Professional Documents
Culture Documents
in Construction
Time is of Essence
Delays are inevitable on construction projects
Time and Money go hand-in-hand. When projects get delayed,
additional costs are incurred to all the parties .
This makes it imperative to take control of project delays; timely and
effectively.
FIDIC
FIDIC
FIDIC
FIDIC
FIDIC
http://www.ibclegal.com
http://www.ibclegal.com
http://www.ibclegal.com
http://www.ibclegal.com
http://www.ibclegal.com
http://www.ibcl
egal.com
It is recommended that;
http://www.ibcl
egal.com
www.eotprotocol.com
http://www.ibclegal.com
Basic Principles
suggested and recommended by
the SCL Protocol
http://www.ibcl
egal.com
http://www.ibcl
egal.com
RULE NO. 1
If there is an Employers delay, which is beyond the Contractors
control, and if this delay impacts the Completion Date of the Works,
http://www.ibcl
egal.com
RULE NO. 2
For the case of recovery of delay (or prolongation) costs incurred due to
the Employer delays, the Contractor must be able to prove that there has
been no other delay, which is in his own control, and which is equally
(or partly) contributing for delaying the Time for Completion.
http://www.ibcl
egal.com
RULE NO. 3
Where Contractors Delay to Completion
occurs concurrently with Employers Delay
to Completion, the Contractors concurrent
delay should NOT reduce any
Extension of Time (EOT), which is due.
[Result of Rule No. 1 will not change and is irrespective of the result
of Rule No. 2]
http://www.ibcl
egal.com
http://www.ibcl
egal.com
http://www.ibcl
egal.com
1 2 3
Path 1
Weeks
9 10 11 12 13 14 15 16 17 18 19 20 21 22
Contract
Completion Date
Path 2
http://www.ibcl
egal.com
10
Weeks
11 12 13
14
15
16
17
18
19
20
21 22
Contract
Completion Date
Path 2
Excusable Delay
Contract
Completion Date
Path 1 Float = 1.0 Week
Path 2
http://www.ibcl
egal.com
10
Weeks
11 12 13
14
15
16
17
18
19
20
21 22
Contract
Completion Date
Path 2
Excusable Delay
Contract
Completion Date
Float = -0.5 Week
Path 2
http://www.ibcl
egal.com
http://www.ibcl
egal.com
10
Weeks
11 12 13
14
15
16
17
18
19
20
21 22
Contract
Completion Date
Path 2
Path 2
Excusable Delay
Impact on Path 2 = 6.0 Weeks
http://www.ibcl
egal.com
http://www.ibcl
egal.com
10
Weeks
11 12 13
14
15
16
17
18
19
20
21 22
of
Excusable Delay
Contract Completion Date
Contract Start
Date
Path 2
Path 2
http://www.ibclegal.com
http://www.ibclegal.com
10
Weeks
11 12 13
14
15
16
17
18
19
20
21 22
Path 2
Path 2
http://www.ibclegal.com
http://www.ibclegal.com
10
Weeks
11 12 13
14
15
16
17
18
19
20 21 22
Path 2
Path 2 Float = 2.5 Weeks
Path 2
http://www.ibclegal.com
http://www.ibclegal.com
http://www.ibclegal.com
http://www.ibclegal.com
Question 1
Question 2
Question 3
Question 4
(c)
(b)
(a)
(b)
(a)
(b)
(d)
(b)
(c)
(d)
(d)
(c)
(b)
(a)
(d)
(c)
(a)
(b)
(d)
(c)
(c)
(a)
(a)
(b)
http://www.ibclegal.com
Congratulations we
have come to the end of
the Lecture.
You are now a
Qualified and Certified
Delay Claims Analyst
and Expert.
http://www.ibclegal.com
http://www.ibclegal.com
http://www.ibcl
egal.com