You are on page 1of 33

Preliminary Design Review Report

Version - Draft

List of Annexes
Annex 1
Annex 2
Annex 3
Annex 4
Annex 5
Annex 6

Surface Water Resources


Ground Water Resources
Water Treatment
Water Distribution
Sanitation
Site Clearances

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Annex 1
Surface Water Resources
Chilaw

Pictures

Puttalam

Layout Plan
Pictures

Vavuniya

Layout Plan
Pictures

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Surface Water Resources


Chilaw Deduru Oya

Deduru Oya

Deduru Oya

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Surface Water Resources


Puttalam Kala Oya

Kala Oya @ channel to Eluwankulama Tank

Eluwankulama Tank

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Achchimolai Tank

Channel @ Kala Oya

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Surface Water Resources


Vavuniya Per Aru

Proposed Dam location

A9 junction leading to proposed dam access

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Kaddayar Kulam

Farming land irrigated by above dam

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Annex 2
Ground Water Resources
Current status of Chilaw and Puttalam
Report

Current status of Vavuniya and Mannar


Report

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Annex 3
Water Treatment
Rehabilitation of existing Water Treatment Plants
Chilaw

Pictures

Puttalam

Pictures

Mannar

Analysis of raw water quality samples


Pictures

New Water Treatment Plants


Treatment Process Block Diagram
Typical Process flow diagram
Typical Hydraulic Profile

Chilaw

Proposed treatment plant site

Puttalam

Proposed treatment plant site

Vavuniya

Proposed treatment site

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Rehabilitation of existing Water Treatment Plants


Chilaw

Aerator

View from behind aerators

Filters

Storage Reservoirs

Sedimentation Tank

Spiral staircase to aerators

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Rehabilitation of existing Water Treatment Plants


Puttalam

Aerator

Filters

Green Sand from filters

Chlorination System

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Rehabilitation of existing Water Treatment Plants


Mannar

Disinfection unit

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Disinfection Unit

Preliminary Design Review Report


Version - Draft

Chilaw
Proposed treatment site

Proposed water treatment plant site looking towards padi fields

Proposed site for water treatment plant

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Puttalam
Proposed treatment site

Access road to proposed water treatment plant

Proposed site for water treatment plant

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Vavuniya
Proposed treatment site

Proposed location for water treatment plant

Access road to proposed water treatment plant will need upgrading

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Annex 4
Water Distribution
Chilaw

Proposed base map to be used to identify networks


Pictures of proposed sites for towers / sump & pump station

Puttalam

Conceptual network layout


Pictures of proposed sites for towers / sump & pump station

Vavuniya

Proposed network schematic


Pictures of proposed sites for towers / sump & pump station

Mannar

Proposed network schematic


Pictures of proposed sites for towers / sump & pump station

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Chilaw
Pictures of proposed sites for towers / sump & pump station

Proposed tower site @ Bingiriya

Proposed tower site @ Bangadeniya

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Puttalam
Pictures of proposed sites for towers / sump & pump station

Proposed tower site @ Kaladiya

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Vavuniya
Pictures of proposed sites for towers / sump & pump station

Existing tower site

Moonrumurippu tower site

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Nelukulam tower site

Nelukulam sump / pumping station site

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Mannar
Pictures of proposed sites for towers / sump & pump station

Palimurai site for sump & pumping station

Eluthoor tower site

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Pictures of existing towers / sump & pump station sites

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Annex 5
Sanitation
Chilaw

Pictures of proposed Septage site


Pictures of public latrines to be rehabilitated

Puttalam

Pictures of proposed Septage site


Pictures of public latrines to be rehabilitated

Vavuniya

Pictures of existing Septage site


Pictures of public latrines to be rehabilitated

Mannar

Pictures of proposed Septage site

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Chilaw
Pictures of proposed Septage site

Propose Site for Chilaw STP and Bangadeniya

Proposed Site for Chilaw STP and Bangadeniya (Main Entrance)

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Chilaw
Pictures of public latrines to be rehabilitated
CTB bus stand

Front of building

Side of building

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Private bus stand

Corea Road

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Puttalam
Pictures of proposed Septage site

Proposed Site for Puttalam STP

Proposed Site for Puttalam STP

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Puttalam
Pictures of public latrines to be rehabilitated
Main Supermarket

Fish Market

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Urban Council / bus stand

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Vavuniya
Pictures of existing Septage site

Inlet arrangements and Anaerobic Lagoon/Pond at Pohnpemadu STP

Facultative / Oxidation Pond Pohnpemadu STP


ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Vavuniya
Pictures of public latrines to be rehabilitated
Central Bus Stand

Bazaar area

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Mannar
Pictures of proposed Septage site

Propose Site for Mannar Septage Treatment Plant

Access Point from the A32 Road to the Proposed Mannar STP Site

ADB Assisted Dry Zone Urban Water and Sanitation Project Sri Lanka
Design, Construction Supervision and Management Support (Package A)

Preliminary Design Review Report


Version - Draft

Annex 6
Status of Clearances in Project Area
Chilaw / Puttalam

Status of clearances for all proposed construction sites

Vavuniya / Mannar

Status of clearances for all proposed construction sites