Professional Documents
Culture Documents
I.K. Gunarta
Department of Industrial Engineering
ITS
PERT
Three time estimates are required to
compute the parameters of an activitys
duration distribution:
pessimistic time (tp ) - the time the activity would
take if things did not go well
most likely time (tm ) - the consensus best estimate
of the activitys duration
optimistic time (to ) - the time the activity would
take if things did go well
. . . more
5
PERT
From these three time estimates about
an activity, two probability distribution
parameters are calculated: the mean
(te ) and the variance (Vt ).
te = ( to + 4tm + tp ) / 6
Vt = [ ( tp - to ) / 6 ] 2
6
Contoh
Aktivitas
Te
[(b a)/6]2
17
29
47
30
25
12
24
13
16
19
28
20
13
16
19
16
14
Network
B
43
43
59
30 13
43
43 16
59
30
30
59
64
30
30
59
64
50
50
56
33 20
53
53
59
30
10
Te = 64
Ts = 67
11
Solusi
V Path = VA + VB + VD + VF
V Path = 25 + 9 + 1 + 1
path = 6
Z = (67 64)/
= + 0.5
P = 0.69
12
PERT Example
Immed. Optimistic Most Likely Pessimistic
Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.)
A
-4
6
8
B
-1
4.5
5
C
A
3
3
3
D
A
4
5
6
E
A
0.5
1
1.5
F
B,C
3
4
5
G
B,C
1
1.5
5
H
E,F
5
6
7
I
E,F
2
5
8
J
D,H
2.5
2.75
4.5
K
G,I
3
5
7
13
PERT Example
ACTIVITY
A
B
C
D
E
F
G
H
I
J
K
PREDECESSOR OPTIMISTIC
TIME
A
A
A
B, C
B, C
E, F
E, F
D, H
G, I
4
1
3
4
0,5
3
1
5
2
2,5
3
MOST
LIKELY
TIME
6
4,5
3
5
1
4
1,5
6
5
2,75
5
PESSIMISTIC
TIME
8
5
3
6
1,5
5
5
7
8
4,5
7
PERT Example
PERT Network
D
C
B
I
F
G
15
PERT Example
Activity Expected Time and Variance
Activity
A
B
C
D
E
F
G
H
I
J
K
Expected Time
6
4
3
5
1
4
2
6
5
3
5
Variance
4/9
4/9
0
1/9
1/36
1/9
4/9
1/9
1
1/9
4/9
16
PERT Example
Earliest/Latest Times
Activity ES
A
B
C
D
E
F
G
H
I
J
K
0
0
6
6
6
9
9
13
13
19
18
EF
6
4
9
11
7
13
11
19
18
22
23
LS
0
5
6
15
12
9
16
14
13
20
18
LF
Slack
6
9
9
20
13
13
18
20
18
23
23
0 *critical
5
0*
9
6
0*
7
1
0*
1
0*
17
PERT Example
Probability the project will be completed
within 24 hours
Vpath = VA + VC + VF + VI + VK
= 4/9 + 0 + 1/9 + 1 + 4/9
= 2
path = 1.414
z = (24 - 23)/ = (24-23)/1.414 = .71
18
PERT Example
Probability the project will be completed
within 24 hours
.2612
.5000
23 24