Professional Documents
Culture Documents
CHMT4011-PROCESS CONTROL
Project Part 1
Contents
1. Project (Simulation) Description Summary.............................................................................1
2.
Simulation Analysis..................................................................................................................3
3.
Appendices...............................................................................................................................4
3.1
3.2
3.3
3.4
Important Assumptions
1. Density
Density is necessary for the conversion of mass flow rate to volumetric flow-rate; therefore, after
calculating specific gravity (using equation 3 in appendix B), it needs to be translated into
density through a relationship.
By definition, specific gravity is a ratio of densities between fluid of interest and a reference
fluid (usually water at 4 and 1 atm). Mathematically it can be written as follows:
S .G=
fluid /slurry
1Hatm
O
2
The reference density of water was taken as 1000 kg/m3and assumed constant throughout and
densities of slurries were calculated from the relation above.
2. Oversize material concentration
For this simulation, the oversize mass concentration (or fraction) is taken and used on wet basis;
i.e. if Dc represents the mass fraction of oversize material in stream D, then this would be the
fraction of oversize material in the whole slurry. This distinction is important because the dry and
wet basis mass fractions will always be different excerpt in a slurry with no water (e.g. Fresh ore
feed).
3. Hydro-cyclone operation
For the purpose of making hydro-cyclone material balance solvable, it is assumed that the solids
in the underflow (recycle) contain only the oversize material. This is a fair assumption since it is
highly desired to recycle the least amount of finer particles as it would be useless to recycle
fines.
4. Initial slurry level in the sump
To make it possible to solve the dynamic volume balance over the sump, an initial height of 1m
was taken as basis. The simple reason for this assumption is that at t=0 min , volumetric
efflux, given by Q out =80 h will not be computable if h=0; i.e. the simulation will return an
error since square-root of zero is not defined. This has negligible effect at the start of simulation.
5. Parameter change
The Kc value given was not compatible with the hydro-cyclone operation assumption above and
had to be changed to 0.01 in order to give sensible answers. This can be viewed as reducing the
amount of oversize material being recycled.
2. Simulation Analysis
2.1
Maximum and Minimum feed that the circuit can cope with.
The minimum dry ore feed that the system can cope with is approximately 22.5 kg/min. This
minimum is the feed rate required to maintain slurry level in sump at an initial value of 1m. The
maximum that can be achieved before sump overflows is 45kg/min of dry ore feed; above this
value the slurry level exceeds the height of 4m (the tank height).
2.2
has the
Increased recirculation load and overflow and eventually mill feed stream
Reduced mill residence time (due to decrease increase in volumetric flow into mill)figure 2.2
Figure 2.1: Effect of step input in sump dilution water to the slurry level in sump
Figure 2.2: Effect of step input in sump dilution water to the mill residence time
2.3
Mill & Sump water setting for control of slurry S.Gs (For desired S.Gs of slurries); S.Gs
are parameters to control in order to match pump requirements involved in pushing the
slurries around the circuit.Recycle rate used as process variable.
Kw- A parameter that dictates the amount of water being recycled back into mill. This
parameter must be automatically controlled to maintain amount of water in cyclone
overflow at constant value. Usually it is desired to minimise water in cyclone overflow to
prevent downstream solid-liquid separations of fine particles from water.
3. Appendices
5.1
Symbols
F: Dry Feed rate
W1: Mill Feed Dilution Water Feed rate
W2: Sump Feed Dilution Water Feed rate
T: Mill Feed rate
KL=0.72
KW=0.28
KC=5 (changed to 0.01)
=1000 kg/m3
5.2
Dc=
MTSISg=0.06 %J +2TSISg +
MSISg=
200
Tv ............Equation 2
100OSg
M %Osg100OSgM
Equation 3
dh 1
= ( QinQout ) .Equation 4
dt A
Qout=80 h ....Equation 5
Rv
=K L exp ( 0.54 ) ..Equation 6
Pv
Rv , water=K W CF v 0.9 .Equation 7
Rc =
K c CF c
CF v
0.45
(OSg1)0.5 .Equation 8
5.3
Mill Water
(W1)
New Feed
(F)
Total Feed
(T)
Ball Mill
Product
(OF)
Discharge
Sump
Hydro-cyclone
5.4
Figure 3.3.1: Model Overview: shows the different areas of the model (feed, mill, sump, and
hydro-cyclones systems). It also shows the areas where parameters and simulation results
can be found.
Figure 3.3.4: Subsystems found inside the report scopes system (these subsystems contain scopes for viewing results on
each stream including variables such as mill residence time and sump slurry level)