Installation Quality

Introduction
 Quality check is an activity which needs to be conducted after site
installation is completed.
 Quality Check is done to verify that the installed site meets the
installation guidelines or not.

2013 Samsung Electronics

Table Of Contents
Installation Quality Check List
 RF Antenna
 RRU - Remote Radio Unit
 GPS Antenna
 CDU - Cabinet Digital Unit
 Other Important Quality Checks

2013 Samsung Electronics

1) Antenna Fixing-RF Antenna


 Check for proper antenna bolt tightening.
Tightening of the bolts should be properly done i.e. bolts should not be loose and should not be
over tightened. If the bolts are over tightened, threads may get damaged. Correct torque value is
(239.7-270.3 kgf.cm.)
 Antenna should not move when pushed with force.
Antenna should withstand strong air turbulence and should not move even when pushed with
force. This is to ensure Antennas remain oriented in the desired direction all the time
Attaching Base station Antenna on Poles Using
Clamps

40-90 mm

14 mm

* Torque : 239.7 ~ 270.3 kgf.cm


(23.5~26.5 Nm)

2013 Samsung Electronics

2) Antenna Position- RF Antenna


 In case the height of structure is more than 30M from the ground, lightning-protection
umbrella angle should be 23 degrees.
 In case the height of structure is Less than 30M from the ground, lightning-protection
umbrella angle should be 45degrees.
[Less than 30M ]

[More than 30M ]


Lightning Rod

45

45

23

23

.
GPS Antenna

RRU

2013 Samsung Electronics

GPS Antenna

RF Antenna

RRU

RF Antenna

3) Antenna Azimuth / Tilt


 Ensure according to TSSR data
 Get the values of the Antenna Azimuth for Alpha, Beta and Gamma Sector and Antenna
tilts from the TSSR Document and verify the calculated values with the values mentioned
in the TSSR document. The values should match.

Mechanical down tilt (In the case of tilting)

14 mm
* Torque : 239.7 ~ 270.3 kgf.cm
(23.5~26.5 Nm)

Azimuth Measurement-Compass
Tilt Measurement: Tilt Meter
2013 Samsung Electronics

4) Cable Routing Condition (Jumper & RET) 1/2


 Min. bending radius should be 125 mm

RF Antenna

RET Cable Assembly

Min. radius
of curvature

Straight cable section

RET Connector

RF cable type

Min. Radius

Manufacturer

1/2

125 mm

LS

Connect a 1/2 in. Jumper line to the RF antenna.


- If excessive force is applied to the connector assembled to the antenna port or cable, it
may cause poor contact or damage because the straight cable section is not long enough.
2013 Samsung Electronics

4) Cable Routing Condition (Jumper & RET) 2/2


 First cable tie should be used at 600 mm from antenna port then after at every 300 mm

2013 Samsung Electronics

5) Cable Labeling
 Labeling should be done according to guideline (Alpha-Blue,Beta-Red,Gamma-Green)
Alpha Sector

Sector
Alpha

Beta

Gamma

2013 Samsung Electronics

Beta Sector

Gamma Sector

RF Cable

Color Code

Path#0
Path#1
Path#2
Path#3
Path#0
Path#1
Path#2
Path#3
Path#0
Path#1
Path#2
Path#3

Blue / Yellow(One String)


Blue / Yellow(Two String)
Blue / Yellow(Three String)
Blue / Yellow(Four String)
Red / Yellow(One String)
Red / Yellow(Two String)
Red / Yellow(Three String)
Red / Yellow(Four String)
Green / Yellow(One String)
Green / Yellow(Two String)
Green / Yellow(Three String)
Green / Yellow(Four String)
9

6) Feeder weather proofing


Check Point
 Antenna cables are finished with insulation tape and with 2 ties, no shrinkage tube or
tape missing


Check distance between RRU bottom & the lower cable tie with steel ruler. It should

be minimum 80mm

2013 Samsung Electronics

10

7) AISG(RET) Cable Connection & Daisy Chain port (1/2)


 AISG cable connector should be tighten to RET male port.
 RET daisy chain port should be tighten with weather proof cap to avoid water seepage.

Antenna side

RRH side

2013 Samsung Electronics

11

7) AISG(RET) Cable Connection & Daisy Chain port (2/2)

 If found a Gap, turn the cap clockwise tightly with finger and mark up the permanent marker .

2013 Samsung Electronics

12

Quality Check List for RRU

13

1) RRU Bracket Fixing (1/2)


 Check tightening status of nuts and bolts
 Check horizontal and vertical leveling

Pole Mount Bracket


Assembly (Universal Bracket)
[

Unit Mounting Bracket Assembly


* M8 Hex. Bolt/Nut Torque : 122 kgf.cm (Tolerance 10%)
* M12 Hex. Bolt/Nut Torque : 390~400 kgf.cm

Use Spirit Level to check the leveling of the


RRU

2013 Samsung Electronics

14

1) RRU Bracket Fixing (2/2)


 CHECK POINT
#1 4Bolts on the right and left of RRU shall be securely fastened up
#2 If found loose screws fasten them again.
#3 Make sure that all screws shall be securely fastened up and mark all screws with permanent marker

2013 Samsung Electronics

15

2) Bolt, Nut, Washer, Bushing, Bakelite status


 Check all fixing assembly item should be in place according to installation guideline without
missing or damage

Bakelite(5T)
M830L Hex. Bolt

Unit Mounting
Bracket Upper furrow

Unit Mounting Bracket

Bakelite(5T)
M8 Insulation Bushing
M8 Plain Washer
M8 Spring Washer
M8 x 30L Hex. Bolt

2013 Samsung Electronics

16

3) RRU insulation test


 Check continuity with Multimeter bet
ween Pole and RRH body(Resistance
Value <500V/100M Ohm)

[Strong Anchor fixing Hex. Bolt]

[RRU fixing Hex. Bolt]

 Bakelite and insulation bushing should


be in place
 Perform this test only after disconnect
the Grounding Cable

[Stud Bolt]

[RRU fixing Hex. Bolt]

[U[U-Bolt]

[RRU fixing Hex. Bolt]

2013 Samsung Electronics

Indication standard : more than 500V/100M

17

4) Cable Status
 CPRI, Power, RET cable should be terminated on desired port with correct polarity
 Check all cable for any damage and sharp bend.
 Check the routing of all the cables is done properly.

Power cable cover should be


projected 10mm from floor of
window inside

10mm
Power Gland Nut

2013 Samsung Electronics

18

6) RRU Grounding
 Grounding should be done using F-GV 6.0 x 1C cable, 2Hole Terminal.
 Check cable for any damage and sharp bend.
 Check the routing of the cable is done properly.
 Check whether grounding cable lugs are covered with the green heat shrink tube.
SEMS(M6x12L, 2EA)

RRU
Ground
Cable

Green heat shrink


tube

CPRI for
Pressure Terminal
RRU for
Pressure Terminal

Cable Tie
CPRI Ground Cable
RRU Ground Cable
[R[R-03] ~ [R[R-11] Connection of

Ground Cable

* M6 SEMS Torque : 33.28~49.92 kgf.cm


2013 Samsung Electronics

19

7) RRU Input Power Check


 Measure the voltage at both the terminals.
 Recommended voltage should range from -40 to -57 V DC.
 Voltage drop should not be more than 1 Volt.
 Check whether the caps are fixed on the power tapping after power connection is done inside RRU
 Cross check the color coding of Power cable: Black (RTN) & White (-48 VDC)
 Check the Heat shrink tube color should be RED( RTN) & BLUE ( -48 VDC)

2013 Samsung Electronics

20

8) RRU Window tightening Status


CHECK POINT
#1 4screws shall be securely fastened with 12kgf-cm torque
#2 Check site ID at the bottom of window face and take a picture of it
#3 Make sure that all screws shall be securely fastened up & mark all the screw with
permanent marker

2013 Samsung Electronics

21

9) Cable Labeling(CPRI,Power, Grounding ,RET Cable & Jumper Cable)


 Check all the labeling done as per installation guideline

25
TMC

25
TMC

30
TMC

The new format of


labels

2013 Samsung Electronics

22

10) Cable Gland tightening Status-Optic Cable gland (1/2)


CHECK POINT :
#1 Filler and CAP must be included in Gland
#2 GAP check as shown in figure

2013 Samsung Electronics

23

10) Cable Gland tightening Status-Power Cable gland (2/2)


CHECK POINT :
#1 Filler and CAP must be included in Gland
#2 Gap check
#3 The length of straight power cable and the positions of tied up to Pole as shown in figure

2013 Samsung Electronics

24

Quality Check List for GPS

25

1) GPS Pole Fixing and GPS Arrestor (1/2)


CHECK POINT
#1 GPS antenna should be within 23/45angle of lightning protection umbrella.
[Less than 30M ]

[More than 30M ]


Lightning Rod

45

45

23

GPS Antenna

RRU

2013 Samsung Electronics

23

GPS Antenna

RF Antenna

RRU

RF Antenna

26

1) GPS Pole Fixing and GPS Arrestor (2/2)


CHECK POINT
#2 Ground cable shall be securely connected to CDU
#3 There shall be no missing part
#4 Need to check all the labeling as per guideline
* items required:
Nut and 6sq.mm pressure terminal
tooth washer,
[MGB]
[D[D-25] GPS

Antenna

[D[D-11] ~ [D19]

Connection of GPS Ground Cable

[D[D-30] RG-316D Cable-1

[D[D-27] GPS

2013 Samsung Electronics

Cable(CNT-400)

[D[D-28] GPS

Arrestor

27

2) GPS Connectorization
CHECK POINT
#1 Check both connector should be made as guideline
#2 Crimp ring should crimp with hexagonal crimping tool two times

2013 Samsung Electronics

28

Quality Check List for CDU

29

1) CDU System Fixing- Horizontally installed (1/2)


CHECK POINTS:
#1 FAN MODULE shall be on the left front
#2 The color of Optic cable boots shall be RED and BLUE from the left to right
#3 All dust plug shall be kept securely.
#4 All screws shall be securely fastened

2013 Samsung Electronics

30

1) CDU System Fixing- Vertically installed (2/2)


CHECK POINTS:
#1 FAN MODULE shall be on the top front
#2 The color of Optic cable boots shall be RED and BLUE from the top to bottom
#3 All dust plugs shall be kept securely.
#4 All screws shall be securely fastened

2013 Samsung Electronics

31

2) CDU (Dummy Panel & Unused Port) Condition


CHECK POINT:
#1.Check unused port covered with cap
#2.Check unused slots covered with dummy panel

Dummy Panels
Unused Ports

2013 Samsung Electronics

32

3) CDU Grounding
CHECK POINTS :
#1 Ground cable shall be securely fastened on the back of CDU
#2 Grounding should be done using F-GV 4.0 x 1C cable, 2Hole Terminal.
#3 Check cable for any damage and sharp bend.
#4 Check the routing of the cable is done properly.
#5Check whether grounding cable lugs are covered with the green heat shrink tube.

2013 Samsung Electronics

33

4) Cable status
Power cable connector and ground cable inspection
CHECK POINT
#1 Power connector shall be securely connected to receptacle
#2 Ground cable shall be securely fastened
#3 Check all cable for any damage and sharp bend.
#4Check the routing of all the cables is done properly.

2013 Samsung Electronics

34

5) SFP module
 Check SFP module Single mode (Color Blue)
If Black multi-mode SFP is found, please return it to Samsung contact person after
replacing it with Blue single-mode SFP

Connecting to backhaul cable (Optic)


Connect the backhaul cable (opticsingle mode) from the
switch/router to BH2 and BH3 ports
of the CDU UAMA board.
General Case : Optic single cable
Connect the CDU-side connectors
(LC/UPC) of the cable to the BH2
and BH3 ports of the CDU UAMA
board.

2013 Samsung Electronics

35

Other Important Quality Checks

36

1) Roxtec
 Check all cable entries in roxtec as per guideline
 Boots should be fixed properly without any gap

2013 Samsung Electronics

37

2) ODC Rack internal state


 All cable should be properly laced
 Ensure the cleanliness inside the ODC

2013 Samsung Electronics

38

3)MCB
 Mention the MCB rating
 Ensure the labeling
 MCB screw should be tighten on the copper not on insulation cover
 Cross check the color coding of Power cable: +VE Black & -VE is White

CDU RRU-0

2013 Samsung Electronics

RRU-1 RRU-2

39

4)Cable Tray
 Open cable tray cap and check cable routing at key points and cable should not be
crossed or twisted

5) Equipment Status
 Check for any damages(scratches, dents) on all elements.

2013 Samsung Electronics

40

Quality Checklist
SITE CHECK LIST
Site ID
Site Name

Ite m

Date
Solpar
Result
(OK/NOK
)

Area
Auditor

Remarks

Weig
ht

Description

1. Pane l Ante nna


1.All Antennas bolt should be tightened w ith torque 239.7270.3 kgf .cm.
2.Antenna should not be moving w hen pushing w ith f orce.

1) Antenna Fixing

2) Antenna Position

All antennas should be w ithin 45angle of lightning


protection umbrella

3) Antenna A zimuth / Tilt

Ensure according to TSSR data

4) Cable Routing Condition


(Jumper & RET)

1.Min. bending radius should be 125 mm


2.First cable tie should be used at 600 mm f rom antenna
port then af ter at every 300 mm

5) Cable Labeling

Labeling should be done according to guideline


(Alpha-Blue,Beta-Red,Gamma-Green)

6) Feeder w eather proof ing

7) AISG(RET) cable connection &


Daisy chain port

2.5

1.Heat Shrink Tube length 150 mm, diameter 41mm,


2.Heating should shrink the tube properly w ith no air gap at
both ends of tube

7.5

1. AISG cable connector should be tighten to RET male port.


2. RET daisy chain port should be tighten w ith w eather
proof cap not to be seepage.

2. RRH Part
1) RRH Bracket Fixing
2) Bolt,Nut,Washer,Bushing,
Bakelite status

3) RRH isolation test

1.Check tightening status of nuts and bolts


2.Check horizontal and vertical leveling

Check all f ixing assembly item should be in place according


to installation guideline w ithout missing or damage

4) Cable Status

Check continuity w ith Multimeter betw een Pole and RRH


body(Resistance V alue <500V/100M Ohm)
*Bakelite and insulation bushing should be in place
1.CPRI,Pow er,RET cable should be terminated on desired
port w ith correct polarity
2.Check
all cable
f orlength
any damage
and sharp31mm,
bend.
1.Heat Shrink
Tube
150 mm,diameter

5) RRH Feeder w eather proof ing

2.5

2.Heating should shrink the tube properly w ith no air gap at


both ends of tube

6) AISG(RET) cable connection

7.5

1. AISG cable connector should be tighten to RRH RET


f emale port.
1.Grounding should be done using F-GV 6.0
x 1C cable,
2Hole Terminal,
2.Check cable f or any damage and sharp bend.
3.Check the routing of the cable is done properly.
4.Check w hether grounding cable lugs are covered w ith
the green heat shrink tube.

7) RRH Grounding

8) RRH input Pow er Check

___V

9) RRH Window tightening Status

25

10) Pow er cap , Heat Shrink Tube

11) Cable Labeling(CPRI,Pow er,


Grounding ,RET Cable & Jumper
Cable)
12) CPRI Cable termination inside
the RRH

1. Check DC Voltage, mention the pow er.


1. All the RRH w indow screw should be tightened w ith
torque driver T20 w ith 12.0kgf .cm f orce, in the pattern
mentioned in Installation guideline.
1. Check w hether the caps are f ixed on the pow er tapping
af ter pow er connection done inside RRH.
2. Check w hether pow er cable lugs are covered w ith the
Blue(-) & Red(+)heat shrink tube.
Check all the labeling done as per installation guideline

1.CPRI cable w ith insulation cover inside the RRH Box


should be equal to 60 mm
2.CPRI termination polarity w ill be Blue(Tx) & Red(Rx)

1. Check w hether the Glands of pow er cable, CPRI cable


are tightened using standard torque value 30.0kgf .

1) GPS Pole Fixing

GPS antenna should be w ithin 45angle of lightning


protection umbrella.

2) GPS Arrester

3) Cable status

13) Cable Gland tightening Status


3. GPS Part

4) GPS Labeling(CNT-400,RG- 316


D,Ground cable)
5) GPS Connectorization

2013 Samsung Electronics

1.Install the GPS arrestor on the f rame of 19" rack


2.Grounding should be done using F-GV 6.0
x 1C cable
1.CNT-400,RG- 316 D,Ground cable should be terminated
on desired port
2.Check
all cable f or any damage and sharp bend.
As per Guideline
1.Check both connector should be made as guideline
2.Crimp ring should crimp w ith hexagonal crimping tool tw o
time

41

Acceptance Test Procedure


 ATP 11 A is the acceptance test Procedure for the verification of
the Hardware Installation and includes the sections as per the
ATP Document.
 ATP 11B is the acceptance test for the verification of Backhaul
Integration

Microsoft Office
Word 97 - 2003 Document

2013 Samsung Electronics

43

Commissioning of eNodeB
(Including ATP11_B)

Mode of Commissioning- eNodeB


 Manual Commissioning
Solpar needs to commission the equipment at site.
This is for first 6,216 eNodeBs to be deployed at different locations

 Plug and Play Commissioning


This option is available after deployment of first lot of 6,216 eNodeBs. No Need
to commission the CDU at site. Solpar needs to power on the equipment & site
will automatically get integrated through LSM-R. Solpar team should standby at
the site till the integration activity is done from LSM-R.

2013 Samsung Electronics

45

Pre-requisites of Commissioning
 RS232 C Cable or Ethernet Cable (Debug Cable)
 Laptop with serial or Ethernet Port
 CLI Login details
 TeraTerm Application/other Telnet application software installed
on Laptop
 Site Parameter details like IP of LSM-R, IP of eNodeB, IP of
CSS- Gateway etc.
 4G Dongle for data call test (In case of Backhaul availability)

2013 Samsung Electronics

46

Login Options
1. Serial Port(RS232) interface
2. Ethernet(RJ45) Interface (Recommended)

2013 Samsung Electronics

47

Login Option - Using Serial Port


 Connecting Laptop with the DBG port on UAMA board through
Serial Cable (Requires RS232 on Laptop)

2013 Samsung Electronics

48

Login Option-USB to Serial Convertor


 If serial port is not available on the laptop, use the USB to serial
converter as below

2013 Samsung Electronics

49

Login- Serial Cable


 Access the UAMA board using TeraTerm or any other telnet
program on Laptop through the serial cable.
Steps of Login
Set the Baud Rate to 115200 bps.
Set the Serial Port Settings to COM1
Login ID: *******
Password: *******

2013 Samsung Electronics

50

Login Option 1- Serial Cable


 Access the UAMA board using TeraTerm or any other telnet program
on Laptop through the serial cable.
Steps of Login
Step 1. TeraTerm Settings
 Open TeraTerm Application Software, and do the following setting in it as shown in
figure

Set the Serial Port Settings to COM1


Set the Baud Rate to 115200 bps.
Login ID: *******
Password: *******
2013 Samsung Electronics

51

Step 1-TeraTerm Settings

2013 Samsung Electronics

52

Login Option 2-Ethernet


 Connecting Laptop with the EDBG port on UAMA board through
Ethernet Cable

2013 Samsung Electronics

53

Login Option 2-Ethernet


Steps of Login
Step 1. IP LAN Settings
IP Address:

192.168.32.28

Subnet Mask:

255.255.255.0

Default Gateway:

192.168.32.27

2013 Samsung Electronics

54

Login Option 2-Ethernet


Steps of Login
Step 2. Access UAMA board by TeraTerm or any other Telnet program
Step 3. Connection IP is 192.168.32.27

Step 4. Click Ok, following window get appears


2013 Samsung Electronics

55

Login Option 2-Ethernet


Steps of Login

Step 5. Enter User name & Password


(Contact the person incharge for Username and password)
2013 Samsung Electronics

56

Steps of Commissioning
Steps:
1) Login to UAMA board
2)Setting eNB environment parameters
a) Login as Super User mode
b) Check the original eNB environment parameters
c) Delete/Add eNB environment parameters
d) Confirm parameter settings

3) Initiate memory & eNB reboot


4) Verify network connectivity
5) Check System Status ( Hardware Alarms)
2013 Samsung Electronics

57

Steps of Commissioning- Login to UAMA board


Steps:
1) Login to UAMA board
If the connection to the UAMA board is successful, following window
appears:

2013 Samsung Electronics

58

Steps of Commissioning- Setting eNB environment parameters


Steps:
2) Setting eNB environment parameters
a) Login as Super User mode
Command Used: su

Password: ********

(Contact the person incharge for password)

2013 Samsung Electronics

59

Steps of Commissioning- Setting eNB environment parameters


Steps:
2) Setting eNB environment parameters
b)Check the original eNB environment parameters
Command Used: getenv a
Following window gets appear
__BOOTUP_FLAG__=000000020e
LEIP2_IP=10.5.46.14
LEIP2_NM=16
LEIP2_GW=10.5.0.1
PORT_0_0_2_IPV4_IP=10.5.46.14
PORT_0_0_2_IPV4_GW=10.5.0.1
PORT_0_0_2_IPV4_NM=16
bootdelay=1
baudrate=115200
pci_console_active=yes
pci_console_count=1
pci_console_size=2097152
stdin=pci
stdout=pci
stderr=pci
ethact=octeth0
2013 Samsung Electronics

bootcmd=bootoctbflag
AUTH=yes
BOOTMODE=static
RS_LOGIN=sysuser
RS_PASSWD=syslte123
SECU_CONN=yes
SECU_PASSWD=yes
adminstate=0
RS_IP=100.127.129.84
BOOTPORT=PORT_0_0_0
PORT_0_0_0_IPVER=4
PORT_0_0_0_IPV4_NM=30
PORT_0_0_0_IPV4_IP=100.127.132.1
PORT_0_0_0_IPV4_GW=100.127.132.2
NE_ID=16
IPV6_ENABLE=1
PORT_0_0_0_VLANID=103

60

Steps of Commissioning- Setting eNB environment parameters


Steps:
2) Setting eNB environment parameters
c) Delete/Add eNB environment parameters
Command Used: delenv

-p [Parameter Name]

Ex) root@UAMA:/root> delenv -p NE_ID


Ex) root@UAMA:/root> setenv -p NE_ID XX

As shown in next figure

2013 Samsung Electronics

61

Steps of Commissioning- Setting eNB environment parameters


Steps:
2) Setting eNB environment parameters
c) Delete/Add eNB environment parameters
Command Used: delenv

2013 Samsung Electronics

-p [Parameter Name]

root@UAMA:/root>
root@UAMA:/root> delenv -p NE_ID
Name = NE_ID
Value =
root@UAMA:/root> getenv -a
[Env Information]
bootdelay=1
baudrate=115200
pci_console_active=yes
pci_console_count=1
pci_console_size=2097152
~~
RS_IP=2405:201:fffb:0:1::52
BOOTPORT=PORT_0_0_2
PORT_0_0_2_IPVER=6
PORT_0_0_2_IPV6_NM=112
PORT_0_0_2_IPV6_GW= 4fa1:f00d:1234:5678:9abc:def1:aaaa:3
PORT_0_0_2_IPV6_IP= 4fa1:f00d:1234:5678:9abc:def1:aaaa:25
IPV6_ENABLE=1
__BOOTUP_FLAG__=000000020e

62

Steps of Commissioning- Setting eNB environment parameters


Steps:
2) Setting eNB environment parameters
c) Delete/Add eNB environment parameters
Command Used: setenv

2013 Samsung Electronics

-p [Parameter Name]

root@UAMA:/root> setenv -p NE_ID 26405


Name = NE_ID
Value = 26405
root@UAMA:/root> getenv -a
[Env Information]
bootdelay=1
baudrate=115200
pci_console_active=yes
pci_console_count=1
pci_console_size=2097152
~~
RS_IP=2405:201:fffb:0:1::52
BOOTPORT=PORT_0_0_2
PORT_0_0_2_IPVER=6
PORT_0_0_2_IPV6_NM=112
PORT_0_0_2_IPV6_GW= 4fa1:f00d:1234:5678:9abc:def1:aaaa:3
PORT_0_0_2_IPV6_IP=4fa1:f00d:1234:5678:9abc:def1:aaaa:25
IPV6_ENABLE=1
__BOOTUP_FLAG__=000000020e
NE_ID=26405

63

Steps of Commissioning- Setting eNB environment parameters


Script:

2013 Samsung Electronics

setenv -p bootdelay 1
setenv -p baudrate 115200
setenv -p pci_console_active yes
setenv -p pci_console_count 1
setenv -p pci_console_size 2097152
setenv -p stdin pci
setenv -p stdout pci
setenv -p stderr pci
setenv -p ethact octeth0
setenv -p bootcmd bootoctbflag
setenv -p AUTH yes
setenv -p BOOTMODE static
setenv -p RS_LOGIN sysuser
setenv -p RS_PASSWD syslte123
setenv -p SECU_CONN yes
setenv -p SECU_PASSWD yes
setenv -p adminstate 0
setenv p RS_IP 2405:201:fffb:0:1::52
setenv p BOOTPORT PORT_0_0_2
setenv p PORT_0_0_2_IPVER 6
setenv p PORT_0_0_2_IPV6_NM 112
setenv p PORT_0_0_2_IPV6_GW 4fa1:f00d:1234:5678:9abc:def1:aaaa:3
setenv p PORT_0_0_2_IPV6_IP 4fa1:f00d:1234:5678:9abc:def1:aaaa:25
setenv p NE_ID 26405
Press enter after this
setenv p IPV6_ENABLE 1
setenv p PORT_0_0_2_VLANID 103
64

Steps of Commissioning- Setting eNB environment parameters


Result:

2013 Samsung Electronics

root@UAMA:/root>
root@UAMA:/root> setenv -p bootdelay 1
Name = bootdelay
Value = 1
root@UAMA:/root> setenv -p baudrate 115200
Name = baudrate
Value = 115200
root@UAMA:/root> setenv -p pci_console_active yes
Name = pci_console_active
Value = yes
root@UAMA:/root> setenv -p pci_console_count 1
Name = pci_console_count
Value = 1
root@UAMA:/root> setenv -p pci_console_size 2097152
Name = pci_console_size
Value = 2097152
root@UAMA:/root> setenv -p stdin pci
Name = stdin
Value = pci
root@UAMA:/root> setenv -p stdout pci
Name = stdout
Value = pci
root@UAMA:/root> setenv -p stderr pci
Name = stderr
Value = pci
root@UAMA:/root> setenv -p ethact octeth0
Name = ethact
Value = octeth0
65

Steps of Commissioning- Setting eNB environment parameters


Result:

2013 Samsung Electronics

root@UAMA:/root> setenv -p bootcmd bootoctbflag


Name = bootcmd
Value = bootoctbflag
root@UAMA:/root> setenv -p AUTH yes
Name = AUTH
Value = yes
root@UAMA:/root> setenv -p BOOTMODE static
Name = BOOTMODE
Value = static
root@UAMA:/root> setenv -p RS_LOGIN sysuser
Name = RS_LOGIN
Value = sysuser
root@UAMA:/root> setenv -p RS_PASSWD syslte123
Name = RS_PASSWD
Value = syslte123
root@UAMA:/root> setenv -p SECU_CONN yes
Name = SECU_CONN
Value = yes
root@UAMA:/root> setenv -p SECU_PASSWD yes
Name = SECU_PASSWD
Value = yes
root@UAMA:/root> setenv -p adminstate 0
Name = adminstate
Value = 0
root@UAMA:/root> setenv -p RS_IP 2405:201:fffb:0:1::52
Name = RS_IP
Value = 2405:201:fffb:0:1::52
66

Steps of Commissioning- Setting eNB environment parameters


Result:

2013 Samsung Electronics

root@UAMA:/root> setenv -p BOOTPORT PORT_0_0_2


Name = BOOTPORT
Value = PORT_0_0_2
root@UAMA:/root> setenv -p PORT_0_0_2_IPVER 6
D:\Samsung\SolPar
Training_4G RFE-I&C\So
Name = PORT_0_0_2_IPVER
Value = 6
root@UAMA:/root> setenv -p PORT_0_0_2_IPV6_NM 30
Name = PORT_0_0_2_IPV6_NM
Value = 112
root@UAMA:/root> setenv -p PORT_0_0_2_IPV6_IP 4fa1:f00d:1234:5678:9abc:def1:aaaa:25
Name = PORT_0_0_2_IPV6_IP
Value = 4fa1:f00d:1234:5678:9abc:def1:aaaa:25
root@UAMA:/root> setenv -p PORT_0_0_2_IPV6_GW 4fa1:f00d:1234:5678:9abc:def1:aaaa:3
Name = PORT_0_0_2_IPV6_GW
Value = 4fa1:f00d:1234:5678:9abc:def1:aaaa:3
root@UAMA:/root> setenv -p NE_ID 26405
Name = NE_ID
Value = 26405
root@UAMA:/root> setenv -p IPV6_ENABLE 1
Name = IPV6_ENABLE
Value = 1
root@UAMA:/root> setenv -p PORT_0_0_2_VLANID 103
Name = PORT_0_0_2_VLANID
Value = 103

67

Steps of Commissioning- Setting eNB environment parameters


Steps:
2) Setting eNB environment parameters
c) Delete/Add eNB environment parameters
Command Used: setenv

-p [Parameter Name]

For ready reference following parameter can be use


setenv p RS_IP 2405:201:fffb:0:1::52
setenv p BOOTPORT PORT_0_0_2
setenv p PORT_0_0_2_IPVER 6
setenv p PORT_0_0_2_IPV6_NM 112
setenv p PORT_0_0_2_IPV6_GW 4fa1:f00d:1234:5678:9abc:def1:aaaa:3
setenv p PORT_0_0_2_IPV6_IP 4fa1:f00d:1234:5678:9abc:def1:aaaa:25
setenv p NE_ID 26405
setenv p IPV6_ENABLE 1
setenv p PORT_0_0_2_VLANID 103

2013 Samsung Electronics

 LSM server IP
 Booting port
 Using IP Version
 OAM IP Net-mask
 OAM Gateway IP
 eNB OAM IP
 eNB ID
 IPV6 Enable=1, Disable=0
 OAM VLAN ID

68

Steps of Commissioning- Setting eNB environment parameters


Steps:
2) Setting eNB environment parameters
d) Confirm parameter settings
Command Used: getenv a

After set the environment parameter


according to the information of eNB, finally
check the whole environment parameter
especially confirm the orange line.

2013 Samsung Electronics

root@UAMA:/root> getenv -a
[Env Information]
bootdelay=1
baudrate=115200
pci_console_active=yes
pci_console_count=1
pci_console_size=2097152
stdin=pci
stdout=pci
stderr=pci
ethact=octeth0
bootcmd=bootoctbflag
AUTH=yes
BOOTMODE=static
RS_LOGIN=sysuser
RS_PASSWD=syslte123
SECU_CONN=yes
SECU_PASSWD=yes
adminstate=0
RS_IP=2405:201:fffb:0:1::52
BOOTPORT=PORT_0_0_2
PORT_0_0_2_IPVER=6
PORT_0_0_2_IPV6_NM=112
PORT_0_0_2_IPV6_GW=4fa1:f00d:1234:5678:9abc:def1:aaaa:3
PORT_0_0_2_IPV6_IP=4fa1:f00d:1234:5678:9abc:def1:aaaa:25
NE_ID=26405
IPV6_ENABLE=1
PORT_0_0_2_VLANID=103
__BOOTUP_FLAG__=000000020e
69

Steps of Commissioning- Initiate memory & eNB reboot


Steps:
3) Initiate memory & eNB reboot
Commands Used: cd /mnt & rm rf*
lteuser@UAMA:~$ su Password:
root@UAMA:/root> cd /mnt
root@UAMA:/mnt> rm -rf *
rm: cannot remove directory `CPSW': Device or resource busy
rm: cannot remove directory `ram': Device or resource busy
rm: cannot remove directory `storage': Device or resource busy
rm: cannot remove directory `storage_bk': Device or resource busy
root@UAMA:/mnt> sync

There are lots of memories in UAMA unit in the progress of factory test; it can be affected for
software loading. Therefore, it is recommended to remove all shred memory under /mnt
directory in UAMA unit.

2013 Samsung Electronics

70

Steps of Commissioning- Initiate memory & eNB reboot


Steps:
3) Initiate memory & eNB reboot
Commands Used: reboot

2013 Samsung Electronics

71

Steps of Commissioning- Verify network connectivity


Steps:
4) Verify network connectivity
Commands Used: ping6 [IPv6 IP Address]
root@UAMA:/root> ping6 2405:201:fffb:0:1::223
PING 2405:201:fffb:0:1::223(2405:201:fffb:0:1::223) 56 data bytes
64 bytes from 2405:201:fffb:0:1::223: icmp_seq=1 ttl=63 time=0.289 ms
--- 2405:201:fffb:0:1::223 ping statistics --1 packets transmitted, 1 received, 0% packet loss, time 996ms
rtt min/avg/max/mdev = 0.289/0.289/0.289/0.000 ms

After eNB restart, check the connectivity between eNB and LSM by ping command.
 If there is issue with connectivity, check whether the eNB IP and route, VLAN configuration is
correct, else coordinate with LSM-R Engineer.

2013 Samsung Electronics

72

Steps of Commissioning- Check System Status ( Hardware Alarms)

Steps:
5) Check System Status ( Hardware Alarms)-In normal condition

ACT and GPS LEDs must blinking

TX LED of SFP port should be green

In normal condition
2013 Samsung Electronics

73

Steps of Commissioning- Check System Status ( Hardware Alarms)

Steps:
5) Check System Status ( Hardware Alarms)-In abnormal condition

ACT and GPS LEDs starts glowing RED

No glow of LED at SFP Port

Action to be taken:
Report the current situation to LSM-R team
Troubleshoot the problem, coordinate with LSM-R Team
Dont leave the site till alarm clear

2013 Samsung Electronics

74

ATP11B

Introduction
ATP11_B is conducted after site Integration
Test Tools & Method of procedure will be provided by
RJIL.
Tools needed:
 Laptop
 UE (User Equipment)
 Application to perform test (test tool)

2013 Samsung Electronics

76

ATP11_B- Items

Microsoft Office
Word Document

2013 Samsung Electronics

77

Gamsahapnida
Thank You
Copyright and Confidentiality
Copyright 2013, SAMSUNG Electronics Co., Ltd. SAMSUNG Electronics reserves the right to make changes to the specifications of
the products detailed in this document at any time without notice and obligation to notify any person of such changes. Information
in this document is proprietary to SAMSUNG Electronics Co., Ltd. No information contained here may be copied, translated,
transcribed or duplicated by any form without the prior written consent of SAMSUNG Electronics.

You might also like