MONTHLY PROGRESS REPORT

CONTRACT NO. HQ 514 FM 05


WORK ORDER NO. MSS/11/684
11th OVERHAUL OF KHAFJI DESALTER PLANT
Month
NO.

MONTH DURATION
FROM

CONTRACTOR

: AL JALHAMI CONT. EST.

TO

29/12/11 31/01/12

Total % achieved up to this month(Overall)


Details of work in this week:

: 42.205%

Progress =
C. Overhaul of After cooler DE- 11 A/B/C & DE - 12 A/B/C
1) Draining and Steam purging completed by PRD on 29.12.2011
2) Erection of scaffolding completed on 31.12.2011
3) Blinding of inlet and outlet pipe lines started on 01.01.12 completed on 02.01.12
4) Removal of PSV for calibration completed on 01.01.12.
5) Removal of shell cover, floating head, channel, channel cover for chemical cleaning started on 02.01.12
and completed on 03.01.12.
6) Hydrojetting of tube bundle for chemical cleaning started on 04.01.12 and completed
on 11.01.12.
7) Re-installation of floating head and channel head and channel cover for chemical cleaning started
and completed on 12.01.12.
8) Chemical cleaning of After cooler DE-12 A/B/C started on 12.01.12 and completed on 14.01.12.
9) Removal of shell cover, floating head, channel, channel cover,tube bundles for DE 12 A/B/C started on
14.01.12 and completed on 16.01.12.
10) Hydrojetting of tube bundle for DE-12 A/B/C started on 16.01.12 and completed on 18.01.12.
11) Chemical cleaning of After cooler DE-11 A/B/C started on 16.01.12 and completed on 20.01.12.
12) Removal of shell cover, floating head, channel, channel cover,tube bundles for DE 11 A/B/C started on
20.01.12 and completed on 21.01.12.
13) Hydrojetting of tube bundle for DE-11 A/B/C started on 20.01.12 and completed on 22.01.12.
14) Tube inspection of DE-12 A/B/C by ESD started on 26.01.12 and completed on 31.01.12.
15) Tube inspection of DE-11 A/B/C by ESD started on 31.01.12 and is in progress.

Prepared by:

Checked by:
Al Jalhami Cont.

Date:

Approved by:
MSS/TMD-Eng'r

Date:

MSS/TMD- Sup'r
Date:

NT

AL JALHAMI CONT. EST.

Page 2 of 4

70%

aning started on 02.01.12

cal cleaning started

ted on 14.01.12.

DE 12 A/B/C started on

d on 18.01.12.

ted on 20.01.12.

DE 11 A/B/C started on

d on 22.01.12.

MSS/TMD- Sup'r

COMPLETIONREPORT
CONTRACTNO.HT003SS11
WORKORDERNO.MSS/14/353R
REPAIROFMISALIGNED16"PIPELINEATATK31
ASPERWORKREQUESTOMD/DES/13/02
REPORT MONTHDURATION
NO.

FROM

TO

10/12/14

07/01/15

CONTRACTOR

:ALJALHAMICONT.&TRAD.CO.(W.L.L)

Detailsofwork:
Progress =

1.Removalofdamagedbracketsupportsfrom16outletline.(10.12.2014)
2.Pullback16pipelineaxiallyby55mmtoitsoriginalposition.(13.12.2014)
3.Dimensionalmeasurementofbellowandgapforfabricationofpipespool.(16.12.2014)
4.Fabricationforbaseplate,supportstructuresandlimitstopsweredoneparallel.(20.12.2014)
5.ExcavationforPS-01andPS-02.(20.12.2014)
6.DemolitionofDummysupport.(20.12.2014)
7.DemolitionofpipesupportsatPS-03&PS-04.(21.12.2014)
8.ExcavationforPS-03,PS-04anddummysupport.(21.12.2014)
12.Compactionofexcavatedareas.(23.12.2014)
9.FabricationofpipespoolatJalhamiyard.(23.12.2014)
13.PreparationofsteelformsforcastingofPipesleepers.(23.12.2014)
14.Shutteringworkforallpipesleepers.(23.12.2014)
10.VisualinspectionofpipespoolbyESD.(24.12.2014)
15.Castingofallpipesleepers.(24.12.2014)
11.HydrotestingofpipespoolasperESDrecommendation.(27.12.2014)
16.Isolationofoutletlinebyblinding.(27.12.2014)
17.Flushinganddrainingofoutletlinewithwater.(27.12.2014)
18.Installationofpipespoolandexpansionbellow.(28.12.2014)
19.Fillingofoutletlinewithfreshwater.(28.12.2014)
20.Installationofsupportstructures.(31.12.2014)
21.Installationoflimitstops.(31.12.2014)
22.Installationofguidemembers.(31.12.2014)
23.Coatingofpipespoolasperstandard.(31.12.2014)
24.Coatingofallsupportstructuresasperstandard.(31.12.2014)
25.Backfillingandhousekeeping.(01.12.2014)
26.Jointinspectionofsite.(04.12.2014)
27.Touchupwork.(06.12.2014)
28.Readyforhandover.(07.12.2014)

Preparedby:

Checkedby:
AlJalhamiCont.

Date:

Approvedby:
MSS/TMDEng'r

Date:

MSS/TMDSup'r
Date:

TK31

NT.&TRAD.CO.(W.L.L)
PAGE 1 OF 1

100.00%

(16.12.2014)
allel.(20.12.2014)

MSS/TMDSup'r

MONTHLY PROGRESS REPORT


CONTRACT NO. HT003SS11
WORK ORDER NO. MSS/13/060
11th OVERHAUL OF KHAFJI DESALTER PLANT
Month
NO.

MONTH DURATION
FROM

CONTRACTOR

: AL JALHAMI CONT. EST.

TO

01/09/13 31/07/12

Total % achieved up to this month(Overall)


Details of work in this week:

: 7.642%

Progress =
C. Overhaul of After Coolers DE- 13 A/B/C & 14 A/B/C.
1) Removal of FRP spools as per the instruction given by OND, work completed on 18/09/13.
2) Erection of scaffolding completed on 18/09/13.
3) Steam purging completed by OND on 17/09/13.
4) Blinding works completed on 18/09/13.
5) Removal of channel cover, channel cover head and floating head are in progress.
6) Removal of PSVs completed on 23/09/2013 send for calibration.
1) Cleaning of tube bundles by hydrojetting are in progress.
2) Cleaning of Anodes at channel head are in progress.

D Overhaul of Preheater E71-B , E61-D.


1) Erection of scaffolding completed on 18/09/13 in E61-D.

Progress =

2) Steam purging completed by OND on 17/09/13 E61-D.


3) Blinding works completed on 18/09/13 E61-D.
4) Removal of channel cover, channel cover head and floating head are completed 20/09/13 E61-D
5) Cleaning of tube bundles by hydrojetting are in progress in E61-D.

Prepared by:

Checked by:
Al Jalhami Cont.

Date:

Approved by:
MSS/TMD-Eng'r

Date:

MSS/TMD- Sup'r
Date:

NT

AL JALHAMI CONT. EST.

Page 2 of 3

14%

30%

d 20/09/13 E61-D

MSS/TMD- Sup'r

MONTHLY PROGRESS REPORT


Contract No.
: HT003SS11
Work O. No.
: MSS/13/060
Contract title
: 12th OVERHAUL OF KHAFJI DESALTER PLANT
Contractor
: AL JALHAMI CONT. EST
A. Fixed Scope of Work:
Sl.
No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
B.
1)
2)
3)

WEIGHT
%

DESCRIPTION
Desalter Vessels DV-1A/B
Desalter Vessels DV-2A/B
Desalter Vessels DV-3A/B
Desalter Vessels DV-4A/B
Fuel Gas Scrubber DV-11 and DV-13
Air Reciever DV-14
Oxygen Stripper DV-15
Condensate Drum DV-18
Rawcrude Preheaters DE-1A/B/C and DE-2A/B/C
Rawcrude Preheaters DE-3A/B/C and DE-4A/B/C
Rawcrude Preheaters DE-5A/B/C to DE-6A/B/C
Desalted Crude Aftercoolers DE-11A/B/C & DE-12A/B/C
Desalted Crude Aftercoolers DE-13A/B/C & DE-14A/B/C

Desalted Crude Aftercoolers DE-15A and DE-16A


Desalted Crude Aftercoolers DE-15B and DE-16B

8.873
8.873
8.873
8.873
1.065
0.444
0.710
0.532
5.324
5.324
6.388
12.245
12.245
4.614
0.365
0.177
3.549
3.549
1.065
1.420
0.621
0.444
0.355
0.887
0.355
2.830
100.000

Report No.
From
01.09.2013

Completion %
Previous
Month

Instrument Air Reciever DM-3


Rawcrude Direct Heater DHT-1
Rawcrude Direct Heater DHT-5
Fuel Gas heater GHT-1 and GHT-2
Surge Tank DTK-1 & Slop Oil Tank DTK-2
Wash Water Surge Tank DTK-3
Demulsifier Chemical tank, cone roof, DTK-11
Demulsifier Chemical tank, DTK-12
Oxygen Scavanger Tank DTK-14
Inhibitor chemical drums
High Stacks HST-1 and HST-2
Sub Total of fixed scope of work
Other Variable scope of Work:
Replacement of ALFA LAVAL DE -16B completed on 29/08/13
General maintenance of Presettling tank TK-060A Cleaning completed
Overhaul of Preheater E61- D
Prepared By:

Checked by:
Al Jalhami Cont. Est

Date:

Total to Date %

This Month

0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0.0%
0%
0%
0%
0%
0%
0%
0.0%
0%
0%
0%
0%
0%
0%
0%
0%
0.000%

Completion

0%
0%
59%
59%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
13%
13%
0%
0%
0%
0%
14%
14%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0.000%
0.000%
86%
86%
Progress 100%
Progress..88%
Progress 30%

Weightage

0.000%
5.235%
0.000%
0.000%
0%
0%
0%
0%
0.000%
0.692%
0.000%
0.000%
1.714%
0.000%
0.000%
0%
0.000%
0.000%
0%
0%
0%
0%
0%
0%
0%
0%
7.642%

Approved By:
MSS/TMD-Eng'r

Date:

Page 3 0f 3
1
To
30.09.2013

MSS/TMD- Sup'r
Date: