Create Multi Counter Maintenance Plan

Manage Physical Assets

Create Multi Counter Maintenance Plan

IP43

This guide explains how to create a multi counter maintenance plan.


In the case of a multiple counter plan, there are no individual packages as there are for performance-based and
time-based maintenance plans. When a cycle is due, all the operations from the assigned task list are
automatically due.
Activities include:

1.

Create a multi counter maintenance plan.


Enter the transaction code IP43 in the SAP Command box. Click

to start the transaction.

OR
Drill down to the transaction through the SAP Menu: Logistics
Plant Maintenance
Preventive
Maintenance
Maintenance Planning
Maintenance Plans
Create
Multiple Counter Plan.
Create Maintenance Plan: Initial

2.

As required, complete/review the following fields:


Field Name
Maint. plan cat.

Description
Enter the maintenance plan category.

In most cases this will be Maintenance order. If notifications


are used as the category these notifications will have to be
processed into Work Orders. If using Maintenance orders as
the category, work orders will be automatically generated.
Example:

3.

Click

Maintenance order

Activity Instruction
Last Modified: 05 May 2010
Business Solution
Create Multi Counter Maintenance Plan_AI

Page 1 of 11
2009 Rio Tinto

Create Multi Counter Maintenance Plan


Manage Physical Assets

Create Maintenance Plan: Multiple cntr plan

Multi counter plans enable the creation of maintenance plans that are triggered by
different cycles. For example, where maintenance needs to be performed either 3
monthly or 150 hourly
4.

As required, complete/review the following fields:


Field Name

Description

Maintenance plan

Enter the Maintenance plan description.


Example:
Primary Service Back Hoe

Cycle

Enter the cycle.


Example:

U..

Enter the unit of measure.


Example:
MON

Maintenance cycle text

Enter the maintenance cycle text.


Example:
3 Monthly

Cycle

Enter another Cycle on the next line.


Example:
150

Enter the Unit of measure.


Example:
H

Maintenance cycle text

Enter the Maintenance cycle text.


Example:
150 Hourly

Counter

Enter the Counter.

The counter in this case would be recording the operating


hours of the unit and is entered against all cycles.
Example:

100140

Activity Instruction
Last Modified: 05 May 2010
Business Solution
Create Multi Counter Maintenance Plan_AI

Page 2 of 11
2009 Rio Tinto

Create Multi Counter Maintenance Plan


Manage Physical Assets

5.

Scroll down to view all maintenance item fields.


Create Maintenance Plan: Multiple cntr plan

6.

Complete the following fields under the

tab:

Field Name

Description

Maintenance Item

Enter the Maintenance Item description.


Example:
Primary Service Back Hoe

Functional loc

Enter the Functional location.


Example:
219047901

7.

Click
to populate the fields under the Planning data area with the defaults from the functional location
that has been selected.

8.

As required, complete/review the following field:


Field Name
Priority

Description
Enter the Priority of the task.
The Priority should be determined by the criticality of the task to be
performed on the scheduled date. If the task must be performed on the date
which is set when the plan call is generated then the priority should be High.
Example:
Medium

MaintActivityType

Enter the Maintenance Activity Type.

For example:
110 Routine Service
140 Component Lubrication
150 - Calibration
Example:

110

Activity Instruction
Last Modified: 05 May 2010
Business Solution
Create Multi Counter Maintenance Plan_AI

Page 3 of 11
2009 Rio Tinto

Create Multi Counter Maintenance Plan


Manage Physical Assets

9.

Double-click the Functional loc. field to display the master data.

10.

Click the

tab to display the Construction type (Assembly).

Display Functional Location: Master data

The Assembly number for the functional location is required to locate the appropriate
task list. Make note of the construction type for the selected functional location.
11.

Click

12.

Click

.
in the Task list area.

Display Task Lists: Task List Selection

Activity Instruction
Last Modified: 05 May 2010
Business Solution
Create Multi Counter Maintenance Plan_AI

Page 4 of 11
2009 Rio Tinto

Create Multi Counter Maintenance Plan


Manage Physical Assets

13.

Complete the following fields:


Field Name
Usage

Description
Enter 01 to limit the selection to primary maintenance task lists only.
Example:

Assembly

01

Enter the assembly code.

The Assembly is the Construction type assigned to the functional


location.
Example:

14.

Click

60028111

Create Maintenance Plan: Multiple cntr plan

15.

Scroll up to view the packages associated with the task list.

Activity Instruction
Last Modified: 05 May 2010
Business Solution
Create Multi Counter Maintenance Plan_AI

Page 5 of 11
2009 Rio Tinto

Create Multi Counter Maintenance Plan


Manage Physical Assets

Create Maintenance Plan: Multiple cntr plan

16.

Click

Create Maintenance Plan: Multiple cntr plan

17.

As required, complete/review the following fields:


Field Name
Sort field

Description
Enter the Sort field.

The sort field is used to manage the deadline monitoring


process which automatically reschedules maintenance plans
and creates maintenance orders (or notifications).
Example:

CAL Weipa Activity Based

Activity Instruction
Last Modified: 05 May 2010
Business Solution
Create Multi Counter Maintenance Plan_AI

Page 6 of 11
2009 Rio Tinto

Create Multi Counter Maintenance Plan


Manage Physical Assets

18.

Click

Create Maintenance Plan: Multiple cntr plan

Multi counter plans accommodate situations where regular maintenance is to be


scheduled at one parameter, cycle and package, or any other parameter with an
and/or relationship. For example, every 6 months or 4000 hours. These parameters
are assigned in the maintenance plan header, and this type of maintenance plan can
have one or more items, so the cycle and package assigned in the header is applied to
all maintenance plan items.
19.

As required, complete/review the following fields:


Field Name
Scheduled Period

Description
Enter the Scheduled Period.

The scheduling period determines the length of time for which


the system creates maintenance calls during initial
maintenance plan scheduling.
Example:

20.

Click

30

Refer to MPA_IP10 Schedule Maintenance Plan for information in relation to the


scheduling of maintenance plans.

Activity Instruction
Last Modified: 05 May 2010
Business Solution
Create Multi Counter Maintenance Plan_AI

Page 7 of 11
2009 Rio Tinto

Create Multi Counter Maintenance Plan


Manage Physical Assets

Start time

21.

Select

22.

Click

.
.

The system displays the message, "Maintenance plan xxxx created."


23.

You have completed this transaction.

Result
You have created a multi counter Maintenance plan, ready for scheduling.