Professional Documents
Culture Documents
TABLE OF CONTENTS
Page
Article 1.
Article 2.
Article 3.
Article 4.
Article 5.
Article 6.
Article 7.
Article 8.
Article 9.
Article 10.
Article 11.
Article 12.
Article 13.
Article 14.
Article 15.
Article 16.
Article 17.
Article 18.
Article 19.
Article 20.
Article 21.
Article 22.
Article 23.
Article 24.
Article 25.
Article 26.
Article 27.
Article 28.
Article 29.
Article 30.
Article 31.
Article 32.
Article 33.
Article 34.
Article 35.
Article 36.
Article 37.
Article 38.
Article 39.
Article 40.
Page i
Article 41.
Article 42.
Article 43.
Article 44.
Article 45.
Article 46.
Article 47.
Article 48.
Article 49.
Article 50.
Article 51.
Article 52.
Article 53.
Article 54.
Article 55.
Article 56.
Article 57.
Article 58.
Article 59.
Page ii
In the Contract, the following works and expressions shall have the meanings hereby
assigned to them where the context otherwise requires:
1) Addenda A written amendment or clarification of the Tender Documents issued to
prospective Bidders prior to the date and time indicated in the Instructions to
Bidders for submission of bids.
2) Advanced Payment- The payment given by the Client to the Contractor for the
mobilization and start-up operations.
3) Award The written acceptance of the Bid.
4) Bill of Quantities A list of the specific items of the Work and their corresponding
unit prices, lump sums and provisional sums.
5) Calendar Day A period of twenty-four hours extended from midnight to midnight.
6) Client or the Procuring Entity The Japan International Cooperation Agency
(JICA) Philippine Office.
7) Commencement Date The date when the Contractor is obliged under the Contract
to commence the Work. It may be fixed or determinable from the Contract or stated in
the Notice to Proceed to the Contractor.
8) Construction Equipment or Contractors Equipment All equipment, facilities,
supplies, appliances, materials or things required for the execution and completion of
the Work and which shall not form or are not intended to form part of the Permanent
Works.
9) Construction Plant All appliances or things of whatsoever nature required in or
about the execution, completion or maintenance of the Work or Temporary Work (as
hereinafter defined) but does not include materials or things intended to form or form
part of the Permanent Work.
10) The Engineer or Procuring Entitys Representative The Engineering firm
contracted by JICA for this project.
11) Contract The Contract Agreement and the Contract Documents.
12) Contract Agreements The written agreement between JICA Philippine Office and
the Contractor setting forth the rights and obligations of the parties thereof, including
but not limited to the performance of the works, the furnishing of labor, equipment
and materials, and the basis of payment.
13) Contract Documents The Documents consisting the following:
i. Contract Agreement
ii. Performance Bond
iii. Form of Bid & BOQ of the Successful Bidder
Page 1of 25
iv.
v.
vi.
vii.
viii.
ix.
x.
xi.
xii.
Conditions of Contract
Technical Specifications
Tender Drawings
Construction Methodology
Organizational Chart
Construction, Manpower & Equipment Utilization Schedules
Cash Flow and Payment Schedules
All addenda and questions and replies issued prior to the Tender
All minutes of meetings as agreed between the parties hereto before
execution of the Contract
xiii. Curriculum Vitae of Proposed Project Manager, Civil Engineer, Structural
Engineer, Architect, Project Engineer and Foreman, indicating among others the
projects where the said proposed personnel were involved, and including an
affidavit of commitment that they would be available for the Project
xiv. Instructions to Bidders and such other documents intended to form the
Contract
14) Contract Price The sum stated in the Contract as payable to the Contractor for the
timely execution and completion of the Works.
15) Contract Time The period stipulated in the Contract for completion of the Works
and any authorized extensions of such period. This period includes the passing of the
tests required under the Contract upon completing the execution of the Work.
16) Contractor The successful Bidder.
17) Construction Program A work schedule prepared and submitted by the Contractor
and approved by the Engineer prior to the commencement of the Work. This schedule
shall show the equipment schedule, manpower loading, and the Contractors cash
flow projection taking into account revenue from the Client for the Contractors
completion of certain phases of the work. It shall include estimates of work items,
quantities and costs and a PERT-CPM network of the activities contemplated in
executing the work.
18) Detour A means of access such as temporary road or bridge for the use of the
traveling public to replace the temporary use of the site.
19) Force Majeure An event which the Contractor could not have foreseen or even
though foreseen was inevitable. An event of force majeure is generally beyond the
reasonable control of the Contractor. It is synonymous with Fortuitous Event. It shall
not include (i) ordinary unfavorable weather conditions; and (ii) any other cause the
effects of which could have been avoided with the exercise of reasonable diligence by
the Contractor.
20) IRR-RA 9184 The current Implementing Rules and Regulations of Republic Act
No. 9184: Prescribing Policies, Guidelines, Rules and Regulations for Government
Procurement Reform Act of the Republic of the Philippines applicable to the
Procurement and Contract.
21) Laboratory The field testing laboratory or any other laboratory acceptable to the
Engineer.
22) Notice to Proceed A written notice issued by the Client to the Contractor
requiring the latter to begin the prosecution of the Work not later than a specified or
Page 2of 25
determinable date.
23) Permanent Works All permanent structures and all other project features and
facilities required to be constructed and completed in accordance with the
Contract and which shall be delivered to the Client and which shall remain at the site
after the removal of all Temporary works.
24) Plans, also known as Drawings The approved drawings, profiles, typical crosssections, working drawings and supplemental drawings or exact reproductions thereof
which show the locations, description, dimensions and details of the Work.
25) Site the project component that comprise the six (6) Packages under the QIP of
the Comprehensive Capacity Development Project for the Bangsamoro (CCDP-B).
26) Specifications The Contract Document denominated as Specifications listed
herein including any additions thereto or modifications thereof by the Engineer or
submitted by the Contractor and approved by the Engineer.
27) Subcontractor Any person or company to whom a part of the Works has been
subcontracted by the Contractor with the express approval of the Client.
28) Substantial Completion That state of completion of the Work where the remaining
work consists of punch list items, or where the Client, without canceling or rescinding
the Contract, accepts turnover of the Works as substantially completed or without
formally accepting the turnover of the Work, uses or is able to use fully the Work
according to its intended purpose, unless Article 54.1 applies. The Work is also
substantially completed when it is 95% complete.
29) Successful Bidder The Bidder to which the contract was awarded.
30) Supervisor Resident representative appointed by the JICA CPO. to perform
day-to-day construction supervision.
31) Temporary Works All temporary works of every kind (other than Construction
Equipment) required in or about the execution and completion of the Works and the
remedying of any defects therein.
32) Bid An offer (or proposal, bid, or quotation) to perform the Work under the terms
and conditions specified in the Contract.
33) Tender Documents All documents issued by the Client giving instructions to
prospective Bidders and providing them with information about the site, the project,
the form and contents of a responsive tender, and the Contract (including the Contract
Documents) to be signed by the successful Bidder.
34) Bidder A company or Corporation properly accredited and legally qualified to
submit a tender to perform the Work.
35) Work or Works The permanent Works and temporary Works to be executed by
the Contractor in accordance with the Contract including the furnishing of all labor,
materials, equipment and others incidental, necessary for the complete execution of
the Works, the passing of any test before acceptance by the Client of the Works, and
the carrying out of all duties and obligations of the Contractor imposed by the
Contract.
Page 3of 25
1.3
Singular and Plural Words stated in the singular in the Tender Documents or in the
Contract shall also signify and impart the plural and vice versa, unless a different meaning
is intended.
1.4
Date The period provided in the Contract whether it is stated in days, months or years
shall be reckoned according to the Gregorian Calendar.
1.5
Apply and/or Lay These words or any of them or the phrase containing a
combination of these words whenever used in the Tender Documents or in the Contract,
shall be deemed to include all works to be done and all expenses to be incurred by the
Contractor, all labor, materials, Construction Equipment, Plant, overhead, including taxes
and profits in performing the whole works; or in supplying or delivering to a specified
location or locations designated in the Contract Documents, or required by the nature of the
work, a particular item, article or piece of apparatus, or equipment.
1.6
1.7
The words Notice, Notify, Inform or Information shall mean notice, notification
or information in writing properly directed and delivered to the person or persons to whom
such notice, notification or information shall be given as provided in the Contract.
The Engineer contracted by JICA, will provide general administration of the Contract,
including performance of the functions hereinafter described.
2.2
The Engineer, personified by the Team Leader will be the Clients representative during
construction and until final payment. The Engineer will have authority to act on behalf of
the Client to the extent provided in the Agreement between the Client and the Contractor,
and as enumerated in Article 2.4 hereof, unless otherwise modified by written instrument
which will be shown to the Contractor. The Engineer will advise and consult with the
Client and all of the Clients instruction to the Contractor shall be issued through the
Engineer.
2.3
The Engineer or his representatives will attend actual field work at the sites. The engineers
representatives will be authorized by the Engineer to work in the field on behalf of the
Engineer.
2.4
The Engineer or his representatives shall act on behalf of the Client as follows:
a) Review and approval of Work Plan, shop drawings, samples and other
submissions of the Contractor.
b) Attend tests and inspections of the Equipment under this Contract.
Page 4of 25
Notices in respect to the Work between the parties shall be referred to the Engineer
provided always as follows:
a) If the Contractor shall be dissatisfied by reason of any decision of the Supervisor, he
shall be entitled to refer the matter to the Engineer or his representatives who shall
thereupon confirm, reverse or vary such decisions.
ARTICLE 3. SUPERVISOR
3.1
The Supervisor who is the staff nominated by the JICA - CPO will watch and supervise
day-to-day activities of the contractor with respect to the general progress and quality of
work and to test and examine any materials to be used or workmanship employed in
connection with the Work. It shall have no authority to relieve the Contractor from any of
its duties or obligations under the Contract or to order any work involving delay.
3.2
The Supervisor will assist to and cooperate with the Engineer or his representatives the
implementation of construction supervision work by the Engineer or his representatives as
described in Article 2.2, 2.3 and 2.4.
3.3
The Supervisor shall assist the Contractor to secure the necessary Building Permit, Sanitary
Permit, Electrical Permit, Excavation Permit and other permits deemed necessary. The cost
in securing all necessary permits for the project shall be borne by the Contractor. The
Supervisor shall also assist the Contractor in coordinating with local electric cooperatives
for installation of electrical equipment and facilities.
ARTICLE 4. SUBLETTING
4.1
The Contractor shall not sublet the whole of the Work. Except where otherwise provided by
the Contract, the Contractor shall not sublet any part of the Work without the prior written
consent of the Engineer and the Client. However, such consent, if given, shall not relieve
the Contractor from any liability or obligation under the Contract and he shall be
responsible for the acts, defaults or neglects of the Sub-Contractor, supplier, its agents,
officials or workmen. However, the provision of labor on a piecework basis shall not be
deemed to be a subletting under this Clause.
The Drawings shall remain in the sole custody of the Engineer or his representatives but
two copies thereof shall be furnished to the Contractor free of cost. The Contractor shall
provide and make at its own expense any further copies required by him. At the completion
of the Contract the Contractor shall return to the Engineer or his representatives all
drawings provided under the Contract.
5.2
The Contractor shall give adequate notice in writing to the Engineer of any further drawing
or specification that may be required for the execution of the Work under the Contract.
Page 5of 25
5.3
One copy of the Drawings furnished to the Contractor as aforesaid shall be kept by the
Contractor on the Site and the same shall at all reasonable times be available for inspection
and use by the Engineer and Supervisor.
The Engineer shall have full authority to supply the Contractor from time to time during the
progress of the Work such further drawings and instructions as shall be necessary forthe
purpose of the proper and adequate execution and maintenance of the Work and the
Contractor shall carry out and be bound by the same.
ARTICLE 7.
7.1
The Drawings attached to the Tender Documents which subsequently become the Contract
Drawings are for proposal preparation purposes only. Provided that after the Contract
Agreement is concluded, the Contractor may use the Contract Drawings as the basis for
placing preliminary orders for materials and for preparing the working drawings. The
Contract Drawings shall not be used directly as basis for fabrication and/or construction
works.
7.2
The Contractor shall check the Contract Drawings carefully and advise the Engineer or his
representatives in writing of all discrepancies, errors or omissions, if any. Instructions from
the Engineer or his representatives will be furnished to the Contractor should any
discrepancy, error, and omission be found. The Contractor shall be required to perform the
Works in accordance with the further issues of the Drawings.
7.3
Although the Drawings are prepared to scale, work shall be based upon dimensions
indicated on the Drawings and not on dimensions scaled from the Drawings.
All the various types of drawings prepared by the Contractor shall be made in a form
approved by the Engineer or his representatives and shall be submitted in advance to give
the Engineer or his representatives sufficient time to review without causing any delay to
the field works. These drawings shall include but are not limited to the following types;
however, it should be noted that the names given to the drawings are only to provide a
general description and can be changed as the Engineer or his representatives or the Client
deems necessary.
1) Working Drawings
As mentioned in Sub-clause ARTICLE 7 above, the Contractor will use the Contract
Drawings as the basis for preparing the working drawings. Working drawings will be
made for all items of permanent works and where applicable will show, amongst others,
concrete outlines, bending, cutting schedules and layout of reinforcing steel bars, types
of material to be used, grades, stations, exact dimensions and any other details which
may be required. All working drawings shall be reviewed and duly approved by the
Engineer or his representatives prior to the execution of the works.
Page 6of 25
2) Shop Drawings
Shop drawings will be prepared by the Contractor or by the Contractors
materials/equipment supplier on behalf of the Contractor to show the outline,
dimensions, type of material, and all other necessary data and information. Shop
drawings shall be submitted to the Engineer or his representatives for his review and
subsequent approval by the Client.
3) Layout Drawings for Temporary Works
Within two (2) weeks calculated from the date of the signing of the Contract, the
Contactor shall submit to the Engineer or his representatives for review and comments
three (3) sets of drawings that show the layout of the Temporary Works. These drawings
shall show the location and other pertinent details of the principal components of the
construction plant, offices, storage buildings, housing facilities, storage area, etc.,which
the Contractor proposes to construct at the site or other authorized areas. In addition,
the drawings shall show the unloading facilities for the site materials and equipment
which the Contractor proposes to bring to the site, and the capacity of each major plant.
ARTICLE 9. AS-BUILT DRAWINGS
9.1
Within thirty (30) calendar days after the receipt of the Certificate of Completion, the
Contractor shall furnish to both the Client and the JICA -CPO one set each of all approved
drawings and documents which have been clearly revised and brought up to date to show
the permanent construction actually made in such a manner that the set of drawings and
documents shall be of high quality reproducible polyester transparent Mylar film (or
similar material) from which clear copies can be made; whereas, the set of drawings for the
Engineer or his representatives shall be reduced into A3. Also, two bound sets each of AsBuilt approved blueprinted drawings shall be submitted to both the Engineer and JICA
CPO.
10.1 The Contractor shall submit to the Engineer or his representatives for approval three (3)
sets of applicable catalogs, pamphlets, manufacturers specifications, diagrams, calculation
sheet, drawings, or other descriptive data for all materials and equipment to be furnished
under the Contract and those which the Contractor proposes to use, within seven (7)
calendar days after the signing of the Contract. The approval by the Engineer or his
representatives of such descriptive data shall not relieve the Contractor of any of his
responsibilities under the Contract.
ARTICLE 11. TEST PROCEDURE INSTRUCTIONS
11.1 The Contractor shall submit to the Engineer or his representatives for approval, during or
immediately following the submission of drawings, tests procedure instructions describing
tests that may be required during manufacture and/or tests which have to be performed on
completion.
Page 7of 25
11.2 Such instructions shall define the sequence of tests, equipment preparation, operation
procedures to be followed and the detailed procedures for conducting the tests. Further
details mentioned in the Technical Specifications which pertain to test procedure
instructions and types of tests to be performed shall be followed.
ARTICLE 12. INSTRUCTION MANUALS FOR OPERATION AND MAINTENANCE
12.1 The Contractor shall provide the Engineer or his representatives, and Supervisor an
Operation and Maintenance Manual which should include easily readable diagrammatic
drawings of the structures and equipment upon completion of the Work. The Contractor
shall, in preparing the instruction manuals, take into account the lack of experience and
non-familiarity of the operation and maintenance personnel on the type of equipment.
12.2 In this regard, the Engineer shall fully cooperate with and assist the Contractor in
establishing an operation and maintenance (O&M) program.
ARTICLE 13. SUBMISSION AND REVIEW OR APPROVAL OF CONTRACTOR
13.1 The Contractor shall, except as specifically noted elsewhere in the Contract or directed by
the Engineer or his representatives, submit his drawings and documents to the Engineer or
his representatives for his review and subsequent approval, at least seven (7) calendar days
prior to the execution of the work concerned in the said drawings and documents.
13.2 The Engineer or his representatives shall reserve the right to make general changes to the
procedure during the course of the works when he deems the changes to be necessary.
13.3 No concrete or permanent work shall be executed until the applicable drawings and
documents have been approved by the Engineer or his representatives. Prior to execution, a
joint inspection shall be undertaken by the Engineer or his representatives and the
Contractor, or their respective authorized representatives, to ensure that the approved
drawing(s) and documents and the appropriate specifications have been fully complied
with. All discrepancies or deficiencies that may be discovered shall be corrected before
execution.
13.4 All works done prior to the Engineers or his representatives approval of applicable
drawings and/or documents shall be at the Contractors risk.
13.5 Approval by the Engineer or his representatives, on the Contractors drawings and/or
documents shall not relieve the Contractor of his obligations such as the responsibility for
complying with all the requirements of the specifications, the correctness of his drawings
and documents, for adequacy, of the method of construction and others.
ARTICLE 14. DOUBTS
14.1 The Contractor shall promptly notify the Engineer or his representatives in any of the
following cases:
a) If the Contractor discovers any indication in the Drawings or Specification which is not
clear and definite, any discrepancy between the Drawings and Specifications, or any
error or omission in the Drawings or Specifications;
Page 8of 25
b) If the Contractor deems it inappropriate to execute the Work in accordance with the
Drawings, Specifications or instructions of the Engineer or his representatives;
c) If the Contractor discovers any difference between the conditions of execution
indicated in the Contract and the actual circumstances;
d) If any unforeseeable condition is found at the Site of the Work, which gives
construction an obstacle to the execution of the Work.
14.2 Upon receipt of the notification mentioned in the preceding paragraph 14.1, or upon
discovery by himself of the facts enumerated in any of the items of the preceding paragraph
14.1, the Engineer or his representatives shall promptly give instructions appropriate to the
Contractor.
ARTICLE 15. INSPECTION OF SITE
15.1 The Contractor shall be deemed to have relied upon its own examination of the Site and to
have informed himself fully and its own expense as to all data, matters and things, local or
otherwise, requisite to the fulfillment of the Contract.
15.2 Failure to acquaint himself fully with all available information concerning conditions
affecting the Work will not relieve the Contractor of its responsibility for estimating the
difficulties and costs of satisfactory performing the Work.
ARTICLE 16. WORK TO THE SATISFACTION OF THE ENGINEER
16.1 Save in so far as it is legally or physically impossible, the Contractor shall execute,
complete and maintain the Work in strict accordance with the Contract to the satisfaction of
the Engineer and shall comply with and adhere strictly to the directions made by the
Engineer or his representatives.
ARTICLE 17. PROGRAM TO BE FURNISHED
17.1 The Contractor shall submit to the Engineer or his representatives, for his approval a
detailed construction schedule and a program within seven (7) calendar days after signing
of the Contract showing the order of procedure and method in which he proposes to carry
out the Work. Whenever required by the Engineer or his representatives, the Contractor
shall furnish for its information particulars in writing of the Contractors arrangements for
carrying out the Work and of the Construction Plant and Temporary Work which the
Contractor intends to supply, use or construct as the case may be.
17.2 The submission to and approval by the Engineer or his representatives of such program or
the furnishing of such particulars shall not relieve the Contractor of any of its duties or
responsibilities under the Contract.
Page 9of 25
Page 10of 25
j)
A statement detailing the status of progress on the overall project and how to regain any
lost time or setbacks, which may have occurred.
k) A general description of the weather, maximum and minimum temperatures for each
day throughout the month.
l)
Page 11of 25
Page 12of 25
Page 13of 25
27.3 If, at any time during the progress of the Work, any error shall appear or arise in the
position, levels, dimensions or alignment of any part of the Work, the Contractor, on being
required to do so by the Engineer, shall rectify such error to the satisfaction of the Engineer
or his representatives.
27.4 The checking of any setting-out or of any line or level by the Engineer or his
representatives shall not in any way relieve the Contractor of its responsibility for the
correctness thereof and bench- marks, site-rails, pegs and other things used in setting out
the Work.
ARTICLE 28. PREVENTION OF DAMAGE
28.1 The Contractor shall, at his own expense, take necessary measures appropriate to the Work
and its surroundings, in accordance with the Contract Documents and relevant laws,
ordinances and regulations, in order to prevent damage to the Work, construction materials,
adjacent structures or a third party, until the final completion and delivery of the Work.
28.2 The Contractor shall, whenever he considers it especially necessary to do so for the
prevention of accidents, take appropriate measures, asking in advance for the opinion of the
Engineer; provided, however, that in case of urgency, the Contractor shall, after taking such
measures, notify the Engineer or his representatives, thereof.
28.3 Whenever the Engineer or his representatives consider it necessary to take measures
appropriate for the prevention of accidents and has requested the Contractor to do so, the
Contractor shall promptly comply therewith.
ARTICLE 29. DAMAGE TO THIRD PARTY
29.1 If, during the execution of the Work, any injury or loss of life has been caused to a third
party, or if any damage has been caused to its property, or if any other dispute has arisen
with the third party, the Contractor shall be fully responsible to compensate the third party
for such loss and damage.
29.2 The Contractor shall take out and maintain insurance against any loss and damage on the
third party under the name of the Contractor.
ARTICLE 30. GENERAL DAMAGE
30.1 If any damage for which the Contractor is responsible has been caused to any part of the
Work, or approved construction materials or equipment for the execution of the Work,
before the delivery of the Work, the Contractor shall make the necessary corrective measure
of such damage.
30.2 The Engineer shall be liable for those arising from any of the following cases, and the
Contractor shall be entitled to an extension of time for Completion of the Work.
a) When the Contractor has been unable to commence the Work by the date of
commencement due to the Clients convenience, or when the Client/ the Engineer has
postponed or suspended the Work, or
Page 14of 25
b) When such damages have been caused by any person for whom the Client or Engineer
is responsible.
ARTICLE 31. DAMAGES CAUSED BY FORCE MAJEURE
31.1 If any damage has been caused to any work done or to approved construction materials or
equipment for the Work due to Force Majeure such as war, epidemic quarantine restriction,
earthquake, flood, fire, strike, insurrection and any other natural disaster or unusual event
or any other cause beyond the control of the parties, the Contractor shall notify the
Engineer and the Client promptly after such occurrence.
ARTICLE 32. INSURANCE OF THE WORK
32.1 During the execution of the Work, the Contractor shall take out and maintain insurance
against any loss or damage, other than the damages caused by Force Majeure stipulatedin
the preceding ARTICLE 31, on the Work and the Construction materials and
equipment for the Work as follows:
1) The Work for the time being executed at its estimated current contract value thereof,
together with the materials for incorporation in the Work at their replacement value.
2) The construction materials and equipment for the Work brought to the Site by the
Contractor at the replacement value of such construction materials and equipment.
32.2 The Contractor shall, whenever required, submit to the Engineer the policy or policies of
insurance and the receipts for payment of the current premiums.
ARTICLE 33. FOSSILS, ETC.
33.1 All fossils, coins, articles of value or antiques and structures and other remains or things of
geological or archaeological interest discovered on the site of the Work shall be deemed to
be the absolute property of the Client. The Contractor shall take reasonable precautions to
prevent its workman or any other persons from removing or damaging any such article or
thing and shall immediately upon discovery thereof and before removal acquaint the
Engineer of such discovery and carry out the Engineers orders as to the disposal of the
same.
ARTICLE 34. PATENTS, RIGHTS AND ROYALTIES
34.1 The Contractor shall save harmless and indemnify the Client from and against all claims
and proceedings for or on account of infringement of any patents, rights, design, trademark
or name or other protected rights in respect of any Construction Plant, machine, work or
material used for or in connection with the Work or Temporary Work or any of them and
from and against all claims, demands, proceedings, damages, costs, charges and expenses
whatsoever in respect thereof or in relation thereto.
34.2 Except where otherwise specified the Contractor shall pay all tonnage and other royalties,
rent and other payments or compensation for extracting stone, sand, gravel, clay or other
materials required for the Work or Temporary Work or any of them.
Page 15of 25
Page 16of 25
Page 17of 25
Page 18of 25
44.4 In the event of any boundary or survey marks being disturbed or displaced as a result of the
Contractors operations, the Contractor shall forthwith, at his own expense, replace the
survey marks. The Contractor shall employ the services of a qualified surveyor for this
purpose if the boundary or survey beacon disturbed or displaced was established for the
purpose of land title deeds.
ARTICLE 45. PRECAUTIONS FOR SAFETY
45.1 The Contractor shall take all necessary precautions against risks of loss of life or of injury
to any person employed on the Works, or to employees of the Engineer and of the
Supervisor or of others, or to visitors or persons having good and sufficient reasons to be
around the Works. To this end, the Contractor shall provide safeguards in the Works to the
satisfaction of the Engineer and the Supervisor. The Contractor shall, furthermore, take all
necessary precautions against damage to the property of the Supervisor or of others located
at or adjacent to the Site.
45.2 The Contractor shall at all times comply with all accident prevention regulations and all
safety regulations peculiar to the various trades employed on the Works.
45.3 The Implementing Rules and Regulation provisions on performance security shall form
part of these General Conditions, but in case of conflict between these General Conditions
on performance security and the IRR-RA 9184 provisions on the same project, the IRR-RA
9184 shall prevail.
45.4 The Contractor shall report promptly to the Engineer and/or Supervisor all accidents
involving the death of or serious injury to any persons, on the Site or resulting from the
Contractors operations.
45.5 The Contractor shall provide all necessary signs for the Works. These shall include but not
be limited to the following:
a)
b)
c)
d)
e)
f)
45.6 Wording on all signs shall be in English and Filipino languages. The size, color, lettering
and location of all signs shall be subject to approval of the Engineer and the Supervisor and
special attention shall be paid to the international system of signs.
45.7 The Contractor shall maintain all signs so placed as well as those placed by the Supervisor.
The Contractor shall pay particular attention to the traffic control on public roads where his
equipment or vehicle frequently passes. In addition to road signs, he shall post flagmen at
critical places on such roads to maintain the smooth flow of traffic.
Page 19of 25
45.8 The Contractor shall, within twenty-four (24) hours of the occurrence of any accident at or
about the Site or in connection with the execution of the Works, reports such accident to the
Engineer. The Contractor shall also report such accident to the appropriate authorities when
it is required by law. The Contractor shall be required to furnish monthly reports of all
accidents to staff, workmen, equipment or plant involving loss of time, giving such
information as may be prescribed by the Engineer and the Supervisor.
45.9 Safety instructions shall deal with all safety measures including but not limited to the
following:
a)
b)
c)
d)
e)
f)
g)
Page 20of 25
riotous or disorderly conduct by or amongst its employees and for the preservation of peace
and protection of persons and property in the neighborhood of the Work against the same.
ARTICLE 47. DAILY REPORT OF LABOR, ETC.
47.1 The Contractor shall, if required by the Engineer, deliver to the Engineer or at its office a
daily report in such form and at such intervals as the Engineer may prescribe showing the
supervisory staff and the numbers of the several classes of labor from time to time
employed by the Contractor on the Site and such information with respect to Construction
Plant.
ARTICLE 48. ACCESS TO SITE
48.1 The Engineer and the Supervisor or any person authorized by them shall at all times have
access to the Work and to the Site and to all workshops and places where work is being
prepared or whence materials, manufactured articles or machinery are being obtained for
the Work and the Contractor shall afford every facility for and every assistance in obtaining
the right to such access.
ARTICLE 49. WORKS NOT IN COMPLIANCE WITH THE CONTRACT
49.1 Any part of the Work found to be in noncompliance with the Contract shall be
reconstructed by the Contractor in accordance with the instruction of the Engineer.
ARTICLE 50. SUSPENSION OF WORK
50.1 The Contractor shall, on the written order of the Engineer, suspend the progress of the
Work or any part thereof for such time or times and in such manner as the Engineer may
consider necessary and shall during such suspension properly protect and secure the Work
so far as is necessary in the opinion of the Engineer.
50.2 On the written order of the Engineer, the progress of the Work or any part thereof shall be
suspended for a period or consecutive periods amounting in all to sixty (60) days. Or the
Engineer having previously issued a Suspension Order for a period which has lasted less
than sixty (60) days shall, within less than sixty (60) days from the expiration of that period
of suspension, issue a further Suspension Order either in respect of the whole of the Work
or (where the previous Suspension Order has affected only a part) affecting or include that
part then. And in any such case the Contractor may serve a written notice to the Engineer
requiring permission within twenty-eight (28) days from the receipt thereof to proceed with
the work or that part thereof in regard to which progress is suspended. And if such
permission is not granted within that time, the Contractor by a further written notice so
served may (but is not bound to) elect to treat the suspension where it affects part only of
the Work as an omission of such part under Article of Alteration, Addition and Omission
hereof or where it affects the whole work as an abandonment of the Contract by the Client.
Page 21of 25
Page 22of 25
Page 23of 25
Page 24of 25
Page 25of 25