera recommends minimum of
two years testing prior to commission the cable to portray an accurate reading
of cable behaviour.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

233

Chapter 8: Conclusions and Recommendations

Figure 8.1: Citipower 66kV LQ-JA pilot sub-model


Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

234

Chapter 8: Conclusions and Recommendations

As this will be the first installation of an underground HTS cable in Australia,


particular attention has to be paid to the installation site. Comprehensive
surveys need to be carried out for sites manholes, ducts and mounting
locations so that no unexpected dilemmas are experiencing during the cable
installation.

A major milestone would be the evaluation phase, in which determining the


cable performance capability to cater for the forecasted load without requiring
regular maintenance or attention. To obtain accurate data on the cables
behaviour, key parameters of the cable and cooling system must be utilised in
addition to constantly measuring the cables temperature at different points in
the route, this temperature reading must be captured before and after the
termination points. All of these readings must be collated and stored in a central
location to be further processed and analysed for verification purposes.

HTS cable pilot project can demonstrate the potential superconductivity which
plays a vital role in the modernisation of electrical power networks. It also
showcases the reliability, security and potential benefits that they would bring to
the Victorian aging electrical infrastructure. This pilot also leads one step closer
to full commercialisation and utilisation of HTS cable technology.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

235

References

REFERENCES
1.

Christensen, P. and Roes, T., 'Underground EHV System In


Copenhagen', Transmission and Distribution World: NESA. 2000.

2.

Barber, K., 'Undergrounding transmission and distribution lines in


Australia', Australian Power Transmission & Distribution magazine. 2004.

3.

Mutton, S., Tebbs, J., Simpson, S., and Mann, R., 'Investigation of Low
Reliability Urban and Rural Feeders Phase Two of Two TXU Networks'.
2000.

4.

U.S. Department of Labor, O.S.H.A., 'Electric Power, Generation


Transmission Distribution eTool'. 2005.

5.

Brown, R., 'Undergrounding Assessment Phase 1 Final Report Literature


Review and Analysis of Electric Distribution Overhead to Underground
Conversion': Raleigh. 2007.

6.

Cowell, R., 'The Scope for Undergrounding Overhead Electricity Lines'.


2003.

7.

ICF Consulting Ltd, 'Overview of the Potential for Undergrounding the


Electricity Networks in Europe': London. 2003.

8.

Kelley, N. and Jipping, J. 'HTS cable system demonstration at Detroit


Edison'. Power Engineering Society Winter Meeting, 2002. IEEE. 2002.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

236

References

9.

Putting Cables Underground Working Group, 'Putting Cables


Underground Report'. 1998.

10.

Wales, I.P.a.R.T.o.N.S., 'Electricity Undergrounding in New South


Wales'. 2002.

11.

Citipower, 'DISTRIBUTION SYSTEM PLANNING REPORT'. 2006.

12.

Karlstrand, J., Bergman, G., and Jonsson, H.-A. 'Cost-efficient XLPE


cable system solutions'. AC-DC Power Transmission, 2001. Seventh
International Conference on (Conf. Publ. No. 485). 2001.

13.

Communities, C.o.t.E., 'Background Paper Undergrounding of electricity


lines in europe': Brussels. 2003.

14.

Chang, G.W., Huang, H.M., and Lai, G.G. 'A study on controlling
electrical stress of underground cable by semi-conductive shielding'.
Transmission and Distribution Conference and Exhibition 2002: Asia
Pacific. IEEE/PES. 2002.

15.

Johnson, B., 'Out of Sight, Out of Mind?' Washington. 2006.

16.

Commission, J.L.A.a.R., 'Evaluation of Underground Electric


Transmission Lines in Virginia'. 2006.

17.

Ettedgui, E., Grijalva, S., Silberglitt, R., and Wakefield, C.A.-W., C.


'Potential impact of high temperature superconducting cables on grid
reliability and available transfer capacity: power flow simulation results'.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

237

References

Power Engineering Society Winter Meeting, 2002. IEEE Power


Engineering Society Winter Meeting, 2002. IEEE VO - 1. 2002.
18.

West, R. and Larsen, S. 'Kentish town project [power cable laying]'.


Cables in Tunnels (Ref. No. 2000/070), IEE Seminar. 2000.

19.

Jey, K. and Jeyapalan, P.E., 'Creative Ways to Build Broadband


Networks And Underground Power Cables Through
StrategicPartnerships Among Utilities'. 2003.

20.

Maney, C.T., 'Benefits of urban underground power delivery'. Technology


and Society Magazine, IEEE. 15(1): p. 12-22. 1996.

21.

'Back-to-back hurricanes cripple US network Back-to-back hurricanes


cripple US network'. Power Engineer (see also Power Engineering
Journal). 19(5): p. 4-4. 2005.

22.

Lakervi, E. and Holmes, E.J., 'Electricity distribution network design', ed.


A.T. Johns and Platts, J.R. Vol. 9, London: Peter Peregrinus Ltd. on
behalf of the Institution of Electrical Engineers, London, United Kingdom.
1988.

23.

Bayliss, C., 'Transmission And Distribution Electrical Engineering (Book


Review)'. Power Engineering Journal [see also Power Engineer]. 11(3):
p. 99-99. 1997.

24.

Cable, G., 'General Cables, Electric Utility Cables'. 2004.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

238

References

25.

Kyoung-Soo, R. 'An approach to allocate real power losses of


transmission lines to individual loads'. TENCON 99. Proceedings of the
IEEE Region 10 Conference. 1999.

26.

Nagrath, I.J. and Kothari, D.P., 'Power System Engineering': TATA


McGraw Hill Publishing Company Limited. 1994.

27.

Rabinowitz, M., 'Power systems of the future. I'. Power Engineering


Review, IEEE. 20(1): p. 5-16. 2000.

28.

Citipower, 'Distribution System Planning Report': Melbourne. 2007.

29.

Pansini, A.J. and Smalling, K.D., 'Undergrounding Electric Lines'. Second


ed, Lilburn: The Fairmont Press, Inc. 1993.

30.

Marazzato, H. and Barber, K.W., 'The Challenge for Undergrounding


Electricity Supply', Australian Power Transmission & Distribution
magazine

31.

Ausnet, S., 'SP AusNet Electricity Distribution Price Review 2006'. 2005.

32.

Peter, W., Wally, S., Graham, K., Kelvin, G., David, S., and Dieter, H.,
'Environment Effects Statement': Melbourne. 1989.

33.

Olex, 'High Voltage catalogue',

34.

Koch, H. and Hopkins, M. 'Overview of gas insulated lines (GIL)'. Power


Engineering Society General Meeting, 2005. IEEE. 2005.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

239

References

35.

Benato, R., Di Mario, C., and Koch, H. 'High Capability Applications of


Long Gas-Insulated Lines in Structures'. PES TD 2005/2006. 2006.

36.

Kalam, A., Al-Khalidi, H., and Willen, D. 'HTS cable and its anticipated
effects on power transmission networks'. AC and DC Power
Transmission, 2006. ACDC 2006. The 8th IEE International Conference
on. 2006.

37.

Schroth, R.G. and Obst, D. 'Long distance tunnels for the installation of
400 kV XLPE cables'. Cables in Tunnels (Ref. No. 2000/070), IEE
Seminar. 2000.

38.

Zhang, X., Jiang, X., and Xie, H. 'The application of fiber optic distributed
temperature sensor to fault detection of XLPE insulated underground
cable'. Properties and Applications of Dielectric Materials, 2000.
Proceedings of the 6th International Conference on. 2000.

39.

Mendez, S.J.M. and Monteys, J. 'Design of power and communication


cable installations to minimise interference in tunnels'. Cables in Tunnels
(Ref. No. 2000/070), IEE Seminar. 2000.

40.

Bernstein, R., Oristaglio, M., Miller, D.E., and Haldorsen, J., 'Imaging
radar maps underground objects in 3-D'. Computer Applications in
Power, IEEE. 13(3): p. 20-24. 2000.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

240

References

41.

Orton, H.E. and Samm, R., 'Worldwide underground transmission cable


practices'. Power Delivery, IEEE Transactions on. 12(2): p. 533-541.
1997.

42.

Rahman, M.M. and Nassi, M., 'High capacity cable's role in once and
future grids'. Spectrum, IEEE. 34(7): p. 31-35. 1997.

43.

Abdel-Salam, M., Anis, H., El-Morshedy, A., and Radwan, R., 'HighVoltage Engineering Theory and Practice'. Second ed, New York: Macel
Dekker, Inc. 725. 2000.

44.

Gouge, M.J., Lindsay, D.T., Demko, J.A., Duckworth, R.C., Ellis, A.R.,
Fisher, P.W., James, D.R., Lue, J.W., Roden, M.L., Sauers, I., Tolbert,
J.C., Traeholt, C., and Willen, D., 'Tests of tri-axial HTS cables'. Applied
Superconductivity, IEEE Transactions on. 15(2): p. 1827-1830. 2005.

45.

Willn, D., 'Experience Shapes the Future Superconducting Cables'. p.


26. 2009.

46.

Masuda, T., Yumura, H., Watanabe, M., Takigawa, H., Ashibe, Y.,
Suzawa, C., Kato, T., Okura, K., Yamada, Y., Hirose, M., Yatsuka, K.,
Sato, K., and Isojima, S., 'High-temperature Superconducting Cable
Technology and Development Trends'. 2005.

47.

Shahidehpour, M., 'Cool currents: superconductors' evolution for power


transmission'. Power and Energy Magazine, IEEE. 3(2): p. 17-19. 2005.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

241

References

48.

GESCHIERE, A., WILLN, D., PIGA, E., BARENDREGT, P., ROYAL, J.,
and LYNCH, N. 'LONG DISTANCE TRIAX HTS CABLE'. 19th
International Conference on Electricity Distribution. Vienna. 2007.

49.

Jae-young, Y., Seung Ryul, L., and Jong Yul, K., 'Application
Methodology for 22.9 kV HTS Cable in Metropolitan City of South Korea'.
Applied Superconductivity, IEEE Transactions on. 17(2): p. 1656-1659.
2007.

50.

Willn, D., '66 kV, 300 MVA HTS Triax Cable for Melbourne'. p. 8. 2007.

51.

Citipower, 'Melbourne CBD Security of Supply Enhancement Project


Submission to the Essential Service Commission': Melbourne. p. 188.
2006.

52.

Kimura, A. and Yasuda, K., 'R & D of superconductive cable in Japan'.


Applied Superconductivity, IEEE Transactions on. 15(2): p. 1818-1822.
2005.

53.

Naylor, J.H., 'Fault Calculation', Power System Protection, T.E.T.


Association, Editor, The Institution of Electrical Engineers: London. 1995.

54.

Lue, J.W., Gouge, M.J., and Duckworth, R.C., 'Over-current testing of


HTS tapes'. Applied Superconductivity, IEEE Transactions on. 15(2): p.
1835-1838. 2005.

55.

Lue, J.W., Barber, G.C., Demko, J.A., Gouge, M.J., Stovall, J.P.,
Hughey, R.L., and Sinha, U.K., 'Fault current tests of a 5-m HTS cable'.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

242

References

Applied Superconductivity, IEEE Transactions on. 11(1): p. 1785-1788.


2001.
56.

nkt cables, G., 'HTS Triax Energy Cable Systems HTS Cables and
Accessories'. p. 12. 2009.

57.

Matheus, C., Haubrich, H.J., and Willen, D. 'Superconducting cables as a


new option in network planning'. Power Tech, 2005 IEEE Russia. 2005.

58.

Kelley, N.J., Wakefield, C., Nassi, M., Corsaro, P., Spreafico, S., Von
Dollen, D.W., and Jipping, J., 'Field demonstration of a 24-kV warm
dielectric HTS cable'. Applied Superconductivity, IEEE Transactions on.
11(1): p. 2461-2466. 2001.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

243

Appendix A

Appendix A

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

244

Appendix A

Lakervi [51] presented the power loss as the maximum current or real and
reactive power flows have been determined, the series active and reactive
power losses in a 3-phase circuit or any item of equipment, P1 and Qj can be
calculated from the following equations:

Pl 3I 2 Rl
2

or

(3.4)
2

P
Q
Pl Rl Rl
V
V

(3.5)

and Q 3I 2 Xl
2

P
Q
(3.6)
Xl Xl
V
V
where R1 and X1 refer to the circuit series resistance and reactance as shown

in Figure 3.2.

Given that the circuit shunt impedance is (Rs +jXs), as indicated in Figure 3.2,
the shunt losses can be calculated using the shunt current I instead of I:

Is

V/ 3
Rs 2 Xs 2

(3.7)

Figure 3.2 Calculation of circuit series and shunt losses

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

245

Appendix A

This circuit and method are most relevant for transformers and shunt
capacitors, while parallel connection of the susceptance of the capacitance B
and leakage conductance G is used when cables or high-voltage lines are
concerned. Their shunt losses can be calculated using:
2

V
Ps 3G GV 2
3
2

V
Qs 3B BV 2
3

(3.8)

The shunt resistive losses P for lines are usually very low while the reactive
losses
Q are negative; e.g. the shunt capacitance feeds reactive power to the system.
Here V is the phasephase voltage.
In the previous calculations it has been assumed that the system voltage was 3phase. However, particularly at low voltage, single- or double-phase systems
are sometimes used instead of the conventional 3-phase system because of
their

lower

construction

costs,

even

though

the

losses are

higher.

Example
The ratio of losses between a single-phase and a symmetrical 3-phase line is
derived. It is assumed that the same total real power P is delivered by both
circuits, that all conductors are similar and have resistance R, and also that the
phaseearth voltages are equal.

Single-phase line: The load P represents a certain current I. The current flows
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

246

Appendix A

through the phase line, load and neutral conductor, and thus the system losses
are
Pl1 I 2 (2 R) 2 I 2 R Pl

(3.10)

3-phase system: The load P is divided between three phases and the current in
all of these is 1/3. Because the load is symmetrical the phasor sum of these 3phase currents is zero, and thus no current flows in the neutral conductor:
2

I 2R 1
I
Pl 3 (3R)
Pl1
3
6
3

(3.11)

Thus, when the same real power is being delivered, the losses in a singlephase line are six times the losses in a balanced 3-phase line. In practice not all
loads will be balanced 3-phase loads and the resulting imbalance will reduce
this ratio.

When making economic comparisons, it is not sufficient just to compare the


losses. In the above example the investment required for the 3-phase system is
larger than that for the alternative single-phase arrangement. If the alternative of
a four-conductor 3-phase line operating at single phase is considered, this
would result in two wires in parallel being used for the phase and also the
neutral conductors. Under this mode of single-phase operation the losses would
be
P l1 2 I 2 ( R / 2) I 2 R

which is three times the losses at 3-phase operation of the same line.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

247

Appendix A

3.3.3 Load and loss load factors


In economic comparisons it is often necessary to take account of the recurring
annual system losses. System losses can be separated into so-called fixed
losses and variable losses. The fixed losses are those due to the magnetisation
currents of such items as transformers and reactors, which are often referred to
as iron losses. For simplicity it is assumed that these losses occur for the full
8760 hours per annum, neglecting outages owing to maintenance or faults.
Where more accuracy is required, the effect of the variation of voltage on the
losses may need to be taken into account.

The variable losses are those caused by the flow of current through the different
items of equipment on the network, and are also termed copper losses. Power
losses in a component having resistance R are proportional to the square of the
current flowing through it, i.e. P1 = 12R. For example, in Figure 3.3, the ratio
P1/P is much higher for high values of P than for low P values. The annual
energy losses Wl can be determined by integrating the squared time function or
duration curve of the current or of the power flow:
T

Wl R I (t )dt Pl (t )dt
2

(3.12)

This integration can be applied alternatively to the load curve shown in Figure
3.3a or to the duration curve in Figure 3.3b.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

248

Appendix A

Figure 3.3 Load and load-duration curves


a Load curve
b Duration curves for power (P) and power losses (P1)

The load factor F is defined as the ratio of the average power divided by the
maximum demand, and can be expressed as W/Pmax T. The loss load factor is
defined as the ratio of the average power loss divided by the losses at the time
of peak load, expressed by ( Wi/Pimax T). The load factor can be determined by
integrating the duration curve for F, and the loss load factor by integrating the
P1(t) curve. The quadratic relationship between P1 and P is shown in Figure
3.3b.
Where only the load factor F is available, various formulas have been
developed to obtain a quick approximation of loss load factor (LLF), generally
based on the expression LLF = aF + (1 a)F2. Two examples are given below:
2
Loss load factor 0.1F 0.9F

(3.13)

0.3F 0.7F 2

(3.14)

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

249

Appendix B

Appendix B

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

250

Appendix B

The following section presents a high level description of the risk assessment of
all CitiPower zone substations. It should be noted that the energy at risk
calculations are based on excluding any planned responses to mitigate the risk.

AP Zone Substation, Albert Park


Station Rating & supply area
Albert Park Zone substation has a summer n-1 rating of 61.6MVA comprised of
three 20/27MVA transformers operating at 66/11kV. The Zone Substation
supplies the Albert Park, South Melbourne and Port Melbourne areas.

Although expected demand for the next five years will exceed the stations n-1
rating, there is sufficient load transfer capability via 11kV links to adjacent zone
substations to cover this shortfall. Thus no customer load is at risk for the
outage of a major plant item.

AR Zone Substation, Armadale


Station Rating & supply area
Armadale Zone substation has a summer n-1 rating of 33.7MVA comprised of
two 20/30MVA transformers operating at 66/11kV. The Zone Substation
supplies the Armadale and Malvern areas.
Although expected demand for the next five years will exceed the stations n-1
rating, there is sufficient load transfer capability via 11kV links to adjacent zone
substations to cover this shortfall. Thus no customer load is at risk for the
outage of a major plant item.
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

251

Appendix B

B Zone Substation, Collingwood


Station Rating & supply area
B Zone substation has a summer n-1 rating of 29.0MVA comprised of two
20/27MVA transformers operating at 66/11kV. The Zone Substation supplies
the Collingwood and Abbotsford areas.

Although expected demand for the next five years will exceed the stations n-1
rating, there is sufficient load transfer capability via 11kV links to adjacent zone
substations and 7.4MVA cogeneration capacity to cover this shortfall. Thus no
customer load is at risk for the outage of a major plant item.

BC Zone Substation, Balaclava


Station Rating & supply area
Balaclava Zone substation has a summer n-1 rating of 32.1MVA comprised of
two 30MVA transformers operating at 66/11kV. The Zone Substation supplies
the Balaclava, St.Kilda East and Caulfield North areas.

The expected demand for the next five years is less than the stations n-1
rating, thus no customer load is at risk for the outage of a major plant item.

BK Zone Substation, Brunswick


Station Rating & supply area

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

252

Appendix B

Brunswick Zone substation has a summer n-1 rating of 27.4MVA comprised of


three 10MVA transformers operating at 22/6.6kV. The Zone Substation supplies
the Brunswick area.
The expected demand for the next five years is less than the stations n-1
rating, thus no customer load is at risk for the outage of a major plant item.

BSBQ Zone Substation, Bouverie St


Station Rating & supply area
Bouverie St Zone substation has a summer n-1 rating of 25.8MVA comprised of
three 10MVA transformers operating at 22/11kV. The Zone Substation supplies
the Carlton, Melbourne and Parkville areas.

In the 2006/2007 summer period the stations n-1 rating will be exceeded by
10.6MVA with 1202.3MWh at risk. By 2008/2009 summer, the stations N rating
will be exceeded by 1.2MVA with 2,684.3MWh at risk.

BSBQ SUMMER LOAD PROJECTION 2007-2011


Year
2007
2008
2009
Station Load 36.4
37.7
39.9
(MVA)
n-1 Rating
25.8
25.8
25.8
n Rating
38.7
38.7
38.7

2010
41.7

2011
43.5

25.8
38.7

25.8
38.7

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

253

Appendix B

BSBQ ANNUAL ENERGY & HOURS AT RISK

Network solutions to manage load at risk under n-1 conditions


_ Use of co-generation capacity of up to 14.8MVA.
_ Transfer of load via 11kV links to adjacent zone substations.
_ Upgrade of existing station to a high capacity CBD type station by 2009/10
with ultimate firm capacity of 110 MVA. This will incorporate a new transmission
network connection at BTS 66kV (Brunswick Terminal Station) and the
additional capacity will support existing CBD stations (Refer BTS 66kV report in
Transmission Connection Planning Report 2006).

The load at risk as shown above is before implementation of any network risk
mitigation strategies.
Prior to completion of the BSBQ upgrade, it is expected that the customer load
at risk is manageable by available load transfer capabilities to adjacent stations.
Following completion of the BSBQ upgrade, it is expected that the customer
load at risk will be minimal.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

254

Appendix B

C Zone Substation, Brunswick


Station Rating & supply area
C Zone substation has a summer n-1 rating of 17.0MVA comprised of three
7.5MVA transformers operating at 22/6.6kV. The Zone Substation supplies the
Brunswick area.
The expected demand for the next five years is less than the stations n-1
rating, thus no customer load is at risk for the outage of a major plant item.

CL Zone Substation, Camberwell


Station Rating & supply area
Camberwell Zone substation has a summer n-1 rating of 65.8MVA comprised of
two 20/30MVA transformers and one 20/27MVA transformer operating at
66/11kV. The Zone Substation supplies the Camberwell and Hawthorn areas.

The expected demand for the next five years is less than the stations n-1
rating, thus no customer load is at risk for the outage of a major plant item.

CW Zone Substation, Collingwood


Station Rating & supply area
Collingwood Zone substation has a summer n-1 rating of 32.2MVA comprised
of two 20/27MVA transformers operating at 66/11kV. The Zone Substation
supplies the Collingwood, Fitzroy and Abbotsford areas.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

255

Appendix B

Although expected demand for the next five years will exceed the stations n-1
rating, there is sufficient load transfer capability via 11kV links to adjacent zone
substations to cover this shortfall. Thus no customer load is at risk for the
outage of a major plant item.

DA Zone Substation, Docklands Area


Station Rating & supply area
Docklands Zone substation has a summer n-1 rating of 28.8MVA comprised of
three 10/13.5MVA transformers operating at 22/11kV. The Zone Substation
supplies the Docklands and North Melbourne areas.
In the 2006/2007 summer period the stations n-1 rating will be exceeded by
5.0MVA with 116.7MWh at risk.

DA SUMMER LOAD PROJECTION 2007-2011


Year
2007
2008
2009
Station Load
33.8
35.8
37.8
(MVA)
n-1 Rating
28.8
28.8
28.8
n Rating
42.9
42.9
42.9

2010

2011

40.0

42.3

28.8
42.9

28.8
42.9

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

256

Appendix B

DA ANNUAL ENERGY & HOURS AT RISK

Network solutions to manage load at risk under n-1 conditions


_ Use of Co-generation capacity of up to 2 MVA
_ A planned new 11kV link between DA and WG in 2007/08 to increase load
transfer capability.
_ Following installation of a 3rd 27MVA 66/11kV transformer at WG by 2007/08,
new 11kV feeders will be installed from WG to Docklands area for load transfer.

The load at risk shown above is before implementation of any network risk
mitigation strategies.
Although the expected demand over the next five years is higher than the
stations n-1 rating, it is expected that the customer load at risk is manageable
by available load transfer capabilities to adjacent stations.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

257

Appendix B

E Zone Substation, Port Melbourne


Station Rating & supply area
E Zone substation has a summer n-1 rating of 24.3MVA comprised of one
10/13.5MVA transformer and one 20MVA transformer operating at 66/6.6kV.
The Zone Substation supplies the Port Melbourne and Fishermans Bend areas.

The expected demand for the next five years is less than the stations n-1
rating, thus no customer load is at risk for the outage of a major plant item.

F Zone Substation, Fitzroy


Station Rating & supply area
Fitzroy Zone substation has a summer n-1 rating of 22.9MVA comprised of
three 10MVA transformers operating at 22/6.6kV. The Zone Substation supplies
the Fitzroy north area.
The expected demand for the next five years is less than the stations n-1
rating, thus no customer load is at risk for the outage of a major plant item.

FB Zone Substation, Fishermans Bend


Station Rating & supply area
Fishermans Bend Zone substation has a summer n-1 rating of 63.7MVA
comprised of three 20/30MVA transformers operating at 66/11kV. The Zone
Substation supplies the Fishermens Bend and Port Melbourne areas.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

258

Appendix B

The expected demand for the next five years is less than the stations n-1
rating, thus no customer load is at risk for the outage of a major plant item.
FR Zone Substation, Flinders & Ramsden Place
Station Rating & supply area
FR Zone substation has a summer n-1 rating of 61.4MVA comprised of three
30MVA transformers operating at 66/11kV. The Zone Substation supplies the
Melbourne CBD and Jolimont areas.

Although expected demand for the next five years will exceed the stations n-1
rating, there is sufficient load transfer capability via 11kV links to adjacent zone
substations to cover this shortfall. Thus no customer load is at risk for the
outage of a major plant item.

J Zone Substation, Spencer Street


Station Rating & supply area
J Zone substation has a summer n-1 rating of 38.4MVA comprised of four
10MVA transformers operating at 22/6.6kV. The Zone Substation supplies the
Melbourne CBD and Dockland areas.

The expected demand for the next five years is less than the stations n-1
rating, thus no customer load is at risk for the outage of a major plant item.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

259

Appendix B

JA Zone Substation, Little Bourke Street


Station Rating & supply area
JA Zone substation has a summer n-1 rating of 118MVA comprised of three
55MVA transformers operating at 66/11kV. The Zone Substation supplies the
Melbourne CBD and Docklands areas.
In the 2009/2010 summer period the stations n-1 rating will be exceeded by
6.5MVA with 42.0MWh at risk.

JA SUMMER LOAD PROJECTION 2007-2011


Year
2007
2008
2009
Station Load
94.9
109.1
115.7
(MVA)
n-1 Rating
118.0
118.0
118.0
n Rating
172.5
172.5
172.5

2010

2011

124.5

131.3

118.0
172.5

118.0
172.5

JA ANNUAL ENERGY & HOURS AT RISK

Network solutions to manage load at risk under n-1 conditions


_ Load reduction involving transfer of load via 11kV links to adjacent stations.
_ Installation of 2 x 12MVAr 11kV capacitor banks by 2008/09 to improve
transformer and subtransmission line loading under plant outage contingency.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

260

Appendix B

The load at risk shown above is before implementation of any network risk
mitigation strategies.
Although the expected demand over the next five years is higher than the
stations n-1 rating, it is expected that the customer load at risk is manageable
by available load transfer capabilities to adjacent stations.

L Zone Substation, Deepdene


Station Rating & supply area
L Zone substation has a summer n-1 rating of 32.1MVA comprised of two
20/30MVA transformers operating at 66/11kV. The Zone Substation supplies
the Balwyn, Canterbury and Kew areas.

Although expected demand for the next five years will exceed the stations n-1
rating, there is sufficient load transfer capability via 11kV links to adjacent zone
substations to cover this shortfall. Thus no customer load is at risk for the
outage of a major plant item.

LQ Zone Substation, Little Queen Street


Station Rating & supply area
Little Queen Zone substation has a summer n-1 rating of 131.6MVA comprised
of three 60MVA transformers operating at 66/11kV. The Zone Substation
supplies the Melbourne CBD area.
A total of additional 12MVAr capacitor bank capacity has been installed at LQ in
2006 to improve the transformer loading.
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

261

Appendix B

Although expected demand for the next five years will exceed the stations n-1
rating, there is sufficient load transfer capability via 11kV links to adjacent zone
substations to cover this shortfall. Thus no customer load is at risk for the
outage of a major plant item.

LS Zone Substation, Laurens Street


Station Rating & supply area
Laurens St Zone substation has a summer n-1 rating of 23.6MVA comprised of
two 10MVA transformers and one 13.5MVA transformer operating at 22/6.6kV.
The Zone Substation supplies the North Melbourne and Parkville areas.

In the 2006/2007 summer period the stations n-1 rating will be exceeded by
3.5MVA with 24.3MWh at risk.

LS SUMMER LOAD PROJECTION 2007-2011


Year
2007
2008
2009
Station Load
27.1
28.3
28.8
(MVA)
n-1 Rating
23.6
23.6
23.6
n Rating
35.5
35.5
35.5

2010

2011

29.4

30.0

23.6
35.5

23.6
35.5

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

262

Appendix B

LS ANNUAL ENERGY & HOURS AT RISK

Network solutions to manage load at risk under n-1 conditions


_ Load reduction involving transfer of load via 11kV links to VM via autotransformers.
_ A new HV link is planned to be installed between LS and adjacent zone
substation in 2008/09 to increase load transfer capability.

The load at risk shown above is before implementation of any network risk
mitigation strategies.
Although the expected demand over the next five years is higher than the
stations n-1 rating, it is expected that the customer load at risk is manageable
by available load transfer capabilities to adjacent stations.

MG Zone Substation, Montague Street, Port Melbourne


Station Rating & supply area
Montague Zone substation has a summer n-1 rating of 61.7MVA comprised of
two 20/30MVA transformers and one 20/27MVA transformer operating at
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

263

Appendix B

66/11kV. The Zone Substation supplies the South Melbourne and Melbourne
CBD areas.

Although expected demand for the next five years will exceed the stations n-1
rating, there is sufficient load transfer capability via 11kV links to adjacent zone
substations to cover this shortfall. Thus no customer load is at risk for the
outage of a major plant item.

MP Zone Substation, McIlwraith Place, Melbourne


Station Rating & supply area
Myers Place Zone substation has a summer n-1 rating of 116.3MVA comprised
of three 55MVA transformers operating at 66/11kV. The Zone Substation
supplies the Melbourne CBD area.

A total of additional 24MVAr capacitor bank capacity is being installed at MP for


completion in 2006/07 summer to improve the transformer loading.
In the 2006/2007 summer period the stations n-1 rating will be exceeded by
4.2MVA with 18.4MWh at risk.
MP SUMMER LOAD PROJECTION 2007-2011
Year
2007
2008
2009
Station Load
120.5
123.2
125.9
(MVA)
n-1 Rating
116.3
116.3
116.3
n Rating
169.5
169.5
169.5

2010

2011

128.6

131.4

116.3
169.5

116.3
169.5

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

264

Appendix B

MP ANNUAL ENERGY & HOURS AT RISK

Network solutions to manage load at risk under n-1 conditions


_ Load reduction involving transfer of load via 11kV links to adjacent stations.
_ The planned upgrade of BSBQ in around 2009/10 will allow load to be
permanently transferred from MP to BSBQ.

The load at risk shown above is before implementation of any network risk
mitigation strategies.

Although the expected demand over the next five years is higher than the
stations n-1 rating, it is expected that the customer load at risk is manageable
by available load transfer capabilities to adjacent stations.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

265

Appendix B

NC Zone Substation, Northcote


Station Rating & supply area
Northcote Zone substation has a summer n-1 rating of 28.5MVA comprised of
two 20/30MVA transformers operating at 66/11kV. The Zone Substation
supplies the Northcote area.

The expected demand for the next five years is less than the stations n-1
rating, thus no customer load is at risk for the outage of a major plant item.

NR Zone Substation, North Richmond


Station Rating & supply area
North Richmond Zone substation has a summer n-1 rating of 57.4MVA
comprised of two 23/28MVA transformers and one 20/27MVA transformer
operating at 66/11kV. The Zone
Substation supplies the Richmond and Abbotsford areas.

The expected demand for the next five years is less than the stations n-1
rating, thus no customer load is at risk for the outage of a major plant item.

PM Zone Substation, Port Melbourne


Station Rating & supply area
Port Melbourne Zone substation has a summer n-1 rating of 28.0MVA
comprised of three 10/13.5MVA transformers operating at 66/6.6kV. The Zone
Substation supplies the Port Melbourne area.
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

266

Appendix B

The expected demand for the next five years is less than the stations n-1
rating, thus no customer load is at risk for the outage of a major plant item.

PR Zone Substation, Prahran


Station Rating & supply area
Prahran Zone substation has a summer n-1 rating of 27.5MVA comprised of two
9.3/11.7MVA transformers and one 10/13.5MVA transformer operating at
22/11kV. The Zone Substation supplies the Prahran area.

The expected demand for the next five years is less than the stations n-1
rating, thus no customer load is at risk for the outage of a major plant item.

Q Zone Substation, Kew


Station Rating & supply area
Q Zone substation has a summer n-1 rating of 30.7MVA comprised of two
20/30MVA transformers operating at 66/11kV. The Zone Substation supplies
the Kew area.

Although expected demand for the next five years will exceed the stations n-1
rating, there is sufficient load transfer capability via 11kV links to adjacent zone
substations to cover this shortfall. Thus no customer load is at risk for the
outage of a major plant item.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

267

Appendix B

R Zone Substation, Richmond


Station Rating & supply area
Richmond Zone substation has a summer n-1 rating of 31.4MVA comprised of
three 10/14MVA transformers operating at 22/6.6kV. The Zone Substation
supplies the Richmond area.
Following the installation of additional capacity at TK in 2006/07 permanent load
transfers from R to TK at 11kV will be carried out.

Although expected demand for the next five years will exceed the stations n-1
rating, there is sufficient load transfer capability via 11kV links to adjacent zone
substations to cover this shortfall. Thus no customer load is at risk for the
outage of a major plant item.

RD Zone Substation, Riversdale


Station Rating & supply area
Riversdale Zone substation has a summer n-1 rating of 30.6MVA comprised of
two 20/30MVA transformers operating at 66/11kV. The Zone Substation
supplies the Camberwell area.

Although expected demand for the next five years will exceed the stations n-1
rating, there is sufficient load transfer capability via 11kV links to adjacent zone
substations to cover this shortfall. Thus no customer load is at risk for the
outage of a major plant item.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

268

Appendix B

RP Zone Substation, Russell Place


Station Rating & supply area
Russel Place Zone substation has a summer n-1 rating of 18.7MVA comprised
of three 10/13.5MVA transformers operating at 22/6.6kV. The Zone Substation
supplies the Melbourne CBD area.

The expected demand for the next five years is less than the stations n-1
rating, thus no customer load is at risk for the outage of a major plant item.

SK Zone Substation, St Kilda


Station Rating & supply area
St.Kilda Zone substation has a summer n-1 rating of 62.6MVA comprised of
three 20/30MVA transformers operating at 66/11kV. The Zone Substation
supplies the St.Kilda area.

Although expected demand for the next five years will exceed the stations n-1
rating, there is sufficient load transfer capability via 11kV links to adjacent zone
substations and 7.4MVA cogeneration capacity to cover this shortfall. Thus no
customer load is at risk for the outage of a major plant item.

SM Zone Substation, South Melbourne


Station Rating & supply area

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

269

Appendix B

South Melbourne Zone substation has a summer n-1 rating of 26.7MVA


comprised of three 10/13.5MVA transformers operating at 22/11kV. The Zone
Substation supplies the Southbank and South Melbourne areas.
SM will be reconstructed and upgraded to 66kV with 55MVA transformer firm
capacity for completion by 2009/10.

The reconstruction program has been started and all the SM loads will be
temporarily transferred away to facilitate the reconstruction. A significant
amount of SM loads has already been transferred away prior to the 2006/07
summer and the remaining station demand in 2006/07 summer is expected to
be within the existing zone substation n-1 rating.

SO Zone Substation, South Melbourne


Station Rating & supply area
SO Zone substation has a summer n-1 rating of 63.7MVA comprised of three
20/30MVA transformers operating at 66/11kV. The Zone Substation supplies
the Southbank and South Melbourne areas.

In the 2006/2007 summer period the stations n-1 rating will be exceeded by
6.4MVA with 43.5MWh at risk.

SO SUMMER LOAD PROJECTION 2007-2011


Year
2007
2008
2009
Station Load
70.1
71.6
73.2
(MVA)
n-1 Rating
63.7
63.7
63.7
n Rating
93.5
93.5
93.5

2010

2011

74.7

76.3

63.7
93.5

63.7
93.5

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

270

Appendix B

SO ANNUAL ENERGY & HOURS AT RISK

Network solutions to manage load at risk under n-1 conditions


_ Load reduction involving transfer of load via 11kV links to adjacent stations.
_ The reconstruction of SM zone substation, due for completion in 2009/10, will
allow a permanent load transfer from SO.

The load at risk as shown above is before implementation of any network risk
mitigation strategies.

Prior to completion of the SM upgrade, it is expected that the customer load at


risk is manageable by available load transfer capabilities to adjacent stations.
Following completion of the SM upgrade, it is expected that the customer load
at risk will be minimal.

TK Zone Substation, Toorak


Station Rating & supply area

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

271

Appendix B

Toorak Zone substation has a summer n-1 rating of 28.7MVA comprised of two
20/30MVA transformers operating at 66/11kV. The Zone Substation supplies
the Toorak area.

In the 2006/2007 summer period the stations n-1 rating will be exceeded by
10.3MVA with 420.7MWh at risk.

TK SUMMER LOAD PROJECTION 2007-2011


Year
2007
2008
2009
Station Load
39.0
39.7
40.4
(MVA)
n-1 Rating
28.7
54.1
54.1
n Rating
54.1
78.1
78.1

2010

2011

41.1

41.8

54.1
78.1

54.1
78.1

TK ANNUAL ENERGY & HOURS AT RISK

Network solutions to manage load at risk under n-1 conditions


_ Load reduction involving transfer of load via 11kV links to adjacent stations.
_ Installation of a 3rd transformer at TK is in progress and is available as an
emergency spare for the 2006/07 summer. Following full commissioning of the
3rd transformer, the expected demand for the next five years is less than the

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

272

Appendix B

stations n-1 rating, thus no customer load is at risk for the outage of a major
plant item.

Following installation of the 3rd transformer at TK, there will be sufficient


capacity to meet the station demand over next 5 years, and thus no customer
load at risk for outage of a major plant.

TP Zone Substation, Tavistock Place


Station Rating & supply area
Tavistock Place Zone substation has a summer n-1 rating of 11.6MVA
comprised of two 10MVA transformers operating at 22/6.6kV. The Zone
Substation supplies the Melbourne CBD area.
Although expected demand for the next five years will exceed the stations n-1
rating, there is sufficient load transfer capability via 11kV links to adjacent zone
substations to cover this shortfall. Thus no customer load is at risk for the
outage of a major plant item.

VM Zone Substation, Victoria Market


Station Rating & supply area
Victoria Market Zone substation has a summer n-1 rating of 63.2MVA
comprised of three 20/27MVA transformers operating at 66/11kV. The Zone
Substation supplies the Melbourne, North Melbourne and Parkville areas.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

273

Appendix B

In the 2005/2006 summer period the stations n-1 rating will be exceeded by
11.7MVA with 681.0MWh at risk.

VM SUMMER LOAD PROJECTION 2007-2011


Year
2007
2008
2009
Station Load
74.9
79.7
82.5
(MVA)
n-1 Rating
63.2
63.2
63.2
n Rating
94.8
94.8
94.8

2010

2011

85.2

88.1

63.2
94.8

63.2
94.8

VM ANNUAL ENERGY & HOURS AT RISK

Network solutions to manage load at risk under n-1 conditions


_ Load reduction involves transfer of load via 11kV links to adjacent stations.
_ The planned upgrade of BSBQ around 2009/10 will allow load to be
permanently transferred from VM to BSBQ.

The load at risk shown above is before implementation of any network risk
mitigation strategies.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

274

Appendix B

Although the expected demand over the next five years is higher than the
stations n-1 rating, it is expected that the customer load at risk is manageable
by available load transfer capabilities to adjacent stations.

WA Zone Substation, Waratah Place Melbourne


Station Rating & supply area
WA Zone substation has a summer n-1 rating of 67.0MVA comprised of three
20/27MVA transformers operating at 66/11kV. The Zone Substation supplies
the Melbourne CBD area.

In the 2006/2007 summer period the stations n-1 rating will be exceeded by
6.7MVA with 147.8MWh at risk.

WA SUMMER LOAD PROJECTION 2007-2011


Year
2007
2008
2009
Station Load
73.7
75.4
76.7
(MVA)
n-1 Rating
67.0
67.0
67.0
n Rating
103.5
103.5
103.5

2010

2011

78.1

79.5

67.0
103.5

67.0
103.5

WA ANNUAL ENERGY & HOURS AT RISK

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

275

Appendix B

Network solutions to manage load at risk under n-1 conditions


_ Load reduction involves transfer of load via 11kV links to adjacent stations
_ Planned new 11kV links between WA and JA in 2007/08 to increase load
transfer capability.
_ The planned upgrade of BSBQ in 2009/2010 will allow load to be permanently
transferred from WA to BSBQ. Additional new 11kV links will be established for
permanent load transfers.

The load at risk shown above is before implementation of any network risk
mitigation strategies.

Although the expected demand over the next five years is higher than the
stations n-1 rating, it is expected that the customer load at risk is manageable
by available load transfer capabilities to adjacent stations.

WB Zone Substation, West Brunswick


Station Rating & supply area
West Brunswick Zone substation has a summer n-1 rating of 26.4MVA
comprised of two 20/30MVA transformers operating at 66/6.6kV. The Zone
Substation supplies the West Brunswick area.

The expected demand for the next five years is less than the stations n-1
rating, thus no customer load is at risk for the outage of a major plant item.
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

276

Appendix B

WG Zone Substation, Westgate


Station Rating & supply area
WG Zone substation has a summer n-1 rating of 36.1MVA comprised of two
20/27MVA transformers operating at 66/11kV. The Zone Substation supplies
the Port Melbourne and Fishermans Bend areas.

In the 2007/2008 summer period the stations n-1 rating will be exceeded by
14.1MVA with 2,591.6MWh at risk.

WG SUMMER LOAD PROJECTION 2007-2011


Year
2007
2008
2009
Station Load
34.2
50.2
62.5
(MVA)
n-1 Rating
36.1
36.1
36.1
n Rating
72.2
72.2
72.2

2010

2011

52.1

59.6

36.1
72.2

36.1
72.2

WG ANNUAL ENERGY & HOURS AT RISK

Network solutions to manage load at risk under n-1 conditions


_ Load reduction involves transfer of load via 11kV links to adjacent stations.
_ Installation of a 3rd 27MVA 66/11kV transformer at WG is presently in
progress and due for commissioning in the 4th quarter of 2007.
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

277

Appendix B

_ The reconstruction of SM zone substation, due for completion in 2009/10, will


allow a permanent load transfer from WG.

With the above network solutions implemented, zone substation WG will have
sufficient capacity to meet the station demand, and thus no customer load at
risk for outage of a major plant.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

278

Appendix C

Appendix C

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

279

Appendix C

WMTS SUB-TRANSMISSION LINES


Where the expected demand over the next five years is higher than the n-1
rating of the lines, it is expected that the customer load at risk is manageable by
available load transfer capabilities to adjacent loops.

WMTS-DA 22kV SUBTRANSMISSION LINES


Supply points & line loading
The WMTS-DA subtransmission lines supplies Docklands (DA) zone substation
fed from West Melbourne Terminal Station (WMTS) at 22kV.

In the event of an outage of any one of WMTS-DA213 or WMTS-DA222 lines,


the remaining WMTS-DA line will be loaded up to 17.1% in 2006/07 summer
and up to 51% in 2010/11 summer

Network solutions to manage load at risk


_ Use of Co-generation capacity of up to 2 MVA.
_ Load reduction involving transfer of load via 11kV links to adjacent stations.
_ A planned new 11kV link from WG in 2007/08 to increase load transfer
capability.
_ Following installation of a 3rd 27MVA 66/11kV transformer at WG by 2007/08,
new 11kV feeders will be installed from WG to Docklands area for load transfer.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

280

Appendix C

WMTS-J-LS-BSBQ-WMTS 22kV INTERCONNECTED SUBTRANSMISSION


LOOP
Supply points & line loading
The WMTS-J-LS-BSBQ-WMTS interconnected subtransmission lines supply
the J (Spencer Street), Laurens St (LS) and Bouverie St (BSBQ) zone
substations fed from West Melbourne Terminal Station (WMTS) at 22kV.

Network solutions to manage load at risk


_ Use of Co-generation capacity (14.8 MVA) to meet load at risk.
_ Transfer of load via 11kV links to adjacent zone substations.
_ Establish new 66kV connection point at Brunswick Terminal Station (BTS)
and new 66kV feeders from new connection point in around 2009/10 to support
CBD substations (Refer BTS 66kV report in Transmission Connection Planning
Report 2006). Two new 66kV underground cables have been estimated for this
option and will enable the existing 22kV cables to be retired. This proposal to be
in conjunction with the re-development of station BSBQ from 22kV to 66kV.
_ Establishment of additional transfer capacity between LS and adjacent zone
substations by 2008/09.

WMTS-VM-LQ/WA 66kV SUBTRANSMISSION LINES


Supply points & line loading
The WMTS-VM-LQ/WA subtransmission lines supply the Victoria Market (VM),
Little Queen (LQ) and Warratah Place (WA) zone substations fed from West
Melbourne Terminal Station (WMTS) at 66kV.
Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

281

Appendix C

A total of additional 12MVAr capacitor bank capacity has installed at LQ prior


2006/07 summer to improve the subtransmission line under line outage
contingency.

In the event of an outage of any one of the WMTS-VM1-LQ1/WA1, WMTSVM2-LQ2/WA2 or WMTS-VM3-LQ3/WA3 lines, the remaining lines will be
loaded above their n-1 rating up to 4.3% in 2007/08 summer and up to 17.1% in
2010/11 summer.

Network solutions to manage load at risk


_ Load reduction involves transfer of load via 11kV links to adjacent stations
_ The planned upgrade of BSBQ in 2009/2010 will allow load to be permanently
transferred from VM and WA to BSBQ. New 11kV links will be established for
permanent load transfers.

WMTS-JA 66kV SUBTRANSMISSION LINES


Supply points & line loading
The WMTS-JA subtransmission lines supply the Little Bourke (JA) zone
substation fed from West Melbourne Terminal Station (WMTS) at 66kV.

In the event of an outage of any one of the WMTS-JA1 lines, the remaining
WMTS-JA2 line will be loaded above their n-1 rating by 7.7% in 2007/08
summer and by 30.6% in 2010/11 summer.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

282

Appendix C

In the event of an outage of any one of the WMTS-JA2 lines, the remaining
WMTS-JA1 line will be loaded above their n-1 rating by 6.4% in 2009/10
summer and by 12.1% in 2010/11 summer.

Network solutions to manage load at risk


_ Load reduction involving transfer of load via 11kV links to adjacent stations.
_ Installation of 2 x 12MVAr 11kV capacitor banks by 2008/09 to improve
subtransmission line loading under line outage contingency.

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

283

Appendix D

Appendix D

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

284

Appendix D

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

285

Appendix E

Appendix E

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

286

Appendix E

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

287

Appendix E

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

288

Appendix E

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

289

Appendix E

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

290

Appendix E

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

291

Appendix E

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

292

Appendix E

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

293

Appendix F

Appendix F

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

294

Appendix F

CABLE DATA SUPPLIED BY OLEX CABLES


Conductor
Material:
Design:
Diameter:
Conductor screen
Material
Construction
Nominal thickness

Aluminium
Miliken
48.2 mm
Semi-conductive XLPE
Extruded
1.6 mm

Maximum dielectric stress at the conductor screen (assumed smooth) -4.4


kV/mm
Minimum radial thickness of insulation between Conductor screen and
insulation screen. 10.0 mm
Insulation
Material
XLPE
Type of Extruder
VCV
Type of curing process
Dry
Diameter over insulation 72.4 mm
Max
73.4 mm
Minimum
71.4 mm
Insulation screen
Material
Semi-conductive XLPE
Thickness
1.0 mm
Electrical data
Rated voltage
Highest system voltage
Impulse voltage level
Maximum conductor dc-resistance at 20 C
Nominal operating capacitance

Maximum permissible short circuit for 0.5 second


Phase conductor (from 90 C up to 250 C)
Metallic screen (from 80 C up to 250 200 C) (adiabatic)
Metallic screen (from 80 C up to 250 200 C) (non-adiabatic)
Zero sequence impedance at 90 deg C
R0 + jX0 Ohms/km
Positive sequence impedance at 90 deg C
R1 + jX1 Ohms/km
Capacitance Pico Farads / m
Continuous current rating Summer at 20 deg C, soil thermal

66kV
72.5 kV
325
kV
peak
0.0186
m/m
0.39
F/km

215 kA
23.1 kA
25.0 kA
0.457 +
j0.046
0.0245 +
j0.197
390

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

295

Appendix F

receptivity 1.2 k-m/W, single point bonded, 1m deep


Cables @300mm centre direct buried
Cables @300mm centre in 125mm diameter, (Heavy Duty)
HD, UPVC conduit of AS 2053
Continuous current rating Winter at 10 deg C, soil thermal
receptivity 1.2 k-m/W, single point bonded, 1m deep
Cables @300mm centre direct buried
Cables @300mm centre in 125mm diameter, (Heavy Duty)
HD, UPVC conduit of AS 2053

1260 A
1150 A

1350 A
1230 A

The following are the standard 66kV XLPE insulated cables that have been
used in the sub transmission system:
CABLE TYPE 66Kv XLPE
OLEX 1000 sq mm Cu 1/c
OLEX 1200 sq MM Al 1/c
OLEX 1200 sq MM Al 1/c
BICC 1200 sq mm Al 1/c
PIRELLI 16sq mm Al 1/c
OLEX 1600 sq mm Al 1/c

CABLE CONSTRUCTION
LEAD SHEATH/COPPER WIRE
SCREEN/HDPE OUTERSHEATH
LEAD SHEATH/COPPER WIRE
SCREEN/HDPE OUTERSHEATH
LEAD SHEATH/HDPE
OUTERSHEATH
LEAD SHEATH/HDPE
OUTERSHEATH
COPPER WIRE
SCREEN/ALUMINIUM LAMINATED
POLYETHELENE SHEATH
LEAD SHEATH/PVC/HDPE
OUTERSHEATH

For all new installations 1600mm Al 1/core cable is used.

CABLE DESCRIPTION
38/66(72.5) kV, 1/core, 1600mm Aluminium Miliken construction conductor,
Semi conductive XLPE conductor screen, XLPE insulated using the CDCCProcess (Completely Dry Curing and Cooling Process), Semi conductive XLPE
insulation screen, semi conductive water blocking tape, Lead sheath with or
without plain annealed copper wire screen (Equivalent Copper Area of 105mm)
rated for 22.0kA for 0.5 second phase to earth fault level, Termite protected,
Graphite coated, Black polyethylene Outer Sheath, Cable confirming to AS/NZS
1429.2

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

296

Appendix G

Appendix G

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

297

Appendix G

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

298

Appendix H

Appendix H

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

299

Appendix H

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

300

Appendix H

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

301

Appendix H

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

302

Appendix H

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

303

Appendix H

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

304

Appendix H

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

305

Appendix H

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

306

Appendix H

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

307

Appendix H

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

308

Appendix I

Appendix I

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

309

Appendix I

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

310

Appendix I

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

311

Appendix I

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

312

Appendix I

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

313

Appendix I

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

314

Appendix I

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

315

Appendix I

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

316

Appendix I

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

317

Appendix I

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

318

Appendix J

Appendix J

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

319

Appendix J

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

320

Appendix J

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

321

Appendix J

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

322

Appendix J

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

323

Appendix J

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

324

Appendix J

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

325

Appendix J

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

326

Appendix J

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

327

Appendix J

Technical consideration and impact of converting Overhead Power Lines to Underground Power Cables

328

You might also like