Professional Documents
Culture Documents
Seite 1 von 4
The
circular
is
available
on
the
website
of
the
Directorate:
www.dgshipping.com
This issues with the approval of the Chief Surveyor with the Government of India.
Yours faithfully,
Sd/(D.Mehrotra)
Engineer and Ship Surveyor
Encl : As above.
Guidelines for the maintenance and inspection of FireProtection systems and appliances.
1.
Application
These Guidelines apply to all ships; however it does not contain an exhaustive list of
maintenance items and should be used as a recommendation only.
2.
Operational readiness
All fire protection systems and appliances should at all times be in good order and available for
immediate use while the ship is in service. If a fire protection system is under repair, then
suitable arrangements should be made to ensure safety is not diminished.
3.
Instructions for on-board maintenance, not necessarily by the ship?s crew, and testing of active
and passive fire protection systems and appliances should be easily understood, illustrated
http://www.dgshipping.com/dgship/final/notices/engcir25.htm
2007-07-10
Seite 2 von 4
wherever possible, and, as appropriate, should include the following for each system or
appliance :
1
log for records of inspections and maintenance, listing identified nonconformities and their targeted completion dates.
4.
all public address systems and general alarm systems are functioning
properly; and
2
5.
all fireman?s outfits, fire extinguishers, fire hydrants, hose and nozzles are
in
place,
properly
arranged,
and
are
in
proper
condition;
2
all fixed fire-fighting system stop valves are in the proper open or closed
position, dry pipe sprinkler systems have appropriate pressures as indicated by
gauges;
all fixed fire-extinguishing installation using extinguishing gas are free from
leakage.
6.
all automatic alarms for the sprinkler system are tested using the test
http://www.dgshipping.com/dgship/final/notices/engcir25.htm
2007-07-10
Seite 3 von 4
all fire doors and fire dampers are tested for local operation; and
all CO2 bottle connections for cable operating system clips should be
checked for tightness on fixed fire-extinguishing installations.
7.
all fire extinguishers are checked for proper location, charging pressure and
condition;
all fire doors and dampers are tested for remote operation;
all foam-water and water-spray fixed fire-fighting systems are tested for
operation;
are visually
all fire pumps, including sprinkler system pumps, are flow tested for proper
pressures and flows;
sprinkler system connections from the ship?s fire main are tested for
operation.
10
11
12
13
http://www.dgshipping.com/dgship/final/notices/engcir25.htm
2007-07-10
8.
Seite 4 von 4
Five-year service
Further to engine circular No. 17 dated 08.10.2003, the following inspection and tests are also to
be carried out at least once every five years.
1
http://www.dgshipping.com/dgship/final/notices/engcir25.htm
2007-07-10
Seite 1 von 6
2.
These Guidelines relate to the application of the ISM Code to periodic servicing and
maintenance of lifeboat arrangements and should therefore be reflected in procedures
developed for a ship under that Code.
3.
These Guideline can also be used for the periodic servicing and maintenance of
liferafts, rescue boats and fast rescue boats and their launching appliances and release
gear.
4.
SOLAS regulations
http://www.dgshipping.com/dgship/final/notices/engcir26.htm
2007-07-10
5.
Seite 2 von 6
.2
Responsibilities
6.
The company is responsible for servicing and maintenance onboard its ships in
accordance with SOLAS regulation III/20 and for the establishment and implementation of
health, safety and environment (HSE) procedures covering all activities during servicing
and maintenance.
7.
The personnel carrying out servicing and maintenance are responsible for the
performance of the work as authorized in accordance with the system specified in
paragraph 9.
8.
The above personnel is also responsible for complying with HSE instructions and
procedures.
9.
Where satisfied with an organization?s ability to carry out these functions, the
Administration may authorize such organization to perform the functions of the
manufacturer as assigned under these Guidelines, if the manufacturer is unable to provide
the service.
Authorization
10.
Qualification levels
11.
12.
All other inspections, servicing and repair should be conducted by the manufacturer?s
representative or a person appropriately trained and certified by the manufacturer for the
work to be done.
All reports and checklists should be correctly filled out and signed by the person who
carries out the inspection and maintenance work and should also be signed by the
company?s representative.
14.
15.
When repairs, thorough servicing and annual servicing are completed, a statement
confirming that the lifeboat arrangements remain fit for purpose should be issued by the
manufacturer?s representative.
APPENDIX
SPECIFIC PROCEDURES FOR MAINTENANCE AND SERVICING
1
GENERAL
http://www.dgshipping.com/dgship/final/notices/engcir26.htm
2007-07-10
Seite 3 von 6
1.1
Any inspection, servicing and repair should be carried out according to the system for
inspection and services developed by the manufacturer.
1.2
1.3
The manufacturer?s system for inspection and service should include the following
items as a minimum.
THOROUGH EXAMINATION
2.1
As items listed in checklists for the weekly/monthly inspections also form the first
part
the
appropriately
2.2
2.3
Repairs and replacement of parts should be carried out in accordance with the
manufacturer?s requirement and standards.
Lifeboat
2.4
The following items should be examined and checked for satisfactory condition and
operation:
1
maneuvering system;
bailing system.
Release gear
2.5
http://www.dgshipping.com/dgship/final/notices/engcir26.htm
2007-07-10
hook fastening.
Seite 4 von 6
Notes:
1.
The setting and maintenance of release gear are critical operations with regard to
maintaining the safe operation of the lifeboat and the safety of personnel in the
lifeboat. All inspection and maintenance operations on this equipment should
therefore be carried out with the utmost care.
2.
3.
Hanging-off pennants may be used for this purpose but should not remain
connected at other times, such as when the lifeboat is normally stowed and during
training exercises.
2.6
position the life boat partially into the water such that the mass of the boat is
substantially supported by the falls and the hydrostatic interlock system, where
fitted, is not triggered;
2.7
recover the lifeboat to the stowed position and prepare for operational readiness.
Note:
Prior to hoisting, check that the release gear is completely and properly reset. The final
turning-in of the lifeboat should be done without any persons on board.
http://www.dgshipping.com/dgship/final/notices/engcir26.htm
2007-07-10
Seite 5 von 6
Davit
2.8
The following items should be examined for satisfactory condition and operation:
1
davit
structure,
in
particular
with
regard
to
corrosion,
misalignments,
hydraulic systems.
Winch
2.9
The following items should be examined for satisfactory condition and operation:
1
3.1
Annual operational testing should preferably be done by lowering the empty boat. When
the boat has reached its maximum lowering speed and boat enters the water, the brake should be
abruptly applied.
3.2
Five-yearly operational testing should be done by lowering the boat loaded to a proof
load of 1.1 times the maximum working load of the winch, or equivalent load. When the
boat
has reached its maximum lowering speed and before the boat enters the water, the
brake
Following these tests, the brake pads and stressed structural parts should be re-
inspected.
Note:
In loading the boat for this test, precautions should be taken to ensure that the stability of
http://www.dgshipping.com/dgship/final/notices/engcir26.htm
2007-07-10
Seite 6 von 6
the boat is not adversely affected by free surface effects or the raising of the centre of
gravity.
4
operational test as per above and with a load according to SOLAS regulation
III/20.11.2.3; and
Note:
Non-destructive examination (NDE) techniques, such as dye penetrants (DPE), may be
suitable.
http://www.dgshipping.com/dgship/final/notices/engcir26.htm
2007-07-10
Seite 1 von 2
Ref:
Ref:12.4.2004
Ref:- Eng. Circular No. 17 dated 8th October 2003 and Eng. Circular No. 25 dated 12.4.2004
1. Maintenance plan
plan
The maintenance plan should include, but not limited to the following fire protection systems and Fire
appliances, where installed.
(i)Fire mains, fire pumps and hydrants including hoses, nozzles and international shore connections.
(ii)Fixed fire detection and fire alarm systems
(iii)Fixed fire-extinguishing systems and other fire extinguishing appliances
(iv)Automatic sprinkler, fire detection and fire alarm systems
(v)Ventilation systems including fire and smoke dampers, fans and their controls
(vi)Emergency shut down of fuel supply
(vii)Fire doors including their controls
(viii)General emergency alarm systems
(ix)Emergency Escape Breathing Devices (EEBD)
(x)Portable fire extinguishers including spare charges, and
(xi)Fire-fighter's outfit.
2.
Maintenance of Portable Fire Extinguishers are required to be carried out as specified in IS 2190:1992. Every fire exti
2.
on board ships shall be hydraulically pressure tested as per the schedule given below. Extinguisher, which fails during the p
shall be replaced.
.1 Schedule For Hydraulic Pressure Testing Of Fire Extinguishers.
The Hydraulic Pressure Testing Should Be Carried Out Such That At Least One Third (1/3) Of The Extinguishers A
Year And The Pressure Testing Cycle Of All Extinguishers Are Completed Every Three Years.
Sr.No.
1.
Type of Extinguisher
Water type (gas cartridge)
Test Interval
Test Pressure
Pressure Maintained
3 years
1.75 MPa
2.5 min
(17.5 kg/cm )
http://www.dgshipping.com/dgship/final/notices/engcir66.htm
2007-07-10
Seite 2 von 2
2.
Mechanical foam
3 years
3.
3 years
1.75 MPa
(17.5 kg/ cm2)
2.5 MPa
(25 kg/ cm2)
2.5 min
2.5 min
.2
.2 Extinguishers To Be Refilled / Operated For Performance Test
EVERY YEAR
a) Portable/Non-portable fire
(mechanical foam type).
extinguisher
3.
3. Maintenance, Inspection and Tests
Tests
.1 In addition to above, maintenance, inspection and tests of firefire-protection and fire fighting systems should be carrie
Engine Circular No. 17 dated 8.10.2003 and No. 25 dated 12.4.2004.
.2
.2 A well planned maintenance schedule is essential to ensure that an extinguisher, will operate properly. Details
procedure are given in Annex I, however same should not be considered as exhaustive.
Sd/Sd/(D. Mehrotra)
Dy. Chief Surveyor cum Sr.DDG(Tech)
http://www.dgshipping.com/dgship/final/notices/engcir66.htm
2007-07-10
Seite 1 von 2
On-Sub: Guidelines for Periodic Servicing and Maintenance of Lifeboats, Launching Appliances and On
Load Release Gear to be addressed through the Safety Management System Manual
font>./
Reference : Engineering Branch Circular No.26 dated 12.04.2004
12.04.2004
Recognizing the importance of proper maintenance and inspection of lifeboats, launching appliances and
on-load release gear, Guidelines for Developing Operation and Maintenance Manuals for Lifeboat
Systems and Measures to Prevent Accidents with Lifeboats are enclosed. These Guidelines relate to the
application of the ISM Code to periodic servicing and maintenance of lifeboat arrangements and should
therefore be reflected in procedures developed for a ship under that Code.
The guidelines are as per MSC Circular No.MSC.1/Circ.1205 and 1206. The purpose of these guidelines
is to encourage development of user friendly manuals for operation and maintenance of lifeboat systems
including launching appliances. Personnel undertaking the inspection, maintenance of lifeboats,
launching appliances and associated equipment are required to be fully trained and familiar with the
duties to be carried out, in accordance with approved established procedures and manufacturers?
manuals.
The periodical servicing / maintenance / repair work and testing of lifeboats systems should be conducted
by the manufacturer?s representative or a person appropriately trained and certified by the
manufacturer and attached to a DGS approved work shop for the work to be done in accordance with
MSC.1/Circ.1206. In case the vessel is not in Indian port the servicing / maintenance is to be carried by
the workshops approved by the Administration / Certified by the manufacturer.
All shipping companies are required to ensure that the following are addressed through its Safety
Management System Manual.
1] on-load release equipment used is in full compliance with the requirements of paragraphs
4.4.7.6.2.2 to 4.4.7.6.5 of the LSA Code;
2] all appropriate documentation for the maintenance and adjustment of lifeboats, launching
appliances and associated equipment is available on board;
3] personnel undertaking inspections, maintenance and adjustment of lifeboats, launching appliances
and associated equipment are fully trained and familiar with these duties;
4] maintenance of lifeboats, launching appliances and associated equipment is carried out in
accordance with approved established procedures;
5] lifeboat drills are conducted in accordance with SOLAS regulation III/19.3.3 for the purpose of
http://www.dgshipping.com/dgship/final/notices/engcir78.htm
2007-07-10
Seite 2 von 2
ensuring that ship?s personnel will be able to safely embark and launch the lifeboats in an emergency;
6] the principles of safety and health at work apply to drills as well;
7] personnel undertaking maintenance and repair activities are appropriately qualified;
8] hanging-off pennants should only be used for maintenance purposes and not during training
exercises.
This issues with the approval of the Chief Surveyor with the Government of India.
Sd/Sd/(D.Mehrotra)
Dy. Chief Surveyor cum Sr.DDG(Tech)
http://www.dgshipping.com/dgship/final/notices/engcir78.htm
2007-07-10
Seite 1 von 1
Sub: Maintenance, Inspection and Tests of Fire - Protection and Fire Fighting System on Board Ships ?
amendment to provision there in
In response to Engineering Circular No. 66 on the above subject, it has come to the notice of this
Directorate that shipping companies are not able to comply with the requirement of getting one third of
the fire extinguishers pressure tested every year. In order to facilitate shipping companies, it has been
decided that fire extinguishers may be hydraulically pressure tested during the dry dock once in three
years. However, shipping companies are required to ensure that the ships fire extinguishers are properly
maintained and kept in satisfactory operating condition at all times.
This issues with the approval of the Chief Surveyor with the Government of India.
Sd/Sd/(D.Mehrotra)
Dy. Chief Surveyor cum Sr.DDG(Tech)
http://www.dgshipping.com/dgship/final/notices/engcir81.htm
2007-07-10
Seite 1 von 3
B1) Annual dynamic load tests shall be carried out by lowering the empty boat based on the guidelines of
MSC.1/Circu. 1206, Appendix of Annex 1, Paragraph 3.1 and 3.3 as far as applicable.
The test shall be conducted either by:
file://C:\DOKUME~1\swe\LOKALE~1\Temp\9714SQ4Z.htm
2007-07-10
Seite 2 von 3
authorized surveyor. Workshop carrying out the test / servicing in India to be registered with the
Directorate.
B2) 5-yearly dynamic load tests shall be carried out with test weight 1.1 x GA based on the guidelines of
MSC.1/Circ. 1206, Appendix of Annex 1, Paragraph 3.2 and
3.3 as far as applicable. This requirement applies 5-yearly to all launching appliances with fall and winch
including cranes and davits for freefall lifeboats.
The test shall be conducted either by:
The annual / 5-yearly dynamic load tests under B1 and B2 have always to be conducted upon
completion of the related annual thorough examination under A.
1b) Lifeboat onon-load Release Gear (Regulation 20.11.2)
B) Annual thorough examinations shall be carried out based on the guidelines of MSC.1/Circ.1206,
Appendix of Annex 1, Paragraph 2.5
The thorough examination shall be conducted either by:
D) Annual operational tests shall be carried out based on the guidelines of MSC.1/Circ. 1206, Appendix of
Annex 1, Paragraphs 2.6 and 2.7
The test shall be conducted either by:
E) 5- yearly overhauling and operational test with test weight 1.1 x GA shall be carried out based on the
guidelines of MSC.1/ Circ.1206, Appendix 1, Paragraph 4.
The overhauling and test shall be conducted either by:
file://C:\DOKUME~1\swe\LOKALE~1\Temp\9714SQ4Z.htm
2007-07-10
Seite 3 von 3
file://C:\DOKUME~1\swe\LOKALE~1\Temp\9714SQ4Z.htm
2007-07-10