BEFORE HEADWORKS INSTALLATION


125mm NB FRP CASING WITH 80mm NB SCREENS TELESCOPED
Anticipated Casing String Run
Casing float shoe 396.00 - 395.55
Drill-out Pipe
395.55 - 390.05
Centron x/over
390.05 - 389.60
45 lengths FRP
389.60 - +0.68

273.10mm OD STEEL SURFACE


CASING PRESSURE GROUTED
IN AT - 66 METERS

Stick-Up is 0.68metres

FRP Casing Grades

ENTRALISERS
1 PER CASING LENGTH

DHC200 30 joints 0-266 Approx


DHC250 9 joints 266 - 389 Approx

125mm NB FRP MAIN CASING


WITH RELEVANT GRADE TO SUIT
DEPTH - PRESSURE GROUTED IN
Screen Assembly

SS end plate
80mm 55 Sump
80mm Screen
80mm Riser Pipe
80 x 125 Packer

416.000
410.00 - 408.00
408.00 - 396.00
396.00 - 392.00
392.00 - 391.50

6.50 - METRE 80mm RISER PIPE


WITH VULCANISED BORE K-PACKER

,---5.50 METRE125mm NB SS DRILL-OUT


PIPE PLUS X/OVER

OTTOM OF 125mm NB CASING


FLOAT SHOE AT -396 METRES

12 METRES 80mm NB SS SCREEN


FROM 396m TO 408m

CASING FLOAT SHOE

2 METRES SUMP 80mm NB SS


WITH END PLATE

TOTAL SCREEN ASY EXTENDS


FROM TOP OF PACKER AT
389m TO BASE OF SUMP
(BOTTOM OF HOLE) AT - 410m

Replacement Inflatable Packers and Elements Pty Ltd


29 Wheeler St, Belmont, Perth Western Australia 6104
www.ripe-packers.com
packers@ripe-packers.com

REPLACEMENT INFLATABLE
PACKERS & ELEMENTS PTY LTD
29 WHEELER STREET, BELMONT, WESTERN AUSTRALIA 6104
PH: +61 (08) 9475 0700, Fax: +61 (08) 9475 0770
packersripe-packers.com www.ripe-packers.com

Drilling and Construction


of New Bores

Suggested General Work Procedure


Drilling Technique:
Surface Casing:
Main Casing:
Screen Assembly:

Mud Rotary
273.0m OD steel
125mm NB FRP - 167mm maximum OD at tools joints
Stainless Steel drill-out pipe, casing float shoe and cross-over
Stainless Steel end plate
2metres 80mm NB stainless steel sump extension
12 metres of 80mm NB, grade 316 stainless steel bore screen
6.50 metres 80mm NB stainless steel riser pipe extension
vulcanised bore packer

Bore Construction:
Drill for and install 273.10mm OD steel surface casing at -66metres with a casing float shoe and
centralisers and pressure grout it into place. take 2 samples of the grout slurry.
Allow 12 hours for grout cure.
Top up the annulus with grout to ground level as required.
Drill out the shoe and drill a hole of suitable diameter to the target depth which is
expected to be approximately 410metres.
Stand-by while the contracted operator conducts a geophysical log of the bore.
Install 125mm NB FRP casing with casing float shoe, bottom drill-out pipe, crossover and centralisers and
pressure grout it into place at the depth directed expected to be at - 396metres. Take 2 samples of the
grout slurry. (125mm NB FRP casing has a maximum diameter over the tool joints of 167mm);
\\( **The decision to grout without the bottom of the hole or to gravel pack the bottom of
the hole prior to grouting is entirely at the contractor's discretion.**
Allow 24 hours for grout cure.
Run in and drill out the cement at the shoe.
Continue to clean out the borehole to the depth required for the screen assembly, anticipated to be
41 metres.
Run the 80mm NB stainless steel screen assembly and vulcanised bore packer and set it at the
depth directed.
Develop the bore in line with the requirements o the contract.
Fit the head works assembly standpipe.
Cast a concrete block around the standpipe at surface. the block shall be a minimum of
750mm square x 350mm deep. The top of the block shall be at ground level.
The top of the standpipe shall be not less than 600mm and not more than 750mm above the top
of the block.
** Surface casing depth should be decided on-site as drilling is undertaken.**

Replacement Inflatable Packers and Elements Pty Ltd


29 Wheeler St, Belmont, Perth Western Australia 6104
www.ripe-packers.com
packers@ripe-packers.com

You might also like